Construction method and transport platform used therein

The pre-assembly of refrigerant piping ducts with bent portions and connected pipes at a factory, followed by efficient on-site installation using a crane, addresses inefficiencies in conventional methods, reducing rooftop work and shortening construction timelines.

JP7551101B2Active Publication Date: 2024-09-17ENUPATTO
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
JP2020167161
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2020-10-01
Publication Date
2024-09-17
Estimated Expiration
2040-10-01

AI Technical Summary

Technical Problem

The conventional method for installing refrigerant piping on building rooftops is inefficient, requiring significant manual labor for bending and connecting pipes, which can lead to delays and increased liability due to tight construction schedules.

Method used

A construction method and transportation frame that pre-assemble refrigerant piping ducts with bent portions and connected pipes at a factory, allowing for simultaneous transportation and efficient installation on-site using a crane, minimizing on-site work and reducing the need for skilled labor.

Benefits of technology

This approach reduces the amount of work required on the rooftop, enhances installation efficiency, and shortens construction timelines while maintaining high work quality and reducing costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007551101000008
    Figure 0007551101000008
  • Figure 0007551101000003
    Figure 0007551101000003
  • Figure 0007551101000001
    Figure 0007551101000001
Patent Text Reader

Abstract

To reduce work done on a roof upon installing a refrigerant pipe on the roof of a building, to efficiently perform the work on the roof.SOLUTION: A construction method for installing a refrigerant pipe for air conditioning on a roof of a building, has a first step of forming a duct for a refrigerant pipe in a factory, a second step of arranging a plurality of refrigerant pipes machined to match the length and shape of the duct for a refrigerant pipe in a housing space inside the duct for a refrigerant pipe, a third step of preparing a stand on which a plurality of holding parts is arranged in a vertical direction, and arranging the duct for refrigerant piping in each of the plurality of holding parts, a fourth step of loading the stand on a loading platform of a transportation vehicle and transporting it to a construction site, a fifth step of picking up the stand with a crane and transporting it to the roof of the building at the construction site, and a sixth step of installing the duct for a refrigerant pipe at a predetermined position on the roof of the building, and connecting the plurality of refrigerant pipes housed in each of the plurality of ducts for a refrigerant pipe.SELECTED DRAWING: Figure 2
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a construction method for installing refrigerant piping for air conditioning on the roof of a building, and a transportation platform used for the method. [Background technology]

[0002] An outdoor unit of an air conditioning system is often installed on the roof of a building. At a construction site, when the outdoor unit is installed on the roof, multiple refrigerant pipes are laid to circulate the refrigerant from the outdoor unit to the heat exchange units on each floor.

[0003] Conventionally, a refrigerant piping duct has been used to lay refrigerant piping on the roof of a building (for example, Patent Documents 1 and 2). The refrigerant piping duct of Patent Document 1 has a support member in which the upper parts of a pair of parallel legs are connected to each other by a horizontal plate part, and is formed by arranging a pair of side wall members facing each other at a predetermined interval on the upper surface side of the horizontal plate part of the support member. In this refrigerant piping duct, a plurality of refrigerant pipes are arranged in an accommodation space inside the pair of side wall members. These plurality of refrigerant pipes are supported by the horizontal plate part of the support member that crosses the lower part of the pair of side wall members, and are held inside the pair of side wall members. After the plurality of refrigerant pipes are arranged in the accommodation space, a canopy is attached to the refrigerant piping duct so as to cover the upper opening of the pair of side wall members. The canopy is intended to prevent rainwater and the like from entering the accommodation space. In this type of refrigerant piping duct, the support members support the refrigerant piping in a state in which it is elevated above the rooftop structural surface (floor surface), so that the refrigerant piping can be protected from being submerged even if rainwater or the like flows over the structural surface. [Prior art documents] [Patent documents]

[0004] [Patent Document 1] JP 2016-11706 A [Patent Document 2] JP 2013-164140 A Summary of the Invention [Problem to be solved by the invention]

[0005] In the conventional construction method of the refrigerant piping duct as described above, first, the legs of the support member are fixed to the structural surface (floor surface) of the roof of the building using anchors or the like, and then, a pair of side wall members are attached to the upper surface side of the horizontal plate portion of the support member. In other words, the work of installing the refrigerant piping duct on the roof of the building is performed first. The refrigerant piping duct is rarely arranged in a straight line from the outdoor unit in the roof space, but is usually arranged while bending to avoid various obstacles installed on the roof. Then, after the refrigerant piping duct is installed on the roof, the refrigerant piping for guiding the refrigerant to each floor is arranged in the storage space inside the pair of side wall members.

