Leveling control method in hot rolling, leveling control device, hot rolling equipment, and method for manufacturing hot rolled steel strip
The leveling control method and device address the issue of insufficient meandering control in hot finish rolling by adjusting control timing and amounts across multiple rolling mills, stabilizing meandering and enhancing productivity.
Patent Information
- Application Number
- JP2022054826
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2022-03-30
- Publication Date
- 2024-10-16
- Estimated Expiration
- 2042-03-30
AI Technical Summary
Conventional methods for controlling meandering in hot finish rolling start meandering control after the tail end of the rolled material has passed through the rolling mill, leading to insufficient control amounts and potential damage to the rolling mill due to significant meandering.
A leveling control method and device that adjust the control start timing and amount by using multiple meandering amount detection devices and correction amounts across multiple rolling mills, calculating and applying first and second leveling correction amounts to stabilize meandering control.
Stably controls meandering, reducing the risk of rolling mill damage and improving productivity by ensuring the rolled material passes through the center of the rolling mill effectively.
Smart Images

Figure 0007567847000002 
Figure 0007567847000003 
Figure 0007567847000004
Abstract
Description
[Technical field]
[0001] The present invention relates to a leveling control method in hot rolling, a leveling control device, hot rolling equipment, and a method for producing a hot rolled steel strip. [Background technology]
[0002] Generally, in a hot rolling facility, a slab (rolled material) is heated to a predetermined temperature in a heating furnace, the heated slab (rolled material) is roughly rolled to a predetermined thickness in a roughing mill to form a sheet bar (rolled material), and then the sheet bar (rolled material) is finish-rolled to the predetermined thickness in a finishing rolling facility equipped with multiple rolling mills. The finish-rolled sheet bar (rolled material) becomes a hot-rolled steel strip of a predetermined thickness, and is cooled in a run-out table (cooling facility) installed downstream of the finishing rolling facility. The hot-rolled steel strip is then wound into a coil by a winder to be manufactured.
[0003] Here, when a rolled material is rolled in a finishing rolling facility equipped with a plurality of rolling mills, a phenomenon may occur in which the position of the rolled material in the width direction meanders toward the working side or the driving side with respect to the center of the rolling mill. The driving side is the side where the driving motor for the rolling rolls is attached, and the working side is the side opposite to the driving side. When meandering of the rolled material occurs, the width end of the rolled material comes into contact with the side guide, and the rolled material is rolled in a buckling state, resulting in a squeezing phenomenon. When the squeezing phenomenon occurs, scratches are caused on the rolling rolls, and maintenance work or replacement work for the rolling rolls is required, resulting in a decrease in productivity. Therefore, a technology for controlling the meandering of the rolled material during continuous rolling and passing the sheet through the mill center (the center of the rolling mill) as much as possible is essential in order to prevent the above-mentioned troubles, and is important from the viewpoints of improving productivity and suppressing production costs.
[0004] As methods for controlling such meandering of a rolled material, there have been known a method for controlling the meandering of the tail end of a steel sheet in hot finish rolling, as disclosed in Patent Document 1, and a method for controlling the meandering of a rolled steel sheet, as disclosed in Patent Document 2. The method for controlling meandering at the tail end of a steel sheet in hot finishing rolling shown in Patent Document 1 involves installing a meandering detection device that detects the amount of meandering of a steel sheet at approximately the center between the stands, and controlling the meandering using the detected amount of meandering.
[0005] Moreover, in the method for controlling the meandering of a rolled steel sheet shown in Patent Document 2, the amount of meandering is detected by a meandering meter provided on the entry side of the rolling mill, and the leveling amount is changed to an amount obtained by multiplying the amount of meandering by a control gain, in which the control gain is determined according to the rolling load. Leveling refers to the difference in the opening between the roll gap on the working side and the roll gap on the driving side of a rolling mill. [Prior art documents] [Patent documents]
[0006] [Patent Document 1] Japanese Patent Application Publication No. 7-144211 [Patent Document 2] JP 2004-306125 A Summary of the Invention [Problem to be solved by the invention]
[0007] However, the conventional method for controlling the meandering of the tail end of a steel plate in hot finish rolling disclosed in Patent Document 1 and the method for controlling the meandering of a rolled steel plate disclosed in Patent Document 2 have the following problems. That is, in the case of the method for controlling the meandering of the tail end of a steel plate in hot finishing rolling shown in Patent Document 1 and the method for controlling the meandering of a rolled steel plate shown in Patent Document 2, the meandering control starts after the tail end of the rolled material has passed the rolling mill preceding the rolling mill to be controlled. That is, in the case of the method for controlling meandering of the tail end of a steel plate in hot finishing rolling shown in Patent Document 1, a meandering detection device is installed between the stand to be controlled and the previous stand, and after the tail end of the rolled material passes the previous stand, an optimal control amount for meandering control is calculated based on the amount of meandering detected by the meandering detection device, and the meandering is controlled by adjusting the reduction amount of the left and right chocks of the rolling rolls using a leveling device.
[0008] Furthermore, in the case of the method for controlling the meandering of a rolled steel plate shown in Patent Document 2, a meandering meter is installed on the entry side of the rolling mill to be controlled, and after the tail end of the rolled material passes through the rolling mill preceding the rolling mill to be controlled, the leveling amount is changed to an amount obtained by multiplying the meandering amount detected by the meandering meter by a control gain. In this way, when the timing for starting the meandering control is after the tail end of the rolled material has passed through the rolling mill preceding the rolling mill to be controlled, the following problem occurs.
[0009] The maximum control amount in the leveling control is determined by the residence time of the tail end of the rolled material between the rolling mill to be controlled and the preceding rolling mill, the command value of the control amount, and the operation speed of the actuator. Generally, from the viewpoint of protecting the rolling mill, the control amount and the operation speed of the actuator are set to have upper limits. If the timing of starting the meandering control is after the tail end of the rolled material has left the rolling mill preceding the rolling mill to be controlled, the maximum control amount in the leveling control is small. For this reason, for example, if the rolled material has already meandered significantly when the tail end of the rolled material has left the rolling mill preceding the rolling mill to be controlled, the control amount may be insufficient even if the maximum control is performed, and a squeezing trouble may occur.
[0010] Therefore, in order to stably control the meandering of the rolled material and pass the rolled material through the center of the rolling mill as much as possible, it is necessary to appropriately set the control start timing and the control amount for the rolling mill to be controlled. Therefore, the present invention has been made to solve the conventional problems, and its object is to provide a leveling control method for hot rolling, a leveling control device, hot rolling equipment, and a method for manufacturing hot rolled steel strip, which, when controlling the meandering of a rolled material being rolled in a finishing rolling facility equipped with N rolling mills (N is a natural number of 4 or more), can stably control the meandering of the rolled material and pass the rolled material through the center of the rolling mills as much as possible by appropriately setting the control start timing and the control amount for the rolling mills to be controlled. [Means for solving the problem]
[0011] In order to solve the above-mentioned problems, a leveling control method in hot rolling according to one aspect of the present invention is a leveling control method in hot rolling for controlling meandering of a rolled material rolled in a finishing rolling facility equipped with N rolling mills (N is a natural number of 4 or more), the method including the steps of: calculating a first leveling correction amount for a rolling mill that is to be controlled after the nth rolling mill and the n+1th rolling mill based on a meandering amount detected by a first meandering amount detection device installed between the nth rolling mill and the n+1th rolling mill after the tail end of the rolled material has passed the nth (any of 1 to N-3) rolling mill from the head; and calculating a first leveling correction amount for a rolling mill that is to be controlled after the nth rolling mill and the n+2th rolling mill based on a meandering amount detected by a second meandering amount detection device installed between the n+2th rolling mill and the n+3th rolling mill after the tail end of the rolled material has passed the nth (any of 1 to N-3) rolling mill from the head. The method includes a second leveling correction amount calculation step of calculating a second leveling correction amount for the rolling mill that is the +3rd or later to be controlled, and a leveling control step of controlling the leveling of the rolling mills to be controlled so that a leveling correction of the first leveling correction amount calculated in the first leveling correction amount calculation step is performed in a first control section from when the tail end of the rolled material has passed the first meandering amount detection device to when it reaches the (n+2)th rolling mill, and a leveling correction of a leveling correction amount obtained by adding the second leveling correction amount calculated in the second leveling correction amount calculation step to the first leveling correction amount is performed in a second control section from when the tail end of the rolled material has passed the (n+2)th rolling mill to when it reaches the (n+3)th or later rolling mill to be controlled.
[0012] A leveling control device in hot rolling according to another aspect of the present invention is a leveling control device in hot rolling that controls the meandering of a rolled material rolled in a finishing rolling facility equipped with N rolling mills (N is a natural number of 4 or more), and includes a first leveling correction amount calculation unit that calculates a first leveling correction amount at rolling mills that are to be controlled after the tail end of the rolled material has passed through the nth (any of 1 to N-3) rolling mill from the head, based on a meandering amount detected by a first meandering amount detection device installed between the nth rolling mill and the n+1th rolling mill, and a second leveling correction amount calculation unit that calculates a first leveling correction amount at rolling mills that are to be controlled after the tail end of the rolled material has passed through the nth (any of 1 to N-3) rolling mill from the head, based on a meandering amount detected by a second meandering amount detection device installed between the n+2th rolling mill and the n+3th rolling mill. The present invention relates to a rolling mill that is a third or subsequent controlled mill, and a leveling control unit that controls leveling of the rolling mills to be controlled so that a leveling correction of the first leveling correction amount calculated by the first leveling correction amount calculation unit is performed in a first control section from when the tail end of the rolled material passes through the first meandering amount detection device to when it reaches the (n+2)th rolling mill, and a leveling correction of a leveling correction amount obtained by adding the second leveling correction amount calculated by the second leveling correction amount calculation unit to the first leveling correction amount is performed in a second control section from when the tail end of the rolled material passes through the (n+2)th rolling mill to when it reaches the (n+3)th or subsequent controlled mill.
