Design assistance system and design assistance method
Patent Information
- Application Number
- JP2021193187
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2021-11-29
- Publication Date
- 2024-11-28
- Estimated Expiration
- 2041-11-29
AI Technical Summary
Existing BIM models face challenges in balancing data capacity with user convenience, as embedding excessive information increases storage requirements, while limiting information reduces efficiency and user convenience.
A design support system and method that embeds code information in BIM parts instead of additional parameters, storing these parameters externally to manage data volume, and automates drawing creation using a parameter acquisition and changing unit to facilitate user interaction and customization.
This approach suppresses data volume growth in BIM models, enhances user convenience by automating drawing processes, and allows flexible customization, improving communication and efficiency between users.
Smart Images

Figure 00000000_0000_ABST
Abstract
Description
Technical Field
[0004] ,
[0006] , , , ,
[0005] , , , , ,
[0001] The present disclosure relates to a design support system and a design support method.
Background Art
[0002] BIM (Building Information Modeling), which is a digital model used in architecture, is known. In a 3D building BIM model created on a computer, BIM parts related to facilities of the construction object are incorporated (see Patent Document 1).
Prior Art Documents
Patent Documents
[0003]
Patent Document 1
Summary of the Invention
Problems to be Solved by the Invention
[0004] As described in Patent Document 1, various attribute information can be embedded in BIM parts. However, if too much information is embedded in BIM parts, the data capacity of each BIM part will increase, and a large amount of memory resources will be required for the BIM model. On the other hand, if the information embedded in BIM parts is limited to a minimum, the merit of improving the efficiency of the construction process obtained by utilizing the information embedded in BIM parts will be impaired. That is, the convenience of users using the BIM model will be impaired. <000002A design support system relating to one aspect of this disclosure includes: a parts providing unit that provides a BIM part relating to the equipment of a building object, which includes basic parameters for displaying the three-dimensional shape of the BIM part in a BIM model of the building object and code information uniquely assigned to the BIM part, in a manner that can be incorporated into a BIM model; a storage unit that stores additional parameters for creating drawings relating to the construction or manufacturing of the BIM part in association with the code information of the BIM part; a parameter acquisition unit that acquires the code information of a BIM part included in a BIM model created by a first user and acquires additional parameters associated with the acquired code information from the storage unit; and a drawing creation unit that creates a drawing of the BIM part based on the additional parameters acquired by the parameter acquisition unit.
[0007] A design support method relating to other aspects of this disclosure includes the steps of: providing a BIM part relating to the equipment of a building object in a manner that can be incorporated into a BIM model, the BIM part including basic parameters for displaying the three-dimensional shape of the BIM part in a BIM model of the building object and code information uniquely assigned to the BIM part; obtaining code information of a BIM part included in a BIM model created by a first user, and obtaining additional parameters associated with the obtained code information by accessing a storage unit that stores additional parameters for creating drawings relating to the construction or manufacture of the BIM part in association with the code information of the BIM part; and creating a drawing of the BIM part based on the obtained additional parameters.
[0008] In the design support system and method described above, code information is embedded instead of embedding information (additional parameters) for creating drawings into the BIM part itself. Since additional parameters contain a large amount of information, storing such information in an external storage unit rather than within the BIM part suppresses the increase in data capacity of individual BIM parts. As a result, the increase in data capacity of the BIM model can be suppressed. Furthermore, in the design support system and method described above, the parameter acquisition unit acquires additional parameters associated with the code information embedded in the BIM part, and the drawing creation unit creates drawings based on these additional parameters. This configuration automates and simplifies the drawing creation process for BIM parts, thereby effectively improving user convenience.
[0009] The above design support system may further include a parameter modification unit that performs a process to modify at least some of the additional parameters acquired by the parameter acquisition unit based on the operation content entered by the first user, and the drawing creation unit may create a drawing of the BIM part based on the additional parameters modified by the parameter modification unit. With the above configuration, the first user can freely customize the additional parameters that are pre-associated with the BIM part. This makes it possible to flexibly adjust the contents of the drawing related to the BIM part, thereby further improving user convenience.
