Removal of existing pile and continuous method of constructing new pile

The continuous construction method using bentonite water and cement milk for overlapping holes allows for immediate construction of new piles after removing existing ones, reducing construction time and ensuring stability and verticality.

JP2024143264AActive Publication Date: 2024-10-11KUMAGAI GUMI CO LTD
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
JP2023055845
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-03-30
Publication Date
2024-10-11
Estimated Expiration
2043-03-30

AI Technical Summary

Technical Problem

The construction period is prolonged when constructing new piles immediately after demolishing a building due to the need to wait for poorly blended cement milk and fluidized soil to solidify after removing existing piles.

Method used

A continuous construction method involving the use of bentonite water to fill the extraction hole, drilling a new pile hole that partially overlaps with the extraction hole, and filling it with cement milk to solidify and fix the new pile, ensuring the new pile is constructed without waiting for the cement milk to solidify.

Benefits of technology

This method allows for a significant reduction in construction time by enabling simultaneous removal and construction of new piles, reducing noise and vibration, and ensuring the verticality and stability of the new pile.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024143264000001_ABST
    Figure 2024143264000001_ABST
Patent Text Reader

Abstract

To provide a continuous method of constructing a new pile capable of reducing a construction period upon construction of the new pile after removing an existing pile.SOLUTION: A continuous method of existing pile removal and new pile construction is to fill bentonite water 4 made by mixing bentonite and water in a pull-out hole 5 formed by pulling out an existing pile. An boring hole 7 is formed by excavating the inside of a second casing 6 after boring a ground 1 with the second casing 6 so as to partly overlap with the pull-hole 5. Cement milk 9 is primarily filled from a bottom part of the boring hole 7 to an upper part. The second casing 6 left in the boring hole 7 is pulled out. The cement milk 9 is secondarily filled from the bottom part of the pull-out hole 5 partly having an overlapped part with the boring hole 7 to an upper part to overflow the left bentonite water 4. A new pile is inserted into the boring hole 7 in which the cement mile 9 is filled for installation.SELECTED DRAWING: Figure 8
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a continuous construction method for removing existing piles and constructing new piles. [Background technology]

[0002] When a building is to be demolished, the existing foundation piles (hereinafter referred to as existing piles) are also removed. There are two main methods for removing existing foundation piles: edge cutting and extraction and crushing and removal. The edge cutting and extraction method can reduce noise and vibration. Patent Documents 1 and 2 below disclose edge cutting and extraction methods for existing piles. The holes left after the existing piles are removed are backfilled with backfill materials such as lean-mix cement milk or liquefied treated soil to restore the original ground as much as possible. It usually takes about one month for lean-mix cement milk and liquefied treated soil to solidify and achieve the expected strength. [Prior art documents] [Patent documents]

[0003] [Patent Document 1] JP 2020-23788 A [Patent Document 2] Patent Publication No. 2022-70362 Summary of the Invention [Problem to be solved by the invention]

[0004] If there is no construction of a new building after the building is removed, there is no problem, but if the next building is to be constructed immediately, the construction period will be extended because it is necessary to wait for the lean cement milk and liquefied treated soil to solidify. The object of the present invention is to provide a continuous construction method for removing existing piles and constructing new piles, which can shorten the construction period when constructing new piles after removing existing piles. [Means for solving the problem]

[0005] In the continuous construction method of removing the existing pile and constructing a new pile according to the present invention, after a first casing is used to drill a hole in the ground and cut off the edge around the existing pile, the first casing is pulled out, and while the existing pile is being pulled out, bentonite water, which is a mixture of bentonite and water, is supplied into the inside of the extraction hole formed by the extraction of the existing pile, and the extraction hole formed by the extraction of the existing pile is filled with the bentonite water, the ground is drilled with a second casing for constructing a new pile so that it partially overlaps with the extraction hole, the inside of the second casing buried in the ground is excavated to form a borehole, cement milk is primarily filled from the bottom to the top of the borehole, the second casing that has been placed in the borehole is pulled out, cement milk is secondarily filled from the bottom to the top of the extraction hole that partially overlaps with the borehole, causing the remaining bentonite water to overflow, and the new pile is inserted into the borehole filled with the cement milk for construction. Effect of the Invention

