Floor curing structure, floor curing method, and floor curing panel

The floor curing structure with a planarizing layer, adhesive layer, and waterproof sheet addresses the issue of asbestos dust leakage by stabilizing the waterproof sheet on even surfaces, enhancing safety and efficiency in building demolition.

JP7582648B2Active Publication Date: 2024-11-13NIHON TREAT
View PDF 11 Cites 0 Cited by

Patent Information

Application Number
JP2020150952
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2020-09-09
Publication Date
2024-11-13
Estimated Expiration
2040-09-09

AI Technical Summary

Technical Problem

Existing methods for preventing asbestos dust leakage during building demolition or renovation are inadequate, as waterproofing materials can peel off or get damaged due to uneven floor surfaces, posing safety risks and contamination hazards.

Method used

A floor curing structure comprising a planarizing layer to flatten uneven surfaces, an adhesive layer to secure a waterproof sheet layer, and an enlarged portion to cover joints, ensuring the waterproof sheet remains intact and prevents leakage.

Benefits of technology

The solution effectively prevents asbestos dust leakage by stabilizing the waterproof sheet on even surfaces, reducing damage and ensuring safe, efficient removal of contaminants post-demolition.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007582648000001
    Figure 0007582648000001
  • Figure 0007582648000002
    Figure 0007582648000002
  • Figure 0007582648000003
    Figure 0007582648000003
Patent Text Reader

Abstract

To provide a floor curing structure, a floor curing method and a floor curing panel which can correspond to unevenness occurred on a floor surface, and which prevent a waterproof material from being peeled from the floor surface.SOLUTION: A planarization layer 110 comprising a planarization material for planarizing unevenness of a floor part 200 in a separated and sealed work area in tear-down of a structure 300 and in removal work of interior / exterior finishing materials of the structure 300 is laid on an upper surface of a floor surface, and a waterproof sheet layer 130 is adhered to an upper surface of the planarization layer 110 via an adhesive layer 120.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a floor curing structure, a floor curing method, and a floor curing panel, and in particular to a floor curing structure, a floor curing method, and a floor curing panel that are laid on a floor in order to isolate and seal the work area when removing a coating material that contains harmful substances. [Background technology]

[0002] Asbestos has long been used as a building material. Commonly referred to as asbestos, it is a naturally occurring extremely fine mineral fiber that has properties such as durability, heat resistance, chemical resistance, and electrical insulation, and was used in large quantities from around 1960 to around 1990 for a variety of purposes, including construction materials, friction materials, sealing materials, and insulation materials.

[0003] However, when extremely fine mineral fibers of asbestos turn into dust and are inhaled through the airways, they cause damage to the pleura and bronchi, and eventually lead to cancers such as lung cancer and mesothelioma, which is a problem of carcinogenicity. For this reason, the manufacture and use of asbestos is currently completely prohibited.

[0004] Although the manufacture and use of asbestos is now completely prohibited, it was used in large quantities for many years in construction materials and other applications. For many years, it was used widely in a variety of structures, from ordinary homes to public facilities such as schools. For this reason, many existing buildings still contain construction materials that contain asbestos.

[0005] Asbestos, which has been widely used in construction materials, does not only become dust and scatter when exposed. For example, if a building collapses during a disaster such as an earthquake, there is a risk that a large amount of asbestos used in the construction materials will be scattered. For this reason, measures are being taken to remove construction materials that contain asbestos.

[0006] By the way, asbestos was used not only in construction materials, friction materials, sealing materials, and heat insulation materials, but also in finishing paint materials and base preparation paint materials. However, since the amount of asbestos added in these paint materials is small and they are used by fixing them with cement or synthetic resin, it was thought that asbestos would not scatter easily.

[0007] For example, when demolishing a building that uses paint containing asbestos, there is a risk that asbestos will be dispersed if it is demolished in the same way as a building that does not contain asbestos.

[0008] In addition, it is extremely difficult to demolish a building without destroying the coating made from the asbestos-containing paint. Furthermore, if an exterior wall containing asbestos is destroyed without knowing that it is, there is a risk that the asbestos will be dispersed.

