Facility configuration proposal system and facility configuration proposal method

JP2024141054AActive Publication Date: 2024-10-10HITACHI LTD
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
JP2023052492
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-03-29
Publication Date
2024-10-10
Estimated Expiration
2043-03-29

AI Technical Summary

Benefits of technology

【0008】 本発明の設備構成提案システム、および、設備構成提案方法によれば、実用的な時間内で、KPI最適化に寄与する設備投資シナリオを立案することができる。

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024141054000001_ABST
    Figure 2024141054000001_ABST
Patent Text Reader

Abstract

To formulate a facility investment scenario that contributes to KPI optimization within a practical time period.SOLUTION: A facility configuration proposal system evaluates a plurality of facility investment scenarios. The facility configuration proposal system comprises: an information-before-statistics database that records time-series information on energy consumption of consumers; a statistical processing section that groups the time-series information recorded in the information-before-statistics database on the basis of predetermined criteria, and statistically processes for each group; an information-after-statistics database that records the time-series information statistically processed by the statistical processing section; a rough optimum calculation section that calculates KPIs on the basis of the time-series information recorded in the information-after-statistics database; a scenario selection section that selects some facility investment scenarios from among a plurality of facility investment scenarios on the basis of KPIs that the rough optimum calculation section has evaluated; and a precise optimum calculation section that calculates KPIs for the facility investment scenarios selected by the scenario selection section on the basis of the time-series information recorded in the information-before-statistics database.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a facility configuration proposal system and a facility configuration proposal method that formulates a facility investment scenario for optimizing KPIs. [Background technology]

[0002] There is a global demand for decarbonization to mitigate the progress of global warming, and large-scale energy users such as private companies that consume large amounts of energy, such as electricity and gas, are being asked to promote decarbonization by introducing highly energy-efficient equipment and updating to such equipment. However, many users do not have sufficient knowledge about decarbonization technologies, and therefore have found it difficult to independently create capital investment plans that optimize their contribution to decarbonization within limited budgets.

[0003] Here, the equipment planning method of Patent Document 1 is known as a conventional technology for making a computer create an equipment investment plan. For example, the abstract of this document states that the problem is to "optimize investment effects while responding to future increases in energy demand," and as one of the means for solving this problem, claim 1 discloses "an equipment planning method for a distributed energy system that supplies energy by a plurality of energy supply devices, which determines an optimal combination of the plurality of energy supply devices and the timing of their introduction based on an evaluation function including, as parameters, a predicted energy demand for the distributed energy system over a predetermined future period, a predicted fuel price for the energy supply devices over the predetermined period, and equipment information for the energy supply devices." [Prior art documents] [Patent documents]

[0004] [Patent Document 1] JP 2015-125643 A Summary of the Invention [Problem to be solved by the invention]

[0005] However, the technology of Patent Document 1 has a problem that it requires an excessively long computer processing time to optimize the equipment investment plan. This is because the equipment planning method of the document, as is clear from the configuration of claim 1 of the document, determines the optimal combination of a plurality of energy supply devices and the introduction timing thereof using the predicted energy demand, the predicted fuel price of the energy supply devices, and the equipment information of the energy supply devices as parameters for a predetermined future period, so that if the "predetermined future period" is long, the processing time will be extended, and further, if the variations of the "predicted energy demand," "predicted fuel price of the energy supply devices," and "equipment information of the energy supply devices" increase, a combination explosion will occur, and there is a possibility that the optimization processing of the equipment plan will not be completed within a practical time.

[0006] Therefore, an object of the present invention is to provide an equipment configuration proposal system and an equipment configuration proposal method that are capable of formulating equipment investment scenarios that contribute to KPI optimization within a practical time frame. [Means for solving the problem]

[0007] The present invention includes multiple means for solving the above-mentioned problems. One example is an equipment configuration proposal system for evaluating multiple equipment investment scenarios, comprising: a pre-statistics information database that records time series information of energy consumption of consumers; a statistical processing unit that groups the time series information recorded in the pre-statistics information database based on predetermined criteria and performs statistical processing for each group; a post-statistics information database that records the time series information statistically processed by the statistical processing unit; a rough optimization calculation unit that calculates a KPI based on the time series information recorded in the post-statistics information database; a scenario selection unit that selects some equipment investment scenarios from the multiple equipment investment scenarios based on the KPI evaluated by the rough optimization calculation unit; and a precise optimization calculation unit that calculates the KPI for the equipment investment scenarios selected by the scenario selection unit based on the time series information recorded in the pre-statistics database. Effect of the Invention

