Method and device for controlling the power dynamics of the battery of an electrically powered vehicle
A method for controlling electric vehicle battery power dynamics through first and second current output values and charge value integration addresses complexity and cost issues, enabling intuitive performance management and gradual power adjustments.
Patent Information
- Application Number
- DE102012007989
- Authority / Receiving Office
- DE · DE
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2012-04-20
- Publication Date
- 2024-11-21
- Estimated Expiration
- 2032-04-20
AI Technical Summary
Existing methods for controlling the power dynamics of electric vehicle batteries are complex and computationally demanding, failing to provide a simple and cost-effective way to intuitively understand and manage the battery's performance potential, especially during short-term maneuvers.
A method involving the determination of first and second current output values, integration of current differences over time intervals, and visualization of charge values to intuitively represent battery performance dynamics, allowing for gradual power adjustments based on historical usage and battery state.
Enables a simple, cost-effective control of battery power dynamics, providing drivers with a reproducible and understandable performance indication, avoiding abrupt power reductions and optimizing power usage based on historical load history.
Smart Images

Figure 00000000_0000_ABST
Abstract
Description
[0001] The present invention relates to a method and a device for controlling the power dynamics of the battery of an electrically powered vehicle.
[0002] To provide powerful alternatives to vehicles with combustion engines, high-voltage batteries have been developed in battery technology. A high-voltage battery module consists of individual cells connected in series at a voltage of one to two volts. The individual voltages are added together to produce the high-voltage required for propulsion.
[0003] The peak power of a purely electrically powered vehicle with such a high-voltage battery is only available for a limited period of time due to the physical and chemical processes in the high-voltage battery. After that, the power available from the battery must be reduced to a lower continuous power, which is then available for a considerably longer period of time. In the high-voltage batteries suitable for automotive use today, the peak power is typically available from the battery in the sub-minute range. The continuous power, on the other hand, is orders of magnitude higher, i.e. typically on the order of an hour or at least a good portion of it. If the peak power has been delivered by the battery for the maximum possible period of time, a recovery phase is required, after which the peak power is available again for a short time.
[0004] Thus, the rider only has a certain amount of energy available to exceed the continuous power output. This variable amount of energy, also known as peak power reserve, depends primarily on the rider's exercise history with power outputs above the continuous power output and on the recovery phases.
[0005] The continuous power, the peak power and thus also the maximum possible peak power reserve depend on the operating point of the battery. The operating point is determined in particular by the temperature, the state of charge (SoC) and the state of age (SoH). For this purpose, performance curves are provided which represent the continuous power and possible peak power at a defined operating point, regardless of the load history. The battery parameters at a defined operating point are semi-permanent, i.e. they change only slowly compared to the rapidly changing peak power reserve. The battery parameters at a defined operating point can therefore be regarded as constant for the current performance potential of the battery. The question of whether and when a reduction in performance compared to peak power can be expected is then clarified by the specific load history.Furthermore, other components involved, such as power electronic modules or an engine control unit, can also lead to a reduction in performance.
[0006] The power dynamics, i.e., the power potential available at the moment and in the future, is therefore not constant, unlike with combustion engines, and also depends on the past load history. Therefore, electrically powered vehicles require transparent control of the power dynamics so that the driver can intuitively understand the performance of the vehicle's drive system, especially for short-term maneuvers, such as overtaking or merging onto a highway.
[0007] In particular, it must be taken into account that the power delivered by the battery is relevant for driving performance, but the battery-internal processes are dominated by the battery current. DE 10 2009 049 589 A1 describes a method in which the power forecast is solved using a differential equation by means of an equivalent circuit. The method initially forecasts the maximum permissible operating voltage and the maximum permissible operating current. In order to take the history into account, the bias value on the battery capacitor at the time of the forecast calculation is taken into account, with the measured current and voltage values then being used to solve the differential equation. The power forecast is used in particular for predictive power control. If the power reserve is not sufficient for the forecast period, the power is, for example,limited before an acceleration process or continuously reduced during an acceleration process in order to avoid a sudden drop in performance that is clearly noticeable to the driver.
