Temporary construction scaffolding and method for installing temporary construction scaffolding
The method for installing temporary construction scaffolding from within the building addresses safety and cost issues by allowing ground-level assembly, reducing risks and costs.
Patent Information
- Application Number
- JP2021098379
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2021-06-13
- Publication Date
- 2025-08-19
- Estimated Expiration
- 2041-06-13
AI Technical Summary
Existing scaffolding technologies require assembly from the ground in high-rise buildings, posing safety risks and increasing installation costs.
A method for installing temporary construction scaffolding that allows connection of scaffolding sections to a tower section from within the building, using anchors or weights for support, enabling assembly from the ground floor.
Reduces safety risks and installation costs by allowing assembly from the ground, shortening setup time, reducing material usage, and lowering transportation costs.
Smart Images

Figure 0007725016000001 
Figure 0007725016000002 
Figure 0007725016000003
Abstract
Description
[Technical Field]
[0001] The present invention relates to a temporary construction scaffold and a method for installing the temporary construction scaffold. [Background technology]
[0002] In the past, when construction work was required only on the upper floors of a high-rise building, scaffolding had to be erected from the ground, which caused a problem of high scaffolding installation costs as a proportion of the overall construction cost. One technology that can solve this problem is the suspended scaffolding described in Patent Document 1. [Prior art documents] [Patent documents]
[0003] [Patent Document 1] Japanese Patent Application Laid-Open No. 2005-171703 Summary of the Invention [Problem to be solved by the invention]
[0004] However, with the technology disclosed in Patent Document 1, the scaffolding must be abutted against the wall of a building in order to be fixed, which requires work at a height when assembling the scaffolding, which is dangerous.
[0005] The present invention has been made in consideration of the above, and aims to provide a temporary construction scaffolding and a method for installing temporary construction scaffolding that eliminates the need to assemble scaffolding from the ground in high-rise buildings and that does not pose any risks when installing the scaffolding. [Means for solving the problem]
[0006] The above purpose is A method for installing a temporary construction scaffolding unit (1) having a tower section (5) composed of a frame (5b) and a scaffolding section (10) connected to the tower section, comprising: The scaffolding section is configured to be connected to the tower section at any height, The tower is installed on the floor (50) inside the building, The scaffolding section is extended from an opening (51) of a building, This is achieved by:
[0007] In addition, the above objectives are: The scaffolding unit is installed on the floor inside the building using anchors (7) or weights. This is achieved by:
[0008] In addition, the above objectives are: The above-mentioned temporary construction scaffolding unit installation method, wherein a plurality of running boards are connected at different height positions of the tower section. This is achieved by: [Effects of the Invention]
[0009] According to the present invention, it is possible to provide a temporary construction scaffolding and a method for installing temporary construction scaffolding that eliminates the need to assemble scaffolding from the ground in high-rise buildings and does not pose any risks when installing the scaffolding. [Brief explanation of the drawings]
[0010] [Figure 1] 1 is a diagram illustrating a temporary construction scaffolding 1 according to a first embodiment of the present invention. [Figure 2] 1 is a perspective view of a tower section 5 of a temporary construction scaffolding 1 according to a first embodiment of the present invention. [Figure 3] FIG. 2 is a diagram illustrating anchor positions of a tower part 5 of the temporary construction scaffolding 1 according to the first embodiment of the present invention. [Figure 4] 1 is a diagram illustrating an example of installation of a temporary construction scaffolding 1 according to a first embodiment of the present invention. [Figure 5] 1 is a diagram illustrating an example of installation of a temporary construction scaffolding 1 according to a first embodiment of the present invention. [Figure 6] FIG. 10 is a diagram illustrating a temporary construction scaffolding 3 according to a second embodiment of the present invention. DETAILED DESCRIPTION OF THE INVENTION
[0011] A temporary construction scaffolding unit 1 according to a first embodiment of the present invention will be described below with reference to Figures 1 to 5. In all the following drawings, the dimensions and proportions of each component may be shown as appropriate differently to facilitate understanding.
