Inspection support system, inspection support method, and inspection support program

The inspection support system adjusts inspection schedules based on equipment stability, optimizing resource use by reducing inspections for stable equipment and increasing them for unstable equipment, enhancing overall efficiency.

JP2024151524APending Publication Date: 2024-10-25OMRON CORP
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
JP2023064938
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-04-12
Publication Date
2024-10-25

AI Technical Summary

Technical Problem

Existing inspection systems require inspectors to perform inspections according to predetermined schedules, regardless of the equipment's likelihood of causing abnormalities, leading to inefficient use of resources.

Method used

An inspection support system that includes an acquisition processing unit to gather inspection results and a change processing unit to adjust the inspection schedule based on these results, increasing or decreasing the frequency of inspections based on the equipment's stability.

Benefits of technology

This system optimizes the inspection schedule by reducing inspections for stable equipment and increasing them for unstable equipment, thereby improving the efficiency of inspection processing.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024151524000001_ABST
    Figure 2024151524000001_ABST
Patent Text Reader

Abstract

To provide an inspection support system, an inspection support method, and an inspection support program which can make inspection processing for an inspection object efficient.SOLUTION: An inspection support system 1 includes: an acquisition processing section 212 for acquiring an inspection result of inspection processing for an inspection object on the basis of an inspection schedule; and a change processing section 213 for changing the inspection schedule on the basis of the inspection result acquired by the acquisition processing section 212 when it is determined that the change of the inspection schedule is required.SELECTED DRAWING: Figure 2
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a technique for supporting an inspection process for an inspection target such as equipment installed in a facility. [Background technology]

[0002] In buildings and other facilities, inspectors periodically inspect various equipment (devices) according to pre-registered inspection items and record the inspection results. Conventionally, a system for supporting equipment inspection work has been known (see, for example, Patent Document 1). [Prior art documents] [Patent documents]

[0003] [Patent Document 1] JP 2001-084295 A Summary of the Invention [Problem to be solved by the invention]

[0004] Normally, each facility has a set inspection schedule (inspection frequency, inspection interval, etc.), and inspectors inspect each facility according to the set inspection schedule. Therefore, whether the facility is unlikely to have abnormalities or prone to abnormalities, inspectors must always inspect the facility according to the inspection schedule, which is not efficient.

[0005] An object of the present invention is to provide an inspection support system, an inspection support method, and an inspection support program that can improve the efficiency of inspection processing for inspection objects. [Means for solving the problem]

[0006] According to one aspect of the present invention, an inspection support system includes an acquisition processor and a change processor. The acquisition processor acquires an inspection result of an inspection process for an inspection target based on an inspection schedule. The change processor changes the inspection schedule when it is determined that the inspection schedule needs to be changed based on the inspection result acquired by the acquisition processor.

[0007] An inspection support method according to another aspect of the present invention is a method executed by one or more processors to obtain inspection results of an inspection process for an inspection object based on an inspection schedule, and, if it is determined based on the inspection results that the inspection schedule needs to be changed, to change the inspection schedule.

[0008] An inspection support program relating to another aspect of the present invention is a program for causing one or more processors to obtain inspection results of inspection processing for inspection objects based on an inspection schedule, and, if it is determined based on the inspection results that the inspection schedule needs to be changed, changing the inspection schedule. Effect of the Invention

[0009] According to the present invention, it is possible to provide an inspection support system, an inspection support method, and an inspection support program that are capable of improving the efficiency of inspection processing for inspection objects. [Brief description of the drawings]

[0010] [Figure 1] FIG. 1 is a schematic diagram showing the overall configuration of an inspection support system according to an embodiment of the present invention. [Diagram 2] FIG. 2 is a functional block diagram showing a specific configuration of the inspection support system according to the embodiment of the present invention. [Diagram 3] FIG. 3 is a diagram showing an example of facility information used in the inspection support system according to the embodiment of the present invention. [Figure 4]FIG. 4 is a diagram showing an example of inspection level information used in the inspection support system according to the embodiment of the present invention. [Diagram 5] FIG. 5 is a diagram showing an example of equipment inspection level information used in the inspection support system according to the embodiment of the present invention. [Figure 6] FIG. 6 is a diagram showing an example of inspection history information used in the inspection support system according to the embodiment of the present invention. [Figure 7] FIG. 7 is a diagram showing an example of an inspection work page (menu screen) displayed on the inspector terminal according to the embodiment of the present invention. [Figure 8] FIG. 8 is a diagram showing an example of an inspection work page (inspection work screen) displayed on the inspector terminal according to the embodiment of the present invention. [Figure 9] FIG. 9 is a diagram showing a specific example of an inspection result of the inspection process according to the embodiment of the present invention. [Figure 10] FIG. 10 is a diagram showing an example of equipment inspection level information used in the inspection support system according to the embodiment of the present invention. [Figure 11] FIG. 11 is a flowchart showing an example of a procedure of an inspection support process executed in the inspection support system according to the embodiment of the present invention. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0011] Hereinafter, an embodiment of the present invention will be described with reference to the accompanying drawings to facilitate understanding of the present invention. Note that the following embodiment is an example of the present invention and does not limit the technical scope of the present invention.

[0012] [Inspection support system 1] As shown in FIG. 1, an inspection support system 1 according to an embodiment of the present invention includes a management server 2, an equipment monitoring device 3, an administrator terminal 4, and an inspector terminal 5. The management server 2, the equipment monitoring device 3, the administrator terminal 4, and the inspector terminal 5 can communicate with each other via a communication network N1 such as the Internet, a LAN, a WAN, or a public telephone line. The inspection support system 1 is introduced into a facility in which a plurality of facilities are installed. The facilities include various facilities such as commercial facilities such as commercial buildings, public facilities such as government offices, accommodation facilities such as hotels and inns, and complex facilities. The facilities include various devices such as air conditioning equipment such as boilers, refrigerators, pumps, air conditioners, and blowers, high-pressure equipment, electrical equipment such as generators and power supply equipment, and firefighting equipment such as alarms and fire extinguishers, and are devices that require regular inspection. In this embodiment, a commercial building facility B1 is given as an example of the facility.

[0013] An inspector (worker) of the equipment installed in the facility B1 performs inspection work on the equipment to be inspected (hereinafter also referred to as the equipment to be inspected). Specifically, the inspector carries an inspector terminal 5 (smartphone, mobile terminal, etc.), visits and inspects multiple pieces of equipment to be inspected, and inputs the inspection results (normal, abnormal, actual measurement data, etc.) into the inspector terminal 5. For example, the inspector checks the equipment to be inspected and the inspection items on an operation screen (inspection work page (see Figs. 7 and 8)) provided by the management server 2 and displayed on the inspector terminal 5, and inputs the inspection results of the equipment to be inspected. When there are multiple inspectors, each inspector carries his / her own inspector terminal 5 and performs inspection work on the equipment to be inspected that is assigned to him / her. The inspection support system 1 includes one or more inspector terminals 5.

[0014] The equipment monitoring device 3 monitors equipment to be monitored within the facility B1 (hereinafter also referred to as monitored equipment). Specifically, the equipment monitoring device 3 monitors the monitored equipment by using, for example, BACnet (Building Automation and Control Networking Protocol) ("BACnet"; registered trademark). The equipment monitoring device 3 may be included in a so-called building automation management control system.

