Neutral loss detection
A voltage-based method for detecting neutral connection breaks in electrical networks addresses reliability and cost issues by using phase voltage measurements and predefined criteria, ensuring accurate and efficient detection.
Patent Information
- Application Number
- FR2022006489
- Authority / Receiving Office
- FR · FR
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2022-06-28
- Publication Date
- 2024-10-04
- Estimated Expiration
- 2042-06-28
AI Technical Summary
Existing methods for detecting a break in the neutral connection in a three-phase electrical distribution network are unreliable and costly, often failing to distinguish between neutral and phase breakdowns, and require additional sensors, leading to inefficiencies and potential damage to subscriber electrical installations.
A method using voltage sensors to measure phase voltages and evaluate ratios and balancing quantities to detect a neutral connection break, relying on simple voltage measurements without additional sensors, and employing predefined criteria to confirm the break.
The method provides reliable and cost-effective detection of neutral connection breaks, reducing the risk of misidentification and infrastructure damage by directly analyzing phase voltage imbalances.
Smart Images

Figure 00000022_0000 
Figure 00000023_0000 
Figure 00000032_0000
Abstract
Description
Title of the invention: Neutral loss detection
[0001] The invention relates to the field of electrical energy distribution networks and equipment which is connected to said networks.
[0002] BACKGROUND OF THE INVENTION
[0003] An electrical distribution network allows electrical energy to be transported from an electrical production unit to one or more subscriber electrical installations. The transmission of electrical energy is generally carried out in three-phase, the electrical network then consisting of three phase conductors and a neutral conductor. An electrical network is also typically equipped with a plurality of electrical meters which allow the electrical energy consumption of the subscriber electrical installations to be measured.
[0004] In a three-phase electrical network, it is possible for a break in the neutral connection to occur upstream of one or more meters. Such a break is the responsibility of the energy supplier in charge of the network and can in particular cause significant problems at the level of the subscriber electrical installations. Indeed, depending on the load impedances of the subscriber electrical installations (downstream of the neutral break point), a significant imbalance of the phase voltages carried by the three phase conductors can occur. It is therefore possible for significant voltages to appear at the level of the subscriber electrical installations, which can possibly destroy said installations.
[0005] It is therefore important to be able to reliably, simply and quickly detect a sudden break in the neutral connection in a three-phase electrical distribution network. This allows preventive and / or protective measures to be taken quickly for the subscriber electrical installations.
[0006] Conventionally, the detection of a break in a neutral connection is based on the detection of an abnormal imbalance between the phase voltages of the distribution network and / or an absence of current flowing on the neutral conductor. However, this method generally proves to be unreliable because it does not allow for correct identification of whether the observed imbalance is linked to a break in the neutral or to a break in one or more phases. In addition, the detection of the absence of current through the neutral conductor requires the use of current sensors positioned on said neutral conductor, which has the consequence of increasing costs and posing physical and electrical implementation problems.
[0007] It is also known, to detect a break in the neutral connection, to measure the downstream load impedances (of the subscriber electrical installations) in order to determine the expected phase voltage imbalance in the event of a break in the neutral connection (and therefore to detect it when said imbalance actually occurs). However, the effectiveness and reliability of this method are directly linked to the reliability of the measurements of the downstream load impedances. This is a limiting factor because the determination of the expected imbalance between the phase voltages typically uses a theoretical analysis for which the downstream load impedances are considered to be linear and constant over time (which is not necessarily the case in reality). Furthermore, in the case where the neutral break affects several electricity meters each having distinct (uncorrelated) and unbalanced downstream load impedances, then the method described above no longer allows the neutral connection break to be detected. Indeed, for a given meter the measured downstream load impedance only considers the electrical installations downstream of said meter.However, the imbalance between the phase voltages is linked to the equivalent downstream load impedance resulting from the combination of all the downstream load impedances of all the meters affected by the break in the neutral connection. Since the equivalent load impedance cannot be measured, the method described above is no longer applicable in this case.
[0008] SUBJECT OF THE INVENTION
[0009] The object of the invention is to enable the detection, in an electrical distribution network, of a break in the connection of a neutral upstream of one or more electrical meters in a rapid, simple and reliable manner. Summary of the invention
[0010] With a view to achieving this object, a method is proposed for detecting a break in the connection of a neutral of a three-phase electrical network, the detection method being implemented at least partially in a processing unit of electrical equipment connected to the electrical network, and comprising the steps, repeated regularly, of: • acquire, at a time T, a first phase voltage measured between a first phase of the three-phase electrical network and the neutral, a second phase voltage measured between a second phase and the neutral, and a third phase voltage measured between a third phase and the neutral, the first, second and third phase voltages being measured by voltage sensors of the electrical equipment; • evaluate a first quantity representative of a ratio between a maximum phase voltage and a minimum phase voltage among the first, second and third phase voltages; • if the first quantity is greater than a predetermined threshold, then: • evaluate, from the first, second and third phase voltages, at least one second quantity representative of a current balancing of said first, second and third phase voltages with each other; • detect a break in the neutral connection at time T when at least one second quantity verifies a predetermined reference criterion.
[0011] The detection method according to the invention is therefore particularly advantageous because it makes it possible to detect a break in the connection of a neutral in a distribution network (upstream of an electricity meter) from the simple measurement of the phase voltages carried by the phase conductors of said network. The detection method is therefore simple to implement (because it only requires voltage sensors) and inexpensive.
[0012] Furthermore, the detection method according to the invention is also highly reliable because, when a suspicion of a break in the neutral is established (i.e. when the first quantity is greater than the predetermined threshold) then the second quantity is evaluated and makes it possible to confirm without any possible doubt that a break in the neutral connection has indeed occurred.
[0013] Knowing that the second quantity is directly evaluated on the basis of the phase voltages (and therefore does not require the acquisition of additional measurements), the detection method according to the invention can quickly detect a break in the neutral connection.
[0014] A detection method is further proposed as previously described, in which the at least one second quantity comprises a second quantity which is a function of a sum of two-by-two products of effective values of the first, second and third phase voltages.
[0015] We further propose a detection method as previously described, in which said second quantity G2 is equal to: G2 =
[0016] where Vieff, V2eff and V3eff are respectively an effective value of the first phase voltage, an effective value of the second phase voltage and an effective value of the third phase voltage,
[0017] the predetermined reference criterion being that: Bornelnf < G2 < BorneSup.
[0018] We further propose a detection method as previously described, further comprising the steps of:
[0019] - detect if:
[0020]
[0021]
[0022]
[0023]
[0024]
[0025]
[0026]
[0027]
[0028]
[0029]
[0030]
[0031]
[0032] V, - y and , = V and Vî = V v le fjv nom cl v 2ejj K nom cl v 3ejj y nom, where Vnom is the nominal effective value of the phase voltage of the electrical network; - if this condition is met, define Borneln f and BorneSup as follows: Bornelnf = Vmjm and BorneSup = Vnom We further propose a detection method as previously described, in which, if said condition is not met, and if: V leff = ■ y name and V 2e ff = a2 ' y name and V^ff = «3 ' y name, where, ab a2 and a3 are real coefficients such that Æj Ch Cl^ then: Bomeinf — minÇBl, B2, B3, B4, B5, B6) and BomSup = max ( Bl, B2, B3, B4, B5, B6 ), where Further provided is a detection method as previously described, wherein the at least one second quantity comprises a second quantity which is a function of an area of an effective triangle formed by the first, second and third phase voltages in the Fresnel representation. We further propose a detection method as previously described, in which the area of the effective triangle is determined using the formula: A = i(VieffV2t^ wsin^ ™ A ««la second quantity, Vieff, V2eff and V3eff are respectively the effective values of the first, second and third phase voltages, and q>i2 is a first phase shift between the first phase voltage and the second phase voltage, <p23est un deuxième déphasage entre la deuxième tension de phase et la troisième tension de phase et <p3i est un troisième déphasage entre la troisième tension de phase et la première tension de phase, the reference criterion then being that the second quantity is such that: Aref ~ £ 1 - - ^ref + £ ]
[0033] where Aref is an area of a reference triangle and Ei is a first predetermined measurement uncertainty.