[0008] According to the facility configuration proposal system and facility configuration proposal method of the present invention, a facility investment scenario that contributes to KPI optimization can be formulated within a practical amount of time. [Brief description of the drawings]

[0009] [Figure 1] Overall configuration of the equipment configuration proposal system. [Diagram 2] An example of an input screen image. [Diagram 3] An example of a data format for a pre-statistical demand database. [Figure 4] 1 is an example of a data format for a facility configuration database. [Diagram 5] 1 shows an example of a data format of a coefficient database. [Figure 6] 13 is a processing flow of the grouping part. [Figure 7] An example of a data format for the post-statistical demand database. [Figure 8] 4 shows the processing flow of the rough optimum calculation part. [Figure 9]An example of the data format for a KPI database by facility configuration. [Figure 10] An example of a management format for entered scenarios. [Figure 11] 4 shows the processing flow of the scenario generation part. [Figure 12] An example of the data format for the scenario-specific summary KPI database. [Figure 13] 3 is an example of a screen image of the output unit 11. [Figure 14] Processing flow of the scenario selection section. [Figure 15A] An image of the process for checking the number of included plots. [Figure 15B] An image of the process for checking the number of included plots. [Figure 16] Processing flow of the precise optimum calculation part. [Figure 17] An example of the data format for a scenario-specific refined KPI database. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0010] Hereinafter, a facility configuration proposal system 100 according to an embodiment of the present invention will be described with reference to the drawings.

[0011] <Overall configuration of facility configuration proposal system 100> 1 is a diagram showing the overall configuration of an equipment configuration proposal system 100 of this embodiment, and an instruction input device 200 (keyboard, mouse, touch panel, etc.) and a display device 300 (liquid crystal display, etc.) connected to the system. Specifically, the equipment configuration proposal system 100 is a computer equipped with hardware such as a calculation device such as a CPU, a main storage device such as a semiconductor memory, an auxiliary storage device such as a hard disk, and a communication device. The calculation device executes a program while referring to a specified database to realize each function described below, but the following description will omit such well-known techniques as appropriate.

[0012] As shown in Fig. 1, facility configuration proposal system 100 of this embodiment includes an input unit 1, a pre-statistical demand database 2, a facility configuration database 3, a coefficient database 4, a statistical processing unit 5, a post-statistical demand database 6, a rough optimum calculation unit 7, a facility configuration-specific KPI database 8, a scenario creation unit 9, a scenario-specific rough KPI database 10, an output unit 11, a scenario selection unit 12, a precise optimum calculation unit 13, and a scenario-specific precise KPI database 14, and as indicated by the dashed frame in the figure, the statistical processing unit 5 to the scenario-specific rough KPI database 10 constitute a rough evaluation unit, and the precise optimum calculation unit 13 and the scenario-specific precise KPI database 14 constitute a precise evaluation unit. The details of each unit that constitutes facility configuration proposal system 100 will be explained in order below.

[0013] <Input section 1> The input unit 1 is a functional unit that communicates with the instruction input device 200 and the display device 300 when an operator of the present system sets various setting values, and transmits the values ​​set by the operator to the statistical processing unit 5 and the like.

[0014] 2 is an example of a screen image displayed on the display device 300 when various setting values ​​are being set. In this example, there are setting areas for four items.

[0015] The setting area 301 is an area for defining grouping criteria used by the statistical processing unit 5. In this area, multiple grouping criteria can be selected by checking any checkbox. In FIG. 2, three grouping criteria are provided: "seasonal", "monthly", and "weekday / holiday", and an example is shown in which two of them, "monthly" and "weekday / holiday", have been selected.

[0016] The setting area 302 is an area for alternatively selecting KPIs (Key Performance Indicators) to be used in the rough optimization calculation unit 7 and the precise optimization calculation unit 13. In Fig. 2, two KPIs are prepared: business operating expenses "OPEX" and carbon dioxide emissions "CO2 emissions", and the example shows a state in which minimization of "OPEX" has been selected.

