Invert placement method
The described method enhances invert casting efficiency and reduces costs by using a flexible hose and support member system for distributing concrete layers, addressing space and equipment limitations in tunnel construction.
Patent Information
- Application Number
- JP2023052151
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-03-28
- Publication Date
- 2024-10-10
- Estimated Expiration
- 2043-03-28
AI Technical Summary
Invert casting in tunnels is inefficient due to the need for lane restrictions, difficulty in securing space for concrete pumps, time-consuming rail installation, and high costs associated with specialized equipment, especially when multiple layers of concrete are required.
A method involving a concrete supply system with removably connected piping sections for distributing concrete layers, supported by flexible hoses and support members, allowing for efficient distribution and integration of multiple concrete layers without specialized machinery.
Improves the efficiency and reduces costs of invert casting by allowing simultaneous pouring of multiple concrete layers without lane restrictions and minimizing equipment requirements, while preventing corrosion and reducing the need for rail installation.
Smart Images

Figure 00000000_0000_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to a method for pouring an invert. [Background technology]
[0002] During tunnel construction, the tunnel is subjected to upward pressure from below due to ground swelling and other factors that occur below the bottom of the tunnel. In order to withstand this pressure, an inverted arch-shaped concrete structure called an invert is installed at the bottom of the tunnel (between the bases of both side walls inside the tunnel).
[0003] When pouring the invert, there are cases where the work is done by pouring half of the section at a time while restricting traffic one lane at a time in a two-lane tunnel. Also, when making the invert thicker, it is necessary to pour the concrete in multiple layers, such as pouring the second layer on top of the first layer.
[0004] The technology for pouring inverts is described, for example, in Patent Document 1, which discloses a pouring system having a pouring pipe for supplying concrete for pouring the invert, a cart on which the pouring pipe can be placed, and rails on which the cart can be moved. [Prior art documents] [Patent documents]
[0005] [Patent Document 1] Patent Publication No. 2022-26076 Summary of the Invention [Problem to be solved by the invention]
[0006] However, when pouring the invert while restricting traffic one lane at a time, only one lane on one side of the tunnel can be used because the other lane is in use. This makes it difficult to secure the space for the concrete pump truck to make a U-turn to supply the concrete for pouring.
[0007] Therefore, while considering ways to pour concrete without using a concrete pump truck, a method was considered in which concrete supplied from a stationary pump was distributed to the invert pouring site through a concrete distribution device called a distributor. However, this posed the problem that, within the narrow area permitted by tunnel regulations, great care must be taken to ensure that the distributor's long boom does not enter the one-way lane in use, significantly reducing the efficiency of the invert pouring work.
[0008] In addition, the technology in Patent Document 1 has the problem that installing the rails takes time, reducing work efficiency, and it cannot accommodate the case where concrete is poured in multiple layers when constructing an invert, as described above.
[0009] Furthermore, whether a distributor is used or the case of Patent Document 1, dedicated equipment is required, which poses the problem of increased costs for pouring the invert.
[0010] The present invention has been made against the above-mentioned technical background, and aims to provide a technology that can improve the efficiency of invert casting work.
[0011] Another object of the present invention is to provide a technology that can also be used for pouring an invert having an integral two-layer concrete structure.
[0012] Yet another object of the present invention is to provide a technique that can reduce the costs associated with invert pouring work. [Means for solving the problem]
[0013] In order to solve the above problems, the invert casting method of the present invention described in claim 1 includes a step of installing a concrete supplying means for supplying concrete to the casting area of the invert, a step of providing a plurality of first piping sections in a state of being detachably connected to each other along the concrete distribution direction, a step of installing a first casting pipe for distributing the first layer of concrete of the invert in the casting area of the invert, and a step of providing a plurality of second piping sections in a state of being detachably connected to each other along the concrete distribution direction, and a step of distributing the second layer of concrete of the invert. the step of installing a second pouring pipe for distributing concrete above the first pouring pipe in a state in which the second pouring pipe is supported by a plurality of support members arranged along the second pouring pipe; and the step of installing a concrete supply destination switching means for switching the supply destination of the concrete supplied from the concrete supply means to either the first pouring pipe or the second pouring pipe, and the concrete supplied from the concrete supply means to the first pouring pipe via the concrete supply destination switching means is transferred to the concrete of the first pouring pipe. a first pouring step in which the first layer of concrete is poured by discharging the first layer of concrete from a flexible pipe detachably connected to a discharge end of the first pouring pipe; and a second pouring step in which, after the first pouring step, the flexible pipe is removed from the first pouring pipe and detachably connected to a tip of the second pouring pipe, and the second layer of concrete is poured on the upper surface of the first layer of concrete by discharging the second layer of concrete supplied from the concrete supply means to the second pouring pipe through the concrete supply destination switching means from the flexible pipe. and a step of placing the first concrete layer on the first concrete layer, the first concrete placing step including: (a) a step of placing a first predetermined area; (b) a step of removing the flexible pipe after the first area is placed; (c) a step of removing a predetermined number of the first pipe sections from the tip of the first concrete placing pipe after the first area is placed; and (d) a step of attaching the flexible pipe removed in step (b) to the tip of the first concrete placing pipe remaining after step (c) after step (c), and then resuming placing the first layer of concrete.(e) repeating the steps (a) to (d) until the entire pouring of the first layer of concrete is completed, and the second pouring step comprises: (f) pouring a predetermined second range; (g) removing the flexible piping after the pouring of the second range is completed; (h) removing a predetermined number of the second piping sections from the tip of the second pouring piping after the pouring of the second range is completed; (i) after the step (h), attaching the flexible piping removed in the step (g) to the tip of the second pouring piping remaining after the step (h), and then resuming pouring of the second layer of concrete; and (j) repeating the steps (f) to (i) until the entire pouring of the second layer of concrete is completed.
[0014] The invert casting method of the present invention as described in claim 2 is characterized in that, in the invention as described in claim 1, after the second casting process, the support member is left within the first layer of concrete and the second layer of concrete with the highest part of the support member positioned a predetermined thickness below the upper surface of the cast second layer of concrete.
[0015] The invert pouring method of the present invention as described in claim 3 is characterized in that, in the invention as described in claim 1 above, the support member comprises a support leg, a jig attached in a removable state to the top of the support leg, and a piping holding part connected to the jig and arranged above the upper surface of the poured second layer of concrete, for holding the second pouring piping, and the second pouring process includes pouring the second layer of concrete so that the upper surface of the jig is exposed from the upper surface of the poured second layer of concrete, then pulling out the jig from the second layer of concrete, forming a recess in the place of the jig, and further filling the recess.
