Cross-sea bridge pier tower crane driver shortcut

By designing a temporary access road for tower crane operators on the piers of the cross-sea bridge, and utilizing the threaded connection structure of guardrails and standard tower crane sections, the problems of structural instability and inconvenient disassembly during offshore construction were solved, enabling fast and safe passage for tower crane operators and improving construction efficiency and safety.

CN223813302UActive Publication Date: 2026-01-20CHINA CONSTR EIGHT ENG DIV CORP LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202520340290.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-02-28
Publication Date
2026-01-20
Estimated Expiration
2035-02-28

AI Technical Summary

Technical Problem

Existing technology cannot safely and reliably construct construction elevators on land or sea. The structure is unstable when facing severe weather such as strong winds at sea, which can easily lead to safety accidents. Furthermore, disassembly is inconvenient and reduces construction efficiency.

Method used

Design a temporary access road for tower crane operators on the piers of a cross-sea bridge, including guardrails, standard tower crane sections, and connecting components. The structure is stable through threaded connections and fastening bolts, and is easy to install and disassemble, making it suitable for offshore construction.

Benefits of technology

This enabled rapid passage for tower crane operators on the cross-sea bridge piers, improved construction efficiency and safety, reduced the labor intensity of workers, and prevented safety accidents.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223813302U_ABST
    Figure CN223813302U_ABST
Patent Text Reader

Abstract

The utility model relates to a driver shortcut, belongs to the technical field of bridge tower cranes, and particularly relates to a cross-sea bridge pier tower crane driver shortcut which comprises a protective barrier and a tower crane standard knot, the protective barrier is arranged on one side of the tower crane standard knot, and the cross-sea bridge pier tower crane driver shortcut further comprises a connecting assembly. The channel is fixedly mounted at the bottom of the protective barrier; the utility model achieves the effects of facilitating passage and guaranteeing safety, and solves the problems that the existing construction method is only suitable for a building site on the ground and cannot be built on the sea surface, and the structure is unstable, safety accidents are easily caused, the disassembly is inconvenient, and the construction efficiency is reduced in severe weather such as strong wind on the sea surface.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model relates to bridge tower crane technical field, especially a cross-sea bridge pier tower crane driver's convenient road. BACKGROUND

[0002] In many large cross-sea bridge constructions, construction elevators are equipped near tower cranes. These elevators are usually attached to piers or other auxiliary structures, and when tower crane operators finish their work, they can enter the construction elevators through the passages connecting the tower crane operating rooms and the construction elevator entrances (such as simple trestle bridges or platform passages), and then take the elevators to reach the ground or other designated work platforms.

[0003] Through retrieval, the patent with the publication number CN210193252U discloses a climbing frame attached tower crane driver passage, which comprises a passage frame and a protective member installed at one end of the passage frame. One end of the passage frame is detachably connected with the climbing frame, and the protective member is located at the end of the passage frame close to the climbing frame. The passage frame comprises two symmetrically vertically arranged steel plates and two horizontally symmetrically arranged net-shaped plates. The two steel plates are respectively fixedly connected to the upper and lower ends of the inner side walls of the net-shaped plates. After the tower crane and the climbing frame are lifted to a higher position, a fixed passage frame is installed at the lower layer of the climbing frame. The passage frame is synchronously lifted with the climbing frame, and the tower crane operator can enter and exit the tower crane through the passage frame. The distance that the tower crane operator climbs the tower is greatly shortened. The two steel plates can respectively serve to support the tower crane operator and protect the top of the tower crane operator. The net-shaped plates on both sides can serve to protect the sides of the tower crane operator. After confirming safety, the tower crane can be boarded.

[0004] Based on the above retrieval and combining the prior art, it is found that

[0005] Although the above-mentioned retrieval patent can ensure the safety of passing, it is only applicable to ground building sites and cannot be built on the sea surface. In the face of strong winds and other adverse weather conditions on the sea surface, the structure is unstable and prone to safety accidents. In addition, it is inconvenient to disassemble, which reduces the construction efficiency, and therefore has certain limitations. UTILITY MODEL CONTENTS

[0006] In order to solve the above technical problems, the utility model provides a cross-sea bridge pier tower crane driver's convenient road, which facilitates the rapid passage of tower crane operators and is structurally safe and reliable.

