Pipeline hoisting device
By using a hanging clamp mechanism and a steel rope claw structure, the problems of steel wire rope slippage and coating damage during the hoisting of large-diameter pipelines have been solved, achieving stability and safety during the hoisting process and extending the service life of the pipeline.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-02-25
- Publication Date
- 2026-03-13
AI Technical Summary
When hoisting large-diameter, long pipes, existing technologies often involve wire ropes that slip, causing the pipes to lose balance. Furthermore, the coating is easily damaged during hoisting, affecting safety and lifespan.
The system employs a hanging clamp mechanism, including a roller structure and steel rope claws. The hanging clamp mechanism is pulled close to the center of the pipe by steel cables to maintain balance during the hoisting process, and the clamping stability is enhanced by the clamping rollers and the spacing adjustment structure.
This design ensures that the hanging clamp mechanism does not easily loosen during hoisting, maintains pipeline balance, reduces coating damage, and improves hoisting safety and pipeline service life.
Smart Images

Figure CN223990828U_ABST
Abstract
Description
Technical Field
[0001] This utility model belongs to the field of pipeline hoisting technology, and in particular relates to a pipeline hoisting device. Background Technology
[0002] Pipeline construction is a frequent task in engineering construction. The difficulty of construction varies depending on the diameter and material of the pipeline.
[0003] Especially for large-diameter and long pipelines, their weight and length not only make them heavy, but also pose greater risks during hoisting and installation. In particular, if the pipeline loses its balance during hoisting and falls from a height, it can easily cause injuries to personnel and equipment. More seriously, due to its length, a falling pipeline can cause extensive damage, potentially leading to extremely serious safety accidents.
[0004] Specifically, in the current process of hoisting this type of pipeline, steel wire ropes are often tied to the pipeline, such as at both ends, to improve balance. However, since the pipeline wall is mostly smooth, even if the steel wire ropes are tied tightly before hoisting, the pipeline is prone to swaying when hoisted to a high altitude, especially after the crane changes direction. This can lead to slippage between the steel wire ropes and the pipeline. Once slippage occurs and the tying points change, the pipeline is very likely to lose its balance. Once it loses its balance, the pipeline is prone to tipping over, resulting in an operational safety accident.
[0005] Therefore, in existing technologies, steel wire ropes are often threaded through the inside of the pipe to increase safety. However, this method has a drawback: to enhance the pipe's corrosion resistance, especially for pipes transporting sewage, the inner wall of the pipe is often coated with a rust-proof and corrosion-resistant coating. However, in this method, because the contact area between the steel wire rope and the pipe is small and the pressure is extremely high, the internal coating of the pipe is easily damaged over a large area during hoisting (especially when the pipe shakes violently). This seriously affects the service life of the pipeline. Utility Model Content
[0006] Based on the above background, the purpose of this utility model is to provide a pipeline hoisting device.
[0007] To achieve the above objectives, the present invention adopts the following technical solution:
[0008] A pipe hoisting device includes a hanging clamp mechanism that is respectively hung at both ends of a pipe, and the hanging clamp mechanism is fixedly connected to the other two ends by a steel cable structure.
[0009] The hanging clamp mechanism is held and rolled on the pipe by a roller structure. The hanging clamp mechanism includes a pair of hanging clamp assemblies, and the hanging length is adjusted between the hanging clamp assemblies by a spacing adjustment structure.
[0010] The hanging clamp mechanism is equipped with several steel cable claw structures. The steel cable claw structures grip the pipe opening. During the hoisting process, the crane hoists and pulls the steel cable structure. The steel cable structure pulls the hanging clamp mechanisms on both sides closer to each other until the steel cable claw structure switches from a slack state to a taut state.
[0011] Preferably, the hanging clamp assembly includes a hanging bracket sleeved on the outside of the pipe, and a plurality of adjustable-spaced clamping roller structures are installed on the hanging bracket, with the pipe clamped between the clamping roller structures.
[0012] Preferably, the abutting roller structure includes a roller frame, on which an abutting roller is rotatably connected;
[0013] The hanging bracket is threaded with an adjusting screw, which is rotatably connected to the hanging wheel bracket.
[0014] Preferably, the longitudinal cross-sectional shape of the hanging bracket is square;
[0015] Each of the four sides of the hanging bracket is equipped with a clamping roller structure.