[0009] There is a risk of asbestos-containing paint becoming airborne not only when a structure is demolished, but also when a structure in which asbestos-containing paint has been used is repainted, there is also a risk of asbestos becoming airborne if the paint stripping process is not performed correctly.

[0010] Therefore, when demolishing a structure or removing interior and exterior materials of a structure, methods are taken to prevent harmful substances such as asbestos dust from scattering outside the work area. For example, a method has been developed in which the work area in which the paint removal work is carried out is surrounded by an isolation sheet such as plastic, and the inside of the work area is maintained at a negative pressure, thereby carrying out the paint removal work in such a negative pressure work area.

[0011] These isolation sheets, such as plastic sheets that separate work areas, especially those laid on the floor, can sometimes be damaged by the behavior of workers during work, such as when they step on sand or concrete fragments mixed with asbestos, or when they drop their tools.

[0012] Normally, when demolishing a building or removing interior and exterior materials that contain asbestos, water is sprayed to prevent asbestos dust from scattering. Water jet methods are also used to remove paint using water pressure.

[0013] Since water is used in the removal of interior and exterior materials from buildings that contain asbestos, if the isolation sheet is damaged as mentioned above, there is a problem that contaminated water containing asbestos will leak from the work area.

[0014] Therefore, in order to prevent the leakage of such contaminated water containing asbestos, a method has been developed in which a waterproof material that can reliably prevent damage to the floor protection material during asbestos treatment is used as the floor protection material during asbestos treatment (see, for example, Patent Document 1).

[0015] Specifically, the method of using the waterproofing material disclosed in Patent Document 1, which can reliably prevent damage to the protective material, as a floor protective material for asbestos treatment involves laying a synthetic polymer roofing sheet JISA6008 or a waterproof coating material for architecture JISA6021 on the floor surface of the asbestos treatment work area without gluing it to protect the floor surface.

[0016] The waterproofing material used in the method disclosed in Patent Document 1 is a synthetic polymer roofing sheet JISA6008 or a waterproof coating material for architecture JISA6021, which has excellent durability and can follow the behavior of the base.

[0017] For this reason, the waterproofing material, which is not bonded to the floor surface, follows the movements of the worker, for example, when a worker steps on sand or concrete fragments mixed with asbestos, or when the worker drops a tool. By following the worker's movements, the waterproofing material can be prevented from being damaged. [Prior art documents] [Patent documents]

[0018] [Patent Document 1] JP 2015-57538 A Summary of the Invention [Problem to be solved by the invention]

[0019] However, in the method of Patent Document 1, the waterproofing material is not adhered to the floor surface, so there is a problem that the edge of the waterproofing material peels off from the floor surface. If the waterproofing material peels off from the floor surface, it is very dangerous because contaminated water containing asbestos will leak.

[0020] One idea is to adhere the waterproofing material to the floor surface so that it will not peel off. However, because sand and concrete fragments exist on the floor surface, adhering the waterproofing material to the floor surface means that the waterproofing material will be adhered to the sand and concrete fragments.

[0021] This means that the waterproofing material cannot move with the sand and concrete debris. In other words, if a worker walks on the waterproofing material that has been adhered to a surface that has become uneven due to sand and concrete debris, the waterproofing material will be damaged.

[0022] In addition, in the method of Patent Document 1, the waterproofing material is not adhered to the floor surface, so it is possible that the waterproofing material will bend on the floor surface. If a worker's foot gets caught in the bent part of the waterproofing material, it may cause the worker to fall or fall off the scaffolding, which is very dangerous.

