Building renovation methods

The method uses temporary reinforcing beams to support the cut end of the floor structure from both above and below, preventing bending and cracking during height changes, allowing for efficient and cost-effective multi-floor renovations.

JP7594417B2Active Publication Date: 2024-12-04TAKENAKA CORP
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
JP2020198112
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2020-11-30
Publication Date
2024-12-04
Estimated Expiration
2040-11-30

AI Technical Summary

Technical Problem

Existing building renovation methods cause damage such as cracks in the floor slab when changing the height of a floor structure by separating it from the existing frame due to bending at the cut end, as multiple support points are directly supported by pillars.

Method used

A building renovation method that uses temporary reinforcing beams arranged along the cut end of the floor structure, connected to temporary columns, supporting the load from both above and below to prevent bending and cracking, and allows for simultaneous height change of multiple floors.

Benefits of technology

Prevents damage to the floor slab by supporting the cut end of the floor structure with temporary reinforcing beams, enabling efficient and cost-effective batch height changes of multiple floors without cracking, and maintaining structural integrity during the renovation process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007594417000001
    Figure 0007594417000001
  • Figure 0007594417000002
    Figure 0007594417000002
  • Figure 0007594417000003
    Figure 0007594417000003
Patent Text Reader

Abstract

To provide a building repair method capable of inhibiting a deflection of a floor slab constituting a floor structure part at a cut end of the floor structure part and inhibiting breakage such as a crack in the floor slab in removing the floor structure part, which needs change in height, from an existing skeleton to change the height.SOLUTION: In a building repair method for removing a floor structure part 2, which needs change in height, in an existing skeleton K of a building from the existing skeleton K to change the height, a temporary reinforcement beam 6 is disposed along a cut end 21 of the floor structure part 2 to be removed from the existing skeleton K, the temporary reinforcement beam 6 is connected to a temporary pole 4, and the load of the floor structure part 2 on the cut end 21 side is supported by the temporary pole 4 via the temporary reinforcement beam 6.SELECTED DRAWING: Figure 7
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a building renovation method that can be suitably used when changing the use of the interior of a building, and in particular to a building renovation method for changing the height of a floor structure part of an existing building frame that is to be changed in height by separating the floor structure part from the existing building frame. [Background technology]

[0002] Patent Document 1 describes this type of building renovation method in which the floor structure of a floor to be changed in height is separated from the existing framework, moved vertically, and re-fixed at the new height. In this building renovation method, when the floor structure section to be changed in height is separated from the existing structure to change its height, in order to support the cut end of the floor structure section to be separated from the existing structure, the end of the existing main girder, which is placed with a column spacing between the cut end, is directly connected to a column located directly below. [Prior art documents] [Patent documents]

[0003] [Patent Document 1] JP 2015-063793 A Summary of the Invention [Problem to be solved by the invention]

[0004] In the building renovation method described in Patent Document 1, when the floor structure to be changed in height is separated from the existing structure and its height is changed, the floor structure is directly supported by multiple columns with support points distributed along the cut end of the floor structure. Therefore, at the cut end of the floor structure, the floor slab constituting the floor structure is deflected between the multiple columns constituting the support points, and this deflection may cause damage such as cracks in the floor slab.

[0005] In view of this situation, the main objective of the present invention is to provide a building renovation method that can suppress bending of the floor slab that constitutes the floor structure part at the cut end of the floor structure part when the floor structure part to be changed in height is separated from the existing structure to change its height, thereby suppressing damage such as cracks in the floor slab. [Means for solving the problem]

[0010] The present invention 1 The characteristic configuration is: A building renovation method for changing the height of a floor structure part to be changed in an existing structure of a building by separating the floor structure part from the existing structure, A temporary reinforcement beam is placed along the cut end of the floor structure to be separated from the existing structure, and the temporary reinforcement beam is connected to a temporary column, and the load on the cut end side of the floor structure is supported by the temporary column via the temporary reinforcement beam, The temporary reinforcement beams are disposed on both the upper and lower sides of the cut end of the floor structure, and the upper and lower temporary reinforcement beams support the load on the cut end side of the floor structure from both the upper and lower sides; The floor structure section includes a truss beam, an upper chord side floor slab supported by an upper chord member of the truss beam, and a lower chord side floor slab supported by a lower chord member of the truss beam, The temporary reinforcement beam arranged on the upper surface side of the cut end of the floor structure supports the load on the cut end side of the upper chord side floor slab from above, The temporary reinforcement beam arranged on the underside of the cut end of the floor structure supports the load on the cut end side of the lower chord side floor slab from below.

