A modular, detachable, corrosion-resistant connection node structure for offshore photovoltaic support
By combining sleeves, positioning holes, pins, and ball clamps, along with anti-corrosion measures, the problem of easy corrosion at the connection nodes of offshore photovoltaic supports has been solved, enabling rapid and reliable modular installation and disassembly, thus improving construction efficiency and service life.
Patent Information
- Application Number
- CN202522642769.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-12-12
- Publication Date
- 2026-11-17
- Estimated Expiration
- 2035-12-12
AI Technical Summary
Existing offshore photovoltaic support connection nodes are prone to corrosion in extreme marine environments, leading to reduced mechanical properties, making modular and rapid installation difficult and disassembly cumbersome, thus affecting construction efficiency.
It adopts a combination structure of sleeve, positioning hole, pin, ball retainer, return spring and groove, combined with elastic sealing ring and anode block, to achieve quick connection with self-alignment function, and extends service life through anti-corrosion coating and electrochemical protection.
It enables rapid and reliable connection and disassembly of offshore photovoltaic support structures, reducing operational difficulty and construction time, improving work efficiency, and extending the service life of node structures.
Smart Images

Figure CN224987349U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of marine photovoltaic technology, specifically to a modular and detachable anti-corrosion connection node structure for marine photovoltaic support. Background Technology
[0002] As the global energy structure shifts towards cleaner and lower-carbon energy, marine photovoltaic power generation, as an emerging field of solar energy resource utilization, has shown great development potential. Compared with land-based photovoltaic power plants, marine photovoltaic power has significant advantages such as saving land resources, reducing freshwater consumption, improving power generation efficiency, and reducing dust pollution. However, the extreme conditions of the ocean, such as high salt spray, high humidity, strong winds and waves, and strong corrosion, can cause the coating of the connection nodes to fail, the substrate to be corroded, and then the bolts and nuts to be corroded, which gradually reduces the mechanical properties of the connection nodes and affects the overall rigidity of the structure.
[0003] To reduce the difficulty of offshore construction, shorten operation time, and reduce reliance on specialized vessels and high-cost offshore labor, offshore photovoltaic systems are gradually moving towards modular design. This also places demands on the modularity, standardization, and detachability of connection node structures. In existing technologies, the connection schemes for offshore photovoltaic supports are mainly divided into two categories: one is welding, but this can easily damage the anti-corrosion coating of the connection node structure and the base material, creating new corrosion risks. Moreover, the on-site welding quality is greatly affected by the marine environment, making it difficult to guarantee stability. The other is using flanges with high-strength bolt groups for connection. Although detachable, this method has problems such as large structural weight, high alignment accuracy requirements, difficulty in tightening at sea, and susceptibility to corrosion. These methods often fail to achieve both reliable corrosion protection and load-bearing performance while enabling rapid modular installation. Disassembly is also relatively cumbersome, thus extending the construction cycle of offshore photovoltaic supports and reducing work efficiency. Utility Model Content
[0004] To address the shortcomings of existing technologies, this utility model provides a modular and detachable corrosion-resistant connection node structure for marine photovoltaic support systems.
[0005] The above-mentioned technical objective of this utility model is achieved through the following technical solution: A modular, detachable, corrosion-resistant connection node structure for offshore photovoltaic support includes a pile foundation. A sleeve is provided on the outside of the pile foundation, and a conical disc is fixedly connected to the top of the pile foundation. A positioning and locking assembly is provided on the outside of the sleeve. The positioning and locking assembly includes: a plurality of positioning holes, all formed on the outer circular wall of the sleeve; a pin is provided inside every two positioning holes; two slots are formed on the outer circular wall of the pin; two positioning grooves are formed inside the conical disc; a return spring is fixedly connected inside each positioning groove; a ball is provided at the end of the return spring away from the positioning groove; and two balls are movably engaged with the two slots respectively. A locking assembly is provided on the outer circular wall of the sleeve.
