A method for measuring the output admittance of subsystems in a three-phase power system.
A method for measuring output admittance in three-phase power systems using a simpler configuration with two transformers addresses the complexity and cost issues of conventional methods, achieving accurate results.
Patent Information
- Application Number
- JP2021004015
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2021-01-14
- Publication Date
- 2024-10-09
- Estimated Expiration
- 2041-01-14
AI Technical Summary
Conventional methods for measuring the output impedance of subsystems in three-phase power systems require complex and costly wiring with three transformers, complicating the configuration and increasing costs.
A method that measures the output admittance of a subsystem by generating a perturbation signal, converting voltage and current phases, and using a simpler configuration with only two transformers, allowing for accurate measurement through a series of conversion steps and frequency sweeps.
Enables accurate measurement of output admittance with a simpler configuration than conventional methods, reducing the complexity and cost associated with transformer wiring.
Smart Images

Figure 0007564526000036 
Figure 0007564526000037 
Figure 0007564526000038
Abstract
Description
[Technical field]
[0001] The present invention relates to a method for measuring the output admittance of one of a number of subsystems that make up a three-phase power system. [Background technology]
[0002] The impedance method is suitable for analyzing the stability of three-phase power systems such as grid-connected three-phase inverter systems. In the impedance method, the output impedance or output admittance (hereinafter referred to as "output impedance, etc.") of multiple subsystems that make up a three-phase power system are applied to the Nyquist stability condition, which is a stability criterion that takes into account the interactions between subsystems. Therefore, in order to analyze the stability of a system using the impedance method, the output impedance, etc. of the subsystems are required.
[0003] In stability analysis at the system design stage, analytically determined output impedance, etc. of the subsystem can be used, but in stability analysis at the actual equipment verification stage, measured output impedance, etc. of the subsystem must be used. For this reason, various methods for measuring the output impedance, etc. of the subsystem have been considered. For example, Non-Patent Document 1 describes a method in which a voltage is applied (injected) from outside to the power lines of each phase connecting the voltage source, which is a subsystem, and the load, and the voltage of each phase is measured (see Figure 3-12 on p. 57 in particular). [Prior art documents] [Non-patent literature]
[0004] [Non-Patent Document 1] Z. Shen, "Online Measurement of Three-phase AC Power System Impedance in Synchronous Coordinates," Ph. D. dissertation, Virginia Polytechnic Institute and State University, 2012 Summary of the Invention [Problem to be solved by the invention]
[0005] In the conventional method described in Non-Patent Document 1, three transformers are required to apply voltage to the power lines of each phase. Therefore, this method has the problem that the wiring between the three transformers and their drive circuits is complicated and expensive.
[0006] The present invention has been made in consideration of the above circumstances, and an object of the present invention is to provide a method that can measure the output admittance of a subsystem with the same accuracy as in the conventional method while having a simpler configuration than the conventional method. [Means for solving the problem]
[0007] In order to solve the above problems, the present invention provides a method for measuring an output admittance of a subsystem constituting a three-phase power system, comprising: (1) a first step of generating a perturbation signal that oscillates with a predetermined amplitude; and (2) a voltage v of a two-phase system that oscillates in accordance with the perturbation signal. a and the voltage v of the two-phase system that does not oscillate b and the three-phase voltage v u ,v v ,v w (3) converting the voltages v to v of the u-phase, v-phase, and w-phase of the subsystem. u -v w and voltage v v -v w While applying the current i u ,i v ,i w and voltage vu ,v v ,v w (4) The third step to obtain the current i u ,i v ,i w Converting the current i a ,i b (5) The fourth step to obtain the voltage v obtained in the third step u ,v v ,v w Converting this to the two-phase voltage v a ,v b (5) The current i obtained in the 4th step is a ,i b and the voltage v obtained in the fifth step a ,v b Based on the relationship, the output admittance matrix element Y aa ,Y ba The sixth step is to obtain the voltage v of the two-phase system that oscillates according to the perturbation signal. b and the voltage v of the two-phase system that does not oscillate a and the three-phase voltage v u ,v v ,v w (8) converting the voltages v to v of the u-phase and v-phase of the subsystem. u -v w and voltage v v -v w While applying the current i u ,i v ,i w and voltage v u ,v v ,v w (9) The eighth step to obtain the current i u ,i v ,i w Converting the current i a ,i b (10) The ninth step to obtain the voltage v obtained in the eighth step u ,v v ,v w Converting this to the two-phase voltage v a ,v b(11) The current i obtained in the 9th step a ,i b and the voltage v obtained in the 10th step a ,v b Based on the relationship, the output admittance matrix element Y ab ,Y bb and an eleventh step of determining
[0008] The above method may involve repeatedly executing steps 2 to 6 while changing the vibration frequency within a predetermined measurement frequency range, and then repeatedly executing steps 7 to 11 while changing the vibration frequency within the measurement frequency range.