[0013] A hot rolling facility according to another aspect of the present invention includes the above-mentioned leveling control device. Furthermore, a method for producing a hot rolled steel strip according to another aspect of the present invention is characterized in that it includes a finish rolling step in which the meandering of the rolled material is controlled using the above-mentioned leveling control method and the rolled material is finish rolled. Effect of the Invention
[0014] According to the leveling control method in hot rolling, leveling control device, hot rolling equipment, and method for manufacturing hot rolled steel strip of the present invention, when controlling the meandering of a rolled material rolled in a finishing rolling facility equipped with N rolling mills (N is a natural number of 4 or more), it is possible to provide a leveling control method in hot rolling, a leveling control device, hot rolling equipment, and a method for manufacturing hot rolled steel strip, which can stably control the meandering of the rolled material and pass the rolled material through the center of the rolling mills as much as possible by appropriately setting the control start timing and the control amount for the rolling mills to be controlled. [Brief description of the drawings]
[0015] [Figure 1] 1 is a schematic configuration diagram of a hot rolling facility equipped with a leveling control device according to an embodiment of the present invention. [Diagram 2] 2 is a flowchart for explaining a process flow of the leveling control device shown in FIG. 1. [Diagram 3] 2 is a diagram showing how a meandering amount prediction model is generated by a meandering amount prediction model generating unit of the leveling control device shown in FIG. 1. FIG. [Figure 4] FIG. 13 is a diagram showing a processing flow of a meandering amount prediction model which is a neural network model. [Diagram 5] FIG. 2 is a diagram for explaining leveling control in a rolling mill that is a controlled object and that performs leveling correction by the leveling control device shown in FIG. 1. [Figure 6] FIG. 1 is a schematic configuration diagram of a finishing rolling facility equipped with a leveling control device according to a reference example. [Figure 7] 7 is a graph showing the relationship between the amount of meandering between the fourth rolling mill F4 and the fifth rolling mill F5 from the top and the amount of meandering between the fifth rolling mill F5 and the sixth rolling mill F6 from the top in the finishing rolling facility shown in FIG. [Figure 8] 7 is a graph showing the relationship between the amount of meandering between the fifth rolling mill F5 and the sixth rolling mill F6 from the top and the amount of meandering between the sixth rolling mill F6 and the seventh rolling mill F7 from the top in the finishing rolling facility shown in FIG. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0016] Hereinafter, embodiments of the present invention will be described with reference to the drawings. The embodiments shown below are merely examples of devices and methods for embodying the technical concept of the present invention, and the technical concept of the present invention is not limited to the following embodiments in terms of the materials, shapes, structures, arrangements, etc. of the components. In addition, the drawings are schematic, and therefore, it should be noted that the relationship between thickness and planar dimensions, ratios, etc. may differ from the actual relationship between thickness and planar dimensions, and the drawings may include parts in which the relationship between dimensions and ratios differ from one another.
[0017] FIG. 1 shows a schematic configuration of a hot rolling facility equipped with a leveling control device according to one embodiment of the present invention. 1 includes a heating furnace 2 for heating a slab (rolled material) S to a predetermined temperature, a roughing mill 3 for rough rolling the slab (rolled material) S heated in the heating furnace 2 to a predetermined plate thickness to produce a sheet bar (rolled material) S, and a finish rolling facility 4 for finish rolling the sheet bar (rolled material) S to a predetermined plate thickness. The roughing mill 3 includes M rough rolling stands R1 to RM (M is a natural number of 2 or more).
[0018] The hot rolling equipment 1 also includes a runout table 5 for cooling the finish-rolled hot-rolled steel strip (rolled material) S, and a winder 6 for winding the cooled hot-rolled steel strip (rolled material) S into a coil. Here, the finishing rolling facility 4 is equipped with N rolling mills F1 to FN (N is a natural number of 4 or more), which finish roll the sheet bar (rolled material) S to a specified thickness by tandem rolling. Each of the rolling mills F1 to FN is equipped with a leveling device 7 (only the leveling device 7 installed in the rolling mill FN is shown) that adjusts the reduction amount on the operation side and the drive side. The rolled material S runs (is transported) in the direction shown by the arrow in FIG. 1. Note that the drive side of each of the rolling mills F1 to FN is the side where the drive motor for the rolling rolls is attached, and the working side is the opposite side to the drive side.
[0019] The finishing rolling facility 4 is also provided with a leveling control device 10 that controls the meandering of the rolled material S. The leveling control device 10 controls the meandering of the rolled material S by "means control using a meandering meter" at the rolling mill Fn+3 to be controlled in a first control section A from when the tail end of the traveling rolled material S passes through a first meandering amount detection device 13, which will be described later, installed between the nth rolling mill Fn and the n+1th rolling mill Fn+1 from the front and passes through the n+2th rolling mill Fn+2 from the front, and in a second control section B from when the tail end of the rolled material S passes through the n+2th rolling mill Fn+2 from the front and passes through the n+3th rolling mill Fn+3 to be controlled.
[0020] In the present embodiment, the "wandering control using the wandering meter method" is a method of calculating the leveling amount (roll gap difference, which is the difference in the roll gap gap between the operating side and the driving side in the rolling mill Fn+3) Lv of the rolling mill Fn+3 to be controlled, which is located immediately downstream of the position where the second wandering amount detection device 16 is installed, by comparing the leveling amount Lv detected by the first wandering amount detection device 13 with a preset leveling amount LvL in the first control section A from when the tail end of the rolled material S passes through the first wandering amount detection device 13 installed between the nth rolling mill Fn and the n+1th rolling mill Fn+1 from the front to when it passes through the n+2th rolling mill Fn+2 from the front, as shown in FIG. In the second control section B from when the tail end of the rolled material S passes through the (n+2)th rolling mill Fn+2 from the front to when it passes through the (n+3)th rolling mill Fn+3 to be controlled, the leveling correction amount LvL set in advance is corrected by adding the second leveling correction amount ΔLv2 or the second leveling correction correction amount ΔLv2' proportional to the meandering amount δ2 detected by the second meandering amount detection device 16 to the first leveling correction amount ΔLv1 or the first leveling correction correction amount ΔLv1'.
[0021] If meandering of the rolled material S occurs on the operation side, the leveling amount Lv is corrected (to the "-" side) so that the operation side is closed, and if meandering of the rolled material S occurs on the drive side, the leveling amount Lv is corrected (to the "+" side) so that the drive side is closed. During the period from when the tail end of the rolled material S passes through the first rolling mill F1 from the front to when it passes through the Nth rolling mill FN, except for the above-mentioned first control section A and second control section B, the leveling amount Lv at the rolling mill Fn+3 to be controlled is controlled to a preset leveling amount (lock-on value) LvL.
[0022] The leveling amount Lv is the difference in opening between the roll gap on the operation (OP) side of the rolling mills F1 to FN and the roll gap on the drive (DR) side. If the roll gap between the upper and lower work rolls on the operation (OP) side of the rolling mills F1 to FN is Lv_0p and the roll gap between the upper and lower work rolls on the drive (DR) side of the rolling mills F1 to FN is Lv_dr, then Lv is defined as Lv = Lv_0p - Lv_dr.
[0023] In the leveling control device 10 according to the present embodiment, the leveling amount Lv at the rolling mill Fn+3 to be controlled is calculated by dividing the first leveling correction amount ΔLv1 or the first leveling correction correction amount ΔLv1', which is proportional to the meandering amount δ1 detected by the first meandering amount detection device 13 with respect to the preset leveling amount LvL, in the first control section A from when the tail end of the rolled material S passes through the first meandering amount detection device 13 installed between the nth rolling mill Fn and the n+1th rolling mill Fn+1 from the front to when the tail end of the rolled material S passes through the n+2th rolling mill Fn+2 from the front. In the second control section B from when the tail end of the rolled material S passes through the (n+2)th rolling mill Fn+2 from the head to when it passes through the (n+3)th rolling mill Fn+3 to be controlled, the preset leveling amount LvL is corrected by adding the second leveling correction amount ΔLv2 or the second leveling correction correction amount ΔLv2' proportional to the meandering amount δ2 detected by the second meandering amount detection device 16 to the above-mentioned first leveling correction amount ΔLv1 or the first leveling correction correction amount ΔLv1'. The reason for correcting the leveling correction amount will be described later.
[0024] The leveling control device 10 will be described in detail below. The leveling control device 10 includes a first meandering amount detection device 13, a second meandering amount detection device 16, a first leveling correction amount calculation unit 17, a second leveling correction amount calculation unit 18, a meandering amount prediction model generation unit 19, a meandering amount prediction unit 20, a judgment unit 21, a leveling correction amount correction unit 22, and a leveling control unit 23.
[0025] The first meandering amount detection device 13 is installed between the nth (n is any natural number from 1 to N-3) rolling mill Fn and the n+1th rolling mill Fn+1 from the front, and includes a first imaging device 11 and a first meandering amount calculation unit 12, and detects the meandering amount δ1 of the rolling material S after the tail end of the rolling material S passes through the nth rolling mill Fn. The first imaging device 11 is composed of a line sensor camera or an area sensor camera, and images the surface of the traveling rolling material S. The first meandering amount calculation unit 12 detects the positions of both ends (the driving side and working side ends) of the rolling material S in the width direction based on the image obtained by the first imaging device 11, calculates the position of the width direction center of the rolling material S from the detected positions of both ends of the width direction of the rolling material S, and calculates the distance from the center of the width direction of each of the rolling mills F1 to FN to the calculated position of the width direction center of the rolling material S as the meandering amount δ1 of the rolling material S.
[0026] The second meandering amount detection device 16 is installed between the n+2th rolling mill Fn+2 and the n+3th rolling mill Fn+3 from the front, and includes a second imaging device 14 and a second meandering amount calculation unit 15, and detects the meandering amount δ2 of the rolling material S after the tail end of the rolling material S passes through the n+2th rolling mill Fn+2. The second imaging device 14 is composed of a line sensor camera or an area sensor camera, similar to the first imaging device 11, and captures an image of the surface of the traveling rolling material S. The second meandering amount calculation unit 15 detects the positions of both ends (the driving side and working side ends) of the rolling material S in the width direction based on the captured image obtained by the second imaging device 14, calculates the position of the width direction center of the rolling material S from the detected positions of both ends of the width direction of the rolling material S, and calculates the distance from the center of the width direction of each of the rolling mills F1 to FN to the calculated position of the width direction center of the rolling material S as the meandering amount δ2 of the rolling material S.
[0027] Further, each of the first leveling correction amount calculation unit 17, the second leveling correction amount calculation unit 18, the meandering amount prediction model generation unit 19, the meandering amount prediction unit 20, the judgment unit 21, the leveling correction amount correction unit 22, and the leveling control unit 23 is a computer system having an arithmetic processing function, and each function of the first leveling correction amount calculation unit 17, the second leveling correction amount calculation unit 18, the meandering amount prediction model generation unit 19, the meandering amount prediction unit 20, the judgment unit 21, the leveling correction amount correction unit 22, and the leveling control unit 23 (step S2, and steps S4 to S10 described later) is executed on software in accordance with instructions of various dedicated computer programs pre-stored in hardware.
[0028] The first leveling correction amount calculation unit 17 calculates a first leveling correction amount ΔLv1 for the rolling mill Fn+3 that is the (n+3)th rolling target to be controlled, based on the meandering amount Δ1 detected by the first meandering amount detection device 13. Here, the first leveling correction amount ΔLv1 in the rolling mill Fn+3 to be controlled is calculated in relation to the meandering amount δ1 detected by the first meandering amount detection device 13 by the following formula (1). ΔLv1=α·δ1 …(1) α is a control gain, which is determined in advance taking into consideration the inlet and outlet plate thickness, plate width, and steel grade of the rolled material S of the nth rolling mill Fn.
[0029] In addition, the second leveling correction amount calculation unit 18 calculates the second leveling correction amount ΔLv2 at the rolling mill Fn+3 that is the (n+3)th controlled object, based on the meandering amount δ2 detected by the second meandering amount detection device 16. Here, the second leveling correction amount ΔLv2 in the rolling mill Fn+3 to be controlled is calculated in relation to the meandering amount δ2 detected by the second meandering amount detection device 16 by the following formula (2). ΔLv2=β·δ2 …(2) β is a control gain, which is determined in advance taking into consideration the inlet and outlet plate thickness, plate width, and steel grade of the rolled material S of the (n+2)th rolling mill Fn+2.
