Monitoring and optimization of electricity consumption

The electric meter with integrated current limiters and cut-off members addresses the complexity and cost of existing load shedding devices by optimizing electricity consumption through predefined conditions, enabling efficient energy savings without specialized installation.

FR3140441B1Active Publication Date: 2024-11-22SAGEMCOM ENERGY & TELECOM SAS
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
FR2022009908
Authority / Receiving Office
FR · FR
Patent Type
Patents
Current Assignee / Owner
Filing Date
2022-09-29
Publication Date
2024-11-22
Estimated Expiration
2042-09-29

AI Technical Summary

Technical Problem

Existing solutions for reducing electricity consumption, such as electric load shedding devices, require specific and personalized installation, which is expensive and complex, making them impractical for widespread implementation.

Method used

A monitoring method using an electric meter with integrated current limiters and cut-off members that selectively control and optimize electricity consumption based on predetermined conditions, allowing for implementation without specialized installation.

Benefits of technology

The method effectively limits electricity consumption by activating current limiters or cutting off power supply according to predefined thresholds, achieving energy savings without the need for personalized installation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 00000017_0000
    Figure 00000017_0000
  • Figure 00000018_0000
    Figure 00000018_0000
  • Figure 00000019_0000
    Figure 00000019_0000
Patent Text Reader

Abstract

A monitoring method, using an electricity meter (1) arranged to measure the electrical consumption of an installation (3) and comprising a current limiter (20) arranged to selectively limit the current supplied to the installation, the monitoring method comprising the steps, repeated each current day, for each current period of a predetermined set of at least one successive period defined in the current day, of: verifying a first predetermined condition associated with said current period; if the first predetermined condition is verified, activating the current limiter to limit the current supplied to the installation until the end of said current period. ABRIDGED FIGURE: Fig. 1
Need to check novelty before this filing date? Find Prior Art

Description

Title of the invention: Monitoring and optimization of electrical consumption

[0001] The invention relates to the field of so-called “smart” electric meters.

[0002] BACKGROUND OF THE INVENTION

[0003] We are currently looking for innovative and effective solutions to limit the electricity consumption of end users (subscribers) connected to the electricity network. It is clear that limiting the electricity consumption of each individual not only presents an undeniable interest in terms of ecology, but is also very advantageous for the purchasing power of users.

[0004] A solution is known for reducing electricity consumption, which uses electrical load shedders.

[0005] An electrical load shedder is a device that is installed at the user's premises, near the meter. The electrical load shedder cuts off the power to certain non-priority devices at the time of the current demand, when consumption exceeds a certain threshold. The non-priority devices concerned, as well as the load shedding sequences, can be defined by the user. Non-priority devices typically include electric radiators and the hot water tank.

[0006] This solution is effective and not only allows significant energy savings to be made, but also avoids tripping the installation when the power required is too high.

[0007] However, this solution requires a specific and personalized installation at the user's premises, and is therefore relatively expensive and complex to implement.

[0008] SUBJECT OF THE INVENTION

[0009] The object of the invention is to control and optimize the electrical consumption of a user, in a simple and inexpensive manner to implement. Summary of the invention

[0010] With a view to achieving this aim, a monitoring method is proposed, using an electric meter arranged to measure an electric consumption of an installation and comprising a current limiter arranged to selectively limit a current supplied to the installation, the monitoring method comprising the steps, repeated each current day, for each current period of a predetermined set of at least one successive period defined in the current day, of: • verifying a first predetermined condition associated with said current period; • if the first predetermined condition is verified, activate the limiter current to limit the current supplied to the installation until the end of said current period.

[0011] The monitoring method, which can be implemented by the meter itself or remotely, therefore makes it possible, each current day, to limit the electrical consumption of the installation on the basis of predetermined conditions associated with periods of the current day. The component(s) forming the current limiter are directly integrated into the meter and are the same for all meters, so that the implementation of the monitoring method does not require any particular intervention or specific and personalized installation at the user's premises.

[0012] A monitoring method is further proposed as previously described, the electric meter further comprising a cut-off member arranged to selectively cut off the current supplied to the installation, the monitoring method further comprising the steps, for each current period, of: • verify a second predetermined condition associated with said current period; • if the second predetermined condition is verified, control the cut-off device so as to cut the current supplied to the installation until the end of the said current period.

