Underpass method

The method addresses the challenges of forming underground spaces by using a closed propulsion technique and low-pressure infiltration to improve ground stability and watertightness, enabling efficient and stable construction despite groundwater presence.

JP2024143674APending Publication Date: 2024-10-11OKUMURA CORP +1
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
JP2023056462
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-03-30
Publication Date
2024-10-11

AI Technical Summary

Technical Problem

Existing underpass construction methods face challenges in forming underground spaces below existing underground structures with groundwater, requiring large-scale equipment, high-pressure chemical injection leading to hard ground, and difficulty in sealing gaps between box-shaped pipe members, which complicates the process and stability.

Method used

The method involves forming a working shaft, using a closed propulsion technique to install box-shaped pipe members with a rectangular cross-section, improving the ground with low-pressure infiltration, and applying high-pressure chemical injection to create a protective layer before constructing the box structure, ensuring stability and watertightness.

Benefits of technology

This approach allows for efficient and stable formation of underground spaces by preventing groundwater intrusion, maintaining suitable hardness for easy excavation, and ensuring the integrity of the box structure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024143674000001_ABST
    Figure 2024143674000001_ABST
Patent Text Reader

Abstract

To enable water cut-off treatment to be provided on the ground in a planned installation region by a simple structure so that the ground has an appropriate hardness allowing easy excavation by an underpass method for forming an underground space in the ground including groundwater.SOLUTION: Prior to forming a top surface box-shaped roof 21 and a lateral surface box-shaped roof 22 so as to traverse a section immediately under an existing underground structure 30 and subsequently propelling a box body structure 15 toward the ground immediately under the existing underground structure 30 so as to be replaced with the top surface box-shaped roof and the lateral surface box-shaped roof, underground water is prevented from flowing into the inside of the roofs when propelling the box body structure 15 by improving at least ground 13a surrounding the lateral surface box-shaped roof 22 by a low pressure infiltration injection method by work from the inside of the top surface box-shaped roof 21 and the lateral surface box-shaped roof 22.SELECTED DRAWING: Figure 3
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to an underpass construction method, and more particularly to an underpass construction method for forming an underground space using a box structure in a ground where groundwater exists below an existing underground structure. [Background technology]

[0002] The underpass method is adopted as a method for forming an underground space that crosses existing structures such as existing railways and roads in the ground below these structures, and known methods include the R&C method (registered trademark) (see, for example, Patent Document 1) and the SFT method (registered trademark) (see, for example, Patent Document 2). The underpass method forms a top box roof and a side box roof that support the existing structure from below by installing box-shaped pipe members in series in the ground below the existing structure where the underground space is to be formed, and then replaces the formed top box roof and side box roof with, for example, a precast box structure having a rectangular cross section by propelling it to the location where the underground space is to be formed, thereby forming an underground space by the replaced box structure.

[0003] Also disclosed is a technology that enables easy and quick waterproofing of the ground surrounding the planned location for the formation of an underground space below an existing structure when the ground, including the location where the underground space is planned to be formed, is soft ground or has groundwater present (see, for example, Patent Document 3). In the box jacking method for roof protection work of Patent Document 3, the box-shaped pipe members at the upper corners of the gate-shaped roof protection work consisting of the top roof section and the side roof section are made into large pipes for work with a diameter larger than normal, and ground improvement is performed by injecting a chemical agent with high pressure jets from the inside of this large pipe in any direction to the outside, and for example, by performing ground improvement from the inside of the large pipe downward, the location where the side roof section will be installed is waterproofed in advance. [Prior art documents] [Patent documents]

[0004] [Patent Document 1] JP 2007-177553 A [Patent Document 2] JP 2012-144942 A [Patent Document 3] JP 2009-167595 A Summary of the Invention [Problem to be solved by the invention]

[0005] Meanwhile, in recent years, various construction works have been planned to form underground spaces by crossing the ground further below an existing underground structure formed underground, and it has been considered to adopt the underpass method for such construction works so that the underground space can be formed in the ground area as close as possible to the existing underground structure. When forming an underground space in the ground further below the existing underground structure using the underpass method, the effect of the water pressure of the groundwater becomes large, so that the construction can be carried out in a more stable state, it is desirable to perform a water-stopping treatment on the entire ground in the planned installation area of ​​the box structure, which is the planned location for forming the underground space below the existing underground structure, before advancing the box structure.

