Ground structure estimation method

By leveraging vibration measuring devices at construction sites to collect and analyze microtremor data, the method simplifies ground structure estimation, overcoming installation complexities and noise issues, achieving accurate and efficient ground characterization.

JP2024161805AInactive Publication Date: 2024-11-20OHBAYASHI GUMI LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
JP2023076851
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-05-08
Publication Date
2024-11-20
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The installation of vibration measuring devices to estimate ground structure is complex due to the need for permissions and fees on public or private land, and the challenge of obtaining noise-free data is exacerbated by limited installation times, especially when multiple observation points are required.

Method used

A method that utilizes vibration measuring devices installed at construction sites to collect and centrally manage measurement data, allowing for flexible installation times and locations, and employs microtremor array exploration and H/V spectrum analysis to estimate ground structure without the need for additional permissions or fees, using existing construction site equipment.

Benefits of technology

Facilitates the estimation of ground structure by simplifying the installation process, enabling accurate data collection over extended periods, reducing noise interference, and allowing for high-accuracy estimation of ground characteristics using data from multiple sites.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024161805000001_ABST
    Figure 2024161805000001_ABST
Patent Text Reader

Abstract

To facilitate work for estimating a ground structure on the basis of vibration data at multiple observation points.SOLUTION: A ground structure estimation method is provided, comprising: acquiring measurement data of vibration measurement devices at multiple construction sites, each being provided with one or more vibration measurement devices; and estimating ground structures of target sites, which may be at least either of the construction sites and land other than the construction sites, on the basis of the measurement data respectively measured at the multiple construction sites.SELECTED DRAWING: Figure 3
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a method for estimating a subsurface structure. [Background technology]

[0002] There is a demand for investigating the ground structure at the site in civil engineering and construction. The surface of the Earth is always shaking slightly even when there is no earthquake, and microtremors (weak vibrations) are generated. A method has been proposed to estimate the ground structure by measuring these microtremors. For example, surface waves have the property of dispersion, where the phase velocity changes depending on the frequency. Therefore, Patent Document 1 discloses a method of extracting surface waves from microtremors observed by multiple vibration observation instruments placed at the center of an imaginary circle and at equal intervals around the circumference of the imaginary circle, determining the dispersion curve of the surface waves, and finally analyzing the S-wave velocity of each layer and the corresponding layer, thereby estimating the underground structure (ground structure) at the observation point. [Prior art documents] [Patent documents]

[0003] [Patent Document 1] Japanese Patent Application Publication No. 11-287865 Summary of the Invention [Problem to be solved by the invention]

[0004] However, when installing a vibration measuring instrument that measures microtremors on public land such as a road in order to estimate the ground structure, it is necessary to apply for a usage procedure, and when installing on private land, it is necessary to obtain permission from the owner and pay a usage fee. In addition, in order to obtain data with less noise, the installation time of the instrument may be limited, such as installing the instrument at night. Thus, installing a vibration measuring instrument is a difficult task. Therefore, when estimating the ground structure based on data from multiple observation points as in Patent Document 1, the work becomes even more complicated.

[0005] The present invention has been made in consideration of the above-mentioned problems, and an object of the present invention is to facilitate the task of estimating ground structure based on vibration data from multiple observation points. [Means for solving the problem]

[0006] The main invention for achieving the above-mentioned object is a ground structure estimation method characterized by comprising the steps of: acquiring measurement data from vibration measuring devices at multiple construction sites, each of which has one or more vibration measuring devices installed; and estimating the ground structure of a target land, which is at least one of the construction site and land other than the construction site, based on the measurement data measured at each of the multiple construction sites.

[0007] Other features of the present invention will become apparent from the following detailed description of the present invention and the accompanying drawings. Effect of the Invention

[0008] According to the present invention, it is possible to facilitate the task of estimating ground structure based on vibration data from a plurality of observation points. [Brief description of the drawings]

[0009] [Figure 1] This is a diagram showing an example of a target area pt for estimating the ground structure and multiple construction sites pc. [Diagram 2] FIG. 1 is an explanatory diagram of a vibration measuring device 10 installed at a construction site PC. [Diagram 3] FIG. 2 is a flow diagram of a ground structure estimation method in the first embodiment. [Figure 4] FIG. 1 is a block diagram showing a measurement data collection system. [Diagram 5] FIG. 1 is a schematic diagram for explaining the measurement results of shaking (vibration) in each direction. [Figure 6] 6A to 6D are explanatory diagrams of a method for estimating ground structure using the microtremor array exploration method. [Figure 7] 7A to 7D are explanatory diagrams of a ground structure estimation method based on the H / V spectrum. [Figure 8] FIG. 11 is a flow diagram of a ground structure estimation method in a second embodiment. [Figure 9] FIG. 11 is a flow diagram of a ground structure estimation method in the third embodiment. [Figure 10] FIG. 13 is a diagram showing a ground structure estimation method in a fourth embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0010] At least the following points will become apparent from the description of this specification and the accompanying drawings. (Aspect 1) A ground structure estimation method comprising the steps of: acquiring measurement data from vibration measuring devices at a plurality of construction sites, each of which has one or more vibration measuring devices installed; and estimating the ground structure of a target site, which is at least one of the construction sites and land other than the construction sites, based on the measurement data measured at each of the construction sites.

[0011] According to the first aspect, it is possible to eliminate the need for procedures such as application procedures for installing a vibration measuring instrument on public or private land. Furthermore, at a construction site, there is a high degree of freedom in the time required for installing the vibration measuring instrument. This makes it possible to facilitate the work of estimating the ground structure. Furthermore, since there are many construction sites, there are many options for construction sites from which measurement data can be obtained, making it easy to select a construction site for estimating the ground structure.