[0034] A detection method is further proposed as previously described, in which, if the first, second and third phase voltages are perfectly balanced with each other, the value of the predetermined reference triangle is evaluated in using the formula: 3v3 , where Aref is Doing reference triangle and Vnom ^ref 4 " name- is the nominal effective value of the phase voltage of the electrical network.
[0035] A detection method is further proposed as previously described, in which the at least one second quantity comprises second quantities which comprise a first compound voltage U12 representative of a difference between the first phase voltage and the second phase voltage, a second compound voltage U2j representative of a difference between the second phase voltage and the third phase voltage and a third compound voltage U3i representative of a difference between the third phase voltage and the first phase voltage, the reference criterion then being that: ^*1 - ~ ^12 ~ + ^2 and ^*2 ~ ®2 ~ 23 ~ ^2 and ^3 - ë2 — ^3 i ^3 ^2» where ¢1, ¢2 and ¢3 are reference values of the first, second and third phase-to-phase voltages measured in operation at a reference time To preceding time T and e2 is a second predetermined measurement uncertainty.
[0036] A detection method is further proposed as previously described, in which the at least one second quantity comprises second quantities which comprise a first phase shift between the first phase voltage and the second phase voltage, a second phase shift between the second phase voltage and the third phase voltage and a third phase shift between the third phase voltage and the first phase voltage, the predetermined reference criterion then being that the first, second and third phase shifts are each unaffected and different by 120 degrees.
[0037] A detection method is further proposed as previously described, further comprising the step of detecting a break in the neutral connection when it has been detected that the second quantity verifies the predetermined reference criterion a predetermined number of times, corresponding to consecutive verifications spaced two by two in time by a predetermined duration.
[0038] A detection method as previously described is further proposed, in which, when a break in the neutral connection has been detected, the method further comprises the step of generating an alarm signal which can be time-stamped in a memory of the electrical equipment and / or which can be transmitted to equipment external to said electrical equipment.
[0039] Electrical equipment is further proposed comprising voltage sensors and a processing unit arranged to implement the detection method as previously described.
[0040] Electrical equipment as previously described is further provided, the electrical equipment being an electric meter.
[0041] A computer program is further provided comprising instructions which cause the electrical equipment as previously described to execute the steps of the detection method as previously described.
[0042] A computer-readable recording medium is further provided, on which the computer program as previously described is recorded.
[0043] The invention will be better understood in light of the following description of particular non-limiting embodiments of the invention. Brief description of the drawings
[0044] Reference will be made to the attached drawings, among which:
[0045] [Fig-1] [Fig.l] represents a three-phase electrical distribution network;
[0046] [Fig.2] [Fig.2] represents a Fresnel diagram of the phase voltages of the distribution network shown in [Fig.l] under nominal conditions;
[0047] [Fig.3] [Fig.3] represents an electronic architecture of the voltage sensors of an electric meter of the distribution network illustrated in [Fig.l];
[0048] [Fig.4] [Fig.4] represents the influence of a break in the connection of a neutral on the phase voltages of the distribution network illustrated in [Fig.l];
[0049] [Fig.5] [Fig.5] represents the influence of a break in the connection of a neutral on the phase voltages of the distribution network illustrated in [Fig.l] in the Fresnel representation;
[0050] [Fig.6] [Fig.6] represents the steps of the method for detecting a rupture of the connection of a neutral according to the invention. DETAILED DESCRIPTION OF THE INVENTION
[0051] With reference to [Fig.l], an electrical distribution network 1 is presented. The distribution network 1 makes it possible to transport electrical energy from an electrical production unit 2 to one or more electrical installations, here a first electrical installation 3 and a second electrical installation 4.
[0052] The distribution network 1 is a three-phase electrical network which comprises a first phase conductor 5A, a second phase conductor 5B, a third phase conductor 5C and a neutral conductor 6. To simplify the description, the term “conductor” will subsequently be omitted to simply refer to a first phase 5A, a second phase 5B, a third phase 5C and a neutral 6.
[0053] The distribution network 1 carries a first phase voltage Vi between the first phase 5A and the neutral 6, a second phase voltage V2 between the second phase 5B and the neutral 6 and a third phase voltage V3 between the third phase 5C and the neutral 6. The first, second and third phase voltages Vp V2, V3 are alternating (sinusoidal) voltages having a frequency of 50Hz.
[0054] With reference to [Fig.2], the first phase voltage Vp, the second phase voltage V2 and the third phase voltage V3 are shown in the Fresnel representation when the distribution network 1 is in operation under nominal conditions.
[0055] The effective value of the first phase voltage Vpff, the effective value of the second phase voltage V2eff and the effective value of the third phase voltage V3eff are all equal to the nominal effective value of the phase voltage, denoted Vnom, and which is equal to 230V.
[0056] Furthermore, the first, second and third phase voltages Vp V2, V3 are each out of phase with respect to each other. Thus, a first phase shift q>i2 is present between the vector representation of the first phase voltage Vi and that of the second phase voltage V2, a second phase shift q>23 is present between the vector representation of the second phase voltage V2 and that of the third phase voltage V3 and a third phase shift <p3i est présent entre la représentation vectorielle de la troisième tension de phase V3 et celle de la première tension de phase Vp Le premier déphasage q> i2, the second phase shift q>23 and the third phase shift <p3isont tous égaux à 120°.
[0057] [Fig.3] also highlights a first compound voltage Ui2 which corresponds to a difference between the first phase voltage Vi and the second phase voltage V2, a second compound voltage U23 which corresponds to a difference between the second phase voltage V2 and the third phase voltage V3 and a third compound voltage U3i which corresponds to a difference between the third phase voltage V3 and the first phase voltage Vp
[0058] Again with reference to [Fig. 1], a first meter 7 is connected to the distribution network 1 between the production unit 2 and the first installation 3. The first meter 7 is intended to measure a consumption of electrical energy supplied to the first installation 3 via the distribution network 1. The first installation 3 is here represented by a first electrical impedance Zi connected between the first phase 5A and the neutral 6, by a second electrical impedance Z2 connected between the second phase 5B and the neutral 6 and by a third electrical impedance connected between the third phase 5C and the neutral 6. Thus, in operation under nominal conditions, the first impedance Zi presents the first phase voltage Vi at its terminals, the second impedance Z2 presents the second phase voltage V2 at its terminals and the third impedance Z3 presents the third phase voltage V3 at its terminals.
