POWER GENERATION PLANNING METHOD FOR FUEL CELL DEVICE, POWER GENERATION PLANNING DEVICE FOR FUEL CELL DEVICE, AND POWER GENERATION SYSTEM

The power generation planning method for fuel cell devices extends the remaining period of power generation plans to prevent unnecessary start-stops, ensuring appropriate operation and extending the device's lifespan.

JP7555013B1Active Publication Date: 2024-09-24PANASONIC INTELLECTUAL PROPERTY MANAGEMENT CO LTD
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
JP2024506225
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Priority Date
2022-11-21
Filing Date
2023-08-31
Publication Date
2024-09-24
Estimated Expiration
2043-08-31

AI Technical Summary

Technical Problem

Existing power generation planning methods for fuel cell devices do not adequately address the issue of power generation plan expiration, leading to unnecessary starting and stopping, which can shorten the lifespan of the fuel cell device.

Method used

A power generation planning method that includes receiving and storing power generation plans, and if the next plan is not received, extending the remaining period of the stored plan to be equal to or longer than a predetermined period by repeating the last unit period or adding data to cover the difference between the predetermined and remaining periods.

Benefits of technology

This approach ensures appropriate power generation planning for fuel cell devices, preventing unnecessary start-stops and extending the device's operational lifespan.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007555013000003
    Figure 0007555013000003
  • Figure 0007555013000004
    Figure 0007555013000004
  • Figure 0007555013000010
    Figure 0007555013000010
Patent Text Reader

Abstract

The power generation planning method for a fuel cell device disclosed herein comprises the steps of receiving a power generation plan for the fuel cell device, storing the received power generation plan for the fuel cell device, and, when the next power generation plan is not received and the remaining period of the stored power generation plan becomes less than a predetermined period, using data of the stored power generation plan to add a power generation plan so that the remaining period of the power generation plan is equal to or greater than the predetermined period.
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present disclosure relates to a power generation planning method for a fuel cell device, a power generation planning device for a fuel cell device, and a power generation system. [Background technology]

[0002] Various proposals have been made in the past regarding output control of a power generation system. As an example, Patent Document 1 discloses a system in which a plurality of power generation devices are divided into scheduled operation power generation devices and non-scheduled operation power generation devices. For example, it is described that the total power output value of the non-scheduled operation power generation devices is calculated by subtracting the total power output value of the scheduled operation power generation devices from the power consumption of the load equipment to which the plurality of power generation devices are supplied. It is also described that an operation command is issued to the scheduled operation power generation devices based on a schedule and power output value recorded in advance, and an operation command is issued to the non-scheduled operation power generation devices at a predetermined time interval based on the total calculated power output value. [Prior art documents] [Patent documents]

[0003] [Patent Document 1] Patent No. 4864739 Summary of the Invention [Problem to be solved by the invention]

[0004] An object of the present disclosure is to provide, as an example, a power generation planning method for a fuel cell device, a power generation planning device for a fuel cell device, and a power generation system that can plan power generation in a fuel cell device more appropriately than in the past. [Means for solving the problem]

[0005] In order to solve the above problems, a power generation planning method for a fuel cell device according to one aspect of the present disclosure includes the steps of receiving a power generation plan for the fuel cell device, storing the received power generation plan for the fuel cell device, and, when the next power generation plan is not received and the remaining period of the stored power generation plan falls below a predetermined period, using data of the stored power generation plan to add a power generation plan so that the remaining period of the power generation plan is equal to or greater than the predetermined period.

[0006] In addition, a power generation planning device for a fuel cell device of one embodiment of the present disclosure includes a communicator that receives a power generation plan for the fuel cell device, a memory that stores the received power generation plan for the fuel cell device, and a controller that, when the next power generation plan is not received via the communicator and the remaining period of the power generation plan stored in the memory becomes less than a predetermined period, uses data of the power generation plan stored in the memory to add a power generation plan so that the remaining period of the power generation plan is equal to or greater than the predetermined period.

