Pressure-feeding method for cement-based solidification material

The use of an easy-to-cut cylindrical member allows for efficient and safe filling of horizontally long hollow holes with cement-based materials by repositioning outlets, addressing labor and safety issues in conventional methods.

JP2024146278APending Publication Date: 2024-10-15OKUMURA CORP
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
JP2023059078
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-03-31
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

Conventional methods for filling horizontally long hollow holes with cement-based solidified materials, such as concrete, require significant labor and pose safety risks due to the need for frequent pipe installation and removal, especially in narrow spaces, and can lead to interrupted pressure-feeding and pipe blockage.

Method used

A method using an easy-to-cut cylindrical member, like SunnyHose, is inserted into the cavity to allow cement-based solidified material to be pumped from the terminal end towards the opening, with outlets being sequentially repositioned by cutting the member to accommodate the flow, supported by hanging fittings and cables.

Benefits of technology

Enables smooth and efficient filling of horizontally long cavities without extensive labor, reducing safety hazards and maintaining continuous pressure-feeding even in narrow spaces.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024146278000001_ABST
    Figure 2024146278000001_ABST
Patent Text Reader

Abstract

To provide a method for pressure-feeding and filling concrete that can smoothly fill concrete into a horizontal cavity hole of a considerable length from the end toward the opening without requiring a lot of effort.SOLUTION: An easy-to-cut cylindrical member 11 made of a material that is easy to cut by hand extends along a ceiling 21a of a horizontal cavity hole 20 and from its opening 20a to its end 20b. Concrete 15 pressure-fed through the easy-to-cut cylindrical member 11 is allowed to flow out of an outlet 12a at its tip, and as the concrete 15 is filled into the horizontal cavity hole 20 from the end 20b towards the opening 20a, outlets 12b and 12c are formed sequentially by cutting into the easy-to-cut cylindrical member 11 in a portion behind the outlet 12a in the pressure-feed direction, and the concrete 15 is filled into the horizontal cavity hole 20 while being successively replaced on the opening 20a side.SELECTED DRAWING: Figure 2
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a method for pumping and filling a cement-based solidification material, and more particularly to a method for pumping and filling a cement-based solidification material employed in a process of filling and backfilling an elongated hollow hole left underground with a cement-based solidification material. [Background technology]

[0002] For example, in construction of underground tunnels such as mountain tunnels, inclined shafts connecting to the main tunnel tunnel may be constructed separately from the main tunnel tunnel for the purpose of transporting materials and equipment to and from the main tunnel tunnel being constructed, transporting excavated soil and sand, and ventilating the tunnel. Since such inclined shafts become unnecessary after the main tunnel tunnel is constructed, they are generally backfilled, preferably using excavated soil and the like as backfill soil.

[0003] In addition, when an unnecessary inclined shaft is backfilled with backfill soil, for example, if the soil is backfilled up to a height of about 1.2 m below the ceiling of the inclined shaft, work such as rolling becomes difficult, so a horizontal hollow hole is left in the ground between the ceiling of the inclined shaft and the top surface of the backfilled soil inside the inclined shaft, with the top of the backfilled soil as the opening above the tip of the backfilled soil, and is left in the ground in the horizontal direction along the extension direction of the inclined shaft, as a hollow hole in the ceiling part of the inclined shaft, preferably inclined downward and over a considerable length. It is preferable to backfill the horizontal hollow hole left in the ground in this way by filling it with a cement-based solidification material having fluidity, such as concrete.

[0004] On the other hand, as a method for backfilling such a long hollow hole that has been left continuously in the ground in the horizontal direction and formed over a considerable length, with a cement-based solidification material such as concrete, one possible method is to install a concrete pressure pipe on the top surface of the backfilled soil along the extension direction of the long hollow hole, and pressure-feed a cement-based solidification material such as concrete through the installed concrete pressure pipe, thereby filling the long hollow hole with concrete from the end side toward the opening side (for example, see Patent Document 1). [Prior art documents] [Patent documents]

[0005] [Patent Document 1] JP 2000-104403 A Summary of the Invention [Problem to be solved by the invention]

[0006] However, in the conventional method of filling a long hollow hole formed in the ground over a considerable length by continuously feeding concrete or other cement-based solidification material through a concrete pumping pipe, as the cement-based solidification material is filled from the end of the long hollow hole toward the opening, the position of the outlet for discharging the concrete must be changed sequentially toward the end. For this reason, it is necessary to pipe a plurality of concrete pumping pipes of different lengths on the upper surface of the backfilled soil or to form a concrete pumping pipe using a plurality of unit pipes and to sequentially remove the unit pipes at the tip as the filling work progresses. In particular, in a narrow work space above the backfilled soil, for example, at a height of about 1.2 m from the ceiling, the work of installing and removing the concrete pumping pipe requires a great deal of effort, and it is also possible that the worker will trip or fall during the work.

