Inspection plan support method and inspection plan support apparatus

The inspection plan support method addresses coordination challenges by evaluating combined work periods and times to prevent overlaps, enhancing efficiency and reducing planning time in nuclear power plant inspections.

JP2024159000APending Publication Date: 2024-11-08HITACHI GE NUCLEAR ENERGY LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
JP2023074703
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-04-28
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

Existing inspection planning methods for nuclear power plants fail to efficiently coordinate inspection work among multiple contractors, leading to potential overlaps and inefficiencies that require time-consuming adjustments, or result in extended inspection periods and reduced plant operating rates.

Method used

An inspection plan support method that evaluates potential interferences between upper and lower processes by calculating combined work periods and total required times, using determination formulas to assess feasibility without detailed constraint considerations.

Benefits of technology

Facilitates easy determination of inspection operation interferences, reducing planning time and enabling efficient coordination among contractors, thereby improving plant operating rates.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024159000000001_ABST
    Figure 2024159000000001_ABST
Patent Text Reader

Abstract

To provide an inspection plan support method and an inspection plan support apparatus which can easily determine whether or not inspection works of an actual process are interfered with each other.SOLUTION: The present invention is directed to an inspection plan support method of evaluating interference by a lower process between one upper process of the upper processes formed of a plurality of lower processes and another upper process. The method includes the steps of: calculating a combined work period from start to end of combined upper processes with respect to the combination of upper processes having the possibility that work periods are partially overlapped and interfere with each other; calculating a total required time as a sum of required times of lower processes belonging to the respective upper processes and relating to interference items; and determining establishment property of the lower process in response to whether or not the combined work time and the total required time satisfy a predetermined determination equation.SELECTED DRAWING: Figure 2
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to an inspection plan support method and an inspection plan support device. [Background technology]

[0002] During regular inspections of nuclear power plants, a huge number of pieces of equipment must be inspected, so the inspection work for each piece of equipment is often shared among multiple contractors. When planning regular inspections, the contractor commissioned to carry out the inspection work creates a rough process (standard process) for the inspection work of each piece of equipment, and the contractor who will carry out the inspection work creates a detailed process (actual process) for carrying out the inspection work in accordance with the standard process.

[0003] The actual process is created taking into consideration the precise constraints of each piece of equipment, but it does not take into account the constraints of equipment handled by other contractors. As a result, the inspection work of one contractor may interfere with the inspection work of another contractor, preventing one contractor from carrying out their inspection work according to the actual process.

[0004] In order to avoid interference between inspection work, it is necessary to simultaneously consider the detailed constraints held by multiple contractors and adjust the actual process, which takes time. Alternatively, a standard process could be created that allows for a leeway in the number of days for inspection work in advance so that adjustments between the actual processes of multiple contractors are not necessary. However, in this case, the number of days for regular inspections would be extended, reducing the availability rate of the nuclear power plant.

[0005] Patent Document 1 discloses a conflicting work adjustment device and a conflicting work adjustment method that can determine whether there is conflicting work and, if it is determined that there is conflict, adjust the work data to resolve the conflict. In detail, it is described as "a conflicting work adjustment device that adjusts the conflict of work performed in a maintenance section of a railway line, and includes a work content database in which work content types and conflicting object types are defined, a priority database in which a priority order is defined for performing work with higher importance first, a conflict determination unit that determines whether the dates and locations of work match based on distance data and work plan data, and a work schedule adjustment unit that, when a work determined to match the dates and locations based on the conflicting object types conflicts with another work, refers to the priority database and determines the work schedule of the work with higher priority first." [Prior art documents] [Patent documents]

[0006] [Patent Document 1] JP 2011-022909 A Summary of the Invention [Problem to be solved by the invention]

[0007] In the technology disclosed in Patent Document 1, when resolving a conflict between tasks, the date of one of the tasks is changed, which means that the task may again conflict with another task, requiring multiple conflict adjustments, which is time-consuming.

