Construction management program and construction management system

The construction management program enhances location-based management by integrating site map displays and registration features, addressing inefficiencies in worker recruitment, material procurement, and resident inquiries.

JP2024168307AActive Publication Date: 2024-12-05株式会社RAKUNY
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
JP2023084858
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-05-23
Publication Date
2024-12-05
Estimated Expiration
2043-05-23

AI Technical Summary

Technical Problem

Existing construction management systems lack the ability to efficiently manage location-based aspects of construction projects, such as worker recruitment, material procurement, and resident inquiries, due to the lack of familiarity with the area by system operators.

Method used

A construction management program that integrates construction-related spot registration, ordered construction registration, progress input, and site map display to visually represent construction sites and material sources on a common map, allowing for efficient planning and decision-making.

Benefits of technology

Enables efficient management of worker recruitment, material procurement, and resident inquiries even for operators unfamiliar with the area, reducing errors and increasing operational efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024168307000001_ABST
    Figure 2024168307000001_ABST
Patent Text Reader

Abstract

To provide a construction management program and a construction management system with which a person who is not familiar with the area can efficiently make an arrangement for recruiting workers to another construction site or replenishing materials quickly.SOLUTION: A construction management program causes a computer to function as: construction-related spot registration means which registers positions of construction-related spots including a construction company and a material supplier; ordered construction registration means which registers construction-related information including a client and a period of a construction and a location of a construction site, for each ordered construction; progress input means which inputs, for each construction, progress of the constructions registered by the ordered construction registration means; and site map display means which displays construction sites of the constructions registered by the ordered construction registration means, on a map (site map display screen S9) common to the construction-related spots registered by the construction-related spot registration means.SELECTED DRAWING: Figure 12
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a construction management program installed in a computer for managing the progress of construction work, and a construction management system using this construction management program. [Background technology]

[0002] Many companies that carry out civil engineering and architectural works have introduced construction management systems that use computers to manage the progress of construction work that they have received orders for. Patent Document 1 discloses an example of such a construction management system.

[0003] The construction management system (civil engineering construction management system) of Patent Document 1 is mainly composed of a construction site device 1, a construction company device 2, and a management server 5, as shown in FIG. 4 of the document. The construction site device 1 is used when creating daily reports and the like at the construction site. The construction company device 2 automatically creates a construction progress chart (FIG. 16 of the document) based on the daily reports and the like. The daily reports created by the construction site device 1 and the construction progress chart created by the construction company device 2 are stored in the management server 5 and can be checked remotely. By using this construction management system, the progress of construction can be managed efficiently. [Prior art documents] [Patent documents]

[0004] [Patent Document 1] JP 2002-288272 A Summary of the Invention [Problem to be solved by the invention]

[0005] However, local knowledge is sometimes necessary to efficiently manage the progress of construction work. For example, when a worker is vacant at a construction site, workers must be recruited from other nearby construction sites. If the person who receives the local knowledge can make a rational decision such as, "The construction site where the worker is vacant is close to that construction site, so we can temporarily recruit workers from that construction site." Also, when construction at one construction site is completed in a short time (for example, when it is completed in the morning), one worker may be assigned to work at other nearby construction sites at a different time of the same day (for example, in the afternoon). If the person who receives the local knowledge has local knowledge, the person who receives the call can easily pick out construction sites that the worker can work at that day, and can make efficient plans. Furthermore, when a resident near the construction site makes a phone call to inquire (for example, an inquiry about whether private vehicles can pass through the site), the person who receives the call can give the resident an appropriate answer if he or she has local knowledge. Furthermore, if a problem occurs and unexpected materials are needed, those materials must be procured quickly from nearby sources. If you have local knowledge, you can make the rational decision that "we can get those materials from that nearby source."

[0006] However, the person who operates the construction management system does not necessarily know the location. Therefore, when the above situation occurs, the worker allocation plan (allocation plan when there is a sudden vacancy, allocation plan when the same worker is in charge of multiple sites on the same day, etc.) and material procurement are made while checking the addresses of each construction site and material procurement source, but it is difficult to judge how close the two locations to be compared are just by looking at the address. Also, when a resident inquires about the construction, the person who answers the phone can only reply, "I will contact the person in charge later," and the work of contacting the person in charge increases. Since the above situation occurs frequently for construction contractors, the effort required for these arrangements is enormous. In this regard, even if a conventional construction management system such as the construction management system of Patent Document 1 is introduced, it is mainly a time-series process that can be efficiently managed, and location-based management cannot be efficiently performed.

[0007] The present invention has been made to solve the above-mentioned problems, and provides a construction management system that enables even people who are unfamiliar with the area to efficiently arrange for the replacement of workers and the procurement of materials in situations where workers need to be replaced from other construction sites, when the same worker is in charge of multiple construction sites on the same day, when materials need to be procured quickly, when inquiries from residents need to be answered, etc. [Means for solving the problem]

[0008] The above issues are: A construction management program for causing a computer to function as a means for managing the progress of construction work, Computer, A construction-related spot registration means for registering the positions of construction-related spots including construction companies and material suppliers; An ordered construction registration means for registering construction-related information including the order origin and period of the construction, and the location of the construction site for each ordered construction; A progress status input means for inputting the progress status of each construction work registered in the received construction work registration means; A site map display means for displaying the construction site of each construction registered in the received construction registration means on a common map (hereinafter referred to as a "site map") together with the construction-related spots registered in the construction-related spot registration means; A construction management program characterized by functioning as This is solved by providing

[0009] The construction management program of the present invention is stored (installed, etc.) in a management server (computer). The management server is connected to a user terminal (computer) wirelessly or via a wired connection. Hereinafter, the management server in which the construction management program is stored and the user terminal connected thereto may be collectively referred to as a "construction management system." In this construction management system, the registration of the positions of the above construction-related spots, the registration of construction orders received, the input of the progress status of each construction project, and the display of the site map can be performed on a user terminal located away from the management server.