[0011] According to this configuration, when the floor structure section to be changed in height is separated from the existing structure to change its height, temporary reinforcement beams are placed along the cut ends of the floor structure section to be separated from the existing structure, and the temporary reinforcement beams are connected to temporary columns, and the load of the floor structure section is supported by the temporary columns via the temporary reinforcement beams.Therefore, the cut ends of the floor structure section are reinforced overall with the temporary reinforcement beams, while the load of the floor structure section can be appropriately supported by the temporary columns via the temporary reinforcement beams. Therefore, when the floor structure section to be changed in height is separated from the existing structure to change its height, bending of the floor slab that constitutes the floor structure section at the cut end of the floor structure section can be suppressed, thereby suppressing damage such as cracks in the floor slab. Furthermore, according to this configuration, the cut end of the floor structure can be properly supported from both above and below by the temporary reinforcing beams arranged on both the upper and lower sides of the cut end of the floor structure. Furthermore, According to this configuration, the cut end of the upper chord side floor slab is supported from above by a temporary reinforcement beam arranged on the upper side of the cut end of the floor structure part, and the cut end of the lower chord side floor slab is supported from below by a temporary reinforcement beam arranged on the underside of the cut end of the floor structure part, thereby making it possible to properly support the cut end of a floor structure part which comprises a truss beam, an upper chord side floor slab supported by the upper chord member of the truss beam, and a lower chord side floor slab supported by the lower chord member of the truss beam. The second characteristic configuration of the present invention is that the floor structure section is provided with an upper chord side sub-beam that supports the upper chord side floor slab at a position between adjacent upper chord members of the truss beam, and a lower chord side sub-beam that supports the lower chord side floor slab at a position between adjacent lower chord members of the truss beam, The upper chord side small beam is lifted by a number of lifting parts supported by the temporary reinforcement beam on the upper surface side, so that the upper chord side floor slab is supported from above by the temporary reinforcement beam, The lower surface of the lower chord side joist is abutted against the upper ends of numerous support parts supported by the temporary reinforcement beam on the underside, thereby supporting the lower chord side floor slab from below by the temporary reinforcement beam.

[0014] The present invention 3 The characteristic configuration is: A building renovation method for changing the height of a floor structure part to be changed in an existing structure of a building by separating the floor structure part from the existing structure, A temporary reinforcement beam is placed along the cut end of the floor structure to be separated from the existing structure, and the temporary reinforcement beam is connected to a temporary column, and the load on the cut end side of the floor structure is supported by the temporary column via the temporary reinforcement beam, A collective floor height changing process is provided in which the floor structure parts of the plurality of floors, including the columns connecting them to each other, are separated from the existing structure, moved together along a height direction, and re-fixed to the existing structure at the height of the moved part; In the collective floor height changing process, the temporary reinforcement beams are arranged along the respective cut ends of the floor structure parts of the multiple floors that are to be separated from the existing structure, and the temporary reinforcement beams are connected to the temporary columns, and the load on the cut end side of the floor structure parts of the multiple floors is supported by the temporary columns via the temporary reinforcement beams arranged on the multiple floors; The temporary columns are composed of a cross member that receives the load of the existing main girder of the floor structure of each floor at the longitudinal center, and a pair of supports connected to both ends of the cross member of each floor.