[0008] An object of the present invention is to provide an inspection planning support method and an inspection planning support device that can easily determine whether inspection work in an actual process will not interfere with each other (whether the actual process is viable) without taking into account detailed constraints. [Means for solving the problem]

[0009] In order to solve the above-mentioned problems, the inspection planning support method of the present invention is an inspection planning support method for evaluating interference between lower processes between one upper process and another upper process in an upper process consisting of a plurality of lower processes, and includes the steps of: for a combination of upper processes whose work periods overlap and may cause interference, calculating a combined work period from the start to the end of the combined upper processes; calculating a total required time which is the sum of the required times of lower processes belonging to each upper process and related to the interfering items; and judging the feasibility of the lower processes depending on whether the combined work period and the total required time satisfy a predetermined judgment formula. Effect of the Invention

[0010] According to the present invention, it is possible to easily determine whether inspection work in an actual process does not interfere with each other (whether the actual process is viable) without considering detailed constraints. This makes it unnecessary to coordinate the actual process with other contractors, and it is possible to shorten the time required to plan regular inspections. Alternatively, if a standard process that allows for a leeway in the number of days for inspection work has been created in advance, it is possible to adopt a standard process with an appropriate number of days, thereby improving the operating rate of the plant. [Brief description of the drawings]

[0011] [Figure 1] 1 is a diagram illustrating a configuration of an inspection plan support device according to an embodiment. [Diagram 2] 4 is a flowchart illustrating an operation of the inspection plan supporting device. [Diagram 3] FIG. 1 is a diagram showing an example of a higher-level process. [Figure 4] 13 is another flowchart illustrating the operation of the inspection plan supporting device. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0012] Hereinafter, an embodiment of the present invention will be described in detail with reference to the drawings. In the following explanation, the items that cause interference with the inspection work are called interference items, the rough process (standard process) for the inspection work of the equipment created by the contractor requesting the inspection work is called the upper process, and the detailed process (actual process) for carrying out the inspection work according to the standard process created by the contractor contracted to carry out the inspection work is called the lower process.The case where the interference of the inspection work can be avoided is called the lower process being established. EXAMPLES

[0013] In this embodiment, one tool A is set as an interference item, and the feasibility of a lower process related to the tool A is judged. FIG. 1 is a diagram showing a configuration of an inspection plan support device 100 according to an embodiment.

[0014] The input unit 110 is a keyboard and mouse for inputting past periodic inspection results, safety regulations, current periodic inspection information, and the like. The control unit 120 includes a target range selection unit 121 , a period calculation unit 122 , and a feasibility determination unit 123 .

[0015] The target range selection unit 121 selects a combination of upper processes that are related to the interfering item selected by the user and have a part of an overlapping work period (period from start date and time to end date and time). For the combination of upper-level processes selected by the target range selection unit 121, the period calculation unit 122 calculates the combined work period from the start to the end of the combined upper-level processes and the total required time, which is the sum of the required times of the lower-level processes related to the interfering items belonging to each upper-level process. The feasibility determination unit 123 determines the feasibility of the lower process based on the combined task period calculated by the period calculation unit 122 and the total required time of the lower process related to the interfering item.

[0016] The recording unit 130 stores the information input from the input unit 110 and the results of calculations performed in the process of the target range selection unit 121, the period calculation unit 122, and the feasibility determination unit 123. The output unit 140 displays the results obtained by the control unit 120 .

[0017] In the above, the inspection plan support device 100 is shown to have a configuration including the input unit 110 and the output unit 140, but a communication unit may be provided instead of the input unit 110 and the output unit 140. In this case, the inspection plan support device 100 acquires past regular inspection results, safety regulations, current regular inspection information, etc. inputted in another control terminal via the communication unit. Also, the inspection plan support device 100 notifies the other control terminal of the results obtained in the control unit 120 via the communication unit and displays them on the control terminal.

