High pressure water jet concrete breaking device for viaduct

The disassembly mechanism, consisting of a perforated tube and a ball-locking ring, solves the problem of difficult nozzle disassembly and assembly in high-pressure water jet equipment for viaducts, enabling rapid nozzle replacement and secure connection, thus improving construction efficiency and safety.

CN224955489UActive Publication Date: 2026-11-10HENAN BOMIAO WATER TREATMENT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522505680.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-11-26
Publication Date
2026-11-10
Estimated Expiration
2035-11-26

AI Technical Summary

Technical Problem

In existing high-pressure water jet concrete demolition equipment for viaducts, the nozzles are fixed by threads, which requires a large pre-tightening force, making disassembly and assembly difficult during high-altitude operations and affecting the continuity and safety of construction.

Method used

The disassembly mechanism, consisting of a multi-hole tube, a retaining ball, and a pull ring, uses a spring to provide a restoring force, enabling quick disassembly and installation of the nozzle. The interlocking fit between the retaining ball and the aligning retaining ring ensures a secure connection of the nozzle.

Benefits of technology

It enables rapid nozzle replacement, improves the efficiency and safety of bridge maintenance operations, ensures the stability and reliability of nozzle connections during high-pressure operations, and avoids the inconvenience and safety risks of carrying tools.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224955489U_ABST
    Figure CN224955489U_ABST
Patent Text Reader

Abstract

The utility model relates to engineering machinery technical field discloses a high pressure water jet concrete breaking equipment suitable for viaduct, including mobile device and front end fixed pipe, and the fixed pipe bottom end is installed with dismounting mechanism, and the dismounting mechanism includes porous pipe, drive assembly and ball, and the porous pipe is inserted with the alignment snap ring of nozzle, and drive assembly includes pull ring and spring, and the pull ring is pressed and is kept under the spring action ball and makes it snap into the alignment snap ring outer wall to lock nozzle, and the pull ring compresses spring, and the ball is retracted and releases nozzle, and the mobile device rear end water inlet outside is sleeved with the reinforcing mechanism, and is embraced tightly pipeline interface through double hinged ring and connecting rod locking assembly. The utility model through the steel ball locking structure realizes nozzle bare hands quick assembly and disassembly, solves the difficult problem of replacing in high altitude operation, and is stable in connection, and cooperates water inlet reinforcing mechanism, effectively prevents pipeline vibration and falls off, promotes construction efficiency and safety.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of engineering machinery technology, and in particular to a high-pressure water jet concrete demolition device suitable for viaducts. Background Technology

[0002] With the continuous development of urban transportation infrastructure construction, elevated bridges, as an important part of the urban transportation network, are increasingly undergoing maintenance, reinforcement, and renovation projects. During bridge maintenance, it is often necessary to remove and clean the aging concrete surface, damaged pavement, or substandard concrete structure in order to carry out subsequent repairs or re-pouring. High-pressure water jet technology, due to its advantages such as selective removal, no damage to reinforcing steel, no dust pollution, and low vibration, has gradually replaced traditional pneumatic hammer breaking and has become the preferred process for concrete removal of elevated bridges.

[0003] However, in the actual application of high-pressure water jet demolition operations, the core component—the high-pressure nozzle—is subjected to the scouring of high-speed water flow containing abrasive materials for a long time, resulting in extremely rapid wear. It is a vulnerable part that requires frequent replacement. Currently, most existing demolition equipment uses threaded connections to fix the nozzle. Under high-pressure conditions, this connection method usually requires a huge pre-tightening force to prevent water leakage, making disassembly very difficult. Especially at elevated bridge construction sites, the working environment is often located at high altitudes and in narrow spaces. When changing the nozzle, operators need to carry heavy tools such as pipe wrenches, which is not only time-consuming and laborious, seriously affecting the continuity of construction and work efficiency, but also increases the safety risk of personnel falling or tools falling when performing cumbersome tool operations at high altitudes.