[0030] As shown in FIG. 3 , the meandering amount prediction model generation unit 19 uses as input data information relating to the past size of the rolled material S, information relating to the past temperature of the rolled material S, information relating to the past work rolls of the finishing rolling equipment 4, an actual first leveling correction amount based on the meandering amount detected by the first meandering amount detection device 13 at the rolling mill Fn+3 that is the past object of control, and an actual second leveling correction amount based on the meandering amount detected by the second meandering amount detection device 16 at the rolling mill Fn+3 that is the past object of control, and performs machine learning on a plurality of learning data in which the actual meandering amount of the tail end of the rolled material S at the rear rolling mill FN in the finishing rolling equipment 4 in response to this input data is used as output data to generate a meandering amount prediction model 190.
[0031] Here, examples of "information about the size of the rolled material S" include the dimensions of the product (thickness, width, length), the dimensions of the slab extracted from the heating furnace 2 (thickness, width, length), and the camber amount at the front and rear ends of the rolled material S after rough rolling. Examples of "information about the temperature of the rolled material S" include the temperature of the slab when it is extracted from the heating furnace (average value in the sheet width direction, temperature at the center in the sheet width direction, and temperature at the ends in the sheet width direction), and the temperature of the sheet bar after rough rolling is completed (average value in the sheet width direction, temperature at the center in the sheet width direction, and temperature at the ends in the sheet width direction). Examples of "information about the work rolls of the finishing rolling facility 4" include the number of rolls after the work rolls are changed in each of F1 to FN, the type of work rolls in each of F1 to FN, the rolling tonnage after the work rolls are changed in each of F1 to FN, and the mill rigidity difference in each of F1 to FN.
[0032] Further, the "rear stage rolling mill" for which the meandering amount of the tail end of the rolled material S is predicted means, in a case where the finishing rolling facility 4 has N (N is a natural number equal to or greater than 4) rolling mills F1 to FN, at least one of the rolling mills after the N / 2th rolling mill, counting sequentially from the front in the transport direction of the rolled material S. In this embodiment, the final rolling mill FN, which is the Nth mill from the front, is the "rear stage rolling mill" for which the meandering amount of the tail end of the rolled material S is predicted. Here, the meandering amount of the rolled material S refers to the distance from the center of the width direction of each of the rolling mills F1 to FN (the same direction as the width direction of the rolled material S) to the center of the width direction of the rolled material S. And the meandering amount of the tail end of the rolled material S refers to the distance from the center of the width direction of each of the rolling mills F1 to FN (the same direction as the width direction of the rolled material S) to the center of the width direction of the tail end of the rolled material S.
[0033] In addition, the multiple learning data read into the meandering amount prediction model generation unit 19 (information regarding the past size of the rolled material S, information regarding the past temperature of the rolled material S, information regarding the past work rolls of the finishing rolling equipment 4, the actual first leveling correction amount based on the meandering amount detected by the first meandering amount detection device 13 at the rolling mill Fn+3 that is the object of past control, the actual second leveling correction amount based on the meandering amount detected by the second meandering amount detection device 16 at the rolling mill Fn+3 that is the object of past control, and the actual meandering amount of the tail end of the rolled material S at the rear stage rolling mill FN in the finishing rolling equipment 4) are input to the meandering amount prediction model generation unit 19 from the upper computer 24.
[0034] In this embodiment, since a neural network is adopted as a machine learning technique, a neural network model is generated as the meandering amount prediction model 190. That is, the meandering amount prediction model generation unit 19 creates a neural network model as the meandering amount prediction model 190 that links input actual data in the learning data (information on the size of the rolled material S in the past, information on the temperature of the rolled material S in the past, information on the work rolls of the finishing rolling facility 4, an actual first leveling correction amount based on the meandering amount detected by the first meandering amount detection device 13 in the rolling mill Fn+3 that is the past control target, and an actual second leveling correction amount based on the meandering amount detected by the second meandering amount detection device 16 in the rolling mill Fn+3 that is the past control target) and output actual data (an actual meandering amount of the tail end of the rolled material S in the rear stage rolling mill FN in the finishing rolling facility 4). The neural network model is expressed, for example, by a function formula.
[0035] Further, the meandering amount prediction unit 20 inputs information on the size of the rolled material S in the current rolling pass, information on the temperature of the rolled material S in the current rolling pass, information on the work rolls of the finishing rolling equipment 4 in the current rolling pass, the first leveling correction amount ΔLv1 at the rolling mill Fn+3 to be controlled calculated by the first leveling correction amount calculation unit 17, and the second leveling correction amount ΔLv2 at the rolling mill Fn+3 to be controlled calculated by the second leveling correction amount calculation unit 18 into a meandering amount prediction model 190 generated by the meandering amount prediction model generation unit 19, and performs processing to predict the meandering amount of the tail end of the rolled material S at the rear stage rolling mill FN. Here, among the information regarding the size of the rolled material S in the current rolling pass input to the meandering amount prediction model 190, information regarding the product dimensions (thickness, width, length) and the slab dimensions (thickness, width, length) extracted from the heating furnace 2 are read into the meandering amount prediction unit 20 from the host computer 24.
[0036] In addition, among the information on the size of the rolled material S in the current rolling pass input to the meandering amount prediction model 190, the camber amount of the front and rear ends of the rolled material S after rough rolling is information on the camber amount (lateral bending amount) of the front and rear ends of the rolled material S detected by a shape detector 27 installed between the rough rolling mill 3 and the finish rolling equipment 4. The shape detector 27 is equipped with an imaging device 25 and an image processing device 26 installed between the rough rolling mill 3 and the finish rolling equipment 4. The imaging device 25 is composed of an area sensor camera, and captures an image of the surface of the running rolled material S with the area sensor camera. Then, information on the captured image captured by the area sensor camera is sent to the image processing device 26, and the image processing device 26 detects the positions of both ends of the width direction of the rolled material S from the luminance distribution in the rolling material running direction and the direction perpendicular to the rolling material S based on the captured image, and calculates the camber amount of the front and rear ends of the rolled material S based on the detected positions of both ends of the width direction of the rolled material S.
[0037] Among the information on the temperature of the rolled material S in the current rolling pass input to the meandering amount prediction model 190, the temperature of the slab at the time of removal from the heating furnace (average value in the sheet width direction, temperature at the center in the sheet width direction, and temperature at the ends in the sheet width direction) is input from the host computer 24 to the meandering amount prediction unit 20, and the temperature of the sheet bar after completion of rough rolling (average value in the sheet width direction, temperature at the center in the sheet width direction, and temperature at the ends in the sheet width direction) is input from a thermometer 28 installed on the exit side of the roughing mill 3 to the meandering amount prediction unit 20. Information on the work rolls of the finishing rolling facility 4 in the current rolling pass is read from the host computer 24 to the meandering amount prediction unit 20.
[0038] FIG. 4 shows a process flow of the meandering amount prediction model 190, which is a neural network model. The meandering amount prediction model 190, which is a neural network model, is a machine learning model that predicts the amount of meandering at the tail end of the rolled material S at the rear rolling mill FN in the finishing rolling equipment 4, and includes, from the input side, an input layer 191, an intermediate layer 192, and an output layer 193. The input layer 191 stores information regarding the size of the rolled material S in the current rolling pass, information regarding the temperature of the rolled material S in the current rolling pass, information regarding the work rolls of the finishing rolling equipment 4 in the current rolling pass, the first leveling correction amount ΔLv1 at the rolling mill Fn+3 to be controlled calculated by the first leveling correction amount calculation unit 17, and information regarding the second leveling correction amount ΔLv2 at the rolling mill Fn+3 to be controlled calculated by the second leveling correction amount calculation unit 18.
[0039] The intermediate layer 192 is composed of multiple hidden layers, and multiple neurons are arranged in each hidden layer. The number of hidden layers configured in the intermediate layer 192 is not particularly limited, but it is preferable that the number of hidden layers is 5 or less because, empirically, prediction accuracy decreases when there are too many hidden layers. The output layer 193 combines the neuron information transmitted by the intermediate layer 192 and outputs the information as a predicted meandering amount of the tail end of the rolled material S at the rear rolling mill FN in the final finishing rolling equipment 4.
[0040] The judgment unit 21 judges whether or not the predicted meandering amount of the tail end of the rolled material S in the rear stage rolling mill FN predicted by the meandering amount prediction unit 20 is smaller than a predetermined threshold value. The predetermined threshold value is set to, for example, about 30 mm which is the average value of the difference between the width of the rolled material S and the distance in the width direction of the rolled material between a pair of side guides (not shown) installed on the inlet side of the finishing rolling equipment 4.
[0041] In addition, when the judgment result of the judgment unit 21 is that the predicted meandering amount of the tail end of the rolled material S at the rear stage rolling mill FN predicted by the meandering amount prediction unit 20 is equal to or greater than a predetermined threshold value, the leveling correction amount correction unit 22 corrects the first leveling correction amount ΔLv1 at the rolling mill Fn+3 to be controlled calculated by the first leveling correction amount calculation unit 17 and the second leveling correction amount ΔLv2 at the rolling mill Fn+3 to be controlled calculated by the second leveling correction amount calculation unit 18 so that the predicted meandering amount of the tail end of the rolled material S at the rear stage rolling mill FN predicted by the meandering amount prediction unit 20 becomes smaller than the aforementioned predetermined threshold value.
[0042] Specifically, when the above-mentioned predicted meandering amount is equal to or larger than a predetermined threshold, the leveling correction amount correcting unit 22 corrects the control gain α at the first leveling correction amount ΔLv1=α·δ1 to calculate a first leveling correction correction amount ΔLv1', and also corrects the control gain β at the second leveling correction amount ΔLv2=β·δ2 to calculate a second leveling correction correction amount ΔLv2', so that the above-mentioned predicted meandering amount becomes smaller than the predetermined threshold.
[0043] In addition, when the judgment result of the judgment unit 21 is that the predicted meandering amount of the tail end of the rolled material S at the rear stage rolling mill FN predicted by the meandering amount prediction unit 20 is smaller than the above-mentioned predetermined threshold value, the leveling control unit 23 calculates the first leveling correction amount ΔL calculated by the first leveling correction amount calculation unit 17 in the first control section A from the time when the tail end of the rolled material passes through the first meandering amount detection device 13 to the n+2th rolling mill Fn+2 at the rolling mill Fn+3 to be controlled, as shown in FIG. The leveling control is performed by controlling the leveling device 7 provided in the rolling mill Fn+3 to be controlled so that the leveling correction of v1 is performed by adding the second leveling correction amount ΔLv2 calculated by the second leveling correction amount calculation unit 18 to the first leveling correction amount ΔLv1 in the second control section B from when the tail end of the rolled material S has passed the (n+2)th rolling mill Fn+2 to the (n+3)th or subsequent rolling mill Fn+3 to be controlled.