[0016] The invert pouring method of the present invention described in claim 4 is characterized in that, in the invention described in claim 3 above, the support leg is installed in a state where the top of the support leg is located a predetermined thickness below the upper surface of the poured second layer of concrete.
[0017] The invert casting method of the present invention described in claim 5 is characterized in that, in the invention described in claim 3 or 4 above, when removing the jigs from the second layer of concrete, multiple jigs are removed at once.
[0018] The invert pouring method of the present invention as described in claim 6 is characterized in that, in the invention as described in claim 1 above, the support member comprises a support leg and a pipe holding part that is detachably attached to the top of the arm part of the support leg and holds the second pouring pipe, the top of the arm part and the pipe holding part are located above the pouring top surface of the second layer of concrete, and during the second pouring process, the second layer of concrete is poured from above the pouring top surface of the second layer of concrete.
[0019] The invert pouring method of the present invention as described in claim 7, in the invention as described in claim 6 above, comprises, in the second pouring process, a process of removing the pipe holding portion from the support leg after pouring the second layer of concrete, and a process of cutting and removing the arm portion at a position a predetermined thickness below the upper surface of the poured concrete of the second layer, and is characterized in that, after the second pouring process, the support leg portion is left in the layers of the first and second concrete layers with the cut point of the arm portion positioned a predetermined thickness below the upper surface of the poured concrete of the second layer.
[0020] The invert pouring method of the present invention as described in claim 8, in the invention as described in claim 6 above, is characterized in that, in the second pouring process, after pouring the second layer of concrete, the second pouring process includes a process of removing the pipe holding portion from the support leg portion and bending the arm portion at a position a predetermined thickness below the upper surface of the poured top of the second layer of concrete, and after the second pouring process, the support leg portion is left in the first layer of concrete and the second layer of concrete with the highest part of the arm portion positioned a predetermined thickness below the upper surface of the poured top of the second layer of concrete. Effect of the Invention
[0021] According to the present invention, it is possible to improve the efficiency of invert pouring work.
[0022] Furthermore, according to the present invention, it is also possible to handle the pouring of inverts having an integral two-layer concrete structure.
[0023] In addition, according to the present invention, it is possible to reduce the costs associated with the invert casting work.
[0024] In addition, according to the present invention, a concrete layer of a predetermined thickness is secured on the support member on which the second pouring pipe is placed, and the support member is then left in the concrete layer for constructing the invert, thereby eliminating the need to remove the support member. [Brief description of the drawings]
[0025] [Figure 1] 1 is an explanatory diagram showing the invert pouring equipment of the first embodiment of the present invention as viewed from the side of a tunnel. FIG. [Diagram 2] 1. (a) is a schematic cross-sectional view of the supply destination switching section that constitutes the invert concrete pouring equipment of Figure 1, (b) is a schematic longitudinal cross-sectional view of the key parts at the connection between the piping sections of the pouring piping that constitutes the invert concrete pouring equipment of Figure 1, and (c) is a front view of an example of a support member that constitutes the invert concrete pouring equipment of Figure 1. [Diagram 3]This is an explanatory diagram showing the invert pouring equipment during the invert pouring process viewed from the side of the tunnel. [Figure 4] This is an explanatory diagram showing the invert pouring equipment during the invert pouring process after the process in Figure 3, viewed from the side of the tunnel. [Diagram 5] This is an explanatory diagram showing the invert pouring equipment during the invert pouring process after the process in Figure 4, viewed from the side of the tunnel. [Figure 6] This is an explanatory diagram showing the invert pouring equipment during the invert pouring process after the process in Figure 5, viewed from the side of the tunnel. [Figure 7] This is an explanatory diagram showing the invert pouring equipment during the invert pouring process after the process in Figure 6, viewed from the side of the tunnel. [Figure 8] This is an explanatory diagram showing the invert pouring equipment during the invert pouring process after the process in Figure 7, viewed from the side of the tunnel. [Figure 9] This is an explanatory diagram showing the invert pouring equipment during the invert pouring process after the process in Figure 8, viewed from the side of the tunnel. [Figure 10] 10(a) is an explanatory diagram showing the invert pouring equipment during the invert pouring process after the process in Figure 9, viewed from the side of the tunnel, and (b) is an enlarged cross-sectional view of the area surrounded by the dashed line in Figure 10(a). [Figure 11] 11(a) is an explanatory diagram of the invert pouring equipment of the second embodiment viewed from the side of the tunnel, and (b) is an enlarged side view of the main part of the area surrounded by the dashed line in FIG. 11(a). [Figure 12] This is an explanatory diagram showing the main parts of the invert pouring equipment during the invert pouring process from the side of the tunnel. [Figure 13] 13(a) is an explanatory diagram of the key parts of the invert pouring equipment during the invert pouring process after Figure 12, viewed from the side of the tunnel, and (b) is an explanatory diagram of the key parts of the invert pouring equipment during the invert pouring process after Figure 13(a), viewed from the side of the tunnel. [Figure 14] 14(a) is an explanatory diagram showing the main parts of the invert pouring equipment during the invert pouring process after Figure 13(b) viewed from the side of the tunnel, and (b) is an enlarged cross-sectional view of the area surrounded by dashed lines in Figure 14(a). [Figure 15] An explanatory diagram of the invert pouring equipment of the third embodiment viewed from the side of the tunnel. [Figure 16] 16(a) is a front view of the support member of FIG. 15, FIG. 16(b) is a side view of the support member of FIG. 16(a), and FIG. 16(c) is a perspective view of a pipe holding portion constituting the support member of FIGS. 16(a) and 16(b). [Figure 17] 17(a) is an explanatory diagram showing the main parts of the invert pouring equipment during the invert pouring process viewed from the side of the tunnel, and (b) is an enlarged cross-sectional view of the area surrounded by the dashed line in Figure 17(a). [Figure 18] 18(a) is an explanatory diagram showing the main parts of the invert pouring equipment during the invert pouring process after Figure 17, viewed from the side of the tunnel, and (b) is an enlarged cross-sectional view of the area surrounded by dashed lines in Figure 18(a). [Figure 19] 19(a) is an explanatory diagram showing the main parts of the invert pouring equipment during the invert pouring process after Figure 18, viewed from the side of the tunnel, and (b) is an enlarged cross-sectional view of the area surrounded by dashed lines in Figure 19(a). [Figure 20] 20(a) is an explanatory diagram of the key parts of the invert pouring equipment during the invert pouring process, viewed from the side of the tunnel, and (b) is an explanatory diagram of the key parts of the invert pouring equipment during the invert pouring process after Figure 20(a), viewed from the side of the tunnel. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0026] Hereinafter, an embodiment of the present invention will be described in detail with reference to the drawings. In the drawings for explaining the embodiment, the same components are generally designated by the same reference numerals, and the repeated description will be omitted.
