Incinerator equipment and incinerator equipment startup method

The use of a high-pressure steam reservoir for preheating incinerators and controlled burner activation addresses the inefficiencies and cost issues of conventional startup methods, enhancing durability and reducing fuel consumption.

JP7595106B2Active Publication Date: 2024-12-05KOBELCO ECO SOLUTIONS CO LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
JP2023055343
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2023-03-30
Publication Date
2024-12-05
Estimated Expiration
2043-03-30

AI Technical Summary

Technical Problem

Conventional incinerator equipment startup methods involve rapid heating by burners, which increases costs and reduces the lifespan of furnace refractories.

Method used

A method and system utilizing a high-pressure steam reservoir to preheat incinerators, controlling the temperature increase rate, and activating a burner only when predetermined conditions are met to efficiently and cost-effectively start up the incinerator.

Benefits of technology

This approach extends the lifespan of incinerator refractories by reducing thermal stress, saves fuel costs, and ensures stable startup control by monitoring and adjusting the heating process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007595106000001
    Figure 0007595106000001
  • Figure 0007595106000002
    Figure 0007595106000002
  • Figure 0007595106000003
    Figure 0007595106000003
Patent Text Reader

Abstract

To provide an incinerator facility that has high durability while controlling activation of a halted furnace inexpensively.SOLUTION: An incinerator facility comprises a first treatment system 1A, a second treatment system 1B, a high-pressure steam reservoir 9, and a control unit 8 that controls the operation of the first treatment system 1A and the second treatment system 1B. When either the first treatment system 1A or the second treatment system 1B is in operation and the other of the first treatment system 1A and the second treatment system 1B is stopped, when a target treatment system consisting of the other is operated, the control unit 8 introduces combustion gas having been heat exchanged with the steam supplied from the high-pressure steam reservoir 9 into an incinerator 2 included in the target treatment system to heat it, and when a heating state of the incinerator 2 satisfies a predetermined condition, it operates a burner to heat the incinerator 2.SELECTED DRAWING: Figure 2
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to an incinerator facility equipped with a first treatment system and a second treatment system, and a method for starting up the incinerator facility. [Background technology]

[0002] Conventionally, incinerator facilities equipped with a first treatment system and a second treatment system are known (see, for example, Patent Document 1). The incinerator facility (called a waste treatment facility in the document) described in Patent Document 1 keeps the dust collector insulated during the treatment system shutdown.

[0003] Specifically, the steam generated in the steam receiving section in the first boiler of the first treatment system and the second boiler of the second treatment system is condensed, and the heat of condensation is used to keep the dust collection device in the treatment system warm when it is stopped. [Prior art documents] [Patent documents]

[0004] [Patent Document 1] JP 2015-75299 A Summary of the Invention [Problem to be solved by the invention]

[0005] The incinerator equipment described in Patent Document 1 does not mention start-up control of the incinerator. Normally, incinerator start-up control involves heating the incinerator with a burner, and stopping the burner when the temperature inside the furnace reaches a predetermined temperature (e.g., 500°C) or higher. However, in conventional start-up control, the burner rapidly heats the cooled furnace interior, which can lead to increased costs and shorten the life of the furnace's refractory.

[0006] Therefore, there is a demand for an incinerator system and a method for starting up an incinerator system that can inexpensively perform start-up control of a stopped incinerator while improving durability. [Means for solving the problem]

[0011] One of the characteristic configurations of the incinerator facility according to the present invention is a first treatment system including a first incinerator for burning materials to be incinerated and a first boiler for generating steam using heat of exhaust gas generated by the first incinerator, a second treatment system including a second incinerator for burning materials to be incinerated and a second boiler for generating steam using heat of exhaust gas generated by the second incinerator, a high-pressure steam reservoir for receiving steam generated by the first boiler and the second boiler, and a control unit for controlling the operation of the first treatment system and the second treatment system, When either the first treatment system or the second treatment system is in operation and the other of the first treatment system or the second treatment system is stopped, when a target treatment system consisting of either one of the two is operated, the control unit introduces combustion gas that has exchanged heat with steam supplied from the high-pressure steam reservoir into the incinerator included in the target treatment system to heat it, and when the heated state of the incinerator satisfies a predetermined condition, operates a burner to heat the incinerator, and the predetermined condition is that the internal temperature of the incinerator included in the target treatment system is equal to or higher than a predetermined temperature.

[0012] In this configuration, the large amount of heat contained in the steam supplied from the high-pressure steam reservoir is imparted to the combustion air, so that the incinerator can be efficiently heated when stopped. Also, when the incinerator is operated while stopped, the control unit operates the burner to heat the incinerator when the heating state of the incinerator satisfies a predetermined condition, so that the fuel cost for the burner can be saved. Furthermore, the control unit heats the incinerator while it is stopped by adding the heat contained in the steam supplied from the high-pressure steam reservoir to the combustion air until the incinerator's heating state meets specified conditions, so the temperature rise gradient is gentler than when the incinerator is heated from the beginning with a burner, the load on the incinerator's refractory materials is reduced, and the life of the incinerator can be extended. In this way, the incinerator equipment can be inexpensively started up while having improved durability. Furthermore, as with this configuration, even if the temperature rise rate is equal to or higher than a predetermined value, as long as the temperature inside the furnace is equal to or higher than a predetermined temperature, the temperature gradient will not become steep even if the burner is operated, thereby enabling stable start-up control of the incinerator.

[0013] One of the characteristic configurations of the incinerator facility according to the present invention is a first treatment system including a first incinerator for burning materials to be incinerated and a first boiler for generating steam using heat of exhaust gas generated by the first incinerator, a second treatment system including a second incinerator for burning materials to be incinerated and a second boiler for generating steam using heat of exhaust gas generated by the second incinerator, a high-pressure steam reservoir for receiving steam generated by the first boiler and the second boiler, and a control unit for controlling the operation of the first treatment system and the second treatment system, When one of the first and second treatment systems is in operation and the other of the first and second treatment systems is stopped, when the target treatment system consisting of the other of the first and second treatment systems is operated, the control unit introduces the combustion gas that has exchanged heat with the steam supplied from the high-pressure steam reservoir into the incinerator included in the target treatment system to heat it, and when the heating state of the incinerator satisfies a specified condition, operates a burner to heat the incinerator, and the specified condition is that the temperature rise rate, which is the degree of increase in furnace temperature per unit time in the incinerator included in the target treatment system, becomes less than a specified value.

[0014] In this configuration, the large amount of heat contained in the steam supplied from the high-pressure steam reservoir is imparted to the combustion air, so that the incinerator can be efficiently heated when stopped. Also, when the incinerator is operated while stopped, the control unit operates the burner to heat the incinerator when the heating state of the incinerator satisfies a predetermined condition, so that the fuel cost for the burner can be saved. Furthermore, the control unit heats the incinerator while it is stopped by adding the heat contained in the steam supplied from the high-pressure steam reservoir to the combustion air until the incinerator's heating state meets specified conditions, so the temperature rise gradient is gentler than when the incinerator is heated from the beginning with a burner, the load on the incinerator's refractory materials is reduced, and the life of the incinerator can be extended. In this way, the incinerator equipment can be inexpensively started up while having improved durability. In addition, by monitoring the heating state of the incinerator by the heating rate as in this configuration, the heating state of the incinerator can be accurately grasped. Also, by operating the burner when the heating rate is below a predetermined value, that is, when the heating state reaches a plateau, the fuel cost of the burner can be reduced.

[0015] One of the characteristic configurations of the incinerator facility according to the present invention includes a first treatment system including a first incinerator that burns materials to be incinerated and a first boiler that generates steam using heat of exhaust gas generated by the first incinerator, a second treatment system including a second incinerator that burns materials to be incinerated and a second boiler that generates steam using heat of exhaust gas generated by the second incinerator, a high-pressure steam reservoir that receives the steam generated by the first boiler and the second boiler, and a high-pressure steam reservoir that receives the steam generated by the first boiler and the second boiler. and a control unit that controls the operation of the first and second treatment systems, wherein when one of the first and second treatment systems is in operation and the other of the first and second treatment systems is stopped, when a target treatment system consisting of the other of the first and second treatment systems is operated, the control unit introduces the combustion gas that has been heat exchanged with the steam supplied from the high-pressure steam reservoir into the incinerator included in the target treatment system to heat it, and when the heating state of the incinerator satisfies a predetermined condition, operates a burner to heat the incinerator, The control unit changes the amount of steam supplied from the high-pressure steam reservoir based on the heating state of the incinerator included in the target treatment system.