[0010] The above design support system may further include a drawing presentation unit that presents drawings created by the drawing creation unit to a second user different from the first user, and an approval processing unit that receives approval operations for the drawings from the second user. With this configuration, the process of presenting the created drawings to the second user and the process of receiving approval operations for the drawings from the second user can be carried out smoothly. This further improves user convenience.
[0011] The approval processing unit may accept comments on the drawing from the first or second user, and may associate the comments with the drawing so that they are presented to both the first and second users when comments are entered. With the above configuration, it is possible to enable the first or second user to enter comments on the drawing, while also sharing the content of the entered comments between the first and second users. This facilitates communication between the first and second users, thereby streamlining the flow until the drawing is approved by the second user. This further improves user convenience.
[0012] The additional parameters may include construction drawing parameters necessary for creating construction drawings of BIM parts, and separate drawing parameters necessary in addition to the construction drawing parameters for creating separate drawings of BIM parts. The drawing creation unit may have a construction drawing creation unit that creates construction drawings of BIM parts based on construction drawing parameters, and a separate drawing creation unit that creates separate drawings of BIM parts based on separate drawing parameters. The drawing presentation unit may present the construction drawings created by the construction drawing creation unit to a second user. The approval processing unit may accept approval operations for the construction drawings from the second user. The separate drawing creation unit may create separate drawings based on the separate drawing parameters after the approval operation for the construction drawings has been accepted by the approval processing unit. According to the above configuration, the flow from the creation and approval of construction drawings to the creation of separate drawings after the construction drawings have been approved can be streamlined. This further improves user convenience. [Effects of the Invention]
[0013] According to this disclosure, it is possible to provide a design support system and design support method that can improve user convenience while suppressing the increase in data capacity of BIM models. [Brief explanation of the drawing]
[0014] [Figure 1]FIG. 1 is a diagram showing an example of the functional configuration of a design support system according to an embodiment. [Figure 2] FIG. 2 is a diagram showing an example of the hardware configuration of a computer that constitutes the design support system shown in FIG. 1. [Figure 3] FIG. 3 is a diagram showing an example of a BIM part and a BIM model. [Figure 4] FIG. 4 is a diagram showing an example of the data structure of a BIM part and an example of the data structure of information stored for each BIM part in the storage unit. [Figure 5] FIG. 5 is a diagram showing an example of construction drawing parameters. [Figure 6] FIG. 6 is a diagram showing an example of bar chart parameters. [Figure 7] FIG. 7 is a diagram showing an example of a construction drawing. [Figure 8] FIG. 8 is a diagram showing an example of a bar chart. [Figure 9] FIG. 9 is a flowchart showing an example of the operation of the design support system shown in FIG. 1.
MODE FOR CARRYING OUT THE INVENTION
[0015] Hereinafter, an embodiment of the present disclosure will be described in detail with reference to the drawings. In the following description, the same or corresponding elements are denoted by the same reference numerals, and duplicate descriptions are omitted.
[0016] FIG. 1 is a diagram showing an example of the functional configuration of a design support system 10 according to an embodiment. The design support system 10 is a system that supports design and drawing creation using a BIM model of a construction object.
[0017] The design support system 10 may be configured by one computer, or may be configured by a plurality of computers such as cloud computing. In this case, the plurality of computers are logically connected to each other via a communication network so as to be communicable with each other, and function as one design support system
[0018] The design support system 10 is communicably connected to the worker terminal 2 and the constructor terminal 3 via a communication network. The communication network may be composed of either wired or wireless. Examples of the communication network include the Internet, a WAN (Wide Area Network), and a mobile communication network.
[0019] The worker terminal 2 acquires BIM parts from the design support system 10 and uses the acquired BIM parts to generate (edit) a BIM model. Further, the worker terminal 2 instructs the design support system 10 to create drawings (construction drawings and exploded views) of the BIM parts included in the BIM model. The worker terminal 2 is operated by a worker (first user). The worker is, for example, a subcontractor who has been commissioned by a constructor (second user) who undertakes the construction of the construction object to create construction drawings and exploded views of the facilities of the construction object. A dedicated application for displaying and editing the BIM model and the like is installed on the worker terminal 2.
[0020] The constructor terminal 3 is a terminal operated by a constructor. The constructor terminal 3 at least has a function of displaying construction drawings created by a worker, a function of inputting comments on the construction drawings, and a function of performing an approval operation on the construction drawings.