[0007] A power generation system according to an aspect of the present disclosure includes a fuel cell device and the power generation planning device for the fuel cell device. Effect of the Invention

[0008] The power generation planning method for a fuel cell device, the power generation planning device for a fuel cell device, and the power generation system according to one aspect of the present disclosure provide an effect of enabling more appropriate power generation planning for a fuel cell device than ever before. [Brief description of the drawings]

[0009] [Figure 1] FIG. 1 is a diagram illustrating an example of a power generation system according to a first embodiment. [Diagram 2] FIG. 2 is a flowchart showing an example of the operation of the power generation planning device (power generation planning method) in the power generation system of the first embodiment. [Figure 3A] FIG. 3A is a flowchart showing an example of the operation of the power generation planning device (power generation planning method) in the power generation system of the first example of the first embodiment. [Figure 3B]FIG. 3B is a diagram for explaining a specific example of the operation of step S4A in FIG. 3A. [Figure 4A] FIG. 4A is a flowchart showing an example of the operation of the power generation planning device (power generation planning method) in the power generation system of the second example of the first embodiment. [Figure 4B] FIG. 4B is a diagram for explaining a specific example of the operation of step S4B in FIG. 4A. [Diagram 5] FIG. 5 is a flowchart showing an example of the operation of the power generation planning device (power generation planning method) in the power generation system of the third example of the first embodiment. [Figure 6A] FIG. 6A is a flowchart showing an example of the operation of the power generation planning device (power generation planning method) in the power generation system according to the modified example of the first embodiment. [Figure 6B] FIG. 6B is a diagram for explaining a specific example of the operation in step S6 in FIG. 6A. [Figure 7] FIG. 7 is a diagram illustrating an example of a power generation system according to the second embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0010] In Patent Document 1, the operation of the power generation device when the period of the power generation plan falls short of a predetermined period is not considered. Therefore, there is no sufficient consideration of how to respond to a case where the next power generation plan in the power generation device is not received and the remaining period of the power generation plan stored in the memory falls short of the predetermined period.

[0011] Therefore, the power generation planning method for a fuel cell device of the first aspect of the present disclosure includes the steps of receiving a power generation plan for the fuel cell device, storing the received power generation plan for the fuel cell device, and, when the next power generation plan is not received and the remaining period of the stored power generation plan becomes less than a predetermined period, using data of the stored power generation plan to add a power generation plan so that the remaining period of the power generation plan is equal to or greater than the predetermined period.

[0012] According to the above, the power generation planning method for the fuel cell device of this aspect can plan the power generation of the fuel cell device more appropriately than ever before.

[0013] For example, if the next power generation plan in the fuel cell device is not received and the remaining period of the power generation plan stored in the memory falls below a predetermined period, the power generation of the fuel cell device, which would have continued if the next power generation plan had been received, may be stopped. This may cause the fuel cell device to start and stop more than necessary, which may lead to a shortened lifespan. However, in the power generation planning method for the fuel cell device of this embodiment, when the remaining period of the stored power generation plan falls below the predetermined period, the stored power generation plan data is used to add a power generation plan so that the remaining period of the power generation plan is equal to or greater than the predetermined period, thereby making it possible to operate the fuel cell device appropriately for the predetermined period, compared to a state in which the remaining period of the power generation plan remains less than the predetermined period.

[0014] A second aspect of the power generation planning method for a fuel cell device of the present disclosure may be such that, in the power generation planning method for a fuel cell device of the first aspect, the remaining period of the power generation plan is set to a predetermined period or longer by repeating data of the last unit period of the stored power generation plan.

[0015] According to the above, the power generation planning method of the fuel cell device of this aspect can add a power generation plan so that the remaining period of the power generation plan becomes equal to or longer than the predetermined period by repeating the data of the last unit period of the stored power generation plan, even if the next power generation plan in the fuel cell device is not received and the remaining period of the power generation plan stored in the memory falls below the predetermined period. Therefore, the power generation planning method of the fuel cell device of this aspect can operate the fuel cell device appropriately for the predetermined period, compared to a state in which the remaining period of the power generation plan remains less than the predetermined period.

[0016] A third aspect of the power generation planning method for a fuel cell device of the present disclosure may, in the power generation planning method for a fuel cell device of the first aspect, extract data for a period corresponding to the difference between a predetermined period and the remaining period from the stored power generation plan, and add this data to make the remaining period of the power generation plan longer than the predetermined period.

[0017] According to the above, the power generation planning method of the fuel cell device of this aspect can extract data for a period corresponding to the difference between the predetermined period and the remaining period from the stored power generation plan, and add this data to add a power generation plan so that the remaining period of the power generation plan is equal to or greater than the predetermined period, even if the next power generation plan in the fuel cell device is not received and the remaining period of the power generation plan stored in the memory falls short of the predetermined period. Thus, the power generation planning method of the fuel cell device of this aspect can operate the fuel cell device appropriately for a predetermined period, compared to a state in which the remaining period of the power generation plan remains less than the predetermined period.