[0006] The refrigerant pipes are brought to the rooftop of the building, which is the work site, as straight pipes of a predetermined length. Therefore, workers must bend the straight refrigerant pipes one by one as necessary and arrange them in an aligned state inside a pair of side wall members, which is not efficient. In addition, when connecting multiple refrigerant pipes, a skilled worker must braze them one by one, and the longer the length of the refrigerant pipe duct to be installed, the longer the construction time.

[0007] On the other hand, at new construction sites such as large buildings, the man-hours required to install refrigerant piping in the roof space are set according to the completion schedule. Usually, there is not much leeway in the man-hours, and any delays in the work will lead to liability issues, which places a heavy burden on the workers.

[0008] In view of the above circumstances, in recent years, there has been a demand for improving the efficiency of work required to install refrigerant piping in rooftop spaces, and in particular a reduction in the amount of work required on the roofs of buildings.

[0009] Therefore, the present invention has been made to solve the above-mentioned conventional problems, and has an object to provide a construction method and a transportation stand used therein that reduce the amount of work required on the roof when installing refrigerant piping on the roof of a building and enable the work to be performed efficiently. [Means for solving the problem]

[0010] In order to achieve the above object, first, the present invention provides a method for installing refrigerant piping for air conditioning on the roof of a building, comprising the steps of: installing a pair of legs parallel to each other at a factory; By horizontal joint Interconnected Support Members and preparing the connecting portion. a first step of forming a refrigerant piping duct of a predetermined length and a predetermined shape by arranging a pair of side wall members at a predetermined interval on an upper surface side of the refrigerant piping duct; and a second step of arranging a plurality of refrigerant pipes processed to fit the length and shape of the refrigerant piping duct in an accommodation space sandwiched between the pair of side wall members in the factory. The width dimension is smaller than the distance between the pair of legs, and the connecting portion is disposed between the pair of legs. a rack having a plurality of holding parts for holding the lower surface of the rack, the holding parts being arranged at predetermined intervals in the vertical direction; and a refrigerant piping duct, in which the plurality of refrigerant pipings are arranged within the storage space, is arranged for each of the plurality of holding parts; With the pair of legs hanging down from both sides in the width direction of each of the plurality of holding portions, The method includes a third step of holding the plurality of refrigerant piping ducts by the frame; a fourth step of loading the frame holding the plurality of refrigerant piping ducts onto the bed of a transport vehicle and transporting it from the factory to a construction site of the building; a fifth step of hoisting the frame with a crane at the construction site and transporting the refrigerant piping ducts to the roof of the building; and a sixth step of installing each of the plurality of refrigerant piping ducts at a predetermined position on the roof of the building and connecting the plurality of refrigerant pipes housed in each of the plurality of refrigerant piping ducts.

[0011] Secondly, the present invention is characterized in that, in the above-mentioned first installation method, the second step includes a step of attaching a canopy to cover upper openings of the pair of side wall members after arranging the plurality of refrigerant pipes in the storage space.

[0012] Thirdly, the present invention is characterized in that, in the first or second construction method, the frame is capable of separating each of the multiple holding parts, and the fifth step involves using the crane to lift up each of the multiple holding parts in turn from the top, thereby transporting the multiple refrigerant piping ducts one by one in sequence to the rooftop of the building.

[0013] Fourthly, the present invention is characterized in that in any one of the first to third installation methods, the refrigerant piping duct formed in the first step has a bent portion, and the second step includes a step of bending the refrigerant piping so as to fit the bent portion of the refrigerant piping duct.

[0014] Fifth, the present invention is characterized in that in any one of the first to fourth installation methods, the second step includes a step of connecting a plurality of refrigerant pipes according to the length of the refrigerant piping duct.

[0015] Sixth, the present invention is a pair of legs that are parallel to each other. By horizontal joint Interconnected Support Members and the connecting portion of the support member. A pair of side wall members standing at a predetermined distance from each other on the upper surface of the and A transportation platform for transporting a refrigerant piping duct in which a plurality of refrigerant pipings are arranged in advance in an accommodation space sandwiched between the pair of side wall members, The width dimension is smaller than the distance between the pair of legs, and the connecting portion is disposed between the pair of legs. The refrigerant piping duct can be transported simultaneously by holding the refrigerant piping duct with each holding part, and the holding parts are arranged at predetermined intervals in the vertical direction and hold the refrigerant piping ducts without interfering with each other. Each of the holding portions holds the lower surface of the connecting portion, thereby holding the refrigerant piping duct with the pair of legs hanging down on both sides in the width direction. The configuration is characterized by the above.

