Lifting device for comprehensive pipe gallery construction

By combining the design of the hanger, adjusting cylinder and drive components, the problem of difficult angle adjustment for pipe gallery hoisting in the existing technology is solved, and stable hoisting and efficient splicing are achieved on the slope construction site.

CN224132523UActive Publication Date: 2026-04-17CHONGQING INVESTMENT CONSULTING CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
CHONGQING INVESTMENT CONSULTING CO LTD
Filing Date
2025-05-26
Publication Date
2026-04-17

AI Technical Summary

Technical Problem

Existing technology cannot adjust the angle of the pipe gallery after hoisting, which reduces the efficiency of connecting two adjacent pipe galleries when the construction section has a slope.

Method used

The design adopts a combination of hangers, adjusting cylinders, lifting ropes, and drive components. Through the cooperation of the adjusting and drive components, the length of the lifting ropes and the spacing of the adjusting cylinders can be adjusted to adapt to the hoisting of pipe racks of different lengths and angles.

Benefits of technology

Despite the slope at the construction site, stable hoisting and efficient splicing of the utility tunnel were achieved, improving construction efficiency and hoisting preparation efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224132523U_ABST
    Figure CN224132523U_ABST
Patent Text Reader

Abstract

The utility model provides a lifting device for comprehensive pipe gallery construction, which comprises a lifting frame, a lifting mechanism, a lifting mechanism and a lifting mechanism, the two adjusting cylinders are arranged at the two ends of the channel in a penetrating mode correspondingly; the hoisting unit comprises a hoisting rope and an adjusting assembly, one end of the hoisting rope is arranged in the adjusting cylinder, the other end of the hoisting rope penetrates out of the adjusting cylinder, and the adjusting assembly is arranged on the adjusting cylinder and connected with the hoisting rope; and the adjusting assembly is arranged on the hanging bracket and is connected with the two adjusting cylinders. Under the cooperation of the adjusting assembly, the length of the part, extending out of the adjusting cylinder, of one lifting rope can be adjusted, so that the pipe gallery can be in an inclined state through the two lifting ropes with different lengths, and splicing construction can be conveniently conducted on the pipe gallery under the condition that a construction site has a gradient; and under the action of the driving assembly, the distance between the two adjusting cylinders can be adjusted, so that the horizontal positions of the end parts of the two lifting ropes are changed, and pipe galleries with different lengths can be lifted.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of pipe gallery hoisting construction technology, and in particular to a hoisting device for integrated pipe gallery construction. Background Technology

[0002] Integrated utility tunnels can integrate various engineering pipelines such as electricity, communications, gas, heating, and water supply and drainage, and are equipped with dedicated inspection ports, hoisting ports, and monitoring systems, implementing unified planning, design, construction, and management. During the construction of integrated utility tunnels, prefabricated tunnel segments are currently mainly spliced ​​together one by one using hoisting equipment.

[0003] For example, Chinese patent "CN222410798U" discloses "a prefabricated pipe gallery hoisting device." This device uses multiple tracks to flexibly hoist pipe galleries in different positions. It also includes a gantry frame for installing hoisting components and a hoisting frame and telescopic rods to shorten or extend the frame according to the size of the pipe gallery, thus adapting to the hoisting needs. However, when the construction section of the pipe gallery has a certain slope, it is impossible to adjust the angle of the hoisted pipe gallery, reducing the efficiency of connecting adjacent pipe galleries. Utility Model Content

[0004] To address the shortcomings of existing technologies, this utility model provides a lifting device for the construction of integrated utility tunnels, which solves the problem that existing technologies cannot adjust the angle of the hoisted utility tunnel.

[0005] According to the embodiments of this utility model, the following technical solution is adopted:

[0006] A lifting device for the construction of a utility tunnel includes:

[0007] The hanger has a channel running through both ends along its axial direction;

[0008] Adjusting cylinders, two adjusting cylinders respectively passing through both ends of the channel;

[0009] The hoisting unit includes a hoisting rope and an adjusting assembly. One end of the hoisting rope is located inside the adjusting cylinder, and the other end extends outside the adjusting cylinder. The adjusting assembly is located in the adjusting cylinder and connected to the hoisting rope, and is used to adjust the length of the hoisting rope outside the adjusting cylinder.