[0018] A fourth aspect of the power generation planning method for a fuel cell device of the present disclosure includes a step of receiving first information indicating whether to select the power generation planning method for the fuel cell device of the second aspect or the power generation planning method for the fuel cell device of the third aspect, and may execute either the power generation plan addition method for the fuel cell device of the second aspect or the power generation plan addition method for the fuel cell device of the third aspect based on this first information.

[0019] As described above, the power generation planning method of the fuel cell device of this embodiment is capable of receiving first information indicating whether to select the power generation planning method of the fuel cell device of the second embodiment or the power generation planning method of the fuel cell device of the third embodiment, thereby allowing the fuel cell device to operate more appropriately compared to executing the power generation plan of the fuel cell device without receiving such first information.

[0020] A fifth aspect of the present disclosure is a power generation planning method for a fuel cell device, in any one of the first to fourth aspects, which includes a step of receiving second information indicating that no additions will be made to the power generation plan of the fuel cell device, and upon receiving the second information, no additions may be made to the power generation plan of the fuel cell device.

[0021] As described above, the power generation planning method for the fuel cell device of this embodiment is capable of receiving second information indicating that no additions will be made to the power generation plan for the fuel cell device, thereby allowing the fuel cell device to be stopped in a more timely manner compared to the case where the power generation plan for the fuel cell device is executed without receiving the second information.

[0022] A power generation planning device for a fuel cell device of a sixth aspect of the present disclosure includes a communication device that receives a power generation plan for the fuel cell device, a memory device that stores the received power generation plan for the fuel cell device, and a controller that, when the next power generation plan is not received via the communication device and the remaining period of the power generation plan stored in the memory becomes less than a predetermined period, uses data of the power generation plan stored in the memory to add a power generation plan so that the remaining period of the power generation plan is equal to or greater than the predetermined period.

[0023] With this configuration, the power generation planning device for the fuel cell device of this aspect can plan the power generation of the fuel cell device more appropriately than ever before. Note that the details of the effects and advantages of the power generation planning device for the fuel cell device of this aspect are similar to those of the power generation planning method for the fuel cell device of the first aspect, and therefore will not be described here.

[0024] A power generation system according to a seventh aspect of the present disclosure includes a fuel cell device and the power generation planning device for the fuel cell device according to the sixth aspect.

[0025] With this configuration, the power generation system of this aspect can plan the power generation of the fuel cell device more appropriately than in the past. Note that the detailed effects of the power generation system of this aspect are similar to those of the power generation planning method of the first aspect of the fuel cell device, and therefore will not be described here.

[0026] Hereinafter, specific examples of the above-mentioned aspects of the present disclosure will be described with reference to the accompanying drawings. The specific examples described below are all examples of the above-mentioned aspects of the present disclosure. Therefore, the shapes, numerical values, components, arrangement positions and connection forms of the components shown below do not limit the scope of the claims unless otherwise stated in the claims.

[0027] In addition, among the components described below, components that are not described in the independent claims showing the highest concept of the present disclosure are described as optional components. In addition, in the drawings, the description of components with the same reference numerals may be omitted. The drawings show each component diagrammatically to facilitate understanding, and the shapes and dimensional ratios may not be displayed accurately.

[0028] Furthermore, in the operation of the apparatus, the order of steps may be changed or known steps may be added as necessary.

[0029] (First embodiment) [Device configuration] FIG. 1 is a diagram illustrating an example of a power generation system according to a first embodiment.

[0030] 1, a power generation system 10 of this embodiment includes a fuel cell device 15 and a power generation planning device 20 for the fuel cell device 15. This power generation system 10 may be, for example, a system that supplies large amounts of power to a power grid. In this case, the fuel cell device 15 includes a power generation unit group consisting of a plurality of power generation units including a fuel cell stack, and the detailed configuration of such a power generation system 10 will be described in the second embodiment.

[0031] In the example shown in FIG. 1, the power generation planning device 20 includes a communication device 21, a storage device 22, and a controller .

[0032] The communicator 21 is a receiver that receives the power generation plan of the fuel cell device 15. For example, the communicator 21 may receive the power generation plan transmitted from a terminal or a server via a communication network for each unit period.

[0033] The "unit period" may be, for example, about 30 minutes, but is not limited to this. The "unit period" may be set to an appropriate period based on the configuration of the power generation system 10, etc.