[0006] According to the present invention, the construction period can be shortened when constructing new piles after removing existing piles. [Brief description of the drawings]

[0007] [Figure 1] FIG. 1 is a cross-sectional view showing the first step in a continuous construction method for removing existing piles and constructing new piles according to an embodiment. [Diagram 2] FIG. 4 is a cross-sectional view showing a second step in the above method. [Diagram 3] FIG. 4 is a cross-sectional view showing a third step in the above method. [Figure 4] FIG. 4 is a cross-sectional view showing a fourth step in the above method. [Diagram 5] FIG. 4 is a plan view showing a fifth step in the above construction method. [Figure 6] FIG. 4 is a cross-sectional view showing a fifth step in the above method. [Figure 7] FIG. 4 is a cross-sectional view showing a sixth step in the above construction method. [Figure 8] FIG. 4 is a cross-sectional view showing a seventh step in the above construction method. [Figure 9] FIG. 4 is a cross-sectional view showing an eighth step in the above construction method. [Figure 10] FIG. 11 is a cross-sectional view showing the ninth step in the above construction method. [Figure 11] A cross-sectional view showing a tenth step in the above construction method. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0008] The continuous method of removing existing piles and constructing new piles according to the embodiment will be described with reference to Figures 1 to 11. Note that Figures 1 to 11 are schematic, and the aspect ratios of the piles and holes shown are not realistic.

[0009] In the continuous construction method of this embodiment, the existing foundation pile, i.e., the existing pile P1, is removed prior to the construction of the new foundation pile, i.e., the new pile P2. The new pile P2 of this embodiment is not a concrete pile cast in place, but a so-called prefabricated pile that is manufactured in advance. The existing pile P1 may be a prefabricated pile or a concrete pile cast in place. The existing pile P1 is removed by the edge-cutting and pulling-out method. First, in order to reduce friction with the ground 1 when the existing pile P1 is pulled out, as shown in FIG. 1, the first casing 2, which is a round steel pipe, is drilled in the ground 1 so that the first casing 2 is positioned around the existing pile P1, thereby performing the so-called "edge-cutting". The first casing 2 is rotated to drill the ground 1 from the surface to the ground. At this time, jet water is sprayed from the tip of the first casing 2 to soften the ground 1. Bentonite water may be used as a hole wall protection liquid instead of water. Bentonite water is a mixture of bentonite and water, and is also called bentonite solution or bentonite liquid, and does not contain solidifying components such as cement.

[0010] The state in which the first casing 2 has been buried is shown in Fig. 1, and the process up to this point has been carried out in the past. Between the existing pile P1 and the first casing 2, muddy water, which is a mixture of the jetted water or bentonite water and the drilled ground 1, accumulates. Next, as shown in Fig. 2, the first casing 2 is pulled out from the ground 1. As a result, the existing pile P1 is left inside the pulled-out hole 5 drilled by the first casing 2, and the muddy water remains around the existing pile P1.

[0011] Next, as shown in FIG. 3, the existing pile P1 is removed by winding a wire rope 3 around the upper part of the existing pile P1 and pulling the existing pile P1 upward, a so-called "quoits" pulling out method. Although the "quoits" pulling out method itself has been conventionally used to remove the existing pile P1, in this embodiment, while the existing pile P1 is being pulled out, bentonite water 4 is supplied from the upper part of the first casing 2 to the inside. The supplied bentonite water 4 is filled into the extraction hole 5 formed after the existing pile P1 is pulled out. Note that FIG. 3 shows a state in which the existing pile P1 is partially pulled out, but when the existing pile P1 is completely pulled out, the bentonite water 4 is filled up to the upper part of the inside of the first casing 2, as shown in FIG. 4. The bentonite water 4 has been conventionally used to protect the hole wall, and forms an impermeable film on the inner surface of the hole wall to prevent the hole wall from collapsing.