[0008] The disadvantage of this method is that the solution of a differential equation is comparatively complex and places great demands on the executing computing unit in real-time operation.
[0009] US 2009 / 0091296 A1 describes a method for controlling the charging process of a rechargeable battery comprising at least one electrochemical cell with a predetermined maximum continuous charging current permissible for given temperature and state of charge conditions. The method includes measuring an instantaneous charging current, defining an overcharge capacity, and determining an instantaneous maximum permissible charging current as a function of the overcharge capacity.
[0010] It is the object of the present invention to provide a control concept for the power dynamics of the battery of an electrically powered vehicle, which is simple and cost-effective to implement and which provides the driver with a reproducible and intuitively comprehensible power potential of the vehicle battery in a predictable period of time.
[0011] This object is achieved by a method having the features of claim 1 and by an associated device having the features of claim 9. Advantageous embodiments and further developments emerge from the dependent claims.
[0012] In the method for controlling the power dynamics of the battery of an electrically driven vehicle, a first and second current output value associated with the battery are determined, wherein the first current output value is the continuous current that can be delivered at the current operating point and the second current output value is the peak current that can be delivered at the current operating point, of which the second current output value is higher than the first current output value, and the current currently delivered by the battery is measured over a time interval. A charge value is calculated from the temporal development of the current difference between the current currently delivered by the battery and the first current output value associated with the battery over the time interval.If the calculated charge value is less than or equal to a specified charge limit, above which controlled current limitation is initiated, the maximum current that can be delivered by the battery is set equal to the second current output value associated with the battery. If the calculated charge value is greater than the specified charge limit, the maximum current that can be delivered by the battery, depending on the calculated charge value, is set less than the second current output value associated with the battery. Taking into account the temporal development of a current variable has the advantage of better understanding the battery's internal processes than is the case with a power analysis, although the battery power can still always be calculated from the product of voltage and current.
[0013] Setting the maximum current output is a controlling limitation that can be initiated before the battery's internal processes would cause a reduction in current output. This has the advantage that a current and thus power limitation does not occur abruptly and without consideration of previous history.
[0014] In the method according to the invention, the first current output value is the continuous current that can be delivered at the current operating point, and the second current output value is the peak current that can be delivered at the current operating point. Via the relationship "power equals voltage times current," these values physically correspond to the power levels between which the available power fluctuates at the current operating point. These two power levels therefore determine the operational range for driving the vehicle. Alternatively, other current output values can also be selected, e.g., a current output value slightly below the continuous current that can be delivered at the current operating point, so that a gradual reduction in the continuous current that can be delivered over time is taken into account.
[0015] The charge value is calculated, in particular, as a first integral of the current difference between the current currently delivered by the battery and the first current output value associated with the battery over a first time interval. The integration over time provides an exact and reproducible charge value by which the current battery charge has been reduced compared to the fully charged battery at the respective operating point. For a given battery voltage, this charge value can be converted into an energy amount and related to the peak power reserve mentioned above.
[0016] In particular, it is intended that the first time interval over which the current difference is integrated is reinitialized at the time when the first integral of the current difference over the previous time interval has become negative and the current currently delivered by the battery exceeds the first current output value. This ensures that upon complete recovery of the battery, i.e., when the battery is fully charged for the respective operating point, the charge value is only recalculated when an event occurs that actually results in a higher current output than the first current output value.
[0017] In particular, nonexistent charge buffers are not mathematically created, as low current outputs cause the integral to become negative purely mathematically, and thus the charge value would only become zero after a certain period of loading with currents higher than the first current output value, and then positive again. On the other hand, this ensures that, in the case of permanent alternating loads below and above the first current output value, any previous uses of the peak power reserve are also taken into account if the battery has never fully recovered.