[0027] (First embodiment)
[0028] Figure 1 is an explanatory diagram of the invert concrete pouring equipment of the first embodiment viewed from the side of the tunnel, Figure 2(a) is a schematic cross-sectional view of the supply destination switching section that constitutes the invert concrete pouring equipment of Figure 1, Figure 2(b) is a schematic longitudinal cross-sectional view of the key parts at the connection between the piping sections of the pouring piping that constitutes the invert concrete pouring equipment of Figure 1, and Figure 2(c) is a front view of an example of a support member that constitutes the invert concrete pouring equipment of Figure 1.
[0029] As shown in Fig. 1, the invert pouring equipment CE of this embodiment is a pouring equipment for pouring an invert of two-layer concrete integral structure, for example, at the bottom of a mountain tunnel, and includes a stationary pump P, a supply destination switching unit SW, a first pouring pipe FCP, a second pouring pipe SCP, a plurality of support members S, and a flexible hose FH. Although not particularly limited, the length La of the pouring area is, for example, about 10.5 to 15 m.
[0030] The stationary pump P is a concrete supplying means that pushes out the concrete flowing into the hopper H and pumps it to the casting site. A supply destination switching unit SW is installed downstream of this stationary pump P.
[0031] The supply destination switching unit SW is a concrete switching means that switches the destination of the concrete sent from the stationary pump P to either the first pouring pipe FCP or the second pouring pipe SCP, and is equipped with a branch pipe BP and a switching valve V.
[0032] The branch pipe BP is, for example, a Y-shaped pipe, and is integrally provided with one inlet pipe section BP1 and two outlet pipe sections BP2, BP3 connected to the inlet pipe section BP1. The inlet section of the inlet pipe section BP1 is connected to the concrete discharge port of the stationary pump P, the outlet section of the outlet pipe section BP2 is connected to the first concrete pouring pipe FCP, and the outlet section of the outlet pipe section BP3 is connected to the second concrete pouring pipe SCP.
[0033] The switching valve V is composed of a fluid gate valve such as a pin valve, and is installed at the inlet of the outflow pipes BP2, BP3. As shown in Fig. 2(a), the switching valve V has a valve operation part Vc that operates the opening and closing of the valve, a plurality of gate pins Vp that are provided so as to protrude downward from the lower surface of the valve operation part Vc, and a plurality of through holes Vh drilled in the upper part of the outflow pipes BP2, BP3. The plurality of gate pins Vs and the plurality of through holes Vh are arranged in parallel along a direction that intersects with the longitudinal direction of the outflow pipes BP2, BP3 (the direction perpendicular to the paper surface of Fig. 2).
[0034] When switching the flow path using the switching valve V, the flow path of the outflow pipes BP2, BP3 on the side where concrete is not poured is closed, and the flow path of the outflow pipes BP2, BP3 on the side where concrete is poured is opened. To close the flow paths of the outflow pipes BP2, BP3, the valve operating part Vc of the switching valve V is pushed down to insert multiple partition pins Vp into the outflow pipes BP2, BP3 through the multiple through holes Vh. On the other hand, to open the flow paths of the outflow pipes BP2, BP3, the valve operating part Vc is pulled up to remove the partition pins Vp from inside the outflow pipes BP2, BP3.
[0035] However, the switching valve V is not limited to a pin valve and can be variously modified, for example, a shutter valve may be used. In the case of a shutter valve, a partition plate is provided instead of the partition pin Vp.
[0036] As shown in Figure 1, downstream of the supply switching unit SW, the first pouring pipe FCP, which distributes the first layer of concrete for the invert, is placed directly on the bottom of the excavation of the ground G in the pouring area.
[0037] However, although an example has been given here of the first pouring piping FCP being placed directly on the bottom surface of the excavation of the ground G, this is not limited to this, and for example, when the invert concrete is reinforced concrete, the first pouring piping FCP is placed directly on the reinforcing bars that make up the invert.
[0038] This first concrete pouring pipe FCP is configured by multiple pipe sections (first pipe sections) CP1 that are detachably connected to each other along its longitudinal direction (i.e., the direction in which concrete is dispensed). The pipe sections CP1 are made of steel so that they can withstand the pumping of concrete.
[0039] As shown in Fig. 2(b), the pipe sections CP1, CP1 are detachably connected to each other by, for example, a ring-type Victorik joint member Jv. A radially protruding locking portion (flange portion) CPk is integrally formed at both longitudinal ends of the pipe section CP1. The pipe sections CP1, CP1 are detachably connected to each other by butting the locking portions CPk, CPk against each other and attaching the Victorik joint member Jv to the outer periphery of both the locking portions CPk, CPk via a sealing member SL.
[0040] Also, as shown in Fig. 2(c), the first concrete pouring pipe FCP is installed outside the support member S. This is because if the first concrete pouring pipe FCP is placed under the support member S, it will get in the way when removing the pipe as described later, reducing workability, so the first concrete pouring pipe FCP is installed outside the support member S, and the positions of the first concrete pouring pipe FCP and the second concrete pouring pipe SCP are shifted from each other in the horizontal direction (short direction of the pipe) in Fig. 2(c). This can improve the efficiency of the invert concrete pouring work.
[0041] On the other hand, as shown in Fig. 1, the second concrete pouring pipe SCP for distributing the second layer of concrete of the invert is installed along the first concrete pouring pipe FCP and above the first concrete pouring pipe FCP at the rear stage of the supply destination switching unit SW. This second concrete pouring pipe SCP is configured by multiple pipe sections (second pipe sections) CP2 that are detachably connected to each other along its longitudinal direction (i.e., the concrete distributing direction). The pipe section CP2 is the same as the pipe section CP1 described above, and the structure of the connection between the pipe sections CP2 and CP2 is also the same as that described in Fig. 2(b).
[0042] Such a second concrete pouring pipe SCP is supported by a plurality of support members S. A plurality of support members S are installed in a line at predetermined intervals along the longitudinal direction of the second concrete pouring pipe SCP. The lower portion of each support member S is inserted into the ground G and is firmly fixed thereto.
[0043] When the invert concrete is made of reinforced concrete as described above, the support member S may be placed on top of the rebars (the topmost rebars) that make up the invert, and the lower part of the support member S may be firmly fixed to the rebars (the topmost rebars). In this case, the lower part of the support member S is located above the top surface of the natural ground G and does not come into contact with the natural ground G.