[0009] In the above method, for example, the conversion in the second and seventh steps may be performed according to formula (3-1), the conversion in the fourth and ninth steps may be performed according to formula (3-2), and the conversion in the fifth and tenth steps may be performed according to formula (3-3).
number
number
number
[0010] In addition, in the above method, for example, the conversion in the second and seventh steps may be performed according to formula (4-1), the conversion in the fourth and ninth steps may be performed according to formula (4-2), and the conversion in the fifth and tenth steps may be performed according to formula (4-3).
number
number
number
[0011] According to the present invention, it is possible to provide a method capable of measuring the output admittance of a subsystem with the same accuracy as in the conventional method, while using a configuration that is simpler than in the conventional method. [Brief description of the drawings]
[0012] [Figure 1] 1 is a diagram showing a three-phase power system to which a measurement method according to a first embodiment of the present invention can be applied; [Diagram 2] 2 is a diagram showing an example of a specific configuration of a voltage application unit shown in FIG. 1. [Diagram 3] FIG. 11 is a diagram showing a three-phase power system to which a measurement method according to a second embodiment of the present invention can be applied. [Figure 4] 4 is a block diagram of a PLL included in the signal processing unit shown in FIG. 3. [Diagram 5] FIG. 2 is a flow diagram of a measurement method according to the present invention. [Figure 6] FIG. 1 is a circuit diagram of a three-phase power system that is the measurement target in the first and second measurement examples. [Figure 7] 13 is a graph showing the measurement results (Zdd, Zdq) of the first measurement example. [Figure 8] 13 is a graph showing the measurement results (Zqd, Zqq) of the first measurement example. [Figure 9] 13 is a graph showing the measurement results (Zαα, Zββ) of the second measurement example. [Figure 10] FIG. 11 is a circuit diagram of a three-phase power system that is the measurement target in a third measurement example. [Figure 11] 13 is a graph showing the measurement results (Ydd, Ydq) of the third measurement example. [Figure 12] 13 is a graph showing the measurement results (Yqd, Yqq) of the third measurement example. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0013] [Measurement principle] First, the measurement principle of the method (hereinafter simply referred to as the "measurement method") according to the present invention for measuring the output admittance of a subsystem that constitutes a three-phase power system will be described.
[0014] The instantaneous voltage vector applied to the u, v, and w phase power lines connecting the two subsystems that make up the three-phase power system is expressed as [v~ u v~ v v~ w ] T (where T is the transposition symbol), the instantaneous value vector of the current resulting from this application is [i~ u i~ v i~ w ] T With these phasors expressed in capital letters, the impedance matrix and admittance matrix of the three-phase system can be defined by equations (1) and (2).
number
number
[0015] In addition, the conversion of instantaneous voltage from a three-phase (u,v,w) system to a two-phase (a,b) system and the inverse conversion can be performed using equations (3) and (4), and the conversion of instantaneous current from a three-phase system to a two-phase system and the inverse conversion can be performed using equations (5) and (6).
number
number
number
number
number
[0016] In addition, when converting to a two-phase system by αβ transformation, and when converting to a three-phase system by inverse αβ transformation, the transformation matrix C ab As the following formula, C αβ can be used.
number
number
[0017] The impedance matrix and admittance matrix of the two-phase system can be defined by equations (10) and (11).
number
number
[0018] Symbol indicating that it is a matrix m and the symbol indicating that it is a vector vUsing this, equation (10) can be rewritten as equation (12), and equation (11) can be rewritten as equation (13).
number
number
number
[0019] To find the elements of the admittance matrix shown in equation (11), V~ a and V~ b One of the two can be vibrated at a predetermined amplitude while the other can be made zero. For example, V a ≠0 and V~ b =0 while I~ a ,I~ b If the measurement is performed, as can be understood from the following formula, the formula "I a / V~ a " and matrix element Y aa The formula "I~ b / V~ a " and matrix element Y ba Conversely, V~ a =0 and V~ b ≠0 while I~ a ,I~ b If you measure it, the formula "I~ a / V~ b " and matrix element Y ab The formula "I~ b / V~ b " and matrix element Y bb can be sought.