[0010] And a drive assembly, located on the hanger and connected to two adjusting cylinders, for controlling the distance between the two adjusting cylinders.

[0011] Preferably, the adjusting component includes a jack, which is located inside the adjusting cylinder, and the telescopic end of the jack is provided with a slider, which is slidably located in the adjusting cylinder and fixedly connected to the end of the lifting rope.

[0012] Preferably, the driving component includes:

[0013] Adjusting blocks, both of which are slidably mounted on the hanger and are respectively connected to two adjusting cylinders;

[0014] A two-way adjusting component is located on the hanger and connected to two adjusting blocks.

[0015] Preferably, the bidirectional adjustment element includes:

[0016] Dual-axis motor, the dual-axis motor is fixedly mounted on the hanger;

[0017] Two lead screws are respectively located at the two output ends of the dual-axis motor, and two adjusting blocks are respectively threaded to the two lead screws.

[0018] Preferably, both ends of the hanger are provided with limit seats, and the ends of the two lead screws are respectively rotatably mounted on the two limit seats.

[0019] Preferably, both ends of the hanger are provided with mounting seats, and both mounting seats are provided with lifting rings.

[0020] Preferably, both ends of the adjusting cylinder are equipped with limit wheels, and the hanging rope is mounted on the limit wheels.

[0021] Preferably, both ends of the lifting ropes are equipped with hooks.

[0022] Compared with the prior art, the present invention has the following beneficial effects:

[0023] In this scheme, with the cooperation of the adjusting cylinder and the hoisting unit, the hoisting points on the pipe gallery can be connected by hoisting ropes. The external crane lifts the gantry, thereby hoisting the pipe gallery by the hoisting ropes and moving the gantry to splice the pipe gallery to the designated position. At the same time, with the cooperation of the adjusting component, the length of one of the hoisting ropes extending out of the adjusting cylinder can be adjusted, so that the pipe gallery can be tilted by using two hoisting ropes of different lengths. This facilitates the splicing construction of the pipe gallery even when there is a slope on the construction site. Moreover, under the action of the drive component, the distance between the two adjusting cylinders can be adjusted, thereby changing the horizontal position of the ends of the two hoisting ropes to accommodate the hoisting of pipe galleries of different lengths. Attached Figure Description

[0024] Figure 1 This is a three-dimensional structural diagram of the lifting device in an embodiment of this utility model.

[0025] Figure 2 This is a schematic diagram of the lifting device used to horizontally lift the pipe gallery in an embodiment of this utility model.

[0026] Figure 3 This is a schematic diagram of the lifting device in this embodiment of the utility model, which performs tilted lifting of the pipe gallery.

[0027] Figure 4 This is a cross-sectional structural diagram of the hanger and adjusting rod in an embodiment of this utility model.

[0028] In the above attached diagram: 1. Hanger; 101. Limit seat; 102. Channel; 2. Adjusting cylinder; 201. Adjusting block; 3. Lifting rope; 301. Lifting hook; 4. Mounting base; 401. Lifting ring; 5. Dual-shaft motor; 501. Lead screw; 6. Jack; 601. Sliding block; 7. Limit wheel. Detailed Implementation

[0029] The technical solution of this utility model will be further described below with reference to the accompanying drawings and embodiments.

[0030] This utility model embodiment proposes a lifting device for the construction of integrated utility tunnels, including:

[0031] The hanger 1 has a channel 102 extending through both ends along its axial direction;

[0032] Adjusting cylinder 2, two adjusting cylinders 2 are respectively installed at both ends of channel 102;

[0033] The hoisting unit includes a hoisting rope 3 and an adjusting component. One end of the hoisting rope 3 is located inside the adjusting cylinder 2, and the other end extends through the outside of the adjusting cylinder 2. The adjusting component is located in the adjusting cylinder 2 and connected to the hoisting rope 3, and is used to adjust the length of the hoisting rope 3 outside the adjusting cylinder 2.

[0034] And a drive assembly, located on the hanger 1 and connected to two adjusting cylinders 2, for controlling the distance between the two adjusting cylinders 2.

