The compaction management system addresses oversight of uncompleted sections by integrating GNSS and acceleration sensors to display compaction status, enhancing construction quality and efficiency.
Patent Information
- Application Number
- JP2020176935
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2020-10-21
- Publication Date
- 2024-09-26
- Estimated Expiration
- 2040-10-21
AI Technical Summary
Conventional compaction management systems struggle with oversight of uncompleted sections, leading to reduced construction quality and efficiency due to separate displays of compaction number and degree, making it difficult to ensure both are met in real-time.
A compaction management system that integrates position information from GNSS and acceleration sensors to determine and display the number of compactions and compaction degree for each section, using flags to highlight incomplete areas, and combines overlapping flags to prevent oversight.
Improves construction quality by preventing oversight of uncompleted sections, thereby maintaining work efficiency by ensuring both compaction number and degree are met.
Smart Images

Figure 0007556745000002 
Figure 0007556745000003 
Figure 0007556745000006
Abstract
Description
[Technical field]
[0001] The present invention relates to a rolling compaction management system. [Background technology]
[0002] In the field of compaction work, construction quality is controlled using compaction management systems, etc. Compaction management systems, for example, divide a work area into control blocks of a certain size, and use positioning results from a Global Navigation Satellite System (GNSS) mounted on a compaction machine to tally up the number of times the compaction machine has passed through each control block, thereby managing whether the work area has been compacted a set number of times.
[0003] In compaction work, the number of compactions required to obtain a predetermined degree of compaction and layer thickness is determined by experimentally measuring the relationship between the number of compactions and the degree of compaction and layer thickness in advance, so essentially, if the required number of compactions is reached, the specified degree of compaction and layer thickness should be satisfied after construction. However, because the way the ground and soil are piled up is not uniform, there are cases where the specified degree of compaction and layer thickness are not satisfied even if the required number of compactions is reached.
[0004] Therefore, a technique for improving construction quality is known, for example, by judging the degree of compaction using an acceleration sensor or judging the layer thickness using height data from a GNSS, and displaying whether the specified degree of compaction or layer thickness is satisfied. For example, Patent Document 1 discloses a site management system that obtains completed form information by importing position information based on three-dimensional coordinates transmitted from a vibrating roller that moves and compacts a banking site, in which the banking site is set as a base shape divided into predetermined unit areas in advance, position information based on the three-dimensional coordinates and compaction information for each unit area transmitted from the vibrating roller are obtained, and a compaction completion result corresponding to an arbitrary elevation is output for each unit area based on the elevation data of the position information and the number of compactions data of the compaction information. [Prior art documents] [Patent documents]
[0005] [Patent Document 1] JP 2015-168991 A Summary of the Invention [Problem to be solved by the invention]
[0006] However, in the above-mentioned conventional technology, since the number of times of compaction and the degree of compaction are displayed on separate screens, it is difficult to check in real time during compaction work whether both the number of times of compaction and the degree of compaction are satisfied, and there is a risk of an incomplete section being generated due to overlooking a section that has not reached the specified number of times of compaction or degree of compaction. When an incomplete section is discovered, the operator of the compaction machine needs to move the compaction machine to the incomplete section and perform additional compaction, which reduces work efficiency.