[0016] Preferably, the spacing adjustment structure includes several spacing adjustment screw components, each including a long adjustment screw, and protrusions that are slidably connected to the side walls of the front and rear hanging brackets respectively. Two pairs of nuts, respectively positioned on both sides of the protrusions, are threaded onto the long adjustment screw.
[0017] Preferably, four steel rope claw structures are fixedly installed on the outer hanging bracket;
[0018] The steel rope claw structure is fixed to the center of each side of the hanging bracket.
[0019] Preferably, the steel rope claw structure includes a steel wire rope, and the outer end of the steel wire rope is fixedly connected to a hook plate;
[0020] The hanging bracket is welded with a wire rope fixing seat to fix the wire rope.
[0021] Preferably, steel wire hanging rings are fixedly connected to both sides of the top of the inner hanging bracket;
[0022] The cable structure includes steel cables that are fixedly connected between steel wire hanging rings, and the crane is suspended at the center of the steel cables.
[0023] Preferably, the wire rope fixing seat has a through hole, through which the wire rope passes;
[0024] The wire rope is bolted and fixed at the through hole.
[0025] This utility model has the following beneficial effects:
[0026] 1. During the operation, when the crane lifts and pulls the steel cable structure, the hanging clamps at both ends roll rapidly toward the center of the pipe under the tension of the inclined upward steel cable structure. As the hanging clamps move, the steel rope claw structure that was pre-attached to the pipe opening gradually changes from a relaxed state to a taut state, thereby pulling the pipe opening in.
[0027] Therefore, in this method, because one end of the hanging clamp mechanism is subjected to the tension of the steel cable structure, while the other end is subjected to the anchoring tension of the steel rope claw structure and the pipe opening, the hanging clamp mechanism remains in a different position. The advantages of this method are: during the hoisting process, the position of the hanging clamp mechanism is not easy to loosen, and thus the balance of the pipeline will not be damaged. Secondly, the hanging clamp mechanism can hang a certain length range, thus further increasing the hoisting range.
[0028] 2. Once the pipe is hoisted to the target position, the lifting force disappears, and the steel cable claw structure automatically relaxes, facilitating the release of the pipe. Attached Figure Description
[0029] To more clearly illustrate the technical solutions in the embodiments of this utility model or the prior art, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of this utility model. For those skilled in the art, other drawings can be obtained based on the structures shown in these drawings without creative effort.
[0030] Figure 1 This is a schematic diagram of the overall structure in an embodiment of the present utility model;
[0031] Figure 2 This is a schematic diagram of the hanging clamp mechanism in an embodiment of the present utility model;
[0032] Figure 3 This is a schematic diagram of the anti-locking wheel structure in an embodiment of the present utility model;
[0033] Figure 4 This is an embodiment of the present utility model. Figure 1 A schematic diagram of the planar structure.
[0034] The realization of the purpose, functional features and advantages of this utility model will be further explained in conjunction with the embodiments and with reference to the accompanying drawings. Detailed Implementation
[0035] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the protection scope of the present utility model.
[0036] It should be noted that all directional indicators (such as up, down, left, right, front, back, etc.) in this utility model embodiment are only used to explain the relative positional relationship and movement of each component in a certain specific posture (as shown in the figure). If the specific posture changes, the directional indicator will also change accordingly.
[0037] Furthermore, in this utility model, descriptions involving "first," "second," etc., are for descriptive purposes only and should not be construed as indicating or implying their relative importance or implicitly specifying the number of technical features indicated. Therefore, a feature defined with "first" or "second" may explicitly or implicitly include at least one of that feature. Additionally, the technical solutions of the various embodiments can be combined with each other, but only on the basis of being achievable by those skilled in the art. When the combination of technical solutions is contradictory or impossible to implement, such a combination of technical solutions should be considered non-existent and not within the scope of protection claimed by this utility model.
[0038] Example 1
[0039] like Figure 1-4 As shown, a pipe hoisting device includes a hanging clamp mechanism that is respectively suspended at both ends of a pipe 1, and a steel cable structure is fixedly connected between the hanging clamp mechanisms. The hanging clamp mechanism is held and rolled on the pipe 1 by a roller structure. The hanging clamp mechanism includes a pair of hanging clamp assemblies 2, and the hanging clamp assemblies 2 are adjusted for hanging length by a spacing adjustment structure. Several steel cable claw structures are installed on the hanging clamp mechanism. The steel cable claw structures grip the opening of the pipe 1. During hoisting, the crane hoists and pulls the steel cable structure, and the steel cable structure pulls the two hanging clamp mechanisms closer to each other until the steel cable claw structures switch from a slack state to a taut state.