[0012] (Aspect 2) The ground structure estimation method according to aspect 1, The method is characterized in that the measurement data measured at a specific time at each of the multiple construction sites is acquired, dispersion characteristics indicating the phase velocity at each frequency are calculated from the acquired measurement data, and the relationship between the ground depth and shear wave velocity of the target site is estimated based on the dispersion characteristics.

[0013] According to the second aspect, the ground structure of the target site can be estimated. Furthermore, the ground structure is estimated based on data from multiple observation points, but the work of estimating the ground structure can be simplified by using measurement data from vibration measuring instruments installed at the construction site. Furthermore, since vibration measuring instruments can be easily installed at construction sites for long periods of time, it is easy to collect measurement data at specific times from multiple construction sites.

[0014] (Aspect 3) The ground structure estimation method according to aspect 2, The measurement data includes horizontal vibration data and vertical vibration data, and an H / V spectrum is calculated by dividing the horizontal spectrum obtained from the horizontal vibration data by the vertical spectrum obtained from the vertical vibration data, and the relationship between the ground depth and shear wave velocity of the target site is estimated based on the H / V spectrum.

[0015] According to the third aspect, the ground structure of the target area can be estimated. In addition, since the ground structure based on the dispersion characteristics of the phase velocity and the ground structure based on the H / V spectrum can be obtained, the ground structure can be estimated with high accuracy. In addition, the estimation method from the H / V spectrum can estimate the ground structure of one construction site from the measurement data of the construction site, and the ground structure can be estimated relatively easily.

[0016] (Aspect 4) The ground structure estimation method according to aspect 1, The measurement data includes horizontal vibration data and vertical vibration data, and an H / V spectrum is calculated by dividing the horizontal spectrum obtained from the horizontal vibration data by the vertical spectrum obtained from the vertical vibration data, and the relationship between the ground depth and shear wave velocity of the target site is estimated based on the H / V spectrum.

[0017] According to the fourth aspect, the ground structure of the target land can be estimated. Furthermore, even when acquiring measurement data from multiple construction sites, if the H / V spectrum is used, it is not necessary to acquire measurement data from multiple construction sites at the same time. Furthermore, for example, when using the SPAC method, it is necessary to select measurement values ​​on a virtual circle, but if the H / V spectrum is used, the layout of the construction sites from which data is acquired is less likely to be limited, making it easier to select the construction sites. Therefore, the ground structure of the target land can be estimated relatively easily.

[0018] (Aspect 5) The method for estimating a ground structure according to aspect 3 or aspect 4, The method is characterized in that the relationship between depth and shear wave velocity below the engineering bedrock of the target site is estimated based on the H / V spectrum of each of the multiple construction sites.

[0019] According to the fifth aspect, the ground structure of each construction site is estimated based on the H / V spectrum, and there is a high probability that the ground structure deeper than the engineering bedrock is common to multiple construction sites. Therefore, the ground structure of the target site can be estimated based on the ground structures deeper than the engineering bedrock of multiple construction sites. In this case, if the H / V spectrum is used, there is no need to obtain measurement data at the same time for multiple construction sites. In addition, for example, when using the SPAC method, it is necessary to select measurement values ​​on a virtual circle, but with the H / V spectrum, the layout of the construction sites from which data is obtained is less likely to be limited, and it is easy to select a construction site. Therefore, the ground structure of the target site can be estimated relatively easily based on the ground structures deeper than the engineering bedrock of multiple construction sites.

[0020] (Aspect 6) A ground structure estimation method according to any one of aspects 2 to 4, The method is characterized in that it estimates the relationship between depth and shear wave velocity below the engineering bedrock of the target land, which is land other than the construction site.

[0021] According to the sixth aspect, even if the target site is a land other than the construction site (observation point), if the ground structure is deeper than the engineering bedrock, there is a high probability that it is common between the construction site and the target site. Therefore, the ground structure deeper than the engineering bedrock of the target site can be estimated.

[0022] (Aspect 7) A ground structure estimation method according to any one of aspects 1 to 6, The vibration measuring device is characterized by continuously measuring vibrations at the construction site where it is installed.

[0023] According to the seventh aspect, it is possible to obtain measurement data suitable for estimating the ground structure, for example, measurement data that is not affected by vibrations (noise) caused by construction work at a construction site. In addition, it is possible to obtain measurement data of various vibrations that occur at a construction site, and it is also possible to grasp the difference in the way the ground shakes depending on the type and magnitude of the vibration (dominant frequency). Therefore, it is possible to estimate the ground structure with high accuracy.

[0024] (Aspect 8) A ground structure estimation method according to any one of aspects 1 to 7, The method is characterized in that the ground structure of the target site is estimated based on the measurement data measured by the vibration measuring device outside construction hours at the construction site.

[0025] According to the eighth aspect, it is possible to obtain measurement data that is not affected by vibrations (noise) caused by construction work at a construction site, and therefore it is possible to estimate the ground structure with high accuracy.

[0026] (Aspect 9) A ground structure estimation method according to any one of aspects 1 to 8, The measurement data used to estimate the ground structure is characterized in that it is data on vibrations generated outside the construction site.

[0027] According to the ninth aspect, the ground structure can be estimated with high accuracy based on data of microtremors caused by natural vibrations or artificial vibrations occurring at a distance, without being affected by vibrations (noise) caused by construction work at a construction site.

[0028] (Aspect 10) A ground structure estimation method according to any one of aspects 1 to 9, The measurement data measured by the vibration measuring device is stored in a cloud server.

[0029] According to the tenth aspect, since the data measured at a plurality of construction sites is managed in a centralized manner, the measured data at the plurality of construction sites can be easily collected, which makes it easier to estimate the ground structure.

[0030] (Aspect 11) A ground structure estimation method according to any one of aspects 1 to 10, A ground vibration estimating method, characterized in that the vibration measuring instrument is a measuring instrument used to visually display vibration values ​​from outside the construction site.