number
[0020] As mentioned above, the impedance matrix Z mab and the admittance matrix Y m ab Since the relationship between these is given by equation (14), the admittance matrix Y m ab Each element of Y aa ,Y ab ,Y ba ,Y bb ) is obtained, the impedance matrix Z m ab Each element of (Z aa ,Z ab ,Z ba ,Z bb ) can also be easily calculated.
[0021] [First Example] Next, a first embodiment of the present invention will be described with reference to the accompanying drawings.
[0022] Fig. 1 shows a system to which the measurement method according to the first embodiment can be applied. As shown in the figure, this system includes a first subsystem 10, a second subsystem 11, u-, v-, and w-phase power lines that enable the exchange of three-phase power between these, a frequency characteristic analysis unit 12, a signal processing unit 13, and a voltage application unit 14 installed on the power lines. It can be said that this system is a three-phase power system consisting of the two subsystems 10 and 11 and the power lines to which the frequency characteristic analysis unit 12, the signal processing unit 13, and the voltage application unit 14 have been added. The frequency characteristic analysis unit 12 finally calculates the measured output admittance Y of the second subsystem 11. m αβ (or output impedance Z m αβ ) to output.
[0023] The frequency characteristic analysis unit 12 is composed of a commercially available frequency characteristic analyzer (FRA, Frequency Response Analyzer). The signal processing unit 13 is composed of a commercially available digital signal processor (DSP, Digital Signal Processor). The sampling frequency of the signal processing unit 13 is 100 kHz. As shown in FIG. 2, the voltage application unit 14 is composed of a first transformer T u and the second transformer T v Based on the signal output from the signal processing unit 13, the transformer T u ,T v and drive circuits 15 and 16 that drive the inverters 15 and 16. No transformer is provided in the w-phase power line.
[0024] The frequency characteristic analysis unit 12, the signal processing unit 13, and the voltage application unit 14 calculate the output admittance Y m αβ (Z m αβ ) is measured and output.
[0025] First, in step S1, the frequency characteristic analysis unit 12 generates a perturbation signal that oscillates with a predetermined amplitude. The initial value of the oscillation frequency f is f 1 (For example, 10Hz).
[0026] In step S2, the signal processing unit 13 calculates the two-phase voltage v a (In this embodiment, the voltage v α ) and the non-oscillating two-phase voltage v b (In this embodiment, the voltage v β ) and the three-phase voltage v u ,v v ,v w (In this embodiment, inverse αβ transformation is performed.) The transformation formulas are formula (4) and formula (8).
[0027] In step S3, the voltage application unit 14 applies the voltage v output from the signal processing unit 13 to the u ,vv ,v w Based on the signal, the voltage v is applied to the u and v phase power lines. u -v w , voltage v v -v w More specifically, a voltage v is applied to the u-phase power line. u -v w The drive circuit 15 controls the first transformer T u and applies voltage v to the v-phase power line. v -v w The drive circuit 16 is connected to the second transformer T v Drives.
[0028] In step S3, the instantaneous value i of the current flowing through the power line of each phase is further calculated. u ,i v ,i w is measured. Here, the instantaneous value of the current i u ,i v ,i w "Measurement" is done by i u ,i v ,i w Not only can we measure each of the i u ,i v ,i w This also includes measuring two of the i and calculating the remaining one by the signal processing unit 13. u ,i w From i v Request.
[0029] In step S3, the instantaneous value v of the voltage of the power line of each phase between the voltage application unit 14 and the second subsystem 11 is further u ,v v ,v w is measured. Here, the instantaneous value of the voltage v u ,v v ,v w "Measurement" requires v u ,v v ,v w In addition to measuring each of the phase-to-phase voltages v uv(=v u -v v ),v vw (=v v -v w ),v uw (=v u -v w ) and the signal processor 13 calculates v u ,v v ,v w As shown in FIG. 1, in this embodiment, the measured v uv ,v vw By calculation, v u ,v v ,v w Request.