[0017] The setting area 303 is an area where the operator sets the scenario to be input to the scenario generation unit 9. Here, "10 years" is selected as the number of years for generating the capital investment scenario, and the following is shown as an example of a state in which the equipment configuration #1 is set for the first to third years, the equipment configuration #3 for the fourth and fifth years, the equipment configuration #4 for the sixth to eighth years, and the equipment configuration #2 for the ninth and tenth years as the scenario No. 1. If the "Register" button is pressed in this state, the combination information of the set equipment configuration # is sent to the scenario generation unit 9 as scenario No. 1 and is stored in the scenario database (FIG. 10) described later. In the following, it is assumed that the operator repeats the scenario generation to generate 13 scenarios, from scenario No. 1 to scenario No. 13. The capital investment scenario is not limited to a combination of equipment configuration #s for multiple years, and may be a combination of equipment configuration #s for a single year only.

[0018] The setting area 304 is an area for determining the rules used by the scenario selection unit 12. These rules are for selecting scenarios to be subjected to detailed evaluation from all scenarios to be subjected to rough evaluation, and in Fig. 2, "1" is registered as the tolerance value that defines the rule. The significance of this tolerance value will be explained in detail in Fig. 15A and Fig. 15B, and the explanation thereof will be omitted here.

[0019] <Pre-statistical demand database 2> The pre-statistical demand database 2 is a database in which energy consumed during a certain period in the past by consumers who use this system to create capital investment plans (hereinafter referred to as "specific consumers") is recorded in chronological order.

[0020] Figure 3 is an example of the data format of the pre-statistical demand database 2. In this example, data on "date and time," "season," "month," "weekday / holiday," and "electricity consumption" are registered in order from the leftmost column. As an example, this shows one year's worth of electricity consumption data from April 1, 2022 to March 31, 2023, recorded in 30-minute increments.

[0021] <Facility configuration database 3> The facility configuration database 3 is a database that defines a combination of facilities operated by a specific customer.

[0022] Fig. 4 is an example of the data format of the facility configuration database 3. In this example, data such as "Facility configuration #", "Photovoltaic power generation (first unit)", "Photovoltaic power generation (second unit)", "Storage battery (first unit)", and "Storage battery (second unit)" are registered in order from the leftmost column.

[0023] "Equipment configuration #" in this diagram corresponds to "Equipment configuration #" in the setting area 303 in FIG. 2. Therefore, by referring to this database, it is possible to know the transition of the equipment configuration for each scenario set by the operator. Also, "1" data in the database means applicable, and "0" data means non-applicable. Note that hereinafter, the letters PV will be used to identify elements related to photovoltaic power generation, and the letters BT will be used to identify elements related to storage batteries.

[0024] Referring to this database, Scenario No. 1 shown in Figure 2 can be interpreted as the following capital investment scenario. (1) Years 1 to 3 after facility configuration #1 is established: In the first year, the first unit of the solar power generation equipment is newly installed and begins operation. In the second and third years, the existing solar power generation equipment continues to operate. (2) Years 4 and 5 after setting up facility configuration #3: In the fourth year, the existing solar power generation equipment will continue to operate, and the first unit of the storage battery equipment will be newly installed and started to operate. In the fifth year, the existing solar power generation equipment and storage battery equipment will continue to operate. (3) Years 6 to 8 after setting up facility configuration #4: In the sixth year, the existing solar power generation system and battery storage system will continue to operate, and a second solar power generation system unit will be added and started to operate. In the seventh and eighth years, the existing solar power generation system and battery storage system will continue to operate. (4) Years 9 and 10 after setting up equipment configuration #2: In the 9th year, the existing solar power generation equipment and battery storage equipment will continue to operate, and a second unit of the battery storage equipment will be added and started to operate. In the 10th year, the existing solar power generation equipment and battery storage equipment will continue to operate.

[0025] <Coefficient database 4> The coefficient database 4 is a database in which various set values ​​such as the electricity rate unit price and the CO2 emission coefficient are recorded by fiscal year.

[0026] Figure 5 is an example of the data format of the coefficient database 4. In this example, from the leftmost column, there are "item" and fiscal year (year), and data by year is recorded for each item such as electricity unit price, CO2 emission coefficient, and carbon tax.

[0027] <Statistical processing unit 5> The statistical processing unit 5 is a functional unit that groups the energy consumption recorded in the pre-statistical demand database 2 based on settings made by an operator, and outputs a statistical energy consumption waveform for each group.

[0028] FIG. 6 shows a process flow of the statistical processing unit 5.

[0029] First, in step S51, the statistical processing unit 5 checks the grouping criteria selected by the operator in the setting area 301. In the example of Fig. 2, since "by month" and "by weekday / holiday" are selected, the statistical processing unit 5 recognizes that the data in the pre-statistical demand database 2 will be grouped into groups such as "April and weekday", "April and holiday", "May and weekday", and "May and holiday".