[0010] In this way, by displaying construction sites and material procurement sources (construction-related spots) on the site map, it becomes possible to visually grasp the location of a construction site, the positional relationship between a construction site and other construction sites, and the positional relationship between a construction site and a material procurement source. Therefore, even if a situation arises in which workers must be supplemented from other construction sites, a situation in which the same worker is in charge of multiple construction sites on the same day, a situation in which materials must be promptly procured, a situation in which inquiries from residents must be answered, etc., even a person who is unfamiliar with the area can efficiently arrange for the supplementation of workers and the procurement of materials.

[0011] In the construction management program of the present invention, The site map display means is Construction-related spots and construction sites are displayed on the site map with icons of different types. When the cursor is placed over an icon, a pop-up will appear near the icon with an overview of the construction-related spot or construction site corresponding to that icon. When the icon or a specific part in the overview is selected, a construction progress input screen corresponding to the icon is displayed. It is preferable to use the above-mentioned method.

[0012] If there is a lot of text displayed on the site map, it becomes difficult to read the site map, but by displaying construction-related spots and construction sites on the site map as icons, the site map can be made easier to read. In addition, when you place the cursor over an icon, a pop-up display of the outline of the construction (such as the client, the name of the construction, and the address of the construction site) corresponding to that icon is displayed, so you can check the outline of the construction without switching the screen from the site map. When you want to know more detailed information about the construction (such as the construction period, specific progress, and list of workers) or want to update that information, you can select (click, etc.) the icon or a specific part of the outline to switch to a screen where you can do so (progress input screen).

[0013] In the construction management program of the present invention, it is also preferable that the site map display means extracts construction sites where construction is being carried out on a specific day from among the construction works registered by the received construction work registration means, and displays those construction sites on the site map together with construction-related spots.

[0014] This is because when replenishing workers on a certain day, there is no need to consider the situation at the construction site before that day or the situation at the construction site after that day. Therefore, if construction sites other than that day are also displayed on the site map, there is a risk of mistakes in arranging for the replenishing of workers, etc. In this regard, by extracting construction sites where construction is being carried out on a specific day and displaying them on the site map, mistakes can be made less likely to occur.

[0015] In the construction management program of the present invention, it is also preferable that the site map display means extracts construction sites from each construction project registered by the received construction project registration means, the progress status of which is at a specific stage as input into the progress status input means, and displays those construction sites on the site map together with construction-related spots.

[0016] Examples of specific stages of progress (hereinafter sometimes referred to as "progress stages") include "construction undecided," which indicates the stage where an order has been received but the start date has not been decided, "construction planned," which indicates the stage where the start date has been decided but construction has not yet started, and "construction in progress," which indicates the stage where construction has started but not yet been completed. By extracting construction sites according to the progress stage and displaying them on a site map, construction planning can be carried out efficiently.

[0017] It is also preferable that the construction management program of the present invention has an underground information input means for inputting underground information at a construction site, and that the site map display means, when a point is selected on the site map, displays underground information of other construction sites within a specific range of the selected point on the site map.

[0018] This is because many construction projects, such as gas pipe construction, involve digging up the ground. When digging up the ground, spring water (groundwater) may appear. The presence or absence of this groundwater and the amount of it will affect the difficulty of the construction. For more difficult construction projects, it may be necessary to procure special tools (materials) or increase the number of workers. In this regard, if the presence or absence of groundwater at past construction sites is registered as "underground information," that underground information can be referenced when planning construction at nearby construction sites, making it possible to carry out the planning more efficiently. Effect of the Invention

[0019] As described above, the present invention makes it possible to provide a construction management system that enables even people who are unfamiliar with the area to efficiently arrange for the addition of workers and the procurement of materials in situations where workers need to be recruited from other construction sites, where the same worker is in charge of multiple construction sites on the same day, where materials need to be procured quickly, or where inquiries from residents need to be answered, etc. [Brief description of the drawings]

[0020] [Figure 1]This is a diagram showing an overall picture of the construction management system. [Diagram 2] FIG. 13 is a diagram showing a login screen of the construction management system. [Diagram 3] FIG. 2 is a diagram showing a top screen of a construction management system. [Figure 4] FIG. 13 is a diagram showing a construction registration screen of the construction management system. [Diagram 5] FIG. 13 is a diagram showing a construction list screen of the construction management system. [Figure 6] FIG. 13 is a diagram showing a progress management screen of the construction management system. [Figure 7] FIG. 7 is a diagram showing the progress management screen of the construction management system (continuation of FIG. 6). [Figure 8] FIG. 8 is a diagram showing the progress management screen of the construction management system (continuation of FIG. 7). [Figure 9] FIG. 13 is a diagram showing a preliminary daily report registration screen of the construction management system. [Figure 10] FIG. 13 is a diagram showing a daily report editing screen of the construction management system. [Figure 11] FIG. 13 is a diagram showing a construction-related spot registration screen of the construction management system. [Figure 12] This is a diagram showing the site map display screen of the construction management system (when displaying "Today's site"). [Figure 13] This is a diagram showing the site map display screen of the construction management system (when displaying ``site under construction''). [Figure 14] This is a diagram showing the site map display screen of the construction management system (when displaying ``sites where construction has not been scheduled''). [Figure 15] This is a diagram showing the site map display screen of the construction management system (when displaying "Planned Construction Site"). [Figure 16] This figure shows the site map display screen of the construction management system (when ``Underground Information'' is displayed). [Figure 17] 13 is a diagram showing a construction site submenu displayed as a pop-up on the site map display screen of the construction management system. FIG. [Figure 18]13 is a diagram showing a state in which a submenu for underground information is displayed as a pop-up on the site map display screen of the construction management system. FIG. [Figure 19] FIG. 13 is a diagram showing an example of a photo screen displayed from a site map display screen of the construction management system. [Figure 20] 1 is a diagram showing a state in which the surroundings of a target construction site are enlarged and displayed on a site map display screen of a construction management system. [Figure 21] FIG. 13 is a diagram showing an example of a site map display screen of underground information displayed in a construction management system, with a registered construction site as the reference position. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0021] The construction management system and construction management program used therein of the present invention will be described in more detail with reference to the drawings. However, the configuration described below is merely a preferred embodiment. Therefore, the technical scope of the present invention is not limited to the configuration described below. The construction management system and construction management program of the present invention can be modified as appropriate within the scope that does not impair the spirit of the invention.