[0031] According to the eleventh aspect, a vibration measuring device installed at a construction site can be used for display, and the work of installing a vibration measuring device for estimating the ground structure can be omitted, thus facilitating the work of estimating the ground structure.

[0032] ===First embodiment=== Fig. 1 is a diagram showing an example of a target land pt for estimating a ground structure and a plurality of construction sites pc. Fig. 2 is an explanatory diagram of a vibration measuring device 10 installed at the construction site pc. Fig. 3 is a flow diagram of a ground structure estimation method in a first embodiment. Fig. 4 is a block diagram showing a measurement data collection system. Fig. 5 is a schematic diagram explaining the measurement results of shaking (vibration) in each direction.

[0033] Vibrations generated during construction of buildings, bridges, roads, and other structures have a large impact on nearby residents, and standards regarding vibrations are established by laws and ordinances. For this reason, as shown in Figure 2, vibration measuring devices 10 are often installed at construction sites to monitor the vibrations generated by construction.

[0034] Specifically, examples of methods for monitoring vibration include displaying the vibration values ​​measured by the vibration measuring device 10 in real time on a monitor 2 installed on a temporary fence 1 or the like at the construction site PC, issuing an alarm when the measured value of the vibration measuring device 10 exceeds a preset threshold, and enabling construction personnel to obtain the measured value of the vibration measuring device 10 from a terminal such as a smartphone. By doing so, construction work can be carried out so that the vibration generated by the construction does not exceed the standard value. In particular, by displaying the vibration value on the temporary fence 1 so that it can be seen from outside the construction site, it is possible to reduce anxiety of nearby residents and gain a sense of trust from nearby residents. Note that the noise value may be displayed on the monitor 2 together with the vibration value.

[0035] On the other hand, there is a demand for exploring the ground structure when constructing a structure, etc. The Earth's surface is always shaking slightly even when there is no earthquake, causing microtremors (weak vibrations). Various methods have been proposed for estimating the ground structure by measuring these microtremors. In the first embodiment and the second to fourth embodiments described later, a method for estimating the ground structure is implemented based on microtremor data from a plurality of observation points.

[0036] However, when installing a vibration measuring instrument for measuring microtremors on public land such as a road in order to estimate the ground structure, it is necessary to apply for a usage procedure, and when installing on private land, it is necessary to obtain permission from the owner and pay a usage fee. In addition, in order to obtain data with less noise, the installation time of the vibration measuring instrument may be limited, for example, to install the instrument at night. Thus, installing a vibration measuring instrument is a difficult task. Moreover, when estimating the ground structure based on microtremor (vibration) data from multiple observation points as in this embodiment, vibration measuring instruments must be installed at multiple observation points, which increases the complexity of the work.

[0037] Therefore, in the first embodiment, a process (S02 in FIG. 3) is carried out to acquire measurement data from the vibration measuring device 10 at multiple construction sites pc1 to pc4 where the vibration measuring device 10 is installed, and a process (S03 to S13) is carried out to estimate the ground structure of a target land pt, which is at least one of the construction sites pc1 to pc4 and land other than the construction sites pc1 to pc4, based on the measurement data (microtremor data) measured at each of the multiple construction sites pc1 to pc4.

[0038] When the construction site pc is the target site pt, the target site pt may be one or more of the construction sites pc1 to pc4 where the measurement data was acquired. When land other than the construction site pc is the target site pt, the target site pt may be one land or multiple land. Figure 1 illustrates an example in which the target site pt is one land other than the construction sites pc1 to pc4 where the measurement data was acquired.

[0039] By installing the vibration measuring device 10 for estimating the ground structure at the construction site PC, it becomes unnecessary to apply for procedures for using public or private land or to pay usage fees. This makes it easier to install the vibration measuring device 10, and as a result, makes it easier to estimate the ground structure. Furthermore, a construction site PC increases the freedom in the installation time of the vibration measuring instrument 10. For example, the vibration measuring instrument 10 can be installed during the day, rather than at night to obtain nighttime data with less noise. Also, a construction site PC makes it easier to install the vibration measuring instrument 10 for a long period of time. This makes it easier to obtain data during appropriate times (for example, at night or on holidays when there is less noise). In addition, since there are many construction site pcs, there are many options for the construction site pcs from which measurement data is obtained. Therefore, it is possible to select a construction site pc that is suitable for estimating the ground structure. For example, when using the SPAC method, it is easy to select a construction site pc located on a virtual circle.

[0040] As described above, a vibration measuring instrument 10 is often installed at the construction site PC in order to display the vibration value visibly from outside the construction site PC, for example by displaying the vibration value on the temporary enclosure 1. In this embodiment, the vibration measuring instrument 10 used to display the vibration value visibly from outside the construction site is used to acquire microtremor data for estimating the ground structure. Specifically, the ground structure is estimated using measurement data used to visibly display the measurement data of the vibration measuring instrument 10 on the monitor 2 installed outside the construction site PC.

[0041] By doing so, the ground structure can be estimated using the microtremor data measured by the vibration measuring instrument 10 that was originally installed on the construction site PC, and the work of installing the vibration measuring instrument 10 to estimate the ground structure can be omitted. This makes it even easier to estimate the ground structure. In other words, the data from the vibration measuring instrument 10 that was used to display the vibration values ​​caused by the construction work can be effectively utilized.

[0042] However, the present invention is not limited to the above. For example, the ground structure may be estimated using a vibration measuring device 10 that has been installed on the construction site PC to monitor the vibration of the construction work by a method other than displaying the vibration value. Also, a vibration measuring device 10 solely for estimating the ground structure may be installed on the construction site PC in addition to the vibration measuring device 10 that has been installed to monitor (display, etc.) the vibration of the construction work.

