Steel structure building constructed by using scaffold and scaffold erection method for steel structure building
By using embedded embedded steel bars and two-stage fixing methods in steel structure buildings, the problem of conflict between embedded steel bars and suspension wall structure conflicts during suspension wall installation is solved, and the installation of suspension walls without high-altitude lifting equipment and professional workers is realized, reducing construction costs and improving construction safety and efficiency.
Patent Information
- Application Number
- JP2023176044
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-10-11
- Publication Date
- 2025-04-23
- Estimated Expiration
- 2043-10-11
AI Technical Summary
When it is difficult to use curtain walls in steel structure buildings in the existing technology, it is possible to avoid the structural conflict between embedded steel bars and suspended walls during the installation process, resulting in the need to use high-altitude lifting equipment and professional workers, which increases construction costs.
Embedded reinforcing bars in floor slabs of steel structure buildings and wrapped them on scaffolding, and fixed the scaffolding on an aluminum alloy profile on the exterior of the building using a two-stage fixation method, allowing the hanging wall to be installed on the scaffolding.
This method avoids the use of high-altitude lifting equipment and professional workers, reduces the construction cost of steel structure buildings, improves the safety and construction efficiency of the building, and extends the service life of the building, and meets environmental protection requirements.
Smart Images

Figure 2025066435000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to a steel frame building constructed using scaffolding and a scaffolding erection method for a steel frame building, and in particular to a steel frame building constructed using scaffolding, which makes it possible to assemble exterior walls on the scaffolding without the need for rope work at height by arranging lateral aluminum profiles between stories of the outer shell of the steel frame building and fixing the scaffolding to the outside of the lateral aluminum profiles through two-stage fixing. [Background technology]
[0002] Early residential construction in Taiwan was dominated by brick, but with the introduction of reinforced concrete technology and reduced costs, residential construction began to be dominated by reinforced concrete. Subsequently, as Taiwan's economy developed and the population density increased, land costs soared, leading to an increased demand for steel-framed skyscrapers, and the number of steel-framed skyscrapers increased not only for commercial buildings but also for residential buildings. According to statistics, residential buildings account for the majority of the construction industry in Taiwan, at over 90%.
[0003] Generally speaking, Taiwanese architecture includes three types of structures: RC (reinforced concrete), SS (steel frame) and SRC (steel reinforced concrete). SS (steel frame) or SRC (steel reinforced concrete) structures have a longer lifespan than traditional RC (reinforced concrete) structures, and their materials are recyclable and environmentally friendly. However, the construction costs of SS (steel frame) or SRC (steel reinforced concrete) structures are high, so residential buildings are still mainly made of RC (reinforced concrete) structures.
[0004] For reinforced concrete (RC) buildings, scaffolding can be erected so that construction workers can use the scaffolding to work on the upper floors and complete the building structure. The RC beams of the building structure have embedded rebars (e.g. D10 bamboo joint rebars) and the distance between adjacent embedded rebars is between approximately 160cm and 180cm (adjusted according to the scaffolding erection drawings). The scaffolding can be erected by wrapping the embedded rebars around the scaffolding and fixing it to the outside of the building structure. When scaffolding is erected using embedded rebars, positional errors are tolerated and do not affect subsequent construction, allowing the erection of the scaffolding to be completed quickly.
[0005] Many steel-frame buildings, such as SS (steel frame) or SRC (steel reinforced concrete) structures, use curtain walls for their exterior walls. Curtain walls have the advantages of being lightweight, being in the form of modularized units, and being quick to install during construction. The installation method is to suspend the curtain wall from the outside of the floor slab using connecting members.
[0006] However, curtain walls cannot be assembled using scaffolding because the embedded rebars used to secure scaffolding in building structures get in the way of curtain wall assembly. Currently, curtain walls are assembled using a rope-work at height method, but the costs of the lifting equipment and specialized workers required for rope-work at height are high, which further increases the cost of steel-framed buildings and is detrimental to the spread of steel-framed buildings.
