Drilling Method

The excavation method for deep crustal thermal regions addresses the instability of volcanic magma-based geothermal power by using a shaft system and thermoelectric elements to achieve stable, large-scale, fuel-free power generation.

JP7557256B2Active Publication Date: 2024-09-27NPO KURAMAE BIO ENERGY
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
JP2022098507
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2022-06-20
Publication Date
2024-09-27
Estimated Expiration
2042-06-20

AI Technical Summary

Technical Problem

Geothermal power generation using volcanic magma is limited to small-scale operations and is unstable due to the mobility of magma, making long-term stable power generation challenging and risky.

Method used

An excavation method involving a center shaft, satellite shaft, and connecting shafts is used to access deep crustal thermal regions, with heat transfer pipes and thermoelectric power generation elements to harness heat for stable power generation without relying on magma, utilizing the heat storage chambers and thermoelectric power generation units to transfer and convert deep crustal heat into electricity.

Benefits of technology

Enables long-term, stable, and large-scale power generation without volcanic magma, providing a continuous heat transfer path and reducing maintenance costs through a fuel-free, high-efficiency power generation system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007557256000007
    Figure 0007557256000007
  • Figure 0007557256000005
    Figure 0007557256000005
  • Figure 0007557256000015
    Figure 0007557256000015
Patent Text Reader

Abstract

To provide an excavation method capable of securing a flow passage continuing from a position for heat medium to approach an earth crust hot area of a deep layer to a position to the ground surface area without explosion of a heat medium pipe in a vertical pit so as to generate electric power in a long-term stability without depending on volcanic magma.SOLUTION: An excavation method comprises: a first step excavating a center vertical pit together with a satellite pile, a connected pile, and an elevator pile from a ground surface to a predetermined depth; a second step excavating a first lateral pile intersecting to the center pile; a third step not only discharging earth removal from the elevator pile to the earth surface but constructing at least one of a worker's room and a work facility room as well as a first work floor surface provided with a space where a heat storage room is allowed to be installed; and a fourth step excavating the ground from the work floor separated farmost from the ground surface to the position nearmost to an earth crust hot area of a deep layer after those steps are sequentially carried out.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to an excavation method necessary to enable long-term stable power generation without relying on volcanic magma. [Background technology]

[0002] Typical geothermal power generation is known to generate electricity using turbines (Patent Document 1), where high-temperature steam generated when volcanic lava magma comes into contact with water is guided to a power plant, where electricity is generated using turbines. This type of power generation using magma-water vapor is also based on valuable natural energy, but it is small in scale and is unlikely to become a core technology for large-scale power generation businesses. In addition, magma can move, so it is difficult to expect a long-term stable power generation business. [Prior art documents] [Patent documents]

[0003] [Patent Document 1] Patent No. 6587118 Summary of the Invention [Problem to be solved by the invention]

[0004] Conventional geothermal power generation has various limitations, and can only be expected to generate electricity on a small scale. In addition, because it relies on volcanic magma, which is easy to move, it is not possible to expect stable long-term business viability. Furthermore, there is always the risk of not knowing in advance whether steam will be produced when developing new facilities.

[0005] The object of the present invention is to provide an excavation method that ensures a continuous flow path for the heat transfer medium from the position where it approaches the deep crustal thermal zone to the position where it reaches the surface, without causing the heat transfer medium pipes in the shaft to burst due to internal pressure, so that long-term stable power generation can be performed without relying on volcanic magma. [Means for solving the problem]

[0006] In order to achieve the above object, the excavation method according to the present invention is a method for excavating a center shaft from the ground surface to a position approaching a deep crustal heat region, the method comprising the steps of: a first step of excavating, from the ground surface to a predetermined depth, satellite shafts together with the center shaft, a connecting shaft connecting the satellite shaft and the center shaft, and an elevator shaft around the center shaft; a second step of excavating a first adit shaft intersecting the center shaft formed in the first step using an excavation device carried in from any of the shafts or carried in and assembled; and a second step of discharging the excavated soil from the elevator shaft to the ground surface and loading workers into the first adit shaft. a third step of forming a first working floor surface having at least one of a work room and a work equipment room, and a space capable of installing a heat transfer chamber that is arranged in the center shaft and that transmits deep crustal heat of 250°C to 500°C toward the ground surface via a heat transfer medium moved by a pump, and that draws the heat transfer medium pipes into the satellite shaft through the connecting shaft to relay the heat transfer; and a fourth step of performing the first to third steps sequentially until approaching the deep crustal heat area, so as to replace the ground surface with the first working floor surface and form a second working floor surface in the second cross shaft, and excavating the center shaft from the working floor surface farthest from the ground surface to a position approaching the deep crustal heat area. Effect of the Invention