[0044] In other words, when the judgment result of the judgment unit 21 indicates that the predicted meandering amount of the tail end of the rolled material S at the rear stage rolling mill FN predicted by the meandering amount prediction unit 20 is smaller than the above-mentioned predetermined threshold value, the leveling control unit 23 performs leveling control of the rolling mill Fn+3 to be controlled in the first control section A with a corrected leveling Lv obtained by adding the first leveling correction amount ΔLv1 calculated by the first leveling correction amount calculation unit 17 to the leveling amount (lock-on value) LvL previously set by the setup calculation, and performs leveling control of the rolling mill Fn+3 to be controlled in the second control section B with a corrected leveling Lv obtained by adding the leveling correction amount obtained by adding the first leveling correction amount ΔLv1 to the second leveling correction amount ΔLv2 calculated by the second leveling correction amount calculation unit 18 to the leveling amount (lock-on value) LvL previously set by the setup calculation. Here, the leveling amount (lock-on value) LvL, which is set in advance by the setup calculation, is set to a value that maximizes the wobbling effect among the median values of the wedge variations evaluated in advance.
[0045] The tracking information of the rolled material S is sent to the leveling control unit 23, and the leveling control unit 23 constantly grasps the position of the tail end of the rolled material S. Then, the leveling control unit 23 performs leveling control of the rolling mill Fn+3 to be controlled with the leveling amount LvL set in advance by setup calculation until the tail end of the rolled material S passes the first meandering amount detection device 13, and performs leveling control of the rolling mill Fn+3 to be controlled with the corrected leveling Lv obtained by adding the first leveling correction amount ΔLv1 to the leveling amount LvL when the tail end of the rolled material S is in the first control section A, and performs leveling control of the rolling mill Fn+3 to be controlled with the corrected leveling Lv obtained by adding the first leveling correction amount ΔLv1 to the leveling amount LvL when the tail end of the rolled material S passes the first control section A. After passing through the control section A and entering the second control section B, leveling control of the controlled rolling mill Fn+3 is performed using the corrected leveling Lv obtained by adding the leveling correction amount obtained by adding the first leveling correction amount ΔLv1 and the second leveling correction amount ΔLv2 calculated by the second leveling correction amount calculation unit 18 to the leveling amount LvL, and after the tail end of the rolled material has passed the second control section B, leveling control of the controlled rolling mill Fn+3 is performed using the leveling amount LvL.
[0046] Furthermore, when the leveling control unit 23 corrects the first leveling correction amount ΔLv1 at the rolling mill Fn+3 to be controlled calculated by the first leveling correction amount calculation unit 17 and the second leveling correction amount ΔLv2 at the rolling mill Fn+3 to be controlled calculated by the second leveling correction amount calculation unit 18 in the leveling correction amount correction unit 22, the leveling control unit 23 does not implement a leveling correction of the first leveling correction amount ΔLv1 calculated by the first leveling correction amount calculation unit 17 in the above-mentioned first control section A at the rolling mill Fn+3 to be controlled, and does not implement a leveling correction of the leveling correction amount obtained by adding the second leveling correction amount ΔLv2 calculated by the second leveling correction amount calculation unit 18 to the first leveling correction amount ΔLv1 in the second control section B. Instead, when the leveling correction amount correcting unit 22 corrects the first leveling correction amount ΔLv1 and the second leveling correction amount ΔLv2, the leveling control unit 23 controls the leveling device 7 provided in the rolling mill Fn+3 to be controlled so as to perform leveling correction of the first leveling correction correction amount ΔLv1′ corrected by the leveling correction amount correcting unit 22 in the first control section A, and of the leveling correction amount obtained by adding the second leveling correction correction amount ΔLv2′ corrected by the leveling correction amount correcting unit 22 to the first leveling correction correction amount ΔLv1′ in the second control section B.
[0047] In other words, when the leveling control unit 23 corrects the first leveling correction amount ΔLv1 of the rolling mill Fn+3 to be controlled calculated by the first leveling correction amount calculation unit 17 and the second leveling correction amount ΔLv2 of the rolling mill Fn+3 to be controlled calculated by the second leveling correction amount calculation unit 18 in the leveling correction amount correction unit 22, the leveling control unit 23 performs leveling control of the rolling mill Fn+3 to be controlled in the first control section A with a corrected leveling Lv obtained by adding the first leveling correction correction amount ΔLv1' to the leveling amount (lock-on value) LvL set in advance by the setup calculation, and performs leveling control of the rolling mill Fn+3 to be controlled in the second control section B with a corrected leveling Lv obtained by adding the leveling correction amount obtained by adding the first leveling correction correction amount ΔLv1' to the second leveling correction correction amount ΔLv2' to the leveling amount (lock-on value) LvL set in advance by the setup calculation.
[0048] Therefore, the leveling control unit 23 performs leveling control of the rolling mill Fn+3 to be controlled with the leveling amount LvL set in advance by the setup calculation until the tail end of the rolled material S passes through the first meandering amount detection device 13, and performs leveling control of the rolling mill Fn+3 to be controlled with the corrected leveling Lv obtained by adding the first leveling correction correction amount ΔLv1′ to the leveling amount LvL when the tail end of the rolled material S is in the first control section A, When the tail end of S has passed through the first control section A and is in the second control section B, leveling control of the controlled rolling mill Fn+3 is performed using the corrected leveling Lv obtained by adding the leveling correction amount obtained by adding the first leveling correction correction amount ΔLv1' to the second leveling correction correction amount ΔLv2' to the leveling amount LvL, and after the tail end of the rolled material has passed the second control section B, leveling control of the controlled rolling mill Fn+3 is performed using the leveling amount LvL. In addition, in Figure 5, examples are shown in which the roll gap is tightened on the operator (OP) side for each of the first leveling correction amount ΔLv1, the second leveling correction amount ΔLv2, the first leveling correction correction amount ΔLv1', and the second leveling correction correction amount ΔLv2'.
[0049] Next, the flow of processing by the leveling control device 10 will be described with reference to the flowchart shown in FIG. First, in step S1, the first meandering amount detection device 13 detects the meandering amount δ1 of the rolled material S after the tail end of the rolled material S rough rolled by the roughing mill 3 passes through the n-th rolling mill Fn from the front (first meandering amount detection step). Next, in step S2, the first leveling correction amount calculation unit 17 calculates the first leveling correction amount ΔLv1 for the rolling mill Fn+3 that is the (n+3)th controlled object based on the meandering amount δ1 detected by the first meandering amount detection device 13 (first leveling correction amount calculation step). Here, the first leveling correction amount ΔLv1 in the rolling mill Fn+3 to be controlled is calculated by the above-mentioned formula (1).
[0050] Next, in step S3, the second meandering amount detection device 16 detects the meandering amount δ2 of the rolled material S after the tail end of the rolled material S passes through the (n+2)th rolling mill Fn+2 from the front (second meandering amount detection step). Next, in step S4, the second leveling correction amount calculation unit 18 calculates the second leveling correction amount ΔLv2 at the rolling mill Fn+3 that is the (n+3)th controlled object based on the meandering amount δ2 detected by the second meandering amount detection device 16 (second leveling correction amount calculation step). The second leveling correction amount ΔLv2 in the rolling mill Fn+3 to be controlled is calculated by the above-mentioned formula (2).
[0051] Next, in step S5, the meandering amount prediction model generation unit 19 uses as input data information related to the past size of the rolled material S, information related to the past temperature of the rolled material S, information related to the past work rolls of the finishing rolling equipment 4, the actual first leveling correction amount based on the meandering amount detected by the first meandering amount detection device 13 at the rolling mill Fn+3 that is the past object of control, and the actual second leveling correction amount based on the meandering amount detected by the second meandering amount detection device 16 at the rolling mill Fn+3 that is the past object of control, and performs machine learning on a plurality of learning data in which the actual meandering amount of the tail end of the rolled material S at the rear rolling mill FN in the finishing rolling equipment 4 in response to this input data is used as output data, thereby generating a meandering amount prediction model 190 (meandering amount prediction model generation step).
[0052] Here, examples of "information about the size of the rolled material S" include the dimensions of the product (thickness, width, length), the dimensions of the slab extracted from the heating furnace 2 (thickness, width, length), and the camber amount at the front and rear ends of the rolled material S after rough rolling. Examples of "information about the temperature of the rolled material S" include the temperature of the slab when it is extracted from the heating furnace (average value in the sheet width direction, temperature at the center in the sheet width direction, and temperature at the ends in the sheet width direction), and the temperature of the sheet bar after rough rolling is completed (average value in the sheet width direction, temperature at the center in the sheet width direction, and temperature at the ends in the sheet width direction). Examples of "information about the work rolls of the finishing rolling facility 4" include the number of rolls after the work rolls are changed in each of F1 to FN, the type of work rolls in each of F1 to FN, the rolling tonnage after the work rolls are changed in each of F1 to FN, and the mill rigidity difference in each of F1 to FN.
[0053] Further, the "rear stage rolling mill" for which the meandering amount of the tail end of the rolled material S is predicted means, in a case where the finishing rolling facility 4 has N (N is a natural number equal to or greater than 4) rolling mills F1 to FN, at least one of the rolling mills after the N / 2th rolling mill, counting sequentially from the front in the transport direction of the rolled material S. In this embodiment, the final rolling mill FN, which is the Nth mill from the front, is the "rear stage rolling mill" for which the meandering amount of the tail end of the rolled material S is predicted.
[0054] In addition, the multiple learning data read into the meandering amount prediction model generation unit 19 (information regarding the past size of the rolled material S, information regarding the past temperature of the rolled material S, information regarding the past work rolls of the finishing rolling equipment 4, the actual first leveling correction amount based on the meandering amount detected by the first meandering amount detection device 13 at the rolling mill Fn+3 that is the object of past control, the actual second leveling correction amount based on the meandering amount detected by the second meandering amount detection device 16 at the rolling mill Fn+3 that is the object of past control, and the actual meandering amount of the tail end of the rolled material S at the rear stage rolling mill FN in the finishing rolling equipment 4) are input to the meandering amount prediction model generation unit 19 from the upper computer 24.
[0055] Next, in step S6, the meandering amount prediction unit 20 inputs information about the size of the rolled material S in the current rolling pass, information about the temperature of the rolled material S in the current rolling pass, information about the work rolls of the finishing rolling equipment 4 in the current rolling pass, the first leveling correction amount ΔLv1 at the rolling mill Fn+3 to be controlled calculated in step S2, and the second leveling correction amount ΔLv2 at the rolling mill Fn+3 to be controlled calculated in step S4 into the meandering amount prediction model 190 generated in step S5, and performs a process of predicting the meandering amount of the tail end of the rolled material S at the rear rolling mill FN (meandering amount prediction step).
[0056] Here, among the information regarding the size of the rolled material S in the current rolling pass input to the meandering amount prediction model 190, information regarding the product dimensions (thickness, width, length) and the slab dimensions (thickness, width, length) extracted from the heating furnace 2 are read into the meandering amount prediction unit 20 from the host computer 24.