[0007] The present invention has been made in consideration of the above, and aims to provide a compaction management system that can improve construction quality while suppressing a decrease in work efficiency by preventing incomplete sections from being overlooked. [Means for solving the problem]
[0008] The present application includes a number of means for solving the above-mentioned problems. One example of such a means is a rolling management system including a position information acquisition device that acquires position information of a work machine performing compaction work at a construction site, and a control device that acquires the number of times of compaction for each of a number of sections that are previously set corresponding to the construction site based on the position information of the work machine acquired by the position information acquisition device, and causes a display device to display the number of sections and the number of times of compaction corresponding to each of the number of sections in an overlapping manner. The control device includes a rolling quality information acquisition device that acquires construction quality information that is information related to the construction quality of the rolling work for each of the number of sections, and the control device judges whether the construction quality information for each of the number of sections has reached a predetermined standard rolling quality corresponding to the number of times of compaction, and for a section among the number of sections for which it has been determined that the construction quality information has not reached the standard rolling quality, the control device displays non-achievement information in an overlapping manner on the section and the number of times of compaction displayed on the display device. In addition, a plurality of pieces of non-achievement information located at a distance determined in advance according to the size of the plurality of sections displayed on the display device are extracted and combined into one piece of non-achievement information, and the combined piece of non-achievement information is displayed superimposed on the section and the number of rolling compactions at the center position of the extracted plurality of pieces of non-achievement information. It shall be so. Effect of the Invention
[0009] According to the present invention, by preventing incomplete sections from being overlooked, it is possible to improve construction quality while preventing a decrease in work efficiency. [Brief description of the drawings]
[0010] [Figure 1] FIG. 1 is a functional block diagram illustrating an overall configuration of a rolling compaction management system. [Diagram 2] FIG. 13 is a diagram showing test construction information relating to layer thickness. [Diagram 3] FIG. 13 is a diagram showing test construction information relating to compaction degree. [Figure 4] 13 is a flowchart showing the processing contents of the rolling compaction management system. [Diagram 5] FIG. 4 is a diagram showing an example of a construction site map displayed on a display unit. [Figure 6] FIG. 13 is a diagram showing an example of a construction site map displayed on the display unit, showing a display before flags are grouped together. [Figure 7]FIG. 13 is a diagram showing an example of a construction site map displayed on the display unit, showing the display after flags have been grouped together. [Figure 8] FIG. 4 is a diagram illustrating an example of a display on a display unit. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0011] Hereinafter, an embodiment of the present invention will be described with reference to the drawings, FIGS.
[0012] FIG. 1 is a functional block diagram showing an outline of the overall configuration of a rolling compaction management system according to the present embodiment.
[0013] In FIG. 1, the rolling management system comprises a rolling machine 100 such as a vibrating roller or a pneumatic roller, which is a type of work machine, and an information terminal 200 such as a tablet on which an operator of the rolling machine 100 checks and inputs information.
[0014] The compaction machine 100 is equipped with an acceleration sensor 101 that detects the acceleration acting on the compaction machine 100, a Global Navigation Satellite System (GNSS) 103 as a position information acquisition device that acquires position information of the compaction machine 100 performing compaction work at a construction site, a controller 104 that controls the operation of the compaction machine 100, and a CAN (Controller Area Network) 102 that transmits various information in the compaction machine 100.
[0015] The GNSS 103 acquires the coordinates of the rolling machine 100 in a three-dimensional coordinate system (construction site coordinate system) set at the construction site as position information. The acceleration information acquired by the acceleration sensor 101 and the position information acquired by the GNSS 103 are transmitted to the controller 104 via the CAN 102.
[0016] The controller 104 has a memory unit 104a that stores various information, and a communication unit 104b that communicates between the rolling machine 100 and the outside.
[0017] The storage unit 104a stores the acceleration information transmitted via the CAN 102 in association with the position information.
[0018] The communication unit 104b is a communication function unit that transmits and receives information via, for example, a wireless LAN, and transmits to the information terminal 200 the acceleration information, position information, and the like stored in the storage unit 104a.
[0019] The information terminal 200 is equipped with a communication unit 201 that receives acceleration information, position information, etc. transmitted from the communication unit 104b of the compaction machine 100, a data input unit 203 for inputting various information, a memory unit 202 that stores information received from the compaction machine 100 via the communication unit 201 and information input from the data input unit 203, a compaction progress judgment unit 204 that executes a compaction progress judgment process (described later) based on the information stored in the memory unit 202, a test construction data input unit 205 that inputs the results of test construction (test construction information) performed in advance for compaction work at the construction site, a test construction data recording unit 206 that records the test construction information input from the test construction data input unit 205, a display judgment unit 207 that performs a display judgment process based on the judgment result of the compaction progress judgment unit 204 and the test construction information stored in the test construction data recording unit 206, and a display unit 208 that displays various information to be presented to the operator based on the judgment result of the display judgment unit 207.
[0020] From the data input unit 203, for example, three-dimensional coordinates indicating a construction area where construction work is to be carried out at a construction site are input.