[0007] According to the present invention, it is possible to carry out the excavation necessary to enable long-term stable power generation without relying on volcanic magma. [Brief description of the drawings]

[0008] [Figure 1] FIG. 1 is a schematic diagram showing a drilling method according to an embodiment of the present invention; [Diagram 2] Overall image of a power plant using deep geothermal heat [Diagram 3] (a) is a diagram explaining how the heat transfer pipe is drawn into the heat storage chamber via the satellite shaft and how the heat transfer pipe is connected to the lower floor via a piping unit, and (b) is a diagram showing the relationship between the heat storage chamber and the satellite shaft. [Figure 4] (a) is an explanatory diagram of how the folded heat transfer pipe is installed in the heat storage chamber, (b) is a diagram of the relationship between the heat storage chamber and the heat transfer pipe, and (c) is a diagram of the heat storage chamber structure. [Diagram 5] An explanatory diagram of the lowest heat transfer pipe that uses a heat transfer medium in a gaseous state [Figure 6] (a) is an explanatory diagram showing the cross-sectional configuration of the heat transfer pipe and the configuration of the bottom layer, and (b) is a diagram showing the flow of the heat transfer medium between adjacent layers in the depth direction. [Figure 7] An explanatory diagram of a worker room equipped with air conditioning equipment and a work equipment room equipped with cooling equipment [Figure 8] (a) is an explanatory diagram of the shaft being excavated at the same time, and (b) is an explanatory diagram of the discharge of soil from the shaft excavation. [Figure 9] (a) is an image of the assembly site for long heat transfer pipes, (b) is a diagram showing how the heat transfer pipes are transported underground using large flanges to bundle the heat transfer pipes, and (c) is a diagram showing the size of the large flanges. [Figure 10] (a) is an explanatory diagram of the connecting shaft that connects the center shaft and the satellite shaft, and (b) is an AA view of the connecting shaft. [Figure 11] Conceptual image of the thermoelectric power generation element unit being loaded onto a trolley and stored in the tunnel [Figure 12] (a) is an image of a huge power plant in which multiple thermoelectric generating element units are installed in each tunnel and integrated in three dimensions. (b) is a diagram explaining the role of the side tracks on each floor. [Figure 13] (a) is a diagram showing an image of an element board equipped with multiple thermoelectric generating elements for temperature difference power generation and how to make it, and (b) is an explanatory diagram showing the one-dimensional arrangement of thermoelectric generating elements. [Figure 14] (a) is an explanatory diagram of the two-dimensional arrangement of thermoelectric generation elements, and (b) is an image of the intersection of the element board, heat transfer pipes, and cold water pipes. [Figure 15] (a) is a diagram showing an experimental method and circuit for measuring the amount of power generated by a thermoelectric generating element, and (b) is a diagram showing the experimental results. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0009] Hereinafter, an embodiment of the present invention will be described with reference to the drawings.

[0010] (First embodiment) (Utilization of deep crustal heat using heat transfer pipes) Before explaining the excavation method according to an embodiment of the present invention based on Figures 1, 8, 9, and 10, for prior understanding, an overall image including the purpose of excavation will be explained based on Figure 2, the heat storage chambers installed on the work floor surface of each floor will be explained based on Figures 3 to 5, the heat transfer pipes will be explained based on Figure 6, and the worker's room and work equipment room installed on the work floor surface of each floor will be explained based on Figure 7.

[0011] Fig. 2 is a schematic image diagram of fuel-free power generation according to a power generation method using the excavation method of this embodiment. 1 indicates a deep crustal high temperature zone (deep crustal heat area), 3 indicates a heat storage chamber, 4 indicates a thermoelectric power generation element unit, 9 indicates a power plant, 10 indicates the ground floor (ground surface), and 20 indicates a heat transfer pipe. Here, the heat transfer pipe refers to a pipe for transmitting crustal heat from the deep crustal heat area toward the ground surface via a heat transfer medium.

[0012] The heat source is not volcanic magma, but deep crustal thermal zones (8-15 km below the surface), and the heat generated by the decay of radioactive isotopes in the Earth's outer core flows through the mantle and crust to the surface, generating electricity using conductive heat (or more preferably, temperature difference power generation (using the Seebeck effect)).