[0016] Seventh, the present invention provides a transportation platform having the configuration as described above in the sixth aspect, further comprising a plurality of pillars arranged at vertices of a rectangle in a plan view, and connecting members connecting the plurality of pillars to each other, and the plurality of holding portions are detachable at positions spaced a predetermined distance apart in the vertical direction of the pillars.

[0017] Eighth, the present invention provides a transportation platform having the seventh configuration, wherein the connecting members are detachable from the plurality of columns. Effect of the Invention

[0018] According to the present invention, it is possible to reduce the amount of work required on the roof of a building when installing refrigerant piping on the roof, and work on the roof can be performed efficiently. [Brief description of the drawings]

[0019] [Figure 1] FIG. 1 is a diagram showing an example of a construction state of refrigerant piping installed on the roof of a building. [Diagram 2] 1A to 1C are diagrams showing the steps of a construction method for installing air conditioning refrigerant piping on the roof of a building. [Diagram 3] FIG. 4 is a diagram showing a refrigerant piping duct formed in a first step. [Figure 4] 4 is a front view of the refrigerant piping duct in a state in which a pair of side wall members are attached to a support member. FIG. [Diagram 5] 13 is a diagram showing a refrigerant piping duct in which a refrigerant piping is arranged in a second step. FIG. [Figure 6] FIG. 1 is a diagram showing a refrigerant piping duct having a bent portion. [Figure 7] FIG. 11 is a diagram showing an example of a connecting step for connecting two refrigerant pipes. [Figure 8] FIG. 2 is a diagram showing an example of a configuration of a stand. [Figure 9] FIG. 13 is a diagram showing an example in which a plurality of refrigerant piping ducts are arranged on a rack. [Figure 10] FIG. 13 is a diagram showing an example of a transportation state of the stand. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0020] DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the drawings. In the drawings referred to below, common members are designated by the same reference numerals, and redundant description thereof will be omitted.

[0021] FIG. 1 is a diagram showing an example of a construction state of refrigerant pipes 20 installed on the roof of a building. As shown in FIG. 1, the refrigerant pipes 20 are installed on the roof of a building in a state in which they are held by a refrigerant pipe duct 10. The refrigerant pipe duct 10 is configured to include a roughly U-shaped support member 13 having a pair of legs 11, with the upper parts of the pair of legs 11 connected to each other, a pair of side wall members 14, 15 attached to the support member 13, and a canopy 17 attached to the upper parts of the pair of side wall members 14, 15. The support member 13 has a pair of legs fixed to the structural body surface (floor surface) of the roof of the building by anchors or the like, and supports the multiple refrigerant pipes 20 at a predetermined height position above the structural body surface. The pair of side wall members 14, 15 are covers for covering the sides of the multiple refrigerant pipes 20 supported by the support member 13. Additionally, the canopy 17 is a cover that closes the upper openings of the pair of side wall members 14, 15 and prevents rainwater and the like from entering the storage space in which the multiple refrigerant pipes 20 are arranged. The refrigerant piping duct 10 having such a configuration is installed in the section from the outdoor unit of the air conditioning system installed on the roof of a building to the openings leading to each floor, and prevents the refrigerant pipes 20 from being exposed to direct sunlight and wind and rain.

[0022] The refrigerant piping duct 10 installed on the roof is rarely installed in a straight line in the section from the outdoor unit to the opening leading to each floor, and the installation length varies. Therefore, the refrigerant piping duct 10 is provided with a bent section 19 or the installation length is adjusted by connecting multiple ducts 10a, 10b, 10c, 10d, and 10e as shown in Fig. 1. In the example shown in Fig. 1, the ducts 10a, 10c, and 10e are ducts that lay the refrigerant piping 20 in a straight line, and the ducts 10b and 10d are ducts that bend the path of the refrigerant piping 20 by 90 degrees.

[0023] The refrigerant pipes 20 arranged inside the refrigerant piping duct 10 are bent to fit the shape of the refrigerant piping duct 10 as described above, and are connected to each other to fit the length of the refrigerant piping duct 10. However, if such processing work is performed on the roof of a building as in the conventional method, the work efficiency is poor. Therefore, in this embodiment, the work performed on the roof of a building is minimized.

[0024] 2 is a diagram showing each step of a construction method for installing air-conditioning refrigerant pipes 20 on the roof of a building in this embodiment. The construction method in this embodiment has six steps from a first step ST1 to a sixth step ST6. Each of these steps will be described in detail below.