[0013] A monitoring method is further proposed as previously described, in which the first predetermined condition is that a cumulative electrical consumption of the installation over said current period is greater than a first predetermined threshold.

[0014] A monitoring method is further proposed as previously described, in which the second predetermined condition is that a cumulative electrical consumption of the installation over said current period is greater than a second predetermined threshold itself greater than the first predetermined threshold.

[0015] A monitoring method is further proposed as previously described, in which the first predetermined threshold and / or the second predetermined threshold depend on said current period and / or said current day and / or a period of the year to which said current day belongs.

[0016] A monitoring method is further proposed as previously described, in which the verification of the first predetermined condition consists of verifying, in a predefined table, that said current period is associated with first information according to which the current supplied to the installation must be limited during the entirety of said current period.

[0017] We further propose a monitoring method as previously described, in which the verification of the second predetermined condition consists of verifying, in the predefined table, that said current period is associated with a second in training according to which the current supplied to the installation must be cut off during the entire said current period.

[0018] A monitoring method is further proposed as previously described, the meter further comprising a cut-off member arranged to selectively cut off the current supplied to the installation, the cut-off member comprising a switch for each phase of a distribution network to which the installation is connected, the current limiter comprising, for each switch of the cut-off member, a relay and a resistive component mounted in parallel with the switch, the activation of the current limiter to limit the current supplied to the installation comprising the steps of closing the relay(s) simultaneously and then, subsequently, opening the switch(es) simultaneously.

[0019] An electric meter is further provided, arranged to measure an electric consumption of an installation, the electric meter comprising a current limiter arranged to selectively limit a current supplied to the installation, the electric meter further comprising a processing unit arranged to implement the monitoring method as previously described.

[0020] An electric meter as previously described is further proposed, the electric meter further comprising a cut-off member arranged to selectively cut off the current supplied to the installation, the cut-off member comprising a switch for each phase of a distribution network to which the installation is connected, the current limiter comprising, for each switch of the cut-off member, a relay and a resistive component mounted in parallel with the switch, the processing unit being arranged, to activate the current limiter, to close the relay(s) simultaneously and then, subsequently, to open the switch(es) simultaneously.

[0021] A computer program is further provided comprising instructions which cause the processing unit of the electric meter as previously described to execute the steps of the monitoring method as previously described.

[0022] A computer-readable recording medium is further provided, on which the computer program as previously described is recorded.

[0023] The invention will be better understood in light of the following description of particular non-limiting embodiments of the invention. Brief description of the drawings

[0024] Reference will be made to the attached drawings, among which:

[0025] [Fig-1] [Fig.l] represents a single-phase electric meter;

[0026] [Fig.2] [Fig.2] represents steps of a monitoring method;

[0027] [Fig.3] [Fig.3] represents a three-phase electric meter. DETAILED DESCRIPTION OF THE INVENTION

[0028] With reference to [Fig. 1], the invention is first implemented in a single-phase electric meter 1.

[0029] The meter 1 is intended to measure electrical energy supplied by a source, in this case by a distribution network 2, to the electrical installation 3 of a user (subscriber).

[0030] The distribution network 2 is a single-phase network and comprises a phase Ph and a neutral N. The meter 1 recovers the phase and the neutral of the network 2 to carry out the metrological measurements.

[0031] A circuit breaker 4 is positioned at the border between the distribution network 2 and the installation 3. The circuit breaker 4, which can be operated by the user, has the role of protecting the installation 3 by opening when an overcurrent, resulting for example from a short circuit downstream of the circuit breaker 4, occurs on the distribution network 2. Here, by "downstream" is meant on the side of the installation 3 and by "upstream" is meant on the side of the distribution network 2.

[0032] The meter 1 comprises an input terminal UP connected to the phase Ph of the network 2 and an input terminal UN connected to the neutral N. The meter 1 further comprises two output terminals UP' and UN' connected to the circuit breaker 4, which is itself connected to the installation 3.

[0033] The meter 1 has a neutral conductor 5 connected to the input terminal UN.

[0034] The meter 1 further comprises a phase conductor 6 connected to the input terminal UP. Phase conductor 6 is connected to an electrical ground 7 of meter 1.

[0035] The meter 1 further comprises a cut-off member 9 which comprises a switch 10 mounted on the phase conductor 6. The cut-off member 9 is notably used to remotely cut off or restore the power supply to the installation 3 (symbolized here by a load) in the event, for example, of termination of the subscription or non-compliance with the subscription contract.