[0012] Normally, the extraction hole 5 is backfilled with lean cement milk or liquefied treated soil to restore the original ground. However, in this embodiment, the construction of the new pile P2 has already been decided, and the process for the construction of the new pile P2 is carried out continuously after the removal of the existing pile P1. First, the ground 1 is drilled by the second casing 6 to match the position where the new pile P2 is to be constructed. In this embodiment, the position of the new pile P2 is shifted from the existing pile P1. For this reason, as shown in the plan view of FIG. 5, the extraction hole 5 formed by extracting the existing pile P1 and filled with bentonite water 4 and the drilling hole 7 for the new pile P2 to be formed inside the second casing 6 are partially overlapped.

[0013] In FIG. 5, the positional relationship between the extraction hole 5 and the second casing 6 (drilled hole 7) in this embodiment is shown by a solid line. The positional relationship shown by the dotted line in FIG. 5 will be described later. In the plan view shown in FIG. 5, O1 is the center of the extraction hole 5, O2 is the center of the drilled hole 7, and the two Qs are intersections between the inner circumference of the extraction hole 5 and the outer circumference of the second casing 6. In other words, the two Qs are intersections between the inner circumference of the extraction hole 5 and the inner circumference of the drilled hole 7 formed by the second casing 6. The hole formed by drilling the first casing 2 and pulling out the first casing 2 and the existing pile P1 is the extraction hole 5. Similarly, the hole formed by drilling the second casing 6 and drilling its interior (described later) and removing the second casing 6 is the drilled hole 7.

[0014] In the plan view shown in FIG. 5, the arc portion of the entire circumference of the drilled hole 7 that overlaps with the extraction hole 5 is called the overlapping arc C. That is, the overlapping arc C is between the two intersection points Q. In this embodiment, the ground 1 is drilled by the second casing 6 so that the centers O1 and O2 are located on opposite sides of the line passing through the two intersection points Q. When drilling with the second casing 6, the drilling resistance of the ground 1 does not act in the overlapping arc C portion, and the drilling resistance is biased along the circumferential direction of the second casing 6. For this reason, when drilling with the second casing 6, attention must be paid to the verticality of the drilling. Usually, the hole to be drilled (excavated) tends to incline toward the side with smaller drilling resistance.

[0015] When the ratio of the overlapping arc C to the circumference of the second casing 6, i.e., the borehole 7 to be formed, increases, the deviation of the excavation resistance in the circumferential direction increases, and the verticality of the borehole 7 to be excavated deteriorates. For this reason, the size (diameter) of the second casing 6 is set so that the ratio of the overlapping arc C to the circumference of the borehole 7 is 1 / 2 or less, preferably 1 / 3 or less. The position of the center O2 of the second casing 6 (borehole 7) is aligned with the center of the new pile P2. When the ratio of the overlapping arc C exceeds 1 / 2, the verticality of the borehole 7 and therefore the verticality of the new pile P2 to be constructed in the borehole 7 deteriorates as described above. In particular, in order to achieve accurate verticality, it is preferable that the ratio of the overlapping arc C is 1 / 3 or less in order to further reduce the deviation of the excavation resistance in the circumferential direction. The verticality of the foundation pile is very important, and it is important to drill the hole with the second casing 6 so that the ratio of the overlapping arc C is satisfied.

[0016] As described above, in this embodiment, the drilling is performed by the second casing 6 so that the ratio of the overlapping arcs C described above is 1 / 2 or less under the condition that the centers O1 and O2 are located on opposite sides of the line passing through the two intersection points Q. However, as shown by the dotted line in FIG. 5, even under the condition that the centers O1 and [O2] are located on the same side of the line passing through the two intersection points [Q], it may be possible to make the ratio of the overlapping arcs C 1 / 2 (preferably 1 / 3) or less. In this case, the drilling hole [7] for the withdrawal hole 5 is shown by the dotted line in FIG. 5, and the center [O2] of the drilling hole [7] and the two intersection points [Q] with the withdrawal hole 5 are also shown. In this way, even when the drilling hole [7] is formed so as to overlap most of the withdrawal hole 5, the ratio of the overlapping arcs C described above can be made 1 / 2 (preferably 1 / 3) or less. As a result, even if the overlapping range between the extraction hole 5 and the borehole [7] is large, the verticality of the borehole [7] can be ensured by sufficiently securing the drilling length of the ground 1 by the second casing 6 and suppressing the bias of the circumferential drilling resistance.