[0018] In an advantageous embodiment of the method according to the invention, if the calculated charge value exceeds the specified charge limit, a second time interval is initialized and a second integral of the current difference between the current currently delivered by the battery and the first current output value is calculated over the second time interval. The maximum current that can be delivered by the battery is then reduced linearly from the second current output value to the value of the second integral of the current difference. For this purpose, it is expedient that the maximum current that can be delivered by the battery is reduced to a maximum of the first current output value, since this corresponds to the continuous current that can be delivered by the vehicle battery. The linear reduction is carried out computationally by scaling with a time factor in order to arrive at a current value dimensionally.The start of such a reduction in the maximum current that can be delivered by the battery, also known as "de-rating," can be adapted to the specific application. In particular, the maximum current that can be delivered can occur before a point in time at which, from a battery-related perspective, a current limitation would occur. The maximum current that can be delivered is limited, for example, because the wiring harnesses that transmit the current from the battery to the electric drive or other components involved, such as power electronics modules, are only designed for the second current output value for a shorter period of time.
[0019] In one embodiment of the method according to the invention, the power map of the battery is calculated and / or simulated over a range of operating points, the current operating point is determined, and a corresponding first and second power output value is determined, and the internal resistance of the battery at the operating point and the open-circuit voltage of the battery are determined. The first and second current output values are then calculated as solutions to a quadratic equation from the first and second power output values, the internal resistance, and the open-circuit voltage of the battery. The power maps can be calculated more precisely in advance than current maps. The derivation of the resulting current maps is obtained in particular from the simplified equivalent circuit diagram of a battery with an internal resistance R0 dependent on the operating point and the resulting open-circuit voltage U0. The current output value I xat an operating point results from the power value P x (x stands here in particular for the indices D and S) according to the equations U=U0−R0*Ix Px=U*Ix Px=U0*Ix−R0*Ix2 where equation (III) is the quadratic equation to be solved.
[0020] The first and second current output values can also be determined without solving this quadratic equation. For this purpose, a current map of the battery was calculated and / or simulated over a range of operating points. The current operating point is determined and an associated first and second current output value is determined, and the operating voltage of the battery is measured. The calculation of a current map is not reproducible, so that discrepancies usually arise between theoretically calculated and actual current output values during operation. The theoretical power output resulting from the first and second current output values and the operating voltage is therefore calculated and compared with the actual power output. The first and second current output values associated with the battery and / or the current map of the battery can then be corrected depending on this comparison.This variant requires fewer computing resources than calculating the solution to a quadratic equation. It can therefore be performed quickly without placing significant demands on computing power.
[0021] Both variants can also be used in parallel. For example, the first and second current output values are each determined using a different one of the two variants. It is also possible to perform the calculation by solving the quadratic equation only sporadically, e.g., once per minute, and use the other variant for interim calculations.
[0022] The first and second current output values are "semi-permanent," meaning they change gradually during operation. They are preferably continuously updated, meaning they are continuously monitored and repeatedly re-determined at the valid operating point. Alternatively, they are only re-determined sporadically, e.g., event-triggered.
[0023] In one embodiment of the method according to the invention, the power dynamics of the battery are visualized by a one-dimensionally representable quantity, wherein a fixed, predetermined proportion of the one-dimensionally representable quantity is assigned to the calculated charge value. This enables the driver of the vehicle to quickly and intuitively grasp the impending power dynamics. The calculated charge value can represent part of a visualized value range, e.g. 100% when the charge value is zero, 60% when the charge value is equal to the charge limit, i.e. at the start of de-rating, and 40% when the deliverable current is reduced to the first current output value. The range 0% to 40% is reserved for the power dynamics range in which the battery discharge process has progressed so far that the continuous power level valid over a wide range of operating parameters can no longer be maintained.