[0030] In step S4, the signal processing unit 13 calculates the instantaneous value i u ,i v ,i w The current i of the two-phase system a ,i b (In this embodiment, the current i α ,i β ) (in this embodiment, αβ transformation). The transformation formulas are formula (5) and formula (8).
[0031] In step S5, the signal processing unit 13 calculates the instantaneous value v of the voltage obtained in step S3. u ,v v ,v w The voltage v of the two-phase system a ,v b (In this embodiment, the voltage v α ,v β ) (in this embodiment, αβ conversion). The conversion formulas are formulas (3) and (8). Note that in step S2, the voltage v α Since only the voltage v β will be zero.
[0032] In step S6, the frequency characteristic analysis unit 12 calculates the current i a ,i b (In this embodiment, the current i α ,i β) and the voltage v calculated in step S5 a ,v b (In this embodiment, the voltage v α ,v β ) (see equation (15)), the output admittance Y m ab (In this embodiment, Y m αβ ) matrix element Y aa ,Y ba (In this embodiment, Y αα ,Y βα ) is required.
[0033] In step S7, the current vibration frequency f is set to the upper limit of the measurement frequency f 2 (For example, 10 kHz) is judged. 2 If the vibration frequency f does not reach f, a predetermined Δf is added to f (step S8). Then, steps S1 to S7 are executed for the vibration frequency f after the addition. 2 In other words, steps S1 to S8 are repeated until the measurement frequency range (f 1 ~f 2 ) in Y aa ,Y ba This is repeated until the above is obtained. Note that Δf may be a constant value or may be a variable value. The same applies to Δf in step S15 described later.
[0034] In step S9, similarly to step S1, the frequency characteristic analysis unit 12 generates a perturbation signal that oscillates with a predetermined amplitude. The initial value of the oscillation frequency f is f 1 It is.
[0035] In step S10, unlike step S2, the signal processing unit 13 calculates the two-phase voltage v b (In this embodiment, the voltage v β ) and the non-oscillating two-phase voltage v a (In this embodiment, the voltage v α ) and the three-phase voltage v u,v v ,v w (In this embodiment, inverse αβ transformation is performed.) The transformation formulas are formula (4) and formula (8).
[0036] Steps S11 to S13 are equivalent to steps S3 to S5.
[0037] In step S14, the frequency characteristic analysis unit 12 calculates the current i a ,i b (In this embodiment, the current i α ,i β ) and the voltage v calculated in step S13 a ,v b (In this embodiment, the voltage v α ,v β ) (see equation (15)), the output admittance Y m ab (In this embodiment, Y m αβ ) matrix element Y ab ,Y bb (In this embodiment, Y αβ ,Y ββ ) is required.
[0038] In step S15, the current vibration frequency f is f 2 Determine whether the vibration frequency f reaches f 2 If the vibration frequency f does not reach f, Δf is added to f (step S16). Then, steps S9 to S15 are executed for the vibration frequency f after the addition. Steps S9 to S16 are executed until the vibration frequency f reaches f 2 In other words, steps S9 to S16 are repeated until the measurement frequency range (f 1 ~f 2 ) in Y ab ,Y bb This is repeated until
[0039] In this manner, the frequency characteristic analysis unit 12, the signal processing unit 13, and the voltage application unit 14 are 1 ~f 2) the output admittance Y of the second subsystem 11 m αβ (Y αα ,Y αβ ,Y βα ,Y ββ The frequency characteristic analysis unit 12 measures the measured output admittance Y m αβ You can output it as it is, or you can set the output impedance Z m αβ The conversion formula is given by formula (14).
[0040] In the measurement method according to the first embodiment of the present invention, the number of transformers required for applying a voltage is only two. Therefore, according to the measurement method according to this embodiment, it is possible to measure the output admittance of a subsystem with a configuration that is simpler than that of the conventional method.
[0041] In addition, the measurement frequency range is specified by f 1 ,f 2 can be changed arbitrarily. For example, f 1 ,f 2 may be set to 100 kHz and 100 Hz, and the vibration frequency f may be decreased by a predetermined amount each time steps S8 and S16 are executed.
[0042] The voltage application unit 14 may be configured to apply a voltage to the u- and w-phase power lines, or may be configured to apply a voltage to the v- and w-phase power lines. u -v w ,v v -v w Applying voltage v to the u and w phases u -v v ,v w -v v and a voltage v is applied to the v and w phases. v -v u ,v w -v u is equivalent to applying
[0043] [Second Example] Next, a second embodiment of the present invention will be described with reference to the accompanying drawings.