[0006] Furthermore, if the method of ground improvement by injecting the chemical agent described in Patent Document 3 mentioned above is adopted as a method of waterproofing the entire ground in the planned installation area of ​​the box structure prior to advancing the box structure, it will require large-scale equipment, such as a large-diameter work pipe with a larger than normal diameter, which will be a heavy burden when working on the deep ground below the existing underground structure, and the improved ground formed by injecting the chemical agent with high-pressure jets will be too hard, so it will be very time-consuming to excavate the ground inside the box-shaped roof on the top and side parts that will be replaced by the box structure when advancing the box structure.

[0007] Furthermore, when the box-shaped pipe components that form the top box roof and side box roof are pushed into the ground in ground where groundwater is present, each box-shaped pipe component needs to be pushed into the ground using a sealed jacking method that does not open the face. Therefore, each box-shaped pipe component does not have a section (joint) on the outer periphery to lock and join adjacent box-shaped pipe components, and gaps are created between them. As a result, it is necessary to waterproof the ground in the gaps between these, especially the gaps in the side box roof.

[0008] The present invention aims to provide an underpass construction method that, when forming an underground space using a box structure in ground where groundwater exists below an existing underground structure, enables the ground in the planned installation area of ​​the box structure to be effectively improved and waterproofed with a moderate hardness that makes excavation easy, using a simple configuration, thereby enabling the efficient formation of an underground space in a stable state. [Means for solving the problem]

[0009] The present invention is an underpass construction method for forming an underground space by a box structure having a rectangular cross-sectional shape, crossing below an existing underground structure in the ground below the existing underground structure where groundwater exists, by pushing a plurality of box-shaped pipe members from a work shaft into the ground below the existing underground structure by a closed jacking construction method so as to connect each of the box-shaped pipe members in a circumferential direction of a cross section perpendicular to the cross direction in the planned installation area along at least the top surface portion and both side surfaces of the planned installation area of ​​the box structure, thereby forming a top surface box-shaped roof and a side surface box-shaped roof that cross the portion directly below the existing underground structure, and then connecting at least the top surface portion to the top surface box-shaped roof. The box structure is adapted to replace the existing underground structure by advancing the box structure from the work shaft toward the ground directly below the existing underground structure, thereby forming an underground space by the box structure.Prior to advancing the box structure toward the ground directly below the existing underground structure, ground improvement is carried out around at least the side box roof by working from inside the multiple box-shaped pipe members that constitute at least the side box roof using a low-pressure penetration injection method, thereby providing an underpass construction method that prevents groundwater from flowing inside the box structure when it is advanced.This objective has been achieved.

[0010] Furthermore, it is preferable that the underpass construction method of the present invention is configured to form a protective and improved ground by a horizontal ground improvement method in which a chemical agent is high-pressure sprayed and injected into the area between the existing underground structure and the planned installation area of ​​the box structure after the work shaft is formed and prior to pushing a plurality of box-shaped pipe components from the work shaft into the ground below the existing underground structure.

[0011] In addition, the underpass construction method of the present invention preferably involves forming a mirror-improved ground by a vertical ground improvement method in which, after forming the work shaft, prior to pushing a plurality of box-shaped pipe members from the work shaft into the ground below the existing underground structure, a chemical agent is high-pressure-sprayed and injected into the ground that will become the mirror portion of the part of the work shaft on the retaining wall side in the planned installation area of ​​the box structure, and into the ground that will become the mirror portion of the box-shaped pipe members propelled from the work shaft and the tip-reaching portion of the box structure, thereby forming a mirror-improved ground.

[0012] Furthermore, in the underpass construction method of the present invention, it is preferable that the retaining wall of the working shaft is formed by the SMW construction method.