[0057] Among the information on the size of the rolled material S in the current rolling pass input to the meandering amount prediction model 190, the camber amount at the front and rear ends of the rolled material S after rough rolling is information on the camber amount (lateral bending amount) at the front and rear ends of the rolled material S detected by a shape detector 27 installed between the roughing mill 3 and the finish rolling equipment 4. Among the information on the temperature of the rolled material S in the current rolling pass input to the meandering amount prediction model 190, the temperature of the slab (average value in the plate width direction, temperature at the center in the plate width direction, temperature at the ends in the plate width direction) at the time of removal from the heating furnace is input from the upper computer 24 to the meandering amount prediction unit 20, and the temperature of the sheet bar after rough rolling (average value in the plate width direction, temperature at the center in the plate width direction, temperature at the ends in the plate width direction) is input from a thermometer 28 installed on the exit side of the roughing mill 3 to the meandering amount prediction unit 20. Moreover, information regarding the work rolls of the finishing rolling equipment 4 in the current rolling pass is read into the meandering amount prediction unit 20 from the host computer 24 .
[0058] Next, in step S7, the judgment unit 21 judges whether or not the predicted meandering amount of the tail end of the rolled material S in the rear-stage rolling mill FN predicted in step S6 is smaller than a predetermined threshold value (judgment step). As described above, the predetermined threshold value is set to, for example, about 30 mm, which is the average value of the difference between the width of the rolled material S and the distance in the width direction of the rolled material between a pair of side guides (not shown) installed on the inlet side of the finishing rolling equipment 4. If the determination result in step S7 is YES, the process proceeds to step S8, and if the determination result in step S7 is NO, the process proceeds to step S9.
[0059] In step S8, the leveling control unit 23 determines that the judgment result in the judgment unit 21 is that the predicted meandering amount of the tail end of the rolled material S at the rear stage rolling mill FN predicted by the meandering amount prediction unit 20 is smaller than the above-mentioned predetermined threshold value, and calculates the leveling correction of the first leveling correction amount ΔLv1 calculated in the first leveling correction amount calculation step (step S2) in the first control section A from the tail end of the rolled material S passing the first meandering amount detection device 13 to the n+2th rolling mill Fn+2. In the second control section B from when the tail end portion has passed the (n+2)th rolling mill Fn+2 to when it reaches the (n+3)th or subsequent rolling mill Fn+3 to be controlled, the leveling device 7 provided in the rolling mill Fn+3 to be controlled is controlled to perform leveling correction by adding the second leveling correction amount ΔLv2 calculated in the second leveling correction amount calculation step (step S4) to the first leveling correction amount ΔLv1 (leveling control step).
[0060] That is, in step S8, the leveling control unit 23 performs leveling control of the rolling mill Fn+3 to be controlled with a corrected leveling Lv obtained by adding the first leveling correction amount ΔLv1 calculated in the first leveling correction amount calculation step (step S2) to the leveling amount (lock-on value) LvL previously set in the setup calculation in the first control section A, assuming that the predicted meandering amount of the tail end of the rolled material S in the rear stage rolling mill FN predicted by the meandering amount prediction unit 20 is smaller than the above-mentioned predetermined threshold value, and performs leveling control of the rolling mill Fn+3 to be controlled with a corrected leveling Lv obtained by adding the leveling correction amount obtained by adding the first leveling correction amount ΔLv1 to the second leveling correction amount calculation step (step S4) to the leveling amount (lock-on value) LvL previously set in the setup calculation in the second control section B.
[0061] On the other hand, in step S9, the leveling correction amount correction unit 22 determines that the judgment result in the judgment unit 21 is that the predicted meandering amount of the tail end of the rolled material S in the rear stage rolling mill FN predicted by the meandering amount prediction unit 20 is equal to or greater than a predetermined threshold, and corrects the first leveling correction amount ΔLv1 in the rolling mill Fn+3 to be controlled calculated in step S2 and the second leveling correction amount ΔLv2 in the rolling mill Fn+3 to be controlled calculated in step S4 so that the predicted meandering amount of the tail end of the rolled material S in the rear stage rolling mill FN predicted in step S6 becomes smaller than the aforementioned predetermined threshold (leveling correction amount correction step).
[0062] Specifically, when the above-mentioned predicted meandering amount is equal to or larger than a predetermined threshold, the leveling correction amount correcting unit 22 corrects the control gain α at the first leveling correction amount ΔLv1=α·δ1 to calculate a first leveling correction correction amount ΔLv1', and also corrects the control gain β at the second leveling correction amount ΔLv2=β·δ2 to calculate a second leveling correction correction amount ΔLv2', so that the above-mentioned predicted meandering amount becomes smaller than the predetermined threshold.
[0063] Then, in step S10, the leveling control unit 23 corrects the first leveling correction amount ΔLv1 at the rolling mill Fn+3 to be controlled, which was calculated in the first leveling correction amount calculation step (step S2), and the second leveling correction amount ΔLv2 at the rolling mill Fn+3 to be controlled, which was calculated in the second leveling correction amount calculation step (step S4), in step S9. Therefore, the first control amount from when the tail end of the rolled material S passes through the first meandering amount detection device 13 to when it reaches the (n+2)th rolling mill Fn+2 is obtained. In the control section A, the leveling correction of the first leveling correction amount ΔLv1 calculated in the first leveling correction amount calculation step (step S2) is not performed, while in the second control section B from when the tail end of the rolled material S passes through the n+2th rolling mill Fn+2 to when it reaches the rolling mill Fn+3 that is the (n+3)th or later to be controlled, the leveling correction of the leveling correction amount obtained by adding the second leveling correction amount ΔLv2 calculated in the second leveling correction amount calculation step (step S4) to the first leveling correction amount ΔLv1 is not performed. Instead, in step 10, the leveling control unit 23 controls the leveling of the rolling mill Fn+3 to be controlled so that in the first control section A from when the tail end of the rolled material S passes through the first meandering amount detection device 13 to when it reaches the (n+2)th rolling mill Fn+2, the leveling correction amount is the first leveling correction correction amount ΔLv1' corrected in the leveling correction amount correction step (step S9) plus the second leveling correction correction amount ΔLv2' corrected in the leveling correction amount correction step (step S9) in the second control section B from when the tail end of the rolled material S passes through the (n+2)th rolling mill Fn+2 to when it reaches the (n+3)th or subsequent rolling mill Fn+3 to be controlled (leveling control step).
[0064] That is, in step S10, the leveling control unit 23 corrects the first leveling correction amount ΔLv1 of the rolling mill Fn+3 to be controlled calculated in step S2 and the second leveling correction amount ΔLv2 of the rolling mill Fn+3 to be controlled calculated in step S4 in step S9, so in the first control section A, it performs leveling control of the rolling mill Fn+3 to be controlled with the corrected leveling Lv obtained by adding the first leveling correction correction amount ΔLv1' to the leveling amount (lock-on value) LvL set in advance by the setup calculation, and in the second control section B, it performs leveling control of the rolling mill Fn+3 to be controlled with the corrected leveling Lv obtained by adding the leveling correction amount obtained by adding the first leveling correction correction amount ΔLv1' to the second leveling correction correction amount ΔLv2' to the leveling amount (lock-on value) LvL set in advance by the setup calculation.
[0065] This ends the processing by the leveling control device 10. Here, in the leveling control device 10 according to the present embodiment, the leveling amount Lv at the rolling mill Fn+3 to be controlled is calculated as a first leveling correction amount ΔLv1 or a first leveling correction correction amount ΔLv1 which is proportional to the meandering amount δ1 detected by the first meandering amount detection device 13 with respect to a preset leveling amount LvL in a first control section A from when the tail end of the rolled material S passes through the first meandering amount detection device 13 installed between the n-th rolling mill Fn and the n+1-th rolling mill Fn+1 from the front to when the tail end of the rolled material S passes through the n+2-th rolling mill Fn+2 from the front. The reason for correcting the leveling correction amount by adding the second leveling correction amount ΔLv2 or the second leveling correction correction amount ΔLv2' proportional to the meandering amount δ2 detected by the second meandering amount detection device 16 to the above-mentioned first leveling correction amount ΔLv1 or the first leveling correction correction amount ΔLv1' in the second control section B from when the tail end of the rolled material S passes through the (n+2)th rolling mill Fn+2 from the front to when it passes through the (n+3)th rolling mill Fn+3 to be controlled is explained below.
[0066] FIG. 6 shows a schematic configuration of a finish rolling facility 4 equipped with a leveling control device 100 according to a reference example. 6, the finishing rolling facility 4 is equipped with seven rolling mills F1 to F7. The finishing rolling facility 4 is also provided with a leveling control device 100 that controls the meandering of the rolled material S. The leveling control device 100 controls the meandering of the rolled material S by "means control using a meandering meter" at the rolling mill F7 to be controlled in a control section B' from when the tail end of the traveling rolled material S passes through the sixth rolling mill F6 from the front to when it passes through the seventh rolling mill F7.
[0067] Regarding the leveling control device 100, the leveling control device 100 includes a meandering amount detection device 33, a leveling correction amount calculation unit 34, and a leveling control unit 35. The meandering amount detection device 33 is installed between the sixth rolling mill F6 from the front and the seventh rolling mill F7 to be controlled, and is equipped with an imaging device 31 and a meandering amount calculation unit 32, and detects the meandering amount δ of the rolled material S after the tail end of the rolled material S has passed through the sixth rolling mill F6. Further, the leveling correction amount calculation unit 34 calculates the leveling correction amount for the rolling mill F7 which is the seventh controlled object, based on the meandering amount δ detected by the meandering amount detection device 33.
[0068] The leveling control unit 35 controls the leveling device 7 provided in the rolling mill F7 to be controlled so as to carry out leveling correction of the leveling correction amount calculated by the leveling correction amount calculation unit 34 in the control section B' from when the tail end of the rolled material S passes through the sixth rolling mill F6 to when it reaches the seventh rolling mill F7.
[0069] On the other hand, in the finishing rolling facility 4 shown in Fig. 6, a meandering amount detection device (not shown) was installed between the fourth rolling mill F4 and the fifth rolling mill F5 from the front to detect the meandering amount between the rolling mill F4 and the rolling mill F5 after the tail end of the rolled material S passed through the rolling mill F4, and a meandering amount detection device (not shown) was installed between the rolling mill F5 and the rolling mill F6 to detect the meandering amount between the rolling mill F5 and the rolling mill F6 after the tail end of the rolled material S passed through the rolling mill F5, and the relationship between the meandering amount between the rolling mill F4 and the rolling mill F5 and the meandering amount between the rolling mill F5 and the rolling mill F6 was investigated. The results are shown in Fig. 7. Figure 7 shows the relationship between the amount of meandering at the time when the tail end of the rolled material S passes through a meandering amount detection device installed between rolling mills F4 and F5, and the amount of meandering at the time when the tail end of the rolled material S passes through a meandering amount detection device installed between rolling mills F5 and F6.