[0013] The heat of the deep earth's high temperature crust zone 1 is drawn up to the earth's surface via the heat transfer medium as a fluid (drawn up by a pump) that moves inside the heat transfer pipe 20 located close to the deep earth's high temperature crust zone 1, and is used for power generation. As a specific example of power generation, preferably, temperature difference power generation is considered, and the heat of the deep earth's high temperature crust zone 1 is provided to the high temperature side in the temperature difference power generation.

[0014] (Heat storage chambers installed on each work floor surface with different depths) Here, the heat medium pipe 20 connects the heat storage chambers 3 provided at every depth of 200 to 500 m. The reason for connecting the heat medium pipe 20 at each heat storage chamber 3 is that if the length of the heat medium pipe 20 becomes longer than a predetermined value, the pressure of the heat medium inside the heat medium pipe 20 increases and the heat medium pipe 20 bursts, and in order to avoid this, the length of the heat medium pipe 30 is set so as to connect the heat storage chambers 3 provided at every depth of 200 to 500 m.

[0015] Then, by pulling the heat transfer pipe 20 from the ground surface to the heat storage chamber 3 at the deepest depth from the ground surface through the vertical shaft (Figures 8 to 10) described later, it becomes possible to pull up deep crustal heat from the heat storage chamber 3 at the deepest depth from the ground surface to the ground surface.

[0016] Similarly, by pulling the heat transfer pipe 20 from the ground surface to the heat storage chamber 3 on the lower floor through the vertical shaft (Figures 8 to 10) described later, it becomes possible to raise deep crustal heat from the heat storage chamber 3 on the lower floor through the heat storage chamber on the upper floor (the heat storage chamber at the deepest depth from the ground surface).

[0017] In this way, by pulling the heat transfer pipes 20 from the ground surface through the vertical shafts (Figures 8 to 10) described later to the heat storage chambers 3 (Figure 3(b)) on each floor, it becomes possible to pull up deep crustal heat to the ground surface through the heat storage chambers 3 on each floor.

[0018] The heat transfer pipe 20 from the heat storage chamber 3 located at the deepest position from the earth's surface extends to the vicinity of the deep crust region, making it possible to raise the deep crustal heat to the heat storage chamber 3 located at the deepest position from the earth's surface. In this way, the deep crustal heat is raised to the earth's surface side via each heat storage chamber 3.

[0019] In each heat storage chamber 3, a heat medium pipe 20 (which is also the heat medium pipe 20 from the lower floor) heading toward the lower floor is provided in the heat storage chamber 3 so that heat can be efficiently exchanged and heat can be reduced. Also, a heat medium pipe 20 (which is also the heat medium pipe 20 from the upper floor) heading toward the upper floor is provided in the heat storage chamber 3.

[0020] 4(a) is an explanatory diagram of how the folded heat medium pipes 38 are installed in the heat storage chamber through the horizontally long hole 39. Inside the heat storage chamber 3, a total of 80 heat medium pipes are installed, including 40 heat medium A pipes arranged vertically in the horizontal plane and 40 heat medium B pipes arranged horizontally in the horizontal plane.

[0021] FIG. 4(b) shows the inside of the heat storage chamber 3 and also shows that inside each heat medium pipe 20, the heat medium is drawn up by a pump P from the heat storage chamber 3 on the lower floor to the heat storage chamber 3 on the upper floor.

[0022] The heat storage chamber 3 shown in Figure 4 (c) is made of blocks of heat storage bricks (heat-resistant bricks containing a material that increases the specific heat) stacked in multiple layers as a lower layer, middle layer, and upper layer, with insulation material provided in the lower and upper layers, and a first group of heat transfer pipes (heat transfer pipes A 28) and a second group of heat transfer pipes (heat transfer pipes B 29) are stacked alternately so as to cross (orthogonally cross) each other through holes provided in the blocks in the middle layer.

[0023] To assemble the heat storage chamber 3, a large number of cubic blocks made of heat storage bricks, each 2m long, 2m wide and 2m high, are made on the ground floor (ground level), and oblong holes are drilled in the side walls of the blocks to accommodate the heat transfer pipes.The blocks are then carried to each floor by elevator, lifted horizontally by a forklift, and stacked on the leveled work floor.