[0023] The present invention has been made in consideration of these points, and aims to provide a floor curing structure, a floor curing method, and a floor curing panel that can respond to unevenness on the floor surface and prevent waterproofing material from peeling off from the floor surface. [Means for solving the problem]

[0024] In order to solve the above problems, the present invention provides a floor curing structure that is laid on the floor of a work area in order to isolate and seal the work area during the demolition of a structure or the removal of interior and exterior materials from the structure. The floor curing structure is made of a planarizing material that makes the unevenness of the floor level, and includes a planarizing layer laid on the upper surface of the floor, a waterproof sheet layer that is adhered to the upper surface of the planarizing layer via an adhesive layer, The present invention provides a floor protection structure comprising: As a result, a leveling layer made of a leveling material that levels out any unevenness in the floor is laid on the upper surface of the floor, and a waterproof sheet layer is adhered to the upper surface of the leveling layer via an adhesive layer.

[0025] The present invention also provides a floor surface treatment method in which a waterproof sheet layer is laid on the floor within a work area in order to isolate and seal the work area during the demolition of a structure or the removal of interior and exterior materials from the structure, the method comprising the steps of: laying a planarizing layer made of a planarizing material for leveling any unevenness in the floor on the upper surface of the floor; and adhering a waterproof sheet layer to the upper surface of the planarizing layer via an adhesive layer. As a result, a leveling layer made of a leveling material that levels out any unevenness in the floor is laid on the upper surface of the floor, and a waterproof sheet layer is adhered to the upper surface of the leveling layer via an adhesive layer.

[0026] The present invention also provides a floor curing panel that is laid on the floor within a work area in order to isolate and seal the work area when demolishing a structure or removing interior and exterior materials from the structure, the floor curing panel being made of a leveling material that levels out any unevenness in the floor, and comprising a leveling layer laid on the upper surface of the floor, and a waterproof sheet layer adhered to the upper surface of the leveling layer via an adhesive layer. As a result, a leveling layer made of a leveling material that levels out any unevenness in the floor is laid on the upper surface of the floor, and a waterproof sheet layer is adhered to the upper surface of the leveling layer via an adhesive layer. Effect of the Invention

[0027] According to the floor curing structure, floor curing method, and floor curing panel of the present invention, a planarizing layer made of a planarizing material that makes the unevenness of the floor level is laid on the upper surface of the floor, and a waterproof sheet layer is adhered to the upper surface of the planarizing layer via an adhesive layer, so that the waterproof sheet layer is not laid on an uneven surface such as sand, concrete debris, etc. Therefore, workers do not walk on the sand or concrete debris, and the waterproof sheet layer is not damaged.

[0028] In addition, since there is no sand or concrete debris and the waterproof sheet layer is adhered to the top surface of the planarizing layer, which is stably laid on the top surface of the floor surface by the weight of the planarizing material, the waterproof sheet layer will not peel off from the planarizing layer. Furthermore, the planarizing layer to which the waterproof sheet layer is adhered will not peel off from the top surface of the floor surface due to the weight of the planarizing material. [Brief description of the drawings]

[0029] [Figure 1] FIG. 2 is a cross-sectional view showing a floor curing panel according to the present embodiment. [Diagram 2] FIG. 1 is a cross-sectional view showing a state in which a plurality of floor curing panels according to the present embodiment are connected and joined together. [Diagram 3] FIG. 11 is a cross-sectional view showing a state in which a plurality of floor curing panels according to the present embodiment are connected and joined by another method. [Figure 4] 1 is a cross-sectional view showing how the waterproof sheet layer of multiple floor surface treatment panels in this embodiment is peeled off from the planarizing layer. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0030] Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings. FIG. 1 is a cross-sectional view showing a floor curing panel according to the present embodiment. The floor protection panel 100 of this embodiment is a floor protection material for preventing the leakage of harmful substances such as asbestos dust from a floor section 200 (not shown) within a work area set up to prevent harmful substances such as asbestos dust from scattering outside a specified area when demolishing a building or removing interior and exterior materials of the building, or paint materials containing harmful substances.

[0031] As shown in FIG. 1, the floor protection panel 100 includes a planarizing layer 110, an adhesive layer 120, and a waterproof sheet layer . The planarizing layer 110 is a rectangular plate-like body that is laid on the top surface of an uneven surface caused by protruding pebbles, concrete fragments, rocks or metal embedded in the ground, i.e., the floor portion 200 (not shown).