[0034] The users of the terminals or servers include direct or indirect users of the power generation planning device 20. A direct user of the power generation planning device 20 is, for example, an administrator of the power generation planning device 20. An indirect user of the power generation planning device 20 can be, for example, an owner of the power generation system 10. Such an owner may be a consumer who receives the service of supplying power generated by the power generation system 10, or a power generation business operator who supplies power to consumers using the power generation system 10.

[0035] The storage device 22 is a memory for storing the power generation plan of the fuel cell device 15 received via the communication device 21 .

[0036] When the next power generation plan for the fuel cell device 15 is not received from the terminal or server via the communication device 21 and the remaining period of the power generation plan stored in the memory device 22 falls below a predetermined period, the controller 23 uses the data of the power generation plan stored in the memory device 22 to add a power generation plan so that the remaining period of the power generation plan is equal to or longer than the predetermined period.

[0037] Here, examples of "when the next power generation plan of the fuel cell device 15 is not received via the communication device 21" include, but are not limited to, cases where a communication failure occurs in the communication network or where the energy management system breaks down.

[0038] The "predetermined period" may be, for example, "three days," but is not limited to this. The "predetermined period" may be set to an appropriate period based on the configuration of the power generation system 10, etc.

[0039] The controller 23 may be any device having a control function, and includes an arithmetic processing unit (not shown) and a storage unit that stores a control program. The arithmetic processing unit reads out and executes the control program stored in the storage unit, thereby performing predetermined control in the controller 23. An example of the arithmetic processing unit is a microprocessor. An example of the storage unit is a memory.

[0040] [Operation] 2 is a flowchart showing an example of the operation of the power generation planning device (power generation planning method) in the power generation system of the first embodiment. The following operation may be performed, for example, by the calculation processing unit of the controller 23 reading out a control program from the storage unit of the controller 23. However, it is not essential that the following operation is performed by the controller 23. An operator may perform some of the operations. In the following example, a case where the operation is controlled by the controller 23 will be described.

[0041] First, when the operation of the power generation planning device 20 starts, in step S1, the power generation plan of the fuel cell device 15 is received via the communication device 21. For example, the power generation plan transmitted from a terminal or a server via a communication network may be received for each unit period.

[0042] Next, in step S2, the power generation plan of the fuel cell device 15 received via the communication device 21 is stored in the memory device 22.

[0043] Next, in step S3, it is determined whether the remaining period of the power generation plan stored in the memory 22 is equal to or longer than a predetermined period.

[0044] If the remaining period of the power generation plan stored in memory 22 is equal to or longer than a predetermined period ("Yes" in step S3), operations from step S1 onwards may be re-executed to receive the next power generation plan of the fuel cell device 15 via communication device 21.

[0045] Here, if the next power generation plan for the fuel cell device 15 is not received via the communication device 21 and the remaining period of the power generation plan stored in the memory device 22 becomes less than the specified period (if the answer is "No" in step S3), then in step S4, a process is performed to add a power generation plan using the data of the power generation plan stored in the memory device 22 so that the remaining period of the power generation plan for the fuel cell device 15 becomes equal to or greater than the specified period.

[0046] When the above-mentioned operation of the power generation planning device 20 is completed, power generation in the fuel cell device 15 is carried out at an appropriate time based on the power generation plan stored in the memory 22.

[0047] Note that, while a specific processing procedure for executing step S4 is received, the received processing procedure may be stored in the storage device 22, but is not limited to this. A specific processing procedure for executing step S4 may be stored in advance in the storage device 22. An example of such a processing procedure will be described in the embodiment.

[0048] According to the present embodiment described above, the power generation plan for the fuel cell device 15 can be more appropriately planned than in the past.

[0049] For example, if the next power generation plan for the fuel cell device 15 is not received and the remaining period of the power generation plan stored in the memory 22 falls below a predetermined period, the power generation of the fuel cell device 15, which would have continued if the next power generation plan had been received, may be stopped. This may cause the fuel cell device 15 to start and stop more than necessary, shortening its lifespan.

[0050] However, according to this embodiment, when the remaining period of the power generation plan stored in memory 22 becomes less than a predetermined period, the data of the power generation plan stored in memory 22 is used to add a power generation plan so that the remaining period of the power generation plan becomes equal to or greater than the predetermined period, thereby allowing the fuel cell device 15 to operate properly for the predetermined period compared to a state in which the remaining period of the power generation plan remains less than the predetermined period.

[0051] (First embodiment) The power generation system 10 of the first example of the first embodiment is similar to the power generation system 10 of the first embodiment, except for the control content of the controller 23, which will be described below.