[0059] A second meter 8 is also connected to the distribution network between the production unit 2 and the second installation 4. The second meter 8 is intended to measure a consumption of electrical energy supplied to the second installation 4 via the distribution network 1.
[0060] The first counter 7 and the second counter 8 are three-phase counters.
[0061] The architecture of the first counter 7 is now described.
[0062] The first counter 7 firstly comprises a processing unit 7A which comprises at least one processing component which may be a digital signal processor or DSP (in English, Digital Signal Processor), a processor, a microcontroller, an FPGA (in English, Field Programmable Gate Array) or even an ASIC (in English, Application-Specific Integrated Circuit).
[0063] The first counter 7 further comprises a memory 7B connected to the processing unit 7A or integrated in the processing unit 7A. The memory 7B forms a computer-readable recording medium, on which is recorded at least one computer program comprising instructions making it possible to implement at least partially the detection method which will be described.
[0064] The first meter 7 further comprises a communication module 7C connected to the processing unit 7A and which is arranged to transmit data according to PLC (for Power Line Carrier) technology. It should be noted that other communication standards could be used, for example, cellular radio technology.
[0065] The first meter 7 further comprises voltage sensors 7D connected to the processing unit 7A and which are arranged to measure the first phase voltage Vi, the second phase voltage V2 and the third phase voltage V3 of the distribution network 1.
[0066] With reference to [Fig.3], the voltage sensors 7D of the first counter 7 are described more precisely.
[0067] The voltage sensors 7D comprise a first branch 10, a second branch 11 and a third branch 12.
[0068] The voltage sensors further comprise a first analog-to-digital converter 13, a second analog-to-digital converter 14 and a third analog-to-digital converter 15. In the following, to simplify the description, the first CAN 13, the second CAN 14 and the third CAN 15 will be discussed.
[0069] The first branch 10 comprises two first resistors R[A, Rib- The first resistor RiA has a first terminal 10A connected to the first phase 5A and a second terminal 10B connected to an input 13A of the first CAN 13. The first resistor RiB has a first terminal 10C connected to the input 13A of the first CAN 13 and a second terminal 10D connected to the neutral 6. The first two resistors Ria, Rib thus form a voltage divider bridge between the first phase 5A and the neutral 6. A first measurement voltage Vlm is therefore present between the input 13A of the first CAN 13 and the neutral 6. The first measurement voltage Vlm is the image of the first phase voltage Viet is consistent with the input voltage range of the first CAN 13.
[0070] The second branch 11 comprises two second resistors R2A, R2B. The second resistor R2A comprises a first terminal 11A connected to the second phase 5B and a second terminal 11B connected to an input 14A of the second CAN 14. The second resistor R2B comprises a first terminal 11C connected to the input 14A of the second CAN 14 and a second terminal 11D connected to the neutral 6. The two second resistors R2A, R2B thus form a voltage divider bridge between the second phase 5B and the neutral 6. A second measurement voltage V2m is therefore present between the input 14A of the second CAN 14 and the neutral 6. The second measurement voltage V2m is the image of the second phase voltage V2 and is consistent with the input voltage range of the second CAN 14.
[0071] The third branch 12 comprises two third resistors R3A, R3B. The third resistor R3A comprises a first terminal 12A connected to the third phase 5C and a second terminal 12B connected to an input 15A of the third CAN 15. The third resistor R3B comprises a first terminal 12C connected to the input 15A of the third CAN 15 and a second terminal 12D connected to the neutral 6. The two third resistors R3A, R3B thus form a voltage divider bridge between the third phase 5C and the neutral 6. A third measurement voltage V3m is therefore present between the input 15A of the third CAN 15 and the neutral 6. The third measurement voltage V3m is the image of the third phase voltage V3 and is consistent with the input voltage range of the third CAN 15.
[0072] The voltage divider bridges of each of the first, second and third branches 10, 11, 12 respectively make it possible to reduce the amplitudes of the first, second and third phase voltages Vb V2, V3 to make them compatible with the measurement range of the first CAN 13, the second CAN 14 and the third CAN 15.
[0073] The first CAN 13 has an output 13B connected to the processing unit 7A. The first CAN 13 will therefore produce first measurement samples representative of the first phase voltage Vi and supply them to the processing unit 7A.
[0074] The second CAN 14 has an output 14B connected to the processing unit 7A. The second CAN 14 will therefore produce second measurement samples representing signals of the second phase voltage V2 and supply them to the processing unit 7A.
[0075] The third CAN 15 has an output 15B connected to the processing unit 7A. The third CAN 15 will therefore produce third measurement samples representative of the third phase voltage V3 and supply them to the processing unit 7A.
[0076] It is expected that the first CAN 13, the second CAN 14 and the third CAN 15 all have adequate characteristics (number of bits, sampling frequency) to correctly convert the first measurement voltage Vlm, the second measurement voltage V2m and the third measurement voltage V3m, respectively. Here, the first CAN 13, the second CAN 14 and the third CAN 15 each have a number of bits greater than or equal to 12 bits and a sampling frequency of at least 2kSps (in English, kilo Samples per second - thousand samples per second).
[0077] The influence of a break in the neutral connection 6 in the distribution network 1 is now described.
[0078] With reference to [Fig.4], it is assumed that a break in the neutral connection 6 occurs in the distribution network 1 at a break point 16 located upstream of the first meter 7. By "upstream", it is understood on the side of the production unit 2 and by "downstream", it is understood on the side of the first installation 3.
[0079] When the neutral connection 6 breaks, a node 17 becomes floating.
[0080] The first phase voltage Vi downstream of the breaking point 16 then spontaneously balances as a function of the first impedance Zi of the first installation 3. Thus, the first impedance Zi presents the first phase voltage Vi at its terminals which is the voltage carried by the first phase 5A downstream of the breaking point 16. The first phase voltage V) is expressed as a function of a first nominal phase voltage V10 (which is the voltage carried by the first phase 5A upstream of the breaking point 16) and a potential difference Vne induced by the breaking of the neutral connection 6:
[0081] =
[0082] Similarly, the second phase voltage V2 downstream of the break point 16 balances spontaneously as a function of the second impedance Z2 of the first installation 3. Thus, the second impedance Z2 presents the second phase voltage V2 at its terminals which is the voltage carried by the second phase 5B downstream of the break point 16. The first phase voltage V2 is expressed as a function of a second nominal phase voltage V20 (which is the voltage carried by the second phase 5B upstream of the break point 16) and the potential difference Vne:
[0083] V2=V20-V^.
[0084] Similarly, the third phase voltage V3 downstream of the break point 16 balances spontaneously as a function of the third impedance Z3 of the first installation 3. Thus, the third impedance Z3 presents the third phase voltage V3 at its terminals which is the voltage carried by the third phase 5C downstream of the break point 16. The third phase voltage V3 is expressed as a function of a third nominal phase voltage V30 (which is the voltage carried by the third phase 5C upstream of the break point 16) and the potential difference Vne:
[0085] V^V^-V^.
[0086] It should be noted that when neutral 6 is correctly connected, V\= Vio, V2 = V2o and V3 = V3Q.
[0087] With reference to [Fig.5], the influence of the break in the neutral connection 6 is shown in the Fresnel representation.