[0007] The applicant of the present application has previously filed Taiwan Patent Application No. 111147640 for a "Steel Frame Building Shell Structure" that reduces the construction costs of steel frame residential buildings. Summary of the Invention [Problem to be solved by the invention]
[0008] The problem that the present invention aims to solve is to provide a steel frame building constructed using scaffolding and a method for erecting scaffolding for a steel frame building, which makes it easier to erect scaffolding for steel frame buildings and enables exterior walls (such as curtain walls) to be assembled on the scaffolding. [Means for solving the problem]
[0009] A steel frame building constructed using the scaffolding of the present invention includes a steel frame building main body, a floor slab, and a building exterior wall, the steel frame building main body includes an H-shaped steel and a deck plate assembled on the H-shaped steel, the floor slab includes an RC slab laid on the deck plate, a reinforcing steel structure and embedded reinforcing bars are laid in the RC slab, the embedded reinforcing bars are extended outside the RC slab and wrapped around the scaffolding, and the scaffolding is fixed in a first stage, the building exterior wall includes an embedded member, a horizontal aluminum profile, and an exterior wall panel, and the embedded member is embedded in the RC slab. The horizontal aluminum profiles are embedded at intervals and are used to screw-fix wall connecting rods, the horizontal aluminum profiles are installed on the outside of the RC slab, one end of the wall connecting rod is inserted into the horizontal aluminum profile and screw-fixed to the embedded member, the other end of the wall connecting rod is screwed and fixed to the scaffolding, the embedded rebars are removed from the scaffolding to complete the second stage of fixing the scaffolding, the exterior wall panels are attached between the floor slabs from the outside, and adjacent exterior wall panels are separated by the horizontal aluminum profiles, and when construction of the building exterior wall is completed, the wall connecting rods are removed and the scaffolding is removed.
[0010] The scaffolding erection method for a steel frame building of the present invention includes a steel frame building including a steel frame building main body, a floor slab, and a building exterior wall, the steel frame building main body including an H-shaped steel and a deck plate assembled on the H-shaped steel, the floor slab including an RC slab laid on the deck plate, the building exterior wall including an embedded member, a horizontal aluminum profile, and an exterior wall plate, the deck plate being assembled on the H-shaped steel and the steel frame building main body being constructed, laying an RC slab on the deck plate to form the floor slab, laying a steel reinforcement structure and embedded reinforcing bars in the RC slab, extending the embedded reinforcing bars to the outside of the RC slab and wrapping them around the scaffolding, and The method includes the steps of constructing the floor slab as a first stage of fixing, burying embedded members used for screwing and fixing wall connecting rods in the RC slab at intervals and installing horizontal aluminum profiles on the outside of the RC slab, inserting one end of the wall connecting rod into the horizontal aluminum profile and screwing and fixing it to the embedded member, screwing and fixing the other end of the wall connecting rod to the scaffolding, removing the embedded rebar from the scaffolding to perform a second stage of fixing of the scaffolding, attaching the exterior wall panels from the outside between the floor slabs, separating the adjacent exterior wall panels by the horizontal aluminum profiles, and constructing the building exterior wall, and when construction of the building exterior wall is completed, removing the wall connecting rods and removing the scaffolding.
[0011] Furthermore, by using D10 bamboo joint rebar as the embedded rebar and wrapping the D10 bamboo joint rebar around the scaffolding at least three and a half turns, the fixing strength specified by regulations is met.
[0012] Furthermore, the embedded rebars are removed from the scaffolding, and the portions of the embedded rebars exposed from the RC slab are cut off.
[0013] Furthermore, the embedded member is an expansion nut, and one end of the wall connecting rod is screwed and fixed to the expansion nut with a screw.