[0022] 1.Overview of the construction management system The construction management system of the present invention is for efficiently managing the progress of construction work. Fig. 1 is a diagram showing an overall view of the construction management system.

[0023] The construction management system of the present invention is composed of a management server 10 and a user terminal 20, as shown in FIG.

[0024] A general server computer can be used as the management server 10. The above-mentioned construction management program is installed (stored) in this management server 10 and is in an executable state (a state in which the management server 10 can function as a means for managing the progress of construction).

[0025] Examples of the user terminal 20 include computer terminals such as personal computers, smartphones, and tablet terminals. A plurality of user terminals 20 are usually prepared. In this embodiment, for convenience of explanation, three user terminals 20 (an office worker terminal 21, a site manager terminal 22, and a worker terminal 23) are used, but four or more user terminals 20 may be prepared.

[0026] The user terminals 20 are connected to the management server 10 by wired or wireless connection. In this embodiment, among the user terminals 20, the clerk terminal 21 is connected to the management server 10 by wired connection (wired LAN), and the site manager terminal 22 and the worker terminal 23 are connected to the management server 10 wirelessly (WiFi communication via the Internet). Therefore, the user terminals 20 and the management server 10 are capable of communicating with each other.

[0027] The user terminal 20 is equipped with a terminal application for connecting to the management server 10. This allows the user terminal 20 to connect to the management server 10 through the terminal application, register a newly ordered construction project in the management server 10, read out various information registered in the management server 10, and update that information. A user of the construction management system can use the terminal application in the user terminal 20 to perform the above operations on the management server 10. In this embodiment, a general web browser is used as the above terminal application.

[0028] 2. Operation and behavior of the construction management system The operation and behavior of the construction management system will be described below. In the following, an example will be given in which a user terminal 20 connects to the management server 10 and performs various operations while referring to various screens displayed on the web browser of the user terminal 20.

[0029] 2.1 Login screen When using the construction management system, a user connects (accesses) to the management server 10 from a user terminal 20. When the management server 10 is accessed, a login screen S1 shown in FIG. 2 is displayed on the display unit (monitor, etc.) of the user terminal 20. FIG. 2 is a diagram showing the login screen S1 of the construction management system. The login screen S1 is provided with a user name input section α1, a password input section α2, and a login button α3. A user of the construction management system inputs the user name and password assigned to the user into the user name input section α1 and password input section α2, respectively, and presses (clicks, etc.) the login button α3. This allows the user to log in to the construction management system. If the user name and password entered into the user name input section α1 and password input section α2 do not match those stored in advance in the management server 10, login to the construction management system is rejected.

[0030] 2.2 Top screen When logging in to the construction management system, the display unit (monitor, etc.) of the user terminal 20 switches from the login screen S1 (FIG. 2) to the top screen S2 of FIG. 3. FIG. 3 is a diagram showing the top screen S2 of the construction management system. The upper part of the top screen S2 is a menu display unit α4, and the lower part is a content display unit α5. Various menu buttons are arranged in the menu display unit α4, and the name of the user who is currently logged in is displayed on the right side. In this embodiment, the menu buttons include a "Calendar" button, a "Site Map" button, a "Construction Registration" button, a "Construction List" button, a "Document Creation" button, a "Maintenance Management" button, a "Screen Print" button, a "Talk" button, and a "Confirmation Required" button. By pressing (clicking) these buttons, the display of the content display unit α5 switches to one corresponding to the button. On the other hand, the menu display unit α4 is always displayed even if the screen is switched by pressing a button on the menu display unit α4.

[0031] 2.3 Construction registration screen To manage the progress of construction work using the construction management system, it is necessary to register the received construction work in the construction management system (construction registration). Construction registration is performed on the construction registration screen S3 shown in Figure 4. Figure 4 is a diagram showing the construction registration screen S3 of the construction management system. This construction registration screen S3 is displayed when the "construction registration" button in the menu display section α1 is pressed. The content display section α5 of the construction registration screen S3 displays a template for entering information about the construction work (construction registration template).

[0032] In this embodiment, as shown in FIG. 4, the upper part of the construction registration template is a place to input the order origin, construction classification, construction company, construction name, construction location, order date, work unit, whether urgent response is required, whether automatic transmission of start and completion emails is required, etc. Of these, the order origin, construction classification, construction company, and work unit are selected from a pull-down menu. The construction name, construction location, and order date are input in a text box. The construction location is usually input as an address such as "XX City XX Town XX No.", but a map display button (not shown) may be provided near the input field (text box) so that the location can be specified on a map that is displayed when the map display button is pressed. The necessity of urgent cases and the necessity of automatic transmission of start and completion emails are input in a check box format. The upper part of the construction registration template also has buttons for attaching electronic data (e.g., PDF data) of various slips (e.g., purchase orders) and various documents (e.g., drawings).

[0033] The middle section of the construction registration template is where you enter the site manager, workers, and administrative staff for the construction work you are registering. Of these, the construction manager is selected from a pull-down menu. For workers and administrative staff, the person in charge is entered by checking a box from a list of candidates displayed on the screen. However, construction managers and workers differ depending on the construction company. For this reason, the construction manager and workers displayed in the list are automatically changed depending on the construction company selected in the pull-down menu that specifies the construction company. This column can also be used to enter candidates for security guards and senior workers.