[0017] As shown in Fig. 4, the extraction hole 5 is filled with bentonite water 4, and the second casing 6 is used to drill the ground 1 so that they partially overlap as shown in Fig. 5. Fig. 6 shows the state after drilling with the second casing 6 is completed. At this time, jet water is sprayed from the tip of the second casing 6 to soften the ground 1. Bentonite water can be sprayed instead of water, but since the wall of the extraction hole 5 is already protected by the bentonite water 4 and the excavation hole 7 formed by the second casing 6 is filled with cement milk 9 before the second casing 6 is removed, there is little point in using bentonite water.

[0018] The second casing 6 cuts the wall of the extraction hole 5, but the wall of the extraction hole 5 is protected by the bentonite water filled inside, so it will not collapse due to drilling by the second casing 6. In addition, the bentonite water 4 remains filled in the extraction hole 5, and the head pressure of the bentonite water also acts on the wall of the extraction hole 5, further suppressing collapse. The cut part of the wall of the extraction hole 5 by the second casing 6 is also protected by the bentonite water 4 in the extraction hole 5. In this embodiment, the second casing 6 is drilled deeper than the bottom of the extraction hole 5. The advantages of this will be described later. It is not a problem even if part of the bentonite water 4 in the extraction hole 5 seeps into the part drilled by the second casing 6.

[0019] Next, as shown in FIG. 7, the inside of the buried second casing 6 is excavated by the screw auger 8 to form a borehole 7. In the state shown in FIG. 7, the second casing 6 is still left inside the borehole 7. This borehole 7 is a hole for the new pile P2. When the screw auger 8 excavates the borehole 7, the bentonite water filled in the excavated ground 1 and the overlapping part with the extraction hole 5 is removed from the top of the borehole 7. In the state shown in FIG. 7, the head of the lower end of the screw auger 8 is located at the bottom of the formed borehole 7. From this state, the screw auger 8 is pulled out while filling the borehole 7 with cement milk 9 from the head of the screw auger 8. FIG. 8 shows a state in the middle of this process. By the time the screw auger 8 is completely pulled out of the borehole 7, the cement milk 9 is filled from the bottom to the top of the borehole 7. This filling of the borehole 7 with the cement milk 9 is the primary filling of the cement milk 9.

[0020] The cement milk 9 will eventually solidify and will hold the new pile P2, which will be inserted into the borehole 7 later, firmly in the ground 1. As in the conventional construction method, the cement milk 9 is made up of two components, a "base consolidation liquid" filled below the borehole 7 and a "pile periphery fixing liquid" filled above the borehole 7, which are filled sequentially from the bottom to the top of the borehole 7.

[0021] Next, the second casing 6 still placed in the borehole 7 is pulled out and removed. FIG. 9 shows the state in which the second casing 6 has been pulled out and completely removed. The specific gravity of the cement milk 9 is greater than that of the bentonite water 4. Therefore, when the bottom of the borehole 7 and the bottom of the extraction hole 5 communicate with each other in the process of pulling out the second casing 6, the head pressure of the cement milk 9 in the second casing 6 also acts, so that some of the cement milk 9 flows into the bottom of the extraction hole 5. The bentonite water 4, which has a low specific gravity, is moved upward by the cement milk 9, which has a high specific gravity. Once the movement of the lower part of the cement milk 9 has stabilized, the cement milk 9 that comes out downward from the lower end of the second casing 6 as the second casing 6 is pulled out is placed on top of the lower part. In addition, when the second casing 6 is pulled out, the head pressure of the cement milk 9 acts sufficiently near the bottom of the borehole 7, so that the wall of the borehole 7 can be protected more stably.