[0088] It is interesting to note that the breaking of the neutral connection 6 induces a new balancing of the first phase voltage Vb of the second phase voltage V2 and of the third phase voltage V3 between them. Apart from in the particular case where the first, second and third electrical impedances Zb Z2, Z3 are perfectly balanced on the first, second and third phases 5A, 5B, 5C, the new balancing will be different from the initial balancing (when the neutral 6 was correctly connected).
[0089] The new balancing involves a variation of the effective value of the first phase voltage Vies, of the effective value of the second phase voltage V2eff and of the effective value of the third phase voltage V3eff which are then no longer necessarily equal to the nominal effective value of phase voltage Vnom.
[0090] The new balancing also involves a variation of the first phase shift q>i2, the second phase shift q>23 and the third phase shift <p3i qui ne sont alors plus nécessairement tous égaux à 120°.
[0091] On the other hand, the new balancing retains the first compound voltage Ui2, the second compound voltage U23 and the third compound voltage U3b
[0092] With reference to [Fig.6], the steps of the method for detecting a break in the connection of a neutral according to the invention are now described.
[0093] The detection method according to the invention is implemented in the processing unit 7A of the first counter 7. More particularly, the detection method according to the invention is implemented by the processing unit 7A of the first counter continuously. The steps of said detection method are therefore repeated regularly over time.
[0094] The method starts at a time T by acquiring the first phase voltage V i between the first phase 5A and the neutral 6, the second phase voltage V2 between the second phase 5B and the neutral 6 and the third phase voltage V3 between the third phase 5C and the neutral 6 (step El).
[0095] More precisely, the processing unit 7A acquires the first measurement samples representative of the first phase voltage Vb, the second measurement samples representative of the second phase voltage V2 and the third measurement samples representative of the third phase voltage V3. The first measurement samples, the second measurement samples and the third measurement samples being transmitted to the processing unit 7A by the voltage sensors 7D.
[0096] The processing unit 7A will, from the first measurement samples, the second measurement samples and the third measurement samples, respectively determine (possibly by applying calibration parameters) an effective value of the first phase voltage Vieff, an effective value of the second phase voltage V2eff and an effective value of the third phase voltage V3eff. The effective values Vieff, V2eff and V3eff are here respectively determined by the processing unit 7A each second on the basis of the first, second and third measurement samples acquired in the previous second. The effective values Vieff, V2eff and V3eff could also be determined over a sliding second or over any other relevant time window.
[0097] Subsequently, the processing unit 7A will define and / or update a predetermined reference criterion (step E2). The predetermined reference criterion will be described subsequently.
[0098] It should be noted that step E2 is optional. Indeed, the definition of the predetermined reference criterion could be carried out only once during an installation phase of the first meter 7 in the distribution network 1 (the predetermined reference criterion being recorded in the memory 7B). The definition and / or the updating of the predetermined reference criterion could also be carried out during a maintenance phase of the first meter 7.
[0099] The processing unit 7A will then evaluate a first quantity representative of a ratio between a maximum phase voltage and a minimum phase voltage among the first, second and third phase voltages Vj, V2, V3 (step E3). More precisely, the first quantity is here a number M which is determined using the following formula:
[0100] max(Vy.ff,V2rffy3efj) • min( Vlei1y2efh V^ff)
[0101] The evaluation of the first quantity M will make it possible to verify whether or not there is an imbalance between the first, second and third phase voltages Vj, V2, V3
[0102] For this purpose, the first quantity M will be compared to a predetermined threshold (step E4). The predetermined threshold is here equal to 1.2 to take into account in particular the dis normal variations of the first, second and third phase voltages Vb V2, V3 (intrinsic in the distribution network 1). If the first quantity M is greater than the predetermined threshold then there is a significant imbalance between the first, second and third phase voltages Vb V2, V3 and this constitutes a first indicator allowing suspicion of a break in the neutral connection 6 in the distribution network 1 upstream of the first meter 7 to be raised.
[0103] Nevertheless, the simple fact that the first magnitude M is greater than the predetermined threshold is not sufficient to ensure that a break in the neutral connection 6 has actually occurred. In particular, a simple break in the connection of a phase (among the first, second and third phases 5A, 5B, 5C) could also lead to the same observation (the first magnitude M is greater than the predetermined threshold). It is therefore necessary to confirm the suspicion of a break in the neutral connection 6 by determining an indicator which is characteristic of a break in the connection of a neutral in a three-phase electrical network.
[0104] It should be noted that if the first quantity M is less than the predetermined threshold then the detection method according to the invention determines that there is no break in the neutral connection 6 and therefore returns to step E1.
[0105] If the first quantity is greater than the predetermined threshold, then the processing unit 7A will evaluate, from the first, second and third phase voltages Vb V2, V3, at least one second quantity representative of a current balancing of said first, second and third phase voltages with each other (step E5). Indeed, as has been shown in [Fig.5], the breaking of the connection of a neutral will cause a new balancing of the first, second and third phase voltages Vb V2, V3 with each other.
[0106] The processing unit 7A will then detect whether the at least one second quantity verifies the predetermined reference criterion.
[0107] From there, several methods are possible and in particular several different second quantities as well as several predetermined reference criteria can be defined to effectively confirm that a break in the neutral connection 6 has occurred.
[0108] According to a first embodiment, the at least one second quantity comprises a second quantity G2 which is a function of a sum of the two-by-two products of the first, second and third phase voltages Vb V2, V3. More precisely, the second quantity G2 is a function of a sum of two-by-two products of effective values of the first, second and third phase voltages Vieff, V2eff, V3eff.
[0109] The approach proposed here is based on the fact that when a suspicion of the breakage of the neutral connection is established, the first, second and third phase voltages Vb V2, V3 will balance according to the new balancing which is not com- completely random.
[0110] If one of the effective values of a phase voltage among the effective values of the first, second and third phase voltages Vieff, V2eff, V3eff decreases sharply, while the other two effective values remain constant, this does not indicate a break in the neutral connection 6. For example, if the effective value Vieff decreases sharply while the effective values V2eff and V3eff remain constant, it will rather be a question of a voltage dip on the first phase 5A or a break in the connection of said first phase 5A. However, if one of the effective values of a phase voltage among the effective values of the first, second and third phase voltages Vleff, V2eff, V3eff decreases sharply and at the same time one of the other two effective values increases (or even that the two effective values increase) then it is highly probable that this is linked to a break in the neutral connection 6.For example, if the effective value Vieff decreases sharply and the effective values Vm and V3eff increase simultaneously, then it is highly likely that this is linked to a break in the neutral connection 6. .
[0111] Similarly, if one of the effective values of a phase voltage among the effective values of the first, second and third phase voltages Vieff, Vm, V3eff increases sharply while the other two effective values remain constant, this does not indicate a break in the neutral connection 6.
[0112] In order to confirm the suspicion of a break in the neutral connection 6, the processing unit 7A will calculate the second quantity G2 using the following formula:
[0114] where Vieff, V2eff and V3eff are respectively the effective value of the first phase voltage, the effective value of the second phase voltage and the effective value of the third phase voltage.
[0115] The second quantity G2 is proposed because it is bounded when a break in the neutral connection 6 occurs. In the first embodiment, the predetermined reference criterion which is defined by the processing unit 7A is therefore to verify that the second quantity G2 is bounded between a lower bound Bornlnf and an upper bound BornSup:
[0116] Terminalnf < G2 < TerminalSup.