[0007] In addition, when changing over the concrete pumping pipe to be used or during the removal of a unit pipe, the concrete whose pumping was stopped may harden further, causing the inside of the pipe to become clogged and preventing smooth pumping, or it may become necessary to shake off the concrete that has accumulated at the tip of the concrete pumping pipe.

[0008] The object of the present invention is to provide a method for pumping and filling a cement-based solidification material, which enables a cement-based solidification material to be smoothly filled from the end of a horizontal hollow hole that is left continuously in the ground and formed over a considerable length, toward the opening, without requiring much labor, even when the working space is narrow. [Means for solving the problem]

[0009] The present invention relates to a method for pumping and filling a cement-based solidification material, which is used in a process of backfilling a horizontal hollow hole with a cement-based solidification material by pumping and filling the cement-based solidification material into a horizontal hollow hole left in the ground in a continuous manner from an opening, and the method comprises the steps of: installing an easily cut tubular member made of a material that can be manually cut by an operator along the ceiling of the horizontal hollow hole, extending from the vicinity of the opening of the horizontal hollow hole to the vicinity of the terminal end; and pumping the cement-based solidification material through the easily cut tubular member and allowing it to flow out from an outlet at the tip. The above-mentioned object has been achieved by providing a pressure-feeding and filling method for a cement-based solidification material, in which, as the cement-based solidification material is filled into the hollow interior of the oblong hollow hole from the vicinity of the terminal end toward the vicinity of the opening, a cut is made in the easy-to-cut tubular member at a portion rearward in the pressure-feeding direction from the outlet at the tip, so that the cut portion serves as a subsequent outlet, and the outlet through which the pressure-feed cement-based solidification material flows out is sequentially shifted toward the opening side, thereby filling the oblong hollow hole with the cement-based solidification material.

[0010] In the method for pumping and filling a cement-based solidification material of the present invention, it is preferable that the easily cut tubular member is made of SunnyHose (registered trademark).

[0011] In addition, in the pressure-feeding method for filling a cement-based solidification material of the present invention, it is preferable that the easy-to-cut tubular member is supported via a plurality of hanging fittings attached to the ceiling part at predetermined intervals in the extension direction of the horizontal hollow hole, and is installed extending along the ceiling part.

[0012] Furthermore, in the pressure-feeding and filling method of the cement-based solidification material of the present invention, it is preferable that a cord such as a wire is inserted inside the easy-to-cut tubular member, and the inserted cord is engaged with each of the multiple hanging fittings, thereby supporting the easy-to-cut tubular member via the multiple hanging fittings.

[0013] Furthermore, in the method for pumping and filling the cement-based solidification material of the present invention, it is preferable that the subsequent outflow outlet is formed by making a cut in the easy-to-cut tubular member in a portion downstream in the pumping direction adjacent to the hanging fitting to which the cord is attached.

[0014] In addition, in the method for pumping and filling a cement-based solidification material of the present invention, it is preferable that the horizontal hollow hole is a hollow hole in the ceiling part of an inclined shaft connected to a main tunnel, which is backfilled after the main tunnel is constructed, and is left between the ceiling part of the inclined shaft and the backfill soil backfilled inside the inclined shaft. Effect of the Invention

[0015] According to the pressure-feeding method for filling a cement-based solidification material of the present invention, even if the working space is narrow, the cement-based solidification material can be smoothly filled from the end of the horizontal hollow hole toward the opening, without much labor, into the horizontal hollow hole that is continuously left in the ground and formed over a considerable length. [Brief description of the drawings]