[0021] Figure 2 shows an example of the hardware configuration of the computer 100 that constitutes the design support system 10 shown in Figure 1. As shown in Figure 2, the computer 100 includes a processor 101, main memory 102, auxiliary storage 103, communication device 104, input device 105, and output device 106. An example of the processor 101 is a CPU (Central Processing Unit). The main memory 102 consists of RAM (Random Access Memory) and ROM (Read Only Memory), etc. An example of the auxiliary storage 103 is semiconductor memory and hard disk drive. An example of the communication device 104 is a network card and wireless communication module. An example of the input device 105 is a keyboard and mouse. An example of the output device 106 is a display. Note that the worker terminal 2 and the contractor terminal 3 may also be configured with computers similar to computer 100.
[0022] As shown in Figure 1, the design support system 10 includes, as functional components, a parts supply unit 11, a parameter acquisition unit 12, a parameter modification unit 13, a construction drawing creation unit 14 (drawing creation unit), a drawing presentation unit 15, an approval processing unit 16, a breakdown drawing creation unit 17 (drawing creation unit), and a storage unit 18.
[0023] The parts supply unit 11 provides BIM parts related to the equipment of the construction object in a manner that can be incorporated into the BIM model. In this embodiment, as an example, the construction object is the interior part of a building, and the equipment of the construction object is a steel door fitting (SD fitting). However, the combination of the construction object and equipment is not limited to the above example. Furthermore, the manner in which BIM parts are provided in a manner that can be incorporated into the BIM model is not limited to a specific form of provision. For example, the parts supply unit 11 may allow the BIM parts to be downloaded to the worker terminal 2, or it may provide the BIM parts to the user in a manner that allows them to be used (selected) on a web-operated platform provided by the design support system 10. In this embodiment, the former manner will be mainly described.
[0024] Figure 3 shows an example of BIM parts and a BIM model. As shown in Figure 3, in this embodiment, the parts supply unit 11 provides the worker terminal 2 with a BIM parts library 20 containing multiple BIM parts 21 related to SD joinery. The BIM parts 21 are digital data that can be incorporated into a BIM model. In this embodiment, as an example, the BIM parts 21 are configured as files (RFA files) in a format that can be imported into Autodesk Revit®, a BIM software.
[0025] In the example shown in Figure 3, the BIM parts library 20 includes five BIM parts 21, but the types and number of BIM parts 21 included in the BIM parts library 20 are not limited to those shown above. The BIM parts library 20 may include multiple BIM parts 21 with pre-prepared standard specifications for each type of door, such as single-leaf doors, double-leaf doors, parent-child doors, single-sliding doors, pocket doors, sliding doors, sliding-through doors, automatic doors, etc. The five BIM parts 21 shown in Figure 3 are examples of BIM parts prepared for double-leaf doors.
[0026] The BIM model M shown in Figure 3 is a BIM model generated using BIM parts 21 provided by the parts supply unit 11. The BIM model M is generated and displayed on the worker terminal 2 by, for example, the worker operating a dedicated application installed on the worker terminal 2 (in this embodiment, BIM software capable of importing RFA files). That is, the worker downloads the necessary BIM parts 21 (or a BIM parts library 20 containing a complete set of BIM parts 21) from the parts supply unit 11, imports the downloaded BIM parts 21 into the dedicated application, and places them in the BIM model M. This generates a BIM model M with the BIM parts 21 incorporated.
[0027] Each BIM part 21 has a data structure D1 shown in Figure 4. That is, each BIM part 21 contains basic parameters and code information.
[0028] Basic parameters are information for displaying the 3D shape of BIM part 21. For example, basic parameters include rendering data for displaying BIM part 21 in 3D on BIM model M. Basic parameters may also include the shape, dimensions, material, specifications, etc. of SD joinery (i.e., data corresponding to the joinery schedule). Thus, basic parameters are data that shows basic information about SD joinery corresponding to BIM part 21.