[0016] In this configuration, the large amount of heat contained in the steam supplied from the high-pressure steam reservoir is imparted to the combustion air, so that the incinerator can be efficiently heated when stopped. Also, when the incinerator is operated while stopped, the control unit operates the burner to heat the incinerator when the heating state of the incinerator satisfies a predetermined condition, so that the fuel cost for the burner can be saved. Furthermore, the control unit heats the incinerator while it is stopped by adding the heat contained in the steam supplied from the high-pressure steam reservoir to the combustion air until the incinerator's heating state meets specified conditions, so the temperature rise gradient is gentler than when the incinerator is heated from the beginning with a burner, the load on the incinerator's refractory materials is reduced, and the life of the incinerator can be extended. In this way, the incinerator equipment can be inexpensively started up while having improved durability. Also, As in this configuration, by changing the amount of steam supplied from the high-pressure steam reservoir based on the heating state of the incinerator, the temperature rise gradient of the incinerator becomes stable and the load on the refractory material of the incinerator is reduced.

[0017] Another characteristic configuration is that the first incinerator and the second incinerator each have a first combustion section and a second combustion section, and the control unit introduces the combustion gas into the first combustion section included in the target treatment system to heat it, and when the specified condition is reached, activates a burner to heat the first combustion section, and introduces the combustion gas into the second combustion section included in the target treatment system to heat it, and when the specified condition is reached, activates a burner to heat the second combustion section.

[0018] With this configuration, even if the incinerator is a fluidized bed type gasification and melting furnace having a gasification fluidized bed furnace (first combustion section) and a melting furnace (second combustion section), or a stoker type incinerator having a first combustion section and a second combustion section, it is possible to increase durability while inexpensively controlling the start-up of both combustion sections.

[0019] Features of the incinerator equipment start-up method according to the present invention One of A start-up method for an incinerator facility including a first treatment system, a second treatment system, and a high-pressure steam reservoir for receiving steam generated in a boiler of the first treatment system and a boiler of the second treatment system, wherein when either one of the first treatment system and the second treatment system is in operation and the other of the first treatment system and the second treatment system is stopped, when a target treatment system consisting of either one of the first treatment system and the second treatment system is operated, combustion gas that has exchanged heat with steam supplied from the high-pressure steam reservoir is introduced into an incinerator included in the target treatment system to be heated, and when the heated state of the incinerator satisfies a predetermined condition, a burner is operated to heat the incinerator. The predetermined condition is that the temperature inside the incinerator included in the target treatment system is equal to or higher than a predetermined temperature. As described above, this method makes it possible to inexpensively perform start-up control of a shut-down furnace while improving its durability. Furthermore, as with this method, even if the temperature rise rate is equal to or higher than a predetermined value, as long as the temperature inside the furnace is equal to or higher than a predetermined temperature, the temperature gradient does not become steep even when the burner is operated, so that stable start-up control of the incinerator can be achieved. One of the features of the start-up method for an incinerator facility according to the present invention is a start-up method for an incinerator facility equipped with a first treatment system, a second treatment system, and a high-pressure steam reservoir that receives steam generated in the boiler of the first treatment system and the boiler of the second treatment system, wherein when either the first treatment system or the second treatment system is in operation and the other of the first treatment system or the second treatment system is stopped, when a target treatment system consisting of either the other is operated, combustion gas that has exchanged heat with steam supplied from the high-pressure steam reservoir is introduced into an incinerator included in the target treatment system to be heated, and when the heating state of the incinerator satisfies a predetermined condition, a burner is operated to heat the incinerator, and the predetermined condition is that the temperature rise rate, which is the degree of increase in furnace temperature per unit time in the incinerator included in the target treatment system, is less than a predetermined value. As described above, this method makes it possible to inexpensively perform start-up control of a shut-down furnace while improving its durability. In addition, by monitoring the heating state of the incinerator by the heating rate as in this method, the heating state of the incinerator can be accurately grasped. Also, by operating the burner when the heating rate is below a predetermined value, that is, when the heating state reaches a plateau, the fuel cost for the burner can be reduced.

[0020] One of the features of the start-up method for an incinerator facility according to the present invention is a start-up method for an incinerator facility equipped with a first treatment system, a second treatment system, and a high-pressure steam reservoir that receives steam generated in the boiler of the first treatment system and the boiler of the second treatment system, wherein when either the first treatment system or the second treatment system is in operation and the other of the first treatment system or the second treatment system is stopped, when a target treatment system consisting of either the other is operated, combustion gas that has exchanged heat with steam supplied from the high-pressure steam reservoir is introduced into an incinerator included in the target treatment system to be heated, and when the heating state of the incinerator satisfies a predetermined condition, a burner is operated to heat the incinerator, and the amount of steam supplied from the high-pressure steam reservoir is changed based on the heating state of the incinerator included in the target treatment system. As described above, this method makes it possible to inexpensively perform start-up control of a shut-down furnace while improving its durability. Furthermore, by changing the amount of steam supplied from the high-pressure steam reservoir based on the heating state of the incinerator, as in this method, the temperature rise gradient of the incinerator becomes stable and the load on the incinerator's refractories is reduced. [Brief description of the drawings]

[0021] [Figure 1] FIG. 1 is a conceptual diagram showing an incinerator facility. [Diagram 2] FIG. 2 is a block diagram showing an incinerator facility. [Diagram 3] FIG. 11 is a block diagram when start-up control is executed. [Figure 4] FIG. 4 is a diagram showing a control flow of a control unit according to the first embodiment. [Diagram 5] FIG. 11 is a diagram showing a control flow of a control unit according to the second embodiment. [Figure 6] FIG. 11 is a diagram showing a control flow of a control unit according to the third embodiment. [Figure 7A] FIG. 13 is a diagram showing a control flow of a control unit according to the fourth embodiment. [Figure 7B] FIG. 13 is a diagram showing a control flow of a control unit according to the fourth embodiment. [Figure 8] FIG. 13 is a diagram showing a control flow of a control unit according to the fifth embodiment. [Figure 9] FIG. 1 is a comparative diagram showing the internal temperature of an incinerator at start-up. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0022] Hereinafter, an embodiment of an incinerator facility and a method for starting up an incinerator facility according to the present invention will be described with reference to the drawings. In this embodiment, a fluidized bed gasification and melting furnace will be described as an example of an incinerator 2 provided in an incinerator facility 1. However, the embodiment is not limited to the following embodiment, and various modifications are possible within the scope of the gist of the embodiment.

[0023] [Basic configuration of incinerator] As shown in FIG. 1, the incinerator equipment 1 includes at least an incinerator 2 including a hopper 2a and a dust feeder 2b, a boiler 3 including a water supply device 31, a control unit 8, and a high-pressure steam reservoir 9. The incinerator equipment 1 also includes a steam turbine generator 30, a gas cooler 4, a bag filter 5, a denitrification device 6, and a chimney 7. The incinerator 2 in this embodiment is composed of a fluidized bed furnace 21 (an example of a first combustion unit) and a melting furnace 22 (an example of a second combustion unit). The control unit 8 includes a program stored in hardware such as a HDD or memory as software for controlling the operation of the incinerator equipment 1, and is executed by a processor including an ASIC, FPGA, CPU, or other hardware of a computer.