[0015] The management server 2 provides equipment management services to various facilities and operates an equipment management service site. Specifically, the management server 2 manages and supports the inspection work of the facility B1 by accepting operations on the inspector terminal 5 by the inspector. The management server 2 also presents various information related to the inspection work to the inspector. When new equipment is introduced to the facility B1, the management server 2 also accepts operations on the administrator terminal 4 by the administrator to register equipment information and set inspection items corresponding to the equipment. The management server 2 may be installed inside the facility B1 or outside the facility B1. The management server 2 also creates an inspection result report including the inspection results of the inspection work on the inspection target equipment by the inspector and the monitoring results of the monitored equipment by the equipment monitoring device 3.

[0016] In this embodiment, the management server 2 alone corresponds to the inspection support system according to the present invention, but the inspection support system according to the present invention may include one or more of the components of the management server 2, the equipment monitoring device 3, the manager terminal 4, and the inspector terminal 5. In addition, when the components of the management server 2, the equipment monitoring device 3, the manager terminal 4, and the inspector terminal 5 cooperate to share and execute the inspection support process (see FIG. 11) described below, a system including the components that execute the process can be regarded as the inspection support system according to the present invention. For example, the management server 2, the equipment monitoring device 3, the manager terminal 4, and the inspector terminal 5 may constitute the inspection support system according to the present invention. In addition, the management server 2 may also have the function of the equipment monitoring device 3. In this case, the management server 2, the manager terminal 4, and the inspector terminal 5 may constitute the inspection support system according to the present invention.

[0017] [Equipment monitoring device 3] As shown in FIG. 2, the equipment monitoring device 3 is a server including a control unit 31, a storage unit 32, an operation display unit 33, and a communication I / F 34. The equipment monitoring device 3 is not limited to one computer, but may be a computer system in which multiple computers work together, or may be configured as a cloud server. Various processes executed by the equipment monitoring device 3 may be executed in a distributed manner by one or multiple processors. The equipment monitoring device 3 monitors the monitored equipment in facility B1 using BACnet. The functions of the equipment monitoring device 3 may be included in the management server 2.

[0018] The communication I / F 34 is a communication interface for connecting the equipment monitoring device 3 to the communication network N1 by wire or wirelessly and for executing data communication with an external device such as the management server 2 via the communication network N1 in accordance with a predetermined communication protocol. The communication I / F 34 also executes data communication with the monitored equipment in accordance with BACnet.

[0019] The operation display unit 33 is a user interface that includes a display unit, such as a liquid crystal display or an organic EL display, that displays various information, and an operation unit, such as a mouse, a keyboard, or a touch panel, that accepts operations.

[0020] The storage unit 32 is a non-volatile storage unit such as a hard disk drive (HDD), a solid state drive (SSD), or a flash memory that stores various information. Specifically, the storage unit 32 includes monitoring equipment information.

[0021] The monitored equipment information includes information such as the name (monitored equipment name), monitored items, units, and classification for each piece of equipment (monitored equipment) that is the target of monitoring among the equipment installed in facility B1. The monitored equipment registered in the monitored equipment information has a communication function that can use BACnet, and periodically transmits data corresponding to the monitored items (information on normal, abnormal, measured values, etc.) to the control unit 31. Each piece of information registered in the monitored equipment information is registered in advance by the administrator of facility B1, the service provider of the equipment management service, or the like. The monitored equipment is an example of an inspection target of the present invention.

[0022] The control unit 31 has control devices such as a CPU, a ROM, and a RAM. The CPU is a processor that executes various arithmetic processing. The ROM is a non-volatile storage unit in which control programs such as a BIOS and an OS for causing the CPU to execute various arithmetic processing are stored in advance. The RAM is a volatile or non-volatile storage unit that stores various information, and is used as a temporary storage memory (work area) for various processes executed by the CPU. The control unit 31 controls the equipment monitoring device 3 by executing, by the CPU, various control programs stored in advance in the ROM or the storage unit 32.

[0023] Specifically, the control unit 31 acquires measurement results from each monitored equipment in the facility B1 and stores them in the memory unit 32. Furthermore, if there is an abnormality in the measurement results, the control unit 31 notifies the manager of the facility B1 of the abnormality. Furthermore, the control unit 31 may transmit the measurement results to the management server 2, and the management server 2 may manage the measurement results (inspection results) of the monitored equipment.

[0024] The facility monitoring device 3 can be implemented using well-known technology, such as an automatic building management control system using BACnet.

[0025] [Management Server 2] 2, the management server 2 is a server including a control unit 21, a storage unit 22, an operation display unit 23, and a communication I / F 24. The management server 2 is not limited to a single computer, but may be a computer system in which multiple computers work together, or may be configured as a cloud server. Various processes executed by the management server 2 may be executed in a distributed manner by one or multiple processors.

[0026] The communication I / F 24 is a communication interface that connects the management server 2 to the communication network N1 via a wired or wireless connection, and performs data communication in accordance with a specified communication protocol between the management server 2 and external devices such as the equipment monitoring device 3, the administrator terminal 4, and the inspector terminal 5 via the communication network N1.

[0027] The operation display unit 23 is a user interface that includes a display unit, such as a liquid crystal display or an organic EL display, that displays various information, and an operation unit, such as a mouse, a keyboard, or a touch panel, that accepts operations.

[0028] The storage unit 22 is a non-volatile storage unit such as an HDD, SSD, or flash memory that stores various information. Specifically, the storage unit 22 includes data such as equipment information D1, inspection level information D2, equipment inspection level information D3, and inspection history information D4.

[0029] FIG. 3 is a diagram showing an example of equipment information D1 corresponding to facility B1. The equipment information D1 includes information on equipment (inspection target equipment) installed in facility B1. Specifically, the equipment information D1 includes information such as classification, equipment, inspection items, and input units. Inspection items are set in advance for each inspection target equipment. Although omitted in FIG. 3, the equipment information D1 may further include information such as the device number, manufacturer model, manufacturing year, manufacturing company, construction company, and repair company for each inspection target equipment. For example, information on all inspection target equipment installed in facility B1 is registered in the equipment information D1. Each piece of information registered in the equipment information D1 is registered in advance by the manager of facility B1, the service provider of the equipment management service, or the like. The equipment information D1 may also include information on the monitoring target equipment.

[0030] FIG. 4 is a diagram showing an example of the inspection level information D2. The inspection level information D2 includes information such as an inspection level, a frequency, a level-up condition, and a level-down condition. The inspection level is information that indicates a level according to the inspection frequency. For example, an inspection level "5" indicates a frequency at which the inspection work is performed once a month, an inspection level "4" indicates a frequency at which the inspection work is performed once every two weeks, an inspection level "3" indicates a frequency at which the inspection work is performed once a week, an inspection level "2" indicates a frequency at which the inspection work is performed once every two days, and an inspection level "1" indicates a frequency at which the inspection work is performed once a day. In this way, the higher the inspection level, the lower the frequency of the inspection work, and the lower the inspection level, the higher the frequency of the inspection work.

[0031] In another embodiment, the interval between inspections (inspection interval) may be registered instead of the frequency. In this case, inspection level "5" indicates that the interval between inspections is "1 month", inspection level "4" indicates that the interval between inspections is "2 weeks", inspection level "3" indicates that the interval between inspections is "1 week", inspection level "2" indicates that the interval between inspections is "2 days", and inspection level "1" indicates that the interval between inspections is "1 day". In this way, the higher the inspection level, the longer the interval between inspections, and the lower the inspection level, the shorter the interval between inspections. "Inspection frequency" and "inspection interval" are examples of the inspection schedule of the present invention.

[0032] The level-up condition is information that indicates a condition for raising the inspection level. For example, in an inspection operation on a specific equipment to be inspected, whose inspection level is set to "1", if the most recent five inspection results are normal ("◯") consecutively, the control unit 21 raises the inspection level of the equipment to be inspected from "1" to "2". When the inspection level is changed to "2", the inspection operation on the equipment to be inspected is performed at the frequency of the inspection level "2" (once every two days) from the next inspection onward. Also, for example, in an inspection operation on a specific equipment to be inspected, whose inspection level is set to "4", if the most recent ten inspection results are normal ("◯") consecutively, the control unit 21 raises the inspection level of the equipment to be inspected from "4" to "5". When the inspection level is changed to "5", the inspection operation on the equipment to be inspected is performed at the frequency of the inspection level "5" (once a month) from the next inspection onward. In this way, the level-up condition may be set to be stricter as the inspection level is higher.

[0033] The level down condition is information that indicates a condition for lowering the inspection level. For example, in an inspection operation on a specific equipment to be inspected, whose inspection level is set to "5", if the inspection result is abnormal ("x"), the control unit 21 lowers the inspection level of the equipment to be inspected from "5" to "4". When the inspection level is changed to "4", the inspection operation on the equipment to be inspected is performed at the frequency of the inspection level "4" (once every two weeks) from the next inspection onwards. Also, for example, in an inspection operation on a specific equipment to be inspected, whose inspection level is set to "2", if the inspection result is abnormal ("x") twice consecutively, the control unit 21 lowers the inspection level of the equipment to be inspected from "2" to "1". When the inspection level is changed to "1", the inspection operation on the equipment to be inspected is performed at the frequency of the inspection level "1" (once a day) from the next inspection onwards. In this way, the level down condition may be set to be more lenient as the inspection level is higher.

[0034] In the inspection level information D2 shown in FIG. 4, the control unit 21 is configured to raise the inspection level by one step when the level-up condition is satisfied, but in another embodiment, the control unit 21 may raise the inspection level by two or more steps. Similarly, the control unit 21 is configured to lower the inspection level by one step when the level-down condition is satisfied, but in another embodiment, the control unit 21 may lower the inspection level by two or more steps. In addition, the step at which the inspection level is raised when the level-up condition is satisfied may be different from the step at which the inspection level is lowered when the level-down condition is satisfied. For example, the control unit 21 may raise the inspection level by one step when the level-up condition is satisfied, and may lower the inspection level by two steps when the level-down condition is satisfied.

[0035] FIG. 5 is an example of the equipment inspection level information D3. The equipment inspection level information D3 includes information on the inspection level set for the equipment to be inspected. Specifically, the equipment inspection level information D3 includes information on the equipment to be inspected, the inspection level, and the like. An inspection level is set in advance for each piece of equipment to be inspected. For example, when new equipment (equipment to be inspected) is introduced into the facility B1, the control unit 21 sets a predetermined inspection level for the equipment to be inspected in response to a registration operation by the manager and registers the equipment in the equipment inspection level information D3. The control unit 21 may automatically set the inspection level in response to the type (such as the above-mentioned classification) of the equipment to be inspected. Furthermore, when the equipment to be inspected satisfies a level-up condition or a level-down condition, the control unit 21 changes (updates) the inspection level set for the equipment to be inspected in the equipment inspection level information D3.

[0036] FIG. 6 is an example of the inspection history information D4. The inspection history information D4 includes information on the inspection results for each piece of equipment to be inspected. Specifically, the inspection history information D4 includes information on the equipment to be inspected and the inspection history. The inspection history accumulates inspection results for a predetermined period of time in the past. The accumulation period of the inspection history may be set differently depending on the equipment to be inspected. For example, the control unit 21 may set the accumulation period depending on the inspection level set for the equipment to be inspected. For example, the control unit 21 sets the accumulation period of the equipment to be inspected whose inspection level is set to "1" to "10 days", sets the accumulation period of the equipment to be inspected whose inspection level is set to "3" to "2 weeks", and sets the accumulation period of the equipment to be inspected whose inspection level is set to "4" to "1 month". The inspection history of the inspection history information D4 is used, for example, in the determination process for the level-up condition and the level-down condition.

[0037] In addition to the above-mentioned information, memory unit 22 may also store information regarding the installation location of each piece of equipment to be inspected, information regarding multiple inspectors who perform inspection work on the equipment to be inspected (inspector information), information regarding the equipment to be inspected assigned to the inspectors (allocation information), and information regarding the work status of each inspector (work status information).

[0038] In another embodiment, some or all of the equipment information D1, the inspection level information D2, the equipment inspection level information D3, and the inspection history information D4 may be stored in another server accessible from the management server 2 via the communication network N1. In this case, the control unit 21 of the management server 2 may acquire the information from the other server and execute various processes such as the inspection support process (see FIG. 11) described below.

[0039] The storage unit 22 also stores layout data and image data for generating various web pages to be displayed on the manager terminal 4 and the inspector terminal 5. In this embodiment, the control unit 21 of the management server 2 generates the various web pages and transmits information of the web pages to the manager terminal 4 and the inspector terminal 5, thereby making it possible to display the various web pages on the manager terminal 4 and the inspector terminal 5. In another embodiment, the control unit 21 of the management server 2 may transmit data required for displaying the various web pages to the manager terminal 4 and the inspector terminal 5, thereby making the control unit 41 of the manager terminal 4 and the control unit 51 of the inspector terminal 5 display the various web pages.

[0040] Furthermore, the storage unit 22 stores control programs such as an inspection support program for causing the control unit 21 to execute an inspection support process (see FIG. 11) described below. For example, the inspection support program is non-temporarily recorded on a computer-readable recording medium such as a CD or DVD, and is read by a reading device (not shown) such as a CD drive or DVD drive provided in the management server 2 and stored in the storage unit 22. The inspection support program is one example of an inspection support program of the present invention.

[0041] The control unit 21 has control devices such as a CPU, a ROM, and a RAM. The CPU is a processor that executes various arithmetic processing. The ROM is a non-volatile storage unit in which control programs such as a BIOS and an OS for causing the CPU to execute various arithmetic processing are stored in advance. The RAM is a volatile or non-volatile storage unit that stores various information, and is used as a temporary storage memory (work area) for various processes executed by the CPU. The control unit 21 controls the management server 2 by executing, with the CPU, various control programs stored in advance in the ROM or the storage unit 22.

[0042] Specifically, as shown in Fig. 2, the control unit 21 includes various processing units such as an inspection processing unit 211, an acquisition processing unit 212, and a change processing unit 213. The control unit 21 functions as the various processing units by executing various processes according to the inspection support program with the CPU. Also, a part or all of the processing units may be configured with electronic circuits. The inspection support program may be a program for causing a plurality of processors to function as the processing units.

[0043] The inspection processing unit 211 executes inspection processing for the equipment to be inspected. Specifically, the inspection processing unit 211 executes an assignment process for assigning the equipment to be inspected to each inspector in charge of the inspection work. Specifically, the inspection processing unit 211 assigns multiple pieces of equipment to be inspected of different types to each inspector. For example, the inspection processing unit 211 assigns 10 pieces of electrical equipment to inspector A1 and 10 pieces of air conditioning equipment to inspector A2. The inspection processing unit 211 registers information about the equipment to be inspected assigned to each inspector in the storage unit 22.

[0044] The inspection processing unit 211 may execute the allocation process based on the inspection history, inspection ability level, qualifications, etc. of each inspector. The inspection processing unit 211 may also allocate the equipment to be inspected to each inspector so that the work time for the inspection of all the equipment to be inspected in the facility B1 is minimized.

[0045] After executing the allocation process, the inspection processing unit 211 executes the inspection process according to the inspection work by the inspector. Specifically, when the equipment management application is executed in the inspector terminal 5, the inspection processing unit 211 displays the inspection work page shown in FIG. 7 and FIG. 8 on the inspector terminal 5 and accepts the operation of the inspector. The inspection work page (menu screen) shown in FIG. 7 displays information such as the number of equipment to be inspected assigned to the inspector (inspector A1 in this case), the number of cases in which the inspector inputted "abnormal" as the inspection result, the number of cases in which the inspector requested the manager to request inspection, and the number of cases in which the inspector inputted report items regarding the inspection. The inspector A1 presses the "inspect" button when starting the inspection work of the equipment to be inspected assigned to him / her. When the inspector A1 presses the "inspect" button, the inspection processing unit 211 displays the inspection work page (inspection work screen) shown in FIG. 8 on the inspector terminal 5. The inspection work screen shown in FIG. 8 displays inspection information such as the name, location, and inspection items of the equipment to be inspected. On the inspection work screen, inspector A1 inspects the equipment to be inspected according to the inspection items, and inputs the inspection results (normal "O", abnormal "X", measurement values, etc.).

[0046] In this way, the inspection processing unit 211 displays the inspection items corresponding to the equipment to be inspected registered in the equipment information D1 (see FIG. 3) on the inspector terminal 5 and accepts the input operation of the inspection result by the inspector. Also, the inspection processing unit 211 displays the inspection information related to the equipment to be inspected according to the inspection schedule (inspection frequency, inspection interval) of the inspection level set in advance (see FIG. 4 and FIG. 5). Also, the inspection processing unit 211 displays the inspection information related to the equipment to be inspected assigned to the inspector on the inspector terminal 5 in sequence. For example, the inspection processing unit 211 displays the inspection information of 10 electrical equipment in sequence on the inspection work page of the inspector terminal 5 of the inspector A1. Also, when the inspector A1 selects the desired equipment to be inspected from the list of the equipment to be inspected assigned to him / her, the inspection processing unit 211 displays the inspection information related to the selected equipment to be inspected on the inspection work screen. When inspector A1 inputs the inspection results and presses the "Confirm" button, the inspection processing unit 211 displays a list of equipment to be inspected, accepts selection of the next equipment to be inspected from inspector A1, and displays inspection information for the selected equipment to be inspected on the inspection work screen.

[0047] In another embodiment, the inspection processing unit 211 may display inspection information of the equipment to be inspected on the inspection work screen based on the location information of the inspector. For example, when the inspector A1 is near the location (electrical room R2) where the equipment E1 ("high voltage receiving board") is located, or when the inspector A1 is moving toward the electrical room R2, the inspection processing unit 211 identifies the equipment E1 as the next equipment to be inspected, and displays the inspection information related to the equipment E1 on the inspection work page.

[0048] In another embodiment, the inspection processing unit 211 may display the inspection information on the inspection work page according to a preset inspection sequence (inspection route). For example, when an inspection sequence is preset for 10 electrical equipments assigned to the inspector A1, the inspection processing unit 211 displays the inspection information of each electrical equipment according to the inspection sequence. In this case, the inspection processing unit 211 may display a travel route (map information) corresponding to the inspection sequence on the inspection work page.

[0049] The inspection processing unit 211 causes the inspector terminal 5 of each inspector to display an inspection work page, and executes the inspection processes in parallel.

[0050] The inspection processing unit 211 also acquires the work status of each inspector. Specifically, the inspection processing unit 211 acquires the work status, such as information on inspection target equipment for which inspection work has been completed, information on inspection target equipment currently undergoing inspection work, and information on inspection target equipment for which inspection work has not been completed, for each inspector. The inspection processing unit 211 registers the acquired work status in the storage unit 22. The inspection processing unit 211 also registers the inspection results in the inspection history information D4 (see FIG. 6) for inspection target equipment for which inspection work has been completed.

[0051] In this way, each of the multiple inspectors performs the inspection work of the equipment to be inspected that is assigned to them in parallel during the inspection work. Also, each of the multiple inspectors performs the inspection work according to the inspection schedule (inspection frequency, inspection interval) of the inspection level that is set in advance for each equipment to be inspected (see Fig. 4 and Fig. 5). Then, the inspection processing unit 211 accumulates the inspection results according to the inspection schedule for each equipment to be inspected (see Fig. 6).

[0052] The inspection processing unit 211 may register the monitoring results (inspection results) of the equipment to be monitored by the equipment monitoring device 3 in the inspection history information D4 (see FIG. 6). That is, the inspection history information D4 may register the inspection history of all the equipment installed in the facility B1.

[0053] The acquisition processing unit 212 acquires the inspection results of the inspection process for the equipment to be inspected based on the inspection schedule. Specifically, the acquisition processing unit 212 acquires the inspection history of the inspection history information D4 (see FIG. 6). For example, the acquisition processing unit 212 acquires the inspection results registered by the inspection work of an inspector. In addition, the acquisition processing unit 212 acquires the measurement results (inspection results) measured by the equipment monitoring device 3. In other words, the inspection process includes the inspection work by the inspector and the monitoring process by the equipment monitoring device 3. The acquisition processing unit 212 is an example of the acquisition processing unit of the present invention.

[0054] The change processing unit 213 executes a process of changing the inspection schedule when a predetermined condition is satisfied for the equipment to be inspected. Specifically, the change processing unit 213 determines whether or not it is necessary to change the inspection schedule set for the equipment to be inspected based on the inspection results of the equipment to be inspected acquired by the acquisition processing unit 212, and changes the inspection schedule when it is determined that it is necessary to change the inspection schedule.

[0055] For example, the change processing unit 213 determines whether or not it is necessary to change the inspection schedule set for the equipment to be inspected based on the most recent inspection result (inspection history) for the equipment to be inspected, and changes the inspection schedule when it is determined that it is necessary to change the inspection schedule. Specifically, when the most recent inspection result of the equipment to be inspected satisfies a level-up condition, the change processing unit 213 raises the inspection level set for the equipment to be inspected, and when the most recent inspection result of the equipment to be inspected satisfies a level-down condition, the change processing unit 213 lowers the inspection level set for the equipment to be inspected.

[0056] That is, when a predetermined number of inspection results are obtained consecutively indicating that the equipment to be inspected is normal ("◯"), the change processing unit 213 increases the inspection level and reduces the frequency of inspection work on the equipment to be inspected. On the other hand, when a predetermined number of inspection results are obtained consecutively indicating that the equipment to be inspected is abnormal ("X"), the change processing unit 213 decreases the inspection level and increases the frequency of inspection work on the equipment to be inspected.

[0057] For example, in an inspection operation on a specific equipment to be inspected, the inspection level of which is set to "1", if the most recent five inspection results are normal ("◯") consecutively, the change processing unit 213 raises the inspection level of the equipment to be inspected from "1" to "2". When the inspection level is changed to "2", the inspection processing unit 211 executes the inspection process on the equipment to be inspected from the next time onwards at the frequency of the inspection level "2" (once every two days). Also, for example, in an inspection operation on a specific equipment to be inspected, the inspection level of which is set to "4", if the most recent ten inspection results are normal ("◯") consecutively, the change processing unit 213 raises the inspection level of the equipment to be inspected from "4" to "5". When the inspection level is changed to "5", the inspection processing unit 211 executes the inspection process on the equipment to be inspected from the next time onwards at the frequency of the inspection level "5" (once a month).

[0058] Also, for example, in an inspection operation on a specific equipment to be inspected, the inspection level of which is set to "5", if the inspection result is abnormal ("x"), the change processing unit 213 lowers the inspection level of the equipment to be inspected from "5" to "4". When the inspection level is changed to "4", the inspection processing unit 211 executes the inspection process on the equipment to be inspected from the next time onwards at the frequency of the inspection level "4" (once every two weeks). Also, for example, in an inspection operation on a specific equipment to be inspected, the inspection level of which is set to "2", if the inspection result is abnormal ("x") twice consecutively, the change processing unit 213 lowers the inspection level of the equipment to be inspected from "2" to "1". When the inspection level is changed to "1", the inspection processing unit 211 executes the inspection process on the equipment to be inspected from the next time onwards at the frequency of the inspection level "1" (once a day).

[0059] When the change processing unit 213 changes the inspection level, it changes (updates) the inspection level registered in the equipment inspection level information D3 (see FIG. 5).

[0060] 9 and 10 show a specific example of the change process of the inspection schedule (inspection level). For example, when the inspection results of the most recent five consecutive inspections of equipment E3, whose inspection level is set to "2", are normal ("◯") (see FIG. 9), the change processing unit 213 raises the inspection level of equipment E3 from "2" to "3" in the equipment inspection level information D3 (see FIG. 10). Also, when the inspection results of equipment E7, whose inspection level is set to "2", are abnormal ("×") two consecutive times (see FIG. 9), the change processing unit 213 lowers the inspection level of equipment E7 from "2" to "1" in the equipment inspection level information D3 (see FIG. 10).

[0061] Furthermore, the change processing unit 213 executes a determination process for determining whether or not it is necessary to change the set inspection schedule (inspection level) for the equipment to be inspected at a predetermined timing. For example, the change processing unit 213 executes the determination process for the equipment to be inspected every time it acquires the inspection result of the equipment to be inspected.

[0062] As described above, each time the change processing unit 213 obtains the inspection result of the equipment to be inspected, it refers to the inspection history of the equipment to be inspected, judges whether the level-up condition or the level-up condition is satisfied, and executes the process of raising the inspection level if the level-up condition is satisfied, and lowering the inspection level if the level-down condition is satisfied. That is, the change processing unit 213 judges the stability of the operating state of the equipment to be inspected by referring to the inspection history, lowers the inspection frequency when the stability is equal to or higher than a predetermined stability, and raises the inspection frequency when the stability is below the predetermined stability.

[0063] The change processing unit 213 may determine the stability of the equipment to be inspected based on the measurement value. For example, the change processing unit 213 analyzes the trend of the measurement value, and when the measurement value exceeds the allowable range, determines that the stability is less than a predetermined stability and increases the inspection frequency. That is, the level-up condition and the level-down condition may be specified by the number of times the measurement value does not exceed the allowable range and the number of times the measurement value exceeds the allowable range. The allowable range is set according to the type of equipment to be inspected and the inspection level.

[0064] If the equipment to be inspected is equipment to be monitored by the equipment monitoring device 3, when the change processing unit 213 changes the inspection level, it outputs information on the changed inspection level (inspection schedule information) to the equipment monitoring device 3. When the control unit 31 of the equipment monitoring device 3 acquires the inspection schedule, it acquires measurement results from the equipment to be monitored according to the inspection schedule (changed inspection frequency). In addition, the control unit 31 transmits the measurement results (inspection results) to the management server 2, and the control unit 21 of the management server 2 registers the measurement results acquired from the equipment monitoring device 3 in the inspection history information D4 (see FIG. 6). The change processing unit 213 is an example of a change processing unit of the present invention.

[0065] In addition to the above-mentioned processes, the control unit 21 executes a process of tallying up the inspection results of each piece of equipment to be inspected. The control unit 21 also outputs the inspection results of the equipment to be inspected. Specifically, the control unit 21 acquires the results of the inspector's inspection of the inspection items of the equipment to be inspected and the monitoring results of the equipment monitoring device 3 monitoring the inspection items of the equipment to be monitored, and outputs the inspection results. Then, the control unit 21 creates and outputs an inspection result report including the inspection results. For example, the control unit 21 may cause a printer to print the inspection result report, or may email the data in a file format to the manager terminal 4 of the facility B1.

[0066] [Administrator terminal 4] 2, the administrator terminal 4 includes a control unit 41, a storage unit 42, an operation display unit 43, and a communication I / F 44. The administrator terminal 4 is, for example, an information processing device such as a smartphone, a tablet terminal, or a personal computer.

[0067] The communication I / F 44 is a communication interface for connecting the administrator terminal 4 to the communication network N1 via a wired or wireless connection, and for performing data communication in accordance with a specified communication protocol with external devices such as the management server 2 via the communication network N1.

[0068] The operation display unit 43 is a user interface that includes a display unit such as a liquid crystal display or an organic EL display that displays information such as various web pages, and an operation unit such as a mouse, keyboard, or touch panel that accepts operations.

[0069] The storage unit 42 is a non-volatile storage unit such as an HDD, SSD, or flash memory that stores various information. For example, a control program such as a browser program is stored in the storage unit 42. Specifically, the browser program is a control program for causing the control unit 41 to execute communication processing with an external device such as the management server 2 according to a communication protocol such as HTTP (Hypertext Transfer Protocol). The browser program may also be a dedicated application for executing communication processing with the management server 2 according to a predetermined communication protocol.

[0070] The control unit 41 has control devices such as a CPU, a ROM, and a RAM. The CPU is a processor that executes various arithmetic processing. The ROM is a non-volatile storage unit in which control programs such as a BIOS and an OS for causing the CPU to execute various processes are stored in advance. The RAM is a volatile or non-volatile storage unit that stores various information, and is used as a temporary storage memory (work area) for various processes executed by the CPU. The control unit 41 controls the administrator terminal 4 by executing, by the CPU, various control programs stored in advance in the ROM or the storage unit 42.

[0071] Specifically, the control unit 41 functions as a browser processing unit 411 by executing various processes according to the browser program stored in the storage unit 42. The browser processing unit 411 is capable of executing browser processing for displaying a web page provided from the management server 2 via the communication network N1 on the operation display unit 43 and inputting operations for the operation display unit 43 to the management server 2. In other words, the administrator terminal 4 can function as an operation terminal for the management server 2 by the control unit 41 executing the browser program. Note that some or all of the processing units included in the control unit 41 may be configured with electronic circuits.

[0072] For example, in the administrator terminal 4, when a user operation is performed to make an access request to a predetermined URL corresponding to a facility management service site of a facility management service provided by the inspection support system 1, the control unit 41 acquires web page data of the facility management service site from the management server 2 and causes the operation display unit 43 to display the web page of the facility management service site. Note that, for example, the access request to the predetermined URL is made by a selection operation from a list of preregistered websites, a selection operation from a search result on an information search site, or a text input operation. In addition, when a dedicated application corresponding to the management server 2 is installed in the administrator terminal 4, the administrator of the administrator terminal 4 performs an operation to start the dedicated application, and the web page of the facility management service site is displayed on the operation display unit 43.

[0073] For example, when using the equipment management service, the manager of facility B1 inputs login information (ID, password) into the login page of the equipment management service site displayed on the manager terminal 4. When the login information is authenticated, the control unit 41 causes various web pages (e.g., a setting page, an inspection result page) to be displayed on the operation display unit 43. For example, the manager registers equipment information D1, inspection level information D2, equipment inspection level information D3, etc. on the setting page.

[0074] [Inspector Terminal 5] 2, the inspector terminal 5 includes a control unit 51, a storage unit 52, an operation display unit 53, and a communication I / F 54. The inspector terminal 5 is, for example, an information processing device such as a smartphone, a tablet terminal, or a personal computer.

[0075] The communication I / F 54 is a communication interface for connecting the inspector terminal 5 to the communication network N1 via wired or wireless connection, and for performing data communication in accordance with a specified communication protocol with external devices such as the management server 2 via the communication network N1.

[0076] The operation display unit 53 is a user interface that includes a display unit such as a liquid crystal display or an organic EL display that displays information such as various web pages, and an operation unit such as a mouse, keyboard, or touch panel that accepts operations.

[0077] The storage unit 52 is a non-volatile storage unit such as an HDD, SSD, or flash memory that stores various information. For example, a control program such as a browser program is stored in the storage unit 52. Specifically, the browser program is a control program that causes the control unit 51 to execute communication processing with an external device such as the management server 2 according to a communication protocol such as HTTP. The browser program may also be a dedicated application for executing communication processing with the management server 2 according to a predetermined communication protocol.

[0078] The control unit 51 has control devices such as a CPU, a ROM, and a RAM. The CPU is a processor that executes various arithmetic processing. The ROM is a non-volatile storage unit in which control programs such as a BIOS and an OS for causing the CPU to execute various processes are stored in advance. The RAM is a volatile or non-volatile storage unit that stores various information, and is used as a temporary storage memory (work area) for various processes executed by the CPU. The control unit 51 controls the inspector terminal 5 by executing various control programs stored in advance in the ROM or the storage unit 52 by the CPU.

[0079] Specifically, the control unit 51 functions as a browser processing unit 511 by executing various processes in accordance with the browser program stored in the storage unit 52. The browser processing unit 511 is capable of executing browser processing for displaying a web page provided from the management server 2 via the communication network N1 on the operation display unit 53 and inputting operations for the operation display unit 53 to the management server 2. That is, the inspector terminal 5 can function as an operation terminal for the management server 2 by the control unit 51 executing the browser program. Note that some or all of the processing units included in the control unit 51 may be configured with electronic circuits.

[0080] For example, in the inspector terminal 5, when a user operation is performed to make an access request to a predetermined URL corresponding to a facility management service site of a facility management service provided by the inspection support system 1, the control unit 51 acquires webpage data of the facility management service site from the management server 2 and causes the operation display unit 53 to display the webpage of the facility management service site. Note that, for example, the access request to the predetermined URL is made by a selection operation from a list of preregistered websites, a selection operation from a search result on an information search site, or a text input operation. In addition, when a dedicated application corresponding to the management server 2 is installed in the inspector terminal 5, the inspector of the inspector terminal 5 performs an operation to start up the dedicated application, and the webpage of the facility management service site is displayed on the operation display unit 53.

[0081] For example, when an inspector of facility B1 uses the facility management service, he or she inputs login information (ID, password) into the login page of the facility management service site displayed on the inspector terminal 5. When the login information is authenticated, the control unit 51 causes the operation display unit 53 to display various web pages (for example, an inspection work page (see FIGS. 7 and 8)).

[0082] [Inspection support processing] Hereinafter, the inspection support process executed in the inspection support system 1 will be described with reference to Fig. 11. Specifically, in this embodiment, the control unit 21 of the management server 2 executes the inspection support process.

[0083] The present invention can be understood as an invention of an inspection support method (one example of the inspection support method of the present invention) that executes one or more steps included in the inspection support process. One or more steps included in the inspection support process described here may be omitted as appropriate. The steps in the inspection support process may be executed in a different order as long as the same action and effect is achieved. Furthermore, although an example is described here in which the control unit 21 executes each step in the inspection support process, another embodiment of the inspection support method may be one in which one or more processors execute each step in the inspection support process in a distributed manner.

[0084] First, in step S1, the control unit 21 acquires the inspection results of a predetermined piece of equipment to be inspected. For example, when an inspector A1 inspects equipment X and inputs an inspection result ("◯" or "X") (see FIG. 8), the control unit 21 acquires the inspection result. When the control unit 21 acquires the inspection result of equipment X, it registers the inspection result in the inspection history information D4 (see FIG. 6).

[0085] Next, in step S2, the control unit 21 acquires the inspection history of the equipment to be inspected. Here, the control unit 21 acquires the inspection history of the equipment X from the inspection history information D4 (see FIG. 6).

[0086] Next, in step S3, the control unit 21 determines whether the equipment to be inspected satisfies the upgrade condition. Specifically, the control unit 21 determines whether the inspection result (inspection history) of equipment X satisfies the upgrade condition (see FIG. 4) corresponding to the inspection level (see FIG. 5) set for equipment X. If the control unit 21 determines that the equipment to be inspected satisfies the upgrade condition (S3: Yes), it shifts the process to step S31. On the other hand, if the control unit 21 determines that the equipment to be inspected does not satisfy the upgrade condition (S3: No), it shifts the process to step S4.

[0087] In step S31, the control unit 21 raises the inspection level of the equipment to be inspected. For example, the control unit 21 raises the inspection level of equipment X when the inspection result (inspection history) of equipment X satisfies a level-up condition corresponding to the inspection level of equipment X. When the control unit 21 changes the inspection level of equipment X, it changes (updates) the inspection level of equipment X registered in equipment inspection level information D3 (see FIG. 5). After step S31, the control unit 21 transitions the process to step S5.

[0088] In response to this, in step S4, the control unit 21 determines whether or not the equipment to be inspected satisfies the level-downgrade condition. Specifically, the control unit 21 determines whether or not the inspection result (inspection history) of equipment X satisfies the level-downgrade condition (see FIG. 4) corresponding to the inspection level (see FIG. 5) set for equipment X. If the control unit 21 determines that the equipment to be inspected satisfies the level-downgrade condition (S4: Yes), it shifts the process to step S41. On the other hand, if the control unit 21 determines that the equipment to be inspected does not satisfy the level-downgrade condition (S4: No), it shifts the process to step S5.

[0089] In step S41, the control unit 21 lowers the inspection level of the equipment to be inspected. For example, the control unit 21 lowers the inspection level of equipment X when the inspection result (inspection history) of equipment X satisfies a level down condition corresponding to the inspection level of equipment X. When the control unit 21 changes the inspection level of equipment X, it changes (updates) the inspection level of equipment X registered in equipment inspection level information D3 (see FIG. 5). After step S41, the control unit 21 transitions the process to step S5.

[0090] In step S5, the control unit 21 judges whether or not the inspection result of the other equipment to be inspected has been acquired. When the control unit 21 acquires the inspection result of the other equipment to be inspected (S5: Yes), it shifts the process to step S2. When the control unit 21 does not acquire the inspection result of the other equipment to be inspected (S5: No), it ends the inspection support process. For example, when the inspector A1 finishes the inspection work of the equipment X and performs the next inspection work of the equipment Y and inputs the inspection result ("◯" or "X"), the control unit 21 acquires the inspection result of the equipment Y (S5: Yes) and further acquires the inspection history of the equipment Y (S2). The control unit 21 judges whether or not the level-up condition or the level-up condition is satisfied for the equipment Y (S3, S4), and executes the process of increasing the inspection level when the level-up condition is satisfied (S31), and decreasing the inspection level when the level-down condition is satisfied (S41).

[0091] The control unit 21 repeatedly executes the above-mentioned process to update the inspection level every time it obtains the inspection result of each piece of equipment to be inspected. Then, the control unit 21 executes the inspection process according to the updated inspection level (inspection schedule). The control unit 21 executes the inspection support process in the above-mentioned manner.

[0092] As described above, the inspection support system 1 of this embodiment acquires the inspection results of the inspection process for the equipment to be inspected based on the inspection schedule, and if it is determined that the inspection schedule needs to be changed based on the acquired inspection results, it changes the inspection schedule.

[0093] For example, the inspection support system 1 determines whether or not the inspection schedule needs to be changed based on the most recent inspection result for the equipment to be inspected.

[0094] Also, for example, the inspection support system 1 reduces the frequency of the inspection process for the equipment to be inspected when inspection results indicating that the equipment to be inspected is normal are obtained a predetermined number of times in succession, and increases the frequency of the inspection process for the equipment to be inspected when inspection results indicating that the equipment to be inspected is abnormal are obtained a predetermined number of times in succession.As another embodiment, the inspection support system 1 may increase the frequency of the inspection process for the equipment to be inspected when inspection results indicating that the equipment to be inspected is abnormal are obtained a predetermined number of times in succession.

[0095] According to the above configuration, the inspection schedule (inspection frequency, inspection interval) is changed according to the inspection results, so that an optimal inspection schedule can be set according to the stability of the operating state of the equipment to be inspected. For example, the inspection frequency can be lowered for equipment that is unlikely to have abnormalities and operates stably, and the inspection frequency can be increased for equipment that is likely to have abnormalities and operates unstably. This makes it possible to improve the efficiency of the inspection process for the equipment to be inspected.

[0096] The frequency of the inspection process may include a plurality of different levels (inspection levels), and a predetermined level of frequency may be set in advance for each piece of equipment to be inspected (see Figs. 4 and 5).

[0097] The predetermined number of times may be set according to the level. For example, the inspection support system 1 sets the predetermined number of times of the level-up condition for the inspection levels "1" and "2" to "5 times," and sets the predetermined number of times of the level-up condition for the inspection levels "3" and "4" to "10 times." In this way, the inspection support system 1 may set the level-up condition to be stricter as the inspection level becomes higher.

[0098] Furthermore, for example, the inspection support system 1 sets the predetermined number of times of the level downgrade condition for the inspection levels "3," "4," and "5" to "1 time," and sets the predetermined number of times of the level downgrade condition for the inspection level "2" to "2 times." In this way, the inspection support system 1 may set the level downgrade condition to be stricter as the inspection level is lower.

[0099] In another embodiment of the present invention, the predetermined number of times may be set according to the type of equipment to be inspected. For example, the inspection support system 1 may set the predetermined number of times for the level-up condition of electrical equipment to be different from the predetermined number of times for the level-up condition of air conditioning equipment. Similarly, the inspection support system 1 may set the predetermined number of times for the level-down condition of electrical equipment to be different from the predetermined number of times for the level-down condition of air conditioning equipment.

[0100] However, when equipment operates for a long period of time or is used frequently, it becomes prone to abnormalities. Therefore, as another embodiment of the present invention, the inspection support system 1 may restrict the process of changing the inspection level according to the operation period or frequency of use of the equipment to be inspected. For example, the control unit 21 (change processing unit 213) of the management server 2 prohibits the process of lowering the frequency of inspection work on the equipment to be inspected (the process of raising the inspection level) when the operation period of the equipment to be inspected is a predetermined period or longer. Also, for example, the control unit 21 (change processing unit 213) prohibits the process of lowering the frequency of inspection work on the equipment to be inspected (the process of raising the inspection level) when the frequency of use of the equipment to be inspected is a predetermined frequency or longer.

[0101] Furthermore, when the operation period of the equipment to be inspected is equal to or longer than a predetermined period or the frequency of use of the equipment to be inspected is equal to or higher than a predetermined frequency, the control unit 21 (change processing unit 213) may set the condition for lowering the frequency of inspection work for the equipment to be inspected to a number of times greater than the predetermined number. For example, for equipment to be inspected whose inspection level is set to "3", when the operation period is equal to or longer than a predetermined period or the frequency of use becomes equal to or higher than a predetermined frequency, the control unit 21 (change processing unit 213) changes the predetermined number of times (see FIG. 4) included in the level-up condition from "10 times" to "20 times". This makes it difficult to raise the inspection level (makes it difficult to lower the inspection frequency) for equipment that is prone to abnormalities. In another embodiment of the present invention, the control unit 21 (change processing unit 213) may set the predetermined number of times included in the level-up condition and the level-down condition according to the operation period or frequency of use of the equipment to be inspected. For example, the control unit 21 updates the predetermined number of times in the level-up condition to a larger value and updates the predetermined number of times in the level-down condition to a smaller value as the operation period becomes longer or the frequency of use becomes higher.