[0029] The code information is a code (identification information) uniquely assigned to the BIM part 21. For example, if the BIM part 21 is provided as an RFA file as described above, and each is assigned a unique file name (for example, "SD001.rfa" as shown in Figure 3), then the file name of the BIM part 21 (for example, "SD001" with the extension removed from the file name) can be used as the code information. However, the code information is not limited to the file name; any information that can uniquely identify the BIM part 21 can be used as the code information.
[0030] The storage unit 18 stores additional parameters for creating drawings related to the construction or manufacturing of the BIM part 21, associated with the code information of the BIM part 21. In this embodiment, the storage unit 18 stores data having the data structure D2 shown in Figure 4 for each BIM part 21. The data structure D2 is a data structure that associates the additional parameters, construction drawing parameters and individual drawing parameters, with the code information.
[0031] Construction drawing parameters are the parameters necessary to create construction drawings for BIM Part 21. Individual drawing parameters are the parameters necessary in addition to construction drawing parameters to create individual drawings for BIM Part 21. In other words, individual drawing parameters are parameters that supplement the information necessary to create individual drawings that is lacking in the construction drawing parameters alone. Individual drawings are drawings that include information showing detailed manufacturing procedures for manufacturing BIM Part 21 (SD joinery) (for example, procedures for bending metal sheets). On the other hand, construction drawings are drawings that are a preliminary stage to individual drawings (drawings that do not include detailed manufacturing procedure information like individual drawings) and are mainly used to allow contractors to confirm the design content.
[0032] Figure 5 shows an example of construction drawing parameters. In the example in Figure 5, the construction drawing parameters include a parameter ID, which is an identifier for identifying the parameter, and a design value associated with that parameter ID. Each parameter has defined settable values. The construction drawing parameters shown in Figure 5 indicate that the basic type is "Exterior (1)", the structure is "Not specified (0)", the exterior finish is "Not specified (0)", the interior finish is "Not specified (0)", and the floor finish is "Mortar (1)". Note that the parameters shown in Figure 5 are only a part of the parameters included in the construction drawing parameters, and in addition to the parameters shown in Figure 5, the construction drawing parameters include information to identify various configurations necessary for creating the construction drawing of BIM part 21.
[0033] Figure 6 shows an example of individual drawing parameters. The individual drawing parameters shown in Figure 6 indicate that the shape of the upper frame (base frame) corresponds to the pre-registered "0", the shape of the upper frame (back of additional frame) corresponds to the pre-registered "1", the shape of the upper frame (front of additional frame) corresponds to the pre-registered "1", the shape of the front side recess corresponds to the pre-registered "0", the shape of the back side recess corresponds to the pre-registered "0", and the shape of the door frame (frame input) corresponds to the pre-registered "0". Note that the parameters shown in Figure 6 are only a part of the individual drawing parameters of BIM part 21 (SD joinery), and the individual drawing parameters include information to identify various configurations necessary for creating the individual drawing of BIM part 21, in addition to the parameters shown in Figure 6. Examples of individual drawing parameters other than those shown in Figure 6 include product information of the hardware used in BIM part 21, information indicating the mounting position, information indicating the bending position and bending direction of the bending process, etc.
[0034] The parameter acquisition unit 12 acquires code information for BIM parts 21 included in the BIM model and acquires additional parameters associated with the acquired code information from the storage unit 18. For example, the parameter acquisition unit 12 acquires code information for BIM parts 21 specified by the worker from among the BIM parts 21 included in the BIM model M created by the worker by operating the worker terminal 2. Then, the parameter acquisition unit 12 acquires additional parameters (construction drawing parameters or individual drawing parameters) corresponding to the acquired code information.
[0035] The parameter modification unit 13 performs a process to modify at least some of the additional parameters acquired by the parameter acquisition unit 12 based on the operation content entered by the operator. For example, the parameter modification unit 13 generates a setting screen (configuration screen) for editing the setting values of construction drawing parameters as shown in Figure 5, or the setting values of individual drawing parameters as shown in Figure 6, and displays it on the operator terminal 2. The configuration screen may display default values (i.e., values set for construction drawing parameters or individual drawing parameters associated with BIM part 21). The operator can change the default values to other setting values by performing input operations on the configuration screen. In other words, the parameter modification unit 13 accepts operations to change the default values of additional parameters (construction drawing parameters or individual drawing parameters) to other settings. The information of the additional parameters after the operation is modified is stored separately from the additional parameter information stored in the storage unit 18 beforehand.