[0036] The meter 1 further comprises an application part and a metrology part.

[0037] The application part (not shown) comprises an application microcontroller.

[0038] The metrology part comprises a metrology microcontroller 11, the function of which primary is to produce measurements of a certain number of parameters allowing the electrical consumption of the installation to be assessed 3.

[0039] The metrology part also comprises one or more memories 12 connected to or integrated in the microcontroller 11. At least one of these memories forms a computer-readable recording medium, on which is recorded at least one computer program comprising instructions which cause the microcontroller 11 to execute at least some of the steps of the monitoring method which will be described below.

[0040] The microcontroller 11 integrates a first analog-digital converter (CAN) 14, a second CAN 15, a voltage measurement module 16 and a current measurement module 17.

[0041] The metrology part also comprises a voltage sensor arranged to produce voltage measurements to evaluate a neutral voltage VN present on the neutral N.

[0042] The voltage sensor here comprises a voltage divider bridge comprising a first measuring resistor RI and a second measuring resistor R2. The first measuring resistor RI has a first terminal connected to the neutral conductor 5 near (and downstream of) the input terminal UN. The second measuring resistor R2 has a first terminal connected to the electrical ground 7. The second terminal of the first measuring resistor RI and the second terminal of the second measuring resistor R2 are connected to each other and to an input of the microcontroller 11 to which an input of the first CAN 14 is connected.

[0043] The level of the measured voltage Vml is adapted (thanks to the divider bridge RI, R2) in order to avoid saturations at the level of the first CAN 14, and so as to apply at the input of the first CAN 14 signals having significant levels (and corresponding to the input range of the first CAN 14).

[0044] The first CAN 14 therefore digitizes the voltage Vml. The voltage measurement module 16 produces, from the samples produced by the first CAN 14, voltage measurements (effective) making it possible to evaluate the neutral voltage VN.

[0045] The metrology part also comprises a current sensor arranged to produce current measurements representative of a phase current Iph flowing on the phase conductor 6.

[0046] The current sensor comprises a shunt 18 mounted on the phase conductor 6 and positioned between the input terminal UP and the switch 10 of the cut-off member 9.

[0047] The metrology part also comprises a current measurement chain 19 having a known gain. The current measurement chain 19 is connected to the terminal of the shunt 18 which is connected to the switch 10 of the cut-off member 9, the other terminal of the shunt 18 being connected to the ground 7 and to the input terminal UP.

[0048] The output of the current measurement chain 19 is connected to an input of the microcontroller 11 to which is connected an input of the second CAN 15.

[0049] The voltage Vm2 at the output of the current measurement chain 19 is a voltage which is an image of the phase current Iph.

[0050] The level of the voltage Vm2 is adapted (thanks to the gain of the current measurement chain 19) in order to avoid saturations at the level of the second CAN 15, and so as to apply at the input of the second CAN 15 signals having significant levels (and corresponding to the input range of the second CAN 15).

[0051] The second CAN 15 digitizes the voltage Vm2. The current measurement module 17 produces, from the samples produced by the second CAN 15, measurements of current allowing the phase current Iph to be evaluated.

[0052] The meter 1 further comprises a current limiter 20 arranged to selectively limit the current supplied to the installation 3 (phase current Iph).

[0053] The current limiter 20 here comprises an activation relay 21 for the current limitation (typically 30A), and a resistive component 22 connected in series with the relay 21. The relay 21 and the resistive component 22 are mounted in parallel with the switch 10 of the cut-off device 9.

[0054] More precisely, the relay 21 comprises a first terminal connected to the terminal of the switch 10 which is connected to the shunt 18, and a second terminal which is connected to a first terminal of the resistive component 22. The second terminal of the resistive component 22 is connected to the terminal of the switch 10 which is connected to the output terminal UP' of the counter 1.

[0055] The resistive component here is a PTC thermistor (Positive Temperature Coefficient thermistor).

[0056] Two examples of components that can be used are provided here: - Vishay 305C9 CTP: this component supports a peak current of 36A and acts as a current limiter when the current reaches a few amperes with a maximum energy consumed by the CTP of the order of a Watt; - CTP TDK EPCOS PTC C840: this component corresponds to a peak current of 4.1 A and acts as a current limiter when the current reaches a few amperes with a maximum energy consumed by the CTP of the order of a Watt.