[0040] In this way, during the operation, when the crane lifts and pulls the steel cable structure, the hanging clamps at both ends roll rapidly toward the center of pipe 1 under the tension of the inclined upward steel cable structure. As the hanging clamps move, the steel rope claw structure that is pre-hanging at the opening of pipe 1 gradually changes from a relaxed state to a taut state, thereby pulling the opening of pipe 1 inward.
[0041] Therefore, in this method, since one end of the hanging clamp mechanism is subjected to the tension of the steel cable structure, while the other end is subjected to the anchoring tension of the steel rope claw structure and the opening of pipe 1, the hanging clamp mechanism remains in a different position. The advantages of this method are: during the hoisting process, the position of the hanging clamp mechanism is not easy to loosen, and thus the balance of pipe 1 will not be damaged. Secondly, the hanging clamp mechanism can hang a certain length range, thus further increasing the hoisting range.
[0042] Even better, once the pipe is hoisted to the target position, the lifting force disappears, and the steel cable claw structure automatically relaxes, making it easy to release the pipe 1.
[0043] Example 2
[0044] like Figure 1-4 As shown, based on the structure of Embodiment 1, the above-mentioned hanging clamp assembly 2 includes a hanging bracket 21 sleeved on the outside of the pipe 1. Specifically, the longitudinal cross-sectional shape of the hanging bracket 21 is square, and several adjustable-spaced clamping roller structures 22 are installed on the hanging bracket 21 (specifically, a clamping roller structure 22 is installed at the center of each of the four sides of the hanging bracket 21), and the pipe 1 is clamped between the clamping roller structures 22.
[0045] Specifically, the clamping pulley structure 22 includes a pulley frame 221, on which a clamping pulley 222 is rotatably connected; an adjusting screw 223 is threadedly connected to the pull bracket 21, and the adjusting screw 223 is rotatably connected to the pulley frame 221. Specifically, a fixed seat 2231 for rotatably connecting the adjusting screw 223 is fixedly connected to the top of the pulley frame 221, similar to existing rotatable connection methods. A T-shaped limiting groove (not shown in the figure) is provided on the fixed seat 2231, and a rotating head (not shown in the figure) for rotatable connection within the limiting groove is fixedly connected to the bottom of the adjusting screw 223. The rotating head and the rod body of the adjusting screw 223 are integrally formed into a T-shaped structure.
[0046] During operation, adjust the four clamping rollers 222 structures 22 until they respectively clamp onto the pipe 1. The operation method is as follows: rotate the adjusting screw 223 and then adjust the clamping rollers 222 structures 22.
[0047] With the cooperation of a pair of hanging clamp assemblies 2, one end of the pipe 1 is clamped, and the clamping has a certain length, so the clamping stability is high.
[0048] Adjust the clamping length of a pair of hanging clamp assemblies 2 according to the weight and length of pipe 1.
[0049] Specifically, the spacing adjustment structure includes four spacing adjustment screws 3, with two spacing adjustment screws 3 arranged vertically and vertically on each side between the left and right sides of the front and rear hanging brackets 21.
[0050] Specifically, the spacing adjustment screw component 3 includes a long adjustment screw 31, and the front and rear sides of the hanging bracket 21 are respectively fixedly connected to the protrusions 311 that are slidably connected to the long adjustment screw 31. The long adjustment screw 31 is threaded with two pairs of nuts 32 that are respectively positioned on both sides of the protrusions 311.
[0051] After loosening nut 32, the distance between the front and rear hanging clamp assemblies 2 can be adjusted to adjust the clamping length. If the distance is increased, the clamping length will increase, allowing for the hanging of pipes 1 with larger lengths and diameters.
[0052] Example 3
[0053] like Figure 1-4 As shown, in this embodiment, based on the structure of embodiment 2, in order to anchor the pipe 1 and the hanging clamp assembly 2 during the hoisting process and increase stability and safety, four steel rope claw structures 4 are fixedly installed on the hanging bracket 21 located on the outer side (i.e., near the pipe 1 opening).
[0054] Specifically, the steel cable claw structure 4 is fixed to the center of each side of the hanging bracket 21. The steel cable claw structure 4 includes a steel wire rope 42, and the outer end of the steel wire rope 42 is fixedly connected to a hook plate 43; a steel wire rope fixing seat 41 for fixing the steel wire rope 42 is welded on the hanging bracket 21.