[0052] When the next power generation plan of the fuel cell device 15 is not received via the communication device 21 and the remaining period of the power generation plan stored in the memory device 22 becomes less than a predetermined period, the controller 23 controls the remaining period of the power generation plan to be equal to or longer than the predetermined period by repeating the data of the last unit period of the stored power generation plan.

[0053] Fig. 3A is a flow chart showing an example of the operation (power generation planning method) of the power generation planning device in the power generation system of the first example of the first embodiment. Fig. 3B is a diagram for explaining a specific example of the operation of step S4A in Fig. 3A.

[0054] The following operations may be performed, for example, by the calculation processing unit of the controller 23 reading out a control program from a storage unit of the controller 23. However, it is not essential that the following operations are performed by the controller 23. An operator may perform some of the operations. In the following example, a case where the operations are controlled by the controller 23 will be described.

[0055] 3A are similar to steps S1, S2, and S3 in FIG 2, respectively, and therefore will not be described in detail. Step S4A in FIG 3A corresponds to a specific example of a processing procedure for adding a power generation plan for the fuel cell device 15.

[0056] If the next power generation plan of the fuel cell device 15 is not received via the communication device 21 and the remaining period of the power generation plan stored in the memory device 22 becomes less than the predetermined period ("No" in step S3), a process is performed in step S4A to make the remaining period of the power generation plan equal to or greater than the predetermined period by repeating the data of the last unit period of the power generation plan stored in the memory device 22. For example, if the "predetermined period" is three days and the "unit period" is 30 minutes, the power generation plan of the fuel cell device 15 for the first to third days is received on the first day, and if the power generation plan for the fourth day is not received on the second day, in the example shown in FIG. 3B, the received data for 23:30 to 24:00 on the third day is repeated for the entire unit period of the fourth day to complement the power generation plan for the fourth day. This makes it possible to make the remaining period of the power generation plan of the fuel cell device 15 three days on the second day.

[0057] According to the present embodiment described above, even if the next power generation plan for the fuel cell device 15 is not received and the remaining period of the power generation plan stored in the memory 22 falls below a predetermined period, the data of the last unit period of the stored power generation plan can be repeated to add a power generation plan so that the remaining period of the power generation plan is equal to or greater than the predetermined period. Thus, according to this embodiment, the fuel cell device 15 can be operated appropriately for the predetermined period, compared to a state in which the remaining period of the power generation plan remains less than the predetermined period.

[0058] The power generation planning method for the fuel cell device 15, the power generation planning device 20 for the fuel cell device 15, and the power generation system 10 of this embodiment may be similar to those of the first embodiment except for the above-mentioned features.

[0059] (Second Example) The power generating system 10 of the second example of the first embodiment is similar to the power generating system 10 of the first embodiment, except for the control content of the controller 23, which will be described below.

[0060] When the next power generation plan of the fuel cell device 15 is not received via the communication device 21 and the remaining period of the power generation plan stored in the memory device 22 becomes less than a predetermined period, the controller 23 extracts data for a period equivalent to the difference between the predetermined period and the remaining period from the stored power generation plan, and adds this data to control the remaining period of the power generation plan to be equal to or greater than the predetermined period.

[0061] Fig. 4A is a flowchart showing an example of the operation (power generation planning method) of the power generation planning device in the power generation system of the second example of the first embodiment. Fig. 4B is a diagram for explaining a specific example of the operation of step S4B in Fig. 4A.

[0062] The following operations may be performed, for example, by the calculation processing unit of the controller 23 reading out a control program from a storage unit of the controller 23. However, it is not essential that the following operations are performed by the controller 23. An operator may perform some of the operations. In the following example, a case where the operations are controlled by the controller 23 will be described.

[0063] 4A are similar to steps S1, S2, and S3 in FIG 2, respectively, and therefore will not be described in detail. Step S4B in FIG 4A corresponds to a specific example of a processing procedure for adding a power generation plan for the fuel cell device 15.

[0064] If the next power generation plan of the fuel cell device 15 is not received via the communication device 21 and the remaining period of the power generation plan stored in the memory 22 becomes less than the predetermined period ("No" in step S3), in step S4B, data of a period corresponding to the difference between the predetermined period and the remaining period is extracted from the power generation plan stored in the memory 22, and this data is added to make the remaining period of the power generation plan equal to or greater than the predetermined period. For example, if the "predetermined period" is three days, and the power generation plan of the fuel cell device 15 for the first to third days is received at the timing of the first day, and the power generation plan of the fourth day is not received at the timing of the second day, in the example shown in FIG. 4B, data of the power generation plan for the period corresponding to the difference between the period of the first to third days and the period of the second to third days (in this example, the first day) is extracted from the power generation plan of the fuel cell device 15 for the first to third days stored in the memory 22, and this data is added to complement the power generation plan of the fourth day. As a result, the remaining period of the power generation plan of the fuel cell device 15 can be set to three days at the timing of the second day.