[0024] The fluidized bed furnace 21 includes a sand layer 10 mainly composed of silica sand, and a blower 11 for forcing air into the sand layer 10. The blower 11 is provided below the sand layer 10 and supplies air to the sand layer 10 from below. During normal operation, the blower 11 sends air (forced air, an example of combustion gas) to the sand layer 10 using a forced air blower and a blowing nozzle (neither of which are shown), and when the incinerator 2 is started up, the air introduced from the forced air blower is sent to the sand layer 10 as heated air (forced air, an example of combustion gas) that has been heated by the forced air preheater Hp. The sand layer 10 is provided in the lower region of the fluidized bed furnace 21, and is heated to about 450°C to about 600°C to incinerate waste D (an example of an incineration target) that has been placed on the sand layer 10. The waste D is temporarily stored in the hopper 2a, and is transported into the fluidized bed furnace 21 through the dust feeder 2b. A secondary air blower (not shown) blows air (secondary air, an example of combustion gas) from the central region to the upper region of the fluidized bed furnace 21, and the waste D is gasified to generate pyrolysis gas. The fluidized bed furnace 21 is provided with an outlet 16 that can discharge sand from the sand layer 10 to the outside when the operation is stopped. In this embodiment, the waste D is composed of garbage, but it may also be composed of sludge, rice husks, wood chips, etc. When the incinerator 2 is started up, the air introduced from the secondary air blower may be blown from the central region to the upper region of the fluidized bed furnace 21 as heated air (secondary air, an example of combustion gas) heated by the secondary air preheater Hs.

[0025] The fluidized bed furnace 21 is provided with a first temperature measuring unit T1, which is composed of a thermocouple or the like, in its lower region. The first temperature measuring unit T1 can measure the temperature of the sand layer 10 while the incinerator 2 is in operation, and can measure the furnace temperature in the lower region of the fluidized bed furnace 21 while the incinerator 2 is stopped. In addition, a start-up burner B (an example of a burner) is provided in the central region of the fluidized bed furnace 21 to increase the furnace temperature of the fluidized bed furnace 21 while the incinerator 2 is stopped.

[0026] The melting furnace 22 is connected to the downstream side of the fluidized bed furnace 21 via a communication passage 12, and is a furnace that performs high-temperature combustion at about 1200°C to 1300°C by a swirling flow. A second temperature measuring section T2 composed of a known temperature sensor or the like is provided in the communication passage 12. The second temperature measuring section T2 can measure the furnace temperature in the upper region of the fluidized bed furnace 21. A third temperature measuring section T3 composed of a known temperature sensor or the like is provided in the upper part of the melting furnace 22. The third temperature measuring section T3 can measure the furnace temperature of the melting furnace 22. In this melting furnace 22, the pyrolysis gas introduced from the fluidized bed furnace 21 is burned, and the ash contained in the pyrolysis gas is melted to generate slag. An auxiliary burner (not shown) is attached to the top 13 of the melting furnace 22, and is ignited as necessary to assist the combustion of the pyrolysis gas. Air (secondary air, an example of combustion gas) is sent into this melting furnace 22 by a secondary air blower (not shown). In addition, a slag outlet 14 is provided at the bottom of the melting furnace 22, and the generated slag is discharged through the slag outlet 14. In this embodiment, when the incinerator 2 is started up, air introduced from the secondary air blower is sent into the melting furnace 22 as heated air (secondary air, an example of combustion gas) heated by the secondary air preheater Hs.

[0027] In the boiler 3, secondary combustion is carried out downstream of the melting furnace 22, and the exhaust gas generated by this secondary combustion is introduced. In the secondary combustion, unburned materials in the exhaust gas from the melting furnace 22 are completely combusted. The boiler 3 generates steam by utilizing the heat of the exhaust gas generated by the secondary combustion. Water is supplied to the boiler 3 from a water supply device 31, and steam is generated by heat exchange with the exhaust gas. The gas from which waste heat has been recovered in the boiler 3 is cooled in a gas cooler 4, has dust removed in a bag filter 5, passes through a denitration device 6, and is discharged to the outside of the system from a chimney 7.

[0028] The steam turbine generator 30 is supplied with steam generated by the boiler 3, and generates electricity by rotating a turbine with the steam. The operating conditions of the incinerator 2 are set so that the amount of steam supplied to the steam turbine generator 30 does not fall below a predetermined amount of steam, and high-pressure steam is generated in the boiler 3. On the other hand, when an excess of high-pressure steam is generated and exceeds the predetermined amount of steam, the steam is not supplied to the steam turbine generator 30, but is sent to a condenser (not shown) by opening the on-off valve 25. The water supply device 31 includes a condenser 31a that cools and condenses the low-pressure wet steam discharged from the outlet of the turbine of the steam turbine generator 30 to return it to saturated water, a condensate tank 31b that stores the saturated water, and a deaerator 31c that performs a deaerating process on the saturated water returned from the condenser to the boiler 3 by the feedwater pump P (see also FIG. 2).

[0029] The boiler 3 generates high-pressure steam by boiling water supplied to the boiler 3 from the water supply device 31 using thermal energy of the exhaust gas generated in the fluidized bed furnace 21. The generated high-pressure steam is temporarily stored in the high-pressure steam reservoir 9 before being supplied to the steam turbine generator 30. The high-pressure steam is introduced from the high-pressure steam reservoir 9 to the turbine of the steam turbine generator 30, and generates power and reduces the pressure by driving the turbine. Then, a part of the steam is extracted from the middle stage of the turbine and stored in the low-pressure steam reservoir 32 as low-pressure steam. The low-pressure steam stored in the low-pressure steam reservoir 32 is introduced into the deaerator 31c and used for deaeration processing, etc. The pressure of the high-pressure steam is 2 to 6 MPa in gauge pressure, the pressure of the low-pressure wet steam discharged from the turbine outlet is -95 to -70 KPa in gauge pressure, and the pressure of the low-pressure steam extracted from the middle stage of the turbine is 0.6 to 1.2 MPa in gauge pressure. By extracting low pressure steam in this way, it is possible to improve the energy recovery efficiency compared to the case where the high pressure steam is simply cooled and reduced in pressure. The low pressure steam reservoir 32 may be omitted.

[0030] [Outline of incinerator equipment] As shown in Fig. 2, the incinerator facility 1 includes a first treatment system 1A, a second treatment system 1B, a control unit 8, and a high-pressure steam reservoir 9. Hereinafter, the terms "first treatment system 1A" and "second treatment system 1B" each mean one or two or more treatment systems.

[0031] The first treatment system 1A includes a first incinerator 2 (hereinafter referred to as "first incinerator 2A") including a first startup burner B1, a first boiler 3 (hereinafter referred to as "first boiler 3A"), a first forced air preheater Hp (hereinafter referred to as "first forced air preheater Hp1") to which air is supplied from a first forced air blower Aa1, and a first steam damper V located between the high-pressure steam reservoir 9 and the first forced air preheater Hp1. p (hereinafter referred to as "first steam damper Vp1"), a first secondary air preheater Hs (hereinafter referred to as "first secondary air preheater Hs1") to which air is supplied from a first secondary air blower Ab1, a first steam damper Vs (hereinafter referred to as "first steam damper Vs1") located between the high-pressure steam reservoir 9 and the first secondary air preheater Hs1, and a first feed water pump P (hereinafter referred to as "first feed water pump Pa"). The first incinerator 2A is provided with a first temperature measuring unit Ta consisting of the above-mentioned first temperature measuring unit T1 to third temperature measuring unit T3.

[0032] The second treatment system 1B includes a second incinerator 2 (hereinafter referred to as the "second incinerator 2B") including a second startup burner B2, a second boiler 3 (hereinafter referred to as the "second boiler 3B"), a second forced air preheater Hp (hereinafter referred to as the "second forced air preheater Hp2") to which air is supplied from a second forced air blower Aa2, and a second steam damper V located between the high-pressure steam reservoir 9 and the second forced air preheater Hp2. p (hereinafter referred to as "second steam damper Vp2"), a second secondary air preheater Hs (hereinafter referred to as "second secondary air preheater Hs2") to which air is supplied from the second secondary air blower Ab2, a second steam damper Vs (hereinafter referred to as "second steam damper Vs2") located between the high-pressure steam reservoir 9 and the second secondary air preheater Hs2, and a second feed water pump P (hereinafter referred to as "second feed water pump Pb"). The second incinerator 2B is provided with a second temperature measuring unit Tb consisting of the above-mentioned first temperature measuring unit T1 to third temperature measuring unit T3.