[0024] Such a visualization is particularly clear because it provides the driver with various performance dynamics information via a single, one-dimensional value. This one-dimensional value can then be easily represented, for example, as a number or as a pointer or bar chart.
[0025] The device according to the invention for controlling the power dynamics of the battery of an electrically driven vehicle comprises a battery monitoring device for detecting at least two different current output values associated with the battery, a measuring device for measuring the current delivered by the battery and a computing unit which is connected to the measuring device and by means of which a charge value can be calculated from the temporal development of the current difference between the current currently delivered by the battery and the first current output value associated with the battery.The device further comprises a control unit which is connected to the battery monitoring device and the computing unit, by means of which the maximum current that can be delivered by the battery can be specified depending on the temporal development of the current delivered by the battery. If the calculated charge value is less than or equal to a set charge limit, the maximum current that can be delivered by the battery can be set by means of the control unit to be equal to the second current output value associated with the battery. If the calculated charge value is greater than the set charge limit, the maximum current that can be delivered by the battery can be set by means of the control unit to be less than the second current output value associated with the battery depending on the calculated charge value. The device according to the invention is particularly suitable for carrying out the method according to the invention.It therefore also has the advantages of the method according to the invention.
[0026] Furthermore, according to the invention, a vehicle with at least a partially electric drive is equipped with such a device for controlling the power dynamics of the battery. This can be a vehicle with a purely electric drive or with an additional electric drive, such as so-called hybrid drives.
[0027] The invention will now be explained in more detail using exemplary embodiments with reference to the figures. Fig. 1 shows an electrically driven vehicle equipped with a device for controlling the power dynamics of the vehicle battery according to an embodiment of the invention, Fig. 2 shows a device for controlling the power dynamics of the battery of an electrically driven vehicle according to an embodiment of the invention, the Fig. 3 and Fig. 4 show exemplary performance curves of the peak power and the continuous power of a high-voltage battery, the power dynamics of which can be controlled according to the invention, Fig. 5 shows an example of a temporal development of the delivered and the maximum deliverable current in connection with the method according to the invention and Fig. 6 shows a possible visualization of the power dynamics of the battery of an electrically powered vehicle according to an embodiment of the method according to the invention.
[0028] In the Fig. Figure 1 shows an electrically powered vehicle 1 equipped with a device for controlling the power dynamics of the battery 2 of the vehicle 1 according to an exemplary embodiment of the invention. The electrically powered vehicle 1 is equipped, as is known per se, with an electric motor 5 connected to the battery 2 for driving the vehicle 1 and with a motor controller 6 connected to the electric motor 5.
[0029] An embodiment of the device according to the invention is shown schematically in the Fig. 1 and Fig. 2. It comprises a sensor device 3 for sensing the operating parameters of the battery 2 and a current history measuring device 4 for recording the current output history of the battery 2, both of which are connected to the battery 2. The device according to the invention further comprises a control unit 7, which is connected to the sensor device 3 and the current history measuring device 4 and by means of which the maximum current I that can be delivered by the battery Max can be specified.
[0030] The control unit 7 is connected to a display device, e.g., the multifunction display 10 of the vehicle 1, in order to visualize the power dynamics. Furthermore, the control unit 7 is coupled to the engine control unit 6, for example, integrated into it.
[0031] The sensor device 3 detects, in particular, the temperature T, the state of charge SOC, and the state of aging SOH of the battery 2. An operating point is determined from these operating parameters of the battery 2. Characteristic curves for possible operating points are stored in the sensor device 3, by means of which the continuous current I for a given operating point D , from which a continuous power PD can be calculated, and the peak current I S , from which a peak power PS can be calculated.
[0032] In particular, a maximum peak power reserve (MSLR) is calculated from the difference between peak power PS and continuous power PD at the respective operating point by multiplying this power difference (PS - PD) by a time factor. This time factor must be adapted to the respective vehicle configuration. The maximum peak power reserve (MSLR) is dimensionally an amount of energy that can be used for temporary additional power in addition to the continuous power PD.