[0044] As shown in Fig. 2(c), the support member S includes a support leg Sk1 and a pipe holding part Sh1 above the support leg Sk1. The support leg Sk1 is a part that supports the pipe holding part Sh1, and the pipe holding part Sh1 is a part that holds and supports the second pouring pipe SCP. The support leg Sk1 and the pipe holding part Sh1 are integrally formed, for example, from a steel material.
[0045] In this embodiment, the highest part of the support member S (i.e. the highest part of the pipe holding part Sh1) is installed in a state where it is located a predetermined thickness (hereinafter referred to as the covering thickness) T below the poured top surface CSS of the second layer of concrete, and by ensuring this covering thickness T, as will be described later, even if the support member S is left in the invert concrete, damage to the invert concrete due to corrosion of the steel can be prevented. Note that the poured top surface CSF in Figure 2(c) indicates the poured top surface of the first layer of concrete.
[0046] As shown in Figure 1, the FH flexible hose is a flexible pipe that guides the concrete to its destination. This FH flexible hose is also called a flexible pipe, flexible tube, or flexible tube, and is made of a metal hose that is flexible and has excellent pressure resistance. Although the FH flexible hose is made of metal and is therefore hard, it is designed to be easily bent by adopting a corrugated shape such as a tube specification or braid specification.
[0047] In Figure 1, the flexible hose FH is shown to be connected in a detachable manner to the tip of the first concrete pouring pipe FCP, but the flexible hose FH is detachable from the tip of both the pipe section CP1 of the first concrete pouring pipe FCP and the pipe section CP2 of the second concrete pouring pipe SCP.
[0048] Next, an example of the invert pouring method of this embodiment will be described with reference to Figures 3 to 10. Figures 3 to 10(a) are explanatory diagrams of the invert pouring equipment during the invert pouring process as seen from the side of the tunnel, and Figure 10(b) is an enlarged cross-sectional view of the area surrounded by the dashed line in Figure 10(a). Note that in Figures 3 to 10(a), concrete is hatched to make the drawings easier to see.
[0049] In this embodiment, for example, a two-lane tunnel is regulated lane by lane, and the invert is poured half-section at a time. That is, for example, one of the two lanes in the tunnel is used, and the adjacent lane is used as the area for pouring work to construct the invert.
[0050] First, as shown in Fig. 3, a stationary pump P, a supply switching unit SW, a first concrete pouring pipe FCP, a support member S, and a second concrete pouring pipe SCP are installed in the pouring area of the invert. A flexible hose FH is then connected to the tip of the first concrete pouring pipe FCP. In addition, in the supply switching unit SW, the flow path of the outflow pipe BP2 is opened and the flow path of the outflow pipe BP3 is closed, so that concrete flows only in the first concrete pouring pipe FCP.
[0051] Next, pouring of the first layer of concrete CC1 begins. That is, the concrete CC1 flowed into the stationary pump P through the hopper H is pumped by the stationary pump P to the first pouring pipe FCP, and is discharged from the outlet of the flexible hose FH connected to the tip of the first pouring pipe FCP to the pouring location of the invert. At this time, the concrete CC1 is discharged to the pouring location of the invert while swinging the flexible hose FH from side to side.
[0052] Thereafter, when pouring of concrete CC1 around the attachment position of the flexible hose FH (a predetermined first range) is completed, the flexible hose FH connected to the piping part CP1 at the tip of the first pouring pipe FCP is removed, and then the piping part CP1 at the tip of the first pouring pipe FCP is removed, as shown in Fig. 4. Then, the removed flexible hose FH is attached back to the tip of the first pouring pipe FCP that remains in the pouring area of the invert.
[0053] Next, as described above, the concrete CC1 pressurized from the stationary pump P to the first pouring pipe FCP is discharged from the outlet of the flexible hose FH connected to the tip of the first pouring pipe FCP to the pouring site of the invert.
[0054] Next, when pouring of concrete CC1 around the attachment position of the flexible hose FH (a predetermined first range) is completed, the flexible hose FH connected to the piping part CP1 at the tip of the first pouring pipe FCP is removed, and then the piping part CP1 at the tip of the first pouring pipe FCP is removed, as shown in Fig. 5. Then, the removed flexible hose FH is attached back to the tip of the first pouring pipe FCP that remains in the pouring area of the invert.
[0055] Thereafter, as described above, the concrete CC1 pumped from the stationary pump P to the first pouring pipe FCP is discharged from the outlet of the flexible hose FH connected to the tip of the first pouring pipe FCP to the pouring location of the invert.
[0056] By repeating such operations, as shown in Fig. 6, when the pouring of the first layer of concrete CC1 is completed, the operation of the stationary pump P is stopped and the flow of concrete CC1 into the stationary pump P is stopped. Then, the flexible hose FH is connected to the tip of the second pouring pipe SCP.
[0057] Next, in the supply destination switching section SW, the flow path of the outflow pipe section BP3 is opened and the flow path of the outflow pipe section BP2 is closed, so that the concrete flows only through the second concrete pouring pipe SCP.
[0058] Next, the pouring of the second layer of concrete begins. That is, as shown in Fig. 7, concrete CC2 flowed into the stationary pump P through the hopper H is pumped by the stationary pump P to the second pouring pipe SCP, and discharged from the outlet of the flexible hose FH connected to the tip of the second pouring pipe SCP to the pouring location of the invert. At this time, the flexible hose FH is also swung left and right to discharge the concrete CC2 onto the pouring top surface CSF of the first layer of concrete CC1 at the pouring location of the invert.
[0059] After that, when pouring of concrete CC2 around the attachment position of the flexible hose FH (a predetermined second range) is completed, as shown in Fig. 8, the flexible hose FH connected to the pipe section CP2 at the tip of the second concrete pouring pipe SCP is removed, and then the pipe section CP2 at the tip of the second concrete pouring pipe SCP is removed. Then, the removed flexible hose FH is attached back to the tip of the second concrete pouring pipe SCP that remains in the pouring area of the invert. At this time, the support member S is left in the concrete.
[0060] Next, as described above, the concrete CC2 pressurized from the stationary pump P to the second pouring pipe FCP is discharged from the outlet of the flexible hose FH connected to the tip of the second pouring pipe SCP onto the upper pouring surface CSF of the first layer of concrete CC1 at the pouring point of the invert.