[0033] The forced air preheater Hp and the secondary air preheater Hs are not particularly limited as long as they can generate high-temperature air by heat exchange between high-pressure steam and air. For example, a fin tube type heat exchanger, a bore tube type heat exchanger, a plate type heat exchanger, etc. can be mentioned. In the incinerator equipment 1 in this embodiment, the high-pressure steam reservoir 9, the steam turbine generator 30, the condenser 31a, the condensate tank 31b, the deaerator 31c, and the low-pressure steam reservoir 32 are shared in the first treatment system 1A and the second treatment system 1B. Note that the high-pressure steam reservoir 9, the steam turbine generator 30, the condenser 31a, the condensate tank 31b, the deaerator 31c, and the low-pressure steam reservoir 32 may be provided separately in the first treatment system 1A and the second treatment system 1B.

[0034] 3 shows a block diagram of start-up control when a target processing system consisting of either the first processing system 1A or the second processing system 1B (hereinafter, the operating processing system will be referred to as the "first processing system 1A") is operating and the other of the first processing system 1A or the second processing system 1B (hereinafter, the stopped processing system will be referred to as the "second processing system 1B") is stopped, and the target processing system consisting of either the stopped processing system (hereinafter, the target processing system will be referred to as the "second processing system 1B") is stopped. Here, "target processing system consisting of either the stopped processing system" refers to the stopped processing system if there is one stopped processing system, and refers to one stopped processing system or any number of stopped processing systems greater than or equal to two if there are two or more stopped processing systems. Since the first treatment system 1A is in operation, the water supplied from the water supply device 31 to the first boiler 3A is boiled and then high-pressure steam is generated. This high-pressure steam is temporarily stored in the high-pressure steam reservoir 9 and introduced into the turbine of the steam turbine generator 30, where it drives the turbine to generate power (see also Figure 2).

[0035] On the other hand, since the second treatment system 1B is stopped, the sand in the sand layer 10 of the fluidized bed furnace 21 of the second incinerator 2B is discharged to the outside through the discharge port 16 (see also FIG. 1). The control unit 8 executes start-up control when the second treatment system 1B is restarted. When the control unit 8 operates the second incinerator 2B, it operates the second forced air blower Aa2 and the second secondary air blower Ab2 to circulate the combustion gas (forced air and secondary air) to the second forced air preheater Hp2 and the second secondary air preheater Hs2. Then, the second steam dampers Vp2 and Vs2 are opened to circulate the high-pressure steam from the high-pressure steam reservoir 9 to the second forced air preheater Hp2 and the second secondary air preheater Hs2, and the combustion gas that has exchanged heat with the high-pressure steam is introduced into the second incinerator 2B included in the second treatment system 1B to be heated. At this time, the high-pressure steam that has exchanged heat with the combustion gas is introduced into the deaerator 31c. Next, when the heating state of the second incinerator 2B satisfies a predetermined condition (sometimes referred to as "when the temperature rise limit is reached"), the control unit 8 operates the second startup burner B2 to heat the second incinerator 2B (see also FIG. 2).

[0036] In this embodiment, the large amount of heat held by the high-pressure steam in the high-pressure steam reservoir 9 is given to the combustion air, so that the second incinerator 2B can be efficiently heated during shutdown. In addition, when the second incinerator 2B is operated during shutdown, the control unit 8 activates the second startup burner B2 to heat the second incinerator 2B when the temperature rise limit of the second incinerator 2B is reached, so that the fuel cost of the second startup burner B2 can be saved. Moreover, the control unit 8 gives the amount of heat held by the high-pressure steam in the high-pressure steam reservoir 9 to the combustion air until the temperature rise limit is reached to heat the second incinerator 2B during shutdown, so that, as shown in FIG. 9, the temperature rise gradient is gentler (solid line in FIG. 9) than when the second startup burner B2 is used to heat the second incinerator 2B from the beginning (broken line in FIG. 9), and the load on the refractory material of the second incinerator 2B is reduced, so that the life of the second incinerator 2B can be extended.

[0037] The start-up control of the second incinerator 2B as the stopped treatment system will be described in detail below, but the start-up control of the first incinerator 2A is similar.

[0038] [Start-up control according to the first embodiment] Fig. 4 shows a start-up control flow of the incinerator 2 according to the first embodiment (start-up method of the incinerator facility 1). The air preheater shown in Fig. 4 is the second forced air preheater Hp2 or the second secondary air preheater Hs2 used for start-up control of at least one of the fluidized bed furnace 21 and the melting furnace 22 of the second incinerator 2B. Hereinafter, the start-up control of igniting the second startup burner B2 after operating the second forced air preheater Hp2 to preheat the fluidized bed furnace 21 of the second incinerator 2B will be described.

[0039] When the first treatment system 1A is in operation and the second treatment system 1B is stopped, the control unit 8 operates the second incinerator 2B of the second treatment system 1B by introducing the heated air that has been heat exchanged with the high-pressure steam in the high-pressure steam reservoir 9 into the fluidized bed furnace 21 of the second incinerator 2B to heat it, and when the heated state of the fluidized bed furnace 21 reaches a state where a predetermined condition is satisfied, the control unit 8 operates the second startup burner B2 to heat the fluidized bed furnace 21. The predetermined condition is that the temperature rise rate (°C / h), which is the degree of rise in the furnace temperature per unit time in the fluidized bed furnace 21 of the second incinerator 2B, becomes less than a predetermined value (reference temperature rise rate X1 (°C / h)) (temperature rise limit). Here, the standard temperature rise rate X1 (℃ / h) is a value that is set in advance for each incinerator facility 1 through trial operation or the like, and is, for example, 20 (℃ / h) to 70 (℃ / h), preferably 40 (℃ / h) to 60 (℃ / h).

[0040] As shown in FIG. 3, since the first treatment system 1A is in operation, water supplied from the deaerator 31c of the water supply device 31 to the first boiler 3A by the first feedwater pump Pa is boiled, and then high-pressure steam is generated, which is temporarily stored in the high-pressure steam reservoir 9 and introduced into the turbine of the steam turbine generator 30 to drive the turbine to generate power (see also FIG. 2). Then, when the control unit 8 operates the second forced air blower Aa2, it operates the second steam damper Vp2 at a predetermined opening (for example, 10 to 50% of full opening) to allow the high-pressure steam from the high-pressure steam reservoir 9 to flow into the second forced air preheater Hp2, and the forced air that has exchanged heat with the high-pressure steam is introduced into the fluidized bed furnace 21 of the second incinerator 2B to be heated (#41 in FIG. 4, operation of the air preheater). Since the second incinerator 2B was stopped, there was no sand in the sand layer 10, and the temperature measured by the first temperature measuring part T1 corresponds to the temperature inside the fluidized bed furnace 21.

[0041] Next, the control unit 8 calculates the temperature rise rate (°C / h), which is the degree of increase in the temperature inside the fluidized bed furnace 21 per unit time, based on the measurement value of the first temperature measurement unit T1 or the second temperature measurement unit T2 and the elapsed time, and determines whether this temperature rise rate (°C / h) is equal to or greater than the reference temperature rise rate X1 (°C / h) (#42 in FIG. 4). At this time, the control unit 8 adjusts the opening degree of the second steam damper Vp2 so that the temperature rise rate (°C / h) is equal to or greater than the reference temperature rise rate X1 (°C / h) and is close to the reference temperature rise rate X1 (°C / h). If the temperature rise rate (°C / h) is equal to or greater than the reference temperature rise rate X1 (°C / h) (#42 Yes in FIG. 4), the control unit 8 continues as is, and if the temperature rise rate (°C / h) is less than the reference temperature rise rate X1 (°C / h) (#42 No in FIG. 4), it determines whether the opening of the second steam damper Vp2 is fully open (#43 in FIG. 4). If the opening of the second steam damper Vp2 is not fully open (#43 No in FIG. 4), the opening of the second steam damper Vp2 is increased to increase the amount of steam supplied to the second forced air preheater Hp2 (#44 in FIG. 4). In other words, the control unit 8 changes the amount of high-pressure steam supplied from the high-pressure steam reservoir 9 based on the heating state of the second incinerator 2B.

