A mounting frame structure and an excavator

The mounting bracket structure with hook and connector solves the problems of complex mounting bracket structure and low reliability in electric hydraulic excavators, and improves convenience and reliability.

CN224955186UActive Publication Date: 2026-11-10LIUZHOU LIUGONG EXCAVATORS CO LTD +2
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202522434740.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-11-17
Publication Date
2026-11-10
Estimated Expiration
2035-11-17

Smart Images

  • Figure CN224955186U_ABST
    Figure CN224955186U_ABST
Patent Text Reader

Abstract

This utility model discloses a mounting frame structure and an excavator. The mounting frame structure includes a mounting support, which has a target hook portion, a target connecting portion, and a fixed connecting portion. The target connecting portion connects to the target bracket to be installed, the target hook portion abuts against the connecting portion between the target bracket and the mounting support, and the fixed connecting portion connects to the underframe of external construction machinery. This utility model's mounting frame structure and excavator can stably support the connecting portion between the target bracket and the mounting support through the target hook portion, providing a certain reaction force to the connecting portion to prevent breakage, thus improving the reliability of the mounting frame. Simultaneously, it eliminates the need for additional complex structural design, reducing the required installation accuracy between the mounting frame and the electric drum bracket, and improving the convenience of loading and unloading the electric drum.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of excavator equipment technology, and in particular to a mounting frame structure and an excavator. Background Technology

[0002] Currently, in electric construction machinery such as electric hydraulic excavators, a mounting bracket is typically used to install the cable reel onto the base frame of the machinery.

[0003] However, current electric drum mounting brackets, such as the one disclosed in patent CN205224143U, have complex welding structures, requiring high precision in the installation and machining between the mounting bracket and the electric drum support. Furthermore, because the electric drum mounting bracket, limited by ground clearance, must be installed at the bottom of the excavator's underframe, the electric drum is susceptible to impacts, which can cause the connecting bolts between the mounting bracket and the electric drum support to break, thus reducing the reliability of the mounting bracket.

[0004] Therefore, how to reduce the required installation accuracy between the mounting frame structure and the electric drum bracket to improve the convenience of loading and unloading the electric drum, and how to improve the reliability of the mounting frame, have become urgent problems to be solved. Utility Model Content

[0005] This utility model discloses a mounting frame structure and an excavator, which can reduce the installation accuracy required between the mounting frame structure and the electric drum support, improve the convenience of loading and unloading the electric drum, and prevent the connection between the mounting frame and the electric drum support from breaking, thereby improving the reliability of the mounting frame.

[0006] To achieve the above objectives, in a first aspect, this utility model discloses a mounting bracket structure, the mounting bracket structure comprising: The mounting bracket has a target barb and a target connecting part at one end, and a fixed connecting part at the other end. The target connecting part is connected to the plane of the target bracket to be installed. The target barb abuts against the connecting part between the target bracket and the target connecting part. The fixed connecting part is connected to the base frame of the external engineering machinery.

[0007] As an optional implementation, in an embodiment of the first aspect of this utility model, the target barb portion includes a first barb portion and a second barb portion, the target connecting portion includes a first threaded connecting portion and a second threaded connecting portion, and the fixed connecting portion includes a first welded portion and a second welded portion; The mounting bracket includes: The first support has a first barb and a first threaded connection at one end, and a first welding part at the other end. The first threaded connection is connected to one end of the target bracket, the first barb abuts against the connection between the target bracket and the first threaded connection, and the first welding part is welded to the base frame of the external engineering machinery. The second support is arranged parallel to the first support. One end of the second support is provided with a second barb and a second threaded connection in sequence. The other end of the second support is provided with a second welding part. The second threaded connection part is connected to the other end of the target bracket. The second barb abuts against the connection between the target bracket and the second threaded connection part. The second welding part is welded to the base frame of the external engineering machinery.

[0008] As an optional implementation, in an embodiment of the first aspect of the present invention, the first threaded connection portion includes a first threaded hole group and a second threaded hole group, and the first welding portion includes a first welding leg and a second welding leg. The first support includes: The first stiffener plate has a first barb portion and a first threaded hole group on one end, and a first welding foot on the other end. The first threaded hole group is screwed to one end of the target bracket. The first barb portion abuts against the connection part between the target bracket and the first threaded hole group. The first welding foot is welded to the base frame of the external engineering machinery. The second stiffener has a second threaded hole group at one end and a second welding foot at the other end. The second threaded hole group is screwed to one end of the target bracket, and the second welding foot is welded to the base frame of the external engineering machinery. The first stiffener and the second stiffener are arranged parallel to each other.