[0043] Next, the ground structure estimating method according to the first embodiment will be described with reference to the flow chart of FIG. First, from among multiple construction sites pc in operation where vibration measuring instruments 10 are installed, multiple construction sites pc1 to pc4 are selected from which measurement data is to be acquired in order to estimate the ground structure of the target site pt (S01). Although Fig. 1 illustrates an example in which four construction sites pc1 to pc4 are selected, the number of selected construction sites pc may be two or more.

[0044] The vibration measuring device 10 installed in the construction site PC is not particularly limited as long as it can measure microtremor data for estimating ground structure, and any known vibration measuring device can be used. As shown in FIG. 4, the vibration measuring device 10 of this embodiment has a sensor 11 for three components, two horizontal components (x direction, y direction) and a vertical component (z direction), a memory unit 12, a communication unit 13, and a control unit 14. The vibration measuring device 10 is connected to a monitor 2 attached to a temporary fence 1 by wire or wirelessly (for example, Bluetooth (registered trademark)). The control unit 14 controls the communication unit 13 to transmit the vibration value measured by the sensor 11 to the monitor 2. The monitor 2 displays the vibration value received from the vibration measuring device 10.

[0045] As shown in FIG. 2, the vibration measuring device 10 (sensor 11) is installed on the ground so that the positive x direction is east (negative west), the positive y direction is north (negative south), and the positive z direction is up (negative down). The vibration measuring device 10 may be installed appropriately in a place where data for estimating the ground structure can be obtained, such as the ground surface or the foundation of a building. The vibration measuring device 10 simultaneously measures and stores the magnitude of vibration (displacement, speed, acceleration, etc.) of each component in the x direction, y direction, and z direction. This allows vibration (microtremors) in each direction to be measured, as shown in FIG. 5. For example, the east-west vibration of the ground is measured as a component in the x direction. The two horizontal components that the vibration measuring device 10 measures are not limited to the east-west and north-south directions, but are two directions that are orthogonal (intersecting at 90 degrees). It is preferable that the two horizontal components of the vibration measuring device 10 (sensor 11) installed at each of the multiple construction site PCs are in the same direction. For example, for a vibration measuring instrument 10 installed at a construction site pc different from the construction site pc in Fig. 2, the x direction is set to the east-west direction and the y direction is set to the north-south direction. However, this is not limited to the above and correction is possible if the installation direction of the vibration measuring instrument 10 is known.

[0046] Next, measurement data (microtremor data) measured at a specific time in each of the selected construction sites pc1 to pc4 is acquired (S02).

[0047] In this embodiment, as shown in Fig. 4, the vibration measuring instrument 10 of each construction site PC is connected to the cloud server 20 via a network N. In detail, the vibration measuring instrument 10 is connected to the network N by wire or wirelessly (for example, Wi-Fi (registered trademark)). The control unit 14 of the vibration measuring instrument 10 controls the communication unit 13 to transmit the measurement data measured by the sensor 11 to the cloud server 20.

[0048] An example of the cloud server 20 includes a storage unit 21, a communication unit 22, and a control unit 23. In the cloud server 20, when the communication unit 22 receives the measurement data of each construction site PC, the control unit 23 creates a vibration database and stores it in the storage unit 21. The vibration database is a data group that associates the measurement data for each construction site PC with the name, position, measurement time, etc. of the construction site PC.

[0049] In this way, a measurement data collection system can be configured in which a plurality of construction site PCs and the cloud server 20 are connected via a network N. The measurement data measured by the vibration measuring device 10 installed on each construction site PC is preferably stored in the cloud server 20.

[0050] In this way, data measured at multiple construction sites pc can be managed centrally using the network N. Therefore, an operator estimating the ground structure can obtain microtremor data for multiple pieces of land (selected construction sites pc1 to pc4) that he or she wishes to use in estimating the ground structure simply by accessing the cloud server 20. This eliminates the need to visit the construction sites pc to collect measurement data from the vibration measuring device 10, and makes it easier to estimate the ground structure.

[0051] Furthermore, if the cloud server 20 is used, multiple workers (for example, a worker who estimates the ground structure of another piece of land, a supervisor of the construction site PC, etc.) can easily access and obtain measurement data, and the data of each construction site PC can be easily shared. In addition, even large amounts of data measured by multiple construction site PCs can be easily stored, and the capacity of the memory unit 21 of the cloud server 20 can be easily adjusted depending on the number of construction site PCs in operation.

[0052] However, the measurement data may be stored in a server (computer) that can be managed centrally, not limited to the cloud server 20. Alternatively, the measurement data of each construction site PC may be collected individually by a worker who estimates the ground structure visiting the construction site PC or contacting a worker at the construction site PC.

[0053] It is also preferable to acquire measurement data measured by the vibration measuring instrument 10 outside construction hours of the construction site pc from among the measurement data accumulated in the memory unit 21 (vibration database) of the cloud server 20. Then, it is preferable to estimate the ground structure of the target land pt based on the measurement data measured by the vibration measuring instrument 10 outside construction hours of the construction site pc.

[0054] The ground structure is estimated based on the ground's microtremors (small vibrations). Therefore, large vibrations caused by construction at the observation point become noise components. Therefore, as described above, by using measurement data measured at night or on holidays when construction is not being carried out, the ground structure of the target site pt can be estimated with high accuracy.

[0055] Furthermore, it is preferable that the measurement data used to estimate the ground structure is data on vibrations that have occurred outside the construction site PC. In other words, it is better to estimate the ground structure based on microtremors that have propagated through the ground to the construction site PC due to natural vibrations (e.g., vibrations caused by ocean waves) or artificial vibrations (e.g., vibrations caused by traffic) that have occurred far away, rather than on large vibrations caused by construction work at the construction site PC, which is the observation point. In this way, the ground structure of the target land PT can be estimated with high accuracy using measurement data that does not include large vibrations (noise components) that occur at the construction site PC.

