Controlling semiconductor switches of a voltage converter circuit arrangement
Patent Information
- Application Number
- EP2022836224
- Authority / Receiving Office
- EP · EP
- Patent Type
- Applications
- Current Assignee / Owner
- Priority Date
- 2021-12-21
- Filing Date
- 2022-12-19
- Publication Date
- 2024-10-30
Smart Images

Figure 1.1 
Figure 1.2
Abstract
Description
[0001] Control of semiconductor switches of a voltage converter circuit arrangement
[0002] The invention relates to a technology for controlling the semiconductor switches of a circuit arrangement for voltage conversion between a power source and an electrical load. In particular, a current control method for a two-switch buck converter circuit arrangement with current signal information from only one semiconductor switch path is provided.
[0003] A buck converter circuit arrangement 10 with a diode 12 as shown in Fig. 1 is known from the prior art. The buck converter circuit arrangement can be operated on the boundary (also: boundary gap, English: "Boundary Conduction Mode", BCM for short) between continuous operation and discontinuous operation of an inductance L (also: choke) in order to achieve low-loss switching of a semiconductor switch (S), whereby a metal-oxide-semiconductor field-effect transistor (MOSFET) is usually used. In this case, the buck converter circuit arrangement is operated near the gap limit of the choke current II SO, so that both currentless switching (ZCS for short) and voltageless switching (ZVS for short) of the semiconductor switch S is possible.The inductor L of the conventional buck converter circuit and the output capacitance Coss of the semiconductor switch form a series resonant circuit. This series resonant circuit is recharged within half the period of its natural frequency, so that when the inductor current II changes sign, the output capacitance Coss is set to twice the value of the buck converter input voltage n, minus the buck converter output voltage V. ou t is recharged. This reduces the switching voltage and the inrush current, and thus the switching losses, when the semiconductor switch S is switched on again. As shown in Fig. 2, the inductor current of the conventional buck converter circuit arrangement gaps during each switching period of the semiconductor switch S. The temporal relationships are as follows:
[0004] In order to ensure that the semiconductor switch S switches with as little loss as possible, the period of a switching cycle T s not be shorter than:
[0005] In particularly loss-optimized applications, a half-bridge circuit with at least two active semiconductor switches (Si, S2) is used, as shown in Fig. 4, instead of a conventional buck converter circuit arrangement with diode 12, as shown in Fig. 1. The diode 12 from Fig. 1 is replaced by the second semiconductor switch S2. The circuit of Fig. 4 can also be referred to as a full-bridge buck converter power factor correction circuit arrangement (short: "full-bridge buck PFC circuit" with buck converter in English: "buck" and power factor correction in English: "PFC" in short).
[0006] Fig. 3 shows an idealized time sequence of the control of the semiconductor switches S1 and S2 of an idealized lossless circuit according to Fig. 4 for a positive input voltage Vj n shown.
[0007] The condition for switching off the first semiconductor switch S1 and switching on the second semiconductor switch S2 in this idealized case is that the inductor current exceeds an upper current threshold lh. The current threshold lh is specified for the respective operating point of the circuit arrangement by a current regulator. The condition for switching off the second semiconductor switch S2 and switching on the first semiconductor switch S1 in this idealized case is that the inductor current falls below a lower current threshold h. The current threshold h is statically specified and ensures complete recharging of coss-
[0008] In contrast to the circuit arrangement in Fig. 1, the semiconductor switch S2 remains switched on until the charge from Coss to zero volts (0 V) has been completely transferred. After that, the first semiconductor S1 is switched on and the second semiconductor switch S2 is simultaneously switched off, so that the current II can commutate from the second semiconductor switch S2 to the first semiconductor switch S1 and the current gradient becomes positive again.
[0009] In the dissertation “Current Mode Control structure: Current-Mode Control: Modeling and Digital Application” by Jian Li (April 14, 2009, Blacksburg, Virginia), an alternative method for the idealized generation of switching times (Ton) of the first semiconductor switch S1 and the second semiconductor switch S2 for the idealized loss-free buck converter circuit arrangement shown in Fig. 5 is described. Fig. 6 (a) shows a peak current mode control (PCMC), Fig. 6 (b) shows an idealized valley current mode control, Fig. 6 (c) shows an idealized constant on-time control, Fig. 6 (d) shows an idealized constant off-time control and Fig. 6 (e) shows an idealized hysteric control.
[0010] Conventional methods for generating switching signals for buck converter topologies operated with two semiconductor switches require all the information about the current flow through the inductance L in order to generate the switching signals using comparators. There are two conventional ways to achieve this, each with significant disadvantages. According to a first conventional switching signal control, the current II is measured directly with a current measuring resistor (short: measuring resistor; also: "shunt") in the path of II using a circuit that brings the signal to the measuring potential. A disadvantage of the first conventional switching signal control is that the circuit for potential isolation is usually very expensive. For example, a Hall measurement is conventionally used.Another disadvantage of the first conventional switching signal control is that the circuit for potential isolation usually has only a small bandwidth and reproduces the signal in a distorted manner.
[0011] According to a second conventional switching signal control, the current is measured using current transformers in the individual switching paths, using additional circuitry to demagnetize the current transformers and additional circuitry to measure the current bidirectionally. A disadvantage of the second conventional switching signal control is that the circuit is complex, with many components. Another disadvantage of the second conventional switching signal control is that current transformers are typically more expensive than current measuring resistors (also known as "shunts").
[0012] The invention is therefore based on the object of specifying a technology for controlling the semiconductor switches of a circuit arrangement for voltage conversion between a power source and an electrical load, in which a potential for measuring circuits and / or control circuits (in particular, regulation circuits) can be set to a low-noise potential, for example, a negative intermediate circuit voltage. Alternatively or additionally, the object is to achieve suitable current measurement with only one measuring resistor and / or only minimal additional circuitry for generating the semiconductor switch signals for the semiconductor switches.
[0013] The object or objects are achieved by the features of the independent claims. Expedient embodiments and advantageous further developments of the invention are specified in the dependent claims. Exemplary embodiments of the invention are described below, partially with reference to the figures.
[0014] According to a first aspect, a buck converter circuit arrangement for supplying power to an electrical load comprises an inductor connected between a first node and a second node, a capacitor connected between the second node and a third node, and a DC voltage output connected between the second node and the third node in parallel with the capacitor for connecting the load. The buck converter circuit arrangement further comprises an input unit for connecting a current source feeding the buck converter circuit arrangement, wherein the input unit has a first pole, which acts as a positive pole at least in a positive half-wave, and a second pole, which acts as a negative pole at least in the positive half-wave.The buck converter circuit arrangement further comprises a first semiconductor switch, which is arranged to selectively conductively connect the first pole to the first node, and a second semiconductor switch, which is arranged to selectively conductively connect the first node and the third node via a fourth node. The buck converter circuit arrangement further comprises at least one current measuring point, which is arranged downstream of the third node in a current path comprising the first node, the second node, and the third node. The buck converter circuit arrangement further comprises a control unit, which is designed to make the first semiconductor switch conductive during a fixed time period (ton) of a magnetization phase of the inductance, at least in the positive half-wave, and during a variable time period (t Off) to switch the second semiconductor switch non-conductive during a demagnetization phase of the inductance at least in the positive half-wave, and to switch the second semiconductor switch non-conductive during the fixed time period (ton) of the magnetization phase of the inductance at least in the positive half-wave and during the variable time period (t O ff) the demagnetization phase of the inductance is to be switched on at least in the positive half-wave.
[0015] The fixed duration (ton) of the magnetization phase of the (for example, first) inductance is determined for each circuit arrangement of the first, second, and third aspects as a function of a predetermined maximum current through the inductance. Alternatively or additionally, the variable duration (t Off) the demagnetization phase of the (for example first) inductance for each circuit arrangement of the first, second and third aspect is variable depending on a comparison of a predetermined minimum current through the inductance and a current measurable across the at least one current measuring point.
[0016] The buck converter circuit can also be referred to as a step-down converter circuit (English “buck converter” and / or “step-down converter”).
[0017] The power supply of the electrical load may comprise a direct current supply and / or a direct voltage supply. At least the positive half-wave may correspond to the direct current supply and / or the direct voltage supply.
[0018] Alternatively or additionally, the power supply may comprise an AC power supply and / or an AC voltage supply. The AC power supply and / or the AC voltage supply may comprise the positive half-wave and a negative half-wave.
[0019] The inductance may comprise a coil and / or choke.
[0020] The capacitance may comprise a capacitor, in particular a smoothing capacitor.
[0021] The electrical consumer can also be referred to as a load.
[0022] The current measuring point can comprise a measuring resistor. The measuring resistor can also be referred to as a current sense resistor or, in technical terms, a "shunt." Alternatively or additionally, the current measuring point can comprise a current sense transformer. Furthermore, alternatively or additionally, the current measuring point can comprise a Hall sensor and / or an inductive current transformer.