[0015] According to this configuration, when the floor structure section to be changed in height is separated from the existing structure to change its height, temporary reinforcement beams are placed along the cut ends of the floor structure section to be separated from the existing structure, and the temporary reinforcement beams are connected to temporary columns, and the load of the floor structure section is supported by the temporary columns via the temporary reinforcement beams.Therefore, the cut ends of the floor structure section are reinforced overall with the temporary reinforcement beams, while the load of the floor structure section can be appropriately supported by the temporary columns via the temporary reinforcement beams. Therefore, when the floor structure section to be changed in height is separated from the existing structure to change its height, bending of the floor slab that constitutes the floor structure section at the cut end of the floor structure section can be suppressed, thereby suppressing damage such as cracks in the floor slab. Furthermore, with this configuration, the load of the floor structure parts on multiple floors can be appropriately supported by temporary columns via temporary reinforcing beams arranged on multiple floors, while a collective height change process can be executed in which the floor structure parts on multiple floors, including the columns connecting them to each other, are separated from the existing structure, moved in the height direction as a whole, and re-fixed to the existing structure at the destination height. This makes it possible to change the height of the floor structure parts on multiple floors at low cost and in a short construction period while suppressing damage such as cracks to the floor slab at the cut ends of the floor structure parts. Furthermore, According to this configuration, the load of the floor structure of each floor can be transmitted to a pair of pillars connected to both ends of the cross member via the cross member of each floor that receives the load of the existing main girder of the floor structure of each floor, and the load of the floor structure of each floor can be supported in a balanced and efficient manner by the pair of pillars during the collective floor height change process. A fourth characteristic configuration of the present invention is that the temporary reinforcing beams are arranged along the outer peripheral edge of the cut end portion on the outer periphery side of the floor structure portion. [Brief description of the drawings]

[0016] [Figure 1] Schematic diagram of the building before the floor height change [Diagram 2] A schematic diagram showing the preparation process for the collective floor height change process. [Diagram 3] A schematic diagram showing the cutting process of the integrated floor height change process [Figure 4] A schematic diagram showing the moving and fixing process of the collective floor height change process [Diagram 5] Schematic diagram of the building after changing the floor height [Figure 6] FIG. 1 is a schematic diagram showing the planar arrangement of the lifting jacks at the lower end of the column to be cut. [Figure 7] FIG. 1 is a schematic diagram showing a method for supporting the cut end of a floor structure. [Figure 8] A schematic diagram showing the connection of the upper chord side small beams to the upper chord side floor slab. [Figure 9] A schematic diagram showing the connection between the lower chord side floor slab and the lower chord side small beam DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0017] An embodiment of a building renovation method according to the present invention will be described with reference to the drawings. Figure 1 shows the building before renovation. This building is constructed as a multi-story building, and includes an existing structure K, including multiple columns 1, multiple floor structural parts (floor parts) 2 supported by the multiple columns 1, and a roof structural part (roof part) 3 supported by the upper ends of the multiple columns 1.

[0018] As column 1, various structures can be used, such as steel frame construction (S construction), reinforced concrete construction (RC construction), steel reinforced concrete construction (SRC construction), concrete filled steel pipe construction (CFT construction), and a composite structure of these.

[0019] The floor structure 2 is composed of a beam structure assembled with girders installed between adjacent columns 1 and small beams installed between adjacent girders, and a floor slab of reinforced concrete or the like supported by the beam structure. The beam structure can also be of various constructions such as steel, reinforced concrete, and steel reinforced concrete.

[0020] In this embodiment, the floor structure section 2 is provided with a truss beam 22 as a main girder, which is configured by assembling a large number of diagonal members 22C between an upper chord member 22A and a lower chord member 22B, and is provided with an upper chord side floor slab 23A supported by the upper chord member 22A of the truss beam 22 and a lower chord side floor slab 23B supported by the lower chord member 22B of the truss beam 22 as a floor slab. In addition, as shown in Fig. 7, as a sub-beam, an upper chord side sub-beam 24A that supports the upper chord side floor slab 23A at a position between the upper chord members 22A of the adjacent truss beams 22, and a lower chord side sub-beam 24B that supports the lower chord side floor slab 23B at a position between the lower chord members 22B of the adjacent truss beams 22 are provided.