[0018] More specifically, the inspection plan support device 100 is realized by a computer (information processing device) equipped with a processor, a storage unit, a communication I / F, and an input / output unit. The target range selection unit 121, the period calculation unit 122, and the feasibility determination unit 123 of the control unit 120 are realized by the processor executing a program in the storage unit.

[0019] Next, the operation of the inspection plan supporting device 100 will be described with reference to the flowchart of FIG.

[0020] In step S200, the input unit 110 acquires data such as past regular inspection results, safety regulations, the work period of the upper process to be performed in the current regular inspection, and daily operating hours, and records the acquired data in the recording unit 130. For example, the daily operating hours are assumed to be 6 hours.

[0021] In step S201, when a tool A is input to the input unit 110 as an interfering item, the inspection plan support device 100 selects the tool A as the interfering item and records the tool A selected as the interfering item in the recording unit 130. The selection of the interfering item may be performed by a user, or may be selected in another system and notified to the input unit 110.

[0022] In step S202, the target range selection unit 121 extracts combinations of upper processes that may have interference. In detail, by referring to the recording unit 130 that the interference item is tool A, the target range selection unit 121 extracts upper processes that may have interference with the use of tool A from all combinations of upper processes including lower processes that use tool A.

[0023] More specifically, as shown in the Gantt chart of an example 300 of upper level processes in Fig. 3, a first upper level process planned to be performed from April 29 to May 3 and a second upper level process planned to be performed from May 1 to May 4, which have overlapping work periods (May 1 to May 3), are extracted as a combination of upper level processes that may interfere. Although not shown in the figure, each of the first and second upper level processes includes at least one lower level process that uses at least tool A.

[0024] In step S203, the target range selection unit 121 judges whether or not there is at least one combination of upper processes that may interfere in step S202. If the first and second upper processes are extracted as upper processes that may interfere as shown in Fig. 3 (Y in S203), the process proceeds to step S204, and if there is no combination of upper processes that may interfere (N in S203), the process proceeds to step S208.

[0025] In step S204, the period calculation unit 122 calculates, for a combination of a first upper level process and a second upper level process extracted in step S202 as having the possibility of interference, a combined work period from the start to the end of the combined upper level processes, and a total required time which is the sum of the required times of the lower level processes related to the interfering items belonging to each upper level process.

[0026] More specifically, as shown in Figure 3, in the combination of the first upper process and the second upper process, the earliest start date is April 29th and the latest end date is May 4th, so the combined work period T during which the first upper process and the second upper process can use tool A is calculated to be 36 hours (= 6 days × 6 hours / day).

[0027] On the other hand, if it is determined from the past regular inspection results recorded in the recording unit 130 that the required time T1A for a lower-level process using tool A in the first higher-level process is 20 hours, and the required time T2A for a lower-level process using tool A in the second higher-level process is 10 hours, then the total required time TA for using tool A in the first and second higher-level processes is calculated to be 30 hours (=T1A+T2A=20+10 hours).

[0028] In step S205, for each combination of upper processes extracted in step S202 as having the possibility of interference, the feasibility determination unit 123 evaluates a determination formula based on the combination work period calculated in step S204 and the total required time of the lower processes related to the interfering item, and determines the feasibility of the lower processes.

[0029] For example, as shown in equation (1), when the combined work period T during which the first upper-level process and the second upper-level process can use tool A is greater than the total time TA required for using tool A in the first upper-level process and the second upper-level process, the lower-level process that uses tool A can be adjusted to avoid interference between the first upper-level process and the second upper-level process without delaying the processes, and therefore the lower-level process is determined to be valid. T > TA ……(1)

[0030] In step S206, the feasibility determination unit 123 determines whether the determination formula is satisfied for all combinations of upper process combinations extracted in step S202 as having the possibility of interference. If the determination formula is satisfied for all combinations (Y in S206), the process proceeds to step S208, and if the determination formula is not satisfied for at least one combination of upper process (N in S206), the process proceeds to step S207.