[0023] The conducting state of any semiconductor switch can also be referred to as closed and / or closed. Alternatively or additionally, the non-conducting state of any semiconductor switch can also be referred to as open.
[0024] A combination of a time period, ton, the magnetization phase of the inductance and the directly subsequent variable time period, t O ff, the demagnetization phase of the inductance can be defined as period, T pe riode, the circuit arrangement.
[0025] The fourth node can be grounded and / or connected to a ground.
[0026] Embodiments of the (for example, buck converter) circuit arrangements can enable low-loss switching of the, in particular, first and second, semiconductor switches, in particular at the boundary (boundary conduction mode, abbreviated to BCM) of discontinuous conduction mode (DCM) to continuous conduction mode (CCM). The modification of a conventional (for example, buck converter) circuit arrangement can be kept as simple as possible, in particular by adding one or more current measuring points (for example, one or more measuring resistors) at suitable (preferably particularly low-interference with respect to a reference potential) locations in the circuit.Alternatively or additionally, one or a few isolated current measurements at one or more current measuring points at specific times of a period may be sufficient to determine the switching time(s) of the at least two semiconductor switches.
[0027] The power source feeding the input unit of the buck converter circuit arrangement can comprise an alternating current source, wherein the first pole acts as a negative pole in a negative half-wave, and wherein the second pole acts as a positive pole in the negative half-wave. The buck converter circuit arrangement can further comprise a third semiconductor switch which selectively connects the fourth node to the first pole via a fifth node in a conductive manner, and a fourth semiconductor switch which selectively connects the fourth node to the second pole via the fifth node in a conductive manner. The control unit can be configured to switch the third semiconductor switch non-conductive and the fourth semiconductor switch conductive during the positive half-wave. The control unit can further be configured to switch the third semiconductor switch conductive and the fourth semiconductor switch non-conductive during the negative half-wave.The control unit can further be configured to switch the first semiconductor switch non-conductive and the second semiconductor switch conductive during the fixed time period (ton) of the magnetization phase in the negative half-wave. The control unit can further be configured to switch the first semiconductor switch non-conductive and the second semiconductor switch conductive during the variable time period (t. O ff) the demagnetization phase in the negative half-wave to switch the first semiconductor switch conductive and the second semiconductor switch non-conductive.
[0028] According to a second aspect, a boost-buck converter circuit arrangement for supplying power to an electrical load comprises an inductor connected between a first node and a second node, a capacitor connected between a third node and a fourth node, and a DC voltage output connected between the third node and the fourth node in parallel with the capacitor for connecting the load. The boost-buck converter circuit arrangement further comprises an input unit for connecting a current source feeding the boost-buck converter circuit arrangement, wherein the input unit has a first pole, which acts as a positive pole at least in a positive half-wave, and a second pole, which acts as a negative pole at least in the positive half-wave.The boost-buck converter circuit arrangement further comprises a first semiconductor switch arranged to selectively conductively connect the first pole to the first node; a second semiconductor switch arranged to selectively conductively connect the first node and the fourth node via a fifth node and a sixth node; a third semiconductor switch arranged to selectively conductively connect the second node and the third node; and a fourth semiconductor switch arranged to selectively conductively connect the second node and the fifth node. The boost-buck converter circuit arrangement further comprises at least one current measuring point arranged in a current path comprising the fourth node and the fifth node and / or the fourth semiconductor switch and the fifth node.The boost-buck converter circuit arrangement further comprises a control unit which, in a function as a buck converter of the boost-buck converter circuit arrangement, is designed to make the first semiconductor switch conductive during a fixed time period (ton) of a magnetization phase of the inductance at least in the positive half-wave and during a variable time period (t. O ff) to switch the second semiconductor switch non-conductive during a demagnetization phase of the inductance at least in the positive half-wave, in the function as a buck converter, to switch the second semiconductor switch non-conductive during the fixed time period (ton) of the magnetization phase of the inductance at least in the positive half-wave and during the variable time period (t Off) to switch the inductance conductive at least in the positive half-wave during the demagnetization phase, and in the function as a buck converter to switch the third semiconductor switch conductive and the fourth semiconductor switch non-conductive.
[0029] The control unit is further configured in a function as a boost converter of the boost-buck converter circuit arrangement to switch the first semiconductor switch conductive and the second semiconductor switch non-conductive at least in a positive half-wave, wherein the control unit in the function as a boost converter is further configured to switch the fourth semiconductor switch conductive during the fixed time period (ton) of the magnetization phase of the inductance at least in the positive half-wave and during the variable time period (t Off) to switch the demagnetization phase of the inductance non-conductive at least in the positive half-wave, and in the function as a boost converter, to switch the third semiconductor switch non-conductive at least in the positive half-wave during the fixed time period (ton) of the magnetization phase of the inductance and during the variable time period (t O ff) the demagnetization phase of the inductance is to be switched on at least in the positive half-wave.
[0030] The step-up converter circuit arrangement can also be referred to as a buck-boost converter.
[0031] The power supply of the boost-buck converter circuit arrangement may comprise a DC current source and / or a DC voltage source. The positive half-wave may correspond to a positive DC current source and / or a positive DC voltage source.
[0032] Alternatively or additionally, the power supply of the boost-buck converter circuit arrangement can comprise an alternating current source and / or an alternating voltage source. The positive half-wave and a negative half-wave can be assigned to the alternating current source and / or the alternating voltage source. In the negative half-wave, the first pole can correspond to the negative pole and the second pole to the positive pole.
[0033] The power source feeding the input unit of the boost-buck converter circuit arrangement can comprise an alternating current source, wherein the first pole acts as a negative pole in a negative half-wave, wherein the second pole acts as a positive pole in the negative half-wave. The boost-buck converter circuit arrangement can further comprise a fifth semiconductor switch which selectively connects the sixth node to the first pole in a conductive manner, and a sixth semiconductor switch which selectively connects the sixth node to the second pole in a conductive manner. The control unit can be configured to switch the fifth semiconductor switch non-conductive and the sixth semiconductor switch conductive during the positive half-wave. The control unit can further be configured to switch the fifth semiconductor switch conductive and the sixth semiconductor switch non-conductive during the negative half-wave.
[0034] The control unit is designed to switch the first semiconductor switch non-conductive and the second semiconductor switch conductive in the function as a buck converter during the specified time period (ton) of the magnetization phase in the negative half-wave. The control unit can further be designed to switch the first semiconductor switch non-conductive and the second semiconductor switch conductive in the function as a buck converter during the variable time period (t O ff) the demagnetization phase in the negative half-wave to switch the first semiconductor switch conductive and the second semiconductor switch non-conductive.
[0035] The control unit can further be configured to switch the first semiconductor switch non-conductive and the second semiconductor switch conductive during the specified time period (ton) of the magnetization phase in the negative half-wave, when functioning as a boost converter. The control unit can further be configured to switch the first semiconductor switch non-conductive and the second semiconductor switch conductive during the negative half-wave, when functioning as a boost converter.
[0036] According to a third aspect, a flyback converter circuit arrangement for supplying power to an electrical load comprises a first inductor and a second inductor, wherein the first inductor and the second inductor are inductively coupled, wherein the first inductor and the second inductor are galvanically isolated, and wherein the second inductor is connected to a first node. The flyback converter circuit arrangement further comprises a capacitor connected between the first node and a second node, and a DC voltage output connected between the first node and the second node in parallel with the capacitor for connecting the load.The flyback converter circuit arrangement further comprises an input unit for connecting a current source feeding the flyback converter circuit arrangement, wherein the input unit has a first pole, which acts as a positive pole at least in a positive half-wave, and a second pole, which acts as a negative pole at least in the positive half-wave. The flyback converter circuit arrangement further comprises a first semiconductor switch, which is arranged to selectively conductively connect the first inductance to the second pole, at least in the positive half-wave, and a second semiconductor switch, which is arranged between the second node and the second inductance, to selectively conductively connect the second inductance and the capacitor.The flyback converter circuit arrangement further comprises at least one current measuring point, which is arranged in a current path comprising the first semiconductor switch and the current source and / or in a current path comprising the second node and second semiconductor switch. The flyback converter circuit arrangement further comprises a control unit, which is designed to make the first semiconductor switch conductive during a fixed time period (ton) of a magnetization phase of the first inductance and the second inductance and to make the first semiconductor switch non-conductive during a variable time period (t). O ff) a demagnetization phase of the first inductance and the second inductance to be non-conductive, and the second semiconductor switch to be non-conductive during the fixed time period (ton) of the magnetization phase of the first inductance and the second inductance at least in the positive half-wave and to be non-conductive during the variable time period (t Off) the demagnetization phase of the first inductance and the second inductance is to be switched on at least in the positive half-wave.