[0021] Returning to Fig. 1, the roof structure 3 is composed of a roof beam structure assembled with roof girders installed between adjacent columns 1 and roof girders installed between adjacent roof girders, and a roof slab and metal roof supported by the roof beam structure. The roof beam structure can also be made of various structures such as steel, reinforced concrete, and steel reinforced concrete.

[0022] In this building renovation method, as shown in Figures 2 to 5, floor structure parts 2 of multiple floors as parts located directly below a roof structure part 3 in an existing skeleton K inside a building are set as height change targets. Then, a collective floor height change process is executed in which the floor structure parts 2 of the multiple floors as height change targets are separated from the existing skeleton K, including the columns 1 connecting them to each other, moved downward in the height direction as a whole, and re-fixed to the existing skeleton K at the height of the moved destination, so that the heights of the floor structure parts 2 as height change targets can be changed collectively across multiple floors to a new height lowered from the existing height, as shown in Figure 5.

[0023] Furthermore, in this building renovation method, by executing a collective height change process on a portion of the height change area K1 in the planar view of the existing structure K, a step D (see Figure 5) that can be used for a truck berth, etc., can be formed in a single step across multiple floors between the floor structure part 2 of the height change area K1 in which the collective height change process has been executed and the floor structure part 2 of the other non-height change area K2 in the planar view in which the collective height change process has not been executed.

[0024] Below, we will explain each step of the collective floor height changing process (preparation step, cutting step, moving and fixing step).

[0025] (preparation process) In this preparation process, as shown in Fig. 2, a temporary support structure 5 is constructed to transmit the load of the roof structural part 3 to the columns 1 on both outer sides (hereinafter, sometimes referred to as non-cut columns 12) so as to prevent deformation, etc., of the roof structural part 3 that will remain without changing the height above the floor structural parts 2 of the multiple floors to be changed in the subsequent processes. In this embodiment, the temporary support structure 5 is configured by connecting the upper part of the non-cut column 12 to the part directly above the cutting point of the column to be cut 11, which is the part located below it, with a steel-framed temporary brace 51, and by connecting the parts directly above the cutting points of adjacent columns to be cut 11 with steel-framed temporary cross members 52.

[0026] Also, in order to lower the floor structure 2 in each subsequent process without causing damage, etc., a hydraulic or other lifting jack J1 is installed at the lower end of multiple existing columns 1 (hereinafter, sometimes referred to as columns 11 to be cut) that connect the floor structure 2 of the multiple floors to be changed in height (the third floor in the illustrated example) at the center side in a plan view. Furthermore, a temporary column 4 is provided to support the cut end 21 (see FIG. 3) on the outer periphery of the floor structure 2 of the multiple floors to be changed in height across the multiple floors, and a lifting jack J2 is also installed at the lower end of the temporary column 4.

[0027] Incidentally, as shown in Figures 2 and 6, four lifting jacks J1 on the lower end side of the column to be cut 11 are arranged to surround the column to be cut 11 in plan view via large steel brackets b1 protruding from both the left and right sides of the column to be cut 11 and steel support bases b2 attached to the lower ends of the brackets b1 in an orientation extending in a direction intersecting the left-right direction (front-to-back direction) in plan view. Therefore, by operating and adjusting each of the four lifting jacks J1 in the moving and fixing process described later, it is possible to adjust the erection of the column to be cut 11 after changing the floor height.

[0028] 2 and 7 to 9, a method of supporting the cut end portion 21 (see FIG. 3) on the outer periphery side of the floor structure portion 2 of the multiple floors to be changed in height will be described.