[0034] The lower section of the construction registration template is a place to enter the construction items planned for the construction being registered (main and branch pipe construction, supply pipe construction, paving work, supply pipe paving, small-scale new inner pipe construction, large-scale new inner pipe construction, or inner pipe expansion work, etc.) as well as the construction cost (labor cost) for each construction item, material cost, total construction cost, and the client's construction number. Construction items are entered using check boxes, while amounts such as the construction cost (labor cost) are entered into text boxes. The total construction cost for each construction item is automatically entered when the construction cost (labor cost) and material cost for the corresponding construction item are entered.

[0035] When you have finished entering each item in the construction registration template, press the "Register" button located in the lower right corner of the content display section α5. This causes the content entered in the construction registration template to be registered in the construction management system (management server 10).

[0036] 2.4 Construction list screen A list of the works registered in "2.3 Work Registration Screen" above (work list) can be viewed on the work list screen S4 shown in FIG. 5. FIG. 5 is a diagram showing the work list screen S4 of the work management system. This work list screen S4 is displayed when the "Work List" button in the menu display section α5 is pressed. The content display section α5 of the work list screen S4 displays the works registered up to that point in list form. The list (work list) has items for each work, such as the work number, client, construction company, work name, work location, progress, work request, and checklist. The work number, work name, and work location of each work can be pressed (clicked).

[0037] Clicking on the construction number or name of each construction project will switch to the construction progress management screen S5 for the corresponding construction project (see Figures 6 to 8 below), where the progress of that construction project can be confirmed and updated. On the other hand, clicking on the construction location for each construction project will open a map on a web mapping platform such as Google Maps (registered commercial law) in a separate window, and the construction location of the corresponding construction project will be displayed on that map. In the construction registration screen S3 (Figure 4) above, when the construction location is entered as an address, the construction location column in the construction list on the construction list screen S4 displays the GPS coordinates converted from that address.

[0038] Above the content display section α5 on the construction list screen S4 is a section (condition input section) for inputting conditions for filtering the constructions displayed in the construction list below. The condition input section is provided with areas for inputting the client, construction company, progress information, construction name / construction location, and client construction number (client construction number). Of these, the client, construction company, and progress information are selected from a pull-down menu, while the construction name / construction location, and client construction number are entered in a text box.

[0039] For example, if you specify "Company A" as the client, the construction list will only display construction projects whose construction company is "Company A," and if you specify "Under Construction" as the progress status, the construction list will only display construction projects that are currently under construction. This filtering function makes it possible to efficiently extract the desired construction project from the construction list, even if a large number of construction projects are registered in the construction management system.

[0040] 2.5 Progress Management Screen As described above in "2.4 Construction List Screen", when a specific location (construction number or construction name) in the construction list on the construction list screen S4 is clicked, the screen switches to the progress management screen S5 for that construction. Figures 6 to 8 are diagrams showing the progress management screen S5 of the construction management system. By looking at this progress management screen S5, it is possible to check the current progress status of the construction.

[0041] As shown in Figs. 6 to 8, the progress management screen S5 is provided with a basic information display section P1, a permission application information display section P2, an accounting information display section P3, a worker display section P4, a last updater display section P5, and a progress display section P6, and various information about the construction is displayed on these sections. The display contents of the progress management screen S5 are automatically created based on the contents entered in the construction registration template on the construction registration screen S3 (Fig. 4) described above. However, the user can also update items that he or she is authorized to update from this progress management screen S5.

[0042] As shown in FIG. 6, the basic information display section P1 displays basic information about the construction work. Specifically, the orderer of the construction work, the construction classification (classification of gas pipe construction or water pipe construction, etc.), the construction company, the construction work name, the construction location, the order date, the construction start date (start date), the construction completion date (completion date), whether or not to automatically send emails, the work unit (type of team unit or person unit), whether or not to respond urgently, underground information, pavement information, etc. are displayed. For items common to the above construction registration template, such as the construction work name and construction location, the contents entered in the construction registration template are displayed as they are. As with the construction registration template, the basic information display section P1 also has buttons for attaching electronic data (e.g., PDF data) of various slips (e.g., purchase orders) and various documents (e.g., drawings).

[0043] Incidentally, among the items in the basic information display section P1, underground information and pavement information are items that were not included in the above-mentioned construction registration template. This is because underground information (information on water volume, depth, soil quality, etc.) and pavement information (information on type and thickness of pavement) are usually not known until the ground at the construction site is actually excavated. This underground information and pavement information are entered at a stage when the construction progresses and information becomes known. The basic information display section P1 also has an "attach photo" button for attaching photos taken when the construction site was excavated (photos showing the amount of groundwater, the condition of the pavement, etc.).

[0044] In this embodiment, the "amount of water" can be selected from a pull-down menu, and can be selected from among "none", "little", "lots" or "maximum". For "depth", the depth at which groundwater emerged is input as a numerical value in a text box. For "soil type", the "sand", "maso", "gravel" or "clay" can be selected from a pull-down menu, and can be selected from among "sand", "asphalt", "gravel", "clay" or "clay". In addition, the "pavement information" can also be selected from a pull-down menu, and can be selected from among "As 5cm" (As is asphalt. The same applies below), "As 8cm", "As 10cm", "As 20cm", "CO 10cm" (CO is concrete. The same applies below), "CO 20cm", "As 10cm + CO 10cm", "interlocking" or "others".

[0045] The permission application information display section P2 displays information related to a permission application, and in this embodiment, information related to a road use permission application is displayed. Specifically, the police station making the application (recipient police station), the acceptance date of the application (road use permission acceptance date), the start date of the road use permission (road use permission start date), and the end date of the road use permission (road use permission end date) are displayed. These items in the permission application information display section P2 are input by an authorized user. The recipient police station can be selected from multiple police stations displayed in a pull-down menu. The road use permission acceptance date, road use permission start date, and road use permission end date are entered as dates in text boxes.