[0007] The technical solution for achieving the purpose of the utility model is as follows: a cross-sea bridge pier tower crane driver's convenient road, comprising a protective barrier and a tower crane standard section, the protective barrier being arranged on one side of the tower crane standard section, further comprising a connecting assembly;

[0008] A passage is fixedly installed at the bottom of the protective barrier.

[0009] The connecting assembly is provided with a plurality of pairs of clamping plates arranged on one side of the tower crane standard section.

[0010] Preferably, the surface of the channel is fixedly installed with a footboard, two sides of the channel are fixedly installed with a connecting plate one, one side of the guardrail is provided with a pair of vertical columns, the upper and lower ends of the vertical columns are welded with a cross beam, a plurality of threaded rods are installed on the pair of clamping plates, and the two ends of each threaded rod are threaded with nuts.

[0011] Preferably, one side of the clamping plate is welded with a connecting plate two, the cross beam is welded between the clamping plate and the connecting plate two, and a pull rod is arranged between the cross beam and the channel.

[0012] Preferably, the inside of the connecting plate two is threaded with a fastening bolt, the connecting plate two is threaded with the pull rod through the fastening bolt, and the other end of the pull rod is threaded with the connecting plate one through a bolt.

[0013] Compared with the prior art, the utility model has the following advantages:

[0014] Firstly, the utility model is assembled, convenient to assemble and disassemble, reduces labor intensity of workers, and building materials and equipment can be used repeatedly, thereby improving economic benefits.

[0015] Secondly, the utility model effectively solves the problem of rapid and efficient passing of the tower crane driver on the cross-sea bridge pier, improves efficiency and effectiveness, ensures the safety of the tower crane driver, and avoids accidents.

[0016] The utility model solves the problems that the existing construction method is only applicable to ground building sites and cannot be used on the sea surface, the structure is unstable and prone to safety accidents when facing strong winds and other bad weather on the sea surface, and the construction efficiency is reduced due to inconvenience in disassembly. BRIEF DESCRIPTION OF DRAWINGS

[0017] The utility model will be further explained in combination with the drawings and embodiments:

[0018] Figure 1 is a first perspective view of the overall structure provided by the utility model;

[0019] Figure 2 is a three-dimensional structure schematic view of the tower crane driver shortcut provided by the utility model;

[0020] Figure 3 is a side view structure schematic view of the tower crane driver shortcut provided by the utility model;

[0021] Figure 4 is a three-dimensional structure schematic view of the tower crane driver shortcut provided by the utility model; Figure 2 is an enlarged structure schematic view of A in the middle.

[0022] Reference numerals:

[0023] 1, guardrail; 2, tower standard section; 3, passageway; 301, scaffold board; 302, connecting plate one; 4, pull rod; 5, stand column; 6, cross beam; 7, clamping plate; 8, connecting plate two; 9, screw rod; 10, nut; 11, fastening bolt. DETAILED DESCRIPTION

[0024] The utility model will be explained in detail below, and the technical scheme in the embodiment of the utility model is clearly and completely described. Obviously, the described embodiment is only a part of the embodiment of the utility model, not all the embodiments. Based on the embodiment in the utility model, all other embodiments obtained by the ordinary skilled in the art without creative labor belong to the scope of protection of the utility model.

[0025] The utility model discloses an improved sea-crossing bridge pier tower crane driver's access road, and the technical scheme of the utility model is:

[0026] As shown in the drawing, Figures 1-4 A sea-crossing bridge pier tower crane driver's access road, comprising a guardrail 1 and a tower standard section 2, the guardrail 1 is arranged on one side of the tower standard section 2, and the traffic safety of workers commuting is ensured, further comprising a connecting assembly.

[0027] Passageway 3, passageway 3 is fixedly installed at the bottom of guardrail 1, the traffic speed is fast, the journey traffic time is shortened, and the construction efficiency is improved.