[0022] The extraction hole 5 and the borehole 7 are partially overlapped to form one large hole. Since the extraction hole 5 was filled with the bentonite water 4, the bentonite water 4 still remains in the large hole. A new pile P2 will be constructed in the borehole 7 later, and it is necessary to replace the bentonite water 4 in the large hole with the cement milk 9. Then, the extraction hole 5 is filled with the cement milk 9 from the bottom to the top using a screw auger 8 or the like. This secondary filling of the cement milk 9 causes the bentonite water 4 to overflow, and the large hole formed by the extraction hole 5 and the borehole 7 is filled with the cement milk 9. FIG. 10 shows the state in the middle of the secondary filling of the cement milk 9 into the extraction hole 5. As described above, the specific gravity of the cement milk 9 is greater than that of the bentonite water 4, so the bentonite water 4 that remained near the extraction hole 5 is moved upward by the cement milk 9 and reliably overflows from the extraction hole 5 and the borehole 7.

[0023] In this embodiment, the secondary filling of the cement milk 9 is performed only by the "pile circumference fixing liquid". Since the new pile P2 is constructed in the borehole 7, the lower end of the new pile P2 is firmly fixed by the "foot fixing liquid" filled in the bottom of the borehole 7. Therefore, there is no need to fill the bottom of the extraction hole 5 with foot fixing liquid, and in this embodiment, the secondary filling of the cement milk 9 is performed only by the pile circumference fixing liquid. In particular, in this embodiment, as described above, the bottom of the borehole 7 is made deeper than the bottom of the extraction hole 5, so that the bottom of the borehole 7 is firmly filled with foot fixing liquid, and the foot fixing liquid in the borehole 7 is prevented from escaping to the bottom of the extraction hole 5 due to the difference in height.

[0024] In addition, since the lower end of the new pile P2 is to be firmly fixed, the lower end of the new pile P2 is to be firmly surrounded by the ground 1. If the bottom of the extraction hole 5 is deeper than the bottom of the excavation hole 7, a part of the bottom of the excavation hole 7 overlaps with the extraction hole 5, which may cause concerns about the fixing strength. For this reason, in this embodiment, the bottom of the excavation hole 7 is made deeper than the bottom of the extraction hole 5, so that the lower end of the new pile P2 can be firmly fixed. Furthermore, since the specific gravity of the root fixing liquid is usually greater than the specific gravity of the pile circumference fixing liquid, in the secondary filling of the cement milk 9 shown in FIG. 10, the root fixing liquid filled at the bottom of the excavation hole 7 does not move to the extraction hole 5 by the secondary filling of the cement milk 9. In addition, in the secondary filling of the cement milk 9, the two components of the "root fixing liquid" and the "pile circumference fixing liquid" may be filled sequentially from the bottom to the top of the extraction hole 5.

[0025] Next, as shown in FIG. 11, the new pile P2 is inserted vertically into the borehole 7. At this time, part of the cement milk 9 overflows from the extraction hole 5 and the borehole 7. After this, if the cement milk 9 is solidified as usual, the new pile P2 is firmly fixed to the ground 1. In this embodiment, the bentonite water 4 is completely overflowed in the second filling of the cement milk 9 in consideration of quality. However, in consideration of overflow when the new pile P2 is inserted into the borehole 7, most of the bentonite water 4 may be overflowed in the second filling of the cement milk 9 in a planned manner while leaving a small amount. The remaining bentonite water 4 may be overflowed when the new pile P2 is inserted into the borehole 7.

[0026] According to the continuous construction method of the above embodiment, the removal of the existing pile and the construction of the new pile are performed in the following steps. (1) The ground 1 is drilled with the first casing 2 to cut the edge around the existing pile P1, and then the first casing 2 is pulled out. (2) While the existing pile P1 is pulled out, the bentonite water 4, which is a mixture of bentonite and water, is supplied into the inside of the extraction hole 5 formed by the extraction of the existing pile P1, and the extraction hole 5 is filled with the bentonite water 4. (3) The ground 1 is drilled with the second casing 6 for the construction of the new pile P2 so that it partially overlaps with the extraction hole 5. (4) The inside of the second casing 6 buried in the ground 1 is excavated to form a borehole 7. (5) The borehole 7 is primarily filled with cement milk 9 from the bottom to the top. (6) The second casing 6 placed in the borehole 7 is pulled out. (7) The extraction hole 5, which partially overlaps with the borehole 7, is secondary filled with cement milk 9 from the bottom to the top, and the remaining bentonite water 4 is allowed to overflow. (8) The new pile P2 is inserted into the borehole 7 filled with cement milk 9 and constructed.