[0032] By forming the planarizing layer 110 in a rectangular shape, the planarizing layer 110 can be assembled and laid without gaps on the floor section 200. If the end of the floor section 200 cannot be laid with a rectangular planarizing layer 110, it can be deformed into any shape. Also, if the floor section 200 can be laid without gaps, the planarizing layer 110 can be formed in any shape.

[0033] Specific examples of floor portion 200 include a concrete slab surface, an asphalt surface, soil, a gravel surface, scaffolding, or a work board, or any other surface on which a worker can step.

[0034] The planarizing layer 110 is made of a planarizing material that makes the unevenness of the floor portion 200 flat. An example of the planarizing material is a hard board member such as a plywood board. In addition, it is preferable that the planarizing material be stably laid on the upper surface of the floor portion 200 by the weight of the planarizing material.

[0035] The planarizing layer 110, which is a hard plate member, is laid on the uneven floor portion 200. As a result, even if the floor portion 200 has unevenness caused by protruding pebbles, concrete fragments, or rocks or metal buried in the ground, the floor portion 200 is made planar.

[0036] The planarizing layer 110 may be formed of an unevenness absorbing material that absorbs and flattens unevenness in the floor portion 200. The unevenness absorbing material should have appropriate elasticity and should also have water resistance.

[0037] Specific examples of the material for the unevenness absorbing material include resins such as polyethylene and polypropylene. In this case, it is preferable that the unevenness absorbing material is stably laid on the upper surface of the floor portion 200. If the unevenness absorbing material is lightweight, a weight increasing means such as a weight to increase the weight of the planarizing layer 110 can be added separately from the unevenness absorbing material.

[0038] The adhesive layer 120 is an adhesive that is laminated on the upper surface of the planarizing layer 110 to adhere the waterproof sheet layer 130. The adhesive layer 120 only needs to be able to adhere the waterproof sheet layer 130 to the upper surface of the planarizing layer 110, and the adhesive layer 120 may be laminated on the entire upper surface of the planarizing layer 110, but the adhesive layer 120 may also be laminated on a portion of any location on the upper surface of the planarizing layer 110 to adhere the planarizing layer 110 and the waterproof sheet layer 130.

[0039] The waterproof sheet layer 130 is made of a waterproof material that is waterproof and water-resistant to prevent moisture containing harmful substances such as asbestos dust from leaking from the floor 200 in the work area. In addition, it is durable and flexible enough to withstand the impact even if a worker drops a tool or the like.

[0040] Specific examples of the waterproof material constituting the waterproof sheet layer 130 include synthetic polymer roofing sheets (Japanese Industrial Standards A6008) and architectural coating waterproof materials (Japanese Industrial Standards A6021).

[0041] The durability and flexibility of the waterproof sheet layer 130 varies depending on its thickness, but this can be changed depending on how often workers walk or work on the floor protection panel 100 and where the floor protection panel 100 is installed.

[0042] The periphery of the waterproof sheet layer 130 is larger than the areas of the planarizing layer 110 and the adhesive layer 120 , that is, an expanded portion 131 is formed which is expanded so as to extend outward beyond the peripheral surface of the planarizing layer 110 . When the floor surface treatment panels 100 are laid on the floor portion 200, the planarizing layers 110 constituting the multiple floor surface treatment panels 100 are laid without any gaps.

[0043] At this time, among the floor treatment panels 100 laid without any gaps, the expanded portion 131 of one of the floor treatment panels 100 is expanded so as to extend outward beyond the peripheral surface of the planarizing layer 110, and therefore overlaps with the other planarizing layer 110 laid adjacently.

[0044] As a result, the expanded portion 131 covers from above, going beyond the joints of adjacently laid planarizing layers 110, thereby preventing the leakage of moisture containing harmful substances such as asbestos dust that is generated on the upper side of the floor treatment panel 100 from the joints of adjacently laid planarizing layers 110.