[0029] 2 and 7, temporary steel reinforcement beams 6 are placed along the outer periphery of the cut ends 21 (see FIG. 3) of the floor structure parts 2 of multiple floors that will be separated from the existing frame K in the subsequent cutting process, and the temporary reinforcement beams 6 of each floor are connected to temporary columns 4, so that the load on the cut ends 21 side of the floor structure parts 2 of multiple floors is supported by the temporary columns 4 via the temporary reinforcement beams 6. Therefore, while the cut ends 21 of the floor structure parts 2 are entirely reinforced by the temporary reinforcement beams 6, the load on the cut ends 21 side of the floor structure parts 2 can be appropriately supported by the temporary columns 4 via the temporary reinforcement beams 6. Therefore, in each subsequent process, when the floor structure part 2 to be changed in height is separated from the existing structure K to change its height, bending of the floor slab that constitutes the floor structure part 2 at the cut end part 21 of the floor structure part 2 can be suppressed, thereby suppressing damage such as cracks in the floor slab.

[0030] 7, in this embodiment, temporary reinforcement beams 6 are arranged on both the upper and lower sides of the cut end 21 of the floor structure part 2, and the cut end 21 of the floor structure part 2 is supported from both above and below by the upper temporary reinforcement beam 6A and the lower temporary reinforcement beam 6B. Specifically, the cut end of the upper chord side floor slab 23A is supported from above by the upper temporary reinforcement beam 6A, and the cut end of the lower chord side floor slab 23B is supported from below by the lower temporary reinforcement beam 6B. This configuration makes it possible to properly support the cut end 21 of the floor structure part 2, which includes the truss beam 22, the upper chord side floor slab 23A supported by the upper chord member 22A of the truss beam 22, and the lower chord side floor slab 23B supported by the lower chord member 22B of the truss beam 22. The temporary reinforcement beams 6A and 6B are made of, for example, H-shaped steel.

[0031] As shown in Figures 7 and 8, the upper chord side floor slab 23A is supported from above by the temporary reinforcement beam 6A by lifting the upper chord side sub-beam 24A with a large number of lifting parts 61 (see Figure 8) supported by the temporary reinforcement beam 6A on the upper surface side. The large number of lifting parts 61 are arranged at predetermined intervals in the extension direction of the upper chord side sub-beam 24A (depth direction of the paper).

[0032] The lifting section 61 is configured with a pair of left and right bolt support members 61A made of steel placed on the upper surface of the upper flange of the temporary reinforcement beam 6A in a position extending in the flange width direction (beam width direction of the temporary reinforcement beam 6A), four lifting bolts 61B on the front, rear, left and right whose upper ends are supported at both ends in the extension direction of each bolt support member 61A arranged to protrude from both outer sides of the upper flange of the temporary reinforcement beam 6A, and a pair of front and rear upper chord side sub-beam support members 61C made of steel whose both ends are supported at the lower ends of the pair of left and right lifting bolts 61B in a position extending in the beam width direction of the upper chord side sub-beam 24A. In the illustrated example, the bolt support members 61A and the upper chord side sub-beam support members 61C are configured with angle iron. The lifting portion 61 is configured to lift the upper chord side sub-beam 24A while the upper surface of the middle portion of the extension direction of the upper chord side sub-beam support member 61C is abutted against the lower surface of the lower flange of the upper chord side sub-beam 24A.

[0033] 7 and 9, the lower chord side floor slab 23B is supported from below by the temporary reinforcement beam 6B by abutting the lower surface of the lower chord side sub-beam 24B against the upper ends of numerous support parts 62 (see FIG. 9) supported by the temporary reinforcement beam 6B on the lower surface side. The numerous support parts 62 function as raising parts to adjust the level difference between the lower surface of the lower chord member 22B of the truss beam 22 and the lower surface of the lower chord side sub-beam 24B, and are arranged at predetermined intervals in the extension direction of the upper chord side sub-beam 24A (depth direction of the paper).

[0034] The support section 62 is configured with a support mechanism 62A whose height can be freely adjusted according to the dimension between the upper surface of the temporary reinforcement beam 6B and the lower surface of the lower chord side sub-beam 24B, and a pair of left and right backing plate members 62B made of steel that are installed on the upper surface of the upper flange of the temporary reinforcement beam 6B in a position extending in the flange width direction (beam width direction of the temporary reinforcement beam 6A) and in a state of abutting on both side end faces of the lower flange of the lower chord side sub-beam 24B. In the illustrated example, the pair of left and right backing plate members 62B are made of angle iron and are fixed to the upper flange of the temporary reinforcement beam 6B by temporary clamping fittings 62C.