[0006] To facilitate the fixing of the sleeve and prevent it from falling off, as a modular and detachable anti-corrosion connection node structure for marine photovoltaic support according to this utility model, the locking component preferably includes: a fixing plate, which is fixedly connected to the outer circular wall of the sleeve; a fixing hinge is movably sleeved on the top of the fixing plate; two clamps are fixedly connected to the outside of the fixing hinge; a positioning plate is fixedly connected to the outer circular wall of the clamps; two threaded rods are threaded between the two positioning plates, and both threaded rods pass through the two positioning plates; and two bolts are threaded to the outer circular wall of each of the two positioning plates.
[0007] To slow down the corrosion rate of the connection node structure and extend its service life, as a modular and detachable anti-corrosion connection node structure for marine photovoltaic supports of this utility model, preferably, a positioning block is fixedly connected to the outer circular wall of the sleeve, an anode block is movably sleeved inside the positioning hole, a plurality of positioning rods are movably sleeved on the side of the positioning block away from the anode block, and a sealing cap is movably sleeved on the end of the plurality of positioning rods away from the positioning block.
[0008] To prevent corrosion inside the sleeve, as a modular and detachable anti-corrosion connection node structure for marine photovoltaic supports of this utility model, preferably, the positioning hole is fixedly connected with an elastic sealing ring, and the inner circular wall surface of every two elastic sealing rings is movably sleeved with the pin.
[0009] To facilitate rapid connection between photovoltaic panels and pile foundations and improve connection speed, as a modular and detachable anti-corrosion connection node structure for offshore photovoltaic support according to this utility model, preferably, the sleeve has two conical grooves inside, and the conical groove near the pile foundation is movably fitted with the conical disc.
[0010] To improve the connection stability of the sleeve and facilitate its disassembly and assembly, as a modular and detachable anti-corrosion connection node structure for marine photovoltaic support according to this utility model, preferably, the end of the return spring away from the positioning groove is fixedly connected to a chuck, the chuck is slidably connected to the positioning groove, and the end of the chuck away from the return spring is fixedly connected to the ball.
[0011] In summary, the present invention has the following main advantages: 1. The sleeve, two positioning holes, pin, ball catch, chuck, return spring, and slot work together. The sleeve and positioning pin work together. When the sleeve is aligned with the positioning hole of the pile foundation, the pin is inserted to complete the initial connection. Then, the ball catch automatically locks into the corresponding slot under the elastic force of the return spring to complete the firm locking. This structure has a built-in centering function. When constructing at sea, only rough positioning is required to complete the insertion and locking. There is no need to rely on the complicated multi-bolt synchronous tightening process, which reduces the difficulty of operation and construction time and improves the work efficiency of the staff. 2. The elastic sealing ring, pin, and positioning hole work together to form a stable sealing barrier by pre-installing the elastic sealing ring in a compressed state before the pin is inserted into the positioning hole. After insertion, the sealing ring fills the gap with its own elasticity, preventing seawater from seeping into the connection. At the same time, the surface of the pin can be treated with an anti-corrosion coating to further enhance its corrosion resistance. The combination of these two protective measures reduces the risk of corrosion inside the sleeve and the connection interface, and extends the service life of the node structure in the high-salt and high-humidity marine environment. 3. The structure utilizes two clamps, a fixed hinge, a fixed plate, two threaded rods, two positioning plates, and bolts in a coordinated manner. By rotating the clamps, the fixed hinge can be embedded into the fixed plate, and then tightened by the threaded rods and bolts. This structure has a certain degree of self-adaptability, which can compensate for minor dimensional deviations that occur during installation, reducing the stringent requirements for construction precision. Operators only need to perform simple rotation and tightening actions to complete the fixing. The assembly and disassembly process is convenient and quick, improving construction efficiency and reducing reliance on large special tools. Attached Figure Description
[0012] Figure 1 This is a three-dimensional structural schematic diagram of the present invention; Figure 2 This is a schematic diagram of the positioning groove structure of this utility model; Figure 3 This is a schematic diagram of the conical groove structure of this utility model; Figure 4 This is a schematic diagram of the threaded rod structure of this utility model; Figure 5 This is a schematic diagram of the positioning block structure of this utility model; Figure 6This is a schematic diagram of the conical disk structure of this utility model.