[0024] The lower floors of the block (for example, the first and second floors) are packed with insulation material, and on the middle floors (for example, the third to sixth floors), as shown in Fig. 4(a), heat transfer pipes A and B are inserted alternately horizontally through the oblong holes 39 described above as heat transfer pipes 38 folded multiple times, vertically on the floor above that, and horizontally on the floor above that. One folded side of the folded heat transfer pipes A and B is the heat transfer pipe from the floor above, and the other folded side is the heat transfer pipe heading to the floor below.

[0025] And, pack the blocks on the higher floors (for example, the 7th floor) with insulation material. And, it is more preferable to thickly cover the area around and the top of the heat storage chamber with insulation material to enhance the insulation effect.

[0026] The small semicircular window shown on the left side of Figure 4(c) allows one to see the heat transfer tube inserted at the bottom.

[0027] 4(c), reference numeral 25 denotes a heat storage material wall portion, 26 denotes a heat storage material beam portion, and 27 denotes a heat storage material partition wall portion. The heat storage material partition wall portion 27 is a wall penetrating a heat medium A pipe 28 and a heat medium B pipe 29.

[0028] Here, Figure 4(b) shows that inside each heat transfer pipe 20, the heat transfer medium is drawn up by pump P from the heat transfer chamber 3 on the lower floor to the heat transfer chamber 3 on the upper floor, and Figure 5 shows the state of the heat transfer chamber 3 that is deepest from the ground surface.

[0029] In Figure 5, a heat transfer pipe 20 inside a center shaft excavated below the work floor surface where the deepest heat storage chamber (lowest heat storage chamber) 3 from the ground surface is installed extends to near the deep crustal heat area, and deep crustal heat is raised to the ground surface through that heat storage chamber and the heat storage chamber above it.

[0030] FIG. 5 shows a case where the liquid heat transfer medium 2 in the cooling tower 18 is changed to gas (steam) 17, and the heat transfer medium is used as a gas rather than a liquid. The heat transfer medium 2, which was liquid due to the high temperature, suddenly becomes gas (steam) 17, and the specific gravity decreases, so that the pressure inside can be kept low even if the heat transfer pipe is set long, and the rupture of the heat transfer pipe 20 can be avoided. Since it is considered that the work surface on the lowest level will be exposed to high heat and will be difficult to work on, there is an advantage to adopting this method of moving the work surface on the lowest level away from the deep crustal heat region (using a longer heat transfer pipe).

[0031] The cross-sectional configuration of the heat transfer pipe extending from the earth's surface to near the deep crustal zone is as shown in Figure 6(a), with multiple heat collection pipes 21 (inexpensive general SUS steel pipes can be used without using special piping materials that can withstand high pressure) arranged circumferentially around a central heat recovery pipe 22 (the heat transfer medium moves inside the pipe due to the action of pump P) that collects heat using the heat transfer medium, and a protective pipe 23 that protects the entire system is provided on the outside.

[0032] With this three-layer structure, the heat collection pipes surround the recovery pipes to prevent the temperature of the heated heat transfer medium from dropping, and they act as insulators to prevent heat from being lost to the surrounding crust.

[0033] The longitudinal configuration of such heat transfer pipes is such that a centralized heat collection pipe of about 200 to 500 m is attached at the bottom layer, and a multiple spiral tube is embedded inside the centralized heat collection pipe to increase the heat collection effect (Figure 6(a)).

[0034] Then, in the bottom layer, the configuration described above in relation to Figure 5 is used (the heat transfer medium 2, which is liquid due to the high temperature, quickly turns into gas (steam) 17, and as its specific gravity decreases, the pressure inside the heat transfer pipe can be kept low even if the heat transfer pipe is set long, and the heat transfer pipe can be prevented from bursting,) but water or mercury is used as the liquid heat transfer medium.

[0035] Here, Fig. 6(b) shows the flow of the heat medium between adjacent floors in the depth direction. The high-temperature heat medium α rising from the bottom in the depth direction and the lower-temperature heat medium β descending from the top exchange heat inside the same heat medium tube, which can contribute to the efficiency of power generation. In other words, the heat medium α and the heat medium β exchange heat inside the heat storage chamber and outside the heat storage chamber. Fig. 6(b) shows that heat exchange takes place outside the heat storage chamber between the heat recovery pipe 22 constituting the heat medium pipe and the heat collection pipe 21 around it.