[0014] Furthermore, after removing the wall tie rod, the embedded member is screwed with a nut or filled with silicone and then flattened and sealed with paint. Effect of the Invention
[0015] According to the present invention, based on the above-mentioned technical features, the following effects can be achieved. 1. The two-stage fixing allows the scaffolding to be fixed to the outside of the horizontal aluminum profiles, allowing the exterior walls to be assembled on the scaffolding, eliminating the need for ropes for high-altitude work. This reduces the costs of steel-framed buildings, is favorable for the popularization of steel-framed buildings, and can extend the service life of buildings and meet environmental protection requirements. 2. The first stage of fixing the scaffolding involves wrapping and fixing the embedded steel bars, which allows the scaffolding to be erected quickly. The second stage of fixing the scaffolding involves using wall connecting rods to replace the embedded steel bars, which allows the exterior wall to be assembled on the scaffolding. The position of the wall connecting rods can be accurately aligned, making the scaffolding more stable and improving safety. [Brief description of the drawings]
[0016] [Figure 1] FIG. 2 is a perspective view of a steel frame building shell after the first stage of scaffolding has been fixed in an embodiment of the present invention. [Diagram 2] FIG. 2 is a cross-sectional view of a steel frame building shell after the first stage of scaffolding fixing has been carried out in an embodiment of the present invention. [Diagram 3] FIG. 2 is a perspective view of a steel frame building shell after the second stage of scaffolding has been fixed in an embodiment of the present invention. [Figure 4] FIG. 2 is a cross-sectional view of a steel frame building shell after the second stage of scaffolding fixing has been carried out in an embodiment of the present invention. [Diagram 5] FIG. 2 is a perspective view of a steel frame building shell with the wall tie rods removed and the embedded members sealed with nuts in an embodiment of the present invention. [Figure 6] FIG. 2 is a plan view of a steel frame building shell with the wall tie rods removed and the embedded members sealed with nuts in an embodiment of the present invention. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0017] Hereinafter, an embodiment of the present invention will be described in detail with reference to the drawings. It goes without saying that the present invention is not limited to the examples. Moreover, since a steel frame building is huge, the drawings are all partial in order to clearly show the features of the present invention.
[0018] In this embodiment, the steel frame building includes a steel frame building main body A, a floor slab B, and a building exterior wall C.
[0019] As shown in Figures 1 and 2, first the steel frame building body A is constructed. The steel frame building body A mainly includes a steel beam made of H-shaped steel 1 and a deck plate 2, and the deck plate 2 is assembled onto the H-shaped steel 1.
[0020] After the assembly of the steel frame building body A is completed, the floor slab B is constructed. An RC slab 3 is laid on the deck plate 2 to form the floor slab B. A reinforcing bar structure 31 and embedded reinforcing bars are laid in the RC slab 3, and in this embodiment, D10 bamboo joint reinforcing bars 32 are used as the embedded reinforcing bars. The D10 bamboo joint reinforcing bars 32 are extended outside the RC slab 3, and are wrapped around the scaffolding 4 to form the first stage of fixing the scaffolding 4. To ensure stable fixing of the scaffolding 4 and to meet the fixing strength stipulated by regulations, the D10 bamboo joint reinforcing bars 32 are wrapped around the scaffolding 4 at least three and a half times. When using other reinforcing bars, such as D13 bamboo joint reinforcing bars, for the embedded reinforcing bars, wrap them around the scaffolding 4 in accordance with the provisions of the relevant laws and regulations.
[0021] As shown in Figures 3 and 4, after the construction of the floor slab B is completed and the scaffolding 4 is erected to perform the first stage of fixation, the construction of the building exterior wall C can be carried out. In this embodiment, the building exterior wall C has a two-layer structure, and includes an embedded member 7, a horizontal aluminum profile 8, an exterior wall panel 101, and an interior wall panel 102.
[0022] To construct the building exterior wall C, first, the RC water stop edge 5 is poured onto the RC slab 3 to form it, and then a number of embedded members 7 used to secure the wall connecting rods 6 are embedded at intervals from the outer surface of the RC slab 3 to the inside. Also, a horizontal aluminum profile 8 is installed on the outside of the RC slab 3, and then one end of the wall connecting rod 6 is inserted through the horizontal aluminum profile 8 and screwed into the embedded member 7.