[0013] Reference numerals in the attached drawings: 1. Pile foundation; 2. Sleeve; 3. Conical groove; 4. Elastic sealing ring; 5. Pin; 6. Positioning groove; 7. Return spring; 8. Ball catch; 9. Slot; 10. Chuck; 11. Conical disc; 12. Clamp; 13. Positioning plate; 14. Threaded rod; 15. Bolt; 16. Fixed hinge; 17. Fixed plate; 18. Positioning hole; 19. Positioning block; 20. Anode block; 21. Positioning rod; 22. Sealing cover. Detailed Implementation
[0014] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the protection scope of the present utility model.
[0015] Example: Reference Figure 1 , Figure 2 , Figure 3 and Figure 6 A modular, detachable, corrosion-resistant connection node structure for offshore photovoltaic support includes a pile foundation 1, a sleeve 2 externally mounted on the pile foundation 1, a conical disc 11 fixedly connected to the top of the pile foundation 1, and a positioning and locking assembly externally mounted on the sleeve 2. The positioning and locking assembly includes several positioning holes 18, all located on the outer circular wall of the sleeve 2. A pin 5 is installed inside every two positioning holes 18, and two slots 9 are formed on the outer circular wall of the pin 5. Two positioning grooves 6 are formed inside the conical disc 11, and a return spring is fixedly connected inside the positioning grooves 6. Spring 7, the end of the return spring 7 away from the positioning groove 6 is provided with a retaining ball 8, the two retaining balls 8 are respectively movably engaged with two retaining grooves 9, the interior of the positioning hole 18 is fixedly connected with an elastic sealing ring 4, the inner circular wall surface of each pair of elastic sealing rings 4 is movably engaged with the pin 5, the interior of the sleeve 2 is provided with two conical grooves 3, the conical groove 3 near the pile foundation 1 is movably engaged with the conical disk 11, the end of the return spring 7 away from the positioning groove 6 is fixedly connected with a chuck 10, the chuck 10 is slidably connected with the positioning groove 6, and the end of the chuck 10 away from the return spring 7 is fixedly connected with the retaining ball 8; With the sleeve 2 in place, when the workers need to connect the sleeve 2 to the pile 1, they first move the sleeve 2 closer to the pile 1. When the two positioning holes 18 are aligned, the pin 5 is passed through the two positioning holes 18. Then the ball 8 and the chuck 10 move away from the pin 5, and the return spring 7 moves away from the pin 5. The return spring 7 is compressed. During the process of the ball 8 passing through the groove 9, the force generated by the deformation of the return spring 7 causes the ball 8 and the chuck 10 to move closer to the pin 5, and then the ball 8 and the groove 9 are locked. The matching structure of the sleeve 2 and the conical plate 11 has a built-in centering function. At sea, only rough positioning is needed to insert the pin 5 and lock it. There is no need to operate the complicated multi-bolt 15 to tighten simultaneously, which reduces the difficulty of operation and construction time and improves the work efficiency of the workers. With the elastic sealing ring 4, when the pin 5 needs to pass through the positioning hole 18, the pre-compressed elastic sealing ring 4 is set in the gap of the positioning hole 18, and a radial seal is formed after insertion; the pin 5 itself can also be treated with anti-corrosion coating to improve the anti-corrosion effect, avoid corrosion inside the sleeve 2, reduce the risk of corrosion inside the sleeve 2 and the connection interface, and extend the service life of the node structure in the marine high-salt and high-humidity environment.