[0025] The first process ST1 is a process of forming a refrigerant piping duct 10 of a predetermined length and shape by arranging a pair of side wall members 14, 15 at a predetermined distance opposite each other on the upper surface of a support member 13 having a pair of parallel legs 11 connected to each other at the upper parts thereof, not at a construction site of a building but in a factory.

[0026] FIG. 3 is a diagram showing the refrigerant piping duct 10 formed in the first step ST1. In the first step ST1, as shown in FIG. 3(a), an operation of attaching a pair of side wall members 14, 15 to a support member 13 is performed in a factory. The support member 13 is a roughly U-shaped metal member in which the upper parts of a pair of legs 11, 11 are connected by a roughly horizontal connecting part 12. For example, the support member 13 is formed by bending a metal plate such as a stainless steel plate or a zinc-plated copper plate having a thickness of about 2 mm. The pair of side wall members 14, 15 are formed by bending a metal plate such as a zinc-plated copper plate having a thickness of about 1 to 2 mm. The pair of side wall members 14, 15 are disposed on the roughly horizontal connecting part 12 so as to face each other with a predetermined gap between them on the upper surface side, and are attached to the connecting part 12 using screws or the like.

[0027] Fig. 4 is a front view of the refrigerant piping duct 10 with the pair of side wall members 14, 15 attached to the support member 13. In the first step ST1, the pair of side wall members 14, 15 are attached to the connecting portion 12 of the support member 13 as shown in Fig. 4. That is, the pair of side wall members 14, 15 are attached in an upright state so as to face each other near both ends of the connecting portion 12 of the support member 13. As shown in Fig. 4, the distance between the pair of legs 11 of the support member 13 is W1. When the pair of side wall members 14, 15 are attached to the connecting portion 12 of the support member 13 in this manner, an accommodation space 16 for accommodating the refrigerant piping 20 is formed between the pair of side wall members 14, 15.

[0028] Next, the second process ST2 is a process of arranging multiple refrigerant pipes 20, which have been processed to fit the length and shape of the refrigerant piping duct 10, in the storage space 16 sandwiched between a pair of side wall members 14, 15 of the refrigerant piping duct 10 in a factory.

[0029] FIG. 5 is a diagram showing the refrigerant piping duct 10 in which the refrigerant piping 20 is arranged in the second step ST2. In the second step ST2, as shown in FIG. 5(a), a plurality of refrigerant pipings 20 are arranged in the accommodation space 16 of the refrigerant piping duct 10 in a factory. As shown in FIG. 5(b), these plurality of refrigerant pipings 20 are supported by the connecting portion 12 of the support member 13 that crosses the lower portion of the pair of side wall members 14, 15. The number of refrigerant pipings 20 arranged in the accommodation space 16 varies depending on the scale of the building. For example, the larger the scale of the building, the more the number of refrigerant pipings 20 arranged in the accommodation space 16 increases, and the work time for arranging the refrigerant pipings 20 becomes longer. Therefore, there is an advantage that the work to be done at the construction site can be reduced by forming the refrigerant piping duct 10 in the factory in the first step ST1 at the factory, and then arranging the refrigerant pipings 20 in advance in the accommodation space 16 inside the refrigerant piping duct 10 in the second step ST2.

[0030] In the second step ST2, for example, it is preferable to connect the straight duct 10a and the bent duct 10b to each other to form the refrigerant piping duct 10 having the bent portion 19, and to arrange a plurality of refrigerant pipes 20 in the refrigerant piping duct 10. FIG. 6 is a diagram showing the refrigerant piping duct 10 having the bent portion 19. When arranging the refrigerant piping 20 in the refrigerant piping duct 10 having the bent portion 19, it is necessary to bend the refrigerant piping 20 according to the angle of the bent portion 19. Therefore, the second step ST2 includes a step of bending the refrigerant piping 20 so as to fit the bent portion 19 of the refrigerant piping duct 10. The work of bending the refrigerant piping 20 according to the bent angle of the refrigerant piping duct 10 requires a certain degree of skill. Therefore, the bending process of the refrigerant piping 20 is performed in advance in a factory, and the refrigerant piping 20 is arranged inside the refrigerant piping duct 10 having the bent portion 19, thereby reducing the work to be performed at the construction site.