[0045] In addition, by overlapping and adhering the expansion portion 131, which covers beyond the joint of the adjacently laid planarizing layer 110, to the waterproof sheet layer 130 of the adjacently laid floor curing panel 100, the joint of the waterproof sheet layer 130 of the adjacently laid floor curing panel 100 is blocked by adhesion. This makes it possible to prevent leakage of moisture containing harmful substances such as asbestos dust generated on the upper side of the floor curing panel 100.

[0046] As described above, the leveling layer 110 made of a leveling material that levels out unevenness in the floor portion 200 is stably laid on the upper surface of the floor by the weight of the leveling material, and the waterproof sheet layer 130 is adhered to the upper surface of the leveling layer 110 via the adhesive layer 120, thereby forming a floor curing structure that can accommodate unevenness in the floor surface and prevent the waterproof material from peeling off from the floor surface.

[0047] Specifically, the waterproof sheet layer 130 is not laid on an uneven surface such as sand, concrete debris, etc. Therefore, workers do not walk on sand or concrete debris, and the waterproof sheet layer 130 is not damaged.

[0048] In addition, since there is no sand or concrete debris and the waterproof sheet layer 130 is adhered to the top surface of the planarizing layer 110, which is stably laid on the top surface of the floor surface by the weight of the planarizing material, the waterproof sheet layer 130 will not peel off from the planarizing layer 110. Furthermore, the planarizing layer 110 to which the waterproof sheet layer 130 is adhered will not peel off from the top surface of the floor surface due to the weight of the planarizing material.

[0049] In addition, the protective material must be removed after the demolition of the building or the removal of the interior and exterior materials of the building, etc. At this time, if only the waterproof sheet layer 130 with the harmful substances attached can be removed, the protective material removal work can be carried out safely and in a short time.

[0050] Therefore, it is advisable to adjust the adhesive strength of the adhesive layer 120 so as to facilitate peeling of the waterproof sheet layer 130 from the planarizing layer 110. When peeling the waterproof sheet layer 130 from the planarizing layer 110, the adhesive layer 120 may be peeled off from the planarizing layer 110 while remaining adhered to the waterproof sheet layer 130, or the waterproof sheet layer 130 may be peeled off while remaining adhered to the adhesive layer 120.

[0051] In this embodiment, the planarizing layer 110 made of a planarizing material that makes the unevenness of the floor portion 200 flat is stably laid on the upper surface of the floor surface by the weight of the planarizing material, but in order to lay the planarizing layer 110 more stably, the floor portion 200 and the planarizing layer 110 may be fixed with stakes or rivets. Also, the floor portion 200 and the planarizing layer 110 may be peelably adhered to each other by using an adhesive.

[0052] In addition, in this embodiment, an example has been shown in which a floor protection structure is formed by laying a floor protection panel 100, in which a planarizing layer 110, an adhesive layer 120, and a waterproof sheet layer 130 are integrated, on the floor section 200. However, a floor protection structure can also be formed by first forming the planarizing layer 110 at the construction site by laying a planarizing material on the floor section 200, laminating the adhesive layer 120 on the formed planarizing layer 110, and laminating the waterproof sheet layer 130 on the laminated adhesive layer 120.

[0053] FIG. 2 is a cross-sectional view showing a state in which a plurality of floor curing panels according to this embodiment are connected and joined together. As shown in FIG. 2, when laying floor surface treatment panels 100 on a floor portion 200, a plurality of floor surface treatment panels 100 can be laid without any gaps.

[0054] At this time, by overlapping and gluing the expanded portions 131 of adjacent floor protection panels 100, it is possible to prevent leakage of moisture containing harmful substances such as asbestos dust that is generated on the upper side of the floor protection panels 100.

[0055] Specifically, an enlarged portion 131 is formed around the periphery of the waterproof sheet layer 130 so as to extend outward beyond the peripheral surfaces of the planarizing layer 110 and the adhesive layer 120. This enlarged portion 131 is laminated so as to overlap the enlarged portion 131 provided on the waterproof sheet layer 130 of the adjacent floor surface treatment panel 100. The laminated portions may be bonded with an adhesive, etc. Alternatively, the expanded portion 131 and the waterproof sheet layer 130 may be joined and bonded with an adhesive tape, etc., from above the overlapping portion of the expanded portion 131 and the waterproof sheet layer 130.