[0036] The construction drawing creation unit 14 creates construction drawings (drawings) of the BIM parts 21 based on the construction drawing parameters acquired by the parameter acquisition unit 12. For example, the construction drawing creation unit 14 has a construction drawing creation program for creating construction drawings in a predetermined format based on the construction drawing parameters. In this case, the construction drawing creation unit 14 can automatically generate construction drawings according to the construction drawing parameters by inputting the construction drawing parameters acquired by the parameter acquisition unit 12 into the construction drawing creation program.
[0037] Furthermore, if at least some of the construction drawing parameters have been changed by the parameter modification unit 13 described above, the construction drawing creation unit 14 will create a construction drawing of the BIM part 21 based on the construction drawing parameters after they have been changed by the parameter modification unit 13.
[0038] Figure 7 shows an example of a construction drawing. As shown in Figure 7, for example, the construction drawing 30 may include a front view 31 of the BIM part 21, a side section view 32, a plan view 33, and text information 34 (for example, information presented in tabular format) that shows detailed information such as the frame shape, parts, and finishes.
[0039] The drawing presentation unit 15 presents the construction drawings (see Figure 7) created by the construction drawing creation unit 14 to the contractor. For example, the drawing presentation unit 15 transmits the display information of the construction drawings to the contractor terminal 3. This allows the contractor to confirm the construction drawings displayed on the display of the contractor terminal 3.
[0040] The approval processing unit 16 receives approval operations for construction drawings from the contractor. For example, the approval processing unit 16 receives information from the contractor terminal 3 indicating the approval operation entered by the contractor operating the contractor terminal 3, thereby accepting the approval operation.
[0041] Furthermore, if the contractor is not satisfied with the contents of the construction drawings and wishes to revise them, the contractor will reject the construction drawings without approving them. In that case, the worker can change (revise) the contents of the construction drawings created by the construction drawing creation unit 14 by modifying the BIM model M or by changing the construction drawing parameters by performing operations on the parameter change unit 13 described above. The revised construction drawings are then presented to the contractor (contractor terminal 3) by the drawing presentation unit 15. In order to facilitate such communication between the worker and the contractor, the approval processing unit 16 may be equipped with the following functions.
[0042] In other words, the approval processing unit 16 accepts comments on the construction drawings from the worker or contractor, and may associate the comments with the construction drawings so that they are presented to both the worker and the contractor when comments are entered. For example, the approval processing unit 16 obtains comments entered by the worker via the worker terminal 2, or comments entered by the contractor via the contractor terminal 3. The comments may be placed at any location on the construction drawing (see Figure 7). In other words, the approval processing unit 16 may provide the worker terminal 2 and the contractor terminal 3 with an interface for inserting comments at any location on the construction drawing. For example, the approval processing unit 16 may generate screen information that displays the construction drawing and allows the input of comments on the construction drawing as described above, and send it to the worker terminal 2 and the contractor terminal 3. The approval processing unit 16 may then receive the comments entered on the screen information from the worker terminal 2 or the contractor terminal 3, and send the screen information reflecting the comments back to the worker terminal 2 and the contractor terminal 3. This mechanism makes it possible to facilitate communication between workers and contractors through the interface (screen information) provided by the design support system 10 (approval processing unit 16).
[0043] The individual drawing creation unit 17 creates individual drawings (drawings) of the BIM parts 21 based on the individual drawing parameters acquired by the parameter acquisition unit 12. Note that, in creating the individual drawings, parameters from the construction drawing parameters that are also necessary for individual drawing creation may be used in conjunction with the individual drawing parameters. For example, the individual drawing creation unit 17 has an individual drawing creation program for creating individual drawings in a predetermined format based on individual drawing parameters (and necessary construction drawing parameters; the same applies hereinafter). In this case, the individual drawing creation unit 17 can automatically generate individual drawings corresponding to the individual drawing parameters by inputting the individual drawing parameters acquired by the parameter acquisition unit 12 into the individual drawing creation program.