[0061] Next, when pouring of concrete CC2 around the attachment position of the flexible hose FH (a predetermined second range) is completed, the flexible hose FH connected to the pipe section CP2 at the tip of the second pouring pipe SCP is removed, as shown in Fig. 9, and then the pipe section CP2 at the tip of the second pouring pipe SCP is removed. Then, the removed flexible hose FH is attached back to the tip of the second pouring pipe FCP that remains in the pouring area of the invert. At this time, the support member S is also left in the concrete.
[0062] Then, as described above, the concrete CC2 pressurized from the stationary pump P to the second pouring pipe SCP is discharged from the outlet of the flexible hose FH connected to the tip of the second pouring pipe SCP onto the upper pouring surface CSF of the first layer of concrete CC1 at the pouring point of the invert.
[0063] By repeating this process, when the second layer of concrete CC2 is stacked on the upper surface CSF of the first layer of concrete CC1, as shown in Figure 10(a), the operation of the stationary pump P is stopped and the flow of concrete CC2 into the stationary pump P is stopped.
[0064] At this time, in this embodiment, as shown in FIG. 10(b), the highest part of the support member S is located below the upper surface CSS of the second layer of concrete CC2 by the covering thickness T, and is covered by the concrete CC2 and is not exposed to the outside air. Therefore, even if the support member S is left in the layers of concrete C1 and C2 that constitute the invert, the support member S will not corrode. As a result, even if the support member S is left in the layers of concrete CC1 and CC2 that constitute the invert, damage to the invert due to corrosion of the steel material can be prevented. Note that, when the lower part of the support member S is pierced and fixed into the natural ground G, the lower part of the support member S is in contact with the natural ground G, but since there is no intrusion of air from the outside on the natural ground G side, the lower part of the support member S will not corrode even if the support member S is left in the layers of concrete C1 and C2. Furthermore, when the lower part of the support member S is fixed to the reinforcing bars that make up the invert (the topmost reinforcing bars), the lower part of the support member S is contained within the layers of concrete CC1 and CC2 and is not exposed to the outside air, so the lower part of the support member S will not corrode even if it is left in the layers of concrete C1 and C2.
[0065] For this reason, in this embodiment, the support member S that supported the second casting pipe SCP is not removed but is left in the layers of concrete CC1 and CC2. This makes it possible to omit the work of removing the support member S, thereby shortening the time required for casting the invert. In addition, it is possible to prevent the concretes C1 and C2 from hardening while the support member S is being removed, preventing them from being integrated at the pouring position.
[0066] Here, when a distributor is used, there is a problem in that, in order to ensure the safety of the one lane in use, concrete pouring work must be carried out with great care to ensure that the long boom of the distributor does not enter the one lane in use, which reduces work efficiency.
[0067] In contrast, in this embodiment, the efficiency of the invert pouring work can be improved because the invert pouring work can be performed without considering the lane in use on one side and without the need for time-consuming work such as installing rails. In addition, the safety of the invert pouring work can be improved because there is no impact on the lane in use on one side.
[0068] In addition, since the invert pouring equipment CE is constructed using existing equipment and components without using dedicated heavy machinery or dedicated facilities such as distributors, the costs associated with invert pouring work can be reduced.
[0069] In addition, two layers of concrete CC1, CC2 can be stacked using the first pouring pipe FCP and the second pouring pipe SCP in sequence, which makes it possible to accommodate invert pouring work that requires pouring concrete in multiple layers, such as pouring the second layer of concrete CC2 on top of the first layer of concrete CC1 in order to make the invert thicker, etc.
[0070] Furthermore, as described above, since the supporting member S is left in the concrete CC1, CC2 for constructing the invert after securing a concrete layer of the necessary covering thickness T on the supporting member S on which the second casting pipe SCP is placed, it is possible to prevent damage to the concrete CC1, CC2 due to corrosion of the steel material even if the supporting member S is left in the concrete CC1, CC2 for constructing the invert. Therefore, the work of removing the supporting member S from the concrete CC1, CC2 for constructing the invert can be omitted, which improves the efficiency of the invert casting work.
[0071] (Second embodiment)
[0072] In this embodiment, the configuration of the support members constituting the invert concrete pouring equipment is different from that of the first embodiment described above. Below, an example of the configuration of the support members of the invert concrete pouring equipment of this embodiment will be described with reference to Fig. 11. Fig. 11(a) is an explanatory diagram of the invert concrete pouring equipment of the second embodiment seen from the side of the tunnel, and Fig. 11(b) is an enlarged side view of the main part of the area surrounded by the dashed line in Fig. 11(a).
[0073] As shown in FIGS. 11(a) and 11(b), in this embodiment, a support member S includes a support leg portion Sk2 and a pipe holding portion Sh2 supported above the support leg portion Sk2 via a P con (jig) PC.
[0074] The support leg Sk2 is made of, for example, a reinforcing bar, and is erected with its lower portion penetrating and firmly fixed into the ground G. As shown in Fig. 11(b), the support leg Sk2 is installed with its top portion located below the top surface CSS of the poured second layer of concrete by a covering thickness T. A male screw portion is formed at the top portion of this support leg Sk2.
[0075] 11(a) and (b), the pipe holding part Sh2 is made of, for example, a steel angle member having an L-shaped cross section, and is installed in a state of extending along the second concrete pouring pipe SCP so as to straddle the multiple support legs Sh2 of the multiple support members S. As shown in FIG. 11(b), the second concrete pouring pipe SCP (piping part CP2) is firmly fixed and held by a wire W1 in the pipe holding part Sh2, and the multiple support legs Sk2 are connected to it via multiple P contacts PC.
[0076] In the first embodiment described above, the piping holding part Sh1 was located below the upper surface CSS of the poured second layer of concrete, whereas in the present embodiment, as shown in Figure 11(b), the piping holding part Sh2 is located above the upper surface CSS of the poured second layer of concrete.
[0077] As shown in Figures 11(a) and (b), the P-concrete PC is made of plastic formed into a truncated cone shape, and is installed with its small diameter side facing down and its large diameter side facing up. The height of this P-concrete PC (the distance between the small diameter side and the large diameter side) is set so that a covering thickness T (see Figure 11(b)) is secured between the top of the support leg Sk2 and the upper surface CSS of the second layer of poured concrete.
[0078] Furthermore, the P-con PC is detachably connected to the top of the support leg Sk2 by screwing a male screw formed on the top of the support leg Sk2 into a female screw formed in the center of the small diameter surface of the P-con PC. However, the P-con PC may be detachably connected to the top of the support leg Sk2 by, for example, inserting the top of the support leg Sk2 into a recess formed in the center of the small diameter surface of the P-con PC without screwing the P-con PC to the top of the support leg Sk2.