[0056] For this reason, it is preferable that the vibration measuring device 10 continuously measures the vibration of the construction site pc where it is installed. By "continuous measurement," we mean that the vibration measuring device 10 measures continuously (24 hours per day) for at least a part of the period from when the vibration measuring device 10 is installed at the construction site pc until the construction is completed.

[0057] By doing so, it is possible to obtain measurement data suitable for estimating the ground structure from the continuously measured data, that is, measurement data that does not include noise such as vibrations caused by construction. In addition, it is possible to obtain measurement data of various vibrations that occur at the construction site PC, and it is also possible to grasp the difference in the way the ground shakes depending on the type and magnitude of the vibration (predominant frequency). Therefore, it is possible to estimate the ground structure of the target land PT with high accuracy. Furthermore, data measured during the day can be used to monitor (display, etc.) vibrations caused by construction. Furthermore, in this embodiment, a vibration measuring device 10 is installed at the construction site PC. Therefore, it is possible to continuously measure vibrations without causing problems such as traffic obstructions. However, it is not limited to the above, and for example, it is possible to measure only for the period necessary to estimate the ground structure.

[0058] Next, the ground structure of the target ground pt is estimated based on the measurement data (microtremor data) acquired from multiple construction sites pc1 to pc4. In the first embodiment, two estimation methods are implemented: a microtremor array exploration method and one based on the H / V spectrum.

[0059] 6A to 6D are explanatory diagrams of a method for estimating ground structure using the microtremor array exploration method. In the "microtremor array exploration method," microtremors are measured at the same time at multiple observation points deployed on a plane, and the phase velocity of each frequency component of the surface wave of the ground at the observation point is obtained. Surface waves have a dispersion property in which the phase velocity changes depending on the frequency, and this dispersion property is closely related to the ground structure. For this reason, a method has been proposed to estimate the ground structure at the observation point by inverse analysis of the dispersion characteristics. In the first embodiment, the well-known microtremor array exploration method is used to estimate the ground structure.

[0060] For this purpose, in the first embodiment, measurement data measured at specific times (at the same time) at each of the selected construction sites pc1 to pc4 is acquired, and dispersion characteristics indicating phase velocities at each frequency are calculated from the acquired measurement data. Based on the dispersion characteristics, the relationship between the ground depth and shear wave velocity of the target ground pt is estimated.

[0061] In this way, the ground structure of the target land pt can be estimated. Particularly in this embodiment, a vibration measuring device 10 that displays information on the temporary fence 1 is used, and measurement data from multiple construction sites pc is centrally managed. Therefore, even when estimating the ground structure based on microtremor data measured at multiple observation points, such as in the microtremor array exploration method, microtremor data can be easily collected. Furthermore, it is easy to install the vibration measuring device 10 over a long period of time at construction sites pc, and by selecting construction sites pc that are operating at the same time, microtremor data measured at the same time can be easily collected.

[0062] Specifically, first, the dispersion characteristic indicating the phase velocity at each frequency is obtained from the observed microtremor data (Fig. 5) (S03). As shown in Fig. 6A, the dispersion characteristic is expressed by a dispersion curve with the horizontal axis (parameter) representing frequency and the vertical axis representing phase velocity. In this specification, the dispersion characteristic of the phase velocity based on this measurement data is also referred to as the "measurement dispersion characteristic." The phase velocity can be estimated from the microtremor data based on well-known microtremor array exploration methods such as the SPAC method and the FK method.

[0063] Next, as shown in the left diagram of FIG. 6B, a theoretical ground model (relationship between ground depth (m) and shear wave velocity (m / s)) is created. The theoretical ground model may be created based on data on ground structure previously surveyed near the observation point (construction site pc), for example. Then, from the theoretical ground model, dispersion characteristics indicating phase velocity at each frequency are obtained (S04), as shown in the right diagram of FIG. 6B. These theoretical dispersion characteristics are also referred to as "theoretical dispersion characteristics" in this specification.

[0064] Next, as shown in Fig. 6C, the measured dispersion characteristics are compared with the theoretical dispersion characteristics to determine whether they are similar to each other (S05). If the theoretical dispersion characteristics differ from the measured dispersion characteristics, the theoretical ground model (left diagram in Fig. 6B) is modified (S06). Then, the theoretical phase velocity dispersion characteristics (right diagram in Fig. 6B) are obtained again, and the measured dispersion characteristics are compared with the theoretical dispersion characteristics. The above steps are repeated until the theoretical dispersion characteristics are approximate (match or similar) to the measured dispersion characteristics. Well-known optimization methods such as the nonlinear least squares method and genetic algorithms can be applied to this analysis.

[0065] Then, the theoretical ground model when the theoretical dispersion characteristics that approximate the measured dispersion characteristics are created is determined as the ground structure (Figure 6D) at the observation points (construction sites pc1 to pc4 where the measurement data was obtained) (S07).

[0066] 7A to 7D are explanatory diagrams of a ground structure estimation method based on the H / V spectrum. "H / V spectrum" is the spectrum obtained by dividing the spectrum of horizontal motion (H) by the spectrum of vertical motion (V) from the three-component observation record of microtremors observed at one location. The H / V spectrum is governed by the characteristics of surface waves, and a method of estimating ground structure by inverse analysis of the H / V spectrum has been proposed. In the first embodiment, a well-known estimation method using the H / V spectrum is utilized to estimate the ground structure. For example, the estimation can be appropriately performed based on the description in the literature (Arai Hiroshi, Tokimatsu Koji, "Estimation of Ground S-Wave Velocity Structure by Inverse Analysis of Microtremor H / V Spectrum," Abstracts of Academic Lectures at the Architectural Institute of Japan Annual Meeting (Kyushu), September 1998).