[0004] Therefore, this utility model proposes a high-pressure water jet concrete demolition device suitable for viaducts to overcome the shortcomings of the prior art. Utility Model Content

[0005] To overcome the above shortcomings, this utility model provides a high-pressure water jet concrete demolition device suitable for elevated bridges. It aims to improve the problem that the nozzle connection method of some high-pressure water jet concrete demolition devices for elevated bridges is mostly fixed by threads, which requires a great pre-tightening force under high pressure conditions, making it extremely difficult to disassemble and assemble in high-altitude operations and narrow spaces on elevated bridges.

[0006] This utility model provides a high-pressure water jet concrete demolition device suitable for viaducts, including: a mobile device and a fixed pipe installed at the front end of the mobile device, and a dismantling mechanism installed at the bottom end of the fixed pipe. The dismantling mechanism consists of a multi-hole pipe, a drive assembly and a locking ball.

[0007] The porous tube is fixedly connected to the bottom end of the fixed tube. A through hole is opened on the side wall of the porous tube. The ball is movably embedded in the through hole. An alignment retaining ring is inserted into the inside of the porous tube. A nozzle is fixedly connected to the bottom end of the alignment retaining ring.

[0008] Furthermore, the drive assembly includes a pull ring slidably sleeved on the outer wall of the porous tube and a spring abutting between the porous tube and the pull ring. Under the elastic force of the spring, the pull ring moves downward and presses against the locking ball, forcing a portion of the spherical surface of the locking ball to protrude from the inner wall of the porous tube and engage with the outer wall of the alignment locking ring to lock the nozzle. When unlocking is required, the pull ring is pulled upward and the spring is compressed, the pull ring releases the pressure on the locking ball, and the locking ball can retract into the wall of the porous tube to release the alignment locking ring.

[0009] Preferably, the outer peripheral wall of the alignment retainer has an annular groove. When the retaining ball is squeezed by the pull ring, it is inserted into the annular groove, and the upper end face of the alignment retainer abuts against the inner top surface of the porous tube, thereby achieving axial stable positioning through the concave-convex fit.

[0010] Preferably, the outer wall of the porous tube is provided with a flange, the inner wall of the pull ring is provided with an inner step, the spring is sleeved on the outer side of the porous tube, and the two ends of the spring abut against the lower surface of the flange and the upper surface of the inner step, respectively, thereby providing the pull ring with a continuous downward reset pressure.

[0011] Preferably, the rear end of the mobile device is provided with a water inlet, and a reinforcement mechanism is sleeved on the outside of the water inlet. The reinforcement mechanism includes a hinge ring one and a hinge ring two rotatably connected to the hinge ring one. The hinge ring one and the hinge ring two together hug the outer periphery of the water inlet to enhance the seismic performance of the pipe connection.

[0012] Preferably, a base plate is fixedly connected to the top of the first hinge ring, a pull-up bend plate is rotatably connected to the front end of the base plate, a frame locking post is rotatably connected to the pull-up bend plate, a locking block is fixedly connected to the top of the second hinge ring, and the end of the frame locking post away from the pull-up bend plate can be sleeved on the outside of the locking block, and quick locking is achieved through a linkage mechanism.

[0013] Preferably, the side of the locking block away from the second hinge ring has a curved structure, and the frame locking post is engaged with the curved structure of the locking block to prevent slippage during the stress process.

[0014] Preferably, a limiting block is fixedly connected to the top surface of the base plate, and a rectangular through hole is provided in the middle of the pull-up bending plate. When the pull-up bending plate rotates to fit the surface of the base plate, the limiting block passes through and protrudes from the rectangular through hole, thereby using a mechanical structure to restrict the springback of the pull-up bending plate.

[0015] Preferably, the mobile device has a robotic arm at its front end, the fixing tube is fixedly installed at the end of the robotic arm, and the bottom of the mobile device has tracks to adapt to the complex working environment of the viaduct.