[0042] The control unit 8 repeats steps #42 to #44 until the second steam damper Vp2 is fully opened. If the temperature rise rate (°C / h) is less than the reference temperature rise rate X1 (°C / h) (temperature rise limit) even when the second steam damper Vp2 is fully opened (No in #42, Yes in #43 in FIG. 4), the control unit 8 ignites the second startup burner B2 to heat the fluidized bed furnace 21 (#45 in FIG. 4). Although not shown, sand is charged into the sand layer 10 while the second startup burner B2 is ignited and the fluidized bed furnace 21 is being heated. Then, when the temperature inside the fluidized bed furnace 21 reaches the preheating completion temperature (for example, 500°C), waste D is charged into the fluidized bed furnace 21, the second startup burner B2 is stopped, and the second treatment system 1B is put into full operation.

[0043] In this way, the control unit 8 heats the stopped second incinerator 2B by giving the large amount of heat held by the high-pressure steam in the high-pressure steam reservoir 9 to the forced air until the temperature rise limit where the temperature rise rate (℃ / h) becomes the reference temperature rise rate X1 (℃ / h), so that, as shown in FIG. 9, the temperature rise gradient becomes gentler (solid line in FIG. 9) than when the second startup burner B2 is used for heating from the beginning (broken line in FIG. 9: maintained at Qth until Tth). If the second startup burner B2 is ignited when the temperature rise gradient reaches a plateau (temperature rise limit), the temperature inside the furnace rises at roughly the reference temperature rise rate X1, so that the preheating of the fluidized bed furnace 21 of the second incinerator 2B can be performed efficiently. In addition, if the temperature rise limit is monitored by the temperature rise rate, the temperature rise of the second incinerator 2B can be accurately grasped. Furthermore, by operating the second startup burner B2 when the heating rate is less than the standard heating rate X1, i.e., when the heating level reaches a plateau, the fuel costs for the second startup burner B2 can be saved compared to using the second startup burner B2 to heat the gas from the beginning.

[0044] [Start-up control according to the second embodiment] Fig. 5 shows a start-up control flow of the incinerator 2 according to the second embodiment (start-up method of the incinerator facility 1). The air preheater shown in Fig. 5 is the second forced air preheater Hp2 or the second secondary air preheater Hs2 used for start-up control of at least one of the fluidized bed furnace 21 and the melting furnace 22 of the second incinerator 2B. Hereinafter, the start-up control for igniting the second startup burner B2 after operating the second forced air preheater Hp2 to preheat the fluidized bed furnace 21 of the second incinerator 2B will be described.

[0045] When the first treatment system 1A is in operation and the second treatment system 1B is stopped, the control unit 8 operates the second incinerator 2B of the second treatment system 1B by introducing the heated air that has been heat exchanged with the high-pressure steam in the high-pressure steam reservoir 9 into the fluidized bed furnace 21 of the second incinerator 2B to heat it, and when the heating state of the fluidized bed furnace 21 satisfies a predetermined condition, the control unit 8 operates the second startup burner B2 to heat the fluidized bed furnace 21. There are two patterns for this predetermined condition. The first pattern is that the furnace temperature (°C) of the second incinerator 2B is equal to or higher than a predetermined temperature (reference furnace temperature Y2 (°C)). The second pattern is that when the furnace temperature (°C) of the second incinerator 2B is less than a predetermined temperature (reference furnace temperature Y2 (°C)), the temperature rise rate (°C / h), which is the degree of increase in the furnace temperature per unit time in the fluidized bed furnace 21 of the second incinerator 2B, becomes less than a predetermined value (reference temperature rise rate X2 (°C / h)) (temperature rise limit). Here, the reference furnace temperature Y2 (°C) and the reference temperature rise rate X2 (°C / h) are values ​​that are set in advance by trial operation or the like for each incinerator facility 1. For example, the reference furnace temperature Y2 (°C) is 50 (°C) to 250 (°C), preferably 80 (°C) to 150 (°C), and the reference temperature rise rate X2 (°C / h) is 20 (°C / h) to 70 (°C / h), preferably 40 (°C / h) to 60 (°C / h).

[0046] As shown in FIG. 3, since the first treatment system 1A is in operation, water supplied from the water supply device 31 to the first boiler 3A is boiled to generate high-pressure steam, which is temporarily stored in the high-pressure steam reservoir 9 and introduced into the turbine of the steam turbine generator 30 to drive the turbine to generate power (see also FIG. 2). When the control unit 8 operates the second incinerator 2B, it operates the second forced air blower Aa2 to circulate the forced air to the second forced air preheater Hp2. Next, it opens the second steam damper Vp2 at a predetermined opening (for example, 10 to 50% of full opening) to circulate the high-pressure steam from the high-pressure steam reservoir 9 to the second forced air preheater Hp2, and introduces the forced air that has exchanged heat with the high-pressure steam into the fluidized bed furnace 21 of the second incinerator 2B to heat it (#51 in FIG. 5, operation of the air preheater). Since the second incinerator 2B was stopped, there was no sand in the sand layer 10, and the temperature measured by the first temperature measuring part T1 corresponds to the temperature inside the fluidized bed furnace 21.

[0047] Next, the control unit 8 determines whether the furnace temperature (°C) of the fluidized bed furnace 21 is equal to or higher than the reference furnace temperature Y2 (°C) based on the measurement value of the first temperature measurement unit T1 or the second temperature measurement unit T2 (#52 in FIG. 5). If the furnace temperature (°C) is equal to or higher than the reference furnace temperature Y2 (°C) (#52 Yes in FIG. 5), the control unit 8 ignites the second startup burner B2 to heat the fluidized bed furnace 21 (#56 in FIG. 5).

[0048] On the other hand, if the furnace temperature (°C) is less than the reference furnace temperature Y2 (°C) (#52 No in FIG. 5), the control unit 8 calculates the temperature rise rate (°C / h), which is the degree of increase in the furnace temperature per unit time in the fluidized bed furnace 21, based on the measurement value of the first temperature measurement unit T1 or the second temperature measurement unit T2 and the elapsed time, and judges whether this temperature rise rate (°C / h) is equal to or greater than the reference temperature rise rate X2 (°C / h) (#53 in FIG. 5). At this time, the control unit 8 adjusts the opening degree of the second steam damper Vp2 so that the temperature rise rate (°C / h) is equal to or greater than the reference temperature rise rate X2 (°C / h) and is close to the reference temperature rise rate X2 (°C / h). If the temperature rise rate (°C / h) is equal to or greater than the reference temperature rise rate X2 (°C / h) (#53 Yes in FIG. 5), the control unit 8 continues this until the furnace temperature (°C) becomes equal to or greater than the reference furnace temperature Y2 (°C). On the other hand, if the temperature rise rate (°C / h) is less than the reference temperature rise rate X2 (°C / h) (temperature rise limit) (#53 No in FIG. 5), the control unit 8 judges whether the opening of the second steam damper Vp2 is fully open or not (#54 in FIG. 5). If the opening of the second steam damper Vp2 is not fully open (#54 No in FIG. 5), the opening of the second steam damper Vp2 is increased to increase the amount of steam supplied to the second forced air preheater Hp2 (#55 in FIG. 5). In other words, the control unit 8 changes the amount of high-pressure steam supplied from the high-pressure steam reservoir 9 based on the heating state of the second incinerator 2B.

[0049] The control unit 8 repeats steps #52 to #55 until the second steam damper Vp2 is fully opened. Even if the temperature inside the furnace (°C) is less than the reference temperature inside the furnace Y2 (°C) and the opening of the second steam damper Vp2 is fully opened, if the temperature rise rate (°C / h) is less than the reference temperature rise rate X2 (°C / h) (temperature rise limit) (No in #52, No in #53, Yes in #54 in FIG. 5), the control unit 8 ignites the second startup burner B2 to heat the fluidized bed furnace 21 (#56 in FIG. 5). Although not shown, sand is charged into the sand layer 10 while the second startup burner B2 is ignited and the fluidized bed furnace 21 is being heated. Then, when the temperature inside the fluidized bed furnace 21 reaches the preheating completion temperature (for example, 500°C), waste D is charged into the fluidized bed furnace 21, the second startup burner B2 is stopped, and the second treatment system 1B is put into full operation.