[0037] The flyback converter circuit arrangement can also be called a “flyback converter”.
[0038] The power supply of the flyback converter circuit arrangement may comprise a DC current source and / or a DC voltage source. The positive half-wave may correspond to a positive DC current source and / or a positive DC voltage source.
[0039] Alternatively or additionally, the power supply of the flyback converter circuit arrangement can comprise an alternating current source and / or an alternating voltage source. The positive half-wave and a negative half-wave can be assigned to the alternating current source and / or the alternating voltage source. In the negative half-wave, the first pole can correspond to the negative pole and the second pole to the positive pole.
[0040] The current source feeding the input unit of the flyback converter circuit arrangement may comprise an alternating current source, wherein the first pole acts as a negative pole in a negative half-cycle, wherein the second pole acts as a positive pole in the negative half-cycle.According to a first exemplary embodiment of the third aspect with an alternating current source, the flyback converter circuit arrangement can further comprise a third semiconductor switch, a fourth semiconductor switch, a fifth semiconductor switch and a sixth semiconductor switch, wherein the third semiconductor switch is designed to selectively connect the first inductance to the first pole, wherein the fourth semiconductor switch is designed to selectively connect the first inductance to the second pole, wherein the fifth semiconductor switch is designed to selectively connect the first semiconductor switch to the second pole, and wherein the sixth semiconductor switch is arranged to selectively connect the first semiconductor switch to the first pole.
[0041] According to the first embodiment of the third aspect with an alternating current source, the control unit can be designed to make the third semiconductor switch and the fifth semiconductor switch conductive during the fixed time period (ton) of the magnetization phase in the positive half-wave and to make the third semiconductor switch and the fifth semiconductor switch conductive during the variable time period (t O ff) the demagnetization phase of the positive half-wave, and to switch the third semiconductor switch and the fifth semiconductor switch non-conductive during the negative half-wave. The control unit can further be designed to switch the fourth semiconductor switch and the sixth semiconductor switch non-conductive during the positive half-wave, and to switch the fourth semiconductor switch and the sixth semiconductor switch conductive during the fixed time period (ton) of the magnetization phase in the negative half-wave and during the variable time period (t Off) the demagnetization phase of the negative half-wave is to be switched non-conductive.
[0042] According to a second exemplary embodiment of the third aspect with an alternating current source, the flyback converter circuit arrangement can further comprise a third inductance and a third semiconductor switch, wherein the third semiconductor switch is designed to selectively connect the third inductance to the first node and the second node. According to the second exemplary embodiment of the third aspect with an alternating current source, the control unit can be designed to switch the second semiconductor switch non-conductive during the negative half-wave. The control unit can further be designed to switch the third semiconductor switch non-conductive during the positive half-wave and during the fixed time period (ton) of the magnetization phase of at least the first inductance in the negative half-wave and during the variable time period (t Off) to switch on at least the first inductance of the negative half-wave during the demagnetization phase.
[0043] The time period t on The magnetization phase can be constant for each of the circuit arrangements according to the invention as a function of a maximum current through the inductance, for example, it can be determined for an operating period of the (for example buck converter) circuit arrangement, for an electrical consumer and / or for an operating point of the respective (for example buck converter) circuit arrangement.
[0044] Alternatively or additionally, t O ff, toffset, t O ff + toffset and / or a minimum current through the inductances of the circuit arrangements depend on tolerances of individual components and / or delays in drivers.
[0045] One or each of the semiconductor switches of one or each circuit arrangement may comprise a MOSFET, in particular an n-channel MOSFET, a bipolar transistor, a thyristor and / or an insulated gate bipolar transistor (IGBT).
[0046] The control unit of one or each circuit arrangement may further be configured to operate the circuit arrangement in a continuous mode of operation (CCM), a discontinuous mode of operation (DCM), and / or on a boundary between the continuous and discontinuous modes of operation (BCM).
[0047] The CCM may include average current control.
[0048] The at least one current measuring point of one or each circuit arrangement can comprise at least one measuring resistor. The at least one current measuring point of one or each circuit arrangement can be arranged in the current path of the first semiconductor switch. The control unit can further be configured to measure at least one current value across the at least one current measuring point during the magnetization phase in the positive half-wave and / or in the negative half-wave.
[0049] The at least one current value may comprise exactly one current value at a specified time of the magnetization phase, preferably at the beginning of the magnetization phase and / or in the vicinity of a switching time from the non-conductive to the conductive state of the first semiconductor switch.
[0050] Alternatively or additionally, the at least one current measuring point of one or each circuit arrangement can be arranged in the current path of the second semiconductor switch. The control unit can further be configured to measure at least one current value during the demagnetization phase in the positive half-wave and / or in the negative half-wave across the at least one current measuring point.
[0051] Alternatively or additionally, the at least one current measuring point can comprise two current measuring points, one in each case in the current path of the first semiconductor switch (Si) and one in the current path of the second semiconductor switch (S2).
[0052] The control unit of one or each circuit arrangement can further be designed to switch at least one or each semiconductor switch to conduction in a voltage-free state and / or in a current-free state of the inductance.
[0053] The zero-voltage state is also referred to as "zero voltage switching" (ZVS for short). Alternatively or additionally, the zero-current state is also referred to as "zero current switching" (ZCS for short). The control unit of one or each circuit arrangement can comprise a digital signal processor (DSP), a microcontroller with control software, a field-programmable gate array (FPGA), and / or an application-specific integrated circuit (ASIC). The application-specific integrated circuit is also referred to as an "application-specific integrated circuit" (ASIC for short).
[0054] According to a fourth aspect, a method is provided for controlling the semiconductor switches of a circuit arrangement during a magnetization phase and a demagnetization phase of an inductance. The method can be carried out using a circuit arrangement according to the first, second, and / or third aspect.
[0055] The method comprises the step of measuring a current value across at least one current measuring point of one of the circuit arrangements of the first, second and / or third aspect, wherein the current value is measured during a fixed point in time of a period comprising a fixed time duration (ton) of a magnetization phase and a variable time duration (t O ff) a demagnetization phase of an inductance. The fixed time duration (ton) of the magnetization phase of the inductance is determined as a function of a predetermined maximum current through the inductance. The method further comprises the step of comparing the measured current value with a reference current value determined for the time of the measurement. The method further comprises the step of changing the variable time duration (t Off) the demagnetization phase of the inductance depending on a result of comparing the measured current value with the reference current value.
[0056] The invention is explained in more detail below with reference to the drawings using preferred embodiments.
[0057] 1 shows a first schematic embodiment of a conventional buck converter circuit arrangement with a semiconductor switch and a diode;
[0058] Fig. 2 shows an idealized current curve through the inductance and an idealized voltage curve across the semiconductor switch of the conventional buck converter circuit arrangement of Fig. 1;
[0059] Fig. 3 shows an idealized current curve through the inductance and an idealized voltage curve across a semiconductor switch of the conventional buck converter circuit arrangement of the following Fig. 4;
[0060] Fig. 4 shows a second schematic embodiment of a conventional buck converter circuit arrangement with two semiconductor switches;
[0061] Fig. 5 shows a third schematic embodiment of a conventional buck converter circuit arrangement with two semiconductor switches;
[0062] Fig. 6 idealized current waveforms through the inductance and idealized voltage waveforms across a semiconductor switch of the conventional buck converter circuit arrangement of Fig. 5;
[0063] 7A and 7B show a schematic embodiment of a buck converter circuit arrangement according to the invention with a direct current source during a magnetization phase and a demagnetization phase, respectively, wherein the buck converter circuit arrangement according to the invention comprises two semiconductor switches and at least one measuring resistor; 8A to 8D show a schematic embodiment of a buck converter circuit arrangement according to the invention with an alternating current source during a positive half-wave (Figs. 8A and 8B) and during a negative half-wave (Figs. 8C and 8D) and each with a magnetization and demagnetization phase, wherein the buck converter circuit arrangement according to the invention comprises four semiconductor switches and at least one measuring resistor;
[0064] Fig. 9A to 9H show a schematic embodiment of a boost-buck converter circuit arrangement according to the invention with an alternating current source in use as a boost converter (Fig. 9A to 9D) and as a buck converter (Fig. 9E to 9H), wherein the boost-buck converter circuit arrangement according to the invention comprises six semiconductor switches and at least one measuring resistor;
[0065] 10A and 10B show a schematic first exemplary embodiment of a flyback converter circuit arrangement according to the invention with an alternating current source during a positive half-wave (Fig. 10A) and during a negative half-wave (Fig. 10B) and in each case a magnetization and demagnetization phase, wherein the flyback converter circuit arrangement according to the invention according to the first exemplary embodiment comprises five semiconductor switches in the circuit of a first inductance and one semiconductor switch in the circuit of a second inductance and at least one measuring resistor in one of the two circuits;
[0066] Fig. 11A and 11B show a schematic second exemplary embodiment of a flyback converter circuit arrangement according to the invention with an alternating current source during a positive half-wave (Fig. 10A) and during a negative half-wave (Fig. 10B) and in each case a magnetization and demagnetization phase, wherein the flyback converter circuit arrangement according to the invention according to the second exemplary embodiment comprises at least one semiconductor switch in the circuit of a first inductance and one semiconductor switch each in the circuit of a second and third inductance, as well as at least one measuring resistor in one of the circuits.