[0070] In addition, the relationship between the meandering amount between the rolling mill F5 and the rolling mill F6 after the tail end of the rolled material S has passed through the rolling mill F5 and the meandering amount between the rolling mill F6 and the rolling mill F7 after the tail end of the rolled material S has passed through the rolling mill F6 was also investigated. The results are shown in Fig. 8. Fig. 8 shows the relationship between the meandering amount at the time when the tail end of the rolled material S passes through the meandering amount detection device installed between the rolling mill F5 and the rolling mill F6 and the meandering amount at the time when the tail end of the rolled material S passes through the meandering amount detection device 33 installed between the rolling mill F6 and the rolling mill F7.
[0071] 7 and 8, when the meandering amount between the rolling mills F4 and F5 is large, the meandering amount between the rolling mills F5 and F6 is large, and accordingly, the meandering amount between the rolling mills F6 and F7 is also large. In other words, when the meandering amount is large in the upstream stages of the rolling mills, the meandering amount increases in the downstream stages. Under these circumstances, in the leveling control device 100 according to the reference example, the leveling control in the seventh rolling mill F7 to be controlled is started after the tail end of the traveling rolled material S passes through the sixth rolling mill F6 from the front. In this case, there are cases where the amount of meandering of the rolled material S cannot be reduced due to insufficient control amount.
[0072] For this reason, in the leveling control device 10 according to the present embodiment, the leveling amount Lv at the rolling mill Fn+3 to be controlled is adjusted by a first leveling correction amount ΔLv1 or a first level correction amount ΔLv2 in proportion to the meandering amount δ1 detected by the first meandering amount detection device 13 with respect to the preset leveling amount LvL in the first control section A from when the tail end of the rolled material S at the stage where the leveling control start timing is advanced passes through the first meandering amount detection device 13 installed between the nth rolling mill Fn and the n+1th rolling mill Fn+1 from the front to when it passes through the n+2th rolling mill Fn+2 from the front. In the second control section B from when the tail end of the rolled material S passes through the (n+2)th rolling mill Fn+2 to when it passes through the (n+3)th rolling mill Fn+3, where the leveling start timing is normal, the leveling correction amount LvL is corrected by adding the second leveling correction amount ΔLv2 or the second leveling correction correction amount ΔLv2' proportional to the meandering amount δ2 detected by the second meandering amount detection device 16 to the above-mentioned first leveling correction amount ΔLv1 or the first leveling correction correction amount ΔLv1' to the preset leveling amount LvL. In the leveling control device 10 of this embodiment, the leveling start timing is normally during the second control section B from when the tail end of the rolled material S passes through the n+2th rolling mill Fn+2 to when it passes through the n+3rd rolling mill Fn+3, so that the leveling control amount can be made small, thereby solving the problem of not being able to reduce the amount of meandering of the rolled material S due to insufficient control amount.
[0073] In this way, according to the leveling control device 10 and the leveling control method of this embodiment, after the tail end of the rolled material S passes through the n-th (any of 1 to N-3) rolling mill Fn from the head, the first leveling correction amount ΔLv1 is calculated for the rolling mill Fn+3 to be controlled based on the meandering amount δ1 detected by the first meandering amount detection device 13 installed between the n-th rolling mill Fn and the n+1-th rolling mill Fn+1. A second leveling correction amount calculation unit 18 (second leveling correction amount calculation unit) for calculating a second leveling correction amount ΔLv2 at the rolling mills to be controlled after the n+3rd rolling mill based on a meandering amount δ2 detected by a second meandering amount detection device 16 installed between the n+2th rolling mill Fn+2 and the n+3rd rolling mill Fn+3 after the tail end of the rolled material S has passed the n+2th rolling mill Fn+2 from the head. and a leveling control unit 23 (leveling control step: steps S8, S10) that controls the leveling of the rolling mill Fn+3 to be controlled so as to perform a leveling correction of the first leveling correction amount ΔLv1 calculated by the first leveling correction amount calculation unit 17 (first leveling correction amount calculation step: step S2) in a first control section A from when the tail end of the rolled material S has passed the first meandering amount detection device 13 to the (n+2)th rolling mill Fn+2, and a leveling correction of the second leveling correction amount ΔLv2 calculated by the second leveling correction amount calculation unit 18 (second leveling correction amount calculation step: step S4) to the first leveling correction amount ΔLv1 in a second control section B from when the tail end of the rolled material S has passed the (n+2)th rolling mill Fn+2 to the (n+3)th or subsequent rolling mill Fn+3 to be controlled.
[0074] As a result, when controlling the meandering of the rolled material S being rolled in a finishing rolling facility 4 equipped with N rolling mills F1 to FN (N is a natural number greater than or equal to 4), the timing at which control begins and the amount of control are appropriately set for the rolling mill Fn+3 to be controlled, thereby enabling the meandering of the rolled material S to be stably controlled and the rolled material S to be passed through the center of the rolling mills F1 to FN as much as possible.
[0075] In addition, according to the leveling control device 10 and the leveling control method of this embodiment, the unit 19 is provided with a meandering amount prediction model generation unit 19 (meandering amount prediction model generation step: step S5) that uses as input data information on the past size of the rolled material S, information on the past temperature of the rolled material S, information on the past work rolls of the finishing rolling equipment 4, the actual first leveling correction amount based on the meandering amount detected by the first meandering amount detection device 13 at the rolling mill Fn+3 that is the past object of control, and the actual second leveling correction amount based on the meandering amount detected by the second meandering amount detection device 16 at the rolling mill Fn+3 that is the past object of control, and uses machine learning to generate a meandering amount prediction model 190 using a plurality of learning data in which the actual meandering amount of the tail end of the rolled material S at the rear rolling mill FN in the finishing rolling equipment 4 in response to this input data is used as output data.
[0076] According to the leveling control device 10 and the leveling control method of this embodiment, the meandering amount prediction model 190 generated by the meandering amount prediction model generation unit 19 (meandering amount prediction model generation step: step S5) is provided with a meandering amount prediction unit 20 (meandering amount prediction step: step S6) that inputs information on the size of the rolled material S in the current rolling pass, information on the temperature of the rolled material S in the current rolling pass, information on the work rolls of the finishing rolling equipment 4 in the current rolling pass, the first leveling correction amount ΔLv1 at the rolling mill Fn+3 to be controlled calculated by the first leveling correction amount calculation unit 17 (first leveling correction amount calculation step: step S2), and the second leveling correction amount ΔLv2 at the rolling mill Fn+3 to be controlled calculated by the second leveling correction amount calculation unit 18 (second leveling correction amount calculation step: step S4) to predict the meandering amount of the tail end of the rolled material S at the rear stage rolling mill FN.
[0077] This makes it possible to predict the amount of meandering of the tail end of the rolled material S at the rear stage rolling mill FN when leveling correction of the first leveling correction amount ΔLv1 calculated by the first leveling correction amount calculation unit 17 (first leveling correction amount calculation step: step S2) is performed in the first control section A from when the tail end of the rolled material S passes through the nth rolling mill Fn to when it reaches the first meandering amount detection device 13, and when leveling correction of the second leveling correction amount ΔLv2 calculated by the second leveling correction amount calculation unit 18 (second leveling correction amount calculation step: step S4) is performed in the second control section B from when the tail end of the rolled material S passes through the n+2th rolling mill Fn+2 to when it reaches the second meandering amount detection device 16, in the rolling mill Fn+3 to be controlled.
[0078] In addition, the leveling control device 10 and the leveling control method according to this embodiment are provided with a judgment unit 21 (judgment step: step S7) that judges whether the predicted meandering amount of the tail end of the rolled material S at the rear stage rolling mill FN predicted by the meandering amount prediction unit 20 (meandering amount prediction step: step S6) is smaller than a predetermined threshold value.
[0079] According to the leveling control device 10 and the leveling control method of this embodiment, when the judgment result of the judgment unit 21 (judgment step: step S7) is that the predicted meandering amount of the tail end of the rolled material S at the rear-stage rolling mill FN predicted by the meandering amount prediction unit 20 (meandering amount prediction step: step S6) is equal to or greater than a predetermined threshold value, the predicted meandering amount of the tail end of the rolled material S at the rear-stage rolling mill FN predicted by the meandering amount prediction unit 20 (meandering amount prediction step: step S6) is smaller than the above-mentioned predetermined threshold value. In order to achieve this, there is provided a leveling correction amount correction unit 22 (leveling correction amount correction step: step S9) that corrects the first leveling correction amount ΔLv1 for the rolling mill Fn+3 to be controlled calculated by the first leveling correction amount calculation unit 17 (first leveling correction amount calculation step: step S2) and the second leveling correction amount ΔLv2 for the rolling mill Fn+3 to be controlled calculated by the second leveling correction amount calculation unit 18 (second leveling correction amount calculation step: step S4).
[0080] As a result, when the predicted meandering amount of the tail end of the rolled material S in the rear stage rolling mill FN is greater than or equal to a predetermined threshold value, the calculated first leveling correction amount ΔLv1 and second leveling correction amount ΔLv2 can be corrected so that the predicted meandering amount of the tail end of the rolled material S in the rear stage rolling mill FN becomes smaller than the predetermined threshold value.
[0081] Moreover, according to the leveling control device 10 and the leveling control method of this embodiment, when the judgment result of the judgment unit 21 (judgment step: step S7) indicates that the predicted meandering amount of the tail end of the rolled material S at the rear stage rolling mill FN predicted by the meandering amount prediction unit 20 (meandering amount prediction step: step S6) is smaller than a predetermined threshold value, the leveling control unit 23 (leveling control step: step S8) controls the leveling of the rolling mill Fn+3 to be controlled so as to perform a leveling correction of the first leveling correction amount ΔLv1 calculated by the first leveling correction amount calculation unit 17 (first leveling correction amount calculation step: step S2) in the first control section A, and a leveling correction of the second leveling correction amount ΔLv2 calculated by the second leveling correction amount calculation unit (second leveling correction amount calculation step: step S4) added to the first leveling correction amount ΔLv1 in the second control section B.
[0082] Moreover, according to the leveling control device 10 and the leveling control method of this embodiment, when the leveling control unit 23 (leveling control step: step S10) corrects the first leveling correction amount ΔLv1 and the second leveling correction amount ΔLv2 in the leveling correction amount correcting unit 22 (leveling correction amount correcting step: step S9), the leveling correction amount is the first leveling correction amount ΔLv1 in the first control section A and the second leveling correction amount ΔLv2 added to the first leveling correction amount ΔLv1 in the second control section B. The leveling of the rolling mill Fn+3 to be controlled is controlled so that, instead of the positive amount of leveling correction, in the first control section A, leveling correction of the first leveling correction correction amount ΔLv1' corrected by the leveling correction amount corrected by the leveling correction amount corrected by the leveling correction amount corrected by the leveling correction amount corrected by the leveling correction amount corrected by the leveling correction amount corrected by the leveling correction amount corrected by the leveling correction amount corrected by the leveling correction amount corrected by the leveling correction amount corrected by the leveling correction amount corrected by the leveling correction amount corrected by the leveling correction amount corrected by the leveling correction amount corrected by the first leveling correction correction amount ΔLv1'.
[0083] As a result, when controlling the meandering of the rolled material S being rolled in a finishing rolling facility 4 equipped with N rolling mills F1 to FN (N is a natural number greater than or equal to 4), the leveling correction amount in the first control section A and the second control section B for the rolling mill Fn+3 to be controlled becomes appropriate, and the amount of meandering of the tail end of the rolled material S in the rear stage rolling mill FN can be reliably suppressed to within a predetermined threshold value.