[0023] In this embodiment, an expansion nut is used as the embedded member 7, and the wall connecting rod 6 is screwed and fixed to the embedded member 7 by a screw. According to a test, this can withstand a load of 2 tons. Furthermore, after the other end of the wall connecting rod 6 is screwed and fixed to the scaffolding 4, the D10 bamboo joint rebar 32 is removed from the scaffolding 4 to complete the second stage of fixing of the scaffolding 4. After removing the D10 bamboo joint rebar 32 from the scaffolding 4, the portion of the D10 bamboo joint rebar 32 exposed from the RC slab 3 can be cut off.
[0024] Next, one of the two C-shaped steels 9 is installed on the RC waterstop edge 5 with its opening facing upward, and the other is installed under the deck plate 2 with its opening facing downward, and then an exterior wall panel 101 and an interior wall panel 102 are affixed to the opposing sides of the RC waterstop edge 5 and the two C-shaped steels 9. A hollow space S is formed between the exterior wall panel 101 and the interior wall panel 102, which gives the building exterior wall C a two-layer structure and allows the building exterior wall C to be installed directly on the floor slab B. The floor slab B completely separates the spaces between the upper and lower floors and serves as an excellent water-proofing / sound-proofing / thermal-insulating layer between the upper and lower floors. The exterior wall panels 101 are installed from the outside between the floor slabs B of the upper and lower floors, and adjacent exterior wall panels 101 are separated by horizontal aluminum profiles 8. Elastic cement can be further filled into the assembled gaps between the exterior wall panels 101 to further improve the waterproofing effect between the inside and outside of the room.
[0025] In this embodiment, the sound-proofing material 20 is installed between two C-shaped steels 9, filling the hollow space S, and extending along the height direction of the building exterior wall C. For example, by filling the hollow space S with rock wool and filling the hollow space S in the building exterior wall C with the sound-proofing material 20, the sound-proofing / heat-insulating effect between the indoor side and the outdoor side can be further improved. Furthermore, by filling the gap between the horizontal aluminum profile 8 and the two exterior wall panels 101 with silicone 30, the drawback of conventional one-piece curtain walls that they are prone to damage due to resonance when vibrated under force is suppressed, and the horizontal aluminum profile 8 separates the exterior wall panels 101, reducing the risk of the exterior wall panels 101 being damaged under force. Furthermore, since the joints between the floors of the building exterior wall C are physically filled with the horizontal aluminum profile 8, the amount of silicone 30 can be reduced, resulting in excellent maintainability and cost savings.
[0026] As shown in Figures 5 and 6, when construction of the building exterior wall C is completed, the wall connecting rods 6 are removed and the scaffolding 4 is taken down (see Figures 3 and 4 for the wall connecting rods 6 and the scaffolding 4). After removing the wall connecting rods 6, the nuts 40 are screwed onto the embedded members 7, or the embedded members 7 are filled with silicone and then flattened and sealed with paint. Since the exterior wall panel 101 is flat and does not require bricks to be attached, a waterproof layer can be sprayed onto the entire exterior wall panel 101, and then a natural paint can be applied to complete the construction of the building exterior wall C.