[0035] The support mechanism 62A is composed of a steel main body 62a placed on the upper surface of the upper flange of the temporary reinforcement beam 6B in a position extending in the flange width direction (beam width direction of the temporary reinforcement beam 6A), and a pair of level adjustment bolts 62b fixed so as to be freely movable up and down with the bolt heads protruding from the upper ends of both ends in the extension direction of the main body 62a. The support mechanism 62A is configured to push up the upper chord side sub-beam 24A from below by adjusting the upward protruding dimension of a pair of level adjustment bolts 62b and abutting the tip surfaces of the bolt heads of the pair of level adjustment bolts 62b against the underside of the lower chord side sub-beam 24B.

[0036] The main body 62a is made of a channel steel having a horizontal plate portion extending in a substantially horizontal position from the upper end of a vertical plate portion in a substantially vertical position, and a reinforcing plate portion 62d in a substantially vertical position is provided at the center of the extending direction. Also, a pair of level adjustment bolts 62b are provided in a state in which they penetrate both ends of the horizontal plate portion of the main body 62a that is arranged to protrude from both outer sides in the beam width direction of the temporary reinforcing beam 6B, and can be moved up and down without being hindered by the temporary reinforcing beam 6B.

[0037] As shown in Fig. 7, the temporary column 4 is composed of a steel-framed horizontal member 41 that receives the load of the truss beam 22 (one example of an existing girder) of the floor structure section 2 of each floor at the center in the longitudinal direction, and a pair of steel-framed supports 42 connected to both ends of the horizontal member 41 of each floor. The horizontal member 41 is provided on each floor having a floor structure section 2 whose height is to be changed, in a state where it abuts against the lower surface of the lower chord member 22B of the truss beam 22. In this embodiment, the horizontal member 41 is configured to double as an erection reinforcement beam 6B as part of the temporary reinforcement beam 6B on the lower surface side. The pair of supports 42 are provided across each floor having a floor structure section 2 whose height is to be changed.

[0038] Further, a steel support base 43 to which the lower ends of the pair of pillars 42 are respectively connected is provided on the lower end side of the temporary pillar 4, and four lifting jacks J2 (one example of a plurality of jacks) are arranged in parallel below the support base 43. Note that, on the lower end side of the temporary pillar 4, a reinforcing body 44 having a brace structure is provided in a region surrounded by the pair of pillars 42, the cross member 41, and the support base 43. By configuring in this manner, the load of the floor structure section 2 on each floor can be transmitted to a pair of pillars 42 connected to both ends of the cross member 41 via the cross member 41 on each floor which receives the load of the truss beams 22 of the floor structure section 2 on each floor, and the load of the floor structure section 2 on each floor can be supported in a balanced and efficient manner by the pair of pillars 42 during the collective floor height changing process.

[0039] (cutting process) In the cutting process which is carried out following the preparation process, as shown in FIG. 3, the load of the floor structure parts 2 of the multiple floors to be changed in height is transferred to each lifting jack J1, J2, while the floor structure parts 2 of the multiple floors are separated from the existing structure K, including the columns 11 to be cut which connect them to each other.

[0040] Specifically, in this cutting process, the cutting point (first cutting point S1) on the lower end of the column to be cut 11 connecting the floor structure sections 2 of the multiple floors to be changed in height, the cutting point (second cutting point S2) on the outer periphery of the floor structure sections 2 of the multiple floors to be changed in height, and the cutting point (third cutting point S3) on the upper end of the column to be cut 11 connecting the floor structure sections 2 of the multiple floors to be changed in height are cut in a state that allows reconnection. At this time, at the first cutting point S1 on the lower end side of the column 11 to be cut, two points above and below with a gap corresponding to the lowering dimension (height change dimension) of the floor structure part 2 are cut to remove the intermediate column part 11a, and a space is formed on the lower end side of the column 11 to be cut to provide a movement allowance for lowering the floor structure part 2. In this manner, the floor structure portion 2 of the multiple stories to be changed in height is separated from the existing framework K so as to be freely lowered.