[0013] Furthermore, in the underpass construction method of the present invention, in the R&C construction method (registered trademark) in which excavation work is performed at the face at the front part of the box structure, it is preferable that each work process is carried out using only the starting shaft as the working shaft. Effect of the Invention

[0014] According to the underpass construction method of the present invention, when forming an underground space using a box structure in ground where groundwater is present below an existing underground structure, the simple configuration makes it possible to effectively improve and watertightly treat the ground in the planned installation area of ​​the box structure to a moderate hardness that makes excavation easy, thereby enabling the underground space to be formed efficiently in a stable state. [Brief description of the drawings]

[0015] [Figure 1] FIG. 2 illustrates the process of installing a working shaft, the process of forming a protective improved ground, and the process of forming an improved ground for the mirror section, where (a) is a schematic vertical cross-sectional view, and (b) is a schematic vertical cross-sectional view along AA in (a). [Diagram 2] 10 is a schematic vertical cross-sectional view illustrating a process of advancing a box-shaped pipe member to form a top box-shaped roof and a side box-shaped roof. FIG. [Diagram 3]FIG. 10 illustrates the process of ground improvement using a low-pressure infiltration injection method after forming a box-shaped roof on the top surface and a box-shaped roof on the side surface. (a) is a schematic vertical cross-sectional view, and (b) is a schematic vertical cross-sectional view along A'-A' in (a). [Figure 4] FIG. 11 is a schematic vertical cross-sectional view illustrating the process of advancing a box structure toward the ground directly below an existing underground structure. [Diagram 5] FIG. 13 is a schematic vertical cross-sectional view illustrating the process of advancing a box structure while excavating the ground inside a box-shaped roof using the R&C method. [Figure 6] FIG. 1(a) is a simplified vertical cross-sectional view illustrating the underground space created by the box structure formed by crossing underneath the existing underground structure, and FIG. 1(b) is a simplified vertical cross-sectional view taken along A”-A” in FIG. 1(a). DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0016] As shown in Figs. 1(a) and (b), the underpass construction method according to a preferred embodiment of the present invention is adopted as a construction method for forming an underground space 10 for a new subway, for example, in the ground below an existing facility structure for a subway as an existing underground structure 30, by using a box structure 11 (see Figs. 6(a) and (b)) that is installed across the part directly below the existing underground structure 30. In addition, in this embodiment, the R&C construction method (registered trademark) is adopted as the underpass construction method, which advances the box structure 11 while excavating the ground left in the inner area surrounded by the box roof 20 at the face 12 (see Fig. 5), and since the existing facility structure 40 is also formed as an underground structure on the arrival side of the box roof 20 and the box structure 11 sandwiching the existing underground structure 30, only the shaft on the starting side is used as a work shaft 31, and each work process is carried out without providing a shaft on the arrival side. Since only the starting shaft is used as the working shaft 31, similar to the underground structure construction method described in, for example, JP 2001-72670 A, the box-shaped pipe members 25 constituting the box-shaped roof 20 are advanced into the working shaft 31 for each unit pipe 25a while the box structure 11 is advanced into the ground below the existing underground structure 30 (see Fig. 5). Note that in Figs. 3(a), 4, and 5, the box-shaped roof 20 is shown with the ground (soil and sand) remaining inside it omitted.

[0017] Furthermore, in this embodiment, groundwater is present in the ground below the existing underground structure 30, and the underpass construction method of this embodiment has the function of enabling the underground space 10 to be formed efficiently in a stable state, even when the underground space 10 is formed using the box structure 11 in ground where such groundwater is present.

[0018] The underpass construction method of the present embodiment is an underpass construction method, preferably by an R&C method, for forming an underground space 10 (see FIG. 6(b)) by a box structure 11 having a rectangular cross-sectional shape across an existing underground structure 30 in the ground below the existing underground structure 30 where groundwater exists, and as shown in FIGS. 1(a) and 1(b) to 6(a) and 6(b), a small area of ​​a planned installation area 16 (see FIGS. 1(a) and 1(b)) of the box structure 11 is formed. At least along the top surface portion 16a and both side surface portions 16b, each of the multiple box-shaped pipe members 25 is arranged in a circumferential direction of a cross section perpendicular to the transverse direction in the planned installation area 16, and is pushed from the work shaft 31 into the ground below the existing underground structure 30 by a closed jacking method to form a top surface box roof 21 and a side surface box roof 22 that cross the part directly below the existing underground structure 30 (see Fig. 2, Fig. 3(a) and (b)). Then, at least the top surface portion 11a is replaced with the top surface box roof 21 (in this embodiment, the side surface portion 11b is also replaced with the side surface box roof 22), and the box structure 11 is advanced from the work shaft 31 toward the ground directly below the existing underground structure 30 (see Fig. 5), forming an underground space 10 by the box structure 11 (see Fig. 6(a) and (b)).