[0036] (Worker rooms and work equipment rooms installed on each work floor at different depths) In addition to the heat storage chamber, at least one of a worker's room and a work equipment room is installed in each space of the work floor surface with different depths so that maintenance work can be carried out safely during construction and after completion. Figure 7 shows a case where a worker's room and a work equipment room are installed, the worker's room is equipped with air conditioning equipment, and the work equipment room is equipped with cooling equipment.

[0037] For cooling or air conditioning, liquid air (a liquid obtained by lowering the temperature of air) that can be produced in-house using electricity is sent to an evaporator and mixed with gaseous air. The liquid air evaporates, removing the heat of evaporation and lowering the temperature of the gaseous air.

[0038] Using this principle, the system shown in Figure 7 uses artificial liquid air instead of liquid air. That is, an oxygen cylinder 44 and a nitrogen tank 45 are installed, and oxygen and nitrogen are mixed in the ratio of 79% and 21%, respectively, to create the artificial air. The liquid oxygen cylinder 44 is connected to a vaporizer mixer 46 via a liquid oxygen supply valve, and the liquid nitrogen tank 45 is connected to the vaporizer mixer 46 via a liquid nitrogen supply valve. The vaporizer mixer 46 can take in room temperature air (gaseous air) through an outside air intake adjustment valve or the like. The liquid turns into gas and removes the heat of evaporation, causing the temperature to drop, and low-temperature air (cooled air) 47 is supplied from the vaporizer mixer 46.

[0039] In Fig. 7, a rest room 50 is provided as a worker's room where workers can take a rest, cooled by low-temperature air 47 and further cooled or heated by a heat pipe system 51. Also provided is a work equipment room where an excavator 52, an AI robot and underground suit 48, air bearings 49 as a transport device, etc. are stored in a cooled state.

[0040] (Drilling of shafts and adits) In Figures 1, 8, 9, and 10, 11 is a center shaft, 12 is a satellite shaft, and 13 is an elevator shaft. As shown in Figure 8(a), satellite shafts 12 and elevator shafts 13 that connect adjacent upper and lower floors are provided around center shaft 11, which runs in a straight line from the ground surface to near the deep crustal heat area. The lower end of satellite shaft 12-1, which connects the ground surface to the floor immediately below (first basement floor), and the upper end of satellite shaft 12-2, which connects the first basement floor to the floor immediately below (second basement floor), are excavated so that they overlap in the depth direction as a margin.

[0041] Reference numeral 33 shown in Figures 10(a) and (b) denotes a connecting shaft that connects the center shaft 11 and the satellite shaft 12. Each shaft is excavated from the ground floor (surface) 10 to a depth of 200 to 500 m.

[0042] The connecting shaft 33 is for enabling the heat transfer pipe to be displaced laterally from the center shaft 11 to the satellite shaft 12 when the heat transfer pipe is drawn from the ground surface into the heat storage chamber. As shown in Fig. 10(b), in the depth direction, the intermediate part is 6500 mm wide (larger than the diameter 6000 mm of the large flange 32 in Fig. 9(c)) as viewed from the arrow AA, and the uppermost and lowermost sides are horizontal shafts each 8500 mm wide.

[0043] The reason why the width of the horizontal shaft is 8,500 mm at the top is because Y1 is necessary to move the shaft (shaft) drilling equipment Y1 (Fig. 1) from the center shaft 11 to the satellite shaft 12. Also, the reason why the width of the horizontal shaft is 8,500 mm at the bottom is because Y1 is necessary to move the shaft (shaft) drilling equipment Y1 (Fig. 1) from the satellite shaft 12 to the center shaft 11.

[0044] Regarding the connecting shaft 33, the top, customs clearance section and bottom can all be unified to a width of 8,500 mm.

[0045] In FIG. 1, Y1 is a shaft (vertical shaft) excavation device, Y2 is a horizontal shaft excavation device, and Y3 is a soil and sand recovery device, which includes an earth removal transport vehicle 15 that transports earth removal and the like on a work floor surface 16 to an elevator gauge 14 installed inside the elevator shaft as shown in FIG. 8(b).

[0046] Although the location of the elevator shaft is shown on the opposite side of the satellite shaft 12 from the center shaft, this is not limited thereto, and it may be arranged around the center shaft together with the location of the satellite shaft 12.

[0047] The satellite shaft 12 is important as an open space for drawing in the long heat transfer pipes assembled on the ground floor (ground surface) through the connecting shaft 33 into the heat storage chamber 3 .

[0048] Items brought into the heat storage chamber 3 are mainly transported by elevator installed in the elevator shaft 13, but long heat transfer pipes are drawn into the heat storage chamber 3 through the center shaft 11, the connecting shaft 33, and the satellite shaft 12.