[0027] According to such a continuous construction method, the removal of the existing pile P1 and the construction of the new pile P2 can be smoothly and continuously performed, thereby shortening the construction period. In this case, there are further advantages as follows. Since the existing pile P1 is removed by the edge-cutting and pulling-out method, noise and vibration are unlikely to be generated. The continuous construction method can be smoothly performed while protecting the hole wall of the extraction hole 5 formed by the extraction of the existing pile P1 with the bentonite water 4. The amount of cement milk 9 can be reduced compared to when the extraction hole 5 is temporarily backfilled. Specifically, when the extraction hole 5 is temporarily backfilled, the cement milk 9 in the overlapping portion between the extraction hole 5 and the borehole 7 is removed when the borehole 7 is excavated after solidification, and is wasted.

[0028] Furthermore, according to the continuous construction method of the above embodiment, the drilling hole 7 is drilled by the second casing 6 so that the ratio of the length of the overlapping arc C of the drilling hole 7 overlapping with the extraction hole 5 to the total circumferential length of the drilling hole 7 is 1 / 2 or less. Therefore, it is possible to reduce the circumferential bias of the drilling resistance during drilling by the second casing 6 and ensure the verticality of the drilling by the second casing 6. Furthermore, it is possible to ensure the verticality of the new pile P2 constructed inside the drilling hole 7 formed by drilling by the second casing 6.

[0029] According to the continuous construction method of the above embodiment, the borehole 7 is excavated so that its bottom is deeper than the bottom of the extraction hole 5. Therefore, the lower end of the new pile P2 located at the bottom of the borehole 7 is completely surrounded by the ground 1 and securely fixed. In addition, the lower end of the new pile P2 is securely fixed to the bottom of the borehole 7 by the root consolidation liquid component in the primary filling of the cement milk 9 into the borehole 7.

[0030] The present invention is not limited to the above-described embodiment, and the components can be modified and embodied in the implementation stage without departing from the spirit of the invention. In addition, various inventions can be formed by appropriately combining the multiple components disclosed in the above-described embodiment. [Explanation of symbols]

[0031] 1 ground 2 First casing 4. Bentonite Water 5 Extraction hole 6 Second casing 7. Borehole 9. Cement Milk C Multiple arcs P1 Existing pile P2 New pile

Claims

1. This is a continuous construction method for removing existing piles and constructing new piles. After drilling a hole in the ground with the first casing to cut off the edge around the existing pile, the first casing is pulled out. While extracting the existing pile, supplying bentonite water, which is a mixture of bentonite and water, into the extraction hole formed by extracting the existing pile to fill the extraction hole with the bentonite water; The ground is drilled with a second casing for constructing a new pile so that the second casing partially overlaps with the extraction hole; The inside of the second casing buried in the ground is excavated to form a borehole; Filling the borehole with cement milk from the bottom to the top; Pull out the second casing placed in the borehole; Fill the extraction hole, which has a part overlapping with the drilling hole, from the bottom to the top with cement milk to overflow the remaining bentonite water; A continuous construction method for removing existing piles and constructing new piles, in which the new piles are inserted into the borehole filled with the cement milk.

2. 2. The continuous construction method for removing existing piles and constructing new piles as described in claim 1, wherein, in a plan view, the drilling hole is drilled by the second casing so that the ratio of the length of the overlapping arc of the drilling hole that overlaps with the extraction hole to the total circumference of the drilling hole is 1 / 2 or less.

3. The continuous construction method for removing an existing pile and constructing a new pile according to claim 1 or 2, wherein the bottom of the excavation hole is excavated so as to be deeper than the bottom of the extraction hole.

Citation Information

Patent Citations

  • Method for continuous lap drilling by leader auger machine and device used therefor

    JP2000319881A

  • Composition for injection liquid and injection liquid for drilling

    JP2012149107A

  • Pile construction method

    JP2015183374A

  • Existing pile pulling out method

    JP2020023788A

  • Continuous construction method for demolition of existing frame and construction of new pile

    JP2022111707A