[0117] In order to correctly define Bornlnf and BornSup the detection method further comprises the steps of:
[0118] - detecting whether the first, second and third phase voltages Vb V2, V3 are perfectly balanced with each other, that is to say if the effective value of the first phase voltage Vieff, the effective value of the second phase voltage V2eff and the effective value of the third phase voltage V3eff are all equal or not to the
[0119]
[0120]
[0121]
[0122]
[0123]
[0124]
[0125]
[0126]
[0127]
[0128]
[0129]
[0130]
[0131]
[0132]
[0133]
[0134]
[0135] nominal effective value of phase voltage Vnom of distribution network 1: lef f ~ ^nom and ^2eff — nomelV^ff—V nom, - if this condition is met, define Bornelnf and BomeSup as follows: Bornelnf = Vmjm and BorneSup = Vnom Otherwise, if the said condition is not met, and therefore if: Vlef f = ÜJ • Vnom and Vieff = ^2 ' nom and V^eff = «3 * Vnom, where ab a2 and a3 are real coefficients such that #2 ^3 and Vnom is the said nominal effective value, then: Bomeinf — minÇBl, B2, B3, B4, B5, B6) and BornSup = max ( Bl, B2, B3, B4, B5, B6 ), where Appendix 1 provides a mathematical demonstration to determine the expression of Bornlnf and BornSup. If the second quantity G2 is bounded between the lower limit Bornlnf and the upper limit BornSup (i.e. if the second quantity G2 verifies the predetermined reference criterion) then the detection method according to the invention detects a break in the neutral connection at time T upstream of the first meter 7. In the first embodiment, it is also possible to detect a break in the neutral connection 6 when one of the first, second and third phases 5A, 5B, 5C is disconnected. It is considered here that the third phase 5C is disconnected. If a break in the neutral connection 6 occurs then we find ourselves with a characteristic relationship between the effective value of the first phase voltage Vieff and the effective value of the second phase voltage V2eff.
[0136] If the first, second and third phase voltages Vb V2, V3 are perfectly balanced with each other, that is to say if: Vieff~ V nom and le ff — Vnom ct ~ Vnom , then the characteristic relation is as follows:
[0137] y + = ^3 Vnom' oa V"™ is 'a nominal effective value of voltage of phase.
[0138] If the first, second and third phase voltages Vb V2, V3 are not perfectly balanced with each other, that is to say if: V\eff = ■ Vfmm and “ a2 ■ Vnom and 3rd ff “ a3 ' Vnom, ï a? * a3) then the characteristic relation is as follows:
[0139] y leff + V2eff = Vnom^a\ + c^ + a}a2 , where Vnom is the nominal effective value of phase voltage.
[0140] A more complete and more detailed algorithm for implementing the detection method according to the first embodiment of the invention is presented in Appendix 2.
[0141] According to a second embodiment, the detection method comprises the step of evaluating the at least one second quantity which comprises a second quantity A which is a function of an area of an effective triangle 19 formed by the first, second and third phase voltages Vb V2, V3 in the Fresnel representation.
[0142] The effective triangle 19 has a first edge constituted by the first compound voltage Ui2, a second edge constituted by the second compound voltage U23 and a third edge constituted by the third compound voltage U3b
[0143] The second quantity A is determined by the processing unit 7A using the formula: A = ™ A is the second quantity (which is the area of the effective triangle 19), Vieff, Vm and V3eff are respectively the effective values of the first, second and third phase voltages, and q>i2 is the first phase shift, <p23est le deuxième déphasage et <p3i est le troisième déphasage. Le premier déphasage q>i2, the second phase shift q>23 and the third phase shift <p3i sont déterminés par l’unité de traitement 7A à partir des première, deuxième et troisième tensions de phase Vb V2, V3 via une méthode de « zero-crossing » (détection de passage par zéro) et un filtrage adéquat.
[0144] The reference criterion then being that the second quantity A is such that:
[0145] Aref - < A < Aref 4- where Aref is an area of a reference triangle 18 prede completed and £i is a first predetermined measurement uncertainty (typically, + / -1% or + / - 2%).
[0146] With reference to [Fig.5], the area of the reference triangle 18 Aref is in fact the area of the triangle formed by the first, second and third phase voltages Vb V2, V3
[0147]
[0148]
[0149]
[0150]
[0151]
[0152]
[0153] in the Fresnel representation under nominal conditions (i.e. when there is no break in the neutral connection 6). It is indeed interesting to note that the area of the reference triangle 18 and the area of the effective triangle 19 are similar in the case of a break in the neutral 6 connection. Thus, by comparing the second quantity A (the area of the effective triangle 19) with the predetermined area of the reference triangle 18 Aref, it is possible to effectively determine whether a break in the neutral 6 connection has occurred. In order to correctly define the area of the reference triangle 18 Aref> the detection method further comprises the steps of: - detect whether the first, second and third phase voltages Vb V2, V3 are perfectly balanced with each other, i.e. whether the effective value of the first phase voltage Vieff, the effective value of the second phase voltage V2eff and the effective value of the third phase voltage V3eff are all equal or not to the nominal effective value of phase voltage Vnom of the distribution network 1: V, , - = V and Vo rr = V and = V v lejj noun v ^fj r noun. r name, - if this condition is met, then the area of the reference triangle 18 is evaluated using the formula: 3^3 , where Vnom is the nominal effective value of ^ref 4 F name phase voltage. Otherwise, if the said condition is not met, and therefore if: V\eff - ' Vnom and Vleff ~ «2 ' Vnom and V^eff ~ a3 ' Vnom, where ab a2 and a3 are real coefficients such as Æj #2 a3 and Vnom is said nominal effective value, then the area of the reference triangle 18 is evaluated using the formula: . / \J3 , where Vnom is said nominal effective value of Aref = a^ + R- Vnom phase voltage.
[0154] If the second quantity A verifies the predetermined reference criterion then the detection method according to the invention detects a break in the neutral connection at time T upstream of the first meter 7.
[0155] According to a third embodiment of the invention, the at least one second quantity comprises second quantities which include the first compound voltage Ui2> the second compound voltage U23 and the third compound voltage U3b
[0156] With reference to [Fig.5], in the event of a break in the neutral connection 6, the first compound voltage Ui2, the second compound voltage U23 and the third compound voltage U3i remain constant.
[0157] The reference criterion verified by the processing unit 7A is therefore to verify whether:
[0158] (Pi- + ¾et
[0159] 3>2 " «2 ^23 ^2 + s2 and
[0160] 03 - s2 1 03 + e2,
[0161] where ¢1, ¢2 and ¢3 are respectively reference values of the first, second and third phase-to-phase voltages Ui2, U23, U31 measured in operation at a reference time To preceding time T and e2 is a second predetermined measurement uncertainty (typically, + / - 1% or + / - 2%).
[0162] If the second quantities Ui2> U23 and U31 verify the predetermined reference criterion then the detection method according to the invention detects a break in the neutral connection at time T upstream of the first meter 7.
[0163] According to a fourth embodiment of the invention, the detection method comprises the step of evaluating the at least one second quantity which comprises second quantities which comprise the first phase shift 912, the second phase shift 923 and the third phase shift cp31.