[0084] The manufacturing method of the hot rolled steel strip according to the present embodiment includes a finish rolling process in which the meandering of the rolled material S is controlled using the above-mentioned leveling control method to finish roll the rolled material S, a cooling process in which the rolled material S that has been finish rolled into a hot rolled steel strip is cooled by a run-out table (cooling equipment), and a winding process in which the cooled hot rolled steel strip is wound into a coil shape by a winder. This makes it possible to reduce the amount of meandering of the rolled material S that is finish rolled, and improve the productivity and yield in the hot rolling of the hot rolled steel strip.
[0085] Although the embodiment of the present invention has been described above, the present invention is not limited to this and various modifications and improvements can be made. For example, in the leveling control device 10 and the leveling control method according to this embodiment, the meandering amount prediction model generating unit 19 (meandering amount prediction model generating step: step S5), the meandering amount predicting unit 20 (meandering amount predicting step: step S6), the determining unit 21 (determining step: step S7), and the leveling correction amount correcting unit 22 (leveling correction amount correcting step: step S9) are omitted, and the meandering amount prediction, determination, and correction of the leveling correction amount are not performed, and the leveling control unit 23 (leveling control step: step S8) The leveling of the rolling mill Fn+3 to be controlled may be controlled so that, in the first control section A, a leveling correction of the first leveling correction amount ΔLv1 calculated by the first leveling correction amount calculation section 17 (first leveling correction amount calculation step: step S2) is performed, and, in the second control section B, a leveling correction of the first leveling correction amount ΔLv1 plus the second leveling correction amount ΔLv2 calculated by the second leveling correction amount calculation section 18 (second leveling correction amount calculation step: step S4) is performed.
[0086] Furthermore, the rolling mill to be controlled is not limited to the (n+3)th rolling mill Fn+3 from the beginning, but may be any one or more rolling mills after the (n+3)th rolling mill. In addition, the "rear stage rolling mill" for which the amount of meandering of the tail end of the rolled material S is predicted means at least one of the rolling mills after the N / 2th rolling mill, counting sequentially from the front in the transport direction of the rolled material S, when the finishing rolling equipment 4 has N (N is a natural number greater than or equal to 4) rolling mills F1 to FN, and is not limited to the case where the "rear stage rolling mill" for which the amount of meandering of the tail end of the rolled material S is predicted is the Nth and final rolling mill FN from the front.
[0087] Furthermore, in the leveling control device 10 and the leveling control method according to this embodiment, in addition to the first leveling correction amount ΔLv1 and the second leveling correction amount ΔLv2, a leveling correction amount at the (n+3)th rolling mill Fn+3 to be controlled may be calculated based on the meandering amount detected by a meandering amount detection device installed between the (n+1)th rolling mill Fn+1 and the (n+2)th rolling mill from the beginning, and the leveling of the (n+3)th rolling mill Fn+3 to be controlled may be controlled so that the leveling correction of the calculated leveling correction amount is performed in the section from when the tail end of the rolled material S passes through the (n+1)th rolling mill to when it reaches the (n+2)th rolling mill Fn+2.
[0088] Furthermore, in the leveling control device 10 and the leveling control method according to this embodiment, the machine learning technique is a neural network, and the meandering amount prediction model 190 is a prediction model constructed by a neural network, but any machine learning method may be used, for example, a decision tree. EXAMPLES
[0089] In FIG. 1, in a finishing rolling facility 4 equipped with seven (N=7) rolling mills F1 to F7, in order to verify the effect of the leveling control method according to the present invention, the amount of meandering in the rear-stage rolling mill F7 was measured in each of Comparative Example 1, Comparative Example 2, Invention Example 1, and Invention Example 2. In comparison example 1, after the tail end of the rolled material S passes through the sixth rolling mill F6 from the front, a leveling correction amount at the seventh rolling mill F7 to be controlled is calculated based on the amount of meandering detected by a meandering amount detection device installed between the sixth rolling mill F6 and the seventh rolling mill F7, and leveling of the rolling mill F7 to be controlled is controlled so that leveling correction of the calculated leveling correction amount is carried out in the control section from when the tail end of the rolled material S passes through the sixth rolling mill F6 to the seventh rolling mill F7 to be controlled.
[0090] In addition, in comparison example 2, after the tail end of the rolled material S passes through the i (i = 4, 5)th rolling mill Fi from the start, a leveling correction amount at the i+1th rolling mill Fi+1 to be controlled is calculated based on the meandering amount detected by a meandering amount detection device installed between the i-th rolling mill Fi and the i+1th rolling mill Fi+1, and leveling of the rolling mill Fi+1 to be controlled is controlled so that leveling correction of the calculated leveling correction amount is implemented in the control section from when the tail end of the rolled material S passes through the i-th rolling mill Fi to the i+1th rolling mill Fi+1.
[0091] In the present invention example 1, after the tail end of the rolled material S passes through the fourth rolling mill F4 from the front, a first leveling correction amount at the seventh rolling mill F7 to be controlled is calculated based on the meandering amount detected by the first meandering amount detection device 13 installed between the fourth rolling mill F4 and the fifth rolling mill F5, and after the tail end of the rolled material S passes through the sixth rolling mill F6 from the front, a first leveling correction amount at the seventh rolling mill F7 to be controlled is calculated based on the meandering amount detected by the second meandering amount detection device 16 installed between the sixth rolling mill F6 and the seventh rolling mill F7. The leveling of the rolling mill F7 to be controlled was controlled so that a second leveling correction amount at the rolling mill F7 was calculated, and a leveling correction of the first leveling correction amount was performed in a first control section A from when the tail end of the rolled material S passed through the fourth rolling mill F4 to when it reaches the sixth rolling mill F6, and a leveling correction of a leveling correction amount obtained by adding the second leveling correction amount ΔLv2 to the first leveling correction amount was performed in a second control section B from when the tail end of the rolled material S passed through the sixth rolling mill F6 to when it reaches the seventh rolling mill F7.
[0092] In the present invention example 2, the first leveling correction amount at the seventh rolling mill F7 to be controlled was calculated based on the meandering amount detected by the first meandering amount detection device 13 installed between the fourth rolling mill F4 and the fifth rolling mill F5 after the tail end of the rolled material S passed through the sixth rolling mill F6 from the top, and the second leveling correction amount at the seventh rolling mill F7 to be controlled was calculated based on the meandering amount detected by the second meandering amount detection device 16 installed between the sixth rolling mill F6 and the seventh rolling mill F7 after the tail end of the rolled material S passed through the sixth rolling mill F6 from the top. And, in the present invention example 2, further, the meandering amount prediction model generation step (step S5), the meandering amount prediction step (step S6), the determination step (step S7), the leveling control step (step S8), the leveling correction amount correction step (step S9), and the leveling control step (step S10) were executed.
[0093] In the present invention example 2, in the meandering amount prediction model generation step (step S5), the meandering amount prediction model 190 was generated by machine learning using Chainer, a known deep learning framework. 30,000 times of operation record data were used as the learning data. A batch normalization method (wherein the batch size was 256) was used during the machine learning, and the Adam method was used to set the learning rate. The input record data for the learning data includes information on the size of the rolled material S in the past (product dimensions (thickness, width, length), dimensions of the slab extracted from the heating furnace 2 (thickness, width, length), and the camber amount of the front and rear ends of the rolled material S after rough rolling), information on the temperature of the rolled material S (slab temperature at the time of extraction from the heating furnace (average value in the plate width direction, temperature at the center in the plate width direction, temperature at the ends in the plate width direction), and temperature of the sheet bar after rough rolling (average value in the plate width direction, temperature at the center in the plate width direction, temperature at the ends in the plate width direction)), information on the work rolls of the finishing rolling equipment 4, and The information to be learned was "the number of rolled pieces after the work roll change in each of F1 to F7, the type of work roll in each of F1 to F7, the rolling tonnage after the work roll change in each of F1 to F7, and the mill stiffness difference in each of F1 to F7", the actual first leveling correction amount based on the meandering amount detected by the first meandering amount detection device 13 in the rolling mill F7 that is the past object of control, and the actual second leveling correction amount based on the meandering amount detected by the second meandering amount detection device 16 in the rolling mill F7 that is the past object of control. Also, the output actual data of the learning data was the actual meandering amount of the tail end of the rolled material S in the rear stage rolling mill F7 in the finishing rolling facility 4.
[0094] In the present invention example 2, in the meandering amount prediction step (step S6), the meandering amount prediction model 190 generated in the meandering amount prediction model generation step (step S5) is input with information on the size of the rolled material S in the current rolling pass "the dimensions of the product (thickness, width, length), the dimensions of the slab extracted from the heating furnace 2 (thickness, width, length), and the camber amount of the front and rear ends of the rolled material S after rough rolling", information on the temperature of the rolled material in the current rolling pass "the temperature of the slab when extracted from the heating furnace (average value in the plate width direction, temperature of the center in the plate width direction, temperature of the end in the plate width direction), and the temperature of the sheet bar after rough rolling (average value in the plate width direction, The amount of meandering of the tail end of the rolled material S in the rear stage rolling mill F7 was predicted by inputting information regarding the work rolls of the finishing rolling equipment 4 in the current rolling pass (the number of rolled pieces after the work rolls were changed for each of F1 to F7, the type of work rolls for each of F1 to F7, the rolling tonnage after the work rolls were changed for each of F1 to F7, and the mill stiffness difference for each of F1 to F7), the calculated first leveling correction amount ΔLv1 in the rolling mill F7 to be controlled, and the calculated second leveling correction amount ΔLv2 in the rolling mill F7 to be controlled.
[0095] In addition, in Example 2 of the present invention, the predetermined threshold value applied in the judgment step (step S7) was set to 30 mm, which is the average value of the difference between the widthwise spacing of the rolled material S and the spacing of a pair of side guides (not shown) installed on the inlet side of the finishing rolling equipment 4. Table 1 shows the measurement results of the amount of meandering in the rear rolling mill F7 when leveling control was performed for 100 pieces of rolled material S with a finished plate thickness of 4 mm or less and a plate width of 1,600 mm or less in Comparative Example 1, Comparative Example 2, Invention Example 1, and Invention Example 2.
[0096] [Table 1]
[0097] In Table 1, absolute values were used to calculate the average value μ (mm) and standard deviation 3σ of the amount of meandering of the tail end of the rolled material S in the rear-stage rolling mill F7. This is because meandering of x mm to the work side and meandering of x mm to the drive side have the same risk of drawing trouble. As shown in Table 1, in the case of Example 1 and Example 2 of the present invention, both the average value μ and the standard deviation 3σ of the amount of meandering of the tail end of the rolled material S in the rear-stage rolling mill F7 were improved compared to the case of Comparative Example 1 and Comparative Example 2, confirming the effect of reducing the amount of meandering of the rolled material S in the rear-stage rolling mill F7.