[0009] As an optional implementation, in an embodiment of the first aspect of this utility model, the second threaded connection portion includes a third threaded hole group and a fourth threaded hole group, and the second welding portion includes a third welding leg and a fourth welding leg; The second support includes: The third stiffener has a third threaded hole group at one end and a third welding leg at the other end. The third threaded hole group is screwed to one end of the target bracket, and the third welding leg is welded to the base frame of the external engineering machinery. The fourth rib plate has a second barb portion and a fourth threaded hole group arranged sequentially at one end, and a fourth welding foot at the other end. The fourth threaded hole group is screwed to the other end of the target bracket. The second barb portion abuts against the connection portion between the target bracket and the fourth threaded hole group. The fourth welding foot is welded to the base frame of the external engineering machinery. The third and fourth stiffening plates are arranged parallel to the first and second stiffening plates.

[0010] As an optional implementation, in an embodiment of the first aspect of this utility model, the mounting bracket structure further includes: The first protective plate is disposed between the first stiffener and the second stiffener, and the supporting surface of the first protective plate is flush with the connecting surface of the first stiffener and the connecting surface of the second stiffener. The second protective plate is disposed between the third and fourth stiffeners, and the supporting surface of the second protective plate is flush with the connecting surface of the third and fourth stiffeners.

[0011] As an optional implementation, in an embodiment of the first aspect of this utility model, the mounting bracket structure further includes: The first set of reinforcing plates is disposed on the bottom surface of the base frame and is connected to the bottom surface of the base frame and the mounting support, respectively.

[0012] As an optional implementation, in an embodiment of the first aspect of this utility model, the mounting bracket structure further includes: The second set of reinforcing plates is disposed at the mounting end of the base frame and is connected to both the mounting end of the base frame and the mounting support.

[0013] Secondly, this utility model discloses an excavator, characterized in that the excavator comprises: Base frame; Target stent; An electric reel, the electric reel being mounted on the target support; As described in the first aspect of this utility model, in the mounting bracket structure, the target connecting part is connected to the target bracket, the target barb part abuts against the connecting portion between the target bracket and the target connecting part, and the fixed connecting part is connected to the base frame.

[0014] Compared with the prior art, the beneficial effects of this utility model are as follows: The mounting bracket structure provided by this utility model provides stable support for the connection between the target bracket and the mounting support through the target barb portion, giving the connection portion a certain reaction force to prevent the connection portion from breaking, thereby improving the reliability of the mounting bracket. At the same time, it does not require additional complex structure design, reduces the installation accuracy required between the mounting bracket and the electric drum bracket, and improves the convenience of loading and unloading the electric drum.

[0015] The excavator provided by this utility model adopts the above-mentioned mounting frame structure. The target hook part stably supports the connection between the target bracket and the mounting support, and gives the connection part a certain reaction force to prevent the connection part from breaking, thereby improving the reliability of the mounting frame. At the same time, it does not require additional complex structure design, reduces the installation accuracy required between the mounting frame and the electric drum bracket, and improves the convenience of loading and unloading the electric drum. Attached Figure Description

[0016] Figure 1 This is a schematic diagram of the mounting bracket structure in this utility model; Figure 2 This is a schematic diagram of a specific embodiment of the mounting frame structure and base frame in this utility model; Figure 3 This is a structural diagram of a specific embodiment of the mounting frame structure, base frame, target support, and electric drum in this utility model.

[0017] The meanings of the reference numerals in the attached figures are as follows: Mounting support 01, target bracket 02, base frame 03, electric drum 04, target barb part 010, first barb part 011, second barb part 012, target connecting part 020, fixed connecting part 030, first support 100, first stiffening plate 110, second stiffening plate 120, second support 200, third stiffening plate 210, fourth stiffening plate 220, first protective plate 310, second protective plate 320, first set of reinforcing plates 410, second set of reinforcing plates 420. Detailed Implementation

[0018] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the protection scope of the present utility model.