[0164] With reference to [Fig.5], it is interesting to note that the first phase shift 912, the second phase shift q>23 and the third phase shift qmne are no longer equal to 120° when a break in the neutral connection 6 occurs.
[0165] The reference criterion defined by the processing unit 7A is then to verify whether the first, second and third phase shifts 912,923,931 are each unaffected and different by 120 degrees.
[0166] If the first, second and third phase shifts 912,923,931 verify the predetermined reference criterion then the detection method according to the invention detects a break in the neutral connection at time T upstream of the first counter 7.
[0167] In the four embodiments of the invention presented above, if the second quantity or quantities do not verify the predetermined reference criterion then the detection method passes to step El' which is similar to step El and possibly passes through a step E2' which is similar to step E2.
[0168] In the four embodiments of the invention presented above, an adequate margin of uncertainty, linked in particular to the precision of the voltage sensors 7D of the first meter 7, is to be taken into account. Typically, the margin of uncertainty is of the order of + / - 1% or + / - 2%.
[0169] In the four embodiments of the invention presented above, the expressions used for the definition of the predetermined reference criterion (Bornlnf, BornSup, Aref, ¢1, ¢2 and ¢3) could be determined by the processing unit 7A by averaging several successive calculations in order to attenuate parasitic phenomena (such as a transient overvoltage of the shock wave or micro-cut type) which could reduce the reliability of the detection method according to the invention. The use of an averaging technique is entirely feasible by assuming that the distribution network 1 is stable for a given duration.
[0170] Whatever the embodiment considered, the detection method according to the invention is implemented by the processing unit 7A of the first continuous counter. The steps of said detection method are therefore repeated regularly over time.
[0171] Advantageously and regardless of the embodiment considered, the detection method according to the invention may further comprise the step of detecting a break in the neutral connection 6 when it has been detected that the second quantity verifies the predetermined reference criterion a predetermined number of times (for example 10 times), corresponding to consecutive verifications (i.e. consecutive implementations of the detection method) spaced two by two in time by a predetermined duration (for example 1 second). This makes it possible to increase the reliability of the detection method according to the invention.
[0172] Optionally, when a break in the neutral connection has actually been detected, the detection method may further comprise the step of generating an alarm signal which can be time-stamped in the memory 7B of the first meter 7 and / or which can be transmitted (via the communication module 7C) to equipment external to said first meter 7, for example an Information System of the distribution network 1.
[0173] Optionally, the alarm signal may be the display of a particular message on a local display of the first counter 7 and / or the alarm signal may be the lighting of a light indicator located on said first counter 7 and / or the lighting of an audible signal emitted by a loudspeaker of said first counter 7.
[0174] Ideally, all the electricity meters in the distribution network 1 are similar and are arranged to implement the detection method according to the invention. Thus, the entire distribution network 1 is correctly monitored.
[0175] Optionally, when a break in the neutral connection has actually been detected and the imbalance between the first, second and third phase voltages is considered too great, then the detection method may further comprise the step, if said detection method is implemented in a particular meter comprising a cut-off device, of opening said cut-off device to protect one or more electrical installations downstream of said particular meter.
[0176] Of course, the invention is not limited to the embodiments described but encompasses any variant falling within the scope of the invention as defined by the claims.
[0177] It is entirely possible to freely combine the different embodiments presented previously. Thus, the processing unit 7A of the first counter 7 can determine several second quantities, for example the second quantity G2 (presented in the first embodiment) and the second quantity A (presented in the second embodiment). This could make it possible to increase the reliability of the detection method according to the invention.
[0178] The voltage sensors 7D of the first meter 7 have been presented, comprising a first CAN 13, a second CAN 14 and a third CAN 15, but it is entirely possible that the voltage sensors 7D comprise a single CAN comprising three separate inputs, each allowing the first phase voltage, the second phase voltage and the third phase voltage to be acquired respectively.
[0179] Appendix 1: Formal demonstration of the relationships proposed for the first embodiment
[0180] The assumption for the present demonstration is that the first, second and third phase voltages Vb V2, V3 are perfectly balanced, i.e. the effective values Vleff, V2eff, V3eff are all equal to the nominal effective value of phase voltage Vnom. This is not necessarily exact in practice, but can be used as a first approximation.
[0181] It should be noted that the voltages in the demonstration are in vector form and that this is overall the demonstration of complex effective values.
[0182] With reference to [Fig.4], once a break in the neutral connection has occurred, then it is possible to write: 101831 v7-E=K 101841 E7E=K 101851 K
[0186] 7)+7:+ fi= o
[0187] h, I2,1= are the electric currents flowing respectively through the first phase 5A, the second phase 5B and the third phase 5C.
[0188] Ci J_._L.J_) Z, + Z-, Z3 — v ne\ Zj ^Zj Z; /
[0189] Using a first admittance Yb, a second admittance Y2 and a third admittance Y3 (Y]=l / Zi Y2=l / Z2, Y3=l / Z3), we have:
[0190] ï^r 1+ v^r2+v7y3= vZ( Yj+y^y^
[0191] We replace y^: (1) 101921 + + Calculation of VI
[0193] Knowing that:
[0194] w O II J7 1
[0195] V - V + V 30“ V10l ' 2 “ /
[0196]
[0197]