[0065] According to the present embodiment described above, even if the next power generation plan for the fuel cell device 15 is not received and the remaining period of the power generation plan stored in the memory 22 falls below a predetermined period, data for a period equivalent to the difference between the predetermined period and the remaining period can be extracted from the stored power generation plan and added to make the remaining period of the power generation plan equal to or greater than the predetermined period. Thus, according to this embodiment, the fuel cell device 15 can be operated appropriately for the predetermined period, compared to a state in which the remaining period of the power generation plan remains less than the predetermined period.

[0066] Other than the above-mentioned features, the power generation planning method for the fuel cell device 15, the power generation planning device 20 for the fuel cell device 15, and the power generation system 10 of this embodiment may be similar to the first embodiment or the first example of the first embodiment.

[0067] (Third Example) The power generation system 10 of the third example of the first embodiment is similar to the power generation system 10 of the first embodiment, except for the control content of the controller 23, which will be described below.

[0068] The controller 23 receives information indicating whether to select the power generation planning method for the fuel cell device 15 of the first embodiment (step S4A in FIG. 3A) or the power generation planning method for the fuel cell device 15 of the second embodiment (step S4B in FIG. 4A) via the communication device 21. Then, based on this information, the controller 23 executes either the power generation planning method for the fuel cell device 15 of the first embodiment (step S4A in FIG. 3A) or the power generation planning method for the fuel cell device 15 of the second embodiment (step S4B in FIG. 4A).

[0069] FIG. 5 is a flowchart showing an example of the operation of the power generation planning device (power generation planning method) in the power generation system of the third example of the first embodiment.

[0070] The following operations may be performed, for example, by the calculation processing unit of the controller 23 reading out a control program from a storage unit of the controller 23. However, it is not essential that the following operations are performed by the controller 23. An operator may perform some of the operations. In the following example, a case where the operations are controlled by the controller 23 will be described.

[0071] 5 are similar to steps S1, S2, and S3 in Fig. 2, respectively, and therefore will not be described in detail. Step S4C in Fig. 5 corresponds to a specific example of a processing procedure for adding a power generation plan for the fuel cell device 15.

[0072] If the next power generation plan of the fuel cell device 15 is not received via the communication device 21 and the remaining period of the power generation plan stored in the memory 22 becomes less than a predetermined period ("No" in step S3), it is determined in step S5 whether to select the power generation planning method of the fuel cell device 15 of the first embodiment (step S4A in FIG. 3A) or the power generation planning method of the fuel cell device 15 of the second embodiment (step S4B in FIG. 4A). Note that information indicating whether to select the power generation planning method of the first embodiment or the power generation planning method of the second embodiment is stored in advance in the memory 22, and the above determination is made by checking this information. This information may be transmitted from the terminal or the server, similarly to the power generation plan of the fuel cell device 15 in step S1. At this time, the power generation planning method of the fuel cell device 15 of the first embodiment and the power generation planning method of the fuel cell device 15 of the second embodiment may be received together with the above information, or such power generation planning method and the above information may be received at different times. Then, in step S4C, based on the judgment in step S5, either the power generation planning method for the fuel cell device 15 of the first embodiment (step S4A in FIG. 3A) or the power generation planning method for the fuel cell device 15 of the second embodiment (step S4B in FIG. 4A) is executed.

[0073] According to the present embodiment described above, it is possible to receive information indicating whether to select the power generation planning method for the fuel cell device 15 of the first embodiment or the power generation planning method for the fuel cell device 15 of the second embodiment, thereby allowing the fuel cell device 15 to operate more appropriately than when the power generation planning for the fuel cell device 15 is executed without receiving such information.

[0074] Other than the above-mentioned features, the power generation planning method for the fuel cell device 15, the power generation planning device 20 for the fuel cell device 15, and the power generation system 10 of this embodiment may be similar to those of the first embodiment or the first to second examples of the first embodiment.

[0075] (Modification) The power generation system 10 of the modified example of the first embodiment is similar to the power generation system 10 of the first embodiment, except for the control content of the controller 23, which will be described below.