[0019] In this invention, the terms "upper," "lower," "left," "right," "front," "rear," "top," "bottom," "inner," "outer," "middle," "vertical," "horizontal," "lateral," and "longitudinal" indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. These terms are primarily for the purpose of better describing this invention and its embodiments, and are not intended to limit the indicated device, element, or component to having a specific orientation, or to be constructed and operated in a specific orientation.

[0020] Furthermore, in addition to indicating direction or positional relationship, some of the aforementioned terms may also have other meanings. For example, the term "above" may also be used in some cases to indicate a certain dependency or connection relationship. Those skilled in the art can understand the specific meaning of these terms in this utility model according to the specific circumstances.

[0021] Furthermore, the terms "installation," "setup," "equipped with," "connection," and "linked" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral structure; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium, or an internal connection between two devices, components, or parts. Those skilled in the art can understand the specific meaning of these terms in this utility model based on the specific circumstances.

[0022] Furthermore, the terms "first," "second," etc., are primarily used to distinguish different devices, components, or parts (which may be the same or different in specific type and construction), and are not intended to indicate or imply the relative importance or quantity of the indicated devices, components, or parts. Unless otherwise stated, "a plurality of" means two or more.

[0023] The technical solution of this utility model will be further described below with reference to the embodiments and accompanying drawings.

[0024] Currently, in electric construction machinery such as electric hydraulic excavators, a mounting bracket is typically used to install the cable reel on the base frame of the machinery.

[0025] However, current electric drum mounting brackets, such as the one disclosed in patent CN205224143U, have complex welding structures, requiring high precision in the installation and machining between the mounting bracket and the electric drum support. Furthermore, because the electric drum mounting bracket, limited by ground clearance, must be installed at the bottom of the excavator's underframe, the electric drum is susceptible to impacts, which can cause the connecting bolts between the mounting bracket and the electric drum support to break, thus reducing the reliability of the mounting bracket.

[0026] Therefore, how to reduce the required installation accuracy between the mounting frame structure and the electric drum bracket to improve the convenience of loading and unloading the electric drum, and how to improve the reliability of the mounting frame, have become urgent problems to be solved.

[0027] In response, this utility model discloses a mounting frame structure and an excavator, which can reduce the installation accuracy required between the mounting frame and the electric drum support, improve the convenience of loading and unloading the electric drum, and prevent the connection between the mounting frame and the electric drum support from breaking, thereby improving the reliability of the mounting frame.

[0028] like Figure 1 As shown, this utility model discloses a mounting frame structure, which includes: a mounting support 01, one end of which is provided with a target barb portion 010 and a target connecting portion 020 in sequence, and the other end of which is provided with a fixed connecting portion 030. The target connecting portion 020 is connected to the target bracket 02 to be installed in a plane, the target barb portion 010 abuts against the connecting portion between the target bracket 02 and the target connecting portion 020, and the fixed connecting portion 030 is connected to the base frame 03 of the external engineering machinery.

[0029] In this embodiment, the construction machinery can be electric construction machinery that requires the use of cables, such as electric hydraulic excavators. (Refer to...) Figure 1 and Figure 2 The upper end of the mounting support 01 is provided with a fixed connection part 030, through which the mounting support 01 is connected to the engineering machinery base frame 03.

[0030] The bottom end of the mounting bracket 01 is provided with a target barb portion 010, and the mounting bracket 01 is provided with a target connecting portion 020 above the target barb portion 010. The mounting bracket 01 and the target support 02 are connected through the target connecting portion 020. (Refer to...) Figure 3 The target bracket 02 can mount the electric drum 04, thereby mounting the electric drum 04 onto the base frame 03 of the working machine. The target barb 010 can support the connection part A between the target bracket 02 and the mounting support 01. When the target bracket 02 and the electric drum 04 are subjected to the impact force of lifting, the target barb 010 can provide a certain reaction force to the connection part A to prevent the connection part A from breaking. At the same time, the connection surface of the mounting support 01 facing the target bracket 02 is designed as a plane, that is, the connection between the mounting support 01 and the target bracket 02 is planar. Moreover, the mounting frame structure of this utility model can ensure the connection stability and reliability between the target bracket 02 and the mounting support 01 through the target barb 010 and the target connection part 020. That is, there is no need to design a complex polygonal structure for the mounting support 01 and the target bracket 02 to ensure connection stability, thus reducing the installation accuracy required between the mounting frame structure and the electric drum 04 bracket.