[0046] The accounting information display section P3 displays accounting information related to the construction work, as shown in Figs. 6 to 7. As already mentioned, in the construction registration screen S3 (Fig. 4), construction items (main and branch pipe construction, supply pipe construction, paving work, supply pipe paving, small-scale construction of new inner pipe, large-scale construction of new inner pipe, or construction of inner pipe extension, etc.) and the construction cost (labor cost) for each construction item, material cost, total construction cost, and the construction number of the client are input, and these contents are also displayed in the accounting information display section P3. However, while the construction cost (labor cost) and material cost in the construction registration screen S3 (Fig. 4) are planned amounts, the accounting information display section P3 of the progress management screen S5 displays the actual amount (actual construction amount and actual material cost) in addition to the planned amount (planned construction amount and planned material cost). In addition, the accounting information display section P3 also has items for provisional payment date and provisional payment amount, so that if a provisional payment is made from the client, the payment date (provisional payment date) and amount (provisional payment amount) can be input. Each item in this accounting information display section P3 is input by an authorized user.

[0047] As shown in Fig. 7, the worker display section P4 displays information about the workers of the construction work. As already mentioned, when the construction manager, workers, and office staff are entered on the construction registration screen S3 (Fig. 4), the same information is displayed on the worker display section P4. This worker display section P4 can be changed by an authorized user. The input format for such changes is the same as that of the construction registration screen S3 (Fig. 4).

[0048] As shown in Fig. 8, the last updater display section P5 displays the name of the user (last updater) who last updated each item on the progress management screen S5. The progress display section P6 displays the progress of the construction in chronological order (in the example of Fig. 8, the top side is newer and the bottom side is older). In this embodiment, the construction number, the implementation date, the type of planned or actual (planned or actual), the progress status, the work content, the number of workers who participated in the construction, the number of supporters, the number of security guards, the number of silver personnel, and the subcontractor are displayed. This progress display section P6 is automatically created and displayed based on the contents entered on the daily report preliminary registration screen S6 (see Fig. 9 below) and the daily report editing screen S7 (see Fig. 10 below).

[0049] 2.6 Daily report creation screen Incidentally, for the construction work registered on the construction work registration screen S3 (FIG. 4), it is possible to register a daily work report as a schedule. In this embodiment, the daily report is pre-registered in the following procedure.

[0050] First, press the "Calendar" button in the menu display section α4. This will switch to the top screen (calendar display screen) S3, which displays a calendar in the content display section α5. If you click on the date on this calendar for which you want to register a daily report template, the screen will switch to the construction list screen S4 shown in Figure 5 (however, only construction projects not yet decided are extracted). If you want to pre-register a daily report for a date that is not on the calendar currently being displayed, you can switch the year and month of the displayed calendar by specifying a different year and month in the pull-down menu in the upper left of the content display section α5, or by pressing the "Previous month" button, "This month" button, or "Next month" button in the upper right of the content display section α5.

[0051] At this time, the user selects the construction project for which a daily report template is to be created from the construction projects displayed in the construction project list on the construction project list screen S4. This switches to the daily report preliminary registration screen S6 shown in Fig. 9. Fig. 9 is a diagram showing the daily report preliminary registration screen S6 of the construction management system. In the daily report preliminary registration screen S6, the process and workers scheduled for that day are entered. When the user presses the "Preliminary registration" button in the lower right of the daily report editing screen S6, a preliminary daily report for that construction project is preliminarily registered for that date.

[0052] The pre-registered daily reports are displayed in the lower column of the corresponding date on the calendar displayed on the top screen (calendar display screen) S3. On the calendar, the daily reports for each construction project are displayed with a title (daily report title) that shows the client, site manager, construction project name, and progress status on one line. To ensure that the daily report title for each construction project fits on one line, the client and site manager are displayed using abbreviations of about one or two characters, only the first few characters of the construction project name are displayed, and the progress status is displayed using about two characters.

[0053] Pressing the title of a daily report on the calendar switches to the daily report editing screen S7 (Fig. 10). Fig. 10 is a diagram showing the daily report editing screen S7 of the construction management system. Preliminary registered daily reports can be edited on this daily report editing screen S7. Although not shown, a field for inputting the working hours (actual results) of workers is also provided at the bottom of the daily report editing screen S7. Daily reports are edited when updating the contents of the construction work on the day the work was carried out, or when there are changes to the schedule before the construction work is carried out. Pressing the "Update" button at the bottom right of the content display section α5 updates the daily report. The updated contents are also reflected in the above-mentioned progress management screen S5 (Figs. 6 to 8), etc.

[0054] 2.7 Construction-related spot registration screen In the construction management system, it is possible to register construction-related spots such as material procurement sources (material storage areas, material storage warehouses, material purchasing companies, etc.), your own company, partner companies, construction companies, etc. Construction-related spots can be registered on the construction-related spot registration screen S8 in FIG. 11. FIG. 11 is a diagram showing the construction-related spot registration screen S8 of the construction management system. This construction-related spot registration screen S8 is displayed when "Construction-related spot registration" is selected from the pull-down menu that is displayed when the cursor is placed over the "Maintenance management" button in the menu display section α4.

[0055] As shown in FIG. 11, the construction-related spot registration screen S8 allows the user to input the category of the construction-related spot to be registered, the spot name, address, and contact information (telephone number, fax number, and e-mail address). The construction-related spot category is selected from among "orderer," "our company / partner," "material supplier," "construction company," or "other" in a pull-down menu. The spot name, location (address, GPS coordinates, etc.), and contact information are entered in a text box. After entering these information, the user presses the "New registration" button at the bottom right to register the construction-related spot. If the user wants to change information about the construction-related spot, the user presses the "Change" tab to switch to the construction-related spot change screen (not shown), where the user can edit the spot name, address, and contact information of the construction-related spot.