[0019] In the underpass construction method of this embodiment, prior to advancing the box structure 11 toward the ground directly below the existing underground structure 30, work is carried out from inside at least the multiple box-shaped pipe members 25 that make up the side box roof 22 to improve the ground 13a around the side box roof 22, and preferably the inner ground 13b surrounded by the top box roof 21 and the side box roof 22, using a low-pressure infiltration injection method, thereby preventing groundwater from flowing inside the ground 13a when the box structure 11 is advanced (see Figure 3(b)).

[0020] In addition, in the underpass construction method of this embodiment, preferably after forming a work shaft 31, prior to pushing multiple box-shaped pipe components 25 from the work shaft 31 into the ground below the existing underground structure 30, a protective improved ground 17 is formed by a horizontal ground improvement method in which a chemical agent is high-pressure sprayed and injected into the area between the existing underground structure 30 and the planned installation area 16 of the box structure 11 (see Figures 1 (a) and (b)).

[0021] Furthermore, in the underpass construction method of this embodiment, after forming the work shaft 31, and prior to pushing multiple box-shaped pipe members 25 from the work shaft 31 into the ground below the existing underground structure 30, mirror-improved ground 18a, 18b is formed by a vertical ground improvement method in which a chemical agent is high-pressure sprayed and injected into the ground that forms the mirror portion of the part of the work shaft 31 on the retaining wall 32 side in the planned installation area 16 of the box structure 11, and into the ground that forms the mirror portion of the tip of the box-shaped pipe members 25 and box structure 11 propelled from the work shaft 31 (see Figure 1 (a)).

[0022] In this embodiment, prior to the work of forming an underground space by the box structure 11 in the ground below the existing underground structure 30, preferably by the R&C method, a work shaft 31 serving as a work base is formed on one side of the existing underground structure 30 (see FIG. 1(a)). In this embodiment, as described above, since the existing facility structure 40 is formed on the other side of the existing underground structure 30, the work shaft 31 is formed only on one side, and each work process is carried out. The work shaft 31 can be easily formed by forming a retaining wall 32 using ground improvement and sheet piles, preferably by the SMW method, which is excellent in water-stopping properties, and excavating to a predetermined depth while retaining the inside of the wall. The surface on the work shaft 31 side is protected by sheet piles and supported by supports such as struts. In the formed work shaft 31, propulsion equipment for propelling the box-shaped pipe member 25 and the box structure 11, removal equipment for removing the box-shaped pipe member 25, and equipment for performing horizontal ground improvement work will be installed as appropriate (see Figures 4 and 5).

[0023] In addition, in this embodiment, preferably after the retaining wall 32 of the working shaft 31 is formed by the SMW method or the like, and prior to excavating the inside of the wall, as described above, the mirror improved ground 18a, 18b is formed as part of the planned installation area 16 in the ground on both sides of the existing underground structure 30 at the same height as the planned installation area 16 of the box structure 11 (see Figure 1(a)). The improved ground 18a, 18b in the head section can be easily formed, for example, by a vertical ground improvement method, such as by injecting a high-pressure spray of an agent from the ground surfaces on both sides of the existing underground structure 30, in the ground at the starting portion of the work shaft 31 on the retaining wall 32 side in the planned installation area 16, and at the tip end of the box-shaped pipe member 25 and box structure 11 advanced from the work shaft 31, in the same way as the improved ground in the head section formed in a shield tunneling method using a shield tunneling machine, so as to have a thickness of, for example, about 3,000 to 3,500 mm.