[0067] Fig. 12 shows an exemplary current curve for the inductance and the two semiconductor switches of the buck converter circuit arrangement of Figs. 7A and 7B, wherein the time period (t O ff) the demagnetization phase is variable due to a lower reference current; and
[0068] Fig. 13 shows an exemplary method for controlling the semiconductor switches of the buck converter circuit arrangement of Figs. 7A and 7B.
[0069] In the following exemplary embodiments, at least one measuring resistor is used as at least one current measuring point. Each of the exemplary embodiments can alternatively or additionally use any other example of a current measuring point (e.g., a Hall sensor).
[0070] 7A and 7B show a buck converter circuit arrangement 100 according to the invention, which is connected to a DC power source with a positive pole 102-1 and a negative pole 102-2. The buck converter circuit arrangement 100 comprises a first semiconductor switch (Si) 112, which is conductive during a magnetization phase 140, shown in Fig. 7A, of an inductor 104 and non-conductive during a demagnetization phase 142, shown in Fig. 7B, of the inductor 104. A second semiconductor switch (S2) 114 is electrically conductively connected to the inductor 104 via a first node 122 during the demagnetization phase 104.
[0071] The control of the semiconductor switch positions for the buck converter circuit arrangement 100 of Figs. 7A and 7B can be summarized as follows:
[0072] The inductance 104 is electrically connected via a second node 124 to an electrical load 108 and a capacitor 106 connected in parallel with the electrical load 108 up to a third node 126. Via a fourth node 128, the electrical load 108 and the capacitor 106 are optionally connectable to the second semiconductor switch (S2) 114 and the negative pole 102-2 of the DC power source.
[0073] The switching of the two semiconductor switches 112; 114 is controlled by a control unit 150 depending on a measured current value. The current value is measured either via a first measuring resistor 110-1 or a second measuring resistor 110-2. The current value can be measured via the first measuring resistor 110-1 either during the magnetization phase 140 or the demagnetization phase 142. The current value can be measured via the second measuring resistor 110-2 only during the magnetization phase 140.
[0074] The buck converter circuit arrangement 100 of Figs. 7A and 7B may optionally comprise only the first measuring resistor 110-1 or the second measuring resistor 110-2.
[0075] 8A, 8B, 8C, and 8D show a buck converter circuit arrangement 100 according to the invention, which is connected to an alternating current source with a first pole 102-1 and a second pole 102-2. The buck converter circuit arrangement 100 of FIGS. 8A to 8D comprises all elements of the buck converter circuit arrangement 100 of FIGS. 7A and 7B, and the first semiconductor switch (S1) 112 and the second semiconductor switch (S2) 114 can be switched accordingly during a positive half-wave. The buck converter circuit arrangement 100 of FIGS. 8A to 8D comprises two further semiconductor switches (S3) 116 and (S4) 118, which function as pole converters, in particular as rectifiers, of the alternating current source.
[0076] In Fig. 8A and 8B, the current paths during the magnetization phase 140 of the inductance 104 and during the demagnetization phase 142 of the inductance 104 are shown during a positive half-cycle.
[0077] In Fig. 8C and 8D, the current paths of the magnetization phase 144 of the inductance 104 and during the demagnetization phase 146 of the inductance 104 are shown during a negative half-cycle.
[0078] The control of the semiconductor switch positions for the buck converter circuit arrangement 100 of Figs. 8A to 8D can be summarized as follows:
[0079] Buck converter, AC power source, switch positions
[0080] The measuring resistor 110-1 carries current in each half-wave and each magnetization phase 140; 142; 144; 146. The measuring resistor 110-2 carries current only in the magnetization phase 140; 144 of each half-wave. A third measuring resistor 110-3 of the buck converter circuit arrangement 100 connected to the AC power source only carries current when the second semiconductor switch (S2) 114 is conductive, i.e., in the demagnetization phase 142 of the positive half-wave and in the magnetization phase 144 of the negative half-wave. The switching of the four semiconductor switches 112; 114; 116; 118 is controlled by a control unit (not shown) depending on a measured current value across at least one of the measuring resistors 110-1; 110-2; 110-3.
[0081] The buck converter circuit arrangement 100 of Figs. 8A to 8D may optionally comprise only the first measuring resistor 110-1, only the second measuring resistor 110-2, only the third measuring resistor 110-3, or a subset of two of the three measuring resistors 110-1; 110-2; 110-3.
[0082] 9A to 9H show a boost-buck converter circuit arrangement 200 connected to a first pole 102-1 and a second pole 102-2 of an alternating current source. The boost-buck converter circuit arrangement 200 comprises six semiconductor switches (S1; S2; S3; S5; Sß) 112; 114; 116; 118; 202; 204, which can be electrically connected via a plurality of nodes 122; 124; 126; 128; 130; 132 selectively to the inductor 104, the alternating current source, and the electrical load 108 and parallel-connected capacitor 106.
[0083] In Fig. 9A to 9D, the current waveforms for the use of the boost-buck converter circuit arrangement 200 as a boost converter during the magnetization phase 140 and the demagnetization phase 142 in the positive half-wave and during the magnetization phase 144 and the demagnetization phase 146 in the negative half-wave are shown.
[0084] The control of the semiconductor switch positions for the boost-buck converter circuit arrangement 200 of Fig. 9A to 9D as a boost converter can be summarized as follows:
[0085] When used as a boost converter of the boost-buck converter circuit arrangement 200, the third semiconductor switch (S3) 116 and the fourth semiconductor switch (S4) 118 serve to switch between the magnetization phase 140; 144 and the demagnetization phase 142; 146. The first, second, fifth and sixth semiconductor switches (S1) 112, (S2) 114, (S5) 202 and (Se) 204 serve as pole converters, in particular as rectifiers for switching between positive and negative half-waves, when used as a boost converter of the boost-buck converter circuit arrangement 200.
[0086] When used as a boost converter of the boost-buck converter circuit arrangement 200, current flows through the first measuring resistor 110-1 in each magnetization phase 140; 144, and current flows through the second measuring resistor 110-2 in each demagnetization phase 142; 146.
[0087] In Fig. 9E to 9H, the current waveforms for the use of the boost-buck converter circuit arrangement 200 as a buck converter during the magnetization phase 140 and the demagnetization phase 142 in the positive half-wave and during the magnetization phase 144 and the demagnetization phase 146 in the negative half-wave are shown.
[0088] The control of the semiconductor switch positions for the boost-buck converter circuit arrangement 200 of Fig. 9E to 9H as a buck converter can be summarized as follows:
[0089] When used as a buck converter of the boost-buck converter circuit arrangement 200, the first semiconductor switch (Si) 112 and the second semiconductor switch (S2) 114 thus serve to switch between the magnetization phase 140; 144 and the demagnetization phase 142; 146. The fifth and sixth semiconductor switches (S5) 202 and (Se) 204, when used as a buck converter of the boost-buck converter circuit arrangement 200, serve as pole converters, in particular as rectifiers for switching between positive and negative half-waves.
[0090] When used as a buck converter of the boost-buck converter circuit arrangement 200, current flows through the second measuring resistor 110-2 in each magnetization phase 140; 144 and each demagnetization phase 142; 146.
[0091] The two measuring resistors 110-1 and 110-2 are shown only as examples. Analogous to the buck converter arrangement 100 connected to an AC power source in Figs. 8A to 8D, additional measuring resistors can be provided at other locations in the circuit diagram.
[0092] The boost-buck converter circuit arrangement 200 with connection to an AC power source can be read as a boost-buck converter circuit arrangement 200 with connection to a DC power source by limiting it to one (for example the positive) half-wave, in which the fifth and sixth semiconductor switches (S5) 202 and (Se) 204 are replaced by a galvanic isolation and a conductive connection for the selection of the positive half-wave or vice versa for the selection of the negative half-wave.
[0093] 10A and 10B show a first embodiment of a flyback converter circuit arrangement 300 connected to an AC power source during the positive and negative half-waves, respectively. The flyback converter circuit arrangement 300 comprises two circuits that are inductively coupled via a first inductor 104 and a second inductor 302. The first inductor 104 is selectively connected to the poles 102-1; 102-2 of the AC power source via a first semiconductor switch (Si) 112.