[0050] In this way, when the in-furnace temperature (°C) of the second incinerator 2B is less than a predetermined temperature (reference in-furnace temperature Y2 (°C)), the control unit 8 heats the stopped second incinerator 2B by giving the large amount of heat held by the high-pressure steam in the high-pressure steam reservoir 9 to the forced air up to the temperature rise limit where the temperature rise rate (°C / h) becomes the reference temperature rise rate X2 (°C / h), so that, as shown in Fig. 9, the temperature rise gradient becomes gentler (solid line in Fig. 9) than when the second startup burner B2 is used for heating from the beginning (broken line in Fig. 9: held at Qth until Tth). If the second startup burner B2 is ignited when the temperature rise gradient reaches a plateau, the in-furnace temperature rises at roughly the reference temperature rise rate X2, so that the fluidized bed furnace 21 of the second incinerator 2B can be preheated efficiently. In addition, if the furnace temperature (℃) of the second incinerator 2B is equal to or higher than the reference furnace temperature Y2 (℃), the temperature gradient will not become steep even if the second startup burner B2 is operated, so stable startup control of the second incinerator 2B can be realized. Also, by monitoring the temperature rise limit with the furnace temperature and the temperature rise rate, it is possible to accurately grasp the heating level of the second incinerator 2B, and more accurate startup control can be realized. Furthermore, by operating the second startup burner B2 when the heating rate is less than the reference heating rate X2, that is, when the heating level has plateaued, the fuel cost of the second startup burner B2 can be saved compared to when the second startup burner B2 is used to heat the furnace from the beginning.

[0051] [Start-up control according to the third embodiment] Fig. 6 shows a start-up control flow of the incinerator 2 according to the third embodiment (start-up method of the incinerator facility 1). The air preheater shown in Fig. 6 is the second forced air preheater Hp2 or the second secondary air preheater Hs2 used for start-up control of at least one of the fluidized bed furnace 21 and the melting furnace 22 of the second incinerator 2B. Hereinafter, the start-up control of igniting the second startup burner B2 after operating the second forced air preheater Hp2 to preheat the fluidized bed furnace 21 of the second incinerator 2B will be described.

[0052] When the first treatment system 1A is in operation and the second treatment system 1B is stopped, the control unit 8 operates the second incinerator 2B of the second treatment system 1B by introducing the heated air that has been heat exchanged with the high-pressure steam in the high-pressure steam reservoir 9 into the fluidized bed furnace 21 of the second incinerator 2B to heat it, and when the heating state of the fluidized bed furnace 21 satisfies a predetermined condition, the control unit 8 operates the second startup burner B2 to heat the fluidized bed furnace 21. There are two patterns for this predetermined condition. The first pattern is that the temperature rise rate (°C / h), which is the degree of rise in the furnace temperature per unit time in the fluidized bed furnace 21 of the second incinerator 2B, is less than a predetermined value (reference temperature rise rate X3 (°C / h)) (temperature rise limit) (the same condition as the first embodiment). The second pattern is that when the temperature rise rate (°C / h), which is the degree of rise in the furnace temperature per unit time in the fluidized bed furnace 21 of the second incinerator 2B, is less than a predetermined value (reference temperature rise rate X3 (°C / h)) (temperature rise limit), the furnace temperature (°C) of the second incinerator 2B becomes equal to or higher than a predetermined temperature (reference furnace temperature Y3 (°C)). Here, the reference furnace temperature Y3 (°C) and the reference temperature rise rate X3 (°C / h) are values ​​that are set in advance by a trial run or the like for each incinerator facility 1. For example, the reference furnace temperature Y3 (°C) is 50 (°C) to 250 (°C), preferably 80 (°C) to 150 (°C), and the reference temperature rise rate X3 (°C / h) is 20 (°C / h) to 70 (°C / h), preferably 40 (°C / h) to 60 (°C / h).

[0053] As shown in FIG. 3, since the first treatment system 1A is in operation, water supplied from the water supply device 31 to the first boiler 3A is boiled to generate high-pressure steam, which is temporarily stored in the high-pressure steam reservoir 9 and introduced into the turbine of the steam turbine generator 30 to drive the turbine to generate power (see also FIG. 2). When the control unit 8 operates the second incinerator 2B, it operates the second forced air blower Aa2 to circulate the forced air to the second forced air preheater Hp2. Next, it opens the second steam damper Vp2 at a predetermined opening (for example, 10 to 50% of full opening) to circulate the high-pressure steam from the high-pressure steam reservoir 9 to the second forced air preheater Hp2, and introduces the forced air that has exchanged heat with the high-pressure steam into the fluidized bed furnace 21 of the second incinerator 2B to heat it (#61 in FIG. 6, operation of the air preheater). Since the second incinerator 2B was stopped, there was no sand in the sand layer 10, and the temperature measured by the first temperature measuring part T1 corresponds to the temperature inside the fluidized bed furnace 21.

[0054] Next, the control unit 8 calculates the temperature rise rate (°C / h), which is the degree of increase in the temperature inside the fluidized bed furnace 21 per unit time, based on the measurement value of the first temperature measurement unit T1 or the second temperature measurement unit T2 and the elapsed time, and determines whether this temperature rise rate (°C / h) is equal to or greater than the reference temperature rise rate X3 (°C / h) (#62 in FIG. 6). At this time, the control unit 8 adjusts the opening degree of the second steam damper Vp2 so that the temperature rise rate (°C / h) is equal to or greater than the reference temperature rise rate X3 (°C / h) and is close to the reference temperature rise rate X3 (°C / h). If the temperature rise rate (°C / h) is equal to or higher than the reference temperature rise rate X3 (°C / h) (#62 Yes in FIG. 6), the control unit 8 continues as is, and if the temperature rise rate (°C / h) is less than the reference temperature rise rate X3 (°C / h) (#62 No in FIG. 6), it judges whether the in-furnace temperature (°C) of the second incinerator 2B is equal to or higher than the reference in-furnace temperature Y3 (°C) (#63 in FIG. 6). If the in-furnace temperature (°C) of the second incinerator 2B is equal to or higher than the reference in-furnace temperature Y3 (°C) (#63 Yes in FIG. 6), it ignites the second startup burner B2 to heat the fluidized bed furnace 21 (#66 in FIG. 6). Although not shown, sand is added to the sand layer 10 while the second startup burner B2 is ignited and the fluidized bed furnace 21 is being heated. Then, when the temperature inside the fluidized bed furnace 21 reaches the preheating completion temperature (for example, 500° C.), the waste D is charged into the fluidized bed furnace 21, the second startup burner B2 is stopped, and the second treatment system 1B is put into full operation.

[0055] As a result of the judgment in #63, if the in-furnace temperature (°C) of the second incinerator 2B is less than the reference in-furnace temperature Y3 (°C) (#63 No in FIG. 6), it is judged whether the opening degree of the second steam damper Vp2 is fully open or not (#64 in FIG. 6). If the opening degree of the second steam damper Vp2 is not fully open (#64 No in FIG. 6), the opening degree of the second steam damper Vp2 is increased to increase the amount of steam supplied to the second forced air preheater Hp2 (#65 in FIG. 6). In other words, the control unit 8 changes the amount of high-pressure steam supplied from the high-pressure steam reservoir 9 based on the heating state of the second incinerator 2B.

[0056] The control unit 8 repeats steps #62 to #65 until the second steam damper Vp2 is fully open, and if the temperature rise rate (℃ / h) is less than the standard temperature rise rate X3 (℃ / h) (temperature rise limit) even when the second steam damper Vp2 is fully open and the furnace temperature (℃) of the second incinerator 2B is less than the standard furnace temperature Y3 (℃) (#62 No, #63 No, #64 Yes in Figure 6), it ignites the second startup burner B2 to heat the fluidized bed furnace 21 (#66 in Figure 6).