[0027] The specific steps for erecting the scaffolding in this embodiment are described below. Among them, the methods that are the same as or similar to those used in the construction of conventional steel frame buildings are known to engineers in this field, so they are not shown in the figures, and detailed explanations of the construction are omitted. (1) Assemble the box columns and H-shaped steel 1, which are the structural materials for each floor; (2) Lay the deck plates 2 and deck boards for each floor; (3) Mark out the piping; (4) Lay the reinforcing bar structure 31 (including welded wire mesh) for each floor, and embed the D10 reinforcing bars 32 in advance; (5) Pour concrete for each floor to form the RC slab 3; (6) Assemble the scaffolding 4, and wrap the D10 reinforcing bars 32 around the scaffolding 4 at least three and a half times to secure the scaffolding 4 in the first stage; (7) Construct the RC water-stop edge 4 (plant reinforcing bars and fill with grout); (8) Lay the steel Marking and installation of Z-shaped steel, which is a common bar material for framed buildings; (9) Spraying fireproof coating material on the box columns and H-shaped steel 1 of each floor; (10) Marking the fixing positions of the embedded members 7 of the wall connecting rods 6; (11) Attaching the embedded members 7 of the wall connecting rods 6 to the RC slab 3; (12) Attaching the horizontal aluminum profiles 8; (13) Attaching the wall connecting rods 6 to the scaffolding 4 and fixing them with screws, and removing the D10 bamboo joint reinforcing bars 32 from the scaffolding 4 to perform the second stage of fixing of the scaffolding 4; (14) Marking and spacing the 125 type C-shaped steel, including the C-shaped steel 9 in the building exterior wall C, and installing it vertically. (15) Mark out the 125-type C-shaped steel on the facade of the opening, door or window (combine the cross bars and fasteners); (16) Fix the exterior wall panel 101; (17) Fill the gaps in the assembly of the exterior wall panel 101 with elastic cement to seal them (fill the gaps in the assembly of the exterior wall panel 101 with mortar to seal them); (18) Close the gaps of the exterior panel materials with a crack-resistant net; (19) Fill the long rock wool inside the building exterior wall C; (20) Fix the interior wall panel 102; (21) Fix the aluminum window mounting parts; (22) Attach the aluminum window frame and door frame. (23) Caulk the doors and windows; (24) Install door and window flashings; (25) Fireproof seal all gaps between the steel frame building body A, the floor slab B, and the building exterior wall C; (26) Spray the waterproof layer of the exterior wall panel 101 over the entire surface; (27) Fill the aluminum window and door frames with silicone; (28) Apply natural paint to the surface of the exterior wall panel; (29) Remove the scaffolding 4 for each floor, and remove the wall connecting rods 6 one by one. Fasten the nuts 40 or fill with silicone and then smooth and seal with paint; (30) Construction of the exterior wall of this floor is completed.
[0028] In this way, the two-stage fixing method allows the scaffolding to be fixed onto the horizontal aluminum profiles and the curtain wall to be assembled on the scaffolding, eliminating the need for rope work at height. This reduces the cost of steel frame buildings, is beneficial for the promotion of steel frame buildings, extends the lifespan of buildings, and meets environmental protection requirements.
[0029] The above describes the best embodiment of the present invention, and the scope of the present invention is not limited thereto. All simple changes and modifications that do not depart from the scope of the claims are included within the scope of the present invention. [Explanation of symbols]
[0030] A Steel frame building body B Floor slab C. Building exterior wall 1 H-beam 2 Deck plate 3. RC slab 31 Reinforced Concrete Structure 32 D10 bamboo knotted reinforcing bar 4. Scaffolding 5 RC watertight edge 6 Wall connecting rod 7 Embedded parts 8. Horizontal aluminum profiles 9 C-shaped steel 101 Exterior wall board 102 Interior wall panel 20 Soundproofing material 30 Silicon 40 Nut S hollow space
Claims
1. A steel-framed building constructed using scaffolding includes a steel-framed building body, a floor slab, and a building exterior wall, The steel frame building body includes an H-shaped steel and a deck plate assembled on the H-shaped steel, The floor slab includes an RC slab laid on the deck plate, A reinforcing bar structure and embedded reinforcing bars are laid in the RC slab, and the embedded reinforcing bars are extended outside the RC slab and wrapped around the scaffolding to form a first stage fixation of the scaffolding; The building exterior wall includes an embedded member, a horizontal aluminum profile, and an exterior wall board, The embedding members are embedded from the outside to the inside of the RC slab at intervals, and are used to screw and fix the wall connecting rods; The horizontal aluminum profile is installed on the outside of the RC slab, One end of the wall connecting rod is inserted into the horizontal aluminum section and fixed to the embedded member, the other end of the wall connecting rod is fixed to the scaffolding, and the embedded reinforcing bar is removed from the scaffolding to perform a second stage fixation of the scaffolding; The exterior wall panels are attached between the floor slabs from the outside, and adjacent exterior wall panels are spaced apart by the horizontal aluminum profiles; A steel frame building constructed using scaffolding, characterized in that, when construction of the exterior wall of the building is completed, the wall connecting rods are removed and the scaffolding is dismantled.