[0041] Incidentally, the cutting order is preferably the third cutting point S3 at the upper end of the column 11 to be cut, the first cutting point S1 at the lower end of the column 11 to be cut, and the second cutting point S2 at the outer periphery of the floor structure 2 of the floors to be changed in height, in order to keep the behavior of the part to be cut during cutting and the axial force introduced to the lifting jacks J1 and J2 within an expected range. Also, the cutting order of the second cutting points S2 on each floor can be, for example, in the order of the floors from the lower floor side to the upper floor side, in which case the axial force introduced to the lifting jack J2 during cutting can be checked in sequence for each floor to be cut.

[0042] (moving / fixing process) In the moving and fixing process which is carried out following the cutting process, as shown in FIG. 4, a lifting jack J1 installed at the lower end of the column 11 to be cut which connects the central sides of the multi-story floor structure parts 2 to be changed in height, and a lifting jack J2 installed at the lower end of the temporary column 4 which supports the cut end parts 21 of the multi-story floor structure parts 2 are both operated substantially simultaneously, and the multi-story floor structure part 2 is lowered to the target height position while the entire multi-story floor structure part 2 is supported by the lifting jacks J1 and J2.

[0043] Thereafter, as shown in FIG. 5, the uncut columns 12 of the existing structure K are also reconnected (rejoined) by welding or the like at the height after the cut ends 21 of the multi-story floor structure parts 2 are moved. In addition, the cut ends of the first cutting point S1 on the lower end side of the column 11 to be cut, which connects the floor structure sections 2 of multiple floors, are directly reconnected (rejoined) by welding, filling with grout, etc. after the erection of the column 11 to be cut is adjusted using four lifting jacks J1 (see Figure 6). Furthermore, between the cut ends of the second cutting points S2 on the upper end side of the cutting target columns 11 that connect the floor structure parts 2 of multiple floors, intermediate column parts 11b corresponding to the lowering dimension of the floor structure parts 2 are interposed and indirectly rejoined by welding, grout filling, etc. Note that the intermediate column parts 11a removed in the cutting process may be used as the intermediate column parts 11b.

[0044] Then, the temporary materials and equipment such as the temporary columns 4, the temporary support structure 5, and the lifting jacks J1, J2 are removed. In this manner, the height of the floor structure 2 of the existing building T can be changed from the existing height to the new height across multiple floors all at once.

[0045] [Another embodiment] Other embodiments of the present invention will be described below. Note that the configurations of the embodiments described below are not limited to being applied alone, but may also be applied in combination with the configurations of other embodiments.

[0046] (1) In the above-described embodiment, an example was shown in which, in the collective height change process, the floor structure parts 2 of the multiple floors to be changed in height are lowered and then re-fixed to the existing structure K at the height after lowering. However, the floor structure parts 2 of the multiple floors to be changed in height may also be raised and then re-fixed to the existing structure K at the height after raising.

[0047] (2) In the above-described embodiment, an example was shown in which, in the preparation process, temporary reinforcement beams 6 are placed on both the upper and lower sides of the cut end 21 of the multi-story floor structure portion 2, which will be separated from the existing body K in the subsequent cutting process, and the cut end 21 of the floor structure portion 2 is supported from both the top and bottom by the temporary reinforcement beam 6A on the upper side and the temporary reinforcement beam 6B on the lower side. However, it is also possible to place a temporary reinforcement beam 6 on either the upper or lower side of the cut end 21 of the multi-story floor structure portion 2, and support the cut end 21 of the floor structure portion 2 from either the top or bottom by one of the temporary reinforcement beams 6.