[0198] From relation (1) we have: v10(r,+ (- i-j4 )yî+(- i+J^ )y3 ^+^+^) r» [(r,4Y24Y,-Y1-Y2-Y3)+j£(Y3-Y2) = -y(y + y+i'3)
[0199]
[0200]
[0201] Vi - vî0 ( |y,+|y3) ( Y^+Y,) .fi t Y: YI 2 (y(+y2+y3) Applying the module we have: (2) U i <Y2+Y3) 10 V\(Yl+Y^Y3) fi (y2-y3) \2 2 ( Fi+Y^Y;,) J Calculation of V2
[0202] From relation (1) we have: 102031 Ytfifi-iJ^r )Y'+(- 4+7t )Y3)=(r2o-y)(
[0204] Knowing that:
[0205] _ / i . fi \ V20~ V10l ' 2~JT )
[0206] It turns out that:
[0207]
[0208] _ / (4Y0 (2xY3+Yi) \ V2 MO ( y^y^yj J? ( y )
[0209] By applying the module we have: (3) [021°] 1 / lY, y / fi~'^ f2 mo ( yt+y2+y3) / + \ 2 ( yl+y2+y,) y Calculation of V3
[0211] From relation (1) we have: 102121 )y2+(- 1+7# )y3)=(vm-v3)( r,+y2+F3)
[0213] Knowing that: [°2141 V - V / l+;£ ] V law ' 2~ I
[0215] It comes that: [°216] V10[(rI4Y24Y3 + iY1 + lY2 + |Y3)+4(Y3-Y2-Y1-Y2-Y3)] = -V2( Y^Y2+Y3)
[0217] / ( -4 YJ fi (2xY2+Yt) \ V3 1 10^ ( y|+y,+y3) + J 2 ( yi+F2+Fj) /
[0218] By applying the module we have: (4)
[0219] r M v v. .2 V - VI 2F1 1 , H3 (2XY.+Y0 \ ■3 F1° y \ ' ( Yi+y^) / \ 2 ( 7+7++0 /
[0220] Using relations (2), (3) and (4) and setting Vi0=Vnom, we have:
[0221] y, v2 + Vs V3+V2 V, = f(Y„ Y2. Y3)
[0222] With:
[0223] f(YYY} = J v1 h 22'131 UH ( y1+y2+Y3) / [ 2 ( yi+y2+y,) / IH ( yj+y2+y3) / ( 2 ( y^r^y,) /
[0224] (7+f2+7)
[0225] (2xY3+Y,) (7+7+7)
[0226] (y2-y3) \2 y^+Fj) ) ( y + Fj + Fd / (^1^2^3) 4( y]+y2+y,)2 \
[0222] +^9(y2 + y3)2 + 3(y3_y2)2j (97| + 3(y1 + 2y2)2)
[0228] + ^(9y2 + 3(yi + 2y3)2) (9y2+3(y1+)
[0229] / (yi5 y^ = ( [°23°] +^(^+^3+^3) ^+7^ + 71)
[0231] + yf + + yf) ( y}+) )
[0232] By studying the borderline cases:
[0233] Case 1: Y1=Y2=Y3=Y: 102341 / (7,-^7,)= ^-,{^Ÿ + ^Ÿ + ^Ÿ) = ^,9Y2 = 3
[0235] Knowing that:
[0236] V| y2+ V} y3+ v2 y3= 7^ / (7,, Xj 7,)
[0237] It follows that (the limiting case studied here constituting the lower bound) - V; and Vj being res respectively the phase voltages of the ith phase and jth phase:
[0238] F. .VV > 3V2
[0239] From where:
[0240] V < v' 'name — y 3
[0241] Case 2: Y1=Y2=Y » Y3=y:
[0242] f ( y y3) = _A_ ( ^(y2 ) (y2) + ^ / (y2) (3y2 ) + (372 ) ) =
[0243] Knowing that:
[0244]
[0245]
[0246]
[0247]
[0248]
[0249]
[0250]
[0251]
[0252]
[0253]
[0254]
[0255]
[0256]
[0257]
[0258]
[0259]
[0260]
[0261]
[0262]
[0263] v, v2+ v, v3+ v, v3= y2, y3) It follows that (the limiting case studied here constituting the upper bound): £ vv <r’ x&M r i * J — * nom 4 From where: / 273+1 y 3 — y 4 F name We have clearly demonstrated by studies of borderline cases that the sum of VtV j remained very precisely bounded between Vnom and 1.056Vnom during a connection break from neutral: Iy v. v Bornelnf < -y - < BorneSup Borneln f = VIlom / 2J3+1 TerminalSup = 4-4- Vmm ( = 1-056 Vnom) The proposed formula can then be generalized, by the same calculation process, to take into account initial conditions for which the distribution network does not have perfectly balanced phase voltages, by posing: name ot ^2ef f ^2 ' ot ^3 ' iioin? or, ai, a2 and a3 are real coefficients such as #3. The fact is that by considering the effect of the initial imbalances between the phase voltages coming from the distribution network, the asymptotic study cases to be considered (which allow us to obtain a bounded limit of the expected result in the event of a break in the neutral connection) increase from 2 to 6, due to loss of symmetry. And finally:
[0264] Vj Bomelnf < y—— < BorneSup
[0265]
[0266]
[0267] Avec : Bornelnf = min(B\ B% B3, B4, B5, B6) et BornSup = max ( Bl, B% B3, B4, B5, B6 ) .
[0268]
[0269]
[0270]
[0271]
[0272]
[0273]
[0274]
[0275]
[0276]
[0277]
[0278]
[0279]
[0280]
[0281]
[0282]
[0283]
[0284]
[0285]
[0286]
[0287]
[0288]
[0289]
[0290]
[0291]
[0292]
[0293]
[0294]
[0295]
[0296]
[0297]
[0298]
[0299]
[0300] Annexe 2 : Algorithme nronosé nour le nremier mode de réalisation / / init Un = 230 U[]=[230;230;230] PhaseConnectStatus[] = [UNKNOWN; UNKNOWN; UNKNOWN] NeutraConnectStatus = UNKNOWN / / param Vmin = 60 Toi = 10% N = 2 AlphaThreshold = 20% DevThresholdLow = 10% DevThresholdHigh = 20% MarginLow = 0.5% MarginHigh = 0.5% MarginLow_bis = 2% MarginHigh_bis = 2% MarginAdd = 5% Loop every second For i = 1 to 3 cnt_unknwn = 0 If (V[i] < Vmin) PhaseConnectStatus[i] = UNKNOWN cnt_unknwn ++ Else PhaseConnectStatus[i] = CONNECTED End If End For For i = 1 to 3 IfV[i] < (l-Tol).Un Vtmp = U[i] ElsifV[i] > (l+Tol).Un Vtmp = U[i]
[0301] Else
[0302] Vtmp = V[i]
[0303] End If
[0304] U[i] = Vtmp / N + (N-l).U[i] / N
[0305] a[i] = U[i] / Un
[0306] Dev[i] = V[i] / U[i]
[0307] End For
[0308] If (cnt_unknwn >= 2)
[0309] For i = 1 to 3
[0310] If (PhaseConnectStatus[i] = UNKNOWN)
[0311] PhaseConnectStatus [i] = DISCONNECTED
[0312] End If
[0313] End For
[0314] End If
[0315] If (cnt_unknwn < 2)
[0316] Alpha = Max(V[]) / MIN(V[])
[0317] If (((Alpha-1) > AlphaThreshold) AND (((l-MIN(Dev[])) > DevThresholdLow) OR ((MAX(Dev[])-l) > DevThresholdHigh)))
[0318] Vref = 0
[0319] Fori=lto3
[0320] j = i+1 %3
[0321] k = i+2%3
[0322] Vref = Vref + V[i].V[j] / 3
[0323] Factorl[i] = SQRT((a[i]2+a[j]2+a[i].a[j]).(a[i]2+a[k]2+a[i].a[k]))
[0324] Factor2[i] = (2.SQRT((4.a[i]2+a[j]2+a[k]2+2.a[i].a[j]+2.a[i].a[k]-a[j].a[k]).(a[j]2+a[k]2+a[j].a[k]))+(a [j]2+a[k]2+a[j].a[k])) / 4
[0325] End For
[0326] Vref = SQRT(Vref)
[0327] Uliml [i] = Un.SQRT(Factor 1 [i] / 3)
[0328] Ulim2[i] = Un.SQRT(Factor2[i] / 3)
[0329] If (NeutralConnectStatus = DISCONNECTED)
[0330] MarginL = MarginLow + MarginAdd
[0331] MarginH = MarginHigh + MarginAdd
[0332] Else
[0333] MarginL = MarginLow
[0334] MarginH = MarginHigh
[0335] End If
[0336] If ((Vref > (l-MargmL).MIN(MIN(Uliml[]),MIN(Ulim2[]))) AND (Vref (l+MarginH).MAX(MAX(Uliml[]),MAX(Ulim2[]))))
[0337] NeutralConnectStatus = DISCONNECTED
[0338] For i = 1 to 3
[0339] If (PhaseConnectStatus[i] = UNKNOWN)
[0340] PhaseConnectStatus[i] = CONNECTED
[0341] End If
[0342] End For
[0343] Else
[0344] NeutralConnectStatus = CONNECTED
[0345] For i = 1 to 3
[0346] If (PhaseConnectStatus[i] = UNKNOWN)
[0347] PhaseConnectStatus[i] = DISCONNECTED
[0348] NeutralConnectStatus = UNKNOWN
[0349] End If
[0350] End For
[0351] End If
[0352] End If
[0353] If (NeutralConnectStatus = UNKNOWN)
[0354] Vref_bis = 0
[0355] For i = 1 to 3
[0356] If (PhaseConnectStatus[i] = CONNECTED)
[0357] Vref_bis = Vref_bis + V[i]
[0358] End If
[0359] End For
[0360] Vref_bis = Vref_bis / 2
[0361] For i = 1 to 3
[0362] a_bis[i] = 0
[0363] If ( PhaseConnectStatus [ i ] = CONNECTED ) .