2. A steel frame building constructed using the scaffolding described in claim 1, characterized in that D10 bamboo joint rebar is used as the embedded rebar and the D10 bamboo joint rebar is wrapped around the scaffolding at least three and a half turns, thereby satisfying the fixing strength specified by regulations.
3. 2. A steel frame building constructed using the scaffolding according to claim 1, characterized in that the embedded reinforcing bars are removed from the scaffolding, and the portions of the embedded reinforcing bars exposed from the RC slab are cut off.
4. 2. The steel frame building constructed using scaffolding according to claim 1, characterized in that the embedded member is an expansion nut, and one end of the wall connecting rod is screwed and fixed to the expansion nut with a screw.
5. The steel frame building constructed using the scaffolding according to claim 1, characterized in that after removing the wall connecting rod, a nut is screwed onto the embedded member or the embedded member is filled with silicone and then flattened and sealed with paint.
6. A scaffolding installation method for a steel frame building, comprising the steps of: The steel frame building includes a steel frame building body, a floor slab, and a building exterior wall, The steel frame building body includes an H-shaped steel and a deck plate assembled on the H-shaped steel, The floor slab includes an RC slab laid on the deck plate, The building exterior wall includes an embedded member, a horizontal aluminum profile, and an exterior wall board, a step of assembling the deck plate onto the H-shaped steel and constructing the steel frame building body; A process of laying an RC slab on the deck plate to form the floor slab, laying a steel bar structure and embedded rebars in the RC slab, extending the embedded rebars outside the RC slab and winding them around the scaffolding, and constructing the floor slab as a first stage fixation of the scaffolding; embedding members used for screwing and fixing the wall connecting rods are embedded from the outside to the inside of the RC slab at intervals, and a horizontal aluminum profile is installed on the outside of the RC slab, one end of the wall connecting rod is inserted into the horizontal aluminum profile and fixed to the embedding member, and the other end of the wall connecting rod is fixed to the scaffolding, and then the embedded reinforcing bar is removed from the scaffolding to perform a second stage fixation of the scaffolding; a step of attaching the exterior wall panels between the floor slabs from the outside, separating the adjacent exterior wall panels by the horizontal aluminum profiles, and constructing the building exterior wall; Upon completion of the construction of the exterior wall of the building, removing the wall connecting rod and removing the scaffolding; A scaffolding installation method for a steel frame building, comprising:
7. The scaffolding erection method for steel frame buildings described in claim 6, characterized in that D10 bamboo joint rebar is used as the embedded rebar and the D10 bamboo joint rebar is wrapped around the scaffolding at least three and a half turns, thereby satisfying the fixing strength specified by regulations.
8. 7. The scaffolding erection method for a steel frame building according to claim 6, characterized in that after removing the embedded reinforcing bars from the scaffolding, the portion of the embedded reinforcing bars exposed from the RC slab is cut off.
9. 7. The scaffolding erection method for a steel frame building according to claim 6, wherein the embedded member is an expansion nut, and one end of the wall connecting rod is screwed and fixed to the expansion nut with a screw.
10. The scaffold erection method for a steel frame building according to claim 6, characterized in that after removing the wall connecting rod, the embedded member is screwed with a nut or filled with silicone and then flattened and sealed with paint.
Citation Information
Patent Citations
Method of executing curtain wall
JP1989021171A
Mounting structure for overhanging scaffolding
JP1994212782A
Curtain wall
JP2003213830A
Support member
JP3226742U