[0024] Furthermore, in this embodiment, preferably after forming the work shaft 31, before pushing and pushing a plurality of box-shaped pipe members 25 constituting the box-shaped roof 20 including the top box-shaped roof 21 and the side box-shaped roof 22 from the work shaft 31 into the ground below the existing underground structure 30, a protective improved ground 17 is formed in the portion between the existing underground structure 30 and the planned installation area 16 of the box structure 11 as described above (see Figs. 1(a) and 1(b)). The protective improved ground 17 is formed by a horizontal ground improvement method by injecting a high-pressure spray of a chemical agent, and can be easily formed in the ground directly below the existing underground structure 30 so as to cover the entire upper part of the planned installation area 16 of the box structure 11, for example, to a thickness of about 1,400 to 2,600 mm, by using a known facility for performing the ground improvement method installed in the work shaft 31.

[0025] By forming a protective improved ground 17 in advance in the area between the existing underground structure 30 and the planned installation area 16 of the box-shaped structure 11 prior to pushing and driving the multiple box-shaped pipe members 25 into the ground below the existing underground structure 30, even if groundwater is present in the ground below the existing underground structure 30, the existing underground structure 30 can be supported from below by the protective improved ground 17, making it possible to effectively avoid affecting the existing underground structure 30 or the buried objects appropriately buried below it when the multiple box-shaped pipe members 25 constituting the box-shaped roof 20 are pushed into the ground below the existing underground structure 30 or when, in place of them, the box structure 11 is pushed into the ground below the existing underground structure 30.

[0026] In this embodiment, after forming the protective improved ground 17, preferably so as to cover the upper part of the planned installation area 16 of the box structure 11, a propulsion facility for the box-shaped pipe members 25 is installed in the work shaft 31, and each of the multiple box-shaped pipe members 25 is propelled and pushed from the work shaft 31 into the ground below the existing underground structure 30 by a closed propulsion method so as to be arranged in a line in the circumferential direction of the cross section of the planned installation area 16 along the top surface part 16a, both side surface parts 16b, and both end parts of the bottom surface part 16c of the planned installation area 16 of the box structure 11, as in the conventional R&C method (see FIG. 2). In this way, in addition to the top surface part box-shaped roof 21 and the side surface part box-shaped roof 22 that cross the part directly below the existing underground structure 30, a box-shaped roof 20 can be formed that preferably includes the bottom surface part box-shaped roof 23 at the corner parts of the ends on both sides (see FIGS. 3(a) and (b)).

[0027] Here, in this embodiment, each of the box-shaped pipe members 25 has a hollow, substantially square cross-sectional shape with dimensions of, for example, about 800 mm in length and width, and has a space inside that is large enough for workers to enter and work inside. The box-shaped pipe members 25 are installed with an extension sufficient to cross the ground directly below the existing underground structure 30, while unit pipes 25a, preferably about 1 m in length, are successively added (see FIG. 3(a)).

[0028] In the embodiment, since groundwater exists in the ground below the existing underground structure 30 to which the box-shaped pipe member 25 is advanced, in order to avoid the intrusion of groundwater into the inside of the box-shaped pipe member 25, the box-shaped pipe member 25 is advanced and pushed into the ground below the existing underground structure 30 by a sealed jacking method in which a fully sealed jacking device is attached to the tip portion of the box-shaped pipe member 25 and advanced. As an excavation device for sealing the entire surface of the tip portion of the box-shaped pipe member 25, for example, a tunneling machine described in JP 2022-134305 A or JP 2022-134306 A can be used. Since these excavation devices can be removed from the tip portion of the box-shaped pipe member 25, after the tip portion of the advanced box-shaped pipe member 25 reaches the mirror-improved ground 18b at the tip reach portion on the front side in the advancing direction across the existing underground structure 30, it can be removed from the tip portion and diverted to another box-shaped pipe member 25 for use.

[0029] In the underpass method of this embodiment, when the box roof 20 consisting of the top box roof 21, the side box roof 22, and preferably the bottom box roof 23 is formed by advancing the multiple box pipe members 25, before advancing the box structure 11 toward the ground directly below the existing underground structure 30, ground improvement can be carried out by low-pressure seepage injection from inside the multiple box pipe members 25 constituting at least the side box roof 22, particularly the ground 13a around the side box roof 22, to form the surrounding injection-improved ground 13a. In addition, ground improvement can be carried out by preferably working from the working shaft 31 on the inner ground 13b surrounded by the top box roof 21 and the side box roof 22, to form the inner injection-improved ground 13b. These make it possible to prevent groundwater from flowing inside the top box roof 21 and the side box roof 22 when advancing the box structure 11 (see FIG. 3(b)). These also make it possible to improve the ground inside the top box roof 21 and the side box roof 22 so that the ground does not collapse during excavation and is hard enough to make excavation easy.