[0049] To achieve this, the excavation work begins with digging from the ground surface to a specified depth, along with the center shaft, satellite shafts, a connecting shaft connecting the satellite shaft and the center shaft, and elevator shafts around the center shaft (the first step shown in Figure 1(a)).

[0050] Then, using a drilling device that has been brought in from one of these shafts, or that has been brought in and assembled, a first cross shaft that intersects with the center shaft formed in the first step is excavated (second step).

[0051] Then, the excavated soil in the second step is discharged to the surface through the elevator shaft, and a first work floor surface 16a is formed in the first cross shaft, which has space to accommodate at least one of a worker's room and a work equipment room, as well as a heat storage chamber that is located in the center shaft and pulls in a heat transfer medium pipe through a connecting shaft to the satellite shaft to transfer deep crustal heat of 250°C to 500°C to the surface via a heat transfer medium moved by a pump (third step shown in Figure 1(b)).

[0052] Then, by replacing the ground surface with the first working floor surface, and without shifting the position of the center shaft, the first to third steps are carried out in sequence until the deep crustal heat zone is approached, so as to form a second working floor surface 16b in the second adit (Figures 1(c) and (d)), and the center shaft is excavated from the working floor surface farthest from the ground surface to a position approaching the deep crustal heat zone (the fourth step shown in Figure 2).

[0053] Here, the size of the heat storage chamber 3 formed on each work floor surface is 20 m in each of the length, width, and height directions as shown in Fig. 4(a). Also, the size of the worker room and the work equipment room formed on each work floor surface is 10 m in length, width, and height.

[0054] In this way, the size of the spaces X1 and X2 shown in FIG. 1 on each work floor surface is at least 30 m in length and width and 20 m in height.

[0055] In the second step, drilling the tunnel is done using a drilling device to make a hole in the hard rock, then dynamite is inserted and exploded, and the crushed rock is removed using a shovel loader. A shield machine can also be used to make larger spaces.

[0056] (Assembly of heat transfer pipes) First, as shown in Figure 9(a), a tower is constructed above the central shaft 11 on the ground floor (ground surface), and the heat transfer pipes for each floor, including the first basement floor, are assembled by welding the blank pipes. The heat transfer pipe for the first basement floor is lowered from the central shaft 11 and moved laterally to the first satellite shaft 12-1 (Figure 8(a)) and pulled into the heat storage chamber for the first basement floor which is formed on the work floor surface for the first basement floor.

[0057] Similarly, the heat transfer pipe for the second basement floor is lowered from the center shaft 11 and moved laterally to the second satellite shaft 12-2 (Figure 8(a)), and then pulled into the heat storage chamber for the first basement floor which is formed on the work floor surface for the second basement floor.

[0058] As for the heat transfer pipe for the lowest layer, it is lowered from the center shaft 11 and moved laterally to the n-th satellite shaft 12-n, and then drawn into the heat storage chamber for the lowest layer formed on the work floor surface for the lowest layer.

[0059] A piping unit 100 (FIG. 3(a)) is provided on each work floor surface, and an end (tip) of a heat transfer pipe that exits the heat storage chamber on the work floor surface and heads toward the lower floor just below is linked (connected) to an end (rear end) of a heat transfer pipe that descends from the center shaft 11 and heads toward the lower floor just below via the piping unit 100.

[0060] The diameters of the center shaft 11 and satellite shafts 12 are 8m, and the maximum width of the connecting shaft 33 is 8.5m. There are about 40 heat transfer pipes 20 (250 to 500m long and bundled together by large flanges 32. The outer diameter of the large flanges 32 is 6m (6000mm) as shown in Figure 9 (b)), making the heat transfer pipes 20 very heavy. For this reason, the heat transfer pipes 20 are placed on a disk supported by about 10 rotating chains 63 and gradually lowered via rotating pulleys 62. When they reach the destination floor, they are moved laterally from the center shaft 11 to the satellite shaft 12 and linked (connected) to the heat storage chamber 3.

[0061] (Excavation of tunnel access for utilizing deep crustal heat for thermal power generation) Furthermore, in this embodiment, in order to form a power generation system (power generation device), a large power plant using a large number of thermoelectric power generation element units that generate power by temperature difference using deep crustal heat as a power generation section is formed, so many tunnel access shafts are further excavated. If an existing tunnel can be used, it will be used.