[0057] In this way, the control unit 8 heats the stopped second incinerator 2B by providing the forced air with a large amount of heat held by the high-pressure steam in the high-pressure steam reservoir 9 up to the temperature limit where the temperature rise rate (℃ / h) becomes the reference temperature rise rate X3 (℃ / h), so that the temperature rise gradient becomes gentler (solid line in FIG. 9) than when the second startup burner B2 is used for heating from the beginning (broken line in FIG. 9: maintained at Qth until Tth), as shown in FIG. 9. If the second startup burner B2 is ignited when the temperature rise gradient reaches a plateau, the temperature inside the furnace rises at roughly the reference temperature rise rate X3, so that the fluidized bed furnace 21 of the second incinerator 2B can be preheated efficiently. In addition, as in this embodiment, when the temperature rise rate (°C / h) is less than the reference temperature rise rate X3 (°C / h) (temperature rise limit), if the in-furnace temperature (°C) of the second incinerator 2B is equal to or higher than the reference in-furnace temperature Y3 (°C), the temperature gradient does not become steep even if the second startup burner B2 is operated, so that stable start-up control of the second incinerator 2B can be realized. Furthermore, by operating the second startup burner B2 when the temperature rise rate is less than the reference temperature rise rate X3 (temperature rise limit), that is, when the heating temperature reaches a plateau, the fuel cost of the second startup burner B2 can be saved compared to the case of heating from the beginning using the second startup burner B2.

[0058] In the following, in the fourth and fifth embodiments, embodiments in which the start-up control of the fluidized-bed furnace 21 and the start-up control of the melting furnace 22 are executed will be described.

[0059] [Start-up control according to the fourth embodiment] 7A and 7B show the start-up control flow of the incinerator 2 according to the fourth embodiment (start-up method of the incinerator equipment 1). In the fourth embodiment, in addition to the start-up control of the fluidized bed furnace 21 according to the first embodiment, the start-up control of the melting furnace 22 is performed in parallel. Regarding the start-up control of the fluidized bed furnace 21 shown in FIG. 7A, #41 to #45 in FIG. 4 correspond to #71 to #75 in FIG. 7A, and the air preheater and the reference temperature rise rate X1 in FIG. 4 correspond to the forced air preheater and the reference temperature rise rate X4α in FIG. 7A, so the description will be omitted. Hereinafter, the start-up control in which the auxiliary burner provided at the top 13 is ignited as a starting burner after the second secondary air preheater Hs2 is operated to preheat the melting furnace 22 of the second incinerator 2B will be described. In this embodiment, the start-up control of the fluidized bed furnace 21 and the start-up control of the melting furnace 22 are performed in parallel, but the start and end times of each can be set arbitrarily.

[0060] When the first treatment system 1A is in operation and the second treatment system 1B is stopped, the control unit 8 operates the second incinerator 2B of the second treatment system 1B by introducing the heated air that has been heat exchanged with the high-pressure steam in the high-pressure steam reservoir 9 into the melting furnace 22 of the second incinerator 2B to heat it, and when the heated state of the melting furnace 22 reaches a state where a predetermined condition is satisfied, the control unit 8 operates the gas combustion burner to heat the melting furnace 22. This predetermined condition is that the temperature rise rate (°C / h), which is the degree of rise in the furnace temperature per unit time in the melting furnace 22 of the second incinerator 2B, becomes less than a predetermined value (reference temperature rise rate X4β(°C / h)) (temperature rise limit). Here, the standard temperature rise rate X4β (℃ / h) is a value that is set in advance for each incinerator equipment 1 through trial operation or the like, and is, for example, 20 (℃ / h) to 70 (℃ / h), preferably 40 (℃ / h) to 60 (℃ / h).

[0061] As shown in FIG. 3, since the first treatment system 1A is in operation, water supplied from the water supply device 31 to the first boiler 3A is boiled to generate high-pressure steam, which is temporarily stored in the high-pressure steam reservoir 9 and introduced into the turbine of the steam turbine generator 30 to drive the turbine to generate power (see also FIG. 2). When the control unit 8 operates the second incinerator 2B, it operates the second secondary air blower Ab2 to circulate the secondary air to the second secondary air preheater Hs2. Next, it opens the second steam damper Vs2 at a predetermined opening (for example, 10 to 50% of full opening) to circulate the high-pressure steam from the high-pressure steam reservoir 9 to the second secondary air preheater Hs2, and introduces the secondary air that has exchanged heat with the high-pressure steam into the melting furnace 22 of the second incinerator 2B to heat it (#76 in FIG. 7B, operation of the secondary air preheater).

[0062] Next, the control unit 8 calculates the temperature rise rate (°C / h), which is the degree of increase in the temperature inside the melting furnace 22 per unit time, based on the measurement value of the third temperature measurement unit T3 and the elapsed time, and determines whether this temperature rise rate (°C / h) is equal to or greater than the reference temperature rise rate X4β(°C / h) (#77 in FIG. 7B). At this time, the control unit 8 adjusts the opening degree of the second steam damper Vs2 so that the temperature rise rate (°C / h) is equal to or greater than the reference temperature rise rate X4β(°C / h) and is close to the reference temperature rise rate X4β(°C / h). If the temperature rise rate (°C / h) is equal to or greater than the reference temperature rise rate X4β (°C / h) (#77 Yes in FIG. 7B), the control unit 8 continues as is, and if the temperature rise rate (°C / h) is less than the reference temperature rise rate X4β (°C / h) (#77 No in FIG. 7B), it determines whether the opening of the second steam damper Vs2 is fully open (#78 in FIG. 7B). If the opening of the second steam damper Vs2 is not fully open (#78 No in FIG. 7B), the opening of the second steam damper Vs2 is increased to increase the amount of steam supplied to the second secondary air preheater Hs2 (#79 in FIG. 7B). In other words, the control unit 8 changes the amount of high-pressure steam supplied from the high-pressure steam reservoir 9 based on the heating state of the second incinerator 2B.

[0063] The control unit 8 repeats steps #77 to #79 until the second steam damper Vs2 is fully opened. If the temperature rise rate (°C / h) is less than the reference temperature rise rate X4β (°C / h) (temperature rise limit) even when the second steam damper Vs2 is fully opened (#77 No, #78 Yes in FIG. 7B), the control unit 8 ignites the auxiliary burner as a start-up burner and heats the melting furnace 22 (#80 in FIG. 7B). Although not shown, when the auxiliary burner is ignited and the temperature inside the melting furnace 22 reaches the preheating completion temperature (for example, 1200°C), the preheating of the melting furnace 22 of the second incinerator 2B is completed, the auxiliary burner is stopped, and the second treatment system 1B is put into full operation. When the melting furnace 22 is fully operated, the auxiliary burner is operated as necessary.

[0064] In this embodiment, in addition to the effects of the first embodiment, when preheating the fluidized bed furnace 21 and the melting furnace 22, the high-pressure steam in the high-pressure steam reservoir 9 provides a large amount of heat to the forced air and secondary air to heat the fluidized bed furnace 21 and the melting furnace 22 in parallel, so that there is little difference in the temperatures inside the fluidized bed furnace 21 and the melting furnace 22. Therefore, the inside of the fluidized bed furnace 21 and the melting furnace 22 is not cooled by cold air flowing from one to the other, so that the fuel cost of the second startup burner B2 and the auxiliary burner can be further saved. Moreover, by first igniting the startup burner in either the fluidized bed furnace 21 or the melting furnace 22, the effect of raising the temperature inside the other furnace can be expected.

[0065] [Start-up control according to the fifth embodiment] FIG. 8 shows a start-up control flow of the incinerator 2 according to the fifth embodiment (start-up method of the incinerator equipment 1). In the fifth embodiment, the start-up control of the fluidized bed furnace 21 according to the first embodiment and the start-up control of the melting furnace 22 are performed in sequence. Regarding the start-up control of the fluidized bed furnace 21 shown in FIG. 8, #71 to #75 shown in FIG. 7A correspond to #81 to #85 shown in FIG. 8, and the standard temperature rise rate X4α of FIG. 7 corresponds to the standard temperature rise rate X5α of FIG. 8, so the description is omitted. Also, regarding the start-up control of the melting furnace 22 shown in FIG. 8, #76 to #80 shown in FIG. 7B correspond to #86 to #90 shown in FIG. 8, and the standard temperature rise rate X4β of FIG. 7 corresponds to the standard temperature rise rate X5β of FIG. 8, so the description is omitted.