[0033] In the Fig. 3 and Fig. Figure 4 shows, as an example, the performance curve 20 of the peak power PS and the performance curve 21 of the continuous power PD of a high-voltage battery 2 as a function of the battery parameters temperature T and battery charge SOC. These were obtained through theoretical calculations or simulations. It can be seen that the peak power PS is typically about twice as high as the continuous power PD and that the peak power PS and continuous power PD are virtually constant over a wide range of battery parameters. Significant performance losses only occur at low battery charge SOC (~30%) and / or at low temperatures (T < 0°C).
[0034] From the performance curves 20, 21, the peak current I S and the continuous current I Dcalculable. For this purpose, the current operating point is determined and the corresponding continuous power PD and peak power PS are calculated. The internal resistance R0 of battery 2 at the operating point and the open-circuit voltage U0 of battery 2 are then determined. From the quadratic equation described in the general section (x again stands for the indices D and S, respectively), Px=U0*Ix−R0*Ix2 are continuous current I D and peak current I S calculated as a solution to this equation.
[0035] Alternatively, current characteristic curves or current maps can be calculated in advance over a wide range of operating points (not shown). However, this poses the problem that the battery's history, i.e., past usage and aging, is more difficult to take into account, leading to partially irreproducible results. In such a case, the predicted power value must be corrected by a comparative measurement. This can be achieved by determining the current operating point and the associated continuous current I D and peak current I S is determined and the operating voltage U of battery 2 is measured. The theoretical power output resulting from these current and voltage values is calculated and compared with the actual power output. This comparison yields a correction term that can be used to correct the current characteristic of battery 2.
[0036] The actual deliverable current from battery 2 depends on the current delivery history. The timescales with which the actual delivered current changes during normal operation of vehicle 1, i.e., in the range of seconds or fractions of minutes, are one to two orders of magnitude smaller than the timescales with which the deliverable current of battery 2 changes due to a change in the operating point (typically in the range of a few minutes to hours). Therefore, the continuous current I determined at a given operating point D and peak current I S , and thus also power values PD, PS, can be regarded as almost constant when compared with the power output history.
[0037] The current history measuring device 4 records the current I currently delivered by the battery 2 Istand its temporal development, i.e. the current output history of battery 2, over a time interval. The recording of the current output history is carried out with reference to the Fig. 5 and explained in more detail in connection with the method according to the invention.
[0038] The data acquired by the sensor device 3 and the current history measuring device 4 are transmitted via the data bus 9 in the vehicle 1 to the control unit 7 and to a computing unit 8 integrated therein. By means of the computing unit 8, the temporal development of the current difference between the current I actually delivered by the battery 2 Ist and the continuous current I D a charge value Q is calculated and from this the maximum current I that can be delivered by battery 2 Maxspecified, as will be explained in more detail in connection with the method according to the invention. Depending on how long and to what extent in a previous time interval the actually delivered current I Ist higher than the continuous current I D The higher the charge value Q is calculated, until it reaches a limit, at which point a controlled current limitation, the so-called de-rating, is initiated. In order to achieve a gradual reduction of the continuous current I over longer periods, D and peak current I S To take this into account, these values are continuously updated. A resulting higher current difference also causes the charge value Q to be higher.
[0039] The charge value Q can be converted into an energy equivalent at any time by multiplying it by the battery voltage U. It can be calculated from the maximum available energy amount, which is available in addition to the continuous power PD and can be released for a short time. The charge value Q corresponds to the shortfall between the peak power reserve SLR and the maximum peak power reserve MSLR.
[0040] The method according to the invention will now be described using exemplary embodiments and with reference to the Fig. 5 and Fig. 6 is explained in more detail. The previously described device according to the invention can be used to carry out the method according to the invention, to which reference is also expressly made below.