[0076] The controller 23 receives information indicating that no addition will be made to the power generation plan of the fuel cell device 15 via the communication device 21. Then, upon receiving this information, the controller 23 performs control so as not to make an addition to the power generation plan of the fuel cell device 15.

[0077] Fig. 6A is a flow chart showing an example of the operation (power generation planning method) of the power generation planning device in the power generation system of the modified example of Embodiment 1. Fig. 6B is a diagram for explaining a specific example of the operation of step S6 in Fig. 6A.

[0078] The following operations may be performed, for example, by the calculation processing unit of the controller 23 reading out a control program from a storage unit of the controller 23. However, it is not essential that the following operations are performed by the controller 23. An operator may perform some of the operations. In the following example, a case where the operations are controlled by the controller 23 will be described.

[0079] Note that steps S1, S2, S3, and S4 in FIG. 6A are similar to steps S1, S2, S3, and S4 in FIG. 2, respectively, and therefore detailed description thereof will be omitted.

[0080] If the next power generation plan for the fuel cell device 15 is not received via the communication device 21 and the remaining period of the power generation plan stored in the memory 22 falls below a predetermined period ("No" in step S3), then in step S6 it is determined whether or not to add to the power generation plan for the fuel cell device 15. The above determination is made based on whether or not information indicating that a power generation plan is not to be added is stored in the memory 22. This information may be transmitted from the terminal or server, similar to the power generation plan for the fuel cell device 15 in step S1. At this time, the power generation plan for the fuel cell device 15 may be received together with the above information, or the power generation plan and the above information may be received at different times.

[0081] If it is determined that a power generation plan for the fuel cell device 15 is not to be added ("No" in step S6), the process of step S4 is bypassed. In other words, a power generation plan for the fuel cell device 15 is not added. For example, when the "predetermined period" is three days, even if the power generation plans for the first to third days of the fuel cell device 15 are received on the first day and the power generation plan for the fourth day is not received on the second day, in the example shown in FIG. 6B, the power generation plan for the fourth day is not supplemented. Therefore, in this case, power generation by the fuel cell device 15 is stopped at the start of the first unit period on the fourth day in the power generation plan of the fuel cell device 15.

[0082] According to the present modified example described above, it is possible to receive information indicating that no additions will be made to the power generation plan of the fuel cell device 15, thereby allowing the fuel cell device 15 to be stopped at a more timely manner than if the power generation plan of the fuel cell device 15 were executed without receiving such information.

[0083] Other than the above-mentioned features, the power generation planning method for the fuel cell device 15, the power generation planning device 20 for the fuel cell device 15, and the power generation system 10 of this modified example may be similar to those of the first embodiment or the first to third examples of the first embodiment.

[0084] Second embodiment FIG. 7 is a diagram illustrating an example of a power generation system according to the second embodiment.

[0085] As shown in FIG. 7, the power generation system 10 of this embodiment includes a fuel cell device 15 (see FIG. 1), a power generation planning device 20 for the fuel cell device 15, and control devices 30A to 30E.

[0086] Here, the internal configuration of the power generation planning device 20 is similar to that of the first embodiment, and therefore a detailed description thereof will be omitted.

[0087] In the example shown in Fig. 7, the power generation system 10 includes a power generation unit group consisting of a plurality of power generation units including a fuel cell stack. The power generation unit group is grouped by the plurality of power generation units. Although not shown, each of the power generation units includes a fuel cell stack, a power conditioner for converting DC power generated by the fuel cell stack into AC power and outputting the AC power to the power grid, and a control device for controlling the operation of these devices.

[0088] In this example, the power generating units are grouped into power generating units a1-an belonging to group A, power generating units b1-bn belonging to group B, power generating units c1-cn belonging to group C, power generating units d1-dn belonging to group D, and power generating units e1-en belonging to group E. All the power generating units belonging to one group are also simply referred to as "power generating units in a group." Note that in this example, each group corresponds to a fuel cell device of the present disclosure.

[0089] However, the above configuration of the power generation unit group is merely an example and is not limited to this example. For example, the power generation unit group may be grouped by a single group of power generation units.

[0090] The control devices 30A to 30E are provided for the power generation units a1 to an in group A, the power generation units b1 to bn in group B, the power generation units c1 to cn in group C, the power generation units d1 to dn in group D, and the power generation units e1 to en in group E, respectively, and control the operation of each of the power generation units in the group.