[0079] The P-con PC is fixed to the pipe holder Sh2 by a mounting bracket Ax provided at the center of the large diameter surface. However, the P-con PC is fixed to the pipe holder Sh2 in a state in which it can be rotated left and right around its central axis. That is, by turning the P-con PC right or left, the male threaded part at the top of the support leg Sk2 can be screwed into the female threaded part of the P-con PC to connect the P-con PC to the top of the support leg Sk2, or the P-con PC can be removed from the top of the support leg Sk2. In FIG. 11(b), the top of the support leg Sk2 inside the P-con PC and the mounting bracket Ax are shown through the transparent part to make the configuration easier to understand.
[0080] In this embodiment, the support members S that make up the invert pouring equipment CE are constructed using existing members rather than special members, making it easy to use and the use of the support members S does not increase the cost of invert pouring work.
[0081] Next, an example of the invert pouring method of this embodiment will be described with reference to Figures 12 to 14. Figures 12 to 14(a) are explanatory diagrams showing the main parts of the invert pouring equipment during the invert pouring process as viewed from the side of the tunnel, and Figure 14(b) is an enlarged cross-sectional view of the area surrounded by the dashed line in Figure 14(a). Note that in Figures 12 to 14, concrete is hatched to make the drawings easier to see.
[0082] As shown in Fig. 12, the first layer of concrete CC1 is poured in the same manner as described in the first embodiment described above, and then the second layer of concrete CC2 is poured in the same manner as described in the first embodiment described above, as shown in Fig. 12 and Fig. 13(a). Here, in this embodiment, the pipe holding part Sh2 constituting the support member S is installed above the pouring upper surface CSS of the second layer of concrete CC2, so that the second layer of concrete CC2 can be poured from above compared to the first embodiment described above. Therefore, the pouring operation of the second layer of concrete CC2 can be made easier than in the first embodiment described above.
[0083] As shown in FIG. 13(a), when pouring the second layer of concrete CC2, the bottom surface (small diameter surface) and side surface of the P-concrete PC are filled and the large diameter surface (top surface) of the P-concrete PC is exposed from the poured top surface CSS of the second layer of concrete CC2. In this manner, in this embodiment, by providing the P-concrete PC, it is possible to easily determine how much concrete CC2 should be piled. Also, the covering thickness T between the poured top surface CSS of the second layer of concrete CC2 and the tops of the multiple support legs Sk2 can be easily set without excess or deficiency.
[0084] When the pouring of the second layer of concrete CC2 is completed as described above, the operation of the stationary pump P is stopped, and the flow of concrete CC2 into the stationary pump P is stopped. At this stage, the pipe holding part Sh2 and the P cone PC are left in place without being removed.
[0085] Next, each P-convex part PC is rotated to release the connection between each P-convex part PC and the top of each supporting leg part Sk2, and then, as shown in FIG. 13(b), the pipe holding part Sh2 constituting the supporting member S is raised to pull up the multiple P-convex parts PC collectively from the second layer of concrete CC2. As a result, a recess Ra is formed in the area where the P-convex part PC was removed from the poured top surface CSS of the second layer of concrete CC2. This recess Ra is formed to a depth of at least a predetermined covering thickness T (see FIG. 11(b)) between the poured top surface CSS of the second layer of concrete CC2 and the top of the supporting leg part Sk2. At this stage, a part of the top of the supporting leg part Sk2 is exposed from the bottom surface of the multiple recesses Ra.
[0086] In this manner, in this embodiment, multiple P-concrete PCs are pulled out all at once from the second layer of concrete CC2, which reduces the labor required and shortens the work time compared to pulling out the P-concrete PCs one by one.
[0087] After that, as shown in Figs. 14(a) and (b), concrete CC3 is filled into the recesses Ra. As a result, the top of the support leg Sk2 is covered and completely embedded with concrete CC3. In this embodiment, as shown in Fig. 14(b), a covering thickness T can be ensured between the top of the support leg Sk2 and the upper surface CSS of the poured second layer of concrete CC2. Therefore, the quality of the invert can be ensured. Note that the effects other than those described above are the same as those described in the first embodiment.
[0088] (Third embodiment)
[0089] In this embodiment, the configuration of the support member constituting the invert concrete pouring equipment is different from that of the first and second embodiments described above. Below, an example of the configuration of the support member of the invert concrete pouring equipment of this embodiment will be described with reference to Figs. 15 and 16. Fig. 15 is an explanatory diagram of the invert concrete pouring equipment of the third embodiment seen from the side of the tunnel, Fig. 16(a) is a front view of the support member of Fig. 15, Fig. 16(b) is a side view of the support member of Fig. 16(a), and Fig. 16(c) is a perspective view of the pipe holding part constituting the support member of Figs. 16(a) and (b).
[0090] As shown in FIGS. 15 and 16, in this embodiment, a support member S includes a support leg portion Sk3 and a pipe holding portion Sh3 supported above the support leg portion Sk3.
[0091] 16(a) and (b), the support leg Sk3 includes, for example, a base portion BS, a body portion BD provided on the upper portion thereof, and an arm portion AM provided on the upper portion thereof, and is erected with the lower portion of the base portion BS penetrating and firmly fixed into the natural ground G. Note that the cutting position CU in Fig. 16(a) and (b) indicates the cutting position of the arm portion AM described below, and the recess Rb indicates the depression formed in the upper surface CSS of the poured second layer of concrete when the arm portion AM described below is cut.
[0092] The base portion BS and the arm portion AM are made of, for example, linear reinforcing bars, and are joined to the body portion BD by welding at their intersections with the body portion BD. The body portion BD is made of, for example, a cube-shaped angle frame member.
[0093] In the first and second embodiments described above, the tops of the supporting legs Sk1, Sk2 were located below the upper surface CSS of the poured second layer of concrete, whereas in this embodiment, the upper part of the supporting leg Sk3 (i.e., the top of the arm portion AM) is located above the upper surface CSS of the poured second layer of concrete.
[0094] 16(a) to 16(c), the pipe holding part Sh3 is a pipe holding jig called a concrete horse or a pipe horse that is used to hold a concrete pressure pipe in concrete pouring work, for example. Although not particularly limited, the front length Lb of the pipe holding part Sh3 is, for example, about 480 mm, the depth length Lc is, for example, about 535 mm, and the height Ld is, for example, about 580 mm.
[0095] The pipe holding part Sh3 comprises a pair of supports US, US, a pair of connecting parts UC, UC that connect the pair of supports US, US, a holding part UH that holds the second pouring pipe SCP, and a step part UP arranged to bridge between the upper parts of the pair of supports US, US.