[0031] As can be seen, the mounting frame structure of this utility model can stably support the connection between the target bracket 02 and the mounting support 01 through the target barb part 010, giving the connection part a certain reaction force to prevent the connection part from breaking, thereby improving the reliability of the mounting frame. At the same time, it does not require additional complex structure design, reduces the installation accuracy required between the mounting frame and the target bracket 02, and improves the convenience of loading and unloading the electric drum 04.

[0032] like Figure 2 and Figure 3 As shown, in an optional embodiment, the target barb portion 010 includes a first barb portion 011 and a second barb portion 012; the target connecting portion 020 includes a first threaded connecting portion and a second threaded connecting portion; the fixed connecting portion 030 includes a first welded portion and a second welded portion; the mounting support 01 includes a first support 100 and a second support 200; one end of the first support 100 is provided with a first barb portion 011 and a first threaded connecting portion in sequence, and the other end of the first support 100 is provided with a first welded portion; the first threaded connecting portion is connected to one end of the target bracket 02, and the first barb portion 011 abuts against... The connection between the target bracket 02 and the first threaded connection is provided, and the first welded part is welded to the base frame 03 of the external engineering machinery. The second support 200 is arranged parallel to the first support 100. One end of the second support 200 is provided with a second barb 012 and a second threaded connection in sequence. The other end of the second support 200 is provided with a second welded part. The second threaded connection is connected to the other end of the target bracket 02. The second barb 012 abuts against the connection between the target bracket 02 and the second threaded connection. The second welded part is welded to the base frame 03 of the external engineering machinery.

[0033] In this optional embodiment, refer to Figure 2 and Figure 3 The mounting bracket 01 specifically includes two brackets: a first bracket 100 on the left and a second bracket 200 on the right. Both brackets are perpendicular to the horizontal plane and are parallel to each other. The top of the first bracket 100 has a first welding part, which is used to weld and fix the first bracket 100 to the base frame 03 of the construction machinery. The top of the second bracket 200 has a second welding part, which is used to weld and fix the second bracket 200 to the base frame 03 of the construction machinery.

[0034] The bottom end of the first support 100 is provided with a first barb portion 011 and a first threaded connection portion in sequence, and the bottom end of the second support 200 is provided with a second barb portion 012 and a second threaded connection portion in sequence. The first support 100 is connected to the first connecting portion A1 of the target bracket 02 through the first threaded connection portion, and the second support 200 is connected to the second connecting portion A2 of the target bracket 02 through the second threaded connection portion. The first barb portion 011 can support the first connecting portion A1 between the target bracket 02 and the first support 100, and the second barb portion 012 can support the second connecting portion A2 between the target bracket 02 and the second support 200.

[0035] As can be seen, this optional embodiment can also achieve connection with the target bracket 02 by setting two supports, each of which is provided with a corresponding threaded connection part and a barb part, thereby further improving the connection stability between the target bracket 02 and the mounting support 01.

[0036] like Figure 2 and Figure 3 As shown, in an optional embodiment, the first threaded connection includes a first threaded hole group and a second threaded hole group, and the first welding part includes a first welding leg and a second welding leg; the first support 100 includes: a first stiffener 110 and a second stiffener 120; one end of the first stiffener 110 is provided with a first barb 011 and a first threaded hole group in sequence, and the other end of the first stiffener 110 is provided with a first welding leg, the first threaded hole group is screwed to one end of the target bracket 02, the first barb 011 abuts against the connection part between the target bracket 02 and the first threaded hole group, and the first welding leg is welded to the base frame 03 of the external engineering machinery; one end of the second stiffener 120 is provided with a second threaded hole group, and the other end of the second stiffener 120 is provided with a second welding leg, the second threaded hole group is screwed to one end of the target bracket 02, and the second welding leg is welded to the base frame 03 of the external engineering machinery; wherein, the first stiffener 110 and the second stiffener 120 are arranged parallel to each other.

[0037] In this optional embodiment, refer to Figure 2 and Figure 3 The first support 100 specifically includes two stiffening plates, namely the leftmost first stiffening plate 110 and the rightmost second stiffening plate 120, which are arranged parallel to each other at a certain preset interval. The upper end of the first stiffening plate 110 has a first welding foot, and the upper end of the second stiffening plate 120 has a second welding foot. The two stiffening plates are welded and fixed to the base frame 03 of the engineering machinery through the corresponding welding feet.