[0044] Furthermore, if at least some of the breakdown drawing parameters have been changed by the parameter modification unit 13 described above, the breakdown drawing creation unit 17 will create a breakdown drawing of the BIM part 21 based on the breakdown drawing parameters after they have been changed by the parameter modification unit 13.
[0045] Figure 8 shows an example of a breakdown drawing. The breakdown drawing 40 shown in Figure 8 is an example of a breakdown drawing that includes information (e.g., bend shape, bend dimensions, etc.) necessary for bending the main body portion (the part formed from a metal plate) of the BIM part 21, which is an SD building component.
[0046] Next, with reference to Figure 9, an example of the operation of the design support system 10 (including a design support method according to one embodiment) will be described.
[0047] In step S1, the parts supply unit 11 provides the BIM parts 21 (see Figure 3) to the worker (worker terminal 2) in a manner that allows them to be incorporated into the BIM model M (see Figure 3). This enables the worker to create the BIM model M using the BIM parts 21 by operating the worker terminal 2.
[0048] In step S2, the parameter acquisition unit 12 acquires code information of BIM parts 21 included in the BIM model created by the worker operating the worker terminal 2, and acquires construction drawing parameters (see Figure 5) associated with the acquired code information from the storage unit 18.
[0049] If the worker modifies the construction drawing parameters via the worker terminal 2 (step S3: YES), the parameter modification unit 13 modifies at least a portion of the construction drawing parameters acquired by the parameter acquisition unit 12 based on the operation entered by the worker (step S4). On the other hand, if no modification operation is performed on the construction drawing parameters (step S3: NO), the process in step S4 is skipped.
[0050] In step S5, the construction drawing creation unit 14 creates a construction drawing of the BIM part 21 (see Figure 7) based on the construction drawing parameters acquired by the parameter acquisition unit 12. If at least some of the construction drawing parameters have been changed in step S4, the construction drawing creation unit 14 creates a construction drawing of the BIM part 21 based on the changed construction drawing parameters.
[0051] In step S6, the drawing presentation unit 15 presents the construction drawings created by the construction drawing creation unit 14 to the contractor.
[0052] In step S7, the approval processing unit 16 accepts the contractor's approval operation for the construction drawings. By using the comment input and sharing function of the approval processing unit 16 described above, comments may be exchanged between the worker and the contractor as needed. Furthermore, if it becomes necessary to modify the construction drawings (i.e., modify the construction drawing parameters), the process in step S4 may be executed again.
[0053] In step S8, the parameter acquisition unit 12 acquires the loose-frame parameters (see Figure 6) associated with the code information of the BIM part 21 acquired in step S2 from the storage unit 18.
[0054] In step S9, the breakdown drawing creation unit 17 creates a breakdown drawing of the BIM part 21 (see Figure 8) based on the breakdown drawing parameters acquired by the parameter acquisition unit 12. At least some of the breakdown drawing parameters may be modified by the parameter modification unit 13, similar to the construction drawing parameters. In this case, the breakdown drawing creation unit 17 creates a breakdown drawing of the BIM part 21 based on the modified breakdown drawing parameters. This completes the series of processes of the design support system 10.
[0055] In the design support system 10 and design support method described above (Figure 9), code information is embedded in the BIM part 21 itself instead of embedding information (additional parameters) for creating drawings (in this embodiment, construction drawings or individual drawings). Since additional parameters contain a large amount of information, storing such information in an external storage unit 18 rather than within the BIM part 21 suppresses the increase in data capacity of individual BIM parts 21. As a result, the increase in data capacity of the BIM model M can be suppressed. Furthermore, in the design support system 10 and design support method described above, the parameter acquisition unit 12 acquires additional parameters associated with the code information embedded in the BIM part 21, and the drawing creation unit (construction drawing creation unit 14 or individual drawing creation unit 17) is configured to create drawings (construction drawings or individual drawings) based on these additional parameters. This configuration automates and simplifies the drawing creation process for BIM parts 21, thereby effectively improving user convenience (mainly for workers).
[0056] Furthermore, additional parameters may constitute confidential information, including know-how, that the administrator of the design support system 10 (i.e., the provider of services using the design support system 10) has spent a considerable amount of time designing. By storing such confidential information outside of the BIM part 21 and configuring it so that only the design support system 10 can access it, the confidentiality of the confidential information related to the BIM part 21 can be improved, and the leakage (disclosure) of confidential information can be prevented.