[0094] In the first embodiment of the flyback converter circuit arrangement 300, the second inductance 302 is optionally connected via a second semiconductor switch (S2) 114 to an electrical load 108 and a parallel-connected capacitor 106.
[0095] The control of the semiconductor switch positions for the first embodiment of the flyback converter circuit arrangement 300 of Figs. 10A and 10B can be summarized as follows:
[0096] In the first exemplary embodiment, the first semiconductor switch (S1) 112 and the second semiconductor switch (S2) 114 thus serve to switch between the magnetization phase 140; 144 (current flow in the left-hand circuit of Figs. 10A and 10B) and the demagnetization phase 142; 146 (current flow in the right-hand circuit of Figs. 10A and 10B). The four further semiconductor switches (S3) 116, (S4) 118, (S5) 202, and (S6) 204 jointly act as pole converters, in particular as rectifiers, in the first exemplary embodiment of the flyback converter circuit arrangement 300.
[0097] In the first embodiment of Figs. 10A and 10B of the flyback converter circuit arrangement 300, current flows through the first measuring resistor 110-1 in the circuit of the first inductance 104 and the AC power source during each magnetization phase 140; 144. During each demagnetization phase 142; 146, current flows through the second measuring resistor 110-2 in the circuit of the second inductance 302, the electrical load 108, and the capacitor 106.
[0098] Figs. 11A and 11B show a second embodiment of a flyback converter circuit arrangement 300 connected to an alternating current source during the positive and negative half-waves, respectively. The flyback converter circuit arrangement 300 comprises two circuits that are inductively coupled via a first inductor 104 and a second inductor 302 and a third inductor 304, respectively. The first inductor 104 is selectively connected to the poles 102-1; 102-2 of the alternating current source via a first semiconductor switch (S1) 112.
[0099] The second inductance 302 is optionally connected via a second semiconductor switch (S2) 114 and the third inductance 304 is optionally connected via a third semiconductor switch (S3) 116 in the second embodiment of the flyback converter circuit arrangement 300 to an electrical load 108 and a parallel-connected capacitor 106.
[0100] The control of the semiconductor switch positions for the second embodiment of the flyback converter circuit arrangement 300 of Figs. 11 A and 11 B can be summarized as follows:
[0101] In the first exemplary embodiment, the first semiconductor switch (S1) 112 serves to switch between the magnetization phase 140; 144 (current flow in the left-hand circuit of Fig. 11A and 11B in the positive and negative half-waves, respectively). The second semiconductor switch (S2) 114 serves to switch between the magnetization phase 140 and the demagnetization phase 142 during the positive half-wave (current flow in the right-hand circuit of Fig. 11A). The third semiconductor switch (S3) 116 serves to switch between the magnetization phase 144 and the demagnetization phase 146 during the negative half-wave (current flow in the right-hand circuit of Fig. 11B).
[0102] In the second embodiment of Figs. 11 A and 11 B, alternating current flows through the first inductance 104, and the selectively conductive circuit of the second inductance 302 and third inductance 304 acts as a pole converter, in particular as a rectifier.
[0103] In the second exemplary embodiment of FIGS. 11A and 11B of the flyback converter circuit arrangement 300, current flows through the first measuring resistor 110-1 in the circuit of the first inductance 104 and the alternating current source during each magnetization phase 140; 144. During each demagnetization phase 142; 146, current flows through the second measuring resistor 1102-2 in the circuit of the second inductance 302 during the positive half-wave and the third inductance 304 during the negative half-wave, the electrical load 108, and the capacitor 106. A flyback converter circuit arrangement 300 connected to a direct current source can be selected according to the selection of a half-wave of the first or second exemplary embodiment, for example by using the first semiconductor switch (Si) 112 and the second semiconductor switch (S2) 114 to switch between the magnetization phases.The further semiconductor switch (S3) 116, as well as in the first embodiment the further semiconductor switches (S4) 118, (S5) 202 and (Se) 204 can each be replaced by a fixed circuit arrangement, for example according to the circuit in the positive half-wave of the tables above.
[0104] In the following, each embodiment is described using the buck converter circuit arrangements 100 with a direct current source according to Figs. 7A and 7B and with an alternating current source according to Figs. 8A to 8D.
[0105] In the exemplary embodiment, the buck converter circuit arrangement 100 operates in boundary conduction mode (BCM). The time ton for magnetizing the inductor (L) 104 is kept proportional to the power and is specified by a voltage regulator designed to keep the circuit's output voltage constant, for example, across the electrical load 108.
[0106] The time t O ff for demagnetizing the inductance (L) 104 is set in the exemplary embodiment of the buck converter circuit arrangement 100. For example, a zero current detection signal (ZCD) is generated, which is conventionally caused by the charge reversal process of a diode 12.
[0107] However, in a buck converter circuit arrangement 100 (also: buck converter topology), in which the function of the diode 12 is realized by a semiconductor switch 114, ZCD cannot be generated without a controller 150, since the semiconductor switch 114 does not block automatically. In a preferred embodiment, the time at which the second semiconductor switch 114 is to switch off is determined in advance (for example, before the expiration of a variable time period t Off of the demagnetization phase, at the end of which the second semiconductor switch 114 is switched off) is determined (for example calculated) and the determination (for example calculation) is corrected by measuring and / or controlling (in particular regulating) the current, in particular by means of a measuring resistor 110-1, 110-2 or 110-3 at a fixed point in time within a period each consisting of a magnetization and a demagnetization phase.
[0108] The time period t O ff of the demagnetization phase, in which the first semiconductor switch is open and the second is closed, is conventionally determined according to formula (2).
[0109] Due to tolerances and other factors such as delays in drivers, the conventional determination can lead to a deviation of an actual current value in the inductor (L) 104 from a predetermined current value of an ideal lossless buck converter circuit arrangement 100. Thus, it will be checked which actual current value was reached in the inductor (L) 104 at the end of the demagnetization phase.
[0110] The required current information can be obtained, for example, from the current path of the semiconductor switch (S2) 114 in Figs. 7A and 7B. Using the measuring resistor 110-1, a measuring voltage can be generated that is proportional to the current through the semiconductor switch 114.
[0111] Alternatively or additionally, a current value can be measured during the time period ton of the magnetization phase of the inductance 104 by means of the measuring resistor (for example, referred to as "shunt R1" in Fig. 7A and 7B) 110-2 in the current path of the first semiconductor switch (S1) 112. In the embodiment of Fig. 7A, the semiconductor switch (S1) 112 is switched on during the time period t on During the magnetization phase, it is connected to a positive input voltage n with positive pole 102-1 and negative pole 102-2. The arrangement of the first measuring resistor 110-1 and / or the second measuring resistor 110-2 between the electrical load 108 and the negative pole 102-2 and / or near a ground connected to node 128 can also be referred to as a "low-side path" arrangement.
[0112] Fig. 12 shows an example of a measured current profile through the inductance 104 of the buck converter circuit arrangement 100 of Figs. 7A and 7B at a positive input voltage Vn with temporal control course comprising the fixed time duration (ton) 1202 of the magnetization phase, variable time duration (t O ff) 1204-1 ; 1204-2 ; 1204-3 of the demagnetization phase and the resulting period (T pe riode) 1206-1 ; 1206-2; 1206-3 as well as a corresponding change ( fset) 1208 (also: settling time, time correction and / or actuator of a current controller for correcting the current limit) of the variable time periods.
[0113] The necessary information to be able to regulate the lower current threshold 1214 is contained in the current through a measuring resistor, for example measuring resistor 110-2 in the current path of the first semiconductor switch 112 of Fig. 7A. The current 1210 flows through the first semiconductor switch 112 during the magnetization phase (ton) 1202. The current 1214 at the time at the beginning of the magnetization phase should be constant at a (for example negative) reference value (lp ef) 1218. Therefore, it is advantageous, for example, to measure the current 1210 as close as possible to the switching time from the demagnetization phase to the magnetization phase.
[0114] The solid line h at reference numeral 1210 denotes the current through the first semiconductor switch 112, which in the magnetization phase (ton) 1202 corresponds to the current through the inductance (L) 104. During the demagnetization phase 1204-1; 1204-2; 1204-3, the current IL at reference numeral 1212 flows through the inductance (L) 104 and the second semiconductor switch 114. Leer (t-1) at reference numeral 1216-1 denotes the measured current error two switching cycles ago, and lerr at reference numeral 1216-2 denotes the most recently measured current error.
[0115] The measured (also read) current value 1214 is fed into the controller 150, for example a DSP or microcontroller, to determine the time period t Off of the demagnetization phase and / or the period T pe riode.
[0116] Fig. 13 shows an embodiment of a method for controlling the semiconductor switches 112; 114 of the buck converter circuit arrangement 100 of Figs. 7A and 7B during a magnetization phase and a demagnetization phase of an inductance 104.