[0030] Step S52 is a loop function for grouping criterion variations. Based on the criterion recognized in step S51, for example, the following steps S53 to S55 are repeatedly executed in the order of "April and weekday", "April and holiday", "May and weekday", "May and holiday", ...

[0031] In step S53, the statistical processing unit 5 extracts data corresponding to the group being processed from the pre-statistical demand database 2. For example, in the first processing loop, a set of data corresponding to "April and weekday" is extracted from the database in FIG.

[0032] Step S54 is a time loop function. Since power consumption is registered in 30-minute intervals in the pre-statistical demand database 2 in Fig. 3, step S55 (described later) is executed in the order of, for example, 00:00, 00:30, 01:00, 01:30, ...

[0033] In step S55, the statistical processing unit 5 calculates the average value of the acquired data. For example, the average value is calculated for the power consumption data corresponding to "April and weekday" and "00:00 to 00:29". Note that although average value calculation is illustrated here as an example of statistical processing, other statistical processing methods such as MBR (Memory Based Reasoning), multiple regression analysis, and exponential smoothing may be used for the statistical processing in this step.

[0034] In step S56, the statistical processing unit 5 records the above processing results in the post-statistical demand database 6.

[0035] <Post-statistical demand database 6> The post-statistical demand database 6 is a database in which the statistical energy consumption waveforms for each group generated by the statistical processing unit 5 are recorded.

[0036] Fig. 7 is an example of the data format of the post-statistics demand database 6. In this example, starting from the leftmost column, data on "season," "month," "weekday / holiday," "time," and "electricity consumption" after statistical processing are registered. Note that since "seasonal unit" is not selected in the setting area 301 in Fig. 2, the "season" column in Fig. 7 is "N / A."

[0037] <Rough Optimization Calculation Unit 7> The rough optimum calculation unit 7 is a functional unit that executes optimum calculations for each year using the coefficient database 4 to optimally operate the equipment in the equipment configuration database 3 under the KPIs set by the operator for each statistical energy consumption waveform recorded in the post-statistical demand database 6, and records the results in an equipment configuration-specific KPI database 8. Note that since the post-statistical demand database 6 generated through statistical processing in the statistical processing unit 5 has a significantly compressed amount of data compared to the pre-statistical demand database 2, calculation processing based on the post-statistical demand database 6 is completed in an extremely short time compared to the same type of calculation processing based on the pre-statistical demand database 2.

[0038] FIG. 8 shows a process flow of the rough optimum calculation unit 7.

[0039] First, in step S71, the rough optimization calculation unit 7 recognizes the optimization element. Specifically, the rough optimization calculation unit 7 checks the setting area 302 in Fig. 2 and confirms that the KPI is the minimization of OPEX.

[0040] In step S72, the rough optimum calculation unit 7 recognizes the grouping criteria. Specifically, it checks the setting area 301 in Fig. 2 and confirms that the grouping criteria are "monthly" and "weekday / holiday".

[0041] Step S73 is an annual loop. To grasp the number of times this loop is executed, the rough optimization calculation unit 7 checks the number of years for generating capital investment scenarios in the setting area 303 in Fig. 2. In Fig. 2, "10" is registered as the number of years for generating capital investment scenarios, so the loop is performed from the first year to the tenth year in order.

[0042] In step S 74 , the rough optimum calculation unit 7 acquires a set of relevant data from the coefficient database 4 .

[0043] Step S75 is a loop for the equipment configuration #. Here, the rough optimization calculation unit 7 performs a loop process for all equipment configurations # recorded in the equipment configuration database 3.

[0044] In step S76, the rough optimization calculation unit 7 recognizes the equipment configuration. Specifically, the rough optimization calculation unit 7 recognizes the equipment configuration # of the loop in step S75 from the equipment configuration database 3.

[0045] Step S77 is a loop for grouping criteria variations. Based on the information recognized in step S72, steps S78 to S7c are repeatedly executed in the following order, such as "April and weekday", "April and holiday", "May and weekday", and "May and holiday".

[0046] In step S78, the rough optimum calculation unit 7 extracts data corresponding to the setting of the loop in step S77 from the post-statistics demand database 6.

[0047] In step S79, the rough optimization calculation unit 7 optimizes the operation plan for the equipment of the target equipment configuration # based on the KPI acquired in step S71. That is, it optimizes Equation 1 by minimizing OPEX.