[0096] The support US is formed by bending, for example, a steel pipe with a diameter of about 34 mm in the center of its longitudinal direction. Therefore, two legs (both ends of the support US) are formed in one support US, and four legs are formed in total in the pipe holding part Sh3. The four legs of the pipe holding part Sh3 are firmly fixed to the tops of the four arms AM of the support leg Sk3 by wire W2.
[0097] The connecting part UC is made of a steel pipe having a diameter of about 34 mm, for example, and both ends of the pipe are joined to the pair of supports US, US at a midpoint in the height direction. Although not particularly limited, the height Le to the connecting part UC shown in FIG. 16(c) is, for example, about 200 mm.
[0098] The holding part UH is provided so as to bridge the upper part of the pair of supports US, US in a bent state. The holding part UH has a pipe abutment part UH1 that contacts the second concrete pouring pipe SCP, and a pair of spring parts UH2, UH2. The spring parts UH2 are provided between both longitudinal ends of the pipe abutment part UH1 and the pair of supports US, US.
[0099] By providing the spring part UH2, the second casting pipe SCP can be held in a swingable state as shown by the arrow Ar in Fig. 16(b), and therefore the swinging and vibration of the second casting pipe SCP accompanying the pumping of concrete can be absorbed. This makes it possible to fix the pipe holding part Sh3 itself so that the pipe holding part Sh3 can be stably supported on the support leg part Sk3 when pumping concrete.
[0100] The platform part UP is installed in a detachable state relative to the pair of supports US, US. A walkway can be formed by placing a runway on the platform part UP. The width Lf of the platform part UP shown in Fig. 16(b) is, for example, about 130 mm. Also, in Fig. 16(c), the platform part UP is not shown in order to make the drawing easier to see.
[0101] In this embodiment, the support members S that make up the invert pouring equipment CE are constructed using existing members rather than special members, making it easy to use and the use of the support members S does not increase the cost of invert pouring work.
[0102] Next, an example of the invert casting method of this embodiment will be described with reference to Figures 17 to 19. Figures 17(a), 18(a) and 19(a) are explanatory diagrams showing the main parts of the invert casting equipment during the invert casting process from the side of the tunnel, and Figures 17(b), 18(b) and 19(b) are enlarged cross-sectional views of the areas surrounded by dashed lines in Figures 17(a), 18(a) and 19(a), respectively. In Figures 17 to 19, concrete is hatched to make the drawings easier to see.
[0103] As shown in Fig. 17, the first layer of concrete CC1 is poured in the same manner as described in the first embodiment, and then the second layer of concrete CC2 is poured in the same manner as described in the first embodiment. Here, in this embodiment, the pipe holding part Sh3 constituting the support member S is installed above the pouring upper surface CSS of the second layer of concrete CC2, so that the second layer of concrete CC2 can be poured from further above than in the second embodiment. Therefore, the pouring work of the second layer of concrete CC2 can be made even easier than in the second embodiment.
[0104] When the pouring of the second layer of concrete CC2 is completed as described above, the operation of the stationary pump P is stopped, and the inflow of concrete CC2 into the stationary pump P is stopped. At this stage, the pipe holder Sh3 is left installed without being removed.
[0105] Next, as shown in Fig. 18, the wire W2 (see Figs. 16(a) and 16(b)) that fastens the arm portion AM of the support leg Sk3 to the leg portion of the pipe holder Sh3 is untied to remove the pipe holder Sh3, and then the concrete CC2 around the arm portion AM of the remaining support leg Sk3 is partially lowered to form a recess Rb. This recess Rb is formed to have a depth equal to or greater than the covering thickness T. Note that the pipe holder Sh3 may be removed after the recess Rb is formed.
[0106] Then, after the concrete is finished, as shown in FIG. 19, the arm portion AM of the support leg Sk3 is fused near the bottom of the recess Rb, the arm portion AM above the fused portion is removed, and the recess Rb of the concrete CC2 is filled. As a result, the top of the support leg Sk3 is covered and completely embedded with the concrete CC2. As a result, even in this embodiment, the covering thickness T can be secured between the top of the support leg Sk3 and the upper surface CSS of the second layer of concrete CC2. Therefore, the quality of the invert can be secured. Note that the effects other than those described above are the same as those described in the first embodiment.
[0107] (Fourth embodiment)
[0108] In this embodiment, the method of pouring the invert differs from that of the third embodiment. An example of the method of pouring the invert in this embodiment will be described below with reference to Fig. 20. Figs. 20(a) and (b) are explanatory diagrams showing the main parts of the invert pouring equipment during the invert pouring process as seen from the side of the tunnel. In Fig. 20, the concrete is hatched to make the drawing easier to see.
[0109] As shown in FIG. 20(a), a first layer of concrete CC1 is poured in the same manner as described in the first embodiment above, and then a second layer of concrete CC2 is poured in the same manner as described in the first embodiment above.
[0110] However, in this embodiment, each time pouring of concrete CC2 around the mounting position of the flexible hose FH (a predetermined second range) is completed, the pipe holding part Sh3 is removed and the arm part AM is bent at a depth of the covering thickness T from the top surface of the poured second layer of concrete CC2 so that the entire arm part AM is completely embedded in the second layer of concrete CC2.
[0111] Then, as shown in FIG. 20(b), when the pouring of the second layer of concrete CC2 is completed, the operation of the stationary pump P is stopped, and the inflow of the concrete CC2 into the stationary pump P is stopped.
[0112] In this manner, in this embodiment, the arm portion AM of the support leg Sk3 is folded and completely embedded in the second layer of concrete CC2, so that the quality of the invert can be ensured. Other effects are the same as those described in the third embodiment.
[0113] The invention made by the inventor has been specifically described above based on the embodiment, but the embodiment disclosed in this specification is illustrative in all respects and is not limited to the disclosed technology. In other words, the technical scope of the present invention should not be interpreted restrictively based on the description in the above embodiment, but should be interpreted strictly according to the description in the claims, and includes technologies equivalent to the described technologies in the claims and all modifications that do not deviate from the gist of the claims.
[0114] For example, in the above-mentioned second embodiment, the case where all the P-containers PC are pulled out at once is illustrated for the sake of simplicity, but the present invention is not limited to this, and for example, the pipe holding part Sh2 may be freely divided into a plurality of parts, and the plurality of P-containers PC fixed to the divided pipe holding parts Sh2 may be pulled out at once. By pulling out the plurality of P-containers PC fixed to the pipe holding part Sh2 at the front (rear) side in the order in which pouring is completed, it is possible to prevent the second layer of concrete CC2 from hardening and making it impossible to pull out the P-containers PC.