[0066] In this embodiment, in addition to the effects of the first embodiment, when preheating the fluidized bed furnace 21 and the melting furnace 22, the large amount of heat contained in the high-pressure steam in the high-pressure steam reservoir 9 is imparted to the forced air and secondary air to heat the fluidized bed furnace 21 and the melting furnace 22 in sequence, and the starting burner B in the fluidized bed furnace 21 is ignited first, thereby making it possible to increase the initial preheat temperature inside the melting furnace 22.

[0067] Other embodiments (1) The incinerator 2 is not limited to a fluidized bed gasification and melting furnace, but may be a stoker incinerator or a fluidized bed gasification furnace, etc. (2) In the first to third embodiments, an example has been shown in which the second forced air preheater Hp2 is operated, but the fluidized bed furnace 21 or the melting furnace 22 may also be preheated by operating the second secondary air preheater Hs2. (3) In the first to fifth embodiments, the case has been described in which the system is composed of two treatment systems, the first treatment system 1A and the second treatment system 1B, but the treatment system may be composed of three or more treatment systems. The above-mentioned start-up control has been described for the second treatment system 1B which is stopped, but it can be executed in the same manner for any treatment system which is stopped. Furthermore, in the case in which there are multiple target treatment systems which are stopped, one of the target treatment systems may execute a general start-up control in which a burner is used for heating from the beginning, and the other target treatment systems may execute the start-up control in the first to third embodiments described above. (4) In the fourth and fifth embodiments, the startup control in the first embodiment has been described as the startup control of the fluidized bed furnace 21 and the melting furnace 22, but the startup control in the second or third embodiment may be used. In addition, the startup controls in the first to third embodiments may be combined as the startup control of the fluidized bed furnace 21 and the melting furnace 22. In addition, the startup method of the incinerator equipment 1 is not limited to the startup control described above, and for example, an operator may monitor the temperature rise rate, etc., and execute burner ignition at the timing when the heating state of the incinerator 2 satisfies a predetermined condition. [Industrial Applicability]

[0068] INDUSTRIAL APPLICABILITY The present invention can be used in an incinerator facility equipped with a first treatment system and a second treatment system. [Explanation of symbols]

[0069] 1: Incinerator equipment 1A: First treatment system 1B: Second treatment system (target treatment system) 2: Incinerator 2A: First incinerator 2B: Second incinerator 3: Boiler 3A: First boiler 3B: No. 2 boiler 8: Control section 9: High pressure steam reservoir 21: Fluidized bed furnace (first incineration section) 22: Melting furnace (second incineration section)

Claims

1. A first treatment system including a first incinerator that burns materials to be incinerated and a first boiler that generates steam using heat of exhaust gas generated by the first incinerator; A second treatment system including a second incinerator that burns the material to be incinerated and a second boiler that generates steam using heat of exhaust gas generated by the second incinerator; a high-pressure steam reservoir that receives steam generated in the first boiler and the second boiler; a control unit that controls operation of the first treatment system and the second treatment system, When one of the first processing system and the second processing system is in operation and the other of the first processing system and the second processing system is stopped, when a target processing system consisting of the other of the first processing system and the second processing system is operated, The control unit introduces the combustion gas that has exchanged heat with the steam supplied from the high-pressure steam reservoir into the incinerator included in the target treatment system to heat it, and when the heating state of the incinerator satisfies a predetermined condition, operates a burner to heat the incinerator, The specified condition is that the temperature inside the incinerator included in the target treatment system is equal to or higher than a specified temperature.

2. A first treatment system including a first incinerator that burns materials to be incinerated and a first boiler that generates steam using heat of exhaust gas generated by the first incinerator; A second treatment system including a second incinerator that burns the material to be incinerated and a second boiler that generates steam using heat of exhaust gas generated by the second incinerator; a high-pressure steam reservoir that receives steam generated in the first boiler and the second boiler; a control unit that controls operation of the first treatment system and the second treatment system, When one of the first processing system and the second processing system is in operation and the other of the first processing system and the second processing system is stopped, when a target processing system consisting of the other of the first processing system and the second processing system is operated, The control unit introduces the combustion gas that has exchanged heat with the steam supplied from the high-pressure steam reservoir into the incinerator included in the target treatment system to heat it, and when the heating state of the incinerator satisfies a predetermined condition, operates a burner to heat the incinerator, The specified condition is that the temperature rise rate, which is the degree of increase in furnace temperature per unit time in the incinerator included in the target treatment system, is less than a specified value.

3. A first treatment system including a first incinerator that burns materials to be incinerated and a first boiler that generates steam using heat of exhaust gas generated by the first incinerator; A second treatment system including a second incinerator that burns the material to be incinerated and a second boiler that generates steam using heat of exhaust gas generated by the second incinerator; a high-pressure steam reservoir that receives steam generated in the first boiler and the second boiler; a control unit that controls operation of the first treatment system and the second treatment system, When one of the first processing system and the second processing system is in operation and the other of the first processing system and the second processing system is stopped, when a target processing system consisting of the other of the first processing system and the second processing system is operated, The control unit introduces the combustion gas that has exchanged heat with the steam supplied from the high-pressure steam reservoir into the incinerator included in the target treatment system to heat it, and when the heating state of the incinerator satisfies a predetermined condition, operates a burner to heat the incinerator, The control unit is an incinerator facility that changes the amount of steam supplied from the high-pressure steam reservoir based on the heating state of the incinerator included in the target treatment system.

4. The first incinerator and the second incinerator each have a first combustion section and a second combustion section, The incinerator equipment according to any one of claims 1 to 3, wherein the control unit introduces the combustion gas into the first combustion section included in the target treatment system to heat it, and when the specified condition is reached, activates a burner to heat the first combustion section, and introduces the combustion gas into the second combustion section included in the target treatment system to heat it, and when the specified condition is reached, activates a burner to heat the second combustion section.

5. A start-up method for an incinerator facility including a first treatment system, a second treatment system, and a high-pressure steam reservoir that receives steam generated in a boiler of the first treatment system and a boiler of the second treatment system, comprising: When one of the first treatment system and the second treatment system is in operation and the other of the first treatment system and the second treatment system is stopped, when a target treatment system consisting of the other of the first treatment system and the second treatment system is operated, the combustion gas that has exchanged heat with the steam supplied from the high-pressure steam reservoir is introduced into an incinerator included in the target treatment system to be heated, and when the heating state of the incinerator satisfies a predetermined condition, a burner is operated to heat the incinerator, A method for starting up an incinerator facility, wherein the specified condition is that the temperature inside the incinerator included in the target treatment system is equal to or higher than a specified temperature.

6. A start-up method for an incinerator facility including a first treatment system, a second treatment system, and a high-pressure steam reservoir that receives steam generated in a boiler of the first treatment system and a boiler of the second treatment system, comprising: When one of the first treatment system and the second treatment system is in operation and the other of the first treatment system and the second treatment system is stopped, when a target treatment system consisting of the other of the first treatment system and the second treatment system is operated, the combustion gas that has exchanged heat with the steam supplied from the high-pressure steam reservoir is introduced into an incinerator included in the target treatment system to be heated, and when the heating state of the incinerator satisfies a predetermined condition, a burner is operated to heat the incinerator, A method for starting up an incinerator facility, wherein the specified condition is that a temperature rise rate, which is the degree of increase in furnace temperature per unit time in the incinerator included in the target treatment system, is less than a specified value.

7. A start-up method for an incinerator facility including a first treatment system, a second treatment system, and a high-pressure steam reservoir that receives steam generated in a boiler of the first treatment system and a boiler of the second treatment system, comprising: When one of the first treatment system and the second treatment system is in operation and the other of the first treatment system and the second treatment system is stopped, when a target treatment system consisting of the other of the first treatment system and the second treatment system is operated, the combustion gas that has exchanged heat with the steam supplied from the high-pressure steam reservoir is introduced into an incinerator included in the target treatment system to be heated, and when the heating state of the incinerator satisfies a predetermined condition, a burner is operated to heat the incinerator, A method for starting up an incinerator facility, wherein the amount of steam supplied from the high-pressure steam reservoir is changed based on the heating state of the incinerator included in the target treatment system.