[0031] In step S207, the output unit 140 notifies the user that the lower process for tool A is not established, and the process ends. In step S208, the output unit 140 notifies the user that the sub-process is established for the tool A, and the process ends.

[0032] The judgment formula in step S205 may be formula (2) using a delay coefficient α that takes into account any time delay that occurs when tool A is used interchangeably between the first upper process and the second upper process, or formula (3) using a delay time Td. αT > TA ……(2) T-Td > TA ……(3)

[0033] The determination formula to be used among formulas (1) to (3) may be manually set by the user depending on the interference item, or an appropriate determination formula may be automatically set by the feasibility determination unit 123 of the control unit 120. As a method for automatically setting the determination formula, the feasibility determination unit 123 may calculate the formula based on past periodic inspection results, or may reflect an estimated result through machine learning.

[0034] In this embodiment, the example in which the interfering item is the tool A has been described, but the interfering item may be a piece of equipment used in the inspection work. Also, the interfering item may be a work crew performing the inspection work, a work area in which the inspection work is performed, or a protected area in which work is performed based on the safety regulations for fire load. Other embodiments will be described in detail below. EXAMPLES

[0035] In this embodiment, the flowchart in Figure 2 is used to explain an example in which work team B, one of two teams performing inspection work, is treated as an interfering item and the feasibility of a sub-process related to work team B is judged, that is, an example of judging whether or not a sub-process can be carried out by work team B, one of two teams.

[0036] In step S200, the input unit 110 acquires the work period of the first higher-level process as from 9:00 on May 2nd to 16:00 on May 5th, the work period of the second higher-level process as from 9:00 on May 3rd to 16:00 on May 4th, and the daily operating hours as 6 hours, and records these in the recording unit 130. In step S201, when work crew B is input to the input unit 110 as an interfering item, the inspection plan supporting device 100 selects work crew B as the interfering item.

[0037] In step S202, the target range selection unit 121 selects the combination of the first and second upper order processes as a combination of upper order processes that may interfere with each other, since their work periods overlap from 9:00 on May 3rd to 16:00 on May 4th. In step S203, since there is a combination of upper processes that may cause interference, the target range selection unit 121 proceeds to step S204.

[0038] In step S204, the period calculation unit 122 calculates, for a combination of a first upper level process and a second upper level process, a combined work period from the start to the end of the combined upper level processes, and a total required time which is the sum of the required times of lower level processes related to interfering items belonging to each upper level process.

[0039] Specifically, for the combination of the first upper process and the second upper process, the earliest start date and time is 9:00 on May 2nd, and the latest end date and time is 16:00 on May 5th. In addition, because there are two work crews B, the combined work period T in which work crew B can inspect the first upper process and the second upper process is 48 hours (= (6 + 6 + 6 + 6) hours × 2 crews).

[0040] In addition, if there are 8 sub-processes in the first higher-level process that are handled by the work team B out of a total of 11 sub-processes in the first higher-level process, the work time of the first higher-level process is 24 hours, and the required time T1B of the sub-processes in the first process that are handled by the work team B is 17.5 hours (=24 hours×8÷11). If there are 7 sub-processes in the second higher-level process that are handled by the work team B out of a total of 8 sub-processes in the second higher-level process, the work time of the second higher-level process is 12 hours, and the required time T2B of the sub-processes in the second process that are handled by the work team B is 10.5 hours (=12 hours×7÷8). Therefore, the period calculation unit 122 calculates the total required time TB of the sub-processes in the first higher-level process and the second higher-level process that are handled by the work team B to be 28 hours (=T1B+T2B=17.5+10.5 hours).

[0041] In step S205, the feasibility judgment unit 123 evaluates that the combined work period T that work team B can inspect in the first higher-level process and the second higher-level process is 48 hours, and the total required time TB of the lower-level processes handled by work team B in the first higher-level process and the second higher-level process is 28 hours, which satisfies formula (1).

[0042] In step S206, the validity determination unit 123 determines that the determination formula is satisfied, and therefore the process proceeds to step S208.