[0057] The microcontroller 11 comprises an output 23 connected to the relay 21, by which the microcontroller 11 transmits to the relay 21 a control signal Cmde to control it.

[0058] Activation of the current limiter 20 to limit the current supplied to the installation consists first of all in closing the relay 21, then in opening the switch 10 of the cut-off device 9.

[0059] The monitoring method, which is implemented here by the microcontroller 11, is now described.

[0060] The purpose of the monitoring method is to limit or cut off the electricity to prevent the consumption of the installation 3 from being too high.

[0061] Each current day is divided into a predetermined set of at least one successive period Pk, k varying from 1 to N.

[0062] Each period Pk has duration Hk and we therefore have, for each current day:

[0063] = 24 hours

[0064] The durations Hk of these periods Pk are not all necessarily identical.

[0065] Consumption limitation and control are carried out period by period (and not daily, unless the current day has only one period).

[0066] These periods are preprogrammed in a predefined table which is stored in one of the memories 12 of the metrology part.

[0067] Each current day, for each current period, the microcontroller 11: • verifies a first predetermined condition associated with said current period; • if the first predetermined condition is verified, the microcontroller 11 activates the current limiter 20 to limit the current supplied to the installation 3 until the end of said current period.

[0068] In addition, for each current period, the microcontroller 11: • verifies a second predetermined condition associated with said current period; • if the second predetermined condition is verified, the microcontroller 11 controls the cut-off device 9 so as to cut the current supplied to the installation 3 until the end of said current period.

[0069] Here, the first predetermined condition is that a cumulative electrical consumption of the installation 3 over said current period is greater than a first predetermined threshold, and the second predetermined condition is that a cumulative electrical consumption of the installation 3 over said current period is greater than a second predetermined threshold itself greater than the first predetermined threshold.

[0070] By “consumption” we mean here any quantity representative of the electrical energy distributed to the installation: current, energy, power, etc.

[0071] The first predetermined threshold and / or the second predetermined threshold may depend on said current period and / or said current day and / or a period of the year to which said current day belongs.

[0072] It may indeed be relevant, for example, to authorize higher consumption in the morning (before leaving for work or school) and in the evening (on returning).

[0073] It may also be relevant, for example, to authorize higher consumption on weekends or on public holidays.

[0074] It may also be relevant, for example, to allow higher consumption in winter than in summer.

[0075] The first predetermined thresholds and the second predetermined thresholds are therefore preprogrammed thresholds which are associated in the predefined table of the memory 12 with the periods of the predetermined set of successive periods.

[0076] A particular embodiment of the monitoring method is described with reference to [Fig.2].

[0077] The method begins at step E0.

[0078] The variable “Period” is initialized to 0 (step El).

[0079] The microcontroller 11 closes the cut-off device 9 and opens the relay 21. The micro- controller 11 increments the Period variable:

[0080] Period = Period + 1 (step E2).

[0081] The following variables are initialized by the microcontroller 11 (step E3): - S_Summer_limitation = 30kWh*Hk / 24; - S_Limitation_winter = 62kWh*Hk / 24; - S_Limitation = S_Limitation_été if the current day belongs to a period from April to September inclusive, and = S_Limitation_hiver if the current day belongs to a period from October to March inclusive; - S_Breaker_summer = 45kWh*Hk / 24; - S_Breaker_winter = 80kWh*Hk / 24; - S_Breaker = S_Breaker_été if the current day belongs to a period from April to September inclusive, and = S_Breaker_hiver if the current day belongs to a period from October to March inclusive.

[0082] S_Limitation is the first predetermined threshold and S_Breaker is the second predetermined threshold.

[0083] It can be seen that, for each period, the predetermined thresholds are defined here in proportion to the duration of said period reported to the corresponding daily reference threshold (30kWh, 62kWh, 45kWh, 80kWh). Each current day, the thresholds therefore depend solely on the duration of the period concerned, and furthermore, the thresholds depend on the period of the year to which the current day belongs (of the season: summer or winter).

[0084] The microcontroller 11 then checks whether the present time corresponds to the end of the current period: step E4.

[0085] If this is the case, the microcontroller 11 checks whether the current period is the last of the current day, that is to say whether:

[0086] Period = N (step E5).

[0087] If this is the case, the method goes back to step EL. Otherwise, the method goes to step E2.