[0041] In the Fig. 5 shows an example of a current output history 22. The initial situation is that the electric motor 5 of the vehicle 1 only delivers a limited power on average below the continuous current I D from battery 2. Battery 2 has fully regenerated according to the operating point, so that the peak current I S is available for a maximum period of time. For example, vehicle 1 has just been restarted after a break in operation or was previously driven with only a low load on battery 2.
[0042] The continuous current I D and the peak current I S of the battery 2. Furthermore, the current history measuring device 4 determines the current I currently delivered by the battery 2. Istcontinuously measured and buffered with a corresponding time stamp, e.g., as an average value over a short time interval in the seconds or subsecond range. This data is transmitted to the control unit 7 and to the computing unit 8. The control unit 7 outputs the value of the current I max that may be emitted by the battery 2 and transmits this to the engine control unit 6.
[0043] At time t0, the vehicle 1 is accelerated so that the electric motor 5 has a higher current I Ist than the continuous current I D from battery 2. The time interval for recording the current output history 22 of battery 2 is then reinitialized. The temporal progression of the current output history 22 is recorded by the current history measuring device 4, and the associated data is transmitted to the computing unit 8. In the computing unit 8, the current difference between the delivered current I Ist and the continuous current ID integrated in time and thus the charge value Q is calculated. In the further course, different current outputs I Ist of battery 2, which is temporarily below the continuous current I D At a time t1, the current output was reduced such that the integral of the current difference between the actually delivered current I Ist and the continuous current I D becomes mathematically negative over the time interval from t0 to t1. This corresponds to a complete regeneration of battery 2 at the current operating point.
[0044] At time t2, the current I delivered by battery 2 is Ist again greater than the continuous current I D , whereupon the time interval for calculating the charge quantity Q is reinitialized and the calculation of Q starts again from zero. Different current outputs I Istof battery 2, which is temporarily below, but on average above, the continuous current I D so that battery 2 is no longer fully regenerated.
[0045] For example, at time t3 the charge value Q reaches 40%, at time t4 80%, at time t5 93% and at time t6 100% of a predetermined maximum charge value Q Max . The maximum charge value Q Max represents a charge reserve (or when multiplied by the battery voltage U, an energy reserve, ie the maximum peak power reserve MSLR). The maximum charge value Q Max is adapted to battery 2, like the maximum peak power reserve MSLR.
[0046] Conveniently, the maximum charge value Q Max lower than the maximum charge value that would be possible for battery-technical reasons. This is primarily due to the fact that the wiring harnesses that carry the current I Isttransferred from the battery 2 to the electric motor 5, or other components involved, such as power electronics modules, are only designed for such a higher electric current for a shorter period of time. The current I delivered by the battery 2 Ist must then be reduced to prevent damage to the wiring harness or the components involved due to overload.
[0047] In today's vehicle configurations, a peak current I S A sudden drop in power from the peak current I S corresponding peak power PS to the continuous current I D The corresponding continuous power PD is undesirable. On the one hand, such a drop in power is perceived negatively by the driver. On the other hand, a maneuver initiated at peak power PS could only be completed with significantly reduced power.
[0048] According to the invention, an electronic control is provided which determines the maximum current I max predictive of a value of the peak current I S continuously or gradually to the level of the continuous current I D down-regulated.
[0049] Until time t4, the specified value of the current I max , which may be delivered by the battery as specified by the control unit 7, is equal to the peak current I S set. At time t4, the charge value Q now reaches the charge limit value Q Gr = 80% of the maximum charge value Q max , so that the successive power limitation, the so-called de-rating, begins. For this purpose, from time t4 onwards, a second integral of the current difference between the current I currently delivered by battery 2 Ist and the continuous current I D calculated. The current I Maxis then first calculated by the computing unit 8 so that the value of the peak current I S is reduced linearly by the value of the second integral of the current difference.
[0050] The maximum “allowed” current I that can be delivered by battery 2 Max is reduced until it reaches the value of the continuous current I D This occurs at time t6, when the charge value Q reaches the maximum charge value Q Max has reached.