[0062] More specifically, as shown in FIG. 12(a), the method includes the steps of forming a plurality of tunnels, each having a diameter of 8 m, spaced apart from each other at a predetermined interval (e.g., 16 m) in a first direction (X direction), and forming a plurality of second tunnel adits, each of which is spaced apart from the first tunnel adit in the depth direction (Z direction) at a predetermined interval (e.g., 16 m) in a second direction (Y direction) intersecting the first direction.

[0063] In this manner, the first and second groups of tunnels are alternately stacked so as to intersect (orthogonally) with each other (FIG. 12(a)).

[0064] The siding 53 shown in Figures 11 and 12(b) refers to a lead-in track or shunting track to each tunnel adit that is provided separately from the track (rail) laid inside each tunnel adit so that moving vehicles can move inside the tunnel adit. The 9th floor surface of Figure 12(b) shows the state after being drawn into the tunnel adit, and the 10th floor surface of Figure 12(b) shows the state before a new thermoelectric element unit 4 is drawn into the tunnel adit by a maintenance replacement vehicle.

[0065] The overall layout space of each tunnel 42 is set to a scale of 3500 m in the X and Y directions, and 300 m (10 stories) in the Z direction.

[0066] In each tunnel 42, a plurality of thermoelectric power generation element units 4 spaced 16 m apart from one another are carried in and installed by a mobile vehicle 72 such as a trolley shown in Fig. 11 in a connected state. Then, the thermoelectric power generation elements in different tunnels 42 are connected to one another by sidings 53.

[0067] (Thermoelectric power generation element unit) Generally, thermoelectric generating elements (temperature difference generating elements) are known from the following documents.

[0068] · January 13, 2021 issue Journal of physics D; Applied physics pp.115503 Mixed-Phase effect of the high Seebeck coefficient and low electrical resistivity in the Ag2S 2) August 21, 2019, Nikkei Shimbun NEDO, Aisin Seiki, and Ibaraki University announced that they have succeeded in developing a technology that uses only common materials to generate electricity using slight temperature differences such as body heat. Made of iron, aluminum, and silicon, it does not contain any rare or toxic elements like conventional materials, and material costs can be reduced to one-fifth or less.

[0069] It is expected that further research and development of such thermoelectric generation elements will be carried out in the future.

[0070] In this embodiment, thermoelectric power generation elements using the Seebeck effect are unitized into a thermoelectric power generation element unit (element unit), and the earth's crustal heat transmitted to the surface side by a heat transfer pipe is circulated to the high-temperature side, while cold water is circulated to the low-temperature side, generating electricity from the temperature difference between the two. A large number of these element units are used to create a huge power plant with a capacity of several million kW.

[0071] Figure 13(a) shows an image of an element board equipped with multiple thermoelectric generation elements for temperature difference power generation and how to make it. Alumel wire with a wire diameter of 1 mm is used with a vertical wire density of 23,322 wires / 75,000 mm 2 The ceramic element is wrapped around a U-shaped SUS plate and both ends are fixed with ceramic material. Then, multiple element plates like this are arranged.

[0072] In FIG. 13(b), the element boards 37 are arranged one-dimensionally in the longitudinal direction, and multiple element boards 37 are arranged in a direction intersecting the longitudinal direction, with heat transfer medium flow paths 35 and cold water flow paths 36 arranged alternately in parallel, sandwiching each thermoelectric power generation element, in the direction intersecting the longitudinal direction.

[0073] In Fig. 14(a), the element board 37 is arranged two-dimensionally, and the heat transfer medium flow path and the cold water flow path are arranged perpendicular to each other. In Fig. 14(a) and (b), 38 indicates the flow of the heat transfer medium, 39 indicates the flow of the cold water, 40 indicates the drainage, and 41 indicates the return to the heat storage chamber.

[0074] Figure 15(a) shows the experimental method and circuit diagram for measuring the amount of power generated by a thermoelectric generating element, and Figure 15(b) shows the experimental results. In the figure, 54 is a kettle, 55 is an ice pack, 56 is an Alumel wire, 57 is a copper plate, 58 is a Bakelite plate, 59 is pine wood, 60 is an ammeter, and 61 is a voltmeter. From the experimental results, it was demonstrated that, using 100°C on the high temperature side and 0°C on the low temperature side, the thermoelectric generating element output 0.2mW of power due to the Seebeck effect.