[0088] In step E4, if the present time does not correspond to the end of the current period, the microcontroller 11 compares the cumulative consumption of installation 3 over the current period with the first predetermined threshold (S_Limitation) and with the second predetermined threshold (S_Breaker): step E6.

[0089] If the cumulative consumption C is lower (here strictly) than the first predetermined threshold (and therefore the second predetermined threshold),

[0090] that is to say if:

[0091] C < S_Limitation and C < S_Breaker,

[0092] the microcontroller 11 does not perform any particular action and the method returns to step E4.

[0093] If the cumulative consumption is between the first predetermined threshold (here greater than or equal to this) and the second predetermined threshold (here less than strictly to this one),

[0094] that is to say if:

[0095] S_Limitation < C < S_Breaker,

[0096] the microcontroller 11 limits the current supplied to the installation 3. To do this, the microcontroller 11 activates the current limiter 20 by closing the relay 21 and then, subsequently, by opening the switch 10 of the cut-off device 9: step E7.

[0097] The microcontroller 11 then waits for the end of the current period (step E8), then the method moves on to step E5.

[0098] In step E6, if the cumulative consumption is greater (here greater than or equal to) the second predetermined threshold,

[0099] that is to say if:

[0100] S_Breaker < C,

[0101] the microcontroller 11 cuts the current supplied to the installation 3 by opening the relay 21 and the switch 10 of the cut-off device 9: step E9.

[0102] The microcontroller 11 then waits for the end of the current period (step E8), then the method moves to step E5.

[0103] In the embodiment which has just been presented, the verification of the predetermined conditions, making it possible to decide whether to limit or cut off the current during the current period, therefore comprises the step of comparing the cumulative consumption of the installation over the current period with predetermined thresholds.

[0104] In a second embodiment, the microcontroller 11 does not take into account the consumption thresholds. The microcontroller 11 simply checks, for each current period of the current day, in a predefined table preprogrammed in one of the memories 12, whether, during said current period, it is planned: to limit the current supplied to the installation; to cut the current; not to act at all on the current.

[0105] Thus, each current day, for each current period, the microcontroller 11 verifies a first predetermined condition associated with said current period. If the first predetermined condition is verified, the microcontroller 11 activates the current limiter to limit the current supplied to the installation 3 until the end of said current period.

[0106] The verification of the first predetermined condition consists of verifying, in the predefined table, that said current period is associated with first information according to which the current supplied to the installation must be limited during the entire said current period.

[0107] Similarly, the microcontroller 11 verifies a second predetermined condition associated with said current period. If the second predetermined condition is verified, the microcontroller 11 controls the cut-off member 9 so as to cut off the current provided to facility 3 until the end of said current period.

[0108] The verification of the second predetermined condition consists of verifying, in the predefined table, that said current period is associated with a second piece of information according to which the current supplied to the installation 3 must be cut off during the entire said current period.

[0109] Returning to [Fig.2], the implementation of this embodiment consists, in step E6, of checking in the predefined table whether an action is associated with the current period. The actions, corresponding to this embodiment, are indicated in bold in [Fig.2].

[0110] If no action is planned, the method returns to step E4.

[0111] If the action of limiting the current is planned, the method proceeds to step E7.

[0112] If the action of cutting the current is planned, the method proceeds to step E9.

[0113] With reference to [Fig.3], the invention can of course be implemented with an electric meter 101 which is not a single-phase meter, but a three-phase one.

[0114] The distribution network 102 therefore comprises three phases Ph and a neutral N.

[0115] The circuit of the counter 101 is shown for one phase only in [Fig.3], but the diagram is the same for all 3 phases.

[0116] A circuit breaker 104 is positioned at the border between the distribution network 102 and the installation 103.

[0117] For each phase Ph of the network 102, the meter 101 comprises an input terminal UP connected to said phase Ph of the network 102. The meter 101 also comprises an input terminal UN connected to the neutral N. The meter 101 further comprises three output terminals UP' and one output terminal UN' connected to the circuit breaker 104, which is itself connected to the installation 103.

[0118] The meter 101 comprises a neutral conductor 105 connected to the input terminal UN. The neutral conductor 105 is connected to an electrical ground 107 of the meter 101.

[0119] The meter 101 comprises three phase conductors 106, each phase conductor 106 being connected to a separate UP input terminal.

[0120] The meter 101 further comprises a cut-off member 109 which comprises three switches 110, i.e. a switch 110 mounted on each phase conductor 106.