[0067] For this purpose, in the first embodiment, the vibration measuring instrument 10 is capable of measuring vibrations in the horizontal and vertical directions, and the measurement data acquired from the vibration measuring instrument 10 installed at the construction site pc includes horizontal (x and y) vibration data and vertical (z) vibration data. Then, an H / V spectrum is calculated by dividing the horizontal spectrum (H) obtained from the horizontal vibration data by the vertical spectrum (V) obtained from the vertical vibration data, and the relationship between the ground depth and shear wave velocity of the target ground pt is estimated based on the H / V spectrum.

[0068] In this way, the ground structure of the target land pt can be estimated. Furthermore, the H / V spectrum is measured at one point. Therefore, an H / V spectrum is obtained for each of the multiple construction sites pc1 to pc4 from which measurement data was acquired, and the ground structure is estimated based on each H / V spectrum. Therefore, when measurement data is acquired from multiple construction sites pc1 to pc4 as in this embodiment, the ground structure is estimated based on the H / V spectrum for each of the construction sites pc1 to pc4. Therefore, based on the estimation results of the multiple ground structures, estimation errors in the ground structure due to measurement errors, etc. can be suppressed, and accurate estimation can be achieved.

[0069] Specifically, the following process is carried out for each of the measurement data from construction sites pc1 to pc4. First, the microtremor data (Fig. 5) of each component (x, y, z) observed at a certain construction site pcn (n=1 to 4) is frequency analyzed (e.g., fast Fourier transform: FFT analysis) to calculate the spectra (Hx, Hy, V) in the x, y, and z directions. Although not shown, the spectrum of microtremors is expressed with the horizontal axis (parameter) representing frequency (Hz) and the vertical axis representing amplitude.

[0070] Next, the spectrum of horizontal motion (Hx, Hy) is divided by the spectrum of vertical motion (Hz). This results in an H / V spectrum at each frequency as shown in FIG. 7A (S08). In FIG. 7A, the horizontal axis represents frequency (Hz) and the vertical axis represents the H / V spectrum. The spectrum of horizontal motion H may be a value obtained by using the geometric mean or the square root of the sum of the squares of the spectrum Hx in the x direction and the spectrum Hy in the y direction. The spectrum of horizontal motion H may be Hx / Hz only in the x direction or Hy / Hz only in the y direction. The H / V spectrum based on this measurement data is also referred to as "measured H / V" in this specification.

[0071] Thereafter, as in the method described in the microtremor array exploration method, a theoretical ground model (relationship between ground depth (m) and shear wave velocity (m / s)) is created as shown in the left diagram of FIG. 7B. Then, from the theoretical ground model, the H / V spectrum at each frequency is obtained (S09), as shown in the right diagram of FIG. 7B. This theoretical H / V spectrum is also referred to as the "theoretical H / V" in this specification.

[0072] Next, as shown in Fig. 7C, the measured H / V is compared with the theoretical H / V to determine whether they are close to each other (S10). If the theoretical H / V differs from the measured H / V, the theoretical ground model (left diagram in Fig. 7B) is modified (S11). Then, the theoretical H / V spectrum (right diagram in Fig. 7B) is obtained again, and the measured H / V is compared with the theoretical H / V. The above steps are repeated until the theoretical H / V is close to (matches or is similar to) the measured H / V. Well-known optimization methods such as the nonlinear least squares method and genetic algorithms can be applied to this analysis.

[0073] Then, the theoretical ground model when the theoretical H / V that is close to the measured H / V is created is determined as the ground structure of a certain construction site pcn (observation point) (Figure 7D). By executing the above process for each of the multiple construction sites pc1 to pc4, the H / V spectrum of each construction site pc1 to pc4 is obtained and the ground structure is determined.

[0074] As a result of the above, in the first embodiment, one ground structure (FIG. 6D) is determined by the microtremor array exploration method, and multiple ground structures (for each of the construction sites pc1 to pc4) (FIG. 7D) are determined based on the H / V spectrum. These multiple ground structures are, for example, averaged to determine one ground structure, and the averaged ground structure is regarded as the ground structure of the target land pt (S13).

[0075] In addition, even if the target land pt is one of the construction sites pc1 to pc4 or a land other than a construction site, the ground structure of the observation point (the averaged ground structure) is considered to be the ground structure of the target land pt. Therefore, when determining the construction site pc from which measurement data is to be obtained, it is advisable to select a construction site pc whose ground structure is similar to that of the target land pt.

[0076] In this way, the thickness of each layer and the shear wave velocity (hardness of the ground) of each layer are obtained for the multiple strata that make up the ground of the target land pt. In the first embodiment, the ground structure is estimated using two different estimation methods (microtremor array exploration method and estimation method using H / V spectrum), so the ground structure can be estimated with high accuracy. By estimating the ground structure of the target land pt (what kind of hardness the layer structure has), it is possible to carry out ground improvement work before the construction of a structure such as a building, or to take earthquake countermeasures for the structures of the target land pt, for example.

[0077] In addition, the above-mentioned method of estimating ground structure (for example, each process such as selecting a construction site PC, acquiring measurement data, and determining the dispersion characteristics of phase velocity) may be performed by a worker (human) using a computer, or may be performed automatically by a computer according to a program, or may be shared between the two.