[0016] [Figure 1] FIG. 1 is a schematic vertical cross-sectional view illustrating a method for pumping and filling a cement-based solidification material according to a preferred embodiment of the present invention. [Diagram 2] FIG. 2 is an enlarged view illustrating a method for pumping and filling a cement-based solidification material according to a preferred embodiment of the present invention. [Diagram 3] 1 is an enlarged view of part A illustrating a state in which the easy-to-cut tubular member is supported by a hanging bracket attached to a ceiling portion. FIG. [Figure 4] FIG. 2 is an enlarged schematic vertical sectional view illustrating a method for pumping and filling a cement-based solidification material according to a preferred embodiment of the present invention. [Diagram 5] FIG. 1(a) to (i) are step diagrams illustrating a pressure-feeding method for filling a cement-based solidification material according to a preferred embodiment of the present invention. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0017] The pressure-feeding method for filling a cement-based solidification material according to a preferred embodiment of the present invention shown in FIG. 1 is employed as a pressure-feeding method for backfilling an inclined shaft 21 formed separately from a main tunnel tunnel (not shown) connected to the main tunnel tunnel in a construction work for constructing a tunnel such as a mountain tunnel, after the main tunnel tunnel is constructed, in which a space portion formed by leaving a considerable length area continuously in the horizontal direction along the axial direction of the inclined shaft 21 due to a gap portion between the ceiling 21a of the inclined shaft 21 and the backfilled backfill soil 22 is formed as a horizontal hollow hole 20, and a cement-based solidification material, preferably concrete, is pumped into the horizontal hollow hole 20 to fill the horizontal hollow hole 20, thereby backfilling the horizontal hollow hole 20.

[0018] In this embodiment, the inclined shaft 21 preferably has a horseshoe-shaped hollow cross section with an arched upper portion, is provided at an inclination angle of, for example, about 10 degrees so as to have a downward gradient toward the main tunnel, and has an overall length of about 700 m. The backfilling of the inclined shaft 21 is carried out for each construction span S with an extension of, for example, about 10 to 30 m, and above the backfill soil 22 backfilled for each construction span S using excavation surplus soil, etc., between the ceiling 21a of the inclined shaft 21 and the top part of the backfill soil 22 is formed as an opening 20a, and the part of the hardened body 24 made of concrete backfilled in the gap between the ceiling 21a in the preceding construction span S is formed as a hollow part having an extension of about 10 to 30 m similar to the construction span, as a horizontally elongated hollow hole 20. The hollow interior of the formed horizontally elongated hollow hole 20 is a narrow working space with a height of, for example, about 1.5 m.

[0019] The pressure-feeding method of the cement-based solidification material of the present embodiment is a pressure-feeding method that allows the pressure-feeding cement-based solidification material, preferably concrete 15, to be efficiently filled and backfilled into the horizontal hollow hole 20 without much effort, even in the narrow working space inside the hollow of the horizontal hollow hole 20, while smoothly rearranging the outlets 12a, 12b of the easy-to-cut tubular member 11 from the terminal end 20b of the horizontal hollow hole 23 toward the opening 20a.

[0020] The method for pumping and filling the cement-based solidification material of this embodiment is a method for pumping and filling concrete 15, which is a cement-based solidification material, employed in the process of backfilling a horizontal hollow hole 23 with hardened concrete 15 by pumping and filling the cement-based solidification material, preferably concrete 15, into a horizontal hollow hole 20 left in the ground continuously from the opening 20a in the horizontal direction, as shown in Figs. 2 to 4. The easy-to-cut tubular member 11 is made of a material that can be manually cut by an operator, and is installed along the ceiling part and 21a of the inclined shaft 21, which is the ceiling part of the horizontal hollow hole 20, so as to extend from the vicinity of the opening 20a of the horizontal hollow hole 20 to the vicinity of the terminal end 20b. The easy-to-cut tubular member 11 is placed in a position such that the concrete 15, which is a cement-based solidification material, is pumped through the easy-to-cut tubular member 11 and allowed to flow out from the outlet 12a at the tip (see FIG. 2). As the concrete 15 fills the hollow interior of the horizontally elongated hollow hole 20 from the vicinity of the terminal end 20b toward the vicinity of the opening 20a, a cut is made in the easy-to-cut tubular member 11 at a portion rearward in the pumping direction from the outlet 12a at the tip, and this cut portion is made into the subsequent outlet 12b (see FIG. 4). The outlets 12a, 12b, through which the pumped cement-based solidification material 15 flows out, are sequentially moved toward the opening 20a side, while the horizontally elongated hollow hole 20 is filled with the concrete 15.