[0121] The metrology part comprises a metrology microcontroller 111 which integrates one or more memories 112, a first CAN 114, a second CAN 115, a voltage measurement module 116 and a current measurement module 117.

[0122] For each phase, the metrology part also comprises a voltage sensor arranged to produce voltage measurements to evaluate a phase voltage Vph present on said phase Ph. The voltage sensor here comprises a voltage divider bridge comprising a first measurement resistor RI and a second measurement resistor R2 measurement. The first CAN 114 digitizes the Vml voltage.

[0123] The first CAN 114 therefore comprises three inputs each connected to the voltage divider bridge associated with one of the phases Ph.

[0124] The voltage measurement module 116 produces, from the samples produced by the first CAN 114, voltage measurements (effective) making it possible to evaluate the phase voltages Vph.

[0125] For each phase Ph, the metrology part also comprises a current sensor arranged to produce current measurements representative of a phase current Iph flowing on the phase conductor 106. The current sensor comprises a toroid 118 mounted on the phase conductor 106 upstream of the switch 110 of the cut-off member 109. A third measurement resistor R3 is mounted between the output terminals of the toroid 118.

[0126] The metrology part also comprises a current measurement chain 119 having a known gain. The current measurement chain 119 is connected to one terminal of the third measurement resistor R3, the other terminal of the measurement resistor R3 being connected to ground 107.

[0127] The second CAN 115 digitizes the voltage Vm2.

[0128] The second CAN 115 therefore comprises three inputs each connected to the current measurement chain 117 associated with one of the phases Ph.

[0129] The current measurement module 117 produces, from the samples produced by the second CAN 115, current measurements making it possible to evaluate the phase currents Iph.

[0130] The meter 101 further comprises a current limiter 120 arranged to selectively limit the current supplied to the installation 3 (including the phase currents).

[0131] For each phase Ph, the current limiter 120 is similar to that described in [Fig.l], and comprises an activation relay 121 of the current limitation, and a resistive component 122 connected in series with the relay 121. The relay 121 and the resistive component 122 are mounted in parallel with the switch 110 of the cut-off member 109 which is mounted on said phase Ph.

[0132] The components of the limiter 120 (relay, resistive component of the PTC type), presented for the single-phase meter, can be used for the three-phase meter.

[0133] The microcontroller 111 comprises a single output 123 connected to the three relays, by which the microcontroller 111 transmits to the relays the same control signal Cmde to control them.

[0134] The command Cmde is therefore unique for the three phases Ph so that it is simultaneous (the three activation relays 121 are either all three open or all three closed).

[0135] The monitoring method (and in particular the embodiment presented in [Fig.2]) is implemented in the same way as in the case of single-phase meter 1.

[0136] To limit the current, the microcontroller 111 first closes the three relays 121 simultaneously, then opens the three switches 110 of the cut-off device 109 simultaneously.

[0137] To cut off the current, the microcontroller 111 opens the three relays 121 simultaneously, and opens the three switches 110 of the cut-off device 109 simultaneously.

[0138] It should be noted that the service, i.e. the monitoring and limitation of consumption, must in practice be "authorized" by the operator (i.e. by the energy distributor or by the network manager), in particular when equipment sensitive to the user's health is present at the user's premises.

[0139] It is also noted that the values ​​of the durations Hk of the periods Pk are typically deduced from the typical consumption profile corresponding to the load curves which give consumption values ​​every 10 minutes or every 1 / 2 hour typically.

[0140] Of course, the invention is not limited to the embodiments described but encompasses any variant falling within the scope of the invention as defined by the claims.

[0141] The invention of course applies to any multi-phase meter (not just three-phase).

[0142] The current limiter may be different from that described here. It could be, for example, for each phase conductor, a single component integrating a switch (or relay) and a resistive component, and mounted directly on the phase conductor.

[0143] It has been indicated that the monitoring method is implemented in the microcontroller of the metrology part.

[0144] The monitoring method could also be implemented in the microcontroller of the application part.

[0145] More generally, the monitoring method can be implemented in any processing unit which comprises at least one processing component and at least one memory connected or integrated in one of the processing components. The processing component is for example a “general purpose” processor, a processor specialized in signal processing (or DSP, for Digital Signal Processor), a microcontroller (as is the case here), or a programmable logic circuit such as an FPGA (for Field Programmable Gate Arrays) or an ASIC (for Application Specific Integrated Circuit).