[0051] In the case shown, the maximum allowed current I Max in the time interval between times t4 and t6. As a result, the value of the second integral does not increase linearly with time, but rather results in an exponential decay of the maximum permissible current I until time t6. Max . The de-rating is therefore relatively "soft," without a sudden drop in performance.
[0052] The performance dynamics are expressed and visualized using a performance indicator as a one-dimensional value. The performance indicator can take a percentage value between 0% and 100% and is calculated as follows: For a first portion up to the ratio PD / PS, the performance indicator is calculated according to the available power as a percentage of the peak power PS, e.g., up to 50% if the peak power PS is twice the continuous power PD. If the available power is higher than the continuous power PD, the performance indicator is composed of the sum of the first portion, i.e., PD / PS, and a second portion. This second portion is calculated from the difference between the maximum charge value Q Max and the charge value Q divided by the maximum charge value Q Maxand multiplied by the remaining percentage value 100% * (1 - PD / PS), in this case also 50%. For the regenerated battery, the charge value Q is zero, and thus the second portion is maximum. The second portion decreases with increasing charge value Q until the maximum charge value Q Max is reached, at which the maximum current I specified by the control unit 7 Max on the continuous current I D is limited and thus only the continuous power PD is available.
[0053] In the Fig. 6, the performance indicator is visualized by a performance dynamic bar 13. With reference to the Fig.At the times t2 - t6 discussed in section 5, the power dynamic bar 13 is dynamically changed according to the associated available power, currents and the charge value Q. The visualization is carried out by filling the bar 13 or by another suitable marking or highlighting, e.g. by using two colors, as is known from bar displays. The first part of the performance indicator is visualized in a first display area 16, the second part of the performance indicator in a display area 15. The second display area 15 is proportionally, ie in area 15A, according to the ratio (Q Max - Q) / Q Max displayed, with the remaining area 15B not being highlighted accordingly.
[0054] The first display area 16 is fully displayed as long as the continuous current I Dand the associated continuous power PD is still available. Only when the continuous power PD is undershot, e.g., due to increasing discharge of battery 2 during operation, is this area 16 also only displayed proportionally to the extent that the actual power has decreased in relation to the continuous power PD. List of reference symbols 1 electrically powered vehicle 2 high-voltage batteries 3 Sensor device for operating parameters 4 Power history meter 5 Electric motor 6 Engine control 7 Control unit 8 computing unit 9 Data bus in the vehicle 10 multifunction display 11 round instruments 12 freely programmable display field 13 power dynamic bars 14 Display area for third dynamic range 15, 15A, 15B Display area for second dynamic range 16 Display area for first dynamic range 17 Warning symbol for first dynamic range 20 Peak power curve of a high-voltage battery 21 Continuous power of a high-voltage battery 22 Electricity supply history HP peak power PD continuous power I D Continuous current I S Peak current I max maximum output current I N Nominal current
Claims
[1] Method for controlling the power dynamics of the battery (2) of an electrically driven vehicle (1), in which - a first and second current output value (I D , I S ), whereby the first current output value is the continuous current (I D ) and the second current output value is the peak current that can be delivered at the current operating point (I S ), of which the second current output value (I S ) higher than the first current output value (I D ) is, - the current (I Ist ) is measured over a time interval and - from the temporal development of the current difference (I Ist - I D ) between the current (I Ist ) and the first current output value (I D) a charge value (Q) is calculated over the time interval, - where, if the calculated charge value (Q) is less than or equal to a specified charge limit value (Q Gr ), from which a controlled current limitation is initiated, is the maximum current (I Max ) equal to the second current output value (I S ) is set, and - where, if the calculated charge value (Q) is greater than the set charge limit value (Q Gr ), the maximum current that can be delivered by the battery (I Max ) depending on the calculated charge value (Q) is less than the second current output value (I S ) is set. [2] Method according to claim 1, characterized by that the charge value (Q) is a