[0044] 3 shows a system that can apply the measurement method according to the second embodiment. As shown in the figure, this system includes a signal processor 13 that measures the inter-phase voltage v^ between the first subsystem 10 and the voltage application unit 14. uv ,v^ vw The signal processing unit 13 performs a dq transform (inverse dq transform) instead of an αβ transform (inverse αβ transform), and the frequency characteristic analysis unit 12 uses the output admittance Y m dq (or output impedance Z m dq ) in that the second embodiment outputs the first signal, but in other respects the two are the same.
[0045] The signal processing unit 13 includes, for example, a known phase locked loop (PLL) shown in FIG. 4 in order to obtain the phase angle θ (see equation (9)) at each time required for the dq transformation and the inverse dq transformation. The voltage v^ input to this loop u ,v^ v ,v^ w is the phase-to-phase voltage v^ uv ,v^ vw Also, ω 0 is the fundamental angular frequency to be measured, and T is the sampling time of the signal processing unit 13. As described above, the sampling frequency of the signal processing unit 13 is 100 kHz, so the sampling time T is 10 μs.
[0046] The signal processing unit 13 uses equation (9) instead of equation (8) when converting the two-phase voltage to a three-phase voltage (inverse dq transformation in this embodiment) in steps S2 and S10. The signal processing unit 13 also uses equation (9) instead of equation (8) when converting the three-phase voltage / current to a two-phase voltage / current (dq transformation in this embodiment) in steps S4, S5, S12, and S13.
[0047] The measurement method according to the second embodiment of the present invention also provides the same effects as the measurement method according to the first embodiment.
[0048] In addition, when the signal processing unit 13 is also responsible for controlling the object to be measured, the phase angle θ in equation (9) is known in the signal processing unit 13. Therefore, in this case, the phase-to-phase voltage v^ uv ,v^ vw Measurement of the frequency and synchronous control using a phase-locked loop can be omitted.
[0049] [Measurement example] Next, a measurement example using the measurement methods according to the first and second embodiments of the present invention will be described.
[0050] (First measurement example) In the first measurement example, the output admittance Y of the second subsystem 11 constituting the three-phase power system shown in FIG. 6 is measured using the measurement method according to the second embodiment of the present invention. m dq (Y dd ,Y dq ,Y qd ,Y qq ) and compare it with the output impedance Z m dq (Z dd ,Z dq ,Z qd ,Z qq As shown in the figure, the second subsystem 11 is a three-phase RL load, with R = 30 Ω, L = 5 mH, and ω 0 =2π×60.
[0051] Figures 7 and 8 show the analysis results (solid line), simulation results (◇ marks), and measurement results (dashed line). dd ,Z dq ,Z qd and Z qq In both cases, the analytical results and the simulation results were in good agreement. dd and Z qq The analysis results, simulation results, and measurement results were generally in agreement.
[0052] In addition, Z dd ,Z dq ,Z qd and Z qq The analytical value of is as shown in equation (16).
number
[0053] (Second measurement example) In the second measurement example, the output admittance Y of the second subsystem 11 constituting the three-phase power system shown in FIG. 6 is measured using the measurement method according to the first embodiment of the present invention. m αβ (Y αα ,Y αβ ,Y βα ,Y ββ ) and compare it with the output impedance Z m αβ (Z αα ,Z αβ ,Z βα ,Z ββ ) was converted. As in the first measurement example, the second subsystem 11 is a three-phase RL load, with R = 30 Ω, L = 5 mH, and ω 0 =2π×60.
[0054] Figure 9 shows the analysis results (solid line), the simulation results (◇ mark), and the measurement results (dashed line). αα and Z ββ In all cases, the analysis results, simulation results, and measurement results were generally in agreement.