[0091] For example, the control device 30A controls the output of each of the power generation units a1 to an belonging to group A via a communication network so as to enable efficient operation (eg, optimization of the life span) of these power generation units.

[0092] The control devices 30A to 30E may have any control function, and include a calculation processing unit (not shown), a storage unit that stores a control program, and a communication device. The calculation processing unit reads out and executes the control program stored in the storage unit, thereby performing predetermined control in the control devices 30A to 30E. An example of the calculation processing unit is a microprocessor. An example of the storage unit is a memory.

[0093] The power generation planning device 20 instructs each of the control devices 30A-30E on various information such as the power generation plan of each group via a communication network in response to, for example, an output request from an external user. Each of the control devices 30A-30E adjusts the number of power generation units that generate power among the multiple power generation units belonging to each group in accordance with the power generation output in the received power generation plan.

[0094] The effects achieved by the power generation system 10 of this embodiment are similar to those described in any one of the first embodiment, the first to third examples of the first embodiment, and the modified example of the first embodiment, and therefore description thereof will be omitted.

[0095] The above-described configuration of the power generation system 10 is merely an example, and is not limited to this example. For example, the controller 23 (see FIG. 1) of the power generation planning device 20 may directly control the operation of each of the power generation units in the group without going through the control devices 30A to 30E.

[0096] The first embodiment, the first to third examples of the first embodiment, the modified example of the first embodiment, and the second embodiment may be combined with each other as long as they do not exclude each other. From the above description, many improvements and other embodiments of the present disclosure will be apparent to those skilled in the art. Therefore, the above description should be construed as merely illustrative and is provided for the purpose of teaching those skilled in the art the best mode for carrying out the present disclosure. The details of the structure and / or function thereof may be substantially changed without departing from the spirit of the present disclosure. [Industrial Applicability]

[0097] An aspect of the present disclosure can be used in a power generation planning method for a fuel cell device, a power generation planning device for a fuel cell device, and a power generation system, which can plan power generation in a fuel cell device more appropriately than ever before. [Explanation of symbols]

[0098] 10: Power generation system 15:Fuel cell device 20: Power generation planning device 21: Communication device 22:Memory 23: Controller 30A: Control device 30B: Control device 30C: Control device 30D: Control device 30E: Control device a1~an: Power generation unit b1~bn: Power generation units c1~cn: Power generation units d1~dn: Power generation units e1~en: Power generation unit

Claims

1. receiving a power generation plan for a fuel cell device; storing the received power generation plan of the fuel cell device; The power generation planning method for a fuel cell device includes a step of, when the next power generation plan is not received and the remaining period of the stored power generation plan becomes less than a predetermined period, adding a power generation plan using data of the stored power generation plan so that the remaining period of the power generation plan becomes equal to or greater than the predetermined period.

2. 2. The power generation planning method for a fuel cell device according to claim 1, wherein the remaining period of the power generation plan is set to a predetermined period or more by repeating data of the last unit period of the stored power generation plan.

3. 2. The power generation planning method for a fuel cell device as described in claim 1, further comprising the steps of: extracting data for a period corresponding to the difference between the specified period and the remaining period from a stored power generation plan; and adding this data to make the remaining period of the power generation plan equal to or longer than the specified period.

4. receiving first information indicating whether to select the power generation planning method according to claim 2 or the power generation planning method according to claim 3; 4. The power generation planning method for a fuel cell device according to claim 1, further comprising the steps of: executing either the power generation plan adding method according to claim 2 or the power generation plan adding method according to claim 3 based on the first information.

5. A power generation planning method for a fuel cell device described in any one of claims 1 to 4, comprising a step of receiving second information indicating that no addition is to be made to the power generation plan, and when the second information is received, no addition is made to the power generation plan.

6. A communication device that receives a power generation plan of the fuel cell device; a storage device that stores the received power generation plan of the fuel cell device; A power generation planning device for a fuel cell device comprising: a controller that, when the next power generation plan is not received via the communication device and the remaining period of the power generation plan stored in the memory falls below a predetermined period, uses data of the power generation plan stored in the memory to add a power generation plan so that the remaining period of the power generation plan becomes equal to or longer than the predetermined period.

7. A fuel cell device; The power generation planning device for a fuel cell system according to claim 6 ; A power generation system comprising:

Citation Information

Patent Citations

  • Generation system for power retail

    JP2003111273A

  • Power generating system

    JP2014053234A

  • Power management system, information device and program

    JP2017055606A

  • JP1973064739A