[0056] The expanded portion 131 on the side to be laminated from above may be woven into the bottom side of the planarizing layer 110 so as to cover the ends of the planarizing layer 110 and the adhesive layer 120. This eliminates gaps between adjacent floor curing panels 100, making it possible to prevent leakage of moisture containing harmful substances such as asbestos dust that is generated on the upper side of the floor curing panels 100.

[0057] The enlarged portion 131 can also be attached to a wall 310 that corresponds to the wall portion of the structure 300 in the work area, for example. This allows the joint portion between the floor 200 and the wall 310 of the structure 300 to be covered with the enlarged portion 131, making it possible to prevent leakage of moisture containing harmful substances such as asbestos dust that is generated above the floor curing panel 100.

[0058] Further, the enlarged portion 131 can be adhered to a partition material installed to separate a work area, specifically, a wall 310 that corresponds to a wall portion such as a waterproof material installed in the vertical direction.

[0059] This allows the joint between the floor section 200 and a wall body 310 such as a waterproofing material installed vertically to be covered with the enlarged section 131, thereby preventing leakage of moisture containing harmful substances such as asbestos dust that are generated above the floor protection panel 100.

[0060] FIG. 3 is a cross-sectional view showing a state in which a plurality of floor curing panels according to this embodiment are connected and joined by another method. As shown in FIG. 3, when laying floor surface treatment panels 100 on a floor portion 200, a plurality of floor surface treatment panels 100 can be laid without any gaps.

[0061] For example, a non-adhesive area N is provided on the peripheral surface of the floor protection panel 100 where the planarizing layer 110 and the waterproof sheet layer 130 are not adhered by the adhesive layer 120, i.e., no adhesive layer 120 is interposed, and an enlarged portion 131 is formed to cover the non-adhesive area N.

[0062] When connecting and joining multiple floor treatment panels 100, the expansion portion 131A provided on one floor treatment panel 100A is interposed between the flattening layer 110B, which is the non-adhesive area N provided on the other floor treatment panel 100B, and the expansion portion 131B.

[0063] The overlapping portions of the laminated expanded portion 131A and expanded portion 131B may be bonded with an adhesive, etc. Also, the overlapping portions of the expanded portion 131A and expanded portion 131B may be connected and bonded with an adhesive tape, etc.

[0064] This prevents gaps from forming between adjacent floor curing panels 100, making it possible to prevent leakage of moisture containing harmful substances such as asbestos dust that is generated above the floor curing panels 100.

[0065] FIG. 4 is a cross-sectional view showing how the waterproof sheet layers of a plurality of floor surface treatment panels according to this embodiment are peeled off from the planarizing layer. In the floor treatment panel 100 of this embodiment, the adhesive layer 120 can be made to have an adhesive strength that enables the waterproof sheet layer 130 to be peeled off from the planarizing layer 110, so that the waterproof sheet layer 130 can be easily peeled off from the planarizing layer 110.

[0066] 4, when peeling the waterproof sheet layer 130 from the planarizing layer 110, the waterproof sheet layer 130 can be peeled from the planarizing layer 110 while the adhesive layer 120 remains on the planarizing layer 110. Also, the waterproof sheet layer 130 and the adhesive layer 120 may be peeled from the planarizing layer 110 while the adhesive layer 120 remains on the waterproof sheet layer 130.