[0016] This utility model has the following beneficial effects: 1. This utility model, by setting up a disassembly mechanism, utilizes the cooperation of pull ring, spring and locking ball to realize the quick disassembly and installation of nozzles, which solves the problem that the nozzles in the prior art mostly use threaded connection, which is time-consuming, inefficient and has safety hazards when replacing them in high-altitude operations or harsh environments. It achieves the technical effect of completing nozzle replacement by hand without the need for additional tools, which significantly improves the efficiency and safety of bridge maintenance operations.

[0017] 2. This utility model solves the problem that existing quick-release structures are prone to loosening or falling off under the recoil force of ultra-high pressure water jets by setting a multi-hole tube at the bottom of the fixed tube in conjunction with an embedded retaining ball, and setting an alignment retaining ring with an annular groove above the nozzle. It achieves the technical effect of using a multi-point mechanical locking structure with steel balls to provide strong axial tensile load-bearing capacity and ensure a stable and reliable nozzle connection during high-pressure operations.

[0018] 3. This utility model, by setting up an inlet reinforcement mechanism and adopting a double-hinged ring clamp with a connecting rod elbow locking structure, solves the problem that the interface of the existing high-pressure water inlet pipeline is prone to loosening, leakage, or even falling off when there is severe vibration during operation. It achieves the technical effect of being able to quickly and forcefully tighten and reinforce the pipeline interface, and using a limit block to achieve mechanical self-locking to prevent accidental opening, thus ensuring the continuity of construction and the safety of water supply.

[0019] 4. This utility model, by adopting a tracked mobile chassis combined with a front-end robotic arm structure, solves the problems of existing equipment having difficulty moving on elevated bridge surfaces covered with concrete debris and having many blind spots in operation. It achieves the technical effect of having good obstacle-crossing ability and operational flexibility, being able to adapt to the complex construction environment of elevated bridges, and realizing all-round and efficient concrete demolition. Attached Figure Description

[0020] Figure 1 This is a three-dimensional schematic diagram of a high-pressure water jet concrete demolition device suitable for viaducts proposed in this utility model; Figure 2 Exploded view of the dismantling mechanism of a high-pressure water jet concrete demolition device for viaducts proposed in this utility model; Figure 3 This is a schematic diagram of the inlet structure of a high-pressure water jet concrete demolition device suitable for viaducts, as proposed in this utility model. Figure 4 for Figure 3 Enlarged view of point A in the middle.

[0021] Legend: 1. Mobile equipment; 2. Fixed pipe; 3. Water inlet; 4. Disassembly mechanism; 41. Perforated tube; 42. Drive assembly; 421. Pull ring; 422. Spring; 43. Ball jamming; 44. Alignment retaining ring; 45. Nozzle; 5. Reinforcing mechanism; 51. Hinge ring one; 52. Hinge ring two; 53. Base plate; 54. Pull-up bending plate; 55. Limiting block; 56. Frame locking column; 57. Locking block. Detailed Implementation

[0022] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the protection scope of the present utility model.

[0023] Example: Reference Figures 1 to 4 This utility model provides a high-pressure water jet concrete demolition device suitable for viaducts, which aims to solve the structural defects in the prior art of cumbersome nozzle replacement and easy loosening of high-pressure water inlet pipeline connection due to vibration during concrete demolition operations on viaducts.

[0024] like Figure 1 As shown, the device includes a mobile device 1 and a fixed pipe 2 installed at the front end of the mobile device 1. The mobile device 1 serves as the mobile carrier and power platform for the entire device. The fixed pipe 2 is used to deliver high-pressure water to the end of the operation. A robotic arm is provided at the front end of the mobile device 1. The fixed pipe 2 is fixedly installed at the end of the robotic arm. The robotic arm is used to adjust the position and angle of the fixed pipe 2 and the spray end. Tracked walking mechanisms are provided on both sides of the bottom of the mobile device 1 for stable movement on complex construction surfaces.