[0048]

number

[0049] Here, OPEX(g) is the OPEX (¥) in group g, D(g, t) is the power consumption (kWh) in group g and at time t, Ppv(n, g, t) is the power generation amount (kWh) of photovoltaic power generation PV(n) in group g and at time t, Pbt(m, g, t) is the charge / discharge amount (kWh) of storage battery BT(m) in group g and at time t (where charging is positive and discharging is negative), UP(y) is the electricity rate unit price (¥ / kWh) in fiscal year y, and Pbt(m, g, t) is the optimization design variable. T is the final value of the time loop, N is the number of photovoltaic power generation equipment PV (total of new installations and expansions), and M is the number of storage battery equipment BT (total of new installations and expansions). Note that the constraints are that the remaining amount of storage does not exceed the storage battery capacity and does not become negative.

[0050] In step S7a, the approximate optimum calculation unit 7 calculates the amount of received power as a result of executing step S79 using Equation 2. Here, Pbt(m, g, t) uses the value obtained by the optimum calculation in step S79. Also, P(y, g, t) is the amount of received power (kWh) in year y, group g, and time t. Hereafter, descriptions of elements already mentioned will be omitted.

[0051]

number

[0052] In step S7b, the rough optimum calculation unit 7 calculates the CO2 emission amount using Equation 3. Here, UC(y) is the CO2 emission coefficient (t-CO2 / kWh) in year y, and CO2(y, g) is the CO2 emission amount (t-CO2 / kWh) in year y and group g.

[0053]

number

[0054] In step S7c, the rough optimization calculation unit 7 calculates OPEX using Equation 4. Here, OPEX(y, g) is the OPEX (yen) for the year y and group g.

[0055]

number

[0056] In step S7d, the rough optimum calculation unit 7 calculates the annual values ​​of OPEX and CO2 emissions. To calculate the annual values, both OPEX and CO2 emissions can be integrated by group g, and are calculated using Equations 5 and 6.

[0057]

number

[0058]

number

[0059] In step S7e, the rough optimization calculation unit 7 records the results calculated by the formulas 5 and 6 for each fiscal year in the facility configuration-specific KPI database 8.

[0060] <KPI database by facility configuration 8> Fig. 9 is an example of the data format of the equipment configuration-specific KPI database 8. In this example, "Equipment configuration #", "Year", "OPEX", and "CO2 emissions" are registered in this order from the leftmost column. As is clear from this figure, the rough optimization calculation unit 7 records the calculation result of formula 5 in the "OPEX" column for each combination of "Equipment configuration #" and "Year", and records the calculation result of formula 6 in the "CO2 emissions" column.

[0061] <Scenario Generation Unit 9> The scenario creation unit 9 is a functional unit that defines the equipment configuration (equipment investment scenario) for each fiscal year based on the operator's settings, and calculates the KPI for each equipment investment scenario.

[0062] Fig. 10 is an example of a management format for capital investment scenarios entered by an operator. Here, the equipment configurations # for the first to tenth years are recorded for each scenario number. The correspondence between scenario numbers and equipment configurations # is the result of settings made by the operator in the setting area 303 in Fig. 2.

[0063] FIG. 11 shows a process flow of the KPI calculation by the scenario generating unit 9.

[0064] In step S91, the scenario generating unit 9 refers to the table in FIG. 10 and performs loop processing by scenario number.

[0065] In step S92, a loop is performed by year, in this case from the 1st year to the 10th year.

[0066] In step S93, the scenario generating unit 9 recognizes the equipment configuration #. The equipment configuration # is identified by the scenario No. and year with reference to the table in FIG.

[0067] In step S94, the scenario generation unit 9 refers to the equipment configuration-specific KPI database 8 to recognize the OPEX and CO2 emission amount. For example, by referring to the table in Fig. 9, the corresponding OPEX and CO2 emission amount are identified from the equipment configuration number and year recognized in step S93.

[0068] In step S95, the scenario generating unit 9 accumulates the values ​​in step S94 for a predetermined number of years (here, 10 years).

[0069] In step S96, the scenario generating unit 9 records the calculation results (accumulated OPEX, accumulated CO 2 emission amount) in step S95 in the scenario-specific summary KPI database 10.

[0070] <10 KPI databases by scenario> The scenario-specific summary KPI database 10 is a database in which the output results of the scenario generation unit 9 are stored.

[0071] Fig. 12 is an example of the data format of the scenario-specific summary KPI database 10. In this example, "Scenario No.", "Cumulative OPEX", and "Cumulative CO2 emissions" are registered in this order from the leftmost column. The values ​​calculated in step S95 of Fig. 11 are recorded in the "Cumulative OPEX" and "Cumulative CO2 emissions" columns.