[0021] The memory unit 202 stores information received from the rolling machine 100 via the communication unit 201 and the three-dimensional coordinates of the work area input from the data input unit 203.
[0022] The compaction progress determination unit 204 performs compaction progress determination processing, which includes a count determination process for determining the number of compactions performed by the compaction machine 100 at each position in the work area, a compaction determination process for determining the degree of compaction at each position in the work area, and a layer thickness determination process for determining the layer thickness at each position in the work area, and has a count determination unit 204a for performing the count determination process, a compaction degree determination unit 204b for performing the compaction degree determination process, and a layer thickness determination unit 204c for performing the layer thickness determination process.
[0023] The number of times determination unit 204a determines the number of times of compaction at each position of the construction site based on the position information of the compaction machine 100 stored in the memory unit 202. The determination of the number of times of compaction is performed, for example, according to the method specified by the Ministry of Land, Infrastructure, Transport and Tourism in the "Guidelines for Compaction Management of Embankments Using TS and GNSS". The number of times of compaction is calculated by counting the number of times the compaction function unit (for example, roller) of the compaction machine 100 passes through each of a plurality of sections previously set in the construction site. Here, the section set in the construction site is a unit block (control block) for managing the construction quality, and is obtained by dividing the construction range (within the area where compaction is performed) into square areas of a size predetermined according to the type of compaction machine used for the compaction work. For example, in the "Guidelines for Compaction Management of Embankments Using TS and GNSS" (Ministry of Land, Infrastructure, Transport and Tourism), the control block for a tire roller is specified as a square with one side of 0.50 meters.
[0024] That is, the count determination unit 204a calculates the passing range and traveling direction of the compaction machine 100 at the construction site based on the position information of the compaction machine 100, and calculates the number of times the compaction machine 100 passes through each management block as the number of compactions. The passing range of the compaction machine 100 can be calculated from pre-stored design information of the compaction machine 100 and mounting position information of the GNSS 103 for the compaction machine 100. Also, the traveling direction of the compaction machine 100 can be calculated from the movement direction of the position information.
[0025] The compaction degree determination unit 204b determines the degree of compaction at each position (management block) of the construction site based on the acceleration information of the rolling machine 100 stored in the memory unit 202 and the corresponding position information. For example, when a vibrating roller is considered as the rolling machine 100, the acceleration generated in the vibrating roller due to the reaction force of the impact applied from the vibrating roller to the ground is small on soft ground and large on hard ground. In other words, there is a tendency that the acceleration is large on ground with a high degree of compaction and small on ground with a low degree of compaction. Therefore, the compaction degree of the ground is determined using this principle. It is also possible to use a calculation direction of the compaction degree based on information other than acceleration.
[0026] The layer thickness determination unit 204c determines the layer thickness at each position (management block) on the construction site based on the position information (altitude data) of the compaction machine 100 stored in the memory unit 202 and the altitude data before compaction work (before filling up) that has been stored in advance. Specifically, as stipulated in the "Guidelines for Compaction Management of Fillings Using TS / GNSS" (Ministry of Land, Infrastructure, Transport and Tourism), the layer thickness is determined as the difference between the altitude of the management block at the time of compaction work and the altitude of the management block immediately below this management block at the time of construction of the lower layer. The altitude of the management block uses the average value within the management block.
[0027] The trial construction information recorded in the trial construction data recording unit 206 is obtained based on the results of a trial compaction work (compaction work using the actual embankment material and a compaction machine) equivalent to the actual construction content in a test yard set up for the test before the start of work at the construction site, and indicates the degree of compaction relative to the number of compactions, and the layer thickness relative to the number of compactions. In other words, in the compaction work at the construction site, the degree of compaction and the number of compactions can be estimated by comparing the number of compactions in each management block with the trial construction data.
[0028] Fig. 2 is a diagram showing test construction information related to layer thickness, and Fig. 3 is a diagram showing test construction information related to compaction degree.
[0029] As shown in Fig. 2, the experimental value hr(n) of the layer thickness, which is the test construction information, decreases as the number of compactions (n) increases. The measured value h(n) of the layer thickness of each management block as determined by the layer thickness determination unit 204c is close to the experimental value, and the layer thickness can be estimated with high accuracy from the number of compactions (n).