[0028] The connecting assembly is provided with a plurality of connecting assemblies, and the connecting assembly comprises a pair of clamping plates 7 arranged on one side of the tower standard section 2.

[0029] Further, the surface of the passageway 3 is fixedly installed with a scaffold board 301, the two sides of the passageway 3 are fixedly installed with a connecting plate one 302, one side of the guardrail 1 is provided with a pair of stand columns 5, the upper and lower ends of the stand column 5 are both welded with a cross beam 6, a plurality of screw rods 9 are threadedly installed on the pair of clamping plates 7, the two ends of each screw rod 9 are both threadedly installed with a nut 10, the nut 10 and the screw rod 9 are threadedly matched, and different components can be firmly connected together to prevent loosening or separation.

[0030] As a further scheme of the utility model, one side of one clamping plate 7 is welded with a connecting plate two 8, the cross beam 6 is welded between the clamping plate 7 and the connecting plate two 8, and the pull rod 4 is arranged between the cross beam 6 and the passageway 3. The cross beam 6 can increase the overall rigidity of the structure, reduce deformation and vibration, and ensure the stability and safety of the structure.

[0031] Further, the inside of the connecting plate two 8 is provided with a fastening bolt 11, the connecting plate two 8 is connected with the pull rod 4 through the fastening bolt 11, the other end of the pull rod 4 is connected with the connecting plate one 302 through a bolt, and the fastening bolt 11 can enhance the tightness of connection by applying a pre-tightening force.

[0032] The specific working method is: first, the channel 3 is welded at the bottom of the guardrail 1, the footboard 301 is laid on the channel 3, the worker is safely passed, the guardrail 1 is arranged on one side of the tower standard section 2, the accurate position is measured, the upper and lower ends of the guardrail 1 are installed with the tower standard section 2 through the connecting assembly, the guardrail 1 is connected with the stand 5 through the connecting assembly, the connecting assembly comprises a screw rod 9, a nut 10 and a fastening bolt 11, the guardrail is effectively prevented from loosening, the safety accident is avoided, the strong stability can be kept on the sea, finally, the cross beam 6 is welded on the stand 5 to prevent structural deformation, the pull rod 4 is installed to form a triangular structure, and the safety and the firmness of connection are further guaranteed.

[0033] The technical means disclosed by the utility model scheme is not only limited to the technical means disclosed by the above technical means, but also includes the technical scheme composed by the above technical features and equivalent replacement. The unfinished matters of the utility model belong to the common knowledge of the person skilled in the art.

Claims

1. A temporary access road for tower crane operators on a cross-sea bridge pier, comprising guardrails (1) and a standard tower crane section (2), characterized in that: The guardrail (1) is installed on one side of the standard section (2) of the tower crane, and also includes; Channel (3), which is fixedly installed at the bottom of the guardrail (1); The connecting components are provided in multiple ways, and the connecting components include a pair of clamps (7) disposed on one side of the standard section (2) of the tower crane.

2. The access road for crane operators on a cross-sea bridge pier according to claim 1, characterized in that: The surface of the passage (3) is fixedly installed with scaffold boards (301), and the two sides of the passage (3) are fixedly installed with connecting plates (302). A pair of uprights (5) are provided on one side of the guardrail (1). The upper and lower ends of the uprights (5) are welded with crossbeams (6). Multiple screws (9) are threaded on the pair of clamps (7), and nuts (10) are threaded on both ends of each screw (9).

3. The access road for crane operators on a cross-sea bridge pier according to claim 2, characterized in that: One of the clamps (7) is welded with a connecting plate two (8) on one side. The crossbeam (6) is welded between the clamp (7) and the connecting plate two (8). A tie rod (4) is provided between the crossbeam (6) and the channel (3).

4. The access road for crane operators on a cross-sea bridge pier according to claim 3, characterized in that: The connecting plate 2 (8) has a fastening bolt (11) installed in its internal thread. The connecting plate 2 (8) is threadedly connected to the pull rod (4) by the fastening bolt (11). The other end of the pull rod (4) is threadedly connected to the connecting plate 1 (302) by a bolt.

Citation Information

Patent Citations

  • Climbing frame attached type tower crane driver passage

    CN210193252U