[0056] 2.8 Site map display screen In this construction management system, when the cursor is pressed on the "Site Map" button in the menu display section α4, a site map (FIGS. 12 to 16) can be displayed on a common map showing the positions of the construction sites (construction sites) registered in the construction management system and the positions of construction-related spots. FIGS. 12 to 16 are diagrams showing the site map display screen S9 of the construction management system, and FIG. 12 shows the site map display screen S9 when "Today's Site" is displayed. 9.1 FIG. 13 shows the site map display screen S when "site under construction" is displayed. 9.2FIG. 14 shows the site map display screen S when "construction pending site" is displayed. 9.3 FIG. 15 shows the site map display screen S when the "construction site" is displayed. 9.4 Figure 16 shows the site map display screen S when "underground information" is displayed. 9.5 For the site map on the site map display screen S9, a map from a web mapping platform such as Google Maps (registered trademark) can be used.

[0057] When the cursor is placed over the "Site Map" button in the menu display section α4, a pull-down menu is displayed listing "Today's site," "Sites under construction," "Sites with construction pending," "Sites scheduled for construction," and "Underground information." When "Today's site" is selected from the menu, the site map display screen S 9.1 (Figure 12) is displayed, and when you select "Construction site", the site map display screen S 9.2 (Figure 13) is displayed, and when you select "Unconfirmed construction site", the site map display screen S 9.3 (Figure 14) is displayed, and when you select "Planned construction site", the site map display screen S 9.4 (Figure 15) will be displayed, and when you select "Underground Information", the site map display screen S 9.5 (Figure 16) will be displayed.

[0058] Site map display screen S 9.1 In FIG. 12, a map (site map) showing the location of the construction site where construction is being carried out on that day (today) is displayed, and the site map display screen S 9.2 In FIG. 13, a map (site map) showing the locations of construction sites that are in the construction period that day (today) is displayed, and the site map display screen S 9.3 In FIG. 14, a map (site map) showing the location of a construction site where an order has been received but the start date has not yet been decided is displayed, and the site map display screen S 9.4 In FIG. 15, a map (site map) showing the location of a construction site where an order has been received and the start date has been decided, but construction has not yet started at that time, is displayed, and the site map display screen S 9.5In (Fig. 16), a map (site map) showing the underground information around the designated point is displayed.

[0059] In addition, the above pull-down menu is provided with items such as "Supply pipe removal work" and "Ancillary work". When "Supply pipe removal work" is selected, a site map showing the location of the construction site where the supply pipe removal work is to be carried out among the sites where the work is undecided or planned is displayed, or when "Ancillary work" is selected, a site map showing the location of the construction site where the ancillary work is to be carried out among the sites where the work is undecided or planned can also be displayed.

[0060] The site map display screens S in Figs. 12 to 16 9.1 , S 9.2 , S 9.3 , S 9.4 , S 9.5 In the site maps displayed on etc., the positions of each construction site and construction-related spots (material acquisition sources, construction companies or orderers, etc.) are indicated by icons.

[0061] For example, the icon β1 (Figs. 12 and 13) representing the character "Work" indicates the location of the construction site where work is being carried out on that day. The icon β2 (Fig. 13) representing the character "Rest" indicates the location of the construction site where work is not being carried out on that day although that day is within the construction period (the construction site where work is on break). The icon β3 (Fig. 14) representing the character "Undecided" indicates the location of the site where the construction is undecided (the construction site whose start date has not been determined). The icon β4 (Fig. 15) representing the character "Scheduled" indicates the location of the site where the construction is scheduled (the construction site whose start date has been determined but has not yet arrived). The location of each construction site is specified from the construction location input on the above-mentioned construction registration screen S3 (Fig. 4).

[0062] Furthermore, mountain-shaped icon β5 (FIGS. 12-15) indicates the location of the material source (material storage area, material storage warehouse, material purchasing company, etc.). Human-shaped icon β6 (FIGS. 12-15) indicates the location of the construction company. Tank-shaped icon β7 (FIGS. 12-15) indicates the location of the order origin. The locations of construction-related spots other than the material source, construction company, and order origin can also be indicated using other types of icons (not shown). The locations of these construction-related spots are identified based on the locations entered on the construction-related spot registration screen S8 (FIG. 11) described above.

[0063] In this way, by displaying the positions of construction sites and construction-related spots (material suppliers, construction companies, orderers, etc.) on the site map, it becomes possible to visually grasp the location of a certain construction site, the positional relationship between a certain construction site and other construction sites, and the positional relationship between a certain construction site and a certain material supplier. Therefore, even people who are not familiar with the area can efficiently make arrangements when a situation arises in which workers need to be supplemented from other construction sites, when the same worker is in charge of multiple construction sites on the same day, when materials need to be procured quickly, when inquiries from residents need to be answered, etc. In addition, by displaying the positions of construction sites and construction-related spots with icons, the site map can be made easier to view.

[0064] In this embodiment, as shown in Fig. 17, when the cursor γ1 is placed on an icon β1, β2, β3, β4, β5, or β6, a pop-up speech bubble (submenu) γ2 is displayed near the icon, and an overview of the construction site or construction-related spot corresponding to the icon is displayed in the submenu γ2. Fig. 17 shows the site map display screen S of the construction management system. 3,1 This figure shows the construction site submenu popped up. This submenu γ2 can be closed by clicking the "X" mark in the upper right corner with cursor γ1.

[0065] The summary displayed in the submenu γ2 includes the order source of the work, the name of the work, the address of the work site, and the progress status when the cursor γ1 is over the icon β1, β2, β3, or β4 indicating the construction site. When the cursor γ1 is over the icon β5 indicating the material source, the name, address, and contact information of the material supplier are included. When the cursor γ1 is over the icon β6 indicating the construction company, the name, address, and contact information of the construction company are included. When the cursor γ1 is over the icon β7 indicating the order source, the name, address, and contact information of the order source are included. The display contents of the summary displayed in the submenu γ2 are automatically generated based on the contents entered when registering the work on the above-mentioned construction registration screen S3 (FIG. 4), the contents entered when updating the progress status on the progress management screen S5 (FIGS. 6 to 8), and the contents entered when registering the construction-related spot on the construction-related spot registration screen S8 (FIG. 11).