[0031] The second step ST2 includes a connecting step of connecting the plurality of refrigerant pipes 20 in series according to the length of the refrigerant pipe duct 10. FIG. 7 is a diagram showing an example of a connecting step of connecting two refrigerant pipes 20a, 20b. As shown in FIG. 7(a), the refrigerant pipes 20a, 20b have metal pipes 21a, 21b made of copper pipes or the like, and heat insulating materials 22a, 22b covering the outer circumferential surfaces of the metal pipes 21a, 21b. The heat insulating materials 22a, 22b are flexible members made of, for example, polyethylene foam. When these two refrigerant pipes 20a, 20b are connected, the metal pipes 21a, 21b are connected by a connecting method such as brazing. At this time, the two metal pipes 21a, 21b may be connected using a joint or the like. When the two metal pipes 21a, 21b are connected, a heat insulating member 23 made of polyethylene foam or the like is wrapped around the connection portion 20c as shown in FIG. 7(b). The heat insulating member 23 ensures the heat insulating performance of the connection part 20c. The work of connecting the two refrigerant pipes 20a, 20b to each other in this manner requires a certain degree of skill. Therefore, when arranging the refrigerant pipes 20 inside the refrigerant piping duct 10, the two refrigerant pipes 20a, 20b can be connected in advance at a factory as necessary, thereby reducing the work to be done at the construction site.

[0032] Furthermore, the second step ST2 may include a step of attaching a canopy 17 to the refrigerant piping duct 10 after arranging the multiple refrigerant pipes 20 inside the refrigerant piping duct 10, as necessary. However, it is expected that the canopy 17 will get in the way when the multiple refrigerant piping ducts 10 fabricated in a factory are connected at a construction site. Therefore, the canopy 17 may be attached to the refrigerant piping duct 10 in a temporarily fastened state. Also, the canopy 17 may be attached at the construction site, and the canopy 17 may not be attached to the refrigerant piping duct 10 in the second step ST2 performed at the factory.

[0033] When the second step ST2 is performed in this manner, the refrigerant piping duct 10 is formed in the factory, in which the multiple refrigerant pipes 20 are arranged. Note that the length of the refrigerant piping duct 10 formed at the end of the second step ST2 is preferably long enough to allow the refrigerant piping duct 10 to be loaded onto a transportation vehicle. Therefore, the refrigerant piping duct 10 to be installed on the roof of a building is formed as multiple refrigerant piping ducts 10 having a predetermined length or less at the end of the second step ST2.

[0034] Next, the third step ST3 is a step of preparing a stand 30 for holding the plurality of refrigerant piping ducts 10 in a factory, and arranging the plurality of refrigerant piping ducts 10 on the stand 30.

[0035] FIG. 8 is a diagram showing an example of the configuration of the stand 30. The stand 30 is a stand that holds a plurality of refrigerant piping ducts 10 that are cut to a predetermined length or less so as not to interfere with each other, and is a transport stand used to transport a plurality of refrigerant piping ducts 10 from a factory to a construction site. As shown in FIG. 8, the stand 30 has four support columns 31 that are provided at the four corners of a rectangle in a plan view and stand upright in a state parallel to each other, wheels 32 provided at the lower ends of the four support columns 31, a connecting member 33 that connects the lower parts of the four support columns 31 to each other, and a plurality of holding parts 36 that can be attached and detached to different height positions of the four support columns 31. Each support column 31 is provided with a plurality of mounting parts 35 for mounting the holding parts 36 at a predetermined interval in the height direction, and the holding parts 36 can be attached to the mounting parts 35. For example, the intervals between the plurality of mounting parts 35 are set to be slightly larger than the height dimension of the refrigerant piping duct 10. The mount 30 of this embodiment has mounting parts 35 at three locations on one support 31, and three holding parts 36 can be attached to these mounting parts 35. Incidentally, the support 31 in this embodiment is made of a cylindrical metal pipe, but is not limited to this.

[0036] Such a frame 30 is, for example, a frame having a rectangular shape in a plan view, short in the X direction and long in the Y direction. The length of the frame 30 in the Y direction may be designed according to the length of the refrigerant piping duct 10 formed in a factory, for example. The size of the frame 30 can be arbitrarily adjusted by changing the length of the connecting member 33.

[0037] The connecting member 33 has clamps 34 at both ends. The clamps 34 are for attaching and detaching the connecting member 33 to the support posts 31. In other words, the connecting member 33 is configured to be attachable and detachable to the support posts 31. When the connecting member 33 is detached from the support posts 31, the pedestal 30 can be carried with the four support posts 31 disassembled.