[0067] In this way, by peeling off the waterproof sheet layer 130 from the planarizing layer 110, it is possible to remove only the waterproof sheet layer 130 with harmful substances attached after the demolition of the building and the removal of the building's interior and exterior materials are completed, and the protective material removal work can be carried out safely and in a short time. [Explanation of symbols]

[0068] 100 Floor protection panel 110 Planarization layer 120 Adhesive layer 130 Waterproof Sheet Layer 131 Enlarged section 200 Floor 300 Structures 310 Wall N non-adhesive area

Claims

1. A floor curing structure that is laid on the floor within a work area in order to isolate and seal the work area during the demolition of a structure or the removal of interior and exterior materials of the structure, a planarizing layer made of a planarizing material for planarizing the unevenness of the floor portion and laid on the upper surface of the floor portion; a waterproof sheet layer attached to an upper surface of the planarizing layer via an adhesive layer; Equipped with The planarizing material is A wooden board member, The waterproof sheet layer is an enlarged portion formed so as to protrude outward beyond a peripheral surface of the planarizing layer; The enlarged portion is being disposed over a junction with an adjacently laid planarizing layer; A floor curing structure characterized by the above.

2. The adhesive layer is The adhesive strength is such that the layer can be peeled off from the planarizing layer or the waterproof sheet layer.

2. The floor curing structure according to claim 1,

3. The waterproof sheet layer is Synthetic polymer roofing sheet or architectural coating waterproof material.

2. The floor curing structure according to claim 1,

4. The synthetic polymer roofing sheet is It is A6008 as specified by the Japanese Industrial Standards. The floor curing structure according to claim 3,

5. The architectural coating waterproof material is It is A6021 as specified by the Japanese Industrial Standards. The floor curing structure according to claim 3,

6. A floor curing structure that is laid on the floor within a work area in order to isolate and seal the work area during the demolition of a structure or the removal of interior and exterior materials of the structure, a planarizing layer made of a planarizing material for planarizing the unevenness of the floor portion and laid on the upper surface of the floor portion; a waterproof sheet layer attached to an upper surface of the planarizing layer via an adhesive layer; Equipped with The planarizing material is A wooden board member, The waterproof sheet layer is an enlarged portion formed so as to protrude outward beyond a peripheral surface of the planarizing layer; The enlarged portion is being bonded over the tarpaulin layer which is bonded to an adjacently laid planarizing layer; A floor curing structure characterized by the above.

7. The adhesive layer is The adhesive strength is such that the layer can be peeled off from the planarizing layer or the waterproof sheet layer. The floor curing structure according to claim 6,

8. The waterproof sheet layer is Synthetic polymer roofing sheet or architectural coating waterproof material. The floor curing structure according to claim 6,

9. The synthetic polymer roofing sheet is It is A6008 as specified by the Japanese Industrial Standards. The floor curing structure according to claim 8,

10. The architectural coating waterproof material is It is A6021 as specified by the Japanese Industrial Standards. The floor curing structure according to claim 8,

11. A floor curing structure that is laid on the floor within a work area in order to isolate and seal the work area during the demolition of a structure or the removal of interior and exterior materials of the structure, a planarizing layer made of a planarizing material for planarizing the unevenness of the floor portion and laid on the upper surface of the floor portion; a waterproof sheet layer attached to an upper surface of the planarizing layer via an adhesive layer; Equipped with The planarizing material is A wooden board member, The waterproof sheet layer is an enlarged portion formed so as to protrude outward beyond a peripheral surface of the planarizing layer; The enlarged portion is Attached to a structure inside the work area or to a wall portion of a partition material installed to separate the work area; A floor curing structure characterized by the above.

12. The adhesive layer is The adhesive strength is such that the layer can be peeled off from the planarizing layer or the waterproof sheet layer. The floor curing structure according to claim 11,

13. The waterproof sheet layer is Synthetic polymer roofing sheet or architectural coating waterproof material. The floor curing structure according to claim 11,

14. The synthetic polymer roofing sheet is It is A6008 as specified by the Japanese Industrial Standards. The floor curing structure according to claim 13,

15. The architectural coating waterproof material is It is A6021 as specified by the Japanese Industrial Standards. The floor curing structure according to claim 13,

16. A floor curing method for isolating and sealing a work area during demolition of a structure or removal of interior and exterior materials of the structure, comprising laying a floor covering on the floor within the work area, laying a planarizing layer on the upper surface of the floor, the planarizing layer being made of a planarizing material that plans out any unevenness in the floor; a step of adhering a waterproof sheet layer to an upper surface of the planarizing layer via an adhesive layer; Equipped with The planarizing material is A wooden board member, The waterproof sheet layer is an enlarged portion formed so as to protrude outward beyond a peripheral surface of the planarizing layer; The enlarged portion is being disposed over a junction with an adjacently laid planarizing layer; A floor curing method characterized by the above.