[0066] In this embodiment, when the cursor γ1 is used to click on the icon β1, β2, β3, β4 or a predetermined location of the submenu γ2 popped up nearby, the content display section α5 is switched to the construction progress input screen S5 (FIGS. 6 to 8) corresponding to the icon. This allows more detailed information (construction period, specific progress, list of workers, etc.) about the construction site shown on the site map to be acquired with a simple operation. This makes it easier to make arrangements such as replenishing workers and procuring materials. Even if the name (construction name) of the construction for which progress is to be updated is unknown, it is possible to open the construction progress input screen S5 from the site map if the approximate location of the construction site is known.

[0067] Furthermore, the cross-shaped icon β8 (Fig. 16) indicates the reference position. The reference position can be specified by double-clicking on the site map, but in the default state (when the site map is not double-clicked), it is displayed at the user's current location. The user's current location can be identified from the GPS coordinates of a PC or mobile device.

[0068] Furthermore, the teardrop-shaped icon β9 (FIG. 12) indicates underground information at that location. There are teardrop-shaped icons β9 that show the character "none," "few," "many," and "most" (not shown). The "none" icon β9 shows a location where no groundwater was found when excavated, the "few" icon β9 shows a location where only a small amount of groundwater was found when excavated, the "many" icon β9 shows a location where a large amount of groundwater was found when excavated, and the "most" icon β9 (not shown) shows a location where a considerable amount of groundwater was found when excavated.

[0069] The teardrop-shaped icon β9 is displayed at the position of a past construction site (a construction site where the "water volume" of "underground information" in the basic information display section P1 of the progress management screen S5 (FIG. 6) has already been entered) within a specific range from the reference position (the position of the icon β8), and based on the input of the "water volume", the text displayed on the icon β9 is determined to be "none", "little", "lots" or "maximum". This makes it possible to grasp underground information around the reference position and predict underground conditions, such as how much groundwater will come out when the reference position is excavated.

[0070] The range in which the teardrop-shaped icon β9 is displayed (the distance from the reference position; hereinafter, sometimes referred to as the "underground information display range") is not particularly limited. However, if the underground information display range is too narrow, the site map display screen S 9.5 There is a risk that almost no underground information will be displayed on the site map in (Figure 16). For this reason, it is preferable that the underground information display range is 50m or more. It is more preferable that the underground information display range is 100m or more, and even more preferable that it is 150m or more. However, since underground information at locations far away from the reference position is not useful, there is no point in making the underground information display range too wide. For this reason, the underground information display range is usually set to 1000m or less. It is preferable that the underground information display range is 500m or less. In this embodiment, the underground information display range is set to 200m.

[0071] In this embodiment, as shown in Fig. 18, when a cursor γ1 is placed on an icon β9, a balloon (submenu) γ3 is popped up near the icon, and an overview of the location (past construction site location) corresponding to the icon is displayed in the submenu γ3. Fig. 18 shows a site map display screen S of the construction management system. 3,5 This figure shows the state in which the underground information submenu γ3 is displayed as a pop-up. This submenu γ3 can be closed by clicking the "X" mark in the upper right corner with the cursor γ1.

[0072] The summary displayed in the submenu γ3 includes the name of the construction at that point (construction site), the address, the construction period, underground information (water volume, depth, and soil quality), pavement information, etc. The display contents of the summary displayed in the submenu γ3 are automatically generated based on the contents entered when registering the construction on the construction registration screen S3 (Fig. 4) described above, and the contents entered when updating the progress status on the progress management screen S5 (Figs. 6 to 8).

[0073] In this embodiment, the word "photo display" is written at the bottom of the submenu γ3. When the word is clicked, a photo screen S is displayed showing a photo of the location (construction site) as shown in FIG. 10 is displayed in a separate window. Figure 19 shows the site map display screen S of the construction management system. 9.5 The photo screen displayed from 10 FIG. 1 is a diagram showing an example of a photo screen S 10 The photo was attached by clicking the "Attach Photo" button in the basic information display section P1 of the progress management screen S5 (Fig. 6). By being able to see such photos of past construction sites, it becomes easier to imagine how much equipment and manpower will be required when excavating the reference position, making it easier to plan the construction.

[0074] As already mentioned, the reference position (the position of icon β8) can be changed by double-clicking on the site map. If you want to use a point that is not currently displayed as the reference position, you can scroll the site map. The site map can also be enlarged or reduced by clicking the "+" or "-" button at the bottom right. In addition, the site map can be switched between map display and aerial photo display by clicking the "Map" button or the "Aerial Photo" button at the top left of the site map. This makes it possible to obtain underground information and pavement information around any point (reference position) on the site map. This makes it easier to predict underground information and pavement information for future construction sites where construction has not been registered.

[0075] The above describes the case of viewing underground information around a site where no construction work has been registered, but it is of course possible to view underground information around a site where construction work has been registered. This can be done by the following procedure. First, display one of the site map display screens S9 showing construction sites (icons β1 to β4) such as those in Figures 12 to 14. Since underground information around a construction site is often desired in the planning stage before construction begins, it is usually the site map display screen S9 for a site where construction work has not yet been decided is displayed. 9.3 (Figure 14) or the site map display screen S of the planned construction site 9.4 The site map display screen S9 (FIG. 15) is then displayed. The site map display screen S9 is scrolled or enlarged so that the target construction site is displayed as shown in FIG. 20. FIG. 20 shows the site map display screen S9 of the construction management system (in the example shown in FIG. 20, the site map display screen S of a site where construction has not yet been decided). 9.3 ) showing the enlarged view of the area around the target construction site.