[0038] The holding portion 36 has a holding member 37 for holding the lower surface of the refrigerant piping duct 10, mounting rods 38 provided on both ends of the holding member 37, and insertion pieces 39 provided on both ends of the mounting rod 38. The holding member 37 is configured by disposing a metal mesh inside a metal frame as shown in FIG. 8, for example. However, the present invention is not limited to this, and the holding member 37 may be configured by two metal rods parallel to each other. The length of the holding member 37 in the Y direction is a length that matches the length of the frame 30 in the Y direction. In addition, the width W2 of the holding member 37 in the X direction is formed to be smaller than the interval W1 (see FIG. 4) between the pair of legs 11, 11 of the refrigerant piping duct 10. Such a holding portion 36 is attached to the support 31 by inserting the insertion pieces 39 provided on both ends of the mounting rod 38 into the mounting portions 35 provided on each support 31 from above. In addition, a mechanism for preventing the insertion piece 39 from coming out of the mounting part 35 when the insertion piece 39 is inserted into the mounting part 35 may be provided on either the support 31 or the insertion piece 39. In this embodiment, the insertion piece 39 is inserted into each mounting part 35 provided at three positions in the vertical direction of the support 31, so that three holding parts 36 can be installed on the gantry 30. In addition, the gantry 30 of this embodiment shows an example in which three holding parts 36 can be attached to three mounting parts 35 arranged at a predetermined interval in the vertical direction, but the number of holding parts 36 attached to the gantry 30 is not limited to this. In other words, the gantry 30 may be one in which two or more holding parts 36 can be attached.

[0039] Fig. 9 is a diagram showing an example in which a plurality of refrigerant piping ducts 10 are arranged on a stand 30. As shown in Fig. 9, the stand 30 holds the lower surface of the refrigerant piping duct 10 with each of a plurality of holding portions 36. That is, since the width W2 of the holding portion 36 is smaller than the interval W1 between the pair of legs 11, 11 of the support member 13, the holding portion 36 is disposed between the pair of legs 11, 11 and holds the lower surface of the connecting portion 12 of the support member 13. In addition, the plurality of holding portions 36 hold the plurality of refrigerant piping ducts 10 at a predetermined interval in the vertical direction without causing the plurality of refrigerant piping ducts 10 to interfere with each other.

[0040] In this way, the rack 30 can hold the plurality of refrigerant piping ducts 10 without damaging them by vertically stacking the plurality of refrigerant piping ducts 10 on each of the plurality of holding portions 36. That is, as described above, the pair of side wall members 14, 15 of the refrigerant piping duct 10 are thin, about 1 to 2 mm thick, and easily dented and damaged when an external force acts on the side wall surface. In addition, although the pair of legs 11, 11 of the support member 13 are reinforced to some extent by forming ribs or the like by bending, the base material is thin, about 1 to 2 mm thick, and easily bent and damaged when an external force acts on the pair of legs 11, 11 from the lateral direction. Therefore, in this embodiment, the holding portion 36 holds the underside of the connecting portion 12 of the support member 13, so that the stand 30 can hold the refrigerant piping duct 10 without external force acting on the side wall members 14, 15 or the pair of legs 11, 11, preventing damage to the side wall members 14, 15 and the pair of legs 11, 11 during transportation of the refrigerant piping duct 10.

[0041] In addition, since wheels 32 are provided on the bottom of the stand 30, the work vehicle can easily move the stand 30 even when multiple refrigerant piping ducts 10 are loaded on it as shown in Fig. 9. It is preferable that the stand 30 is provided with a wheel lock mechanism that prohibits the wheels 32 from rolling.

[0042] Next, the fourth step ST4 is a step of loading the frame 30 holding the multiple refrigerant piping ducts 10 onto the bed of a transport vehicle and transporting it to the construction site. For example, a crane or the like is used to load the frame 30 holding the multiple refrigerant piping ducts 10 onto the transport vehicle. When the frame 30 is loaded onto the transport vehicle, the wheels 32 are locked and the frame 30 is fixed to the bed. FIG. 10 is a diagram showing the state of the frame 30 in the fourth step ST4. As shown in FIG. 10, the frame 30 is transported from the factory to the construction site while being loaded onto the transport vehicle 50. At the construction site, a building 60 is being constructed, and a crane 61 is installed on the roof of the building 60. When the transport vehicle 50 arrives at the construction site, the process proceeds to the fifth step ST5. Note that the fifth step ST5 and subsequent steps are steps performed at the construction site.