[0078] <<<Modifications>>> Unlike the microtremor array exploration method, the H / V spectrum is measured at one point, and the ground structure based on the H / V spectrum is determined for each observation point. Therefore, in the estimation method based on the H / V spectrum, instead of using the measurement data of multiple construction sites pc1 to pc4 as in the above embodiment, the H / V spectrum may be obtained based on the measurement data measured at one construction site pc, and the ground structure may be estimated based on that one H / V spectrum. For example, the ground structure may be estimated based on the measurement data of one construction site (pc4 in the case of FIG. 1) that is closest to the target land pt among the multiple construction sites pc1 to pc4 from which measurement data was obtained. In this way, the estimation method from the H / V spectrum can estimate the ground structure of one construction site pc from the measurement data of that construction site, and can estimate it relatively easily.

[0079] Furthermore, the construction site pc from which measurement data is obtained may be different between the microtremor array exploration method and the estimation method based on the H / V spectrum. For example, when estimating phase velocity using the SPAC method in the microtremor array exploration method, the center of a virtual circle and the circumference of the virtual circle are set as measurement points, so the construction sites pc1 to pc4 shown in Figure 1 are selected. On the other hand, in the estimation method using the H / V spectrum, the construction site pc closest to the target site pt may be selected.

[0080] The ground also comprises deep ground below the engineering bedrock (including the engineering bedrock) where the shear wave velocity is 400 m / s or more, and relatively soft shallow ground on top of the engineering bedrock. In general, the deep and hard deep ground can be considered to have the same ground structure over a wide area compared to the shallow ground.

[0081] The ground structure based on the H / V spectrum is obtained for each observation point (construction site), but there is a high probability that the deep ground is common to multiple construction sites pc1 to pc4. Therefore, the relationship between depth and shear wave velocity below the engineering bedrock of the target site pt may be estimated based on the H / V spectrum of each of the multiple construction sites pc1 to pc4.

[0082] For example, as shown in Fig. 7D, the data on the deep ground below the engineering foundation is used from the relationship between depth and shear wave velocity obtained for each of the construction sites pc1 to pc4. In other words, the ground structure obtained by averaging the data on the deep ground of each of the construction sites pc1 to pc4 can be regarded as the ground structure of the deep ground of the target site pt.

[0083] In this way, by using the deep ground structure estimated at each of the multiple construction sites pc1 to pc4, estimation errors due to measurement errors can be suppressed, and the ground structure can be estimated with high accuracy. In particular, with the H / V spectrum, it is not necessary to obtain measurement data at the same time for multiple construction sites pc1 to pc4. In addition, for example, when using the SPAC method, it is necessary to select the construction sites pc on a virtual circle, but with the H / V spectrum, the placement of the construction sites pc from which data is obtained is less likely to be limited, and it is easy to select the construction sites pc. In addition, in a boring survey that actually excavates the ground, it takes time and cost to investigate deep ground. Therefore, by using the measurement data of the microtremors at the construction sites pc, it is easy to estimate the deep ground. The layer structure of the shallow ground may be obtained by a microtremor array exploration method, or it may be estimated by a boring survey that does not use microtremor data.

[0084] In addition, when land other than the construction sites pc1 to pc4 is set as the target land pt, the relationship between depth and shear wave velocity below the engineering bedrock may be estimated based on the measurement data of the construction sites pc1 to pc4. For example, the data on the deep ground of the ground structure at the observation point obtained by the microtremor array exploration method (Fig. 6D) and the data on the deep ground of the ground structure at the observation point obtained by the H / V spectrum (Fig. 7D) may be averaged and utilized.

[0085] If it is an engineering foundation, there is a high probability that the ground structure is the same at the observation points (construction sites pc1 to pc4) and the target site pt. Therefore, even if the target site pt is land other than the observation point, the ground structure can be estimated with high accuracy. In this case, the ground structure can be estimated by conducting a boring survey for the shallow ground.

[0086] In addition, the layer structure below the engineering bedrock is reflected in the data in the low-frequency region of the phase velocity dispersion characteristics for each frequency (Fig. 6A) and the H / V spectrum (Fig. 7A). Therefore, when estimating the deep ground, it is advisable to determine the ground structure that approximates the graph in the low-frequency region when comparing the measured and theoretical dispersion characteristics of phase velocity, or the measured and theoretical H / V. This allows for a more accurate estimation of the structure of the deep ground.

[0087] ===Second embodiment=== FIG. 8 is a flow diagram of a ground structure estimating method in the second embodiment. In the second embodiment, the ground structure is not estimated based on the H / V spectrum, but the ground structure at the observation point is estimated based on the measurement data at specific times of multiple construction sites pc1 to pc4, and the estimated ground structure is regarded as the ground structure of the target land pt. The method of estimating the ground structure is the same as in the first embodiment.

[0088] In the microtremor array exploration method, ground structure is estimated from microtremor data from multiple observation points. Therefore, in the second embodiment, as in the first embodiment, the vibration measuring device 10 installed at the construction site pc is used, and the measurement data from multiple construction sites pc is centrally managed, so that microtremor data at specific times (the same time) from multiple construction sites pc1 to pc4 can be easily collected.

[0089] ===Third embodiment=== FIG. 9 is a flowchart of a ground structure estimating method in the third embodiment. In the third embodiment, the microtremor array exploration method is not performed, and the ground structure is estimated based on the H / V spectrum. The method of estimating the ground structure is the same as in the first embodiment, and measurement data from multiple construction sites pc1 to pc4 is acquired, and the H / V spectrum is obtained for each of the construction sites pc1 to pc4 to estimate the ground structure. Therefore, in the third embodiment, as in the first embodiment, microtremor data can be easily collected by using the vibration measuring device 10 installed at the construction site pc and by centrally managing the measurement data from the multiple construction sites pc. Note that the measurement data acquired from the multiple construction sites pc1 to pc4 does not need to be data measured at a specific time (the same time).