[0012] FIG. 1 is a side view of an installed temporary construction scaffolding unit 1 according to this embodiment. The temporary construction scaffolding unit 1 is broadly composed of a tower section 5 installed inside a building and a scaffolding section 10 connected to the tower section 5. FIG. 2 is a perspective view of the tower section 5, which has frames 5b, 5b1, and 5b2, and a base plate 5a. The tower section 5 is formed by assembling the frame 5b into a tower as shown in FIG. 2. A base plate 5a is provided on each of the four support pillars of the tower section 5, and four anchor bolts 7 are provided on the base plate 5a. The anchor bolts 7 are installed in a floor 50 of a building to secure the tower section 5 to the floor 50. As shown in FIG. 1, the scaffolding section 10 has running boards 10a1 to 10a4 and a frame 10b at different heights. In addition, stairs may be provided in the tower section 5 and the scaffolding section 10. In addition, the tower part 5 may be fixed to the floor 50 using a weight.
[0013] The tower section 5 is provided with a step pusher 5c1 and a step support 5c2 at any height position. The step pusher 5c1 and the step support 5c2 are flat-shaped. The step pusher 5c1 is provided on the frame 5b (extending diagonally) farther from the opening 51 of the building, and the scaffold support 5c2 is provided on the frame 5b (extending vertically) closer to the opening 51 of the building. The step pusher 5c1 and the step support 5c2 are configured to have different height positions due to the thickness of the steps 10a1, 10a2, and one end of the steps 10a1, 10a2 is pressed down by the step pusher 5c1. The height positions of the step pusher 5c1 and the step support 5c2 are configured to be freely changeable.
[0014] Steps 10a1 and 10a2 connected to tower section 5 protrude outside through the opening of the building. Steps 10a1 and 10a2 are connected by frame 10b. Above step 10a2, steps 10a3 and 10a4 are connected by frame 10b. Steps 10a1 to 10a4 are provided with staircase sections (not shown) to facilitate vertical movement of workers.
[0015] 3 is a schematic diagram of anchor positions of the temporary construction scaffolding unit 1 according to this embodiment. In this embodiment, only one support pillar of the tower section 5 is installed per square meter. Note that the tower section 5 may be configured so that only one support pillar is installed per area larger than one square meter, or may be configured so that only one support pillar is installed per area smaller than one square meter.
[0016] 4 shows an example of installation of the temporary construction scaffolding units 1 according to this embodiment. In this installation example, the temporary construction scaffolding units 1 are installed in positions facing the openings of a building, and the running boards 20 are laid across each temporary construction scaffolding unit 1 to install the scaffolding.
[0017] 5 shows an example of installation of a temporary construction scaffolding unit 1 according to this embodiment. In this installation example, the temporary construction scaffolding units 1 may or may not be installed in a position facing an opening in a building, and the scaffolding is installed by suspending a running board 20 across each temporary construction scaffolding unit 1. Furthermore, multiple temporary construction scaffolding units 1 are connected by connecting parts 9 made of metal, and in places where no temporary construction scaffolding units 1 are installed, these connecting parts 9 are fixed to the floor 50 with anchor bolts 7. Note that the intervals at which the temporary construction scaffolding units 1 and anchor bolts 7 are installed can be changed as appropriate.
[0018] The tower section 5 of the temporary construction scaffolding unit 1 according to this embodiment may be any three-dimensional shape, such as a cylindrical, rectangular column, cone, pyramid, etc. The anchor bolts 7 may be made of various materials such as adhesive or metal.
[0019] A temporary construction scaffolding unit 3 according to a second embodiment of the present invention will be described using Figure 6. In all of the following drawings, the dimensions and ratios of each component may be illustrated as appropriate to facilitate understanding. Note that the same components as those in the temporary construction scaffolding unit 1 according to the first embodiment may be designated by the same reference numerals, and their description may be omitted.