[0025] like Figure 1 and Figure 2As shown, a disassembly mechanism 4 is installed at the bottom end of the fixed tube 2. The disassembly mechanism 4 is used to realize the quick installation and disassembly of the nozzle 45, thereby improving the efficiency of the replacement operation. The disassembly mechanism 4 includes a porous tube 41, a drive assembly 42, and a retaining ball 43. The porous tube 41 is fixedly connected to the bottom end of the fixed tube 2. The porous tube 41 serves as a connecting base, and its side wall has a through hole for accommodating the retaining ball 43. The retaining ball 43 is movably embedded inside the through hole and can move radially along the through hole.

[0026] like Figure 2 As shown, the drive assembly 42 includes a pull ring 421 slidably sleeved on the outer wall of the porous tube 41 and a spring 422 abutting between the porous tube 41 and the pull ring 421. The pull ring 421 is used to control the radial position of the locking ball 43 by sliding up and down. The spring 422 is used to provide a reset force to maintain the locked state. The outer wall of the porous tube 41 is provided with a flange, and the inner wall of the pull ring 421 is provided with an inner step. The spring 422 is sleeved on the outer side of the porous tube 41, and the two ends of the spring 422 abut against the lower surface of the flange and the upper surface of the inner step, respectively, so as to always provide a downward thrust to the pull ring 421.

[0027] An alignment ring 44 is inserted inside the porous tube 41, and a specific structural fit and connection relationship is formed between the alignment ring 44 and the dismantling mechanism 4. A nozzle 45 is fixedly connected to the bottom end of the alignment ring 44. The alignment ring 44 is used as an intermediate part for docking the nozzle 45 and the dismantling mechanism 4. The nozzle 45 is used to spray high-pressure water to carry out concrete demolition operations.

[0028] Reference Figure 2 The alignment retaining ring 44 has an annular groove on its outer peripheral wall and a flat contact surface on its upper end face. The alignment retaining ring 44 is installed in the internal cavity of the porous tube 41 by insertion, and the upper end face of the alignment retaining ring 44 abuts against the inner top surface of the porous tube 41. Its function is to ensure that the nozzle 45 has accurate axial positioning after installation and to prevent it from being displaced under high pressure recoil force.

[0029] Meanwhile, the ball 43 is configured to cooperate with the annular groove of the aligning retaining ring 44. In the locked state, the pull ring 421 is in a low position under the elastic force of the spring 422. The inner wall of the pull ring 421 presses against the ball 43, forcing part of the spherical surface of the ball 43 to protrude from the inner wall of the porous tube 41 and be inserted into the annular groove on the outer wall of the aligning retaining ring 44. This steel ball locking structure ensures that the nozzle 45 is firmly locked in the porous tube 41 and cannot fall off axially.

[0030] When disassembly is required, the operator unlocks the device via drive assembly 42. Specifically, by pulling the pull ring 421 upwards and compressing the spring 422, the pull ring 421 moves upwards along the outer wall of the porous tube 41. The wider part of the inner wall of the pull ring 421 moves to the retaining ball 43 or the pull ring 421 is completely removed, thereby releasing the pressure on the retaining ball 43. The retaining ball 43 loses its radial constraint and can retract into the wall of the porous tube 41, thereby exiting the annular groove of the alignment retaining ring 44 to release the alignment retaining ring 44. At this point, the nozzle 45 can be pulled downwards to complete the disassembly. When replacing the nozzle 45, simply insert the new nozzle with the alignment retaining ring 44 into the porous tube 41 and release the pull ring 421. The mechanism will then automatically reset and lock.

[0031] The rear end of the mobile device 1 is provided with a water inlet 3, which is used to connect to an external water supply pipe. A reinforcing mechanism 5 is sleeved on the outside of the water inlet 3, which is used to assist in locking the pipe connection.