[0038] The bottom end of the first stiffening plate 110 is sequentially provided with a first barb portion 011 and a first threaded hole group. The bottom end of the second stiffening plate 120 only needs to be provided with a second threaded hole group. The first threaded hole group and the second threaded hole group are arranged horizontally correspondingly, and each threaded hole group contains at least two threaded connection holes. The two stiffening plates are screwed to the first connecting part A1 of the target bracket 02 through the corresponding threaded hole groups by screws, and the first connecting part A1 is supported by the first barb portion 011 of the first stiffening plate 110. It can be understood that the number of threaded connection holes provided in the first threaded hole group and the second threaded hole group can be adaptively adjusted according to actual needs, for example... Figure 2 The first and second threaded hole groups each have four threaded connection holes.

[0039] As can be seen, this optional embodiment can also be equipped with two stiffening plates through the first support 100, and can be connected to the target bracket 02 through the corresponding threaded hole group and barb part, thereby further improving the connection stability between the target bracket 02 and the mounting support 01.

[0040] like Figure 2 As shown, in an optional embodiment, the second threaded connection includes a third threaded hole group and a fourth threaded hole group, and the second welding part includes a third welding leg and a fourth welding leg; the second support 200 includes: a third stiffener 210 and a fourth stiffener 220; one end of the third stiffener 210 is provided with a third threaded hole group, and the other end of the third stiffener 210 is provided with a third welding leg, the third threaded hole group is screwed to one end of the target bracket 02, and the third welding leg is welded to the base frame 03 of the external engineering machinery; one end of the fourth stiffener 220 is provided with a second barb 012 and a fourth threaded hole group in sequence, the other end of the fourth stiffener 220 is provided with a fourth welding leg, the fourth threaded hole group is screwed to the other end of the target bracket 02, the second barb 012 abuts against the connection part between the target bracket 02 and the fourth threaded hole group, and the fourth welding leg is welded to the base frame 03 of the external engineering machinery; wherein, the third stiffener 210, the fourth stiffener 220 and the first stiffener 110 and the second stiffener 120 are arranged parallel to each other.

[0041] In this optional embodiment, refer to Figure 2 and Figure 3The second support 200 specifically includes two stiffening plates: a third stiffening plate 210 located to the right of the second stiffening plate 120 and a fourth stiffening plate 220 located on the far right. The first stiffening plate 110, the second stiffening plate 120, the third stiffening plate 210, and the fourth stiffening plate 220 are arranged parallel to each other at a certain preset interval. The interval between the first stiffening plate 110 and the second stiffening plate 120 can be the same as the interval between the third stiffening plate 210 and the fourth stiffening plate 220. The interval between the second stiffening plate 120 and the third stiffening plate 210 is greater than the interval between any two adjacent stiffening plates. The upper end of the third stiffening plate 210 has a third welding foot, and the upper end of the fourth stiffening plate 220 has a fourth welding foot. The two stiffening plates are welded and fixed to the base frame 03 of the engineering machinery through their corresponding welding feet.

[0042] The bottom end of the third stiffener 210 only needs to be provided with a third threaded hole group, while the bottom end of the fourth stiffener 220 is provided with a second barb portion 012 and a fourth threaded hole group in sequence. The third and fourth threaded hole groups are horizontally corresponding, and each threaded hole group contains at least two threaded connection holes. The two stiffeners are screwed to the second connecting part A2 of the target bracket 02 through the corresponding threaded hole groups using screws, and the second connecting part A2 is supported by the second barb portion 012 of the fourth stiffener 220. It can be understood that the number of threaded connection holes provided in each of the third and fourth threaded hole groups can be adaptively adjusted according to actual needs, for example... Figure 2 The first, second, third, and fourth threaded hole groups are each provided with four threaded connection holes.

[0043] As can be seen, this optional embodiment can also be equipped with two stiffening plates through the second support 200, and can be connected to the target bracket 02 through the corresponding threaded hole group and barb part, thereby further improving the connection stability between the target bracket 02 and the mounting support 01.