[0030] In this embodiment, the box-shaped pipe members 25 forming the top box roof 21 and the side box roof 22 are pushed into the ground where groundwater exists, and since the box-shaped pipe members 25 are driven into the ground by a closed jacking method that does not open the face, each box-shaped pipe member 25 does not have a section (joint) on the outer periphery for locking and joining adjacent box-shaped pipe members, and gaps are likely to occur between them. For this reason, it is preferable to form a peripheral injection improved ground 13a in the ground around the top box roof 21 by working from inside the box-shaped pipe members that form the top box roof 21 so that the ground in the gaps between them can be effectively waterproofed.

[0031] Here, the low-pressure infiltration injection method is known as a low-pressure infiltration injection method using a medium-setting to instant-setting grout, which is gradually injected in each stage from the front to the back of the target ground. The low-pressure infiltration injection method uses a lightweight and small drilling machine and tool, so it is possible to work in narrow places where a bone machine cannot be brought in, and it is a method that can effectively inject into compact sandy ground or complex ground with sand layers. In addition, since a medium-setting to instant-setting grout is injected at low pressure, a low-pressure infiltration effect is obtained, and there is almost no impact on ground uplift or surrounding structures, and since improvement can be made at each stage by the downward injection method, it is also possible to carry out construction while checking the injection effect (spring water situation, etc.). Furthermore, the improved ground has a moderate hardness that makes excavation easy. As such a low-pressure infiltration injection method, for example, the "stage injection method" manufactured by Japan Sogo Waterproof Co., Ltd. can be adopted.

[0032] A peripheral injection improved ground 13a is formed by a low-pressure infiltration injection method performed from the inside of the box-shaped pipe member 25, and then an inner injection improved ground 13b is formed by ground improvement work, preferably from a work shaft 31.Then, as with the conventional R&C method, the top surface 11a and side surface 11b are replaced with a top surface box-shaped roof 21 and a side surface box-shaped roof 22, and the box structure 11 is advanced from the work shaft 31 toward the ground directly below the existing underground structure 30, thereby forming an underground space formed by the box structure 11 (see Figures 4 and 5).

[0033] In this embodiment, since it is not possible to form a work shaft 31 with a large space due to location conditions, etc., the box structure 11 is configured to be composed of a plurality of unit boxes 14 made of precast concrete that are continuously connected and integrated in the axial direction. Also, each unit box 14 is formed by assembling a plurality of divided pieces 14a divided in the circumferential direction as a single unit in the work shaft 31. That is, each unit box 14 is formed by assembling the divided pieces 14a hung from the ground into the work shaft 31 in the work shaft 31, and the formed unit boxes 14 are sequentially connected in the axial direction and are advanced as the box structure 11 toward the ground directly below the existing underground structure 30 by the advancing equipment 15 installed in the work shaft 31 (see FIG. 4).

[0034] Furthermore, in this embodiment, as described above, the R&C method involves advancing the box structure 11 while excavating the ground remaining inside the box roof 20 at the face 12, and since only the starting shaft is used as the work shaft 31, the box-shaped pipe members 25 that make up the box roof 20 are recovered unit pipes 25a at a time into the work shaft 31, while the box structure 11 is advanced into the ground below the existing underground structure 30 (see Figure 5).

[0035] In this way, the box structure 11 is advanced into the ground, and the tip of the box structure 11 reaches the head-improved ground 18b at the tip reach part on the front side in the advancing direction across the existing underground structure 30, thereby forming an underground space 10 by the box structure 11 installed across the part directly below the existing underground structure 30 (see Figs. 6(a) and (b)). The formed underground space 10 can be used in communication with the existing facility structure 40, for example, by removing the side wall 40a of the existing facility structure 40 at the part corresponding to the underground space 10.