[0043] In step S208, the output unit 140 notifies the user that the sub-process is completed for work group B, and the process ends. EXAMPLES

[0044] In this embodiment, the work area C is treated as an interference item, and an example of determining the feasibility of a lower-level process related to the work area C, that is, an example of determining whether or not a lower-level process can be carried out due to overlapping use of the work area C, is explained using the flowchart in Figure 2.

[0045] In step S200, the input unit 110 obtains the work period of the first higher-level process as from 9:00 on April 29th to 16:00 on May 3rd, the work period of the second higher-level process as from 9:00 on May 1st to 16:00 on May 4th, and the work period of the third higher-level process as from 9:00 on May 2nd to 16:00, with the daily operating hours being 6 hours, and records these in the recording unit 130. In step S201, when a work area C is input to the input unit 110 as an interfering item, the inspection plan supporting device 100 selects the work area C as an interfering item.

[0046] In step S202, the target range selection unit 121 selects the combination of the first upper order process, the second upper order process, and the third upper order process as a combination of upper order processes that may interfere with each other, since the work periods from 9:00 to 16:00 on May 2nd overlap. In step S203, since there is a combination of upper processes that may cause interference, the target range selection unit 121 proceeds to step S204.

[0047] In step S204, the period calculation unit 122 calculates, for a combination of a first upper level process, a second upper level process, and a third upper level process, a combined work period from the start to the end of the combined upper level processes, and a total required time which is the sum of the required times of the lower level processes related to the interfering items belonging to each upper level process.

[0048] Specifically, for the combination of the first upper process, the second upper process, and the third upper process, the earliest start date and time is 9:00 on April 29th, and the latest end date and time is 16:00 on May 4th. For the first upper process, the second upper process, and the third upper process, the combined work period T during which work area C can be used is 36 hours (= 6 days × 6 hours / day).

[0049] In addition, in the past regular inspection results recorded in the recording unit 130, if the required time T1C of the lower process to be performed in work area C of the first higher-level process is 20 hours, the required time T2C of the lower process to be performed in work area C of the second higher-level process is 12 hours, and the required time T3C of the lower process to be performed in work area C of the third higher-level process is 6 hours, the period calculation unit 122 calculates the total required time TC of the lower processes performed in work area C to be 38 hours (=T1C+T2C+T3C=20+12+6 hours).

[0050] In step S205, the feasibility judgment unit 123 evaluates that the combined work period T in which work area C can be used in the first upper-level process, the second upper-level process, and the third upper-level process is 36 hours, and the total required time TC of the lower-level processes to be performed in work area C is 38 hours, which does not satisfy formula (1).

[0051] In step S206, since the validation determination unit 123 determines that the determination formula is not satisfied, the process proceeds to step S207.

[0052] In step S207, the output unit 140 notifies the user that the sub-process for the work area C has not been established, and the process ends. EXAMPLES

[0053] In this embodiment, the flowchart in Figure 4 explains an example of determining whether a sub-process can be carried out based on whether the fire load in the protected area D satisfies the safety regulations, with the protected area D being treated as an interfering item.

[0054] The flowchart in FIG. 4 is obtained by adding the processing of fire loads in steps S501, S502, and S503 to the flow in FIG. 2, and steps S200 to S208 are the same as those in FIG.

[0055] In step S200, the input unit 110 obtains the work period of the first higher-level process as from 9:00 on April 29th to 16:00 on May 3rd, the work period of the second higher-level process as from 9:00 on May 1st to 16:00 on May 4th, and the work period of the third higher-level process as from 9:00 on May 2nd to 16:00, with the daily operating hours being 6 hours, and records these in the recording unit 130.

[0056] In step S201, when the protection area D is input to the input unit 110 as an interfering item, the inspection plan supporting device 100 selects the protection area D as the interfering item.

[0057] In step S202, the target range selection unit 121 selects the combination of the first and second upper order processes as a combination of upper order processes that may interfere with each other, since the work periods from 9:00 on May 1st to 16:00 on May 3rd overlap.