[0117] The method can be executed by the control unit 150, for example, comprising a DSP and / or microcontroller. Alternatively or additionally, the method can be referred to as a control structure.
[0118] With the help of the control unit 150, for example a DSP, the information on the input voltage ( n ) 1302 and output voltage (V ou t) 1304, which is connected at reference numeral 1312 to a reference output voltage (V Out_ref) 1306, and a (for example proportional-integral) controller 1318, which sets or determines the time duration ton of the magnetization phase, precalculates a period Tperiode (for example at reference number 1316 and / or added with ton according to formula (2)), with which the current II through the inductance 104 would have to reach the lower current threshold 1218.
[0119] After the end of the period, both semiconductor switches 112 and 114 are off, and shortly afterwards the first semiconductor switch (Si) 112 is switched on again. The measuring resistor 110-2 (also: shunt R1 ) is current-carrying, and directly after the switching of the first semiconductor switch (S1 ) 112, the current value 1214 is measured. If the measured current value 1214 at reference symbol 1314 deviates from the reference current value 1218, a current controller (also: "huik controller" or "h controller" for short) 1320 sets a deviation toffset, which at reference symbol
[0120] 1322 is added to the previously calculated period. The time period T pe The duration of a period at reference numeral 1322 and the time duration ton of the magnetization phase at reference numeral 1324 are fed to a pulse wave modulation (PWM for short) at reference numeral 1326, which controls the semiconductor switches (for example 112 and 114 in the exemplary embodiment of the buck converter circuit arrangement of Figs. 7A and 7B), in particular at high frequency.
[0121] Thus, the current value 1214 approaches the reference current value 1218 at the measurement time of the next period (also: in the next pulse). The current controller 1320 adjusts the current 1214 at the measurement point to the reference current 1218. For example, according to Fig. 12, the lower limit of the (e.g., triangular) inductor current II 1210; 1212 is used as the reference current value 1218.
[0122] The above-described time of measuring the current value 1214 is merely exemplary. The method can be performed at any other point on a current edge, for example, the current edge 1210, by adjusting a determination of the reference current value 1218.
[0123] By choosing a different reference current value, an average current can be controlled, for example.
[0124] For example, the buck converter circuit arrangement 100 can be operated with an average current as a reference current in continuous mode (CCM).
[0125] Alternatively or additionally, a current measurement through the second semiconductor switch (S2) 114 can be used, for example as input value 1214 in the method of Fig. 13, for example by using a current transformer and / or by switching the reference potential, for example the ground shown at node 128 in Fig. 7A and 7B. For example, the (for example triangular) current 1210; 1212 through the inductance 104 can be measured at the measuring resistor 110-1 (also shunt R3). Due to a permanent current conduction, in particular both in the magnetization phase and the demagnetization phase in Fig. 7A and 7B, higher losses can occur when using the measuring resistor 110-1 than when using the measuring resistor 110-2, which is only current-conducting in the magnetization phase of Fig. 7A.
[0126] Fig. 8A to 8D show a generalization of the buck converter circuit 100 for an AC power source, which can also be referred to as a “buck converter as bridgeless PFC topology”.
[0127] In the positive half-wave shown in Figs. 8A and 8B, according to the buck converter circuit 100 of Figs. 7A and 7B, current values can be measured either via the measuring resistor 110-2 during the magnetization phase 140 or via the measuring resistor 110-1 during the entire period. Alternatively or additionally, one or more current values can be measured during the demagnetization phase 142 at a measuring resistor 110-3 in the current path of the second semiconductor switch (S2) 114, or via current transformers (not shown) in the current paths of the first semiconductor switch (S1) 112 and / or the second semiconductor switch (S2) 114.
[0128] The semiconductor switches (S3) 116 and (S4) 118 in Fig. 8A to 8D serve as polarity inverters and are switched on alternately depending on the polarity of the input voltage.
[0129] When the input voltage is positive, the fourth semiconductor switch (S4) 118 is switched on, and the control and functionality of the semiconductor switches (S1) 112 and (S2) 114 behaves as described for the positive DC source.
[0130] With a negative input voltage, the fourth semiconductor switch (S4) 118 is turned off, and the third semiconductor switch (S3) 116 is turned on. The second semiconductor switch (S2) 114 is then turned on to magnetize the inductor 114 at reference numeral 144, and the semiconductor switch (S1) 112 is turned on for the demagnetization phase 146.
[0131] The current direction through the measuring resistor 110-2 (also: shunt R1) is reversed at a negative input voltage compared to the current direction at a positive input voltage. A fixed measurement time does not need to change in this case (for example, compared to a positive DC source). The current measured through the measuring resistor 110-2 (also: shunt R1) indicates the current through the inductance during the magnetization phase 140 of the positive half-wave in Fig. 8A and / or the magnetization phase 144 of the negative half-wave in Fig. 8C.
[0132] A reference potential (English: “ground”, abbreviated: GND) can be applied to the negative contact to the supply voltage in the buck converter circuit arrangement 100 of Fig. 8A to 8D, which can describe, for example, the neutral conductor.
[0133] To utilize the typically less noisy potential of the measuring resistor 110-1 (also known as shunt R3) and the capacitance 106, the current information via the measuring resistor 110-1 (also known as shunt R3) can also be used. A potential disadvantage of measuring the current via the measuring resistor 110-1 is that the four semiconductor switches (Si, S2, S3, and S4) 112, 114, 116, and 118 must all be controlled in a potential-isolated manner. Therefore, the circuit complexity is lower with the reference potential shown near the measuring resistor 110-3 (also known as shunt R4).
[0134] When using the current information from the measuring resistor 110-3 (also shunt R4), the time of the measurement depends on the polarity. The second semiconductor switch (S2) 114 carries the demagnetization current 142 when the input voltage is positive and the magnetization current 144 when the input voltage is negative. The current direction through the measuring resistor 110-3 (also: shunt R4) is independent of the polarity of the supply voltage. The method for controlling the semiconductor switches of a circuit arrangement during a magnetization phase and a demagnetization phase of an inductor 104 can be used for other circuit arrangements, for example the boost-buck converter and flyback converter circuit arrangements 200 and 300, respectively, of Figs. 9A to 9H, Figs. 10A and 10B, and Figs. 11A and 11B.
[0135] For each circuit arrangement 100; 200; 200, a variable time period, for example t Off of the demagnetization phase, adjusted (also: corrected). The method is particularly suitable for circuit arrangements (also: topologies) 100; 200; 300 that can be switched quasi-resonantly. The method can be used, for example, in flyback converter circuit arrangements 300, in particular with a pole converter (for example a rectifier or synchronous rectifier), in boost-buck converter circuit arrangements 200 with a second semiconductor switch (S2) 114 instead of a diode, in buck converter circuit arrangements 100 as described here, and in boost converter circuit arrangements (English: "boost converter" or "step-up converter").
[0136] The control of the boost-buck converter circuit arrangement 200 as a boost converter circuit arrangement with a direct current source and / or alternating current source can also be applied to the circuit diagrams of the German patent applications 102020117180.3 "Boost converter for a power supply of an electrical load and power supply and method for boosting the input voltage in a power supply of an electrical load", 102020 120 530.9 "Boost converter circuit arrangement, power supply and method for converting an input voltage out" and 102020126471.2 "Boost converter circuit arrangement, power supply and method for converting an input voltage out". As can be seen from the above exemplary embodiments, low-loss switching of the semiconductor switches with a stable, for example, negative, current component can be achieved by the switch arrangements 100; 200 and 300 according to the invention.In particular, the duration of a magnetization phase can be fixed, and the duration of a demagnetization phase can be varied depending on the, for example, negative, current component. In particular, the, for example, negative, current component can be measured across a measuring resistor at one or a few predetermined times during a period comprising a magnetization and demagnetization phase.
[0137] Although the invention has been described with reference to exemplary embodiments, it will be apparent to those skilled in the art that various changes may be made and equivalents may be substituted. Furthermore, many modifications may be made to adapt a particular situation or material to the teachings of the invention. Consequently, the invention is not limited to the disclosed embodiments, but includes all embodiments falling within the scope of the appended claims.