[0072] <Output section 11> The output unit 11 is a functional unit for displaying the KPIs of each scenario on the display device 300 based on the records in the scenario-specific outline KPI database 10 and the records in the scenario-specific detailed KPI database 14 described below.

[0073] 13 is an example of a screen image displayed on the display device 300 connected to the output unit 11. The outline evaluation graph 305 on the left is the result of the outline evaluation, and the detailed evaluation graph 306 on the right is the result of the detailed evaluation. In both graphs, the horizontal axis is the accumulated OPEX and the vertical axis is the accumulated CO2 emissions. The outline evaluation graph 305 is displayed with reference to a table in the scenario-specific outline KPI database 10, and the detailed evaluation graph is displayed with reference to a table in the scenario-specific detailed KPI database 14, which will be described later. The outline evaluation graph 305 on the left shows KPIs from scenario No. 1 to scenario No. 13 as an example, and the detailed evaluation graph 306 on the right shows KPIs from selected scenario No. 1 to scenario No. 8.

[0074] <Scenario Selection Section 12> The scenario selection unit 12 is a functional unit that selects, from the equipment investment scenarios handled in the above-mentioned rough evaluation unit, equipment investment scenarios to be handled in the detailed evaluation of the detailed optimization calculation unit 13 and the scenario-specific detailed KPI database 14, based on the operator's settings.

[0075] FIG. 14 shows a processing flow of the scenario selection unit 12.

[0076] First, in step S121, the scenario selection unit 12 recognizes the allowable number of plots set in the setting area 304. In Fig. 2, "1" is set as the allowable value.

[0077] In step S122, the scenario selection unit 12 refers to the scenario-specific summary KPI database 10 and checks the number of capital investment scenarios that have been roughly evaluated in the rough evaluation unit ("13" in the example of FIG. 12).

[0078] In step S123, a loop is performed using the scenario number.

[0079] In step S124, the scenario selection unit 12 checks the number of included plots for each capital investment scenario in the outline evaluation graph 305. An image of the specific processing of this step will be described with reference to Figs. 15A and 15B.

[0080] Fig. 15A is an image showing the procedure for checking the number of plots included in scenario No. 7. If a rectangle is drawn with the plot of scenario No. 7 and the origin as its diagonal, the plots within this rectangle are better scenarios than scenario No. 7 in terms of both the KPIs of cumulative OPEX and cumulative CO2 emissions. In this example, the number of plots within the rectangle that corresponds to the number of scenarios better than scenario No. 7 is only one plot, that of scenario No. 3, so the scenario selection unit 12 determines the number of plots included in scenario No. 7 to be "1."

[0081] Similarly, Fig. 15B is an image showing the procedure for checking the number of plots included in scenario No. 11. If a rectangle is drawn with the plot of scenario No. 11 and the origin as its diagonal, the plots within this rectangle are better scenarios than scenario No. 11 in terms of both the KPIs of cumulative OPEX and cumulative CO2 emissions. In this example, the number of plots within the rectangle that corresponds to the number of scenarios that are better than scenario No. 11 is four plots, namely scenarios Nos. 3, 4, 5, and 7, so the scenario selection unit 12 determines that the number of plots included in scenario No. 11 is "4."

[0082] In step S125, the scenario selection unit 12 makes a branching decision as to whether the number of included plots is equal to or less than the allowable number of plots. If the requirement is met, the process proceeds to step S126, and if the requirement is not met, the process skips step S126. As shown in Figure 2, if the allowable value set in the setting area 304 is "1", only scenario numbers with an included plot number of "0" or "1" proceed to step S126, and scenario numbers with an included plot number of "2" or more do not proceed to step S126.

[0083] In step S126, the scenario numbers that satisfy the requirements of step S125 are recorded in memory (not shown). In the above example, scenario No. 7 in Fig. 15A is recorded in memory because the number of included plots is "1", and scenario No. 11 in Fig. 15B is not recorded in memory because the number of included plots is "4". Therefore, in this step, scenarios No. 1 to No. 8 are selected from the capital investment scenarios in the overview evaluation graph 305 in Fig. 13 and recorded in memory.

[0084] <Precise optimal calculation section 13> The precise optimization calculation unit 13 is a functional unit that uses data from the pre-statistical demand database 2, the equipment configuration database 3, and the coefficient database 4 for the equipment investment scenario selected by the scenario selection unit 12, and creates an optimal equipment operation plan based on settings made by the operator.