[0030] Similarly, as shown in Fig. 3, the experimental value pr(n) of the compaction degree, which is the test construction information, decreases as the number of compactions (n) increases. The measured value p(n) of the compaction degree of each managed block as determined by the compaction degree determination unit 204b is close to the experimental value, and the compaction degree can be estimated with high accuracy from the number of compactions (n).
[0031] The display determination unit 207 displays the number of times of compaction for each management block on the display unit 208 in a visually easy-to-distinguish manner. Specifically, for example, colors are defined according to the number of times of compaction, and when a construction site map simulating the construction site and the management blocks is displayed on the display unit 208, the number of times of compaction is presented to the operator by color-coding each management block according to the number of times of compaction. In addition, the display determination unit 207 performs a display determination process based on the determination result of the compaction progress determination unit 204 and the trial construction information stored in the trial construction data recording unit 206. Specifically, for each management block, it is determined whether or not the current compaction degree and layer thickness obtained by the compaction progress determination unit 204 satisfy the estimated values of the compaction degree and layer thickness calculated from the trial construction information stored in the trial construction data recording unit 206 and the current number of times of compaction, and the determination result is displayed superimposed on the construction site map.
[0032] FIG. 4 is a flowchart showing the processing contents of the rolling compaction management system.
[0033] In FIG. 4, the compaction progress determination unit 204 first reads observation data such as acceleration information and position information of the compaction machine 100 from the storage unit 202 (step S100).
[0034] Next, the count determination unit 204a calculates the number of times each mesh (each management block) has been compacted, and outputs this to the display determination unit 207 (step S110), and the display determination unit 207 displays the number of times each mesh has been compacted on the display unit 208 (step S120).
[0035] FIG. 5 is a diagram showing an example of a construction site map displayed on the display unit.
[0036] As shown in Figure 5, the construction site map displays the number of times each management block has been compacted in a way that makes it easy to visually distinguish. For convenience of illustration, in Figure 5, differences in the number of times compaction has been performed are expressed by different types of hatching. Also, the boundary between the area to be worked on (the construction zone) and other areas at the construction site is shown by a dotted line.
[0037] 4, the compaction degree determination unit 204b calculates the compaction degree of each mesh (each management block) and outputs it to the display determination unit 207 (step S130), and the display determination unit 207 determines whether the compaction degree is sufficient or not (step S140). Here, in the determination of step S140, it is determined whether the absolute value of the difference between the current compaction degree obtained by the compaction degree determination unit 204b and the compaction degree calculated from the trial construction information stored in the trial construction data recording unit 206 and the current number of rolling operations is smaller than a predetermined value.
[0038] If the judgment result in step S140 is NO, it is judged whether the corresponding management block is within a construction area (step S141), and if the judgment result is YES, a flag (symbol) indicating that the degree of compaction is insufficient is generated for the management block (step S142).
[0039] When the judgment result in step S140 is YES, when the judgment result in step S141 is NO, or when the processing in step S142 is completed, the layer thickness judgment unit 204c subsequently calculates the layer thickness of each mesh (each management block) and outputs it to the display judgment unit 207 (step S150), and the display judgment unit 207 judges whether the layer thickness is sufficient or not (step S160). Here, in the judgment in step S160, it is judged whether the absolute value of the difference between the current layer thickness obtained by the layer thickness judgment unit 204c and the layer thickness calculated from the trial construction information stored in the trial construction data recording unit 206 and the current number of rolling compactions is smaller than a predetermined value.
[0040] If the judgment result in step S160 is NO, it is judged whether the corresponding management block is within a construction area (step S161), and if the judgment result is YES, a flag (symbol) indicating that the layer thickness is insufficient is generated for the management block (step S162).
[0041] If the judgment result in step S140 is YES, if the judgment result in step S141 is NO, or if the processing in step S142 is completed, the display judgment unit 207 then judges whether the size specification of the construction site map displayed on the display unit 208 (for example, the size specification by the operator via the data input unit 203) is a reduced display or not (step S170), and if the judgment result is NO, a flag (symbol) related to the degree of compaction and a flag (symbol) related to the layer thickness are displayed superimposed on the number of compactions displayed on the construction site map on the display unit 208 (step S190).