[0021] In addition, in this embodiment, the easy-to-cut tubular member 11 is preferably made of Sunnyhose (registered trademark), and the easy-to-cut tubular member 11 is preferably supported via a plurality of hanging fittings 13 attached to the ceiling portion 21a at predetermined intervals in the extension direction of the horizontal hollow hole 20 (see Figures 2 and 3), and is installed by extending along the ceiling portion 21a.

[0022] Furthermore, in this embodiment, a cable 14 such as a wire is preferably inserted inside the easy-to-cut tubular member 11, and the inserted cable 14 is engaged with each of the multiple hanging fittings 13, thereby supporting the easy-to-cut tubular member 11 via the multiple hanging fittings 13.

[0023] In this embodiment, in each construction span S of the inclined shaft 21, which is connected to the main tunnel and preferably has a horseshoe-shaped cross section, a process of backfilling the interior of the inclined shaft 21 with backfilling soil in the construction span is carried out after the process of backfilling the preceding construction span with backfilling soil and the process of backfilling the horizontal hollow hole 20 with concrete 15 are completed. The process of backfilling the interior of the inclined shaft 21 with backfilling soil in the construction span can be easily carried out by using, as backfilling soil, the excavation surplus soil that was removed when the inclined shaft 21 was formed and stored outside the shaft, and by using a known transport vehicle or excavation heavy machine. In addition, in the process of backfilling the interior of the inclined shaft 21 with backfilling soil, as described above, if the backfilling soil 22 is backfilled up to a height of about 1.2 m below the ceiling part 21a of the inclined shaft 21, it becomes difficult to perform compaction or other operations. Therefore, between the ceiling 21a of the inclined shaft 21 and the upper surface of the backfill soil 22, as shown in Fig. 1, an elongated hollow hole 20 is formed, preferably inclined downward, over a considerable length, with an opening 20a above the tip of the backfill soil 22 and an end 20b at the hardened concrete body 24 backfilled in the preceding construction span. In this embodiment, even if the working space of the elongated hollow hole 20 is narrow, the concrete can be efficiently and smoothly pumped and filled into the elongated hollow hole 20 formed over such a considerable length by the pressure-feeding and filling method described later.

[0024] That is, in this embodiment, concrete 15 is preferably pumped into the horizontal hollow hole 20 left in the ground in a continuous horizontal direction from the opening 20a, and in the process of backfilling the horizontal hollow hole 20 with the hardened concrete 15, a flexible easy-to-cut tubular member 11 made of SunnyHose (registered trademark), preferably with an inner diameter of about 6 inches, is installed as a material that can be manually cut by an operator, extending from the vicinity of the opening 20a of the horizontal hollow hole 20 to the vicinity of the terminal end 20b along the ceiling 21a of the inclined shaft 21, which is the ceiling of the horizontal hollow hole 20 (see Figures 1 and 2). The easy-to-cut tubular member 11 made of Sunny Hose is preferably attached by being hung and supported by a plurality of hanging fittings 13 attached to the ceiling 21a of the inclined shaft 21 (horizontal hollow hole 20) at a predetermined interval, for example, a pitch of about 1 to 2 m, in the extension direction of the horizontal hollow hole 20. As the hanging fittings 13, a known hanging jig with an anchor that can be fixed to the ceiling 21a of the inclined shaft 21 by, for example, a driving-in anchor, can be used (see FIG. 3).

[0025] In this embodiment, the easily cut tubular member 11 made of SunnyHose is made of a flexible material and does not have shape retention, so it is preferable to insert a cord 14 such as a wire or messenger as a core material into the easily cut tubular member 11 made of SunnyHose. When the easily cut tubular member 11 is supported by a plurality of hanging fittings 13 and attached along the ceiling portion 21a, the easily cut tubular member 11 can be supported in a more stable state by hanging it from the hanging fittings 13 by engaging each of the multiple hanging fittings 13 with the inserted cord 14. The easily cut tubular member 11 made of SunnyHose is made of a material that is easy to cut manually by a worker, so that, for example, by making appropriate cuts in necessary places and exposing the cord 14, it becomes possible to easily engage the cord 14 with the hanging fittings 13.