[0032] Reference Figure 3 and Figure 4 The reinforcing mechanism 5 includes a first hinge ring 51 and a second hinge ring 52 rotatably connected to the first hinge ring 51. The first hinge ring 51 and the second hinge ring 52 are hinged by a pin at the bottom, allowing them to open and close relative to each other and together clamp around the outer periphery of the connection between the inlet 3 and the external pipe. A strong radial clamping force is provided by a clamp-like structure. A base plate 53 is fixedly connected to the top of the first hinge ring 51, and a pull-up bend plate 54 is rotatably connected to the front end of the base plate 53. A frame clamping post 56 is rotatably connected to the pull-up bend plate 54. A clamping block 57 is fixedly connected to the top of the second hinge ring 52, and the end of the frame clamping post 56 away from the pull-up bend plate 54 can be fitted onto the outside of the clamping block 57. This linkage toggle mechanism utilizes the lever principle, enabling convenient operation while generating tremendous locking force. The locking block 57 has a curved structure on the side opposite to the hinge ring 52, forming an outwardly protruding hook-shaped part. The frame locking post 56 engages with the curved structure of the locking block 57 to prevent the frame locking post 56 from slipping during tightening. The top surface of the base plate 53 is fixedly connected to a limit block 55. A rectangular through hole is provided in the middle of the pulling bent plate 54. When the pulling bent plate 54 rotates to the locking position and fits against the surface of the base plate 53, the limit block 55 passes through and protrudes from the rectangular through hole, mechanically limiting and blocking the springback tendency of the pulling bent plate 54 to ensure the safety of the locking state.

[0033] The implementation principle of this application embodiment is as follows: When the equipment is preparing for operation, the rear end of the mobile device 1 is connected to an external water pipe through the water inlet 3. In order to prevent the pipe from vibrating and falling off due to high pressure water flow, the operator uses the reinforcement mechanism 5 to reinforce the pipe connection. Specifically, the hinge ring 1 51 and hinge ring 2 52 are put on the connection between the pipe and the water inlet 3, and then the frame clamp post 56 is put on the bend of the clamp block 57.

[0034] Subsequently, the pulling bend plate 54, which rotates at the front end of the base plate 53, is pulled to rotate towards the base plate 53. During this process, the frame locking post 56 is pulled closer to the base plate 53 by the pulling force of the pulling bend plate 54, thereby realizing the alignment and clamping fixation of the first hinge ring 51 and the second hinge ring 52, until the pulling bend plate 54 is fitted onto the limiting block 55, completing the self-locking limit.

[0035] During the operation, the mobile device 1 travels to the elevated bridge work site and controls the fixed pipe 2 to rotate and adjust the angle through the front robotic arm. High-pressure water flows through the fixed pipe 2 and is ejected from the nozzle 45 to spray and peel off the concrete from the cement soil of the elevated bridge for bridge repair, reinforcement and renovation.

[0036] When the nozzle 45 needs to be replaced, the user can quickly disassemble it by driving the component 42. Specifically, the user pulls the pull ring 421 upwards, and the pull ring 421 slides on the outside of the porous tube 41. At the same time, the user squeezes the spring 422 at both ends that abuts the porous tube 41 and the pull ring 421. At this time, the pull ring 421 moves upwards, releasing the ball 43 that was squeezed on the inside of the pull ring 421.

[0037] At this point, the nozzle 45 can be pulled down, causing the alignment ring 44 to disengage from the ball 43. The ball 43 retracts into the inside of the porous tube 41. When replacing the nozzle 45, simply align and insert the new alignment ring 44 into the porous tube 41. The alignment ring 44 contacts the ball 43 and pushes it away, so that the ball 43 is finally inserted into the annular groove of the alignment ring 44. Release the pull ring 421, and the spring 422 will return and reset the pull ring 421. The pull ring 421 will then apply pressure to the ball 43 again, so that the ball 43 is stably positioned inside the annular groove of the alignment ring 44, thus achieving the purpose of fixed installation and disassembly.