[0138] List of reference symbols
[0139] Conventional buck converter circuit arrangement 10
[0140] Diode 12
[0141] Buck converter circuit arrangement 100
[0142] First pole of the power source 102-1
[0143] Second pole of the power source 102-2
[0144] Inductance 104
[0145] Capacity 106
[0146] Load / electrical consumer 108
[0147] Current measuring point, optional measuring resistor or shunt 110-1; 110-2; 110-3
[0148] First semiconductor switch (Si) 112
[0149] Second semiconductor switch (S2) 114
[0150] Third semiconductor switch (S3) 116
[0151] Fourth semiconductor switch (S4) 118
[0152] First junction 122
[0153] Second junction 124
[0154] Third junction 126
[0155] Fourth junction 128
[0156] Fifth junction 130
[0157] Sixth junction 132
[0158] Current path, positive half-wave, magnetization phase 140
[0159] Current path, positive half-wave, demagnetization phase 142
[0160] Current path, negative half-wave, magnetization phase 144 Current path, negative half-wave, demagnetization phase 146 Control unit 150
[0161] Boost-buck converter circuit arrangement 200
[0162] Fifth semiconductor switch (S5) 202
[0163] Sixth semiconductor switch (Se) 204
[0164] Flyback converter circuit arrangement 300
[0165] Second inductance 302
[0166] Third inductance 304
[0167] Fixed duration ton of the magnetization phase 1202 Variable duration t O ff of the demagnification phase 1204-1; 1204-2; 1204-3 period T pe Riode 1206-1 ; 1206-2 ; 1206-3
[0168] Change toffset from toff, Tperiod 1208
[0169] Current through first semiconductor switch (Si) 1210
[0170] Current through second semiconductor switch (S2) 1212
[0171] Measured lower current value 1214
[0172] Deviation of the lower current value from the reference current value 1216-1 ; 1216-2
[0173] Reference current value 1218
[0174] Input voltage (Vin) 1302
[0175] Output voltage (Vout) 1304
[0176] Reference output voltage (V ou t_ref) 1306
[0177] Comparison of voltage values 1312
[0178] Comparison of current values 1314
[0179] Equation 1316
[0180] Proportional-integral controller (PI controller) 1318
[0181] Current regulator 1320
[0182] Timer (or timer) of period 1322
[0183] Timer (or timer) of the magnetization phase 1324
[0184] PWM output 1326
Claims
39 Patent claims 1. Buck converter circuit arrangement (100) for supplying power to an electrical load (108), comprising: an inductor (104) connected between a first node (122) and a second node (124); a capacitor (106) connected between the second node (124) and a third node (126); a DC voltage output connected in parallel to the capacitor (106) between the second node (124) and the third node (126) for connecting the load (108); an input unit for connecting a current source (102) supplying the buck converter circuit arrangement (100), wherein the input unit has a first pole (102-1) which acts as a positive pole at least during one positive half-cycle, and a second pole (102-2) which acts as a negative pole at least during the positive half-cycle;a first semiconductor switch (112) arranged to selectively connect the first pole (102-1) to the first node (122); a second semiconductor switch (114) arranged to selectively connect the first node (122) and the third node (126) via a fourth node (128); at least one current measuring point (110-1; 110-2; 110-3) arranged in a current path comprising the first node (122), the second node (124) and the third node (126) downstream of the third node (126); and a control unit (150) configured to conduct the first semiconductor switch (112) during a defined time period, ton, a magnetization phase of the inductance (104) at least during the positive half-cycle and during a variable time period, t; O ff, one 40 to switch the second semiconductor switch (114) to non-conducting at least during the positive half-wave of the demagnetization phase of the inductor (104), and to switch it to non-conducting at least during the positive half-wave of the magnetization phase of the inductor (104) and during the variable time period, t O ff, to switch the inductor (104) to conducting at least during the positive half-wave during the demagnetization phase; wherein the specified time period, t on , the magnetization phase of the inductor (104) is determined as a function of a predetermined maximum current through the inductor (104); and wherein the variable time period, t O ff, the demagnetization phase of the inductance (104) can be changed depending on a comparison of a given minimum current through the inductance (104) and a current measurable across the at least one current measuring point (110-1 ; 110-2; 110-3).
2. Buck converter circuit arrangement (100) according to claim 1, wherein the current source (102) supplying the input unit comprises an alternating current source, wherein the first pole (102-1) acts as the negative pole in a negative half-wave, and the second pole (102-2) acts as the positive pole in the negative half-wave; wherein the buck converter circuit arrangement (100) further comprises a third semiconductor switch (116) selectively connecting the fourth node (128) to the first pole (102-1) via a fifth node (130), and a fourth semiconductor switch (118) selectively connecting the fourth node (128) to the second pole (102-2) via the fifth node (130); wherein the control unit (150) is configured to switch the third semiconductor switch (116) to non-conducting and the fourth semiconductor switch (118) to conducting during the positive half-wave; 41 wherein the control unit (150) is configured to switch the third semiconductor switch (116) conducting and the fourth semiconductor switch (118) non-conducting during the negative half-wave; wherein the control unit (150) is configured to switch the first semiconductor switch (112) non-conducting and the second semiconductor switch (114) conducting during the fixed time period, ton, of the magnetization phase in the negative half-wave; and wherein the control unit (150) is configured to switch during the variable time period, t Off, during the demagnetization phase in the negative half-wave, to switch the first semiconductor switch (112) conducting and the second semiconductor switch (114) non-conducting. Buck converter circuit arrangement (200) for supplying power to an electrical load, comprising: an inductor (104) connected between a first node (122) and a second node (124); a capacitor connected between a third node (126) and a fourth node (128); a DC voltage output connected in parallel to the capacitor (106) between the third node (126) and the fourth node (128) for connecting the load (108);an input unit for connecting a current source (102) supplying the boost converter circuit arrangement (200), wherein the input unit has a first pole (102-1) which acts as a positive pole at least in one positive half-wave, and a second pole (102-2) which acts as a negative pole at least in one positive half-wave; a first semiconductor switch (112) which is arranged to selectively connect the first pole (102-1) to the first node (122); a second semiconductor switch (114) which is arranged to selectively connect the first node (122) and the fourth node (128) via a fifth node (130) and a sixth node (132); a third semiconductor switch (116) arranged to selectively connect the second node (124) and the third node (126); a fourth semiconductor switch (118) arranged to selectively connect the second node (124) and the fifth node (130); at least one current measuring point (110-1; 110-2) arranged in a current path comprising the fourth node (128) and the fifth node (130) and / or the fourth semiconductor switch (118) and the fifth node (130); and a control unit (150) configured to act as a buck converter of the buck converter circuit arrangement (200), conducting the first semiconductor switch (112) for a defined period, ton, during a magnetization phase of the inductor (104) at least in the positive half-wave and for a variable period, t Off, to switch the second semiconductor switch (114) to non-conducting at least in the positive half-wave during a demagnetization phase of the inductance (104), in its function as a buck converter for the specified time period, t on , the magnetization phase of the inductor (104) is non-conducting at least in the positive half-wave and during the variable time period, t Off, to switch the demagnetization phase of the inductor (104) to conducting at least in the positive half-wave, in the function as a buck converter to switch the third semiconductor switch (116) to conducting and the fourth semiconductor switch (118) to non-conducting; wherein the control unit (150) in a function as a boost converter of the buck-boost converter circuit arrangement (200) is further configured to switch the first semiconductor switch (112) to conducting and the second semiconductor switch (114) to non-conducting at least in a positive half-wave, wherein the control unit (150) in the function as a boost converter is further configured to switch the fourth semiconductor switch (118) during the specified time period, t on , the magnetization phase of the inductor (104) is conducting at least in the positive half-wave and during the variable time period, t Off, to switch the third semiconductor switch (116) non-conducting at least in the positive half-wave during the demagnetization phase of the inductor (104), and in its function as a boost converter, to switch the third semiconductor switch (116) non-conducting during the fixed time period, ton, during the magnetization phase of the inductor (104) at least in the positive half-wave and during the variable time period, t O ff, to switch the inductor (104) to conducting at least during the positive half-wave during the demagnetization phase; wherein the specified time period, t on , the magnetization phase of the inductor (104) is determined as a function of a predetermined maximum current through the inductor (104); and wherein the variable time period, t Off, the demagnetization phase of the inductance (104) can be changed depending on a comparison of a given minimum current through the inductance (104) and a current measurable across the at least one current measuring point (110-1 ; 110-2; 110-3).A boost-bubble converter circuit arrangement (200) according to claim 3, wherein the current source (102) supplying the input unit comprises an alternating current source, wherein the first pole (102-1) acts as the negative pole in a negative half-wave, and wherein the second pole (102-2) acts as the positive pole in the negative half-wave; wherein the boost-bubble converter circuit arrangement (200) further comprises a fifth semiconductor switch (202) selectively connecting the sixth node (132) to the first pole (102-1), and a sixth semiconductor switch (204) selectively connecting the sixth node (132) to the second pole (102-2); wherein the control unit (150) is configured to switch the fifth semiconductor switch (202) non-conductively and the sixth semiconductor switch (204) conductively during the positive half-wave; 44 wherein the control unit (150) is configured to switch the fifth semiconductor switch (202) conducting and the sixth semiconductor switch (204) non-conducting during the negative half-wave; wherein the control