first integral of the current difference (I Ist - I D ) between the current (IIst ) and the first current output value (I D ) is calculated over a first time interval (t0 - t4). [3] Method claim 2, characterized by that the first time interval (t0 - t6) over which the current difference (I Ist - I D ) is integrated, is reinitialized at the time (t2) when - the first integral of the current difference (I Ist - I D ) has become negative over the previous time interval and - the current (I Ist ) the first current output value (I D ) exceeds. [4] Method according to one of the preceding claims, characterized by , - that if the calculated charge value (Q) is greater than the set charge limit value (Q Gr ), a second time interval (t4 - t6) is initialized, - a second integral of the current difference (I Ist - ID ) between the current (I Ist ) and the first current output value (I D ) is calculated over the second time interval (t4 - t6) and - the maximum current (I Max ) from the second current output value (I S ) linear to the value of the second integral of the current difference (I Ist - I D ) is reduced, - whereby the maximum current (I Max ) to a maximum of the first current output value (I D ) is reduced. [5] Method according to one of the preceding claims, characterized by , that - the performance map (20, 21) of the battery (2) has been calculated and / or simulated over a range of operating points, - the current operating point is determined and a corresponding first and second power output value (P D , P S ) is determined, - the internal resistance (R0) of the battery (2) at the operating point and the open circuit voltage (U0) of the battery (2) are determined and - the first and second current output values (I D , I S ) as a solution of a quadratic equation from the first and second power output value (P D , P S ), the internal resistance (R0) and the open circuit voltage (U0) of the battery (2). [6] Method according to one of the preceding claims, characterized by , that - a current characteristic map of the battery (2) has been calculated and / or simulated over a range of operating points, - the current operating point is determined and a corresponding first and second current output value (I D , I S ) is determined, - the operating voltage (U) of the battery (2) is measured, - the first and second current output values (I D , I S) and the operating voltage (U) resulting theoretical power output is calculated and compared with the actual power output and - that the first and second current output values (I D , I S ) and / or the current characteristic of the battery (2) is corrected depending on this comparison. [7] Method according to one of the preceding claims, characterized by that the first and second current output values (I D , I S ) are continuously updated. [8] Method according to one of the preceding claims, characterized by that the power dynamics of the battery (2) is visualized by a one-dimensionally representable quantity (13), wherein a fixed predetermined proportion (15) of the one-dimensionally representable quantity (13) is assigned to the calculated charge value (Q). [9] Device (3, 4, 7, 8) for controlling the power dynamics of the battery (2) of an electrically driven vehicle, comprising - a battery monitoring device (3) for detecting at least two different current output values (I D , I S ), whereby the first current output value is the continuous current (I D ) and the second current output value is the peak current that can be delivered at the current operating point (I S ) is, - a measuring device (4) for measuring the current (I Ist ) over a time interval, - a computing unit (8) which is connected to the measuring device (4) and by means of which the temporal development of the current difference (I Ist - I D ) between the current (I Ist) and the first current output value (I D ) a charge value (Q) can be calculated over the time interval, and - a control unit (7) connected to the battery monitoring device (3) and the computing unit (8), - by means of which, if the calculated charge value (Q) is less than or equal to a specified charge limit value (Q Gr ), from which a controlled current limitation is initiated, is the maximum current (I Max ) by means of the control unit (7) equal to the second current output value (I S ) is settable, and - by means of which, if the calculated charge value (Q) is greater than the set charge limit value (Q Gr ), the maximum current (I Max) by means of the control unit (7) as a function of the calculated charge value (Q) is less than the second current output value (I S ) can be set.
Citation Information
Patent Citations
Methods for determining and / or predicting the maximum performance of a battery
DE102009049589A1
Method for detecting the charge limit of a battery
EP0487784B1
Battery with charge and discharge management
US20090091296A1