[0076] Next, the user places the cursor γ1 on the icon of the desired construction site (icon β3 in the example of FIG. 20), or clicks on the sub-menu γ2 that pops up when the cursor γ1 is placed over the icon. This will display a progress management screen S5 (FIGS. 6-8) for the construction at that construction site. This progress management screen S5 can also be displayed from the construction list screen S4 (FIG. 5) or the like, without going through the site map display screen S9. By clicking on the word "Underground Information" in the basic information display section P1 of the progress management screen S5, a site map display screen S will appear, with the desired construction site shown at the reference position (icon β8), as shown in FIG. 21. 9.5 Switches to.

[0077] FIG. 21 shows a construction site map display screen S of underground information in a construction management system, with a construction site registered as a reference position. 3,5 FIG. 21 shows an example of a site map display screen S. 3,5 In the example, the target construction site is replaced with an icon β8 indicating the reference position, and the construction site map display screen S in FIG. 3,5 Similarly, underground information within the underground information display range (within a radius of 200 m) from the reference position (target construction site) is displayed. 3,5 However, just like the site map in Figure 16, when the cursor γ1 (see Figure 18) is placed over the icon β9 showing underground information, the submenu γ3 (see Figure 18) for underground information is popped up and the photo screen S 10 (See FIG. 19) can then be displayed.

[0078] 3.Other As shown in FIG. 18, when the cursor γ1 is placed over the icon β9 showing underground information, a submenu γ3 pops up, which can display not only underground information and pavement information, but also information (pipe information) about pipes such as gas pipes and water pipes buried at that point. This makes it possible to predict the condition of a pipe buried at a certain point from the condition of pipes buried at nearby points (past construction sites), making it easier to appropriately plan the replacement timing of the pipes. This is because pipes buried nearby are often installed relatively close to each other, and corrosion of pipes buried underground often progresses to the same extent in nearby areas.

[0079] This function can be realized by providing a pipe information item in the basic information display section P1 of the progress management screen S6 (Figs. 6 to 8) or the like, and allowing the pipe condition to be input there. The pipe condition can be selected from among "no corrosion", "little corrosion", "corrosion present", "advancing corrosion" or "completely corroded" in a pull-down menu, for example. As with groundwater, it is also possible to attach a photograph showing the state of corrosion of the pipe, and to make the photograph viewable from a submenu γ3 (Fig. 18) or the like. [Explanation of symbols]

[0080] 10 Management Server 20 User terminal 21 Clerk's terminal 22 Terminal for site manager 23 Worker terminal P1 basic information display section P2 permit application information display section P3 Accounting Information Display Section P4 worker display section P5 Last updated user display section P6 Progress Display S1 login screen S2 top screen (calendar display screen) S3 construction registration screen S4 Construction List Screen S5 progress management screen S6 Daily report preliminary registration screen S7 Daily Report Editing Screen S8 Construction-related spot registration screen S9 site map display screen S 3.1 Site map display screen when "Today's Site" is displayed S 3.2 Site map display when "site under construction" is displayed S 3.3 Site map display screen when "sites pending construction" is displayed S 3.4 Site map display screen when "Planned construction site" is displayed S 3.5 Site map display screen when "Supply pipe removal site" is displayed S 10 Photo Screen α1 User Name Input Area α2 password input section α3 login button α4 menu display α5 content display area β1 Icon showing a construction site in progress Icon showing construction site where β2 work is suspended β3 Undetermined construction site icon Icon showing planned construction site for β4 Icon showing where to get β5 materials β6 Construction company icon Icon showing the source of β7 order Icon showing β8 reference position β9 Underground Information Icon γ1 Cursor γ2 Submenu γ3 Submenu

Claims

1. A construction management program for causing a computer to function as a means for managing the progress of construction work, Computer, A construction-related spot registration means for registering the positions of construction-related spots including construction companies and material suppliers; An ordered construction registration means for registering construction-related information including the order origin and period of the construction, and the location of the construction site for each ordered construction; A progress status input means for inputting the progress status of each construction work registered in the received construction work registration means; A site map display means for displaying the construction site of each construction work registered in the received construction work registration means on a common map (hereinafter referred to as a "site map") together with the construction-related spots registered in the construction-related spot registration means; A construction management program characterized by functioning as a construction management program.

2. The site map display means is Construction-related spots and construction sites are displayed on the site map with icons of different types. When the cursor is placed over an icon, a pop-up is displayed near the icon showing an overview of the construction-related spot or construction site corresponding to the icon. When the icon or a specific part in the overview is selected, a construction progress input screen corresponding to the icon is displayed.

2. The construction management program according to claim 1 .

3. A construction management program as described in claim 2, wherein the site map display means extracts construction sites where construction is being carried out on a specific day from among the construction works registered by the received construction work registration means, and displays those construction sites on the site map together with construction-related spots.

4. A construction management program as described in claim 3, wherein the site map display means extracts construction sites from each construction project registered by the received construction project registration means, the progress status of which is at a specific stage as input to the progress status input means, and displays the construction sites on the site map together with construction-related spots.

5. An underground information input means for inputting underground information at a construction site, When a point is selected on the site map, the site map display means displays underground information of other construction sites within a specific range from the selected point on the site map. The construction management program according to claim 4.

6. A management server in which the construction management program according to claim 1 is stored; A user terminal connected to the management server wirelessly or via a wired connection Equipped with This construction management system enables a user terminal to register the locations of construction-related spots using a construction-related spot registration means, register received construction work using an ordered construction work registration means, input progress status using a progress status input means, and display a site map using a site map display means.

Citation Information

Patent Citations

  • Management system for putting civil engineering work into effect

    JP2002288272A

  • Document data linkage method, document data linkage program, document data linkage device and record medium

    JP2003233646A

  • Application permission and managing system and construction managing system