unit (150) is configured, in its function as a buck converter, to switch the first semiconductor switch (112) non-conducting and the second semiconductor switch (114) conducting during the fixed time period, ton, of the magnetization phase in the negative half-wave; wherein the control unit (150) is configured, in its function as a buck converter, to switch the first semiconductor switch (112) non-conducting and the second semiconductor switch (114) conducting during the variable time period, t O ff, during the demagnetization phase in the negative half-wave, to switch the first semiconductor switch (112) conducting and the second semiconductor switch (114) non-conducting; wherein the control unit (150) is configured to function as a boost converter during the specified time period, t on, during the magnetization phase in the negative half-wave, to switch the first semiconductor switch (112) non-conductive and the second semiconductor switch (114) conductive; and wherein the control unit (150) is configured to switch the first semiconductor switch (112) non-conductive and the second semiconductor switch (114) conductive in the negative half-wave, acting as a boost converter. Flyback converter circuit arrangement (300) for supplying power to an electrical load, comprising: a first inductor (104) and a second inductor (302), wherein the first inductor (104) and the second inductor (302) are inductively coupled, wherein the first inductor (104) and the second inductor (302) are galvanically isolated, and wherein the second inductor (302) is connected to a first node (112); a capacity (106) connected between the first node (122) and a second node (124); 45 a DC voltage output connected in parallel to the capacitor (106) between the first node (122) and the second node (124) for connecting the load (108); an input unit for connecting a current source (102) supplying the flyback converter circuit arrangement (300), wherein the input unit has a first pole (102-1) which acts as a positive pole at least during one positive half-cycle, and a second pole (102-2) which acts as a negative pole at least during one positive half-cycle; a first semiconductor switch (112) which is arranged to selectively connect the first inductor (104) to the second pole (102-2) at least during one positive half-cycle; a second semiconductor switch (114) which is arranged between the second node (124) and the second inductor (302) to selectively connect the second inductor (302) and the capacitor (106); at least one electricity metering point (110-1 ;110-2), which is arranged in a current path comprising the first semiconductor switch (112) and the current source (102) and / or in a current path comprising the second node (124) and second semiconductor switch (114); and a control unit (150) configured to conduct the first semiconductor switch (112) for a fixed time period, ton, a magnetization phase of the first inductor (104) and the second inductor (302) and for a variable time period, t; O ff, to switch the first inductor (104) and the second inductor (302) to a non-conducting phase of demagnetization, and the second semiconductor switch (114) during the specified time period, t on , the magnetization phase of the first inductor (104) and the second inductor (302) is non-conducting at least in the positive half-wave and during the variable time period, t Off, to switch the first inductor (104) and the second inductor (302) to conducting at least during the positive half-wave during the demagnetization phase; 46 wherein the fixed duration, ton, of the magnetization phase of the inductor (104) is determined as a function of a predetermined maximum current through the inductor (104); and wherein the variable duration, t OThe demagnetization phase of the inductor (104) can be varied depending on a comparison of a predetermined minimum current through the inductor (104) and a current measurable across the at least one current measuring point (110-1; 110-2; 110-3). Flyback converter circuit arrangement (300) according to claim 5, wherein the current source (102) supplying the input unit comprises an alternating current source, wherein the first pole (102-1) acts as the negative pole in a negative half-wave, and the second pole (102-2) acts as the positive pole in the negative half-wave;wherein the flyback converter circuit arrangement (300) further comprises a third semiconductor switch (116), a fourth semiconductor switch (118), a fifth semiconductor switch (202) and a sixth semiconductor switch (204), wherein the third semiconductor switch (126) is configured to selectively connect the first inductor (104) to the first pole (102-1 ), wherein the fourth semiconductor switch (118) is configured to selectively connect the first inductor (104) to the second pole (102-2), wherein the fifth semiconductor switch (130) is configured to selectively connect the first semiconductor switch (112) to the second pole (102-2), and wherein the sixth semiconductor switch (132) is arranged to selectively connect the first semiconductor switch (112) to the first pole (102-1 );wherein the control unit (150) is configured to conduct the third semiconductor switch (116) and the fifth semiconductor switch (202) respectively during the fixed time period, ton, the magnetization phase in the positive half-wave and during the variable time period, t; O ff, to switch the demagnetization phase of the positive half-wave to non-conductive operation, and the third semiconductor switch (116) and the fifth 47 The control unit (150) is further configured to switch the fourth semiconductor switch (118) and the sixth semiconductor switch (202) to a non-conductive state during the positive half-wave, and to switch the fourth semiconductor switch (118) and the sixth semiconductor switch (204) to a conductive state during the fixed time period, ton, of the magnetization phase in the negative half-wave and during the variable time period, tOff, to switch to non-conductive operation during the demagnetization phase of the negative half-wave. Flyback converter circuit arrangement (300) according to claim 5, wherein the current source (102) supplying the input unit comprises an alternating current source, wherein the first pole (102-1) acts as the negative pole in a negative half-wave, and the second pole (102-2) acts as the positive pole in the negative half-wave; wherein the flyback converter circuit arrangement (300) further comprises a third inductor (304) and a third semiconductor switch (116), wherein the third semiconductor switch (116) is configured to selectively connect the third inductor (304) to the first node (122) and the second node (124); wherein the control unit (150) is configured to switch the second semiconductor switch (114) to non-conductive operation during the negative half-wave;wherein the control unit (150) is configured to make the third semiconductor switch (116) non-conducting during the positive half-wave and during the fixed time period, ton, the magnetization phase of at least the first inductor (104) in the negative half-wave and during the variable time period, t; O ff, to switch the demagnetization phase of at least the first inductance (104) of the negative half-wave to conducting. 48 Circuit arrangement (100; 200; 300) according to any one of claims 1 to 7, wherein one or each of the semiconductor switches (112; 114; 116; 118; 202; 204) comprises a MOSFET, in particular an n-channel MOSFET; a bipolar transistor; a thyristor and / or an insulated-gate bipolar transistor, IGBT. Circuit arrangement (100; 200; 300) according to any one of claims 1 to 8, wherein the control unit (150) is further configured to operate the circuit arrangement in at least one of continuous continuous operation (CCM); discontinuous continuous operation (DCM); and at a boundary between continuous and discontinuous operation (BCM). Circuit arrangement (100; 200; 300) according to one of claims 1 to 9, wherein the at least one current measuring point (110-1 ; 110-2; 110-3) comprises at least one measuring resistor (110-1 ; 110-2; 110-3) or at least one Hall sensor or at least one inductive current transformer.Circuit arrangement (100; 200; 300) according to any one of claims 1 to 10, wherein the at least one current measuring point (110-1; 110-2; 110-3) is arranged in the current path of the first semiconductor switch (112), and wherein the control unit (150) is further configured to measure at least one current value during the magnetization phase in the positive half-wave and / or in the negative half-wave across the at least one current measuring point (110-1; 110-2; 110-3). Circuit arrangement (100; 200; 300) according to claim 11, wherein the at least one current value comprises exactly one current value at a defined time point during the magnetization phase, preferably at the beginning of the magnetization phase and / or near a switching point from the non-conductive to the conductive state of the first semiconductor switch (112). 49 Circuit arrangement (100; 200; 300) according to one of claims 1 to 12, wherein the at least one current measuring point (110-1 ; 110-2; 110-3) is arranged in the current path of the second semiconductor switch (114), and wherein the control unit (150) is further configured to measure at least one current value during the demagnetization phase in the positive half-wave and / or in the negative half-wave across the at least one current measuring point (110-1 ; 110-2; 110-3). Circuit arrangement (100; 200; 300) according to one of claims 1 to 13, wherein the control unit (150) is further configured to switch at least one or each semiconductor switch (112; 114; 116; 118; 202; 204) in a conducting state in a voltage-free state and / or in a current-free state of the inductor (104).Circuit arrangement (100; 200; 300) according to any one of claims 1 to 14, wherein the control unit (150) comprises at least one digital signal processor (DSP); a microcontroller with control software; a field-programmable gate array (FPGA); and an application-specific integrated circuit (ASIC). The circuit arrangement (100; 200; 300) is designed for controlling the semiconductor switches of a circuit arrangement (100; 200; 300) during a magnetization phase and a demagnetization phase of an inductor (104), comprising: Measuring a current value across at least one current measuring point (110-1; 110-2; 110-3) of one of the circuit arrangements (100; 200; 300) of claims 1 to 14, wherein the current value during a defined point in time of a period comprising a defined time duration, ton, a magnetization phase and a variable time duration, t O ff, a demagnetization phase of an inductor (104; 302; 304) is measured, where the specified time period, ton , the magnetization phase of the inductor (104) is determined as a function of a predetermined maximum current through the inductor (104); 50 Comparing the measured current value with a reference current value defined for the time of measurement; and Changing the variable duration, t O ff, the demagnetization phase of the inductance (104) as a function of a result of comparing the measured current value with the reference current value.