[0055] In addition, Z αα and Z ββ The analytical value of is as shown in equation (17).
number
[0056] (Third measurement example) In the third measurement example, the output admittance Y of the second subsystem 11 constituting the three-phase power system shown in FIG. 10 is measured using the measurement method according to the second embodiment of the present invention.m dq (Y dd ,Y dq ,Y qd ,Y qq ) was measured. As shown in the figure, the second subsystem 11 is a three-phase inverter with a filter, and its circuit parameters are as shown in the table below. This three-phase inverter is controlled by a state feedback control system including a sine wave compensator. [Table 1]
[0057] Figures 11 and 12 show the analysis results (solid line), the simulation results (◇ mark), and the measurement results (dashed line). dd For both amplitude and phase, the analysis results, simulation results, and measurement results were generally consistent. dd Although the accuracy is slightly lower than that of the results of Y qq For both amplitude and phase, the analysis results, simulation results, and measurement results were generally consistent. dq ,Y qd is Y dd ,Y qq The amplitude is 30 dB smaller than that of the measured value, so the difference between the analysis result and the measured result seems large. However, Y dq ,Y qd The amplitude measurements showed a similar trend to the analytical results.
[0058] Although detailed explanation is omitted, the state equation of the two-phase (α, β) system at time t is expressed as equation (18), and the state variable vector x αβ When equation (19) is used, the output admittance Y m αβ The analytical value of can be obtained by equations (20) and (21).
number
number
number
number
[0059] where the continuous system coefficient matrix A c , continuous system input coefficient vector b c , continuous disturbance coefficient vector h c and the continuous system output coefficient vector c c is as shown in equation (22).
number
[0060] 10. First Subsystem 11 Second Subsystem 12 Frequency response analysis section 13 Signal Processing Section 14 Voltage application section 15 Drive circuit 16 Drive circuit T u Transformer No. 1 T v 2nd transformer
Claims
1. 1. A method for measuring output admittance of a subsystem in a three-phase power system, comprising: A first step of generating a perturbation signal oscillating with a predetermined amplitude; The voltage v of the two-phase system oscillates according to the perturbation signal. a The voltage v of the two-phase system does not oscillate. b and the voltage v of the three-phase system u , v v , v w and a second step of converting Of the u-phase, v-phase and w-phase of the subsystem, the u-phase and the v-phase are each supplied with a voltage v u -v w and voltage v v -v w While applying the current i u , i v , i w and voltage v u , v v , v w and a third step to obtain The current i obtained in the third step u , i v , i w Converting the current i of the two-phase system a , i b and a fourth step to obtain The voltage obtained in the third step, v u , v v , v w Converting this to the two-phase voltage v a , v b and a fifth step to obtain The current i obtained in the fourth step a , i b and the voltage v obtained in the fifth step a , v b Based on the relationship, the matrix element of the output admittance, Y aa , Y ba A sixth step of calculating The voltage v of the two-phase system oscillates according to the perturbation signal. b The voltage v of the two-phase system does not oscillate. a and the voltage v of the three-phase system u , v v , v w and a seventh step of converting Of the u-phase, v-phase and w-phase of the subsystem, the u-phase and the v-phase are each supplied with a voltage v u -v w and voltage v v -v w While applying the current i u , i v , i w and voltage v u , v v , v w and an eighth step to obtain The current i obtained in the eighth step u , i v , i w Converting the current i of the two-phase system a , i b A ninth step to obtain The voltage obtained in the eighth step, v u , v v , v w Converting this to the two-phase voltage v a , v b A tenth step of obtaining The current i obtained in the 9th step a , i b and the voltage v obtained in the 10th step a , v b Based on the relationship, the matrix element of the output admittance, Y ab , Y bb The 11th step is to find A method comprising:
2. Repeatedly executing the second to sixth steps while changing the frequency of the vibration within a predetermined measurement frequency range, and then repeatedly executing the seventh to eleventh steps while changing the frequency of the vibration within the measurement frequency range.
2. The method of claim 1 .
3. The conversion in the second and seventh steps is performed according to formula (3-1), the conversion in the fourth and ninth steps is performed according to formula (3-2), and the conversion in the fifth and tenth steps is performed according to formula (3-3).
3. The method according to claim 1 or 2. [0010] [0025] [0030]
4. The conversion in the second and seventh steps is performed according to formula (4-1), the conversion in the fourth and ninth steps is performed according to formula (4-2), and the conversion in the fifth and tenth steps is performed according to formula (4-3).
3. The method according to claim 1 or 2. [0045] [0050] [006]
Citation Information
Patent Citations
Verification method and experimental setup for power grid impedance identification
CN106771786B
Insulation measuring method and apparatus therefor
JP2007071774A
Short circuit fault diagnosis method for stator winding in ac motor
JP2012186973A
Power measuring device, control circuit, interconnection inverter system, and power measuring method
JP2013108846A
Measurement device and measurement method
JP2018081019A