[0057] Furthermore, the design support system 10 includes a parameter modification unit 13, and the drawing creation unit (construction drawing creation unit 14 or individual drawing creation unit 17) creates drawings (construction drawings or individual drawings) of the BIM part 21 based on the additional parameters modified by the parameter modification unit 13. With the above configuration, the worker can freely customize the additional parameters that are pre-associated with the BIM part 21. This makes it possible to flexibly adjust the content of the drawings related to the BIM part 21, thereby further improving the convenience for the user (mainly the worker).
[0058] Furthermore, the design support system 10 includes a drawing presentation unit 15 and an approval processing unit 16. With this configuration, it becomes possible to smoothly carry out the process of presenting the created drawings (construction drawings in this embodiment) to the contractor and the process of receiving the contractor's approval operation for the drawings. This further improves the convenience for users (both workers and contractors).
[0059] Furthermore, the approval processing unit 16 accepts comments on the drawing (in this embodiment, the construction drawing) from the worker or contractor, and when a comment is entered, it associates the comment with the drawing so that the comment is presented to both the worker and the contractor. With the above configuration, it is possible to enable the worker or contractor to enter comments on the drawing, while also sharing the content of the entered comments between the worker and the contractor. This facilitates communication between the worker and the contractor, and streamlines the flow until the drawing is approved by the contractor. This further improves the convenience for users (both workers and contractors).
[0060] Furthermore, in the design support system 10, construction drawings and individual drawings are created in stages as follows: First, the construction drawing creation unit 14 creates a construction drawing based on the construction drawing parameters, and then the drawing presentation unit 15 presents the construction drawing to the contractor (contractor terminal 3). Subsequently, the approval processing unit 16 receives the contractor's approval operation for the construction drawing. After the approval processing unit 16 has received the approval operation for the construction drawing (i.e., after the contents of the construction drawing have been finalized), the individual drawing creation unit 17 creates the individual drawing based on the individual drawing parameters. With the above configuration, the flow from the creation and approval of construction drawings to the creation of individual drawings after the construction drawings have been approved can be streamlined. This further improves the convenience for users (both workers and contractors).
[0061] The design support system and design support method relating to this disclosure are not limited to the embodiments described above. Some functions included in the design support system 10 of the embodiments described above may be omitted or replaced with other functions. For example, if it is not necessary to obtain approval from the contractor for the construction drawings (i.e., if it is only necessary to create individual drawings to proceed to the manufacturing process of the joinery), the construction drawing creation unit 14, the drawing presentation unit 15, and the approval processing unit 16 may be omitted.
[0062] Furthermore, in the above embodiment, examples of drawing creation units included in the design support system were given as a construction drawing creation unit 14 for creating construction drawings and a separate drawing creation unit 17 for creating separate drawings. However, the types of drawings created by the drawing creation unit are not limited to construction drawings and separate drawings. The design support system may be configured to create drawings other than construction drawings and separate drawings using a mechanism similar to that of the above embodiment. That is, the storage unit 18 may store code information embedded in the BIM part 21 and parameters necessary to create any drawing related to the BIM part 21 in association with each other.
[0063] Furthermore, in the above embodiment, the process of generating (editing) and displaying the BIM model M was performed by the worker terminal 2 (i.e., a dedicated application installed on the worker terminal 2). However, the design support system 10 may perform the process of generating (editing) and displaying the BIM model M based on user operations via the worker terminal 2. In other words, the design support system 10 may include BIM software for generating (editing) and displaying the BIM model M.
[0064] Furthermore, in the above embodiment, a worker was given as an example of the first user and a contractor as an example of the second user, but the combination of the first user and the second user is not limited to the combination of worker and contractor described above. For example, at the stage of designing the BIM model M of the object to be constructed, a design officer of a design office or construction company may use the design support system 10 (mainly BIM parts provided by the parts supply unit 11) as the first user. [Explanation of Symbols]
[0065] 10...Design support system, 11...Parts supply unit, 12...Parameter acquisition unit, 13...Parameter modification unit, 14...Construction drawing creation unit (drawing creation unit), 15...Drawing presentation unit, 16...Approval processing unit, 17...Individual drawing creation unit (drawing creation unit), 18...Storage unit, 21...BIM parts, 30...Construction drawings, 40...Individual drawings, M...BIM model.