[0058] In step S203, since there is a combination of upper processes that may cause interference, the target range selection unit 121 proceeds to step S501.

[0059] In step S501, the feasibility determination unit 123 calculates the total fire load in the protected area D for each combination of higher-level processes from the past periodic inspection results recorded in the recording unit 130. Specifically, if the total fire load W1D brought in by the work of the lower-level processes carried out in the protected area D in the first higher-level process is obtained as 20 GJ, and the total fire load W2D brought in by the work of the lower-level processes carried out in the protected area D in the second higher-level process is obtained as 10 GJ, the total fire load WD brought in the protected area D is calculated as 30 GJ (=W1D+W2D=20+10 GJ).

[0060] In step S502, it is determined whether the total fire load in the protected area D satisfies the safety regulations. In detail, as shown in formula (4), the maximum value of the fire load in the protected area D in the safety regulations is W, and if the total amount of fire load WD brought in the first upper process and the second upper process in the protected area D is smaller than the maximum value W, it is determined that the fire load in the first upper process and the second upper process in the protected area D satisfies the safety regulations (does not violate the safety regulations). WD < W ……(4)

[0061] Then, in step S502, if the total amount of fire load in the protected area D satisfies the safety regulations (Y in S502), proceed to step S208, and if the total amount of fire load in the protected area D does not satisfy the safety regulations (N in S502), proceed to step S204. Specifically, when the maximum fire load W that can be brought into the protected area D is referred to as 20 GJ from the information on the safety regulations recorded in the recording unit 130, the total amount of fire load WD of 30 GJ does not satisfy formula (4), so proceed to step S204.

[0062] In step S204, the period calculation unit 122 calculates, for a combination of a first upper level process and a second upper level process extracted in step S202 as having the possibility of interference, a combined work period from the start to the end of the combined upper level processes, and a total required time which is the sum of the required times of the lower level processes related to the interfering items belonging to each upper level process.

[0063] More specifically, as shown in Figure 3, the earliest start date for the combination of the first upper-level process and the second upper-level process is April 29th and the latest end date is May 4th, so the combined work period T during which the first upper-level process and the second upper-level process can bring fire load into the protected area D is calculated to be 36 hours (= 6 days × 6 hours / day).

[0064] On the other hand, if it is determined from the past regular inspection results recorded in the recording unit 130 that the required time T1D for the lower-level process performed within the protected area D in the first upper-level process is 20 hours, and the required time T2D for the lower-level process performed within the protected area D in the second upper-level process is 10 hours, the total required time TD for the lower-level processes performed within the protected area D in the first and second upper-level processes is calculated to be 30 hours (=T1A+T2A=20+10 hours).

[0065] In step S205, the feasibility determination unit 123 evaluates that the combined work period T for the first upper process and the second upper process that can bring a fire load into the protected area D is 36 hours, and the total required time TD of the lower process performed in the protected area D is 30 hours, which satisfies formula (1). Note that the total required time TA for using tool A in the upper process in formula (1) is replaced with the total required time TD of the lower process performed in the protected area D.

[0066] In step S206, when the combined task period T is 36 hours and the total required time TD is 30 hours, the feasibility determination unit 123 determines that the formula (1) is satisfied (Y in S206), and proceeds to step S503. If the formula is not satisfied (N in S206), the feasibility determination unit 123 proceeds to step S207.

[0067] In step S503, the feasibility determination unit 123 notifies the contractor for the inspection work to prepare detailed processes by adjusting the total amount of fire load so that the total amount of fire load satisfies the safety regulations when preparing lower processes (actual processes) to be performed in the protected area D for the first upper process and the second upper process. Then, the feasibility determination unit 123 proceeds to step S208.

[0068] In step S207, the output unit 140 notifies the user that the sub-step regarding the fire load in the protection section D is not established, and the process ends. In step S208, the output unit 140 notifies the user that the sub-step is established with respect to the fire load in the protected section D, and the process ends.