[0102] As another embodiment of the present invention, the inspection support system 1 may prohibit a process of reducing the frequency of inspection work on an inspection target facility when the facility is a specific device. For example, for important facilities that may have various effects when an abnormality occurs, the control unit 21 (change processing unit 213) prohibits a process of reducing the frequency of inspection work (a process of increasing the inspection level) even if the level-up condition is satisfied. In this way, the control unit 21 (change processing unit 213) may prohibit a process of reducing the frequency of inspection work according to the importance of the inspection target facility. Furthermore, the control unit 21 (change processing unit 213) may set the predetermined number of times included in the level-up condition and the level-down condition according to the importance of the inspection target facility (for example, the degree of impact on facility users, etc.).

[0103] As another embodiment of the present invention, when the equipment to be inspected is a specific device, the inspection support system 1 may set the condition for lowering the frequency of inspection work for the equipment to be inspected to a number of times greater than the predetermined number of times. For example, when the inspection level of important equipment is set to "3", the control unit 21 (change processing unit 213) sets the predetermined number of times (see FIG. 4) included in the level-up condition to "20 times". This makes it difficult to raise the inspection level (makes it difficult to lower the inspection frequency) for important equipment.

[0104] In another embodiment of the present invention, the inspection support system 1 may set a level-up condition and a level-down condition according to the installation environment of the equipment to be inspected. For example, the lifespan of the equipment to be inspected may be shortened when the equipment to be inspected is set in a high-temperature environment, installed in a cold environment, installed in a coastal area, etc. Therefore, the inspection support system 1 may set the predetermined number of times included in the level-up condition and the level-down condition according to the installation environment of the equipment to be inspected.

[0105] The present invention is not limited to the above-described embodiment. For example, the inspection target of the present invention is not limited to the equipment in the facility. For example, the inspection target of the present invention may be a guest room in an accommodation facility.

[0106] [Notes on the invention] The following is an outline of the invention extracted from the embodiment. Note that the configurations and processing functions described in the following supplementary notes can be selected and combined as desired.

[0107] <Appendix 1> an acquisition processing unit that acquires an inspection result of an inspection process for an inspection target based on an inspection schedule; a change processing unit that changes the inspection schedule when it is determined that the inspection schedule needs to be changed based on the inspection result acquired by the acquisition processing unit; and An inspection support system equipped with

[0108] <Appendix 2> The change processing unit determines whether or not the inspection schedule needs to be changed based on the most recent inspection result of the inspection target. Attachment 1. An inspection support system as described in claim 1.

[0109] <Appendix 3> The change processing unit: When the inspection result indicating that the inspection target is normal is obtained a predetermined number of times in succession, the frequency of the inspection process for the inspection target is reduced; increasing the frequency of the inspection process for the inspection target when the inspection result indicating that the inspection target is abnormal is obtained a predetermined number of times; 3. An inspection support system according to claim 1 or 2.

[0110] <Appendix 4> The frequency of the inspection process includes a plurality of different levels; A predetermined level of frequency is preset for each inspection object. Attachment 3: An inspection support system.

[0111] <Appendix 5> The predetermined number of times is set according to the level. Attachment 4: An inspection support system.

[0112] <Appendix 6> The predetermined number of times is set according to the type of the inspection target. 6. An inspection support system according to claim 4 or 5.

[0113] <Appendix 7> The change processing unit prohibits a process of reducing the frequency of the inspection work for the inspection target when the operation period of the inspection target is a predetermined period or more or the use frequency of the inspection target is a predetermined frequency or more. An inspection support system according to any one of appendix 3 to 6.

[0114] <Appendix 8> The change processing unit sets a condition for reducing the frequency of the inspection work on the inspection target to a number of times greater than the predetermined number of times when the operation period of the inspection target is a predetermined period or more or the frequency of use of the inspection target is a predetermined frequency or more. An inspection support system according to any one of appendix 3 to 7.

[0115] <Appendix 9> The change processing unit prohibits a process of reducing a frequency of an inspection operation for the inspection target when the inspection target is a specific device. An inspection support system according to any one of appendix 3 to 8.

[0116] <Appendix 10> the change processing unit sets a condition for reducing the frequency of the inspection work for the inspection target to a number of times greater than the predetermined number of times when the inspection target is a specific device. An inspection support system according to any one of appendix 3 to 9. [Explanation of symbols]

[0117] 1: Inspection support system 2: Management Server 3: Equipment monitoring device 4: Administrator terminal 5: Inspector terminal 211: Inspection processing section 212: Acquisition processing unit 213: Change processing section 411: Browser processing unit 511: Browser processing section D1: Equipment information D2: Inspection level information D3: Equipment inspection level information D4: Inspection history information

Claims

1. an acquisition processing unit that acquires an inspection result of an inspection process for an inspection target based on an inspection schedule; a change processing unit that changes the inspection schedule when it is determined that the inspection schedule needs to be changed based on the inspection result acquired by the acquisition processing unit; and An inspection support system equipped with

2. The change processing unit determines whether or not the inspection schedule needs to be changed based on the most recent inspection result of the inspection target. The inspection support system according to claim 1 .

3. The change processing unit: When the inspection result indicating that the inspection target is normal is obtained a predetermined number of times in succession, the frequency of the inspection process for the inspection target is reduced; increasing the frequency of the inspection process for the inspection target when the inspection result indicating that the inspection target is abnormal is obtained a predetermined number of times; The inspection support system according to claim 2 .

4. The frequency of the inspection process includes a plurality of different levels; A predetermined level of frequency is preset for each inspection object. The inspection support system according to claim 3.

5. The predetermined number of times is set according to the level. The inspection support system according to claim 4.

6. The predetermined number of times is set according to the type of the inspection target. The inspection support system according to claim 4.

7. The change processing unit prohibits a process of reducing the frequency of the inspection work for the inspection target when the operation period of the inspection target is a predetermined period or more or the use frequency of the inspection target is a predetermined frequency or more. The inspection support system according to any one of claims 3 to 6.

8. The change processing unit sets a condition for reducing the frequency of the inspection work on the inspection target to a number of times greater than the predetermined number of times when the operation period of the inspection target is a predetermined period or more or the frequency of use of the inspection target is a predetermined frequency or more. The inspection support system according to any one of claims 3 to 6.

9. The change processing unit prohibits a process of reducing a frequency of an inspection operation for the inspection target when the inspection target is a specific device. The inspection support system according to any one of claims 3 to 6.

10. the change processing unit sets a condition for reducing the frequency of the inspection work for the inspection target to a number of times greater than the predetermined number of times when the inspection target is a specific device. The inspection support system according to any one of claims 3 to 6.

11. Obtaining an inspection result of an inspection process for an inspection target based on an inspection schedule; When it is determined that the inspection schedule needs to be changed based on the inspection result, changing the inspection schedule; and The inspection support method is executed by one or more processors.

12. Obtaining an inspection result of an inspection process for an inspection target based on an inspection schedule; When it is determined that the inspection schedule needs to be changed based on the inspection result, changing the inspection schedule; and An inspection support program for executing the above on one or more processors.

Citation Information

Patent Citations

  • Facility periodic inspection support system using risk assessment

    JP2013088828A

  • Inspection support method and inspection support system

    JP2017071972A

  • Planning device, planning method, and planning program

    WO2020075767A1

  • Maintenance / inspection method for facility unit and maintenance / inspection period managing method

    JP2001084295A