Claims
1. A part providing unit that acquires a BIM part related to equipment of a construction object, the BIM part including basic parameters for displaying a three-dimensional shape of the BIM part in a BIM model of the construction object and code information uniquely assigned to the BIM part, in a manner that can be incorporated into the BIM model; A storage unit that stores additional parameters for creating drawings related to the construction or manufacture of the BIM part in association with the code information of the BIM part; A parameter acquisition unit that acquires the code information of the BIM part included in the BIM model created by a first user and acquires the additional parameters associated with the acquired code information from the storage unit; A drawing creation unit that creates the drawing of the BIM part based on the additional parameters acquired by the parameter acquisition unit; a parameter change unit that executes a process of changing at least a part of the additional parameters acquired by the parameter acquisition unit based on the operation content input by the first user; Equipped with The drawing creation unit creates the drawing of the BIM part based on the additional parameters after being changed by the parameter change unit. Design support system.
2. a drawing presenting unit that presents the drawing created by the drawing creation unit to a second user different from the first user; an approval processing unit that accepts an approval operation for the drawing by the second user; Further comprising: The design support system according to claim 1 .
3. The approval processing unit: accepting an input of a comment on the drawing by the first user or the second user; associating the comment with the drawing such that, when the comment is entered, the comment is presented to both the first user and the second user; The design support system according to claim 2 .
4. The additional parameters include a construction drawing parameter required to create a construction drawing of the BIM part, and a rose drawing parameter required in addition to the construction drawing parameter to create a rose drawing of the BIM part; The drawing creation unit includes a working drawing creation unit that creates a working drawing of the BIM part based on the working drawing parameters, and a rose drawing creation unit that creates a rose drawing of the BIM part based on the rose drawing parameters, The drawing presenting unit presents the construction drawing created by the construction drawing creation unit to the second user, The approval processing unit accepts the approval operation for the working drawing by the second user, The rose drawing creation unit creates the rose drawing based on the rose drawing parameters after the approval operation for the working drawing is accepted by the approval processing unit. The design support system according to claim 2 or 3.
5. Providing a BIM part relating to equipment of a construction object, the BIM part including basic parameters for displaying a three-dimensional shape of the BIM part in a BIM model of the construction object and code information uniquely assigned to the BIM part, in a manner that can be incorporated into the BIM model; A step of acquiring the code information of the BIM part included in the BIM model created by a first user, and acquiring the additional parameters associated with the acquired code information by accessing a storage unit that stores additional parameters for creating drawings related to the construction or manufacturing of the BIM part in association with the code information of the BIM part; generating the drawing of the BIM part based on the obtained additional parameters; changing at least a part of the acquired additional parameters based on the operation content input by the first user; Including, In the drawing creation step, the drawing of the BIM part is created based on the additional parameters after being changed in the parameter change step. Design support method.
6. Presenting the created drawing to a second user different from the first user; receiving an approval operation for the drawing by the second user; The design support method according to claim 5 , further comprising:
7. In the approval processing step, accepting an input of a comment on the drawing by the first user or the second user; associating the comment with the drawing such that, when the comment is entered, the comment is presented to both the first user and the second user; The design support method according to claim 6.
8. The additional parameters include construction drawing parameters necessary for creating a construction drawing of the BIM part, and rose drawing parameters required in addition to the construction drawing parameters for creating a rose drawing of the BIM part, The drawing creation step includes a construction drawing creation substep of creating a construction drawing of the BIM part based on the construction drawing parameters, and a rose drawing creation substep of creating a rose drawing of the BIM part based on the rose drawing parameters, In the drawing presentation step, the construction drawing created in the construction drawing creation sub-step is presented to the second user; In the approval processing step, the approval operation for the working drawing by the second user is accepted, In the rose drawing creation sub-step, after the approval operation for the working drawing is accepted by the approval processing step, the rose drawing is created based on the rose drawing parameters. The design support method according to claim 6 or 7.
9. A program for causing a computer to execute each step of the design support method described in any one of claims 5 to 8.