[0069] Furthermore, the present invention is not limited to the above-mentioned examples, and various modified examples are included. The above-mentioned examples have been described in detail to easily explain the present invention, and the present invention is not necessarily limited to those having all of the configurations described. Furthermore, it is possible to replace a part of the configuration of one embodiment with the configuration of another embodiment, and it is also possible to add the configuration of another embodiment to the configuration of one embodiment. [Explanation of symbols]

[0070] 100 Inspection planning support device 110 Input section 120 Control section 121 Target Scope Selection Division 122 Period Calculation Department 123 Validity determination part 130 Recording Section 140 Output section

Claims

1. 1. An inspection planning support method for evaluating interference between a lower-level process and another upper-level process in an upper-level process that is composed of a plurality of lower-level processes, comprising: A step of calculating a combined work period from the start to the end of a combination of upper processes, the combined work periods of which partially overlap and may interfere with each other; A step of calculating a total required time which is a sum of the required times of lower processes which belong to each higher process and are related to the interfering item; determining whether the sub-process is viable based on whether the combined task period and the total required time satisfy a predetermined determination formula; An inspection plan support method comprising:

2. The inspection plan support method according to claim 1, selecting an interfering item; A step of extracting combinations of upper-level processes that may interfere with each other; determining that the lower process is established when there is no combination of upper processes that may interfere with each other; a step of calculating the combined operation period and the total required time for the upper processes which may interfere with each other when there is a combination of upper processes which may interfere with each other, and judging the feasibility of the lower process depending on whether or not the combined operation period and the total required time satisfy a predetermined judgment formula; An inspection plan support method comprising:

3. The inspection plan support method according to claim 2, The interference item is any one of a tool used in the inspection work, equipment used in the inspection work, a work crew performing the inspection work, or a work area performing the inspection work. The inspection plan support method according to the present invention is characterized in that:

4. The inspection plan support method according to claim 2, A step of calculating a total amount of fire load in a combination of upper processes when a protection section in which work is performed based on a safety provision for fire load is selected for the interference item; a step of calculating the combined work period and the total required time for the upper processes which may interfere with each other when there is a combination of upper processes which may interfere with each other and the total amount of the fire load does not satisfy the safety regulations, determining whether or not the combined work period and the total required time satisfy a predetermined judgment formula, and adjusting the total amount of the fire load for the lower processes when the judgment formula is satisfied; An inspection plan support method comprising:

5. a target range selection unit that selects a combination of upper processes that are related to the interfering item and have a part of an overlapping work period; a period calculation unit that calculates a combined work period from the start to the end of the combined upper process for the combination of upper processes selected by the target range selection unit, and a total required time that is the sum of the required times of lower processes related to interference items belonging to each upper process; a feasibility determination unit that determines feasibility of a sub-process based on the combined work period and the total required time; An inspection plan support device comprising:

6. 6. The inspection planning support device according to claim 5, The feasibility determination unit determines feasibility of a sub-process depending on whether the combined task period and the total required time satisfy a predetermined determination formula. An inspection planning support device characterized by:

7. 6. The inspection planning support device according to claim 5, The target range selection unit is configured to select any one of a tool used in the inspection work, equipment used in the inspection work, a work crew performing the inspection work, or a work area performing the inspection work as an interference item. An inspection planning support device characterized by:

8. 6. The inspection planning support device according to claim 5, When a protected area is selected for the interference item based on the fire load safety regulations, The target range selection unit is The interference item is the protected area where work is carried out based on the fire load safety regulations, The feasibility determination unit is Calculate the total fire load for the combination of upper processes, When there is a combination of upper processes that may interfere with each other and the total amount of fire load does not satisfy the safety regulations, it is determined whether or not the combined work period and the total required time satisfy a predetermined determination formula; If the judgment formula is satisfied, the total fire load of the lower process is adjusted. An inspection planning support device characterized by: