Method and device for allocating procurement sources
By modeling supplier priorities hierarchically and applying specific constraints, the supplier allocation method addresses 'no solution' errors, ensuring efficient supplier allocation and maintaining supply and demand balance, thereby enhancing operational efficiency.
Patent Information
- Application Number
- JP2021000138
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2021-01-04
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2041-01-04
AI Technical Summary
The occurrence of 'no solution' errors in supplier allocation calculations due to conflicting priorities between procurement sources and retail stores leads to inefficiencies and increased operational time in demand balancing groups, especially as contract types become more diverse, disrupting supply and demand balance and requiring lengthy corrective work.
A supplier allocation method and device that models priority as a hierarchical set with variable-length structures, incorporating individual and hierarchical sufficiency determinations, and allocation limits to ensure efficient allocation calculations by generating and applying specific mathematical constraints.
This approach reduces the occurrence of 'no solution' errors, maintains supply and demand balance, and enhances operational efficiency by allowing for seamless allocation calculations even with diverse contract types, thus improving overall operational efficiency.
Smart Images

Figure 0007558816000001 
Figure 0007558816000002 
Figure 0007558816000003
Abstract
Description
[Technical field]
[0001] The present invention relates to a method and device for allocating procurement sources taking into account multiple priorities. [Background technology]
[0002] In the calculation of supplier allocation, it is common to apply mathematical optimization problems to calculate a plan that satisfies economics such as minimizing costs or maximizing profits. In this case, the supplier of generators and other equipment is selected based on the lowest cost.
[0003] On the other hand, since liberalization, transactions have become more diverse, and various types of contracts are being concluded. For example, it is necessary to perform allocation calculations that are not necessarily optimal in terms of economic efficiency. Specifically, this includes wired use of renewable energy, and cases where priority purchases are specified in individual contracts. In these cases, economic efficiency is secondary, and allocation calculations are performed by specifying the preferred procurement source as a schedule, that is, a constant in the optimization problem. [Prior art documents] [Patent documents]
[0004] Patent No. 5159518 Weighting priorities of objective functions in allocation calculations [Non-Patent Document 1] HP Williams "How to Create Mathematical Programming Models" Sangyo Tosho 1995 (ISBN-13: 978-4782846018) A basic book on how to handle logical conditions in integer programming. [Non-Patent Document 2] Ryuhei Miyashiro, "Introduction to Integer Programming Solvers", Operations Research, 57, 4, pp.183-189 (2012) Basic literature on trends in software for solving integer programs Summary of the Invention [Problem to be solved by the invention]
[0005] A demand balancing group (hereafter, demand BG) that bundles multiple retail businesses is known. In a demand BG, each retail business has thermal power generation, wind power generation, hydroelectric power generation, etc. as its procurement sources. For example, a demand BG with retailers 1 and 2 has hydroelectric generators y and w and wind power generators x and z as its procurement sources, with hydroelectric generator y and wind power generator x belonging to retailer 1, and hydroelectric generator w and wind power generator z belonging to retailer 2. Here, it is possible to set the priority of the procurement sources within retailers 1 and 2. For example, if hydroelectric power generation has a higher priority than wind power generation, then hydroelectric generators y and w will have priority 0, and wind power generators x and z will have priority 1.
[0006] In addition to setting such priorities for suppliers, it is also possible to set priorities for retailers (hereinafter referred to as retail priority) that indicate which retailer should be given priority in allocating electricity from the viewpoint of the power generators that are suppliers. For example, if retailer 1 is given a higher priority than retailer 2, and unless wind power generator x belonging to retailer 1 is allocated electricity up to a preset value, it will not be allocated to wind power generator z belonging to retailer 2.
[0007] For this reason, unless the allocation reaches the preset value for wind turbine x belonging to retailer 1, retailer 2 cannot receive supply from wind turbine z. Therefore, retailer 2 has no choice but to rely on hydroelectric generator w alone to meet demand, and if hydroelectric generator w alone cannot meet demand, retailer 2 will lose the balance between supply and demand even though it has an allocation resource, wind turbine z. As a result, a "no solution" error will occur in the allocation calculation.
[0008] In the demand BG, when the number of retail businesses increases, the priority of the supplier and the priority of the retailer compete with each other, and the frequency of the occurrence of the "no solution" error in the result of the allocation calculation may increase. When the "no solution" error occurs in the allocation calculation, it is necessary to determine the cause of the "no solution" error, perform correction work such as resetting the priority of the supplier, and execute the allocation calculation again. However, the cause of the "no solution" error is rarely immediately identified, and it often takes time to investigate the cause of the "no solution" error in the allocation calculation and to correct and re-execute the calculation. With the current trend of diversifying contract types, the work time required to investigate the cause of the "no solution" error in the allocation calculation and to correct and re-execute the calculation is likely to be long and troublesome. Therefore, the occurrence of the "no solution" error has been a factor that reduces the operational efficiency of supply and demand operations.
[0009] In particular, even if there are allocation resources, if the supply and demand balance of a retailer is disrupted and a "no solution" error occurs in the allocation calculation, it may happen that the supply and demand of the retailer can actually be matched, and the correction work itself will be a futile effort. Therefore, in recent years, there has been a strong demand to reduce the occurrence of "no solution" errors and improve business efficiency.
[0010] An object of the present invention is to provide a method and apparatus for allocating procurement sources that can avoid the occurrence of a "no solution" error if the method is realistic, thereby improving the operational efficiency of supply and demand operations. [Means for solving the problem]
[0011] In order to achieve the above object, the method of allocating procurement sources according to this embodiment is a method of allocating procurement sources when there are multiple retail businesses, and includes the following steps (1) to (15). (1) A supplier storage step for storing supplier data, which is the basis of the allocation calculation. (2) A priority storing step of storing priorities of suppliers having a variable-length hierarchical structure with the number of registered suppliers as a maximum value and retail priorities set between retail businesses. (3) storing data relating to the retailer; (4) A priority assignment generation step of generating a priority assignment in which one or more suppliers are associated with each priority of each supplier. (5) A priority assignment storage step for storing the priority assignment. (6) An individual upper limit judgment constraint generating step of reading out the priority allocation and generating, as an individual upper limit judgment constraint, a formula for determining whether the allocation to each procurement source has reached a predefined upper limit value. (7) A supply and demand match determination constraint generating step of generating a mathematical expression for determining whether the supply and demand of the retail business to which the supplier belongs are matched as a supply and demand match determination constraint. (8) An individual satisfaction judgment constraint generating step of generating, as an individual satisfaction judgment constraint, a formula for determining whether an individual satisfaction condition is satisfied, that is, whether each procurement source satisfies either the individual upper limit judgment constraint or the supply and demand match judgment constraint. (9) A hierarchical satisfaction judgment constraint generation step of reading out the priority allocation and generating, as a hierarchical satisfaction judgment constraint, a mathematical formula for determining whether a hierarchical satisfaction condition is satisfied, that is, whether all of the suppliers belonging to each priority hierarchy satisfy the individual satisfaction conditions. (10) An allocation restriction constraint generation step of reading out the priority allocation and generating, as an allocation restriction constraint, a formula that enables allocation to a supplier belonging to a lower priority hierarchy only when the immediately higher priority hierarchy satisfies the hierarchy satisfaction condition. (11) An optimization problem priority constraint storage step of storing the individual upper limit judgment constraint, the supply and demand match judgment constraint, the individual fulfillment judgment constraint, the hierarchical fulfillment judgment constraint, and the allocation limit constraint as optimization problem priority constraints. (12) An optimization problem objective function storage step for storing the optimization problem objective function. (13) A performing optimization step of reading the optimization problem priority constraints and the optimization problem objective function and solving the corresponding optimization problem. (14) An optimization result storage step for storing the optimization result. (15) An optimization result display step for displaying the optimization result.
[0012] An embodiment of the present invention can also be seen as a source allocation device having components for executing the above steps. [Brief description of the drawings]
[0013] [Figure 1] Block diagram of the first embodiment [Diagram 2] A flowchart showing a flow of data generation and data display according to the first embodiment. [Diagram 3] FIG. 1 is an explanatory diagram showing a relationship of data generation in the first embodiment; [Figure 4] FIG. 1 is a diagram showing mathematical expressions according to a first embodiment; [Diagram 5] FIG. 1 shows the formulas, formulas and subscript definitions of the first embodiment. [Figure 6] FIG. 13 is a diagram showing a calculation example of a comparative example with the first embodiment; [Figure 7] FIG. 13 is a diagram showing a calculation example of a comparative example with the first embodiment; [Figure 8] FIG. 13 is a diagram showing a calculation example of a comparative example with the first embodiment; [Figure 9] FIG. 1 is a diagram showing a calculation example of the first embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0014] (First embodiment) [composition] The first embodiment will be described with reference to the block diagram of FIG. 1. The first embodiment is a source allocation method in which each component executes each step. The first embodiment may be understood as a source allocation device having components that execute each step. Note that the aspects of the embodiment include a source allocation method and device, as well as a source allocation program that causes a computer to execute each step, and a recording medium on which the program is recorded.
[0015] 1, the supplier allocation device 100 is provided with databases (hereinafter referred to as DB) 1, 2, 4, 8, 9, 11, 13, 16, 17, and 18, which are data storage units. The supplier allocation device 100 is also provided with six generation units 3, 5, 6, 7, 14, and 15. In addition to the above components, the supplier allocation device 100 is also provided with an optimization execution unit 10 and an optimization result display unit 12.
[0016] Each of the DBs provided in the supplier allocation device 100 performs a storage step of storing data. Of these, 1 is a supplier DB, 2 is a priority DB, 16 is a retailer DB, and 4 is a priority allocation DB. Supplier DB 1 stores supplier data, which is the basis of the allocation calculation (supplier storage step), and priority DB 2 stores supplier priorities and retail priorities set between retailers (priority storage step). Supplier priorities have a variable-length hierarchical structure with the number of registered suppliers as the maximum value. Retailer DB 16 stores data related to retailers (retailer storage step). The data related to retailers includes supply and demand data of retailers, etc. Priority allocation DB 4 stores priority allocations generated by priority allocation generation unit 3, which will be described later (priority allocation storage step).
[0017] Reference numeral 8 denotes an optimization problem priority constraint DB, 9 an optimization problem objective function DB, 11 an optimization result DB, 13 an optimization problem normal constraint DB, 17 an optimization problem supply and demand match judgment constraint DB, and 18 an optimization problem individual satisfaction judgment constraint DB. Of these, the optimization problem priority constraint DB 8 reads data such as the individual upper limit judgment constraint, the supply and demand match judgment constraint, and the allocation limit constraint from data generation units 5, 6, and 7 described later, respectively, and stores these constraints as optimization problem priority constraints (optimization problem priority constraint storage step). Note that the optimization problem priority constraint DB 8 may also read data such as the supply and demand match judgment constraint and the individual satisfaction judgment constraint from data generation units 14 and 15 described later, respectively, and store these constraints as optimization problem priority constraints.
[0018] The optimization problem objective function DB9 stores the optimization problem objective function (optimization problem objective function storage step). The optimization result DB11 stores the optimization result as a solution of the optimization problem solved by the optimization execution unit 10 (optimization result storage step). As shown in the example of FIG. 9, the embodiment according to the present invention is included in a class of optimization problems mathematically called "integer programming". As shown in Non-Patent Document 2, integer programming is generally solved by applying commercial / non-commercial software called a general-purpose solver. The same assumption is made in the embodiment according to the present invention. The optimization problem normal constraint DB13 stores the optimization problem normal constraint as a conventional existing constraint, not the optimization problem priority constraint (optimization problem normal constraint storage step). The optimization problem normal constraint is, for example, a supply and demand matching constraint, an upper limit value constraint of the supplier, a lower limit value constraint of the supplier, etc. The optimization problem supply and demand matching judgment constraint DB17 is a database that reads the supply and demand matching judgment constraint from the data generation unit 14 described later and stores it. The optimization problem individual satisfied judgment constraint DB 18 is a database that reads individual satisfied judgment constraints from the data generating unit 15, which will be described later, and stores them.
[0019] Each of the six generating units provided in the supplier allocation device 100 performs a data generating step. Of these, the unit 3 is a priority assignment generating unit. The priority assignment generating unit 3 reads supplier data from the supplier DB 1, reads supplier priorities from the priority DB 2, and generates a priority assignment in which one or more suppliers belong to each supplier priority (priority assignment generating step).
[0020] Reference numeral 5 denotes an individual upper limit judgment constraint generation unit, 6 denotes a hierarchical fulfillment judgment constraint generation unit, 7 denotes an allocation limit constraint generation unit, 14 denotes a supply and demand match judgment constraint generation unit, and 15 denotes an individual fulfillment judgment constraint generation unit. The individual upper limit judgment constraint generation unit 5 reads out the priority allocation from the priority allocation DB 4, and generates, as an individual upper limit judgment constraint, a formula for determining whether the allocation to each procurement source has reached a predefined upper limit value (individual upper limit judgment constraint generation step).
[0021] The hierarchical satisfaction judgment constraint generating unit 6 reads out the priority assignment from the priority assignment DB4, and generates a formula as a hierarchical satisfaction judgment constraint for judging whether or not the hierarchical satisfaction condition is satisfied, that is, all of the suppliers belonging to each priority hierarchy satisfy the individual satisfaction condition (hierarchical satisfaction judgment constraint generating step). The allocation restriction constraint generating unit 7 reads out the priority assignment from the priority assignment DB4, and generates a formula as an allocation restriction constraint for enabling allocation to the suppliers belonging to the lower priority hierarchy only when the immediately higher priority hierarchy satisfies the hierarchical satisfaction condition (allocation restriction constraint generating step).
[0022] The supply and demand match judgment constraint generating unit 14 calls up data on retailers from the retailer DB 16, and generates a formula for judging whether the supply and demand of the retailer to which the supplier belongs are matched as a supply and demand match judgment constraint (a supply and demand match judgment constraint generating step).The individual satisfaction judgment constraint generating unit 15 generates a formula for judging whether an individual satisfaction condition is satisfied, that is, whether either the individual upper limit judgment constraint or the supply and demand match judgment constraint is satisfied at each supplier, as an individual satisfaction judgment constraint (an individual satisfaction judgment constraint generating step).
[0023] The optimization execution unit 10 is a part that reads out the optimization problem priority constraint from the optimization problem priority constraint DB8, the optimization problem objective function from the optimization problem objective function DB9, the optimization problem normal constraint from the optimization problem normal constraint DB13, the supply and demand match judgment constraint from the optimization problem supply and demand match judgment constraint DB17, and the individual satisfaction judgment constraint from the optimization problem individual satisfaction judgment constraint DB18, respectively, and solves the optimization problem corresponding to these. The optimization execution unit 10 also judges whether the optimization execution has been normally completed. The optimization result display unit 12 displays the optimization result if the optimization execution unit 10 judges that the optimization execution has been normally completed, and displays the error type if the optimization execution unit 10 judges that the optimization execution has not been normally completed.
[0024] [Data generation and data display] The flow of data processing in the first embodiment will be described with reference to Fig. 2. As shown in Fig. 2, first, the priority allocation generation unit 3 generates priority allocation data (step 20). Next, the individual upper limit judgment constraint generation unit 5 generates individual upper limit judgment constraint data (step 21), the supply and demand match judgment constraint generation unit 14 generates supply and demand match judgment constraint data (step 22), the individual fulfillment judgment constraint generation unit 15 generates individual fulfillment judgment constraint data (step 23), the hierarchical fulfillment judgment constraint generation unit 6 generates hierarchical fulfillment judgment constraint data (step 24), and the allocation restriction constraint generation unit 7 generates allocation restriction constraint data (step 25).
[0025] The individual upper limit judgment constraint, supply and demand match judgment constraint, individual fulfillment judgment constraint, hierarchical fulfillment judgment constraint, and allocation limit constraint generated in the above steps 21 to 25 are stored as optimization problem priority constraints in the optimization problem priority constraint DB 8. The optimization execution unit 10 reads out the optimization problem priority constraint from the optimization problem priority constraint DB8, the optimization problem objective function from the optimization problem objective function DB9, and the optimization problem normal constraint from the optimization problem normal constraint DB13, and solves the optimization problem corresponding to these (optimization execution step: step 26).
[0026] The optimization execution unit 10 judges whether the optimization execution has been normally completed (normal completion judgment step: step 27), and if the optimization execution has been normally completed (Y in step 27), the optimization result display unit 12 displays the optimization result (optimization result display step: step 28).If the optimization execution unit 10 judges that the optimization execution has not been normally completed (N in step 27), the optimization result display unit 12 displays the type of error (error type display step: step 29).
[0027] In the first embodiment described above, the concept of priority regarding suppliers is modeled as a hierarchical set, and is treated as a constraint condition for the optimization problem. "Modeling the concept of priority as a hierarchical set" means that priority is considered as a hierarchy having a hierarchical structure in which multiple suppliers are registered and the number of registrations is set to a maximum value, and first, multiple hierarchies corresponding to the priorities are considered. Each priority hierarchy corresponds to, for example, "priority 0", "priority 1", etc. If all suppliers belong to one of the priority hierarchies, a set of suppliers corresponding to each priority can be derived.
[0028] In the first embodiment, as shown in FIG. 3, an "individual upper limit determination" is performed to indicate that the allocation to each supplier has reached a predefined upper limit, and a "supply and demand matching determination" is performed to determine whether the supply and demand of the retailer to which each supplier belongs are matched. Then, an "individual fulfillment determination" is performed for each supplier based on the logical sum (OR condition) of the "individual upper limit determination" and the "supply and demand matching determination". Furthermore, in the first embodiment, a "hierarchy fulfillment determination" is performed to determine whether all of the suppliers belonging to each priority hierarchy satisfy the individual fulfillment condition. In the first embodiment, by introducing these fulfillment determinations, the priority of each supplier is defined as "unless the immediately higher priority hierarchy satisfies the hierarchy fulfillment condition, the supplier's own power amount will not be allocated", and an "allocation limit constraint generation" is performed.
[0029] If we model the above priority relationships as constraints for an optimization problem using 0-1 variables, the following five constraint data are required: (a) A logical flag indicating that the allocation to each procurement source has reached a predefined upper limit (individual upper limit judgment) (b) A logical flag indicating whether the supply and demand of the retailer to which the supplier belongs is in agreement (supply and demand matching judgment) (c) A logical flag indicating whether the source meets either the individual upper limit or the supply-demand match (individual fulfillment judgment) (d) A logical flag indicating whether a hierarchy satisfies an individual condition (hierarchy satisfaction judgment) (e) A switching function (allocation restriction) that controls whether or not a procurement source belonging to a lower hierarchy priority is allocated if the immediately higher hierarchy does not satisfy the hierarchy satisfaction conditions.
[0030] In the first embodiment, the individual upper limit judgment constraint generating unit 5, the supply and demand match judgment constraint generating unit 14, the individual fulfillment judgment constraint generating unit 15, the hierarchical fulfillment judgment constraint generating unit 6, and the allocation limit constraint generating unit 7 convert the above five constraint data (a) to (e) into formulas using 0-1 variables. The formulas generated by the generating units 5, 14, and 15 are shown in FIG. 4, and the formulas generated by the generating units 5 and 6 are shown in FIG. 5. Both are for the case where the priorities are x and x-1. The formulas and the definitions of the subscripts are shown in the lower part of FIG. 5.
[0031] As shown in Fig. 4, the individual upper limit judgment constraint generating unit 5 generates formula (1) for any f (for each supplier), and Δ=1 only when allocation is completed up to a predefined upper limit value. The supply and demand matching judgment constraint generating unit 14 generates formula (2) for any f (for each supplier within retailer), and Δ'=1 only when the supplier for the forecasted demand is allocated. The individual fulfillment judgment constraint generating unit 15 generates formula (3) for any f (for each supplier within retailer), and Δ=1 or δ=1 if Δ'=1 is satisfied.
[0032] 5, the hierarchical satisfaction judgment constraint generating unit 6 generates one formula (4) for each priority level in one hierarchy, and L=1 only when δ=1 in all hierarchical levels. Furthermore, the allocation limit constraint generating unit 7 generates formula (5) for any g (for each supplier), and allocation is possible only when L=1.
[0033] [Effect] A specific comparative example will be used to explain a case where a priority constraint is applied according to the first embodiment and a case where a normal constraint is applied according to the conventional technology. Allocation calculations for the entire demand BG are shown in Figs. 6 to 9. In a demand BG having retailers 1 and 2, the demand D1 of retailer 1 is 250 kWh, and the demand D2 of retailer 2 is 300 kWh. There are hydroelectric generators y and w and wind power generators x and z as supply sources, with hydroelectric generator y and wind power generator x belonging to retailer 1, and hydroelectric generator w and wind power generator z belonging to retailer 2.
[0034] The maximum allocation of each generator and the cost per kWh are as follows: Wind turbine x 200 kWh 12 yen, Hydroelectric generator y…210kWh / 16 yen, Wind turbine z…220kWh·8 yen, Hydroelectric generator: 230kWh / 10 yen.
[0035] Since the demand D1 of retail 1 is 250kWh and the demand D2 of retail 2 is 300kWh, the supply and demand matching constraint is x+y=250 for the demand D1 of retail 1 and z+w=300 for the demand D2 of retail 2, and the allocation calculation seeks the minimum cost of 12x+16y+8z+10w for the entire demand BG. Figure 6 shows the case where only normal constraints (for example, the objective function is cost minimization) are applied using conventional technology. As shown in Figure 6, 40kWh is allocated to wind power generator x, 210kWh to hydroelectric generator y, 220kWh to wind power generator z, and 80kWh to hydroelectric generator w. Therefore, 12x+16y+8z+10w=12·
[40] +16·
[0210] +8·
[0220] +10·
[80] =5720 yen, which is the cheapest in terms of cost.
[0036] Here, let us assume that retail priority is set from the generator's perspective. For example, from the wind turbine's perspective, retail 1 takes precedence over retail 2, that is, a priority order is added from retail 1 to retail 2, and wind turbine x belonging to retail 1 takes precedence over wind turbine z belonging to retail 2 (see Figure 7). In this case, wind turbine z will not be allocated power unless it reaches its maximum allocation of 200 kWh. Therefore, as shown in the formula in Figure 7, when wind turbine x's allocation upper limit x=200, Δx=1, and when Δx=1, Lz=1. In other words, when Lz=1, wind turbine x belonging to retail 1 reaches its upper limit, and allocation to wind turbine z belonging to lower retail 2 becomes possible.
[0037] As a result, in retail 1, 200 kWh is allocated to wind turbine x, and since x + y = 250, 50 kWh is allocated to hydroelectric generator y. In addition, in retail 2, as in the case shown in Figure 6 above, 220 kWh is allocated to wind turbine z, and 80 kWh is allocated to hydroelectric generator w. Therefore, 12x + 16y + 8z + 10w = 12 ·
[0200] + 16 ·
[50] + 8 ·
[0220] + 10 ·
[80] = 5,760 yen, which is a slight increase in costs compared to the case with only normal constraints.
[0038] Furthermore, while maintaining the priority order of Retail 1 → Retail 2, suppose that within Retail 1, hydroelectric power is given priority over wind power, i.e., a priority order of hydroelectric generator y → wind turbine x is added (see Figure 8). In this case, hydroelectric generator y will not be allocated to wind turbine x unless it reaches its maximum allocation of 210 kWh. Also, because the priority order of Retail 1 → Retail 2 exists, wind turbine z will not be allocated to wind turbine z unless it reaches its maximum allocation of 200 kWh. Here, since hydroelectric generator y has a maximum allocation of 210 kWh, wind turbine x is only allocated 40 kWh. In other words, wind turbine x will never reach its maximum allocation, and the allocation of wind turbine x will never be "full."
[0039] Therefore, as shown in FIG. 8, the wind power generator z belonging to retail 2 is not allocated any power at all and the result is 0 kWh. Therefore, even if 230 kWh is allocated to the hydroelectric power generator w, it cannot meet the demand D2 of retail 2, which is 300 kW, and the supply and demand balance of retail 2 will collapse. Therefore, even though retail 2's demand D2 has an allocation resource, the wind power generator z, the allocation calculation results in a "no solution" NG. In other words, as a result of the conflict between different retail priorities and supplier priorities in the demand BG, even though retail 2 has excess power, the allocation calculation results in a "no solution" error. In the allocation calculation, the cause of the "no solution" error is not clearly presented, and it takes time to identify the cause of the error. Moreover, if the supply and demand of the retailer can actually be matched, but the calculation shows that the supply and demand balance will collapse, it may be difficult to determine the cause of the "no solution" error.
[0040] Therefore, in the first embodiment, as shown in Fig. 9, the priority constraint for wind power generator x is relaxed (the "full" criterion is relaxed in Fig. 9), and if either the individual upper limit judgment constraint or the supply and demand matching judgment constraint is satisfied, the individual judgment constraint for the procurement source wind power generator x is satisfied. In other words, even if wind power generator x has not reached the maximum allocation of 200 kWh and wind power generator x is not "full", as long as the supply and demand matching judgment constraint x+y=250 is satisfied, there is no disruption to the supply and demand balance of retailer 2, and allocation to wind power generator z is possible.
[0041] That is, as shown in the additional constraints of the formula in Figure 9, when Δx=1 or Δ'=1, δ=1, and Lz=1, allocation to wind power generator z belonging to retail 2 is possible. This means that the criterion of "full" for wind power generator x is relaxed and 220 kWh is allocated to wind power generator z belonging to retail 2. Also, 80 kWh is allocated to hydroelectric generator w. As a result, 12x+16y+8z+10w=12·
[40] +16·
[0210] +8·
[0220] +10·
[80] =6400 yen. Although the cost is higher than the case shown in Figure 7, allocation to wind power generator z is possible, and a solution is found, thereby avoiding the "no solution" error.
[0042] [effect] The first embodiment is a method for allocating procurement sources when there are multiple retail businesses, and includes a priority allocation generation step for generating a priority allocation in which one or more procurement sources belong to the priority of each procurement source; an individual upper limit judgment constraint generation step for generating, as an individual upper limit judgment constraint, a formula for determining whether the allocation to each procurement source has reached a predefined upper limit; a supply and demand match judgment constraint generation step for generating, as a supply and demand match judgment constraint, a formula for determining whether the supply and demand of the retail business to which the procurement source belongs are matched; the individual satisfaction judgment constraint generating step of generating, as an individual satisfaction judgment constraint, a formula for determining whether an individual satisfaction condition is satisfied, that is, whether either the match judgment constraint or the match judgment constraint is satisfied; a hierarchical satisfaction judgment constraint generating step of generating, as a hierarchical satisfaction judgment constraint, a formula for determining whether a hierarchical satisfaction condition is satisfied, that is, whether all of the suppliers belonging to each priority hierarchy satisfy the individual satisfaction condition; and an allocation restriction constraint generating step of generating, as an allocation restriction constraint, a formula that enables allocation to a supplier belonging to a lower priority hierarchy only if the immediately higher priority hierarchy satisfies the hierarchical satisfaction condition.
[0043] In the first embodiment described above, an individual fulfillment judgment is introduced, which is the logical sum of the supply and demand match judgment of the retailer to which each supplier belongs and the individual upper limit judgment of each supplier.While maintaining the definition of the priority of suppliers as "a supplier's own electricity volume will not be allocated unless all of the suppliers belonging to the immediately higher priority hierarchy satisfy the individual fulfillment conditions," it is possible to relax the priorities set between retailers in accordance with the reality that the supply and demand of the retailers to which the suppliers belong match.
[0044] This makes it possible to avoid "no solution" errors that occur when the supply and demand balance of retailers is disrupted even when there are resources to allocate in the demand BG, etc. Therefore, it becomes unnecessary to carry out correction work such as resetting the priority of suppliers, and it becomes possible to execute normal allocation calculations. As a result, it is possible to reliably improve the operational efficiency of supply and demand operations even when the contract types are diversified.
[0045] In the first embodiment, the optimization problem supply and demand match judgment constraint DB 17 that stores the supply and demand match judgment constraints and the optimization problem individual satisfaction judgment constraint DB 18 that stores the individual satisfaction judgment constraints are provided independently. Therefore, the optimization execution unit 10 can efficiently use these judgment constraints to solve the optimization problem.
[0046] (Other embodiments) Although several embodiments of the present invention have been described, these embodiments are presented as examples and are not intended to limit the scope of the invention. These embodiments can be implemented in various other forms, and various omissions, substitutions, and modifications can be made without departing from the spirit of the invention. These embodiments and their modifications are included in the scope of the invention and its equivalents described in the claims, as well as in the scope and spirit of the invention.
[0047] For example, in the demand BG in the first embodiment, there are two retailers and each retailer has two suppliers, but the number of retailers may be three or more, and each retailer may have three or more suppliers. In addition, the same constraint condition may exist between suppliers belonging to retailers with different priorities, and a solution can be obtained by simultaneously considering the constraint condition and the priority in one mathematical program. According to such an embodiment, the allocation calculation creation work can be carried out more efficiently than an operation in which the priority is manually scheduled while considering the constraint.
[0048] Furthermore, the present invention can be applied not only to cost minimization problems but also to profit maximization problems, because the group of constraints that define the priorities are mathematically equivalent even when the objective function is maximization. [Explanation of symbols]
[0049] 1. Supplier DB 2 Priority DB 3. Priority Allocation Generation Unit 4 Priority allocation DB 5 Individual upper limit judgment constraint generator 6 Hierarchical sufficiency judgment constraint generator 7. Allocation constraint generation unit 8 Optimization problem priority constraint DB 9 Optimization problem objective function DB 10 Optimization execution unit 11 Optimization result DB 12 Optimization result display section 13 Optimization problem normal constraint DB 14. Supply and demand matching constraint generation section 15 Individual sufficiency judgment constraint generator 16 Retailer DB 17 Optimization problem supply and demand matching judgment constraint DB 18 Optimization problem individual sufficiency judgment constraint DB 100 Procurement allocation device
Claims