[0090] Then, by estimating the ground structure of the target land pt based on the ground structures estimated at each of the multiple construction sites pc1 to pc4, it is possible to suppress errors in estimating the ground structure due to measurement errors, etc. In particular, with the H / V spectrum, there is no need to obtain measurement data at the same time for multiple construction sites pc1 to pc4. Also, for example, when using the SPAC method, it is necessary to select the construction sites pc on a virtual circle, but with the H / V spectrum, the placement of the construction sites pc from which data is obtained is less likely to be limited, making it easier to select the construction sites pc. Also, the data deeper than the engineering bedrock among the ground structures estimated at each of the multiple construction sites pc1 to pc4 may be used to estimate the structure of the deep ground deeper than the engineering bedrock of the target land pt.

[0091] ===Fourth embodiment=== Fig. 10 is a diagram showing a ground structure estimation method in the fourth embodiment. In the first embodiment, as shown in Fig. 2, a case where one vibration measuring instrument 10 is installed at a construction site pc is illustrated, but this is not limiting. As shown in Fig. 10, a plurality of vibration measuring instruments 10a-10d may be installed at a construction site pc. In other words, at each of a plurality of construction sites pc1-pc4 where measurement data is acquired to estimate the ground structure of a target land pt, a single vibration measuring instrument 10 may be installed (Fig. 2), or a plurality of vibration measuring instruments 10a-10d may be installed (Fig. 10).

[0092] By installing multiple vibration measuring instruments 10 at one construction site pc, for example, when estimating phase velocity using the SPAC method in the microtremor array exploration method, the vibration measuring instruments 10a to 10d can be installed at the center of a virtual circle and on the circumference of the virtual circle as shown in Fig. 10. However, the arrangement of the vibration measuring instruments 10a to 10d is not limited to the above.

[0093] Furthermore, all of the measurement data from the multiple vibration measuring instruments 10a-10d installed on the construction site PC may be used for displaying on the monitor 2 of the temporary fence 1, or only a portion of the measurement data from the multiple vibration measuring instruments 10a-10d may be used for displaying on the monitor 2. Furthermore, the measurement data from the multiple vibration measuring instruments 10a-10d does not have to be used for displaying on the monitor 2.

[0094] ===Other embodiments=== The above-mentioned embodiment is for the purpose of facilitating understanding of the present invention, and is not intended to limit the present invention. The present invention can be modified or improved without departing from the spirit of the present invention, and it goes without saying that the present invention includes equivalents thereof.

[0095] For example, in the above embodiment, the relationship between the depth of the ground of the target ground pt and the shear wave velocity is estimated as the ground structure, but this is not limited to this. The ground structure may be estimated by determining other parameters that represent the ground structure (e.g., P-wave velocity, density, attenuation, type of shaking and predominant frequency, magnitude of shaking and predominant frequency, etc.) based on the measurement data of the vibration measuring device 10 installed at the construction site pc. [Explanation of symbols]

[0096] 1 Temporary enclosure, 2 monitors, 10 Vibration measuring instrument, 11 sensor, 12 memory unit, 13 communication unit, 14 control unit, 20 cloud servers, 21 memory unit, 22 communication unit, 23 control unit, pc construction site, pt target area,

Claims

1. acquiring measurement data of one or more vibration measuring devices at a plurality of construction sites, each of which has one or more vibration measuring devices installed; A step of estimating a ground structure of a target land, which is at least one of the construction sites and land other than the construction sites, based on the measurement data measured at each of the construction sites; A ground structure estimation method comprising the steps of:

2. The method for estimating a ground structure according to claim 1, Acquire the measurement data measured at a specific time at each of the plurality of construction sites; A dispersion characteristic indicating a phase velocity at each frequency is obtained from the acquired measurement data, A ground structure estimation method, comprising estimating the relationship between ground depth and shear wave velocity of the target area based on the dispersion characteristics.

3. The method for estimating a ground structure according to claim 2, The measurement data includes horizontal vibration data and vertical vibration data, Calculating an H / V spectrum by dividing a horizontal spectrum calculated from the horizontal vibration data by a vertical spectrum calculated from the vertical vibration data; A method for estimating ground structure, comprising estimating the relationship between ground depth and shear wave velocity of the target area based on the H / V spectrum.

4. The method for estimating a ground structure according to claim 1, The measurement data includes horizontal vibration data and vertical vibration data, Calculating an H / V spectrum by dividing a horizontal spectrum calculated from the horizontal vibration data by a vertical spectrum calculated from the vertical vibration data; A method for estimating ground structure, comprising estimating the relationship between ground depth and shear wave velocity of the target area based on the H / V spectrum.

5. The method for estimating a ground structure according to claim 3 or 4, A ground structure estimation method, comprising estimating the relationship between depth and shear wave velocity below the engineering bedrock of the target site based on the H / V spectrum of each of the multiple construction sites.

6. The method for estimating a ground structure according to any one of claims 2 to 4, A method for estimating ground structure, comprising estimating the relationship between depth and shear wave velocity below the engineering bedrock of the target land, which is land other than the construction site.

7. The ground structure estimation method according to any one of claims 1 to 4, A ground structure estimation method, characterized in that the vibration measuring device continuously measures vibrations at the construction site where it is installed.

8. The method for estimating a ground structure according to any one of claims 1 to 4, A ground structure estimation method, comprising estimating the ground structure of the target site based on the measurement data measured by the vibration measuring device outside construction hours at the construction site.

9. The ground structure estimation method according to any one of claims 1 to 4, A ground structure estimation method, characterized in that the measurement data used to estimate the ground structure is data on vibrations generated outside the construction site.

10. The ground structure estimation method according to any one of claims 1 to 4, A ground structure estimation method, characterized in that the measurement data measured by the vibration measuring instrument is stored on a cloud server.

11. The ground structure estimation method according to any one of claims 1 to 4, A ground vibration estimating method, characterized in that the vibration measuring instrument is a measuring instrument used to visually display vibration values ​​from outside the construction site.