Claims

1. A high-pressure water jet concrete breaking device suitable for viaducts, comprising a mobile device (1) and a fixed pipe (2) installed at the front end of the mobile device (1); characterized in that A dismounting mechanism (4) is installed at the bottom end of the fixed pipe (2), and the dismounting mechanism (4) comprises a perforated pipe (41), a driving assembly (42) and a clamping ball (43); The perforated pipe (41) is fixedly connected to the bottom end of the fixed pipe (2), the side wall of the perforated pipe (41) is provided with a through hole, and the clamping ball (43) is movably embedded in the through hole; The driving assembly (42) comprises a pull ring (421) slidably sleeved on the outer wall of the perforated pipe (41) and a spring (422) abutting between the perforated pipe (41) and the pull ring (421); The inside of the perforated pipe (41) is inserted with a positioning clamping ring (44), and the bottom end of the positioning clamping ring (44) is fixedly connected with a nozzle (45); Under the elastic force of the spring (422), the pull ring (421) moves downward and abuts against the clamping ball (43), forcing the clamping ball (43) to protrude from the inner wall of the perforated pipe (41) and be clamped into the outer wall of the positioning clamping ring (44), so as to lock the nozzle (45); When the pull ring (421) is pulled upward and the spring (422) is compressed, the pull ring (421) releases the abutment of the clamping ball (43), and the clamping ball (43) can retract into the wall of the perforated pipe (41) to release the positioning clamping ring (44).

2. The high-pressure water jet concrete breaking device for viaducts according to claim 1, characterized in that, The outer peripheral wall of the positioning clamping ring (44) is provided with a ring-shaped groove, the clamping ball (43) is clamped into the ring-shaped groove when it is pressed by the pull ring (421), and the upper end surface of the positioning clamping ring (44) abuts against the inner top surface of the perforated pipe (41).

3. The high-pressure water jet concrete breaking device for viaducts according to claim 1, characterized in that, The outer wall of the perforated pipe (41) is provided with a flange, the inner wall of the pull ring (421) is provided with an inner step, the spring (422) is sleeved on the outer side of the perforated pipe (41), and the two ends of the spring (422) abut against the lower surface of the flange and the upper surface of the inner step, respectively.

4. The high-pressure water jet concrete breaking apparatus for viaducts according to claim 1, characterized in that, The rear end of the mobile device (1) is provided with a water inlet (3), and the outer side of the water inlet (3) is sleeved with a reinforcing mechanism (5); The reinforcing mechanism (5) comprises a hinge ring one (51) and a hinge ring two (52) rotationally connected with the hinge ring one (51), and the hinge ring one (51) and the hinge ring two (52) are jointly clamped on the outer periphery of the water inlet (3).

5. The high-pressure water jet concrete breaking apparatus for viaducts according to claim 4, characterized in that, The top of the hinge ring one (51) is fixedly connected with a bottom plate (53), and the front end of the bottom plate (53) is rotationally connected with a pulling bent plate (54); The pulling bent plate (54) is rotationally connected with a frame clamping column (56), the top of the hinge ring two (52) is fixedly connected with a clamping block (57), and the end of the frame clamping column (56) away from the pulling bent plate (54) can be sleeved on the outer side of the clamping block (57).

6. The high-pressure water jet concrete breaking apparatus for viaducts according to claim 5, characterized in that, The side of the clamping block (57) away from the hinge ring two (52) has a curved structure, and the frame clamping column (56) is clamped at the curved structure of the clamping block (57).

7. The high-pressure water jet concrete breaking apparatus for viaducts according to claim 5, characterized in that, The top surface of the bottom plate (53) is fixedly connected with a limiting block (55), and a rectangular through hole is formed in the middle of the pulling bent plate (54), when the pulling bent plate (54) is rotated to be attached to the surface of the bottom plate (53), the limiting block (55) penetrates through and protrudes from the rectangular through hole.

8. The high-pressure water jet concrete breaking apparatus for viaducts according to claim 1, characterized in that, The front end of the mobile device (1) is provided with a mechanical arm, the fixed pipe (2) is fixedly installed at the tail end of the mechanical arm, and the bottom of the mobile device (1) is provided with a caterpillar track.