1. A method of allocating procurement sources when there are multiple retail businesses, comprising the steps of: A supplier storage step for storing supplier data, which is the basis of the allocation calculation; a priority storing step of storing the priority of suppliers having a variable-length hierarchical structure with the number of registered suppliers as a maximum value and retail priority set between retail businesses; a retailer storage step of storing data relating to the retailer; a priority assignment generation step of generating a priority assignment in which one or more suppliers are associated with each priority of each supplier; a priority assignment storage step for storing the priority assignment; an individual upper limit judgment constraint generating step of reading out the priority allocation and generating, as an individual upper limit judgment constraint, a formula for determining whether the allocation to each procurement source has reached a predefined upper limit value; a supply and demand match determination constraint generating step of generating a mathematical expression for determining whether the supply and demand of the retailer to which the supplier belongs are matched as a supply and demand match determination constraint; an individual satisfaction judgment constraint generating step of generating, as an individual satisfaction judgment constraint, a formula for determining whether an individual satisfaction condition is satisfied, that is, whether each procurement source satisfies either the individual upper limit judgment constraint or the supply and demand match judgment constraint; a hierarchical satisfaction judgment constraint generating step of reading the priority assignment and generating, as a hierarchical satisfaction judgment constraint, a formula for determining whether a hierarchical satisfaction condition is satisfied, that is, whether all of the suppliers belonging to each priority hierarchy satisfy the individual satisfaction condition; an allocation restriction constraint generating step of reading the priority allocation and generating, as an allocation restriction constraint, a formula that enables allocation to a supplier belonging to a lower priority hierarchy only when the hierarchy of the immediately higher priority hierarchy satisfies the hierarchy satisfaction condition; an optimization problem priority constraint storage step of storing the individual upper limit judgment constraint, the supply and demand matching judgment constraint, the individual fulfillment judgment constraint, the hierarchical fulfillment judgment constraint, and the allocation limit constraint as optimization problem priority constraints; an optimization problem objective function storing step of storing an optimization problem objective function; an optimization execution step of reading the optimization problem priority constraints and the optimization problem objective function and solving the corresponding optimization problem; an optimization result storage step of storing the optimization result; and an optimization result display step of displaying the optimization result, the method being performed by a computer.
2. A procurement source allocation device in a case where there are multiple retail businesses, a supplier storage unit for storing supplier data, which is the basis of the allocation calculation; a priority storage unit for storing supplier priorities having a variable-length hierarchical structure with the number of registered suppliers as a maximum value and retail priorities set between retail businesses; A retailer storage unit for storing data related to the retailer; a priority assignment generation unit that generates a priority assignment in which one or more suppliers are associated with each priority of the suppliers; an individual upper limit judgment constraint generating unit that reads the priority allocation and generates, as an individual upper limit judgment constraint, a formula for determining whether the allocation to each supplier has reached a predefined upper limit value; a supply and demand match determination constraint generating unit that generates a mathematical expression for determining whether the supply and demand of the retailer to which the supplier belongs are matched as a supply and demand match determination constraint; an individual satisfaction judgment constraint generating unit that generates, as an individual satisfaction judgment constraint, a formula for determining whether an individual satisfaction condition is satisfied, that is, whether either the individual upper limit judgment constraint or the supply and demand match judgment constraint is satisfied at each procurement source; a hierarchical satisfaction judgment constraint generating unit that reads the priority assignment and generates, as a hierarchical satisfaction judgment constraint, a formula that determines whether a hierarchical satisfaction condition is satisfied, that is, whether all of the suppliers belonging to each priority hierarchy satisfy the individual satisfaction condition; an allocation restriction constraint generating unit that reads the priority allocation and generates, as an allocation restriction constraint, a formula that enables allocation to a supplier belonging to a lower priority hierarchy only when the hierarchy of the immediately higher priority hierarchy satisfies the hierarchy satisfaction condition; an optimization problem objective function storage unit for storing an optimization problem objective function; an optimization execution unit that reads out the individual upper limit judgment constraint, the supply and demand matching judgment constraint, the individual fulfillment judgment constraint, the hierarchical fulfillment judgment constraint, and the allocation limit constraint as optimization problem priority constraints, and reads out the optimization problem objective function to solve a corresponding optimization problem; an optimization result storage unit for storing an optimization result; and an optimization result display unit that displays the optimization result.
3. 3. The procurement source allocation device according to claim 2, further comprising a priority allocation database for storing said priority allocation.
4. 4. The procurement source allocation device according to claim 2, further comprising an optimization problem priority constraint database for storing the optimization problem priority constraints.
5. 5. The procurement source allocation device according to claim 2, further comprising a supply and demand match determination constraint database for storing the supply and demand match determination constraint.
6. 6. The procurement source allocation device according to claim 2, further comprising an individual satisfaction judgment constraint database for storing the individual satisfaction judgment constraints.
Citation Information
Patent Citations
Material requirement planning system and method therefor and material requirement planning program
JP2003242207A
Scheduling device
JP2010257407A
Broadcast schedule generation method, broadcast schedule generation apparatus, and broadcast schedule generation program
JP2013062662A
Power plan assisting device, power plan assisting method, and power plan assisting program
JP2020190965A