[0042] As shown in Figure 5, a flag (symbol) indicating that the degree of compaction is insufficient, a flag (symbol) indicating that the layer thickness is insufficient, and a flag (symbol) indicating that both the degree of compaction and layer thickness are insufficient are displayed superimposed on the number of compactions for each management block.
[0043] Also, in FIG. 4, if the judgment result in step S170 is YES, among the flags (symbols) relating to the degree of compaction and the flags (symbols) relating to the layer thickness, flags (symbols) of the same type that are close to each other are combined into one flag (symbol) (step S180), and the combined flags (symbols) and the flags (symbols) that have not been combined are displayed superimposed on the number of compactions displayed on the construction site map of the display unit 208 (step S190).
[0044] 6 and 7 are diagrams showing an example of a construction site map displayed on the display unit, with FIG. 6 showing the display before the flags are grouped and FIG. 7 showing the display after the flags are grouped.
[0045] As shown in FIG. 6, when the scaled-down display is used, if flags related to compaction level and layer thickness are densely packed, displaying flags for all sections will make the screen crowded and difficult to view. Therefore, as shown in FIG. 7, in places where flags are densely packed, flags are extracted according to conditions according to the magnification rate of the screen (for example, closer than a predetermined distance), the extracted flags are grouped together, and a representative management block and a representative area are set for the grouped flags and displayed. For example, a mathematical method such as cluster analysis is used to set the representative management block and the representative area. In other words, if the distance between management blocks with flags is shorter than a specified value that is predetermined according to the magnification rate, the cluster (group) formed by the corresponding multiple flags is grouped into one flag, the center position (for example, center of gravity) of the grouped flag (cluster) is set as the representative management block, and depending on the spread of the grouped flags, for example, an elliptical (or circular) representative area that contains all the grouped flags and has the smallest area is set. In addition, the grouped clusters (groups) are displayed superimposed on the representative management block. The representative management block may be the center of the representative area.
[0046] Next, it is determined whether the completion condition is met, that is, whether the degree of compaction acquired by the compaction degree judgment unit 204b and the layer thickness acquired by the layer thickness judgment unit 204c each satisfy a predetermined completion standard value (step S200), and if the judgment result is YES, a display indicating the completion of the work (see FIG. 8) is displayed on the display unit 208 (step S210), and the process is terminated. Also, if the judgment result in step S200 is NO, the process is terminated.
[0047] The rolling compaction management system repeats the processes of steps S100 to S210.
[0048] The effects of the present embodiment configured as above will be described.
[0049] In the conventional technology, the number of times of compaction and the degree of compaction are displayed on separate screens, so it is difficult to check in real time during compaction work whether both the number of times of compaction and the degree of compaction are satisfied, and there is a risk of incomplete sections being generated due to overlooking sections that have not reached the specified number of times of compaction or degree of compaction. When an incomplete section is discovered, the operator of the compaction machine needs to move the compaction machine to the incomplete section and perform additional compaction, which reduces work efficiency.
[0050] In contrast to this, in this embodiment, in a rolling management system including a position information acquisition device (e.g., GNSS 103) that acquires position information of a work machine (e.g., a rolling machine 100) that performs rolling work at a construction site, and a control device (e.g., an information terminal 200) that acquires the number of times of rolling for each of a plurality of sections (management blocks) that are previously set corresponding to the construction site based on the position information of the work machine acquired by the position information acquisition device, and causes a display device (e.g., a display unit 208) to display the plurality of sections and the number of times of rolling corresponding to each of the plurality of sections in an overlapping manner, the information relating to the construction quality of the rolling work for each of the plurality of sections being The control device is equipped with a compaction quality information acquisition device (e.g., an acceleration sensor 101, a GNSS 103, and a compaction progress determination unit 204) that acquires construction quality information, and the control device determines whether the construction quality information of each of the multiple sections has reached a predetermined standard compaction quality corresponding to the number of compactions.For a section among the multiple sections where it is determined that the construction quality information has not reached the standard compaction quality, the display device is configured to display incomplete information (e.g., a flag) superimposed on the section and the number of compactions.By preventing incomplete sections from being overlooked, it is possible to improve construction quality while preventing a decrease in work efficiency.