[0035] In the embodiments of this utility model, such as Figure 1 As shown, the hanger 1 is hollow and hollow, forming a channel 102 with openings at both ends. Two adjusting cylinders 2 are respectively inserted at both ends of the channel 102, allowing the adjusting cylinders 2 to move within the channel 102. The end of the lifting rope 3 extending out of the adjusting cylinder 2 falls naturally. When the drive component moves the two adjusting cylinders 2, it can change the position of the projection of the adjusting cylinders 2 on the pipe rack. It is not affected by the length of the pipe rack, and can keep the lifting rope 3 aligned with the lifting point of the pipe rack. This ensures that the lifting rope 3 is in a vertical state when lifting the pipe rack, thus ensuring the stability of the pipe rack during lifting.

[0036] like Figure 2As shown, when hoisting the utility tunnel, the lengths of the hoisting ropes 3 extending from the two adjusting cylinders 2 are the same. When the hoisting frame 1 is lifted by the crane, the utility tunnel is in a horizontal state under the simultaneous hoisting of the two hoisting ropes 3, which is suitable for the splicing construction of the utility tunnel on a horizontal plane. When a certain slope is required in the construction area, there are two operating methods. One is to install an angled jig at the construction site, hoist the pipe rack onto the jig so that its angle matches the jig's angle and the slope. Then, connect two lifting ropes 3 to the pipe rack's hoisting point. While the crane is lifting, the length of one of the lifting ropes 3 can be adjusted to ensure both ropes 3 are taut before lifting. An adjustment component can be installed in only one adjusting cylinder 2, or, to accommodate different placement angles, adjustment components can be installed in both adjusting cylinders 2 to adjust the lifting ropes 3 of one or the other. The second method is to first hoist the pipe rack. Once the pipe rack is off the ground, the length of one end of the corresponding lifting rope 3 is adjusted using the adjustment component in the adjusting cylinder 2 until the pipe rack meets the preset installation angle.

[0037] Based on the above solutions, such as Figure 4 As shown, the adjustment assembly includes a jack 6, which is located inside the adjustment cylinder 2. The telescopic end of the jack 6 is equipped with a slider 601, which is slidably mounted on the adjustment cylinder 2 and fixedly connected to the end of the hoisting rope 3. By controlling the extension or retraction of the telescopic end of the jack 6, the slider 601 slides inside the adjustment cylinder 2, thereby causing the slider 601 to drive the end of the hoisting rope 3 to move inside the adjustment cylinder 2, thus changing the length of the hoisting rope 3 extending out of the adjustment cylinder 2. The jack 6 has a large thrust and a fast response speed, which can quickly complete the adjustment of the length of the hoisting rope 3 and improve the efficiency of hoisting preparation.

[0038] Based on the above solutions, such as Figure 1 As shown, the driving component includes:

[0039] Adjusting blocks 201, both adjusting blocks 201 are slidably mounted on the hanger 1 and respectively connected to the two adjusting cylinders 2;

[0040] A bidirectional adjustment component is provided on the hanger 1 and connected to two adjustment blocks 201.

[0041] The portion of the lifting rope 3 outside the adjusting cylinder 2 naturally descends under its own weight, thus making the position of the end of the adjusting cylinder 2 the vertical lifting position of the lifting rope 3. Due to the length of the pipe gallery, the position of the lifting ring embedded in the pipe gallery will also change. In order to prevent the lifting rope 3 from tilting after connecting to the lifting ring, the two adjusting blocks 201 can be adjusted synchronously under the action of the bidirectional adjusting component, so as to realize the synchronous adjustment of the positions of the two adjusting cylinders 2 until the lifting rope 3 corresponds to the lifting ring in its natural state and is connected. The aforementioned bidirectional adjusting component can be a bidirectional jack or a motor and threaded component transmission.

[0042] Secondly, each of the two lifting ropes 3 is equipped with a hook 301 at its end, which facilitates direct connection to the lifting ring on the pipe rack via the hook 301, improving installation efficiency. At the same time, both ends of the adjusting cylinder 2 are equipped with a limit wheel 7, and the lifting rope 3 is mounted on the limit wheel 7, which prevents the lifting rope 3 from directly rubbing against the end of the adjusting cylinder 2 during adjustment or lifting. Since the limit wheel 7 can rotate freely, the lifting rope 3 slides more smoothly on it, reducing wear and extending the service life of the lifting rope 3.