[0146] The monitoring method, i.e. monitoring consumption and controlling the current limiter and the cut-off device, is not necessarily implemented implemented entirely within the meter. The monitoring method could be implemented at least partially outside the meter.

[0147] For example, the operator (i.e. the energy distributor or the network manager) can remotely manage the command Cmde of the limiter relay(s) and that of the switch(es) of the cut-off device according to daily time periods pre-set for each end user. Thus, in certain time slots of the day, the operator can put the current limiter into service at the user's premises or a power cut for a pre-defined duration. The operator then transmits the commands to the meter via any means of communication (for example cellular, by power line carrier, etc.), and remotely controls the limiter and the cut-off device (via the microcontroller 11 possibly).

[0148] The operator could also acquire the consumption measurements produced by the meter (which transmits them via the means of communication just mentioned), then check, period by period, the predetermined conditions. The operator then transmits the commands to the meter.

Claims

Claims

1. Monitoring method, using an electric meter (1; 101) arranged to measure an electric consumption of an installation (3; 103) and comprising a current limiter (20; 120) arranged to selectively limit a current supplied to the installation, the monitoring method comprising the steps, repeated each current day, for each current period of a predetermined set of at least one successive period defined in the current day, of: • checking a first predetermined condition associated with said current period; • if the first predetermined condition is verified, activating the current limiter (20; 120) to limit the current supplied to the installation (3; 103) until the end of said current period, the electric meter (1; 101) further comprising a cut-off member (9;109) arranged to selectively cut off the current supplied to the installation, the monitoring method further comprising the steps, for each current period, of: • checking a second predetermined condition associated with said current period; • if the second predetermined condition is verified, controlling the cut-off member (9; 109) so as to cut off the current supplied to the installation until the end of said current period.;

2. Monitoring method according to claim 1, in which the first predetermined condition is that a cumulative electrical consumption of the installation (3; 103) over said current period is greater than a first predetermined threshold.

3. Monitoring method according to claim 2, in which the second predetermined condition is that a cumulative electrical consumption of the installation (3; 103) over said current period is greater than a second predetermined threshold itself greater than the first predetermined threshold.

4. Monitoring method according to one of claims 2 or 3, in which the first predetermined threshold and / or the second predetermined threshold depend on said current period and / or said current day. and / or a period of the year to which the said current day belongs.

5. Monitoring method according to claim 1, in which the verification of the first predetermined condition consists of verifying, in a predefined table, that said current period is associated with first information according to which the current supplied to the installation (3; 103) must be limited during the whole of said current period.

6. Monitoring method according to claim 5, wherein the verification of the second predetermined condition consists of verifying, in the predefined table, that said current period is associated with a second piece of information according to which the current supplied to the installation must be cut off during the entirety of said current period.

7. Monitoring method according to one of the preceding claims, the meter further comprising a cut-off member (9; 109) arranged to selectively cut off the current supplied to the installation, the cut-off member comprising a switch (10; 110) for each phase of a distribution network to which the installation is connected, the current limiter (20; 120) comprising, for each switch of the cut-off member, a relay (21; 121) and a resistive component (22; 122) mounted in parallel with the switch, the activation of the current limiter to limit the current supplied to the installation comprising the steps of closing the relay(s) simultaneously and then, subsequently, opening the switch(es) simultaneously.

8. Electricity meter (1; 101) arranged to measure an electrical consumption of an installation (3; 103), the electricity meter comprising a current limiter (20; 120) arranged to selectively limit a current supplied to the installation, the electricity meter further comprising a processing unit (11; 111) arranged to implement the monitoring method according to one of the preceding claims.

9. An electric meter according to claim 8, the electric meter further comprising a cut-off member (9; 109) arranged to selectively cut off the current supplied to the installation, the cut-off member comprising a switch (10; 110) for each phase of a distribution network to which the installation is connected, the current limiter (20; 120) comprising, for each switch of the cut-off member, a relay (21; 121) and a resistive component (22; 122) mounted in parallel with the switch, the processing unit being arranged, to activate the current limiter, to close the relay(s) simultaneously and then,

10. then, to open the switch(es) simultaneously. Computer program comprising instructions which cause the processing unit (11; 111) of the electricity meter (1; 101) according to one of claims 8 to 9 to execute the steps of the monitoring method according to one of claims 1 to 7.

11. A computer-readable recording medium on which the computer program according to claim 10 is recorded.