[0364] a_bis[i] = a[i]
[0365] End If
[0366] End For
[0367] Bis_factor = 0
[0368] For i = 1 to 3
[0369] j = i+1 %3
[0370] Factor_bis = Factor_bis + a_bis[i]2 + a_bis[i].a_bis[j].
[0371] End For
[0372] Ulim_bis = Un.SQRT(bis_factor) / 2
[0373] If ( NeutralConnectStatus = DISCONNECTED ) .
[0374] MarginL_bis = MarginLow_bis + MarginAdd
[0375] MarginH_bis = MarginHigh_bis + MarginAdd
[0376] Else
[0377] MarginL = MarginLow
[0378] MarginH = MarginHigh
[0379] End If
[0380] If ((Vref_bis > (l-MarginL_bis).Ulim_bis) AND (Vref_bis(l+MarginH_bis).Ulim_bis))
[0381] NeutralConnectStatus = DISCONNECTED
[0382] Else [ 0383 ] NeutralConnectStatus = CONNECTED
[0384] End If
[0385] End If
[0386] End If
[0387] End Loop
Claims
Claims
1. Method for detecting a break in the connection of a neutral (6) of a three-phase electrical network, the detection method being implemented at least partially in a processing unit (7A) of an electrical equipment (7) connected to the electrical network (1), and comprising the steps, repeated regularly, of: - acquiring, at a time T, a first phase voltage (Vi) measured between a first phase (5A) of the three-phase electrical network and the neutral (6), a second phase voltage (V2) measured between a second phase (5B) and the neutral (6), and a third phase voltage (V3) measured between a third phase (5C) and the neutral (6), the first, second and third phase voltages being measured by voltage sensors (7D) of the electrical equipment (7); - evaluating a first quantity representative of a ratio between a maximum phase voltage and a minimum phase voltage among the first, second and third phase voltages;- if the first quantity is greater than a predetermined threshold, then: • evaluate, from the first, second and third phase voltages, at least one second quantity representative of a current balancing of said first, second and third phase voltages with each other; • detect a break in the neutral connection (6) at time T when the at least one second quantity verifies a predetermined reference criterion.;
2. A detection method according to claim 1, wherein the at least one second quantity comprises a second quantity which is a function of a sum of two-by-two products of effective values of the first, second and third phase voltages.
3. Detection method according to claim 2, wherein said second quantity G2 is equal to: G2 = ^3(^ / / ^ / / + ^2; / / Kxf / + ^3e / / ^^ ' where Vieff, V2eff and V3eff are respectively an effective value of the first phase voltage (Vi), an effective value of the second phase voltage (V2) and an effective value of the third phase voltage (V3),
4.
5. the predetermined reference criterion being that: Bomeln f < G2 < BorneSup. A detection method according to claim 3, further comprising the steps of: - detecting whether: V, fr = V and VS fr = V and V- ff = V y lej jy nom y Zej j ' nom r ^ejj y nom^ where Vnom is the nominal effective value of the phase voltage of the electrical network; - if this condition is met, define Bornelnf and BorneSup as follows: Bornelnf — V„omet / 2J3+1 BorneSup = Vnom Detection method according to claim 4, wherein, if said condition is not met, and if: V ïeff l ' and 2eff “ ^2 ' Vnom and “ ^3 ' ^nom^ °Ù, ^i, &2 and a3 are real coefficients such that (h a3, then: Bornelnf = min(B\, B2, B3, B4, B5, B6) and BornSup - max(BÏ, B2, B3, B4, B5, B6), where
6.
7. A detection method according to claim 1, wherein the at least one second quantity comprises a second quantity which is a function of an area of an effective triangle (19) formed by the first, second and third phase voltages in the Fresnel representation. A detection method according to claim 6, wherein the area of the effective triangle is determined using the formula: A =ie / / V2<. / / sinç>I2 + V^ / Kv / ySin^ + V3effV le / / sin^ J where A is the second quantity, Vleff, V2eff and V3eff are respectively the effective values of the first, second and third phase voltages, and q>i2 is a first phase shift between the first phase voltage and the second phase voltage, <p23est un deuxième déphasage entre la tension de phase et troisième <p3i est première phase, le critère référence étant alors que grandeur telle : aref aref + g ! où une aire d’un triangle ei incertitude mesure prédéterminée.
8. A detection method according to claim 7, wherein, if the first, second and third phase voltages are perfectly balanced with each other, the area of the predetermined reference triangle (18) is evaluated using the formula: _ 3^ / 3 , where Aref is the area 4 * nom of the reference triangle and Vnom is the nominal effective value of the phase voltage of the electrical network.
9. Detection method according to claim 1, wherein the at least one second quantity comprises second quantities which comprise a first phase-to-phase voltage U12 representative of a difference between the first phase voltage and the second phase voltage, a second phase-to-phase voltage U23 representative of a difference between the second phase voltage and the third phase voltage and a third phase-to-phase voltage U3i representative of a difference between the third phase voltage and the first phase voltage, the reference criterion then being that: - S2 — U^2 — + ^2 and ^23- ^2 + £2 and - s2 U21 î ¢3 + f 7, where ¢1, O2 and O3 are reference values of the first, second and third phase-to-phase voltages measured in operation at a reference time To preceding the time T and e2 is a second predetermined measurement uncertainty.
10. A detection method according to claim 1, wherein the at least a second quantity comprises second quantities which comprise a first phase shift between the first phase voltage (V i ) and the second phase voltage (V2), a second phase shift between the second phase voltage (V2) and the third phase voltage (V3) and a third phase shift between the third phase voltage (V3) and the first phase voltage (VJ, the predetermined reference criterion then being that the first, second and third phase shifts are each unaffected and different by 120 degrees.
11. Detection method according to one of the preceding claims, further comprising the step of detecting a break in the neutral connection when it has been detected that the second quantity verifies the predetermined reference criterion a predetermined number of times, corresponding to consecutive verifications spaced two by two in time by a predetermined duration.
12. Detection method according to one of the preceding claims, in which, when a break in the neutral connection has been detected, the method further comprises the step of generating an alarm signal which can be time-stamped in a memory (7B) of the electrical equipment and / or which can be transmitted to equipment external to said electrical equipment.
13. Electrical equipment comprising voltage sensors and a processing unit (7A) arranged to implement the detection method according to one of the preceding claims.
14. Electrical equipment according to claim 13, the electrical equipment being an electric meter (7).
15. Computer program comprising instructions which cause the electrical equipment according to one of claims 13 or 14 to execute the steps of the detection method according to one of claims 1 to 12.
16. A computer-readable recording medium on which the computer program according to claim 15 is recorded.