[0036] As a result, according to the underpass construction method of this embodiment, when forming an underground space 10 using the box structure 11 in the ground where groundwater exists below an existing underground structure 30, the simple configuration makes it possible to effectively improve and watertightly treat the ground in the planned installation area 16 of the box structure 11 to a moderate hardness that makes excavation easy, and the underground space 10 can be efficiently formed in a stable state.

[0037] The present invention is not limited to the above embodiment and can be modified in various ways. For example, the existing underground structure in which an underground space is formed by a box structure in the ground below does not necessarily have to be an existing facility structure for a subway, and may be an underground structure for a road, as well as various other existing underground structures such as a basement of a building or a sewer pipe. In addition, the box-shaped pipe member and the box-shaped structure may be advanced toward the work shaft on the arrival side by providing a work shaft on the arrival side on both sides of the existing underground structure. The present invention can also be adopted in the SFT method (registered trademark) for removing the ground and earth left inside the box-shaped roof in the work shaft on the arrival side as an underpass construction method.

[0038] 10 Underground space 11 Box structure 11a Top section 11b Side part 12. Face 13a Surrounding injection improved ground (ground around the box roof) 13b Inner injection improved ground (inner ground) 14 Unit Box 14a Split Piece 15 Propulsion equipment 16 Planned installation area of ​​box structure 16a Top surface 16b Side part 16c bottom part 17 Protected improved ground 18a,18b Mirror section improved ground 20 Box Roof 21 Top box roof 22 Side box roof 23 Bottom box roof 25 Box-shaped pipe member 25a Unit Pipe 30 Existing underground structures 31 Working Shaft 32 Earth retaining wall 40 Existing facility structures 40a Side walls of the part corresponding to the underground space

Claims

1. An underpass construction method for forming an underground space by a box structure having a rectangular cross-sectional shape, crossing under an existing underground structure in a ground where groundwater exists under the existing underground structure, a plurality of box-shaped pipe members are arranged in series along at least the top surface portion and both side surface portions of the planned installation area of ​​the box structure in a circumferential direction of a cross section perpendicular to the transverse direction in the planned installation area, and are pushed from a work shaft into the ground below the existing underground structure by a closed jacking method to form a top surface box-shaped roof and a side surface box-shaped roof that cross the portion directly below the existing underground structure, and then at least the top surface portion is replaced with the top surface box-shaped roof, and the box structure is propelled from the work shaft toward the ground directly below the existing underground structure to form an underground space formed by the box structure; An underpass construction method in which, prior to advancing the box structure toward the ground directly below the existing underground structure, ground improvement is carried out around at least the side box-shaped roof by working from inside the multiple box-shaped pipe members that make up at least the side box-shaped roof using a low-pressure penetration injection method, thereby preventing groundwater from flowing inside the box structure when it is advanced.

2. An underpass construction method as described in claim 1, in which, after forming the work shaft, and prior to pushing multiple box-shaped pipe members from the work shaft into the ground below the existing underground structure, a protective and improved ground is formed by a horizontal ground improvement method in which a chemical agent is high-pressure sprayed and injected into the area between the existing underground structure and the planned installation area of ​​the box structure.

3. An underpass construction method as described in claim 1 or 2, in which after forming the work shaft, and prior to pushing multiple box-shaped pipe members from the work shaft into the ground below the existing underground structure, a mirror-improved ground is formed by a vertical ground improvement method in which a chemical agent is high-pressure-sprayed and injected into the ground that will be the mirror portion of the part of the work shaft on the retaining wall side in the planned installation area of ​​the box structure, and into the ground that will be the mirror portion of the tip-reaching portion of the box-shaped pipe members and the box structure propelled from the work shaft.

4. The underpass construction method according to claim 3, wherein the retaining wall of the working shaft is formed by the SMW construction method.

5. An underpass construction method as described in claim 1 or 2, in which, in the R&C method (registered trademark) in which excavation work is carried out at the face of the front part of the box structure, only the starting shaft is used as the working shaft and each work process is carried out.

Citation Information

Patent Citations

  • Shield tunnel joining method

    JP1997067996A

  • Construction of underground structure and tubular body for roof therefor

    JP2001073670A

  • Box jacking construction method using roof protecting construction

    JP2009167595A

  • Wall body for shield excavation

    JP2016006295A

  • Reaction force receiving structure

    JP2020090819A