[0043] The fifth step ST5 is a step of lifting the stand 30 with a crane 61 at the construction site and transporting the refrigerant piping duct 10 to the roof of the building 60. The crane 61 may lift the stand 30 holding the multiple refrigerant piping ducts 10 as a whole and transport the multiple refrigerant piping ducts 10 to the roof in one lifting operation. However, this is not limited to this, and the crane 61 may lift the refrigerant piping ducts 10 held by the holding parts 36 one by one from the upper side of the stand 30 and transport them to the roof. When lifting the refrigerant piping ducts 10 one by one, by releasing the anti-pullout mechanism provided on either the support 31 or the insertion piece 39, the crane 61 lifts the holding part 36 and the refrigerant piping duct 10, and the insertion piece 39 is pulled out from the mounting part 35 and can be lifted as it is. Therefore, the work efficiency is excellent.

[0044] Thereafter, a task of temporarily arranging the plurality of refrigerant piping ducts 10 in their respective installation positions is performed on the rooftop of the building 60. In this temporary arrangement task, the crane 61 may be used, as described above. Once the plurality of refrigerant piping ducts 10 have been temporarily arranged on the rooftop of the building, the process proceeds to a sixth step ST6.

[0045] The sixth step ST6 is a step of connecting the multiple refrigerant pipes 20 housed in the multiple refrigerant pipe ducts 10 to each other while installing each of the multiple refrigerant pipe ducts 10 temporarily arranged on the roof of the building 60 at a predetermined appropriate position. The multiple refrigerant pipes 20 are already arranged inside the refrigerant pipe ducts 10 temporarily arranged on the roof. Therefore, the worker does not need to arrange the refrigerant pipes 20 inside the refrigerant pipe ducts 10 one by one on the roof of the building 60, but only needs to connect the refrigerant pipes 20 arranged in the refrigerant pipe ducts 10 adjacent to each other. In addition, the worker does not need to bend the refrigerant pipes 20 on the roof of the building 60 by bending the refrigerant pipes 20 in advance and arranging them in the refrigerant pipe ducts 10 in the factory. Therefore, the construction method of this embodiment can significantly reduce the work to be performed on the roof of the building 60 compared to the conventional construction method. In addition, in the sixth step ST6, a task of attaching and fixing the canopy 17 to the upper part of the pair of side wall members 14, 15 is performed as necessary. Then, in this embodiment, finally, the legs 11 of the refrigerant piping duct 10 may be fixed to the rooftop structural surface (floor surface) using anchors or the like. As a result, the installation of the refrigerant piping duct 10 with a plurality of refrigerant pipes 20 arranged inside, as shown in FIG. 1, is completed on the rooftop of the building 60.

[0046] In this manner, in the construction method of the present embodiment, a plurality of refrigerant pipes 20 are arranged in the refrigerant pipe duct 10 in a factory, and the refrigerant pipe duct 10 with the plurality of refrigerant pipes 20 arranged therein is brought onto the roof of the building 60, thereby reducing the amount of work to be performed on the roof of the building 60. In particular, in the construction method of the present embodiment, some of the bending process for the straight refrigerant pipe 20 and the brazing process for connecting the plurality of refrigerant pipes 20 are performed in advance in the factory, thereby reducing the amount of work that was conventionally performed on the roof of the building 60. Therefore, the work of installing the refrigerant pipes 20 on the roof can be performed efficiently, and no work delays occur. Rather, the construction method of the present embodiment is a construction method that can shorten the construction period at the construction site.

[0047] In addition, the rack 30 used in this embodiment can simultaneously transport a plurality of refrigerant piping ducts 10 from a factory to a construction site while holding the plurality of refrigerant piping ducts 10. This provides excellent transport efficiency and reduces transport costs. Therefore, the construction method of this embodiment is excellent in that it can shorten the construction period at the construction site without increasing construction costs.

[0048] In addition, after the platform 30 is carried onto the roof of the building 60, each component can be disassembled, and workers can take it down from the roof using an elevator or the like of the building 60. In other words, there is no need to use the crane 61 when carrying the platform 30 out of the roof, which is an advantage in that the platform 30 can be carried out efficiently.

[0049] Although one embodiment of the present invention has been described above, the present invention is not limited to the embodiment described above. In other words, the present invention includes various modified examples of the embodiment described above.