[0016] refer to Figure 1 , Figure 2 , Figure 3 and Figure 4 The outer circular wall of the sleeve 2 is provided with a locking assembly, which includes a fixing plate 17. The fixing plate 17 is fixedly connected to the outer circular wall of the sleeve 2. A fixing hinge 16 is movably sleeved on the top of the fixing plate 17. Two clamps 12 are fixedly connected to the outside of the fixing hinge 16. A positioning plate 13 is fixedly connected to the outer circular wall of the clamps 12. Two threaded rods 14 are threaded between the two positioning plates 13, and both threaded rods 14 pass through the two positioning plates 13. Two bolts 15 are threadedly connected to the outer circular wall of each of the two positioning plates 13. With the clamps 12 in place, when the sleeve 2 needs to be fixed, first rotate the two clamps 12 counterclockwise to move them away from each other, then insert the fixing hinge 16 into the fixing plate 17, and then rotate the two clamps 12 clockwise to move them closer together. After the two clamps 12 are in contact, rotate the two threaded rods 14 clockwise so that they pass through the two positioning plates 13. Then, the operator rotates the bolt 15 to make it fit tightly against the positioning plate 13, which makes it easy for the operator to fix the sleeve 2. At the same time, the two clamps 12 have a certain degree of self-adaptability, which can compensate for small dimensional deviations and reduce the stringent requirements for construction accuracy. The operator only needs to perform simple rotation and tightening actions to complete the fixing. The assembly and disassembly process is convenient and quick, which improves construction efficiency and reduces the dependence on large special tools.
[0017] refer to Figure 1 , Figure 2 , Figure 3 and Figure 5 A positioning block 19 is fixedly connected to the outer circular wall of the sleeve 2. An anode block 20 is movably sleeved inside the positioning hole 18. Several positioning rods 21 are movably sleeved on the side of the positioning block 19 away from the anode block 20. A sealing cover 22 is movably sleeved on the end of the several positioning rods 21 away from the positioning block 19. With the anode block 20 in place, when the connection node structure is corroded, the anode block 20, as part of the sacrificial anode protection structure, preferentially corrodes itself through electrochemical principles, protecting the steel materials such as the node body and connectors. When the anode block 20 needs maintenance and replacement, the staff only needs to open the sealing cover 22, then pull out the old anode block 20 and replace it with a new one. There is no need to cut or weld the sealing cover 22, avoiding damage to the original anti-corrosion coating structure, reducing the dependence on professional technicians and complex equipment, simplifying the later maintenance process, and facilitating the economical and safe operation of the structure throughout its entire life cycle.
[0018] Working principle: Please refer to Figures 1-6 As shown, when the sleeve 2 needs to be connected to the pile 1, the worker first moves the sleeve 2 closer to the pile 1. When the two positioning holes 18 are aligned, the pin 5 is passed through the two positioning holes 18. Then the ball 8 and the chuck 10 move away from the pin 5, and the return spring 7 moves away from the pin 5. The return spring 7 is compressed. During the process of the ball 8 passing through the groove 9, the force generated by the deformation of the return spring 7 causes the ball 8 and the chuck 10 to move closer to the pin 5. Then the ball 8 and the groove 9 are locked. The matching structure of the sleeve 2 and the conical plate 11 has a built-in centering function. At sea, only rough positioning is needed to insert the pin 5 and lock it, without the need for complicated operation of multiple bolts 15 to be tightened simultaneously.
[0019] With the elastic sealing ring 4, when the pin 5 needs to pass through the positioning hole 18, the pre-compressed elastic sealing ring 4 is set in the gap of the positioning hole 18, and a radial seal is formed after insertion; the pin 5 itself can also be treated with anti-corrosion coating to improve the anti-corrosion effect and prevent the inside of the sleeve 2 from being corroded.
[0020] With the clamps 12 in place, when it is necessary to fix the sleeve 2, first rotate the two clamps 12 counterclockwise to move them away from each other, then insert the fixing hinge 16 into the fixing plate 17, and then rotate the two clamps 12 clockwise to move them closer to each other. After the two clamps 12 are in contact, rotate the two threaded rods 14 clockwise so that they pass through the two positioning plates 13. Then, the operator rotates the bolt 15 so that the bolt 15 is in close contact with the positioning plate 13, which makes it easy for the operator to fix the sleeve 2. At the same time, the two clamps 12 have a certain degree of self-adaptability, which can compensate for small dimensional deviations and improve the operator's disassembly and assembly efficiency.