17. A floor curing method for isolating and sealing a work area during demolition of a structure or removal of interior and exterior materials of the structure, comprising laying a floor covering on the floor within the work area, laying a planarizing layer on the upper surface of the floor, the planarizing layer being made of a planarizing material that plans out any unevenness in the floor; a step of adhering a waterproof sheet layer to an upper surface of the planarizing layer via an adhesive layer; Equipped with The planarizing material is A wooden board member, The waterproof sheet layer is an enlarged portion formed so as to protrude outward beyond a peripheral surface of the planarizing layer; The enlarged portion is being bonded over the tarpaulin layer which is bonded to an adjacently laid planarizing layer; A floor curing method characterized by the above.

18. A floor curing method for isolating and sealing a work area during demolition of a structure or removal of interior and exterior materials of the structure, comprising laying a floor covering on the floor within the work area, laying a planarizing layer on the upper surface of the floor, the planarizing layer being made of a planarizing material that plans out any unevenness in the floor; a step of adhering a waterproof sheet layer to an upper surface of the planarizing layer via an adhesive layer; Equipped with The planarizing material is A wooden board member, The waterproof sheet layer is an enlarged portion formed so as to protrude outward beyond a peripheral surface of the planarizing layer; The enlarged portion is Attached to a structure inside the work area or to a wall portion of a partition material installed to separate the work area; A floor curing method characterized by the above.

19. A floor curing panel that is laid on the floor within a work area in order to isolate and seal the work area during the demolition of a structure or the removal of interior and exterior materials of the structure, a planarizing layer made of a planarizing material for planarizing the unevenness of the floor portion and laid on the upper surface of the floor portion; a waterproof sheet layer attached to an upper surface of the planarizing layer via an adhesive layer; Equipped with The planarizing material is A wooden board member, The waterproof sheet layer is an enlarged portion formed so as to protrude outward beyond a peripheral surface of the planarizing layer; The enlarged portion is being disposed over a junction with an adjacently laid planarizing layer; A floor curing structure characterized by the above.

20. A floor curing panel that is laid on the floor within a work area in order to isolate and seal the work area during the demolition of a structure or the removal of interior and exterior materials of the structure, a planarizing layer made of a planarizing material for planarizing the unevenness of the floor portion and laid on the upper surface of the floor portion; a waterproof sheet layer attached to an upper surface of the planarizing layer via an adhesive layer; Equipped with The planarizing material is A wooden board member, The waterproof sheet layer is an enlarged portion formed so as to protrude outward beyond a peripheral surface of the planarizing layer; The enlarged portion is being bonded over the tarpaulin layer which is bonded to an adjacently laid planarizing layer; A floor curing structure characterized by the above.

21. A floor curing panel that is laid on the floor within a work area in order to isolate and seal the work area during the demolition of a structure or the removal of interior and exterior materials of the structure, a planarizing layer made of a planarizing material for planarizing the unevenness of the floor portion and laid on the upper surface of the floor portion; a waterproof sheet layer attached to an upper surface of the planarizing layer via an adhesive layer; Equipped with The planarizing material is A wooden board member, The waterproof sheet layer is an enlarged portion formed so as to protrude outward beyond a peripheral surface of the planarizing layer; The enlarged portion is Attached to a structure inside the work area or to a wall portion of a partition material installed to separate the work area; A floor curing structure characterized by the above.

Citation Information

Patent Citations

  • JP1976146717U

  • JP1987059246U

  • Architectural curing board

    JP1994056365U

  • Floor execution method and floor material with curing sheet

    JP1998088812A

  • Curing board and curing method for floor surface

    JP2004060153A