[0050] For example, in the above embodiment, the pedestal 30 holds a plurality of refrigerant piping ducts 10 in a vertical row. However, the pedestal 30 may be configured to include a plurality of holding portions 36 not only in the vertical direction but also in the horizontal direction, so that a larger number of refrigerant piping ducts 10 can be transported at the same time. [Explanation of symbols]

[0051] ST1...first step, ST2...second step, ST3...third step, ST4...fourth step, ST5...fifth step, ST6...sixth step, 10...duct for refrigerant piping, 11...legs, 13...support members, 14, 15...side wall members, 16...storage space, 20...refrigerant piping, 30...frame (transport frame), 31...pillars, 33...connecting members, 36...holding portion, 60...building, 61...crane.

Claims

1. A construction method for installing refrigerant piping for air conditioning on the roof of a building, comprising the steps of: a first step of preparing a support member in a factory, in which a pair of parallel legs are connected at their upper portions by a horizontal connecting part, and arranging a pair of side wall members on the upper surface of the connecting part at a predetermined distance to face each other, thereby forming a refrigerant piping duct of a predetermined length and a predetermined shape; a second step of arranging, in the factory, a plurality of refrigerant pipes processed to fit the length and shape of the refrigerant piping duct in an accommodation space sandwiched between the pair of side wall members of the refrigerant piping duct; a third step of preparing a stand having a width dimension smaller than the distance between the pair of legs, the stand having a plurality of holding parts disposed between the pair of legs and holding an underside of the connecting part at a predetermined distance in the vertical direction, disposing the refrigerant piping duct in which the plurality of refrigerant pipes are disposed within the storage space for each of the plurality of holding parts, and holding the plurality of refrigerant piping ducts by hanging the pair of legs from both sides in the width direction of each of the plurality of holding parts; a fourth step of loading the frame holding the plurality of refrigerant piping ducts onto a loading platform of a transport vehicle and transporting the frame from the factory to a construction site of the building; A fifth step of lifting the frame with a crane at the construction site and transporting the refrigerant piping duct to a roof of the building; a sixth step of installing each of the plurality of refrigerant piping ducts at a predetermined position on the rooftop of the building and connecting a plurality of refrigerant pipes housed in each of the plurality of refrigerant piping ducts; A construction method comprising the steps of:

2. 2. The installation method according to claim 1, wherein the second step includes a step of attaching a canopy to cover upper openings of the pair of side wall members after arranging the plurality of refrigerant pipes in the storage space.

3. The base is capable of separating each of the plurality of holding portions, The construction method according to claim 1 or 2, characterized in that the fifth step comprises using the crane to lift up each of the plurality of holding parts in turn from the top tier, thereby transporting the plurality of refrigerant piping ducts one by one in turn to the roof of the building.

4. The refrigerant piping duct formed in the first step has a bent portion, 4. The installation method according to claim 1, wherein the second step includes a step of bending the refrigerant piping so as to fit the bent portion of the refrigerant piping duct.

5. 5. The installation method according to claim 1, wherein the second step includes a step of connecting a plurality of refrigerant pipes according to a length of the refrigerant piping duct.

6. A transportation platform for transporting a refrigerant piping duct, the transportation platform having a support member in which upper portions of a pair of parallel legs are mutually connected by a horizontal connecting portion, and a pair of side wall members standing at a predetermined distance from each other on upper surfaces of the connecting portions of the support member, the refrigerant piping duct having a plurality of refrigerant pipings previously arranged within an accommodation space sandwiched between the pair of side wall members, a width dimension of the refrigerant piping duct is smaller than the distance between the pair of legs, the refrigerant piping duct has a plurality of holding parts disposed between the pair of legs for holding a lower surface of the connecting part, and the refrigerant piping duct can be simultaneously transported by holding the refrigerant piping duct with each holding part; The plurality of holding portions are arranged at predetermined intervals in the vertical direction and hold the plurality of refrigerant piping ducts without interfering with each other, A transportation stand characterized in that each holding portion holds the underside of the connecting portion, thereby holding the refrigerant piping duct with the pair of legs hanging down on both sides in the width direction.

7. A plurality of support columns are arranged at vertices of a rectangular shape in a plan view; A connecting member that connects the plurality of columns to each other; Further comprising:

7. The transportation platform according to claim 6, wherein the plurality of holding parts are detachably attached to the support pole at positions spaced apart by a predetermined distance in the vertical direction.

8. 8. The transportation platform according to claim 7, wherein the connecting members are detachable from the plurality of columns.

Citation Information

Patent Citations

  • Conduit gas-insulated transmission line and its assembling and installing method

    JP1997130945A

  • Storage rack

    JP2008061675A

  • Piping cover

    JP2013164140A

  • Long body cover and construction method thereof

    JP2016011706A

  • Air-conditioning pipe installation facility and air-conditioning piping installation method

    JP2019219111A