[0048] (3) In the above-described embodiment, the temporary column 4 is shown as being composed of a steel cross member 41 that bears the load of the truss beam 22 of the floor structure 2 on each floor at its longitudinal center, and a pair of steel supports 42 connected to both ends of the cross member 41 on each floor. However, the temporary column 4 may be composed of a single support that bears the load of the truss beam 22 of the floor structure 2 on each floor. [Explanation of symbols]

[0049] 1 Pillar 2 Floor structure 21 Cut end 22 Truss beam 22A Upper chord material 22B Lower Chord 23A Upper chord side floor slab 23B Lower chord side floor slab 4 Temporary Pillars 41 Cross member 42 Post 6 Temporary reinforcement beam 6A Temporary reinforcement beam 6B Temporary reinforcement beam K Existing frame

Claims

1. A building renovation method for changing the height of a floor structure part of an existing structure of a building by separating the floor structure part to be changed in height from the existing structure, A temporary reinforcement beam is placed along the cut end of the floor structure to be separated from the existing structure, and the temporary reinforcement beam is connected to a temporary column, and the load on the cut end side of the floor structure is supported by the temporary column via the temporary reinforcement beam, The temporary reinforcement beams are disposed on both the upper and lower sides of the cut end of the floor structure, and the upper and lower temporary reinforcement beams support the load on the cut end side of the floor structure from both the upper and lower sides; The floor structure section includes a truss beam, an upper chord side floor slab supported by an upper chord member of the truss beam, and a lower chord side floor slab supported by a lower chord member of the truss beam, The temporary reinforcement beam arranged on the upper surface side of the cut end of the floor structure supports the load on the cut end side of the upper chord side floor slab from above, A building renovation method in which the temporary reinforcement beam arranged on the underside of the cut end of the floor structure supports the load on the cut end side of the lower chord side floor slab from below.

2. The floor structure section is provided with an upper chord side sub-beam that supports the upper chord side floor slab at a position between adjacent upper chord members of the truss beam, and a lower chord side sub-beam that supports the lower chord side floor slab at a position between adjacent lower chord members of the truss beam, The upper chord side small beam is lifted by a number of lifting parts supported by the temporary reinforcement beam on the upper surface side, so that the upper chord side floor slab is supported from above by the temporary reinforcement beam, A building renovation method as described in claim 1, in which the lower surface of the lower chord side joist is abutted against the upper ends of a number of support parts supported by the temporary reinforcement beam on the lower surface side, thereby supporting the lower chord side floor slab from below by the temporary reinforcement beam.

3. A building renovation method for changing the height of a floor structure part of an existing structure of a building by separating the floor structure part to be changed in height from the existing structure, A temporary reinforcement beam is placed along the cut end of the floor structure to be separated from the existing structure, and the temporary reinforcement beam is connected to a temporary column, and the load on the cut end side of the floor structure is supported by the temporary column via the temporary reinforcement beam, A collective floor height changing process is provided in which the floor structure parts of the plurality of floors, including the columns connecting them to each other, are separated from the existing structure, moved together along a height direction, and re-fixed to the existing structure at the height of the moved part; In the collective floor height changing process, the temporary reinforcement beams are arranged along the respective cut ends of the floor structure parts of the multiple floors that are to be separated from the existing structure, and the temporary reinforcement beams are connected to the temporary columns, and the load on the cut end side of the floor structure parts of the multiple floors is supported by the temporary columns via the temporary reinforcement beams arranged on the multiple floors; A building renovation method in which the temporary columns are constructed from a cross member that supports the load of the existing main girder of the floor structure on each floor at the longitudinal center, and a pair of supports connected to both ends of the cross member on each floor.

4. A building renovation method described in any one of claims 1 to 3, wherein the temporary reinforcement beam is positioned along the outer peripheral edge of the cut end portion on the outer periphery of the floor structure portion.

Citation Information

Patent Citations

  • Method for reconstructing building

    JP2003184319A

  • Building structure, building, and base-isolated building

    JP2011174293A

  • Seismic strengthening method for roof