[0044] like Figure 2 As shown, in an optional embodiment, the mounting frame structure further includes: a first protective plate 310 and a second protective plate 320; the first protective plate 310 is disposed between the first stiffener 110 and the second stiffener 120, and the supporting surface of the first protective plate 310 is flush with the connecting surface of the first stiffener 110 and the connecting surface of the second stiffener 120; the second protective plate 320 is disposed between the third stiffener 210 and the fourth stiffener 220, and the supporting surface of the second protective plate 320 is flush with the connecting surface of the third stiffener 210 and the connecting surface of the fourth stiffener 220.

[0045] In this optional embodiment, refer to Figure 2A first protective plate 310 is provided between the first stiffener 110 and the second stiffener 120. The supporting surface of the first protective plate 310 facing the target bracket 02 is flush with the connecting surfaces of the first stiffener 110 and the second stiffener 120 facing the target bracket 02. A second protective plate 320 is provided between the third stiffener 210 and the fourth stiffener 220. The supporting surface of the second protective plate 320 facing the target bracket 02 is flush with the connecting surfaces of the third stiffener 210 and the fourth stiffener 220 facing the target bracket 02. When the four stiffeners are subjected to impact from the target bracket 02 and the electric drum 04, the first protective plate 310 and the second protective plate 320 can prevent the stiffeners from deforming due to insufficient pressure area.

[0046] As can be seen, this optional embodiment can also prevent the stiffeners from deforming due to insufficient pressure area by setting a protective plate between the two stiffeners, thereby further ensuring the reliability of the mounting frame structure.

[0047] like Figure 2 As shown, in an optional embodiment, the mounting frame structure further includes a first set of reinforcing plates 410, which are disposed on the bottom surface of the base frame 03 and are connected to the bottom surface of the base frame 03 and the mounting support 01 respectively.

[0048] In this optional embodiment, refer to Figure 2 A first set of reinforcing plates 410 is provided at the angle between the bottom surface of the engineering machinery base frame 03 and the lower section of the stiffening plate. The first set of reinforcing plates 410 includes multiple first support 100 reinforcing plates, for example... Figure 2 The number of reinforcing plates of the first support 100 can be set to two, that is, each of the first support 100 and the second support 200 is configured with one reinforcing plate of the first support 100.

[0049] As can be seen, this optional embodiment can also fix the connection between the four stiffening plates and the base frame 03 of the engineering machinery through the first set of reinforcing plates 410, thereby improving the stability of the mounting frame structure.

[0050] like Figure 2 As shown, in an optional embodiment, the mounting frame structure further includes a second set of reinforcing plates 420, which are disposed at the mounting end of the base frame 03 and are connected to the mounting end of the base frame 03 and the mounting support 01, respectively.

[0051] In this optional embodiment, refer to Figure 2 The side of the engineering machinery base frame 03 facing the stiffening plate and the target support 02 is the mounting end of the base frame 03. The mounting end of the base frame 03 has a certain concave portion. The second set of reinforcing plates 420 is disposed in the gap between the mounting end of the base frame 03 and the stiffening plate. The second set of reinforcing plates 420 includes multiple second support 200 reinforcing plates, for example... Figure 2The number of reinforcing plates of the second support 200 can be set to two, that is, each of the first support 100 and the second support 200 is equipped with a second support 200 reinforcing plate.

[0052] As can be seen, this optional embodiment can also fix the connection between the four stiffening plates and the base frame 03 of the engineering machinery through the second set of reinforcing plates 420, thereby further improving the stability of the mounting frame structure.

[0053] This utility model also discloses an excavator, which includes a base frame 03, a target support 02, an electric drum 04, and the mounting frame structure described in the above embodiments of this utility model. The electric drum 04 is mounted on the target support 02, the target connecting part 020 is connected to the target support 02, the target barb part 010 abuts against the connecting part between the target support 02 and the target connecting part 020, and the fixed connecting part 030 is connected to the base frame 03.

[0054] As can be seen, in this embodiment, the excavator can use the above-mentioned mounting frame structure to stably support the connection between the target bracket 02 and the mounting support 01 through the target hook part 010, giving the connection part a certain reaction force to prevent the connection part from breaking, thereby improving the reliability of the mounting frame. At the same time, it does not require additional complex structure design, reduces the installation accuracy required between the mounting frame and the electric drum 04 bracket, and improves the convenience of loading and unloading the electric drum 04.