[0098] Furthermore, in the case of Example 2 of the present invention, the average value μ and standard deviation 3σ of the meandering amount of the tail end of the rolled material S in the rear stage rolling mill F7 were both improved compared to Example 1 of the present invention, and it was confirmed that the meandering amount of the rolled material S was further reduced by executing the meandering amount prediction model generation step (step S5), the meandering amount prediction step (step S6), the judgment step (step S7), and the leveling correction amount correction step (step S9). In addition, according to the manufacturing method of hot-rolled steel strip of the present invention, the amount of meandering of the rolled material S being finish-rolled can be reduced, and the productivity and yield in the hot rolling of the hot-rolled steel strip can be improved. [Explanation of symbols]
[0099] 1. Hot rolling equipment 2 Furnace 3 Roughing mill 4. Finishing rolling equipment 5 Runout Table 6 Winder 7 Leveling device 10 Leveling control device 11 First imaging device 12 First meandering amount calculation section 13 First meandering amount detection device 14 Second imaging device 15 Second meandering amount calculation section 16 Second meandering amount detection device 17 First leveling correction amount calculation unit 18 Second leveling correction amount calculation unit 19. Mean-flow prediction model generation section 20. Meandering amount prediction section 21 Judgment section 22 Leveling correction amount correction section 23 Leveling control section 24 Upper computer 25 Imaging device 26 Image Processing Device 27 Shape detector A First control section B. Second control section R1~RM Roughing stand F1~FN rolling mill S rolled material
Claims
1. A leveling control method in hot rolling for controlling meandering of a rolled material rolled in a finishing rolling facility equipped with N rolling mills (N is a natural number of 4 or more), comprising: a first leveling correction amount calculation step of calculating a first leveling correction amount at a rolling mill to be controlled that is the (n+3)th or later, based on a meandering amount detected by a first meandering amount detection device installed between the nth rolling mill and the (n+1)th rolling mill after the tail end of the rolled material has passed through the nth (any of 1 to N-3)th rolling mill from the head; a second leveling correction amount calculation step of calculating a second leveling correction amount at the rolling mills to be controlled after the n+3rd rolling mill based on a meandering amount detected by a second meandering amount detection device installed between the n+2th rolling mill and the n+3th rolling mill after the tail end of the rolled material has passed the n+2th rolling mill from the head; and a leveling control step of controlling the leveling of the rolling mills to be controlled so that a leveling correction of a first leveling correction amount calculated in the first leveling correction amount calculation step is performed in a first control section from when the tail end of the rolled material has passed the first meandering amount detection device until the (n+2)th rolling mill, and a leveling correction of a leveling correction amount obtained by adding the second leveling correction amount calculated in the second leveling correction amount calculation step to the first leveling correction amount is performed in a second control section from when the tail end of the rolled material has passed the (n+2)th rolling mill until the (n+3)th or subsequent rolling mills to be controlled, a meandering amount prediction model generation step of generating a meandering amount prediction model by machine learning a plurality of learning data in which past information about the size of the rolled material, past information about the temperature of the rolled material, past information about the work rolls of the finishing rolling equipment, past actual first leveling correction amounts based on meandering amounts detected by the first meandering amount detection device at the rolling mill to be controlled, and past actual second leveling correction amounts based on meandering amounts detected by the second meandering amount detection device at the rolling mill to be controlled are used as input data, and past actual meandering amounts of the tail end of the rolled material at a rear stage rolling equipment in the finishing rolling equipment for this input data are used as output data.
2. 2. The leveling control method for hot rolling according to claim 1, further comprising a meandering amount prediction step of predicting a meandering amount of the tail end portion of the rolled material at the rear stage rolling mill by inputting information about the size of the rolled material at a current rolling pass, information about the temperature of the rolled material at the current rolling pass, information about the work rolls of the finishing rolling equipment at the current rolling pass, a first leveling correction amount at the rolling mill to be controlled calculated in the first leveling correction amount calculation step, and a second leveling correction amount at the rolling mill to be controlled calculated in the second leveling correction amount calculation step into the meandering amount prediction model.
3. 3. The leveling control method in hot rolling according to claim 2, further comprising a determination step of determining whether or not a predicted meandering amount of the tail end portion of the rolled material in the rear stage rolling mill predicted in the meandering amount prediction step is smaller than a predetermined threshold value.
4. 4. The leveling control method for hot rolling according to claim 3, further comprising a leveling correction amount correcting step of correcting a first leveling correction amount for the rolling mill to be controlled calculated in the first leveling correction amount calculating step and a second leveling correction amount for the rolling mill to be controlled calculated in the second leveling correction amount calculating step, when a judgment result in the judging step is that a predicted meandering amount of the tail end of the rolled material in the rear stage rolling mill predicted in the meandering amount predicting step is equal to or greater than the predetermined threshold value.
5. In the leveling control step, when the judgment result in the judgment step is that the predicted meandering amount of the tail end portion of the rolled material in the rear stage rolling mill predicted in the meandering amount prediction step is smaller than the predetermined threshold value, the leveling of the rolling mill to be controlled is controlled so that, in the first control section, a leveling correction of the first leveling correction amount calculated in the first leveling correction amount calculation step is performed, and, in the second control section, a leveling correction of a leveling correction amount obtained by adding the second leveling correction amount calculated in the second leveling correction amount calculation step to the first leveling correction amount is performed. In the leveling correction amount correction step, 5. The method for controlling leveling in hot rolling according to claim 4, characterized in that, when the correction is made, instead of the leveling correction by the first leveling correction amount in the first control section and the leveling correction amount obtained by adding the second leveling correction amount to the first leveling correction amount in the second control section, the leveling correction by the first leveling correction correction amount corrected in the leveling correction amount correction step is performed in the first control section, and the leveling correction by the second leveling correction correction amount corrected in the leveling correction amount correction step is performed in the second control section.
6. A leveling control device in hot rolling that controls meandering of a rolled material rolled in a finishing rolling facility equipped with N rolling mills (N is a natural number of 4 or more), a first leveling correction amount calculation unit that calculates a first leveling correction amount at a rolling mill that is to be controlled after the nth rolling mill (any of 1 to N-3) based on a meandering amount detected by a first meandering amount detection device installed between the nth rolling mill and the n+1th rolling mill after the tail end of the rolled material has passed through the nth (any of 1 to N-3)th rolling mill from the head; a second leveling correction amount calculation unit that calculates a second leveling correction amount at the rolling mills to be controlled after the n+3rd rolling mill based on a meandering amount detected by a second meandering amount detection device installed between the n+2th rolling mill and the n+3th rolling mill after the tail end of the rolled material has passed the n+2th rolling mill from the head; a leveling control unit that controls leveling of the rolling mills to be controlled so as to implement a leveling correction of a first leveling correction amount calculated by the first leveling correction amount calculation unit in a first control section from when the tail end of the rolled material has passed the first meandering amount detection device to when it reaches the n+2th rolling mill, and a leveling correction of a leveling correction amount obtained by adding a second leveling correction amount calculated by the second leveling correction amount calculation unit to the first leveling correction amount in a second control section from when the tail end of the rolled material has passed the n+2th rolling mill to when it reaches the n+3rd or subsequent rolling mills to be controlled, a meandering amount prediction model generation unit that generates a meandering amount prediction model by machine learning a plurality of learning data, the learning data being information on the past size of the rolled material, information on the past temperature of the rolled material, information on the past work rolls of the finishing rolling equipment, an actual first leveling correction amount based on the past meandering amount detected by the first meandering amount detection device at the rolling mill to be controlled, and an actual second leveling correction amount based on the past meandering amount detected by the second meandering amount detection device at the rolling mill to be controlled, and the output data being the actual meandering amount of the tail end of the rolled material at a rear stage rolling equipment in the finishing rolling equipment for this input data.
7. 7. The leveling control device in hot rolling according to claim 6, further comprising a meandering amount prediction unit that predicts a meandering amount of the tail end portion of the rolled material at the rear stage rolling mill by inputting information about the size of the rolled material at a current rolling pass, information about the temperature of the rolled material at the current rolling pass, information about the work rolls of the finishing rolling equipment at the current rolling pass, a first leveling correction amount at the rolling mill to be controlled calculated by the first leveling correction amount calculation unit, and a second leveling correction amount at the rolling mill to be controlled calculated by the second leveling correction amount calculation unit into the meandering amount prediction model.
8. 8. The leveling control device for hot rolling according to claim 7, further comprising a judgment unit that judges whether a predicted meandering amount of the tail end portion of the rolled material in the rear stage rolling mill predicted by the meandering amount prediction unit is smaller than a predetermined threshold value.
9. 9. The leveling control device for hot rolling according to claim 8, further comprising a leveling correction amount correction unit that corrects a first leveling correction amount for the rolling mill to be controlled, calculated by the first leveling correction amount calculation unit, and a second leveling correction amount for the rolling mill to be controlled, calculated by the second leveling correction amount calculation unit, so that the predicted meandering amount of the tail end of the rolled material in the rear stage rolling mill predicted by the meandering amount prediction unit becomes smaller than the predetermined threshold value when the judgment result of the judgment unit is that the predicted meandering amount of the tail end of the rolled material in the rear stage rolling mill predicted by the meandering amount prediction unit is equal to or larger than the predetermined threshold value.
10. the leveling control unit controls leveling of the rolling mill to be controlled so that, when the judgment result of the judgment unit is that the predicted meandering amount of the tail end of the rolled material in the rear stage rolling mill predicted by the meandering amount prediction unit is smaller than the predetermined threshold value, the leveling control unit executes, in the first control section, a leveling correction of the first leveling correction amount calculated by the first leveling correction amount calculation unit, and, in the second control section, a leveling correction of a leveling correction amount obtained by adding the second leveling correction amount calculated by the second leveling correction amount calculation unit to the first leveling correction amount; and when the leveling correction amount correction unit corrects the first leveling correction amount and the second leveling correction amount, 10. The leveling control device for hot rolling according to claim 9, characterized in that the leveling control device controls the leveling of the rolling mill to be controlled so that, instead of the leveling correction by the first leveling correction amount in the first control section and the leveling correction amount obtained by adding the second leveling correction amount to the first leveling correction amount in the second control section, a leveling correction by a first leveling correction correction amount corrected by the leveling correction amount corrected by the leveling correction amount correcting unit is performed in the first control section, and a leveling correction by a leveling correction amount obtained by adding the second leveling correction correction amount corrected by the leveling correction amount corrected by the leveling correction amount correcting unit to the first leveling correction correction amount is performed in the second control section.
11. A hot rolling facility comprising the leveling control device according to any one of claims 6 to 10.
12. A method for producing a hot rolled steel strip, comprising: a finish rolling step of finish rolling the rolled strip by controlling the meandering of the rolled strip using the leveling control method according to any one of claims 1 to 5.
Citation Information
Patent Citations
Method for controlling meandering of rolled stock
JP1991216207A
Control method of meandering of rolled stock
JP1991275205A
Method for controlling meandering of tail end of sheet steel in hot finishing roll
JP1995144211A
Manufacturing method for rolled material and controlling device for its meandering
JP2004074207A
Meandering control method of rolled steel sheet and manufacturing method of rolled steel sheet
JP2004306125A