[0085] FIG. 16 shows a process flow of the precise optimization calculation unit 13.

[0086] In step S131, the precise optimization calculation unit 13 recognizes the optimization factors. The processing content of this step is the same as that of step S71.

[0087] In step S132, the precise optimization calculation unit 13 performs loop processing in the order of the selected scenario numbers stored in the memory in step S126 of FIG.

[0088] Step S133 loops through the years of the set number of years of the capital investment scenario (from the first year to the tenth year in the example of FIG. 2).

[0089] In step S134, the precise optimization calculation unit 13 refers to the coefficient database 4 to obtain various coefficients corresponding to the year.

[0090] In step S135, the precise optimization calculation unit 13 refers to the table in FIG. 10 and recognizes the facility configuration # corresponding to the scenario No. and year.

[0091] In step S136, the precise optimization calculation unit 13 refers to the equipment configuration database 3 and recognizes an equipment configuration corresponding to the equipment configuration # recognized in step S135.

[0092] Step S137 loops by date. The date used here is the date recorded in the pre-statistical demand database 2. That is, the subsequent processing is performed based on the detailed data recorded in the pre-statistical demand database 2.

[0093] In step S138, the precise optimization calculation unit 13 refers to the pre-statistics demand database 2 and extracts the power demand data for the target date.

[0094] In step S139, the precise optimization calculation unit 13 optimizes the operation pattern of each piece of equipment. That is, it optimizes Equation 7 by minimizing OPEX.

[0095]

number

[0096] Here, OPEX(d) is the OPEX (¥) on date d, D(d, t) is the power consumption (kWh) on date d and time t, Ppv(n, d, t) is the amount of power generated by PV(n) on date d and time t (kWh), Pbt(m, d, t) is the amount of power charged and discharged by the storage battery (m) on date d and time t (kWh) (where charging is positive and discharging is negative), UP(y) is the unit price of electricity in fiscal year y (¥ / kWh), and Pbt(m, d, t) is the optimization design variable. T is the final value of the time loop, N is the number of PV units (total of new and additional installations), and M is the number of storage batteries (total of new and additional installations). Note that the constraints are that the remaining amount of power does not exceed the storage battery capacity and does not become negative.

[0097] In step S13a, the precise optimum calculation unit 13 calculates the amount of received power as a result of executing step S139. The amount of received power is calculated using Equation 8. Here, Pbt(m, d, t) uses the value obtained by the optimum calculation in step S139. Also, P(y, d, t) is the amount of received power (kWh) at time t on year y and date d. Hereafter, descriptions of elements already mentioned will be omitted.

[0098]

number

[0099] In step S13b, the precise optimization calculation unit 13 calculates the CO2 emissions using Equation 9. Here, UC(y) is the CO2 emissions coefficient (t-CO2 / kWh) for the year y, and CO2(y, d) is the CO2 emissions (t-CO2 / kWh) for the year y and date d.

[0100]

number

[0101] In step S13c, the precise optimization calculation unit 13 calculates OPEX using formula 10. Here, OPEX(y, d) is the OPEX (yen) for the year y and the date d.

[0102]

number

[0103] In step S13d, the precise optimization calculation unit 13 calculates the annual values ​​of OPEX and CO2 emissions. To calculate the annual values, both OPEX and CO2 emissions can be integrated on date d, and are calculated using Equations 11 and 12.

[0104]

number

[0105]

number

[0106] In step S13e, the precise optimization calculation unit 13 uses Equations 13 and 14 to add up the annual OPEX value and the annual CO2 emission value on an annual basis.

[0107]

number

[0108]

number

[0109] In step S13f, the refined optimization calculation unit 13 records the OPEX and CO2 emissions calculated using Equation 13 and Equation 14 in the scenario-specific refined KPI database 14. Note that the data recorded in the scenario-specific refined KPI database 14 in this step is calculated based on the refined data recorded in the pre-statistical demand database 2, and is therefore closer to the true values ​​than the recorded data in the scenario-specific outline KPI database 10, which is calculated based on the compressed data recorded in the post-statistical demand database 6.

[0110] <Scenario-specific KPI database 14> The scenario-specific refined KPI database 14 is a database in which the output results of the refined optimization calculation unit 13 are recorded. These results are displayed on the display device 300 via the output unit 11 described above.