[0055] The technical means disclosed in this utility model are not limited to those disclosed in the above embodiments, but also include technical solutions composed of any combination of the above technical features. It should be noted that those skilled in the art can make various improvements and modifications without departing from the principle of this utility model, and these improvements and modifications are also considered within the scope of protection of this utility model.

Claims

1. A mounting rack structure characterized by comprising: The mounting bracket structure includes: The mounting bracket has a target barb and a target connecting part at one end, and a fixed connecting part at the other end. The target connecting part is connected to the plane of the target bracket to be installed. The target barb abuts against the connecting part between the target bracket and the target connecting part. The fixed connecting part is connected to the base frame of the external engineering machinery.

2. The mounting structure of claim 1, wherein The target barb portion includes a first barb portion and a second barb portion; the target connecting portion includes a first threaded connecting portion and a second threaded connecting portion; and the fixed connecting portion includes a first welded portion and a second welded portion. The mounting bracket includes: The first support has a first barb and a first threaded connection at one end, and a first welding part at the other end. The first threaded connection is connected to one end of the target bracket, the first barb abuts against the connection between the target bracket and the first threaded connection, and the first welding part is welded to the base frame of the external engineering machinery. The second support is arranged parallel to the first support. One end of the second support is provided with a second barb and a second threaded connection in sequence. The other end of the second support is provided with a second welding part. The second threaded connection part is connected to the other end of the target bracket. The second barb abuts against the connection between the target bracket and the second threaded connection part. The second welding part is welded to the base frame of the external engineering machinery.

3. The mount structure of claim 2, wherein The first threaded connection portion includes a first threaded hole group and a second threaded hole group, and the first welding portion includes a first welding leg and a second welding leg; The first support includes: The first stiffener plate has a first barb portion and a first threaded hole group on one end, and a first welding foot on the other end. The first threaded hole group is screwed to one end of the target bracket. The first barb portion abuts against the connection part between the target bracket and the first threaded hole group. The first welding foot is welded to the base frame of the external engineering machinery. The second stiffener has a second threaded hole group at one end and a second welding foot at the other end. The second threaded hole group is screwed to one end of the target bracket, and the second welding foot is welded to the base frame of the external engineering machinery. The first stiffener and the second stiffener are arranged parallel to each other.

4. The mount structure of claim 3, wherein The second threaded connection portion includes a third threaded hole group and a fourth threaded hole group, and the second welding portion includes a third welding leg and a fourth welding leg; The second support includes: The third stiffener has a third threaded hole group at one end and a third welding leg at the other end. The third threaded hole group is screwed to one end of the target bracket, and the third welding leg is welded to the base frame of the external engineering machinery. The fourth rib plate has a second barb portion and a fourth threaded hole group on one end, and a fourth welding foot on the other end. The fourth threaded hole group is screwed to the other end of the target bracket. The second barb portion abuts against the connection part between the target bracket and the fourth threaded hole group. The fourth welding foot is welded to the base frame of the external engineering machinery. The third and fourth stiffening plates are arranged parallel to the first and second stiffening plates.

5. The mount structure of claim 4, wherein The mounting bracket structure also includes: The first protective plate is disposed between the first stiffener and the second stiffener, and the supporting surface of the first protective plate is flush with the connecting surface of the first stiffener and the connecting surface of the second stiffener. The second protective plate is disposed between the third and fourth stiffeners, and the supporting surface of the second protective plate is flush with the connecting surface of the third and fourth stiffeners.

6. The mount structure of any one of claims 1 to 5, wherein The mounting bracket structure also includes: The first set of reinforcing plates is disposed on the bottom surface of the base frame and is connected to the bottom surface of the base frame and the mounting support, respectively.

7. The mount structure of any one of claims 1 to 5, wherein The mounting bracket structure also includes: The second set of reinforcing plates is disposed at the mounting end of the base frame and is connected to both the mounting end of the base frame and the mounting support.

8. An excavator, characterized in that, The excavator includes: Base frame; Target stent; An electric reel, which is mounted on the target support; In the mounting bracket structure as described in any one of claims 1 to 7, the target connecting portion is connected to the target bracket, the target barb portion abuts against the connecting portion between the target bracket and the target connecting portion, and the fixed connecting portion is connected to the base frame.

Citation Information

Patent Citations

  • Electronic hydraulic shovel power consumption reel mounting bracket

    CN205224143U