[0055] Meanwhile, a through hole is provided on the wire rope fixing seat 41, and the wire rope fixing seat 41 passes through the through hole; the wire rope fixing seat 41 is bolted and fixed at the through hole.
[0056] Before hoisting, hook plate 43 is attached to the opening of pipe 1. Meanwhile, because wire rope 42 is secured to the through hole, the anchoring point of wire rope 42 can be adjusted to adjust its length, facilitating hoisting.
[0057] During the hoisting process, the hanging bracket 21 rolls on the pipe 1 and gradually moves away from the opening of the pipe 1. At this time, the wire rope 42 gradually tightens and is then hooked onto the hook plate 43.
[0058] The top of the inner hanging bracket 21 is fixedly connected to two sides of the wire hanging ring body 51 respectively; the steel cable structure includes steel cable rope 5 (forming a V-shaped structure) fixedly connected between the wire hanging ring bodies 51 respectively, and the crane is suspended at the center of the steel cable rope 5.
[0059] The crane hook is attached to the center of the steel cable 5.
[0060] Of course, the above description is not intended to limit the present utility model, and the present utility model is not limited to the examples given above. Any changes, modifications, additions or substitutions made by those skilled in the art within the scope of the present utility model should also fall within the protection scope of the present utility model.
Claims
1. A pipe hoisting device, characterized by Including respectively pull in the position of the pipeline both ends of the pull clamp mechanism, the pull clamp mechanism is fixedly connected with the cable structure between it; The pull clamp mechanism is clamped and rolled on the pipeline through the roller structure, and the pull clamp mechanism includes a pair of pull clamp assemblies, and the pull clamp assemblies are adjusted in length through the spacing adjustment structure between them; A plurality of steel rope claw structures are installed on the pull clamp mechanism, the steel rope claw structures are clamped on the pipeline, and in the hoisting process, the crane pulls the cable structure, and the cable structure pulls the two pull clamp mechanisms to approach each other to switch the steel rope claw structure from the relaxed state to the tension state.
2. The pipe hoisting device according to claim 1, characterized in that The pull clamp assembly includes a pull frame sleeved on the outside of the pipeline, a plurality of spacing adjustable abutting hanging wheel structures are installed on the pull frame, and the pipeline is clamped between the abutting hanging wheel structures.
3. The pipe hoisting apparatus according to claim 2, wherein The abutting hanging wheel structure includes a hanging wheel frame, and the hanging wheel frame is rotationally connected with an abutting hanging wheel; The pull frame is threadedly connected with an adjusting screw rod, and the adjusting screw rod is limitingly rotationally connected to the hanging wheel frame.
4. The pipe hoisting apparatus of claim 2, wherein The longitudinal section shape of the pull frame is a square; The four side center parts of the pull frame are each provided with an abutting hanging wheel structure.
5. The pipe hoisting apparatus of claim 4, wherein The spacing adjustment structure includes a plurality of spacing adjustment screw rod pieces, the spacing adjustment screw rod piece includes a long adjusting screw rod, the front and rear sides of the pull frame are respectively fixedly connected with a convex seat slidingly connected with the long adjusting screw rod, and two pairs of nuts positioned on the two sides of the convex seat are threadedly connected with the long adjusting screw rod.
6. The pipe hoisting apparatus of claim 4, wherein Four steel rope claw structures are fixedly installed on the pull frame at the outer side position; The steel rope claw structure is respectively fixed at the center part of each side of the pull frame.
7. The pipe hoisting apparatus of claim 6, wherein The steel rope claw structure respectively includes a steel wire rope, and the outer end of the steel wire rope is fixedly connected with a hook plate; A steel wire rope fixing seat for fixing the steel wire rope is welded on the pull frame.
8. The pipe hoisting apparatus of claim 4, wherein Steel wire hanging ring bodies are respectively fixedly connected on both sides of the top of the pull frame at the inner side; The cable structure includes a steel cable fixedly connected between the steel wire hanging ring bodies, and the crane is hung at the center part of the steel cable.
9. The pipe hoisting apparatus of claim 7, wherein A through hole is formed in the steel wire rope fixing seat, and the steel wire rope penetrates through the through hole position; The steel wire rope is tied and fixed at the through hole position.