[0075] By providing a large number of such thermoelectric generating elements (for example, 100 billion elements when the temperature difference is 100° C.), a large amount of power (for example, 2 million kW) can be output in the huge power plant shown in FIG.

[0076] According to the embodiment of the present invention described above, unlike power generation using magma steam, which can become unstable due to the movement of magma, it is possible to provide an excavation method that can be expected to generate power stably for an ultra-long period of time and even on a large scale.

[0077] By using the drilling method according to this embodiment, fuel-free power generation that does not use fossil fuels such as coal or natural gas becomes possible, eliminating the need to import fuel (self-supplied emergy source). Since the demand in the metropolitan area can be met from power plants in the suburbs, the transmission distance becomes shorter, reducing transmission losses. In addition, most of the equipment has no moving parts, has a long life, and reduces maintenance costs.

[0078] Furthermore, it can be used in most places around the world, except in volcanic areas and places prone to tectonic activity. It is possible to generate electricity in the desert, draw water from large rivers and lakes, green the desert, and build oasis cities with large-scale power generation. And by turning the desert into arable land, it is possible to increase food production to alleviate the world's food shortage.

[0079] (Modification) Although the preferred embodiments of the present invention have been described above, the present invention is not limited to these embodiments, and various modifications and changes are possible within the scope of the gist of the present invention.

[0080] In the above embodiment, the center shaft is described as being provided penetrating from the surface to a position approaching the deep crustal heat area, but the center shaft may be provided so as to suitably follow a continuous trajectory from a position approaching the deep crustal heat area to the surface side via a plurality of heat storage chambers. For example, the center shaft 11 may be provided parallel to and offset between different work floor surfaces by increasing the number of heat storage chambers and shortening the heat storage pipes connecting adjacent heat storage chambers in the depth direction, thereby providing a height for the work floor surface and erecting the heat storage pipes on the work floor surface.

[0081] Furthermore, the shafts may be excavated from the ground surface simultaneously or non-simultaneously.

[0082] In addition, the satellite shaft 12 is not limited to being formed between the center shaft 11 and the elevator shaft 13 (Figure 8 (a)), but the center shaft 11 may be formed between the satellite shaft 12 and the elevator shaft 13.

[0083] The present invention is not limited to applications for temperature difference power generation, but can also be applied to power generation using a system that does not rely on volcanic magma but instead recovers deep crustal heat to turn a steam turbine. [Explanation of symbols]

[0084] 1 Deep crustal high temperature zone, 3 Heat storage chamber, 4 Thermoelectric power generation element unit, 11 Center shaft, 12 Satellite shaft, 13 Elevator shaft, 16 Working floor, 20 Heat transfer pipe, 28 Heat transfer pipe A, 29 Heat transfer pipe B, 33 Connecting shaft, 50 Relaxation room, P Pump

Claims

1. A method for excavating a center shaft from the earth's surface to a position approaching a deep crustal heat field, comprising the steps of: A first step of excavating satellite shafts together with the center shaft from the ground surface to a predetermined depth, a connecting shaft connecting the satellite shafts and the center shaft, and an elevator shaft around the center shaft; a second step of excavating a first cross shaft intersecting the center shaft formed in the first step, using a drilling device brought in from any of the shafts or brought in and assembled; a third step of discharging the excavated soil from the second step to the ground surface through the elevator shaft, and forming a first work floor surface having a space in the first cross shaft for installing at least one of an operator room and a work equipment room, and a heat storage chamber that is arranged in the center shaft and leads a heat transfer medium pipe through the connecting shaft to the satellite shaft to transfer deep crustal heat of 250°C to 500°C to the ground surface via a heat transfer medium moved by a pump; A fourth step of performing the first to third steps in sequence until the deep crustal heat zone is approached, so as to replace the ground surface with the first working floor surface and form a second working floor surface in the second adit, and excavating the center shaft from the working floor surface farthest from the ground surface to a position approaching the deep crustal heat zone; A drilling method comprising the steps of:

2. 2. The drilling method according to claim 1, wherein the center shaft is provided penetrating from the earth's surface to a position approaching a deep crustal heat region.

Citation Information

Patent Citations

  • JP1979002862U

  • The temperature difference between the hydrogen-oxygen gas generator ·

    JP1984000462U

  • Energy supply system reusing existing cavern

    JP2011145050A

  • Geothermal heat recovery from high-temperature, low-permeability formations for power generation using a closed-loop system

    JP2019513211A

  • Geothermal recovery equipment

    JP6587118B1