[0115] For example, in the above-mentioned third and fourth embodiments, as shown in FIG. 16, a piping holding part Sh3 having a spring part UH2 is used, but this is not limited to this, and for example, a piping holding part having a structure in which the spring part UH2 is not provided and both ends of the piping abutment part UH1 are directly connected to the upper part of a pair of supports US, US may be used. [Industrial Applicability]
[0116] The above explanation shows the application of the invert casting method of the present invention to the casting of inverts in mountain tunnels, but the present invention is not limited to this and can be applied, for example, to the casting of inverts in tunnels in urban areas. [Explanation of symbols]
[0117] CE Invert Concrete Pouring Equipment P Stationary pump (means of concrete supply) SW Supply destination switching section (concrete supply destination switching means) FCP No. 1 pouring pipe SCP 2nd pouring pipe CP1 piping section (first piping section) CP2 piping section (second piping section) CPk locking part SL sealing material Jv Victoric joint material S Support member Sk1,Sk2,Sk3 Support legs BS Base BD Body part AM Arm section Sh1,Sh2,Sh3 Piping holding part US support UC connection UH holding part UP Stepping block Platform W1 PC P-con (jig) Ax mounting bracket FH Flexible hose (flexible piping) H Hopper BP Branch Pipe BP1 Inflow pipe section BP2,BP3 Outflow pipe section V Switching Valve Vc valve operation section Vp Partition pin Vh through hole CC1, CC2 Concrete CSF, CSS pouring top surface Ra, Rb Concave T Cover thickness
Claims
1. providing a concrete supply means for supplying concrete to a pouring area of the invert; A process of providing a plurality of first piping sections in a state in which they are detachably connected to each other along a dispensing direction of the concrete, and installing a first pouring pipe for dispensing the first layer of concrete of the invert in a pouring area of the invert; a step of providing a plurality of second piping sections detachably connected to each other along a direction in which the concrete is dispensed, and installing a second pouring pipe for dispensing the second layer of concrete of the invert above the first pouring pipe while being supported by a plurality of support members arranged along the second pouring pipe; A process of installing a concrete supply destination switching means for switching the supply destination of the concrete supplied from the concrete supply means to either the first pouring pipe or the second pouring pipe; having a first pouring step in which the first layer of concrete is poured by discharging the concrete supplied from the concrete supply means to the first pouring pipe through the concrete supply destination switching means from a flexible pipe detachably connected to the concrete discharge end of the first pouring pipe; a second pouring step in which, after the first pouring step, the flexible pipe is removed from the first pouring pipe and detachably connected to the tip of the second pouring pipe, and the concrete supplied from the concrete supply means to the second pouring pipe via the concrete supply destination switching means is discharged from the flexible pipe to pour the second layer of concrete on the poured upper surface of the first layer of concrete; having The first casting step includes: (a) performing a pouring process in a first predetermined area; (b) removing the flexible pipe after the casting of the first area is completed; (c) removing a predetermined number of the first piping sections from the tip of the first casting pipe after the casting of the first range is completed; (d) after the step (c), attaching the flexible pipe removed in the step (b) to the tip of the first pouring pipe remaining after the step (c), and then resuming pouring of the first layer of concrete; (e) repeating steps (a) to (d) until the entire first layer of concrete has been poured; having The second casting process includes: (f) performing a second predetermined area of pouring; (g) removing the flexible pipe after the casting of the second area is completed; (h) removing a predetermined number of the second piping sections from the tip of the second casting pipe after the casting of the second range is completed; (i) after the step (h), attaching the flexible pipe removed in the step (g) to the tip of the second concrete pouring pipe remaining after the step (h), and then resuming pouring of the second layer of concrete; (j) repeating steps (f) to (i) until the entire pouring of the second layer of concrete is completed; A method for pouring an invert, comprising the steps of:
2. 2. The method of pouring an invert as described in claim 1, characterized in that after the second pouring process, the support member is left in the first layer of concrete and the second layer of concrete with the highest part of the support member positioned a predetermined thickness below the upper surface of the poured second layer of concrete.
3. The support member includes a support leg, a jig detachably attached to the top of the support leg, and a pipe holder connected to the jig and disposed above the upper surface of the second layer of concrete to hold the second pouring pipe. The invert casting method described in claim 1, characterized in that in the second casting process, after the second layer of concrete is poured so that the upper surface of the jig is exposed from the upper surface of the poured second layer of concrete, the jig is pulled out from the second layer of concrete, a recess is formed in the location of the jig, and the recess is further filled.
4. The invert casting method according to claim 3, characterized in that the support leg is installed so that the top of the support leg is located a predetermined thickness below the upper surface of the second layer of concrete.
5. A method for pouring an invert as claimed in claim 3 or 4, characterized in that when the jig is pulled out from the second layer of concrete, multiple jigs are pulled out at once.
6. The support member includes a support leg and a pipe holding portion that is detachably provided at the top of the arm portion of the support leg and holds the second casting pipe. The top of the arm portion and the pipe holding portion are located above the upper surface of the poured second layer of concrete, 2. The method for pouring an invert as claimed in claim 1, characterized in that, in the second pouring process, the second layer of concrete is poured from above the upper surface of the second layer of concrete.
7. The second pouring step includes a step of removing the pipe holding portion from the support leg after pouring the second layer of concrete, and a step of cutting and removing the arm portion at a position a predetermined thickness below an upper surface of the poured second layer of concrete, 7. The invert casting method according to claim 6, characterized in that after the second casting process, the support leg is left in the first layer of concrete and the second layer of concrete with the cut point of the arm portion positioned a predetermined thickness below the upper surface of the poured second layer of concrete.
8. The second pouring step includes a step of removing the pipe holding portion from the support leg after pouring the second layer of concrete, and bending the arm portion at a position a predetermined thickness below the upper surface of the second layer of concrete, 7. The invert casting method according to claim 6, characterized in that after the second casting process, the support leg is left in the first layer of concrete and the second layer of concrete with the highest part of the arm portion positioned a predetermined thickness below the upper surface of the second layer of concrete.
Citation Information
Patent Citations
Method and apparatus for placing concrete in dam construction work
JP1982085415A
Method and apparatus for invert concrete covering work for tunnel
JP1989187293A
Method and equipment for executing tunnel invert
JP1998220189A
Tunnel construction method
JP2014173290A
Placement system
JP2022026076A