[0026] In this embodiment, the easy-to-cut tubular member 11 made of Sunny Hose is installed by extending it along the ceiling portion 21a of the horizontal hollow hole 20, and then, as shown in Fig. 1, a concrete pressure-transport pipe 25a extending from a concrete pump vehicle 25 installed in the area of ​​the next construction span S in the inclined shaft 21 is connected to the end of the easy-to-cut tubular member 11 on the opening 20a side of the horizontal hollow hole 20 via a known connection joint 25b. After that, by pressure-transporting the concrete charged from the mixer vehicle 26 by the concrete pump vehicle 25, it is possible to smoothly send the concrete through the easy-to-cut tubular member 11 to the terminal end 20b on the side of the hardened body 24 made of concrete backfilled in the preceding construction span. The concrete pumped out by the pumping pressure flows out from the outlet 12a at the tip of the easy-to-cut tubular member 11 arranged at the terminal end 20b of the horizontally elongated hollow hole 20, as shown in Figure 2, and is gradually filled into the hollow interior of the horizontally elongated hollow hole 20 from the vicinity of the terminal end 20b toward the vicinity of the opening 20a.

[0027] In this embodiment, the concrete 15 to be pumped flows out from the outlet 12a at the tip of the easy-to-cut tubular member 11, and as the concrete 15 fills the hollow interior of the horizontal hollow hole 20 from the vicinity of the end 20b toward the vicinity of the opening 20a, for example, when the outlet 12a at the tip becomes embedded in the poured concrete 15, the easy-to-cut tubular member 11 can be cut in the portion rearward of the outlet 12a at the tip in the pumping direction, as shown in Fig. 4, so that the cut portion becomes the subsequent outlet 12b from which the concrete 15 to be pumped flows out, and the horizontal hollow hole 20 can be filled with the concrete 15 toward the opening 20a. The concrete flowing out from the outlets 12a and 12b can be filled into the horizontal hollow hole 20 while preferably being compacted using a vibrator 27.

[0028] Therefore, according to the method for pumping and filling the cement-based solidification material of this embodiment, as shown in Figures 5(a) to (i), pumped concrete is poured out from the outlet 12a at the tip of the easily cut tubular member 11 that is attached in an elongated hollow hole 20 so as to extend along the ceiling portion 21a, and filled in the vicinity of the end portion 20b (see Figures 5(a) to (c)). For example, when the outlet 12a becomes embedded in the poured concrete 15 (see Figure 5(d)), a cut 16 is made in the easily cut tubular member 11 in a portion, for example, about 1 to 2 m behind the outlet 12a in the pumping direction, and this cut 16 is The part where the concrete 15 is pumped can be continuously discharged from the subsequent outlet 12b (see Fig. 5(e) and (f)). When the subsequent outlet 12b is embedded in the discharged concrete 15 (see Fig. 5(g)), a cut 16 is made in the easy-to-cut tubular member 11 at a portion further rearward in the pumping direction, for example, about 1 to 2 m from the subsequent outlet 12b (see Fig. 5(h)). The portion where the cut 16 is made can be used as the subsequent outlet 12c to continuously discharge the concrete 15 pumped (see Fig. 5(i)). By repeating such a process (step), it becomes possible to easily fill and backfill the hollow interior of the oblong hollow hole 20 with concrete from the vicinity of the terminal end 20b to the vicinity of the opening 20a.

[0029] As a result, according to the pressure-feeding method of the present embodiment, compared to, for example, piping a plurality of concrete pressure pipes of different lengths on the upper surface of the backfill soil 22, or forming a concrete pressure pipe using a plurality of unit pipes, and sequentially removing the unit pipes at the tip as the filling work progresses, by simply making cuts in the easy-to-cut tubular member 11, the subsequent outlets 12b, 12c can be sequentially formed in the rear part in the pressure-feeding direction as the filling work progresses, even if the working space is narrow. This makes it possible to smoothly fill the horizontally elongated hollow hole 20, which is left in the ground continuously in the horizontal direction and formed over a considerable length, from the end 20b of the horizontally elongated hollow hole 20 toward the opening 20a with the cement-based solidification material concrete 15, without much labor.

[0030] In this embodiment, for example, the subsequent outlets 12b, 12c are preferably formed by making a cut 16 in the easy-to-cut tubular member 11 in a portion downstream in the pumping direction adjacent to the hanging fitting 13 to which the cable 14 is anchored. This makes it possible for the easy-to-cut tubular member 11, for example made of SunnyHose (registered trademark), to effectively support the portions adjacent to the outlets 12b, 12c and stably maintain the opening shapes of the outlets 12b, 12c when the concrete flows out, even if the easy-to-cut tubular member 11 is a soft member that does not have shape retention.