[0051] <Additional Notes> The present invention is not limited to the above-described embodiments, and includes various modifications and combinations within the scope of the gist of the present invention. The present invention is not limited to those having all the configurations described in the above-described embodiments, and includes those in which some of the configurations are deleted. The above-described configurations, functions, etc. may be realized by designing some or all of them as an integrated circuit, for example. The above-described configurations, functions, etc. may be realized by software, in which a processor interprets and executes a program that realizes each function. [Explanation of symbols]
[0052] 100... rolling machine, 101... acceleration sensor, 103... GNSS, 104... controller, 104a... memory unit, 104b... communication unit, 200... information terminal, 201... communication unit, 202... memory unit, 203... data input unit, 204... rolling progress status determination unit, 204a... number of times determination unit, 204b... degree determination unit, 204c... layer thickness determination unit, 205... test construction data input unit, 206... test construction data recording unit, 207... display determination unit, 208... display unit
Claims
1. A position information acquisition device that acquires position information of a work machine performing compaction work at a construction site; Acquire the number of times of compaction for each of a plurality of sections previously set in association with the construction site, based on the position information of the work machine acquired by the position information acquisition device; A control device that displays the plurality of sections and the number of times of compaction corresponding to each of the plurality of sections on a display device in an overlapping manner, A rolling quality information acquisition device is provided for acquiring construction quality information relating to the construction quality of each of the plurality of sections, The control device includes: determining whether the construction quality information for each of the plurality of sections has reached a predetermined standard rolling quality corresponding to the number of times of rolling; For a section among the plurality of sections whose construction quality information is determined to not reach the standard rolling quality, non-achievement information is superimposed on the section and the number of rollings displayed on the display device, and A rolling management system characterized by extracting multiple pieces of non-achievement information located at a predetermined distance depending on the size of the multiple sections displayed on the display device, consolidating them into a single piece of non-achievement information, and overlaying the consolidated piece of non-achievement information on the section and number of rolling attempts at the center position of the extracted multiple pieces of non-achievement information.
2. In the rolling compaction management system according to claim 1, The rolling quality information acquisition device is a compaction degree acquisition device that acquires a compaction degree as construction quality information of each of the plurality of sections, The control device includes: determining whether the degree of compaction of each of the plurality of sections has reached a standard degree of compaction, which is a standard rolling quality that is predetermined corresponding to the number of times of compaction; A compaction management system characterized in that for a section among the plurality of sections whose degree of compaction is determined to have not reached the standard degree of compaction, information regarding the degree of compaction that has not been achieved is superimposed on the section and the number of times of compaction displayed on the display device.
3. In the rolling compaction management system according to claim 1, The rolling quality information acquisition device is a layer thickness acquisition device that acquires a layer thickness as construction quality information of each of the multiple sections, The control device includes: determining whether or not the layer thickness of each of the plurality of sections has reached a reference layer thickness, which is a predetermined reference rolling quality corresponding to the number of times of rolling; A compaction management system characterized in that, for a section among the plurality of sections whose layer thickness is determined to have not reached the standard layer thickness, information regarding the layer thickness that has not been achieved is displayed superimposed on the section and the number of compactions displayed on the display device.
4. In the rolling compaction management system according to claim 1, The control device determines whether the construction quality information for each of the multiple sections has achieved a predetermined standard compaction quality corresponding to the number of compactions, and if it determines that the construction quality information for all sections of the construction site has achieved the standard compaction quality, displays on the display device that the compaction work has been completed.
Citation Information
Patent Citations
Roller compaction construction monitored control system
CN207457813U
Banking rolling compaction control system
JP2000352044A
Land formation work rolling control system and land formation work rolling control method
JP2002129546A
Compaction management system for ground
JP2002363963A
Construction navigation system of heavy equipment for land formation work
JP2003239287A