[0111] Fig. 17 is an example of the data format of the scenario-specific detailed KPI database 14. In this example, the data for "Scenario No.", "Cumulative OPEX", and "Cumulative CO2 emissions" are registered in order from the leftmost column. Note that the values ​​calculated in step S13f of Fig. 16 are recorded in the "Cumulative OPEX" and "Cumulative CO2 emissions" columns.

[0112] Let us now return to Fig. 13. The detailed evaluation graph 306 on the right side of this figure is drawn from the records of the scenario-specific detailed KPI database 14 in Fig. 17. This detailed evaluation graph 307 is based on data before statistical processing, and therefore shows a more detailed evaluation that is closer to the true value than the rough evaluation graph 306 on the left, which is based on data (such as average values) from which some information has been lost due to statistical processing. Therefore, by referring to the detailed evaluation graph 306, an operator can easily select an appropriate capital investment scenario that suits his or her needs.

[0113] It should be noted that the present invention is not limited to the above-described embodiment, but includes various modified examples. For example, the above-described embodiment has been described in detail to clearly explain the present invention, and the present invention is not necessarily limited to those including all of the described configurations. [Explanation of symbols]

[0114] 100 Facility configuration proposal system 1 Input section 2 Pre-statistical demand database 3. Facility configuration database 4 Coefficient database 5 Statistical Processing Unit 6 Post-statistical demand database 7. Approximate Optimal Calculation Section 8 KPI database by facility configuration 9 Scenario Generation Section 10 Summary KPI database by scenario 11 Output section 12 Scenario Selection Division 13 Fine optimization calculation section 14 Detailed KPI database by scenario 200 Instruction input device 300 display device

Claims

1. A facility configuration proposal system for evaluating a plurality of facility investment scenarios, comprising: A pre-statistical information database that records time-series information on energy consumption of consumers; a statistical processing unit that groups the time-series information recorded in the pre-statistical information database based on a predetermined criterion and performs statistical processing for each group; a post-statistical information database in which time-series information statistically processed by the statistical processing unit is recorded; a rough optimum calculation unit that calculates a KPI based on the time-series information recorded in the post-statistical information database; a scenario selection unit that selects a portion of the capital investment scenarios from the plurality of capital investment scenarios based on the KPI evaluated by the rough optimization calculation unit; a refined optimization calculation unit that calculates the KPI for the equipment investment scenario selected by the scenario selection unit based on the time-series information recorded in the pre-statistical information database; An equipment configuration proposal system comprising:

2. 2. The facility configuration proposal system according to claim 1, The facility configuration proposal system, wherein the statistical processing performed by the statistical processing unit for each group is any one of average value calculation, MBR, multiple regression analysis, and exponential smoothing.

3. 2. The facility configuration proposal system according to claim 1, The equipment configuration proposal system is characterized in that the scenario selection unit selects the part of the equipment investment scenarios based on the magnitude relationship of the KPI values ​​of each equipment investment scenario calculated by the rough optimization calculation unit.

4. 2. The facility configuration proposal system according to claim 1, The equipment configuration proposal system is characterized in that the scenario selection unit selects a certain equipment investment scenario when the number of equipment investment scenarios with KPIs superior to the KPI of the certain equipment investment scenario is equal to or less than a predetermined value.

5. 2. The facility configuration proposal system according to claim 1, The KPI is OPEX or CO 2 A facility configuration proposal system that is characterized by the fact that the facility configuration proposal system is an emission amount.

6. 2. The facility configuration proposal system according to claim 1, The investment scenario is information defining a single-period investment configuration, or An equipment configuration proposal system characterized by providing information defining the transition of equipment configuration over multiple periods.

7. A facility configuration proposal method for evaluating a plurality of facility investment scenarios, comprising: recording time series information of energy consumption of a consumer in a pre-statistical information database; A step of grouping the time-series information recorded in the pre-statistical information database based on a predetermined criterion and performing statistical processing for each group; recording the statistically processed time series information in a post-statistical information database; Calculating KPIs based on the time series information recorded in the post-statistical information database; selecting a portion of the investment scenarios from the plurality of investment scenarios based on the KPI; Calculating the KPIs for the selected capital investment scenarios based on the time-series information recorded in the pre-statistical information database; A facility configuration proposing method comprising:

Citation Information

Patent Citations

  • Facility planning supporting device for cogeneration system, supporting method, and program

    JP2009026092A

  • System and method of real-time energy diagnosis for energy saving in building

    KR1020150084196A

  • Facilities investment scenario provision device and method

    WO2014109023A1

  • Facility planning method, program and device for distributed energy system

    JP2015125643A