[0031] The present invention is not limited to the above embodiment and can be modified in various ways. For example, the horizontally elongated hollow hole formed over a considerable length does not necessarily have to be a hollow hole in the ceiling part of an inclined tunnel connected to the main tunnel, which is left between the ceiling part of the inclined tunnel and the backfill soil inside, but may be any other horizontally elongated hollow hole. It may be a horizontally elongated hollow hole formed by the hollow interior of a pipe by driving a box-shaped hollow pipe into the ground in an underpass construction method or the like. The easy-to-cut tubular member does not necessarily have to be Sunny Hose (registered trademark) having flexibility, but may be a tubular member made of other materials that can be manually cut by a worker. It may be a tubular member made of a thin-walled plastic material that is easy to cut and has shape retention. The cement-based solidification material pumped through the easy-to-cut tubular member may be concrete, or any other cement-based solidification material such as foamed mortar. [Explanation of symbols]

[0032] 11 Easy-to-cut tubular member (Sunny hose) 12a Tip outlet 12b, 12c Subsequent outlet 13 Hanging hardware 14 Cordicular body 15. Concrete 16 Cutting 20 Horizontal hollow hole 20a opening 20b Termination section 21 Diagonal Shaft 21a Ceiling 22 Backfill soil 22a Tip 24 Hardened body 25 Concrete pump truck 25a Concrete pressure pipe 25b Connection joint 26 Mixer Truck 27 Vibrator S Construction span

Claims

1. A method for pumping and filling a cement-based solidification material, which is used in a process of backfilling a horizontally elongated hollow hole left in the ground continuously from an opening in a horizontal direction with a cement-based solidification material, comprising: an easily cut tubular member made of a material that can be manually cut by an operator is installed along the ceiling of the oblong cavity so as to extend from the vicinity of the opening of the oblong cavity to the vicinity of the terminal end thereof; A method for pumping and filling a cement-based solidification material, in which the cement-based solidification material pumped through the easy-to-cut tubular member is caused to flow out from the outlet at the tip, and as the cement-based solidification material is filled into the hollow interior of the horizontally elongated hollow hole from the vicinity of the terminal end toward the vicinity of the opening, a cut is made in the easy-to-cut tubular member at a portion rearward of the outlet at the tip in the pumping direction, so that the cut portion serves as a subsequent outlet, and the outlet through which the pumped cement-based solidification material flows out is sequentially moved toward the opening side, thereby filling the horizontally elongated hollow hole with the cement-based solidification material.

2. 2. The method for pumping and filling a cement-based solidification material according to claim 1, wherein the easily cut tubular member is made of Sunny Hose (registered trademark).

3. 3. The method for pumping and filling a cement-based solidification material according to claim 1 or 2, wherein the easy-to-cut tubular member is supported by a plurality of hanging fittings attached to the ceiling at predetermined intervals in the extension direction of the horizontal hollow hole, and is installed extending along the ceiling.

4. 4. The method for pumping and filling a cement-based solidification material as described in claim 3, wherein a cord such as a wire is inserted into the inside of the easy-to-cut tubular member, and the inserted cord is engaged with each of the plurality of hanging fittings, thereby supporting the easy-to-cut tubular member via the plurality of hanging fittings.

5. 5. The method for pumping and filling a cement-based solidification material according to claim 4, wherein the subsequent outflow port is formed by making a cut in the easy-to-cut tubular member in a portion adjacent to the hanging fitting to which the cord is attached and downstream in the pumping direction.

6. 3. The method for pumping and filling a cement-based solidification material according to claim 1 or 2, wherein the horizontal hollow hole is a hollow hole in the ceiling portion of an inclined tunnel connected to a main tunnel, which is backfilled after the main tunnel is constructed, and which is left between the ceiling portion of the inclined tunnel and the backfill soil backfilled inside the inclined tunnel.

Citation Information

Patent Citations

  • Hose tower for placing concrete

    JP1978058129A

  • Casting method of concrete

    JP1982193670A

  • Clearance filling method of double pipe

    JP1987266288A

  • Method of placing concrete in long size space

    JP2000104403A

  • Flexible hose and restraint tool for the same

    JP2023040491A