[0043] To reduce the area occupied by the equipment on the hanger 1, the bidirectional adjustment component includes:

[0044] Dual-axis motor 5, which is fixedly mounted on the hanger 1;

[0045] Two lead screws 501 are respectively located at the two output ends of the dual-axis motor 5, and two adjusting blocks 201 are respectively threadedly connected to the two lead screws 501.

[0046] When the dual-axis motor 5 is started, the two output shafts of the dual-axis motor 5 rotate synchronously. Since the threads of the two lead screws 501 are turned in opposite directions, under the drive of the dual-axis motor 5, the two adjusting blocks 201 can be controlled to move closer or further away from each other by the two lead screws 501 respectively, thereby realizing the adjustment of the two adjusting cylinders 2.

[0047] Specifically, such as Figure 4 As shown, both ends of the hanger 1 are provided with limit seats 101. The ends of the two lead screws 501 are respectively rotatably mounted on the two limit seats 101, which can bear the other end of the lead screw 501 and ensure the stability of the lead screw 501 during transmission.

[0048] Specifically, such as Figure 1 As shown, both ends of the hanger 1 are provided with mounting bases 4, and both mounting bases 4 are provided with lifting rings 401. Under the action of the lifting rings 401, the lifting rings 401 serve as load-bearing connection points and can be directly connected to lifting equipment such as cranes through connecting ropes.

[0049] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of this utility model and are not intended to limit it. Although this utility model has been described in detail with reference to preferred embodiments, those skilled in the art should understand that modifications or equivalent substitutions can be made to the technical solutions of this utility model without departing from the spirit and scope of the technical solutions of this utility model, and all such modifications or substitutions should be covered within the scope of the claims of this utility model.

Claims

1. A lifting device for the construction of an integrated utility tunnel, characterized in that, include: The hanger (1) has a channel (102) extending through both ends along its axial direction; Adjusting cylinders (2), two of the adjusting cylinders (2) are respectively inserted at both ends of the channel (102); The hoisting unit includes a hoisting rope (3) and an adjustment component. One end of the hoisting rope (3) is located inside the adjustment cylinder (2), and the other end extends through the outside of the adjustment cylinder (2). The adjustment component is located in the adjustment cylinder (2) and connected to the hoisting rope (3) for adjusting the length of the hoisting rope (3) outside the adjustment cylinder (2). And a drive assembly, located on the hanger (1) and connected to the two adjusting cylinders (2), for controlling the distance between the two adjusting cylinders (2).

2. The hoisting device for utility tunnel construction according to claim 1, characterized in that, The adjustment assembly includes a jack (6), which is located inside the adjustment cylinder (2). The telescopic end of the jack (6) is provided with a slider (601), which is slidably located in the adjustment cylinder (2) and fixedly connected to the end of the hoisting rope (3).

3. The hoisting device for utility tunnel construction of claim 1, wherein The driving component includes: Adjusting blocks (201), both of the adjusting blocks (201) are slidably disposed on the hanger (1) and respectively connected to the two adjusting cylinders (2); A bidirectional adjustment component is provided on the hanger (1) and connected to the two adjustment blocks (201).

4. The hoisting device for utility tunnel construction according to claim 3, characterized in that, The bidirectional adjustment component includes: A dual-axis motor (5) is fixedly mounted on the hanger (1); Two lead screws (501) are respectively located at the two output ends of the dual-axis motor (5), and two adjusting blocks (201) are respectively threadedly connected to the two lead screws (501).

5. A lifting device for integrated utility tunnel construction according to claim 4, characterized in that, Both ends of the hanger (1) are provided with limiting seats (101), and the ends of the two lead screws (501) are respectively rotatably disposed on the two limiting seats (101).

6. The hoisting device for utility tunnel construction of claim 1, wherein The hanger (1) is provided with mounting bases (4) at both ends, and each of the two mounting bases (4) is provided with a lifting ring (401).

7. The hoisting device for utility tunnel construction of claim 1, wherein Both ends of the adjusting cylinder (2) are provided with limiting wheels (7), and the hanging rope (3) is mounted on the limiting wheels (7).

8. The hoisting device for utility tunnel construction of claim 1, wherein Both of the lifting ropes (3) are provided with hooks (301) at their ends.

Citation Information

Patent Citations

  • Assembly type pipe gallery hoisting device

    CN222410798U