[0021] With the anode block 20 in place, when the connection node structure is corroded, the anode block 20, as part of the sacrificial anode protection structure, preferentially corrodes itself through electrochemical principles, protecting the steel materials such as the node body and connectors. When the anode block 20 needs maintenance and replacement, the staff only needs to open the sealing cover 22, then pull out the old anode block 20 and replace it with a new one. There is no need to cut or weld the sealing cover 22, avoiding damage to the original anti-corrosion coating structure, reducing the dependence on professional technicians and complex equipment, simplifying the later maintenance process, and facilitating the economical and safe operation of the structure throughout its entire life cycle.
[0022] Although embodiments of the present invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of the present invention, the scope of which is defined by the appended claims and their equivalents.
Claims
1. A modular detachable corrosion resistant connection node structure for offshore photovoltaic support, characterized in that, include: A pile foundation (1) is provided with a sleeve (2) on the outside of the pile foundation (1) and a conical disk (11) is fixedly connected to the top of the pile foundation (1). The sleeve (2) is provided with a positioning and locking assembly on its exterior. The positioning and locking assembly includes: a plurality of positioning holes (18), all of which are opened on the outer circular wall of the sleeve (2). A pin (5) is provided inside each pair of positioning holes (18). Two slots (9) are opened on the outer circular wall of the pin (5). Two positioning grooves (6) are opened inside the conical disc (11). A return spring (7) is fixedly connected inside the positioning groove (6). A ball (8) is provided at the end of the return spring (7) away from the positioning groove (6). The two balls (8) are respectively engaged with the two slots (9). The outer circular wall of the sleeve (2) is provided with a locking component.
2. The modular and detachable anti-corrosion connection node structure for offshore photovoltaic support according to claim 1, characterized in that, The locking component includes: A fixing plate (17) is fixedly connected to the outer circular wall of the sleeve (2). A fixing hinge (16) is movably sleeved on the top of the fixing plate (17). Two clamps (12) are fixedly connected to the outside of the fixing hinge (16). A positioning plate (13) is fixedly connected to the outer circular wall of the clamps (12). Two threaded rods (14) are threaded between the two positioning plates (13), and both threaded rods (14) pass through the two positioning plates (13). Two bolts (15) are threaded to the outer circular wall of the two positioning plates (13).
3. The modular and detachable anti-corrosion connection node structure for offshore photovoltaic support according to claim 1, characterized in that, A positioning block (19) is fixedly connected to the outer circular wall of the sleeve (2). An anode block (20) is movably sleeved inside the positioning hole (18). Several positioning rods (21) are movably sleeved on the side of the positioning block (19) away from the anode block (20). A sealing cap (22) is movably sleeved on the end of the several positioning rods (21) away from the positioning block (19).
4. The modular and detachable anti-corrosion connection node structure for offshore photovoltaic support according to claim 1, characterized in that: The positioning hole (18) is fixedly connected to an elastic sealing ring (4), and the inner circular wall of each pair of elastic sealing rings (4) is movably sleeved with the pin (5).
5. The modular and detachable anti-corrosion connection node structure for offshore photovoltaic support according to claim 1, characterized in that: The sleeve (2) has two conical grooves (3) inside, and the conical groove (3) near the pile foundation (1) is movably connected to the conical disk (11).
6. The modular and detachable anti-corrosion connection node structure for offshore photovoltaic support according to claim 1, characterized in that: The end of the reset spring (7) away from the positioning groove (6) is fixedly connected to a chuck (10), the chuck (10) is slidably connected to the positioning groove (6), and the end of the chuck (10) away from the reset spring (7) is fixedly connected to the ball (8).