[0020] FIG. 6 is a side view of the temporary construction scaffolding unit 3 according to this embodiment in an installed state. The temporary construction scaffolding unit 3 is broadly composed of a tower section 5 installed inside a building and a scaffolding section 10 connected to the tower section 5. FIG. 2 is a perspective view of the tower section 5, which has frames 5b, 5b1, and 5b2, and a base plate 5a. The tower section 5 is formed by assembling the frame 5b into a tower as shown in FIG. 2. A base plate 5a is provided on each of the four support pillars of the tower section 5, and four anchor bolts 7 are provided on the base plate 5a. The anchor bolts 7 are installed in the floor 50 of the building to secure the tower section 5 to the floor 50. As shown in FIG. 6, the scaffolding section 10 has running boards 10a1, 10a2, 10a31, and 10a41 at different heights and a frame 10b1. In the temporary construction scaffolding unit 3 of this embodiment, the frame 10b1 of the scaffolding section 10 is not provided on the building side. Therefore, the temporary construction scaffolding unit 3 of this embodiment can be made lighter than the temporary construction scaffolding unit 1 of the above-mentioned embodiment. Furthermore, stairs may be provided on the tower section 5 and the scaffolding section 10, respectively. Furthermore, the tower section 5 may be fixed to the floor 50 using a weight.
[0021] The temporary construction scaffolding units 1, 3 according to the embodiments of the present invention and the scaffolding installation method using the same provide the following effects. (a) Since the temporary construction scaffolding units 1 and 3 are set up within the floor, the number of work processes within the floor during scaffolding installation work can be increased, thereby reducing work time at heights (outside) and ensuring safety. (i) The height position of the step connected to the tower section 5 can be changed as desired, making it possible to adapt to a variety of work sites. (c) Since scaffolding only needs to be set up on the necessary floors, the time required to assemble the scaffolding can be shortened, the amount of scaffolding materials used can be reduced, and the cost of transporting the scaffolding materials can be reduced. (e) When carrying out pinpoint construction work on the exterior of a building, it is possible to significantly reduce the cost of assembling scaffolding.
[0022] The above-described embodiment is a preferred example of the present invention, and various technically preferable limitations are applied thereto, but the scope of the present invention is not unduly limited by the above description. Furthermore, not all of the configurations described in the above-described embodiment are essential components of the present invention. Furthermore, the configurations described in the above-described embodiment may be added to or combined with each other. [Industrial Applicability]
[0023] The present invention can also be widely used in temporary construction scaffolding and methods for installing temporary construction scaffolding. [Explanation of symbols]
[0024] 1. Temporary construction scaffolding unit 5. Tower 10 Scaffolding 50 floors 5a Base plate 5b, 5b1, 5b2, 10b frames 7 anchor bolts 10a1~10a4, 20 steps
Claims
1. A method for installing a temporary construction scaffolding unit having a tower section composed of a frame and a scaffolding section connected to the tower section, The scaffolding section is configured to be connected to the tower section at any height, The tower section is installed on the floor inside the building, The scaffolding extends from an opening in the building, The frame of the tower section is composed of four pillars installed on the floor inside the building, the four support columns are a first support column, a second support column, a third support column, and a fourth support column; the first support pillar and the second support pillar are support pillars installed at positions close to an opening of a building, the third support column and the fourth support column are support columns installed at positions far from an opening of a building, the first support and the second support extend perpendicular to the floor; the third support column and the fourth support column extend obliquely toward an opening in the building, A method for installing a temporary construction scaffolding unit, wherein the frame connecting the scaffolding section and the tower section is supported by the first support pillar to the fourth support pillar.
2. 2. The method for installing temporary construction scaffolding units according to claim 1, wherein the tower section is installed on a floor inside the building using anchors or weights.
3. 3. The method for installing a temporary construction scaffolding unit according to claim 1, wherein a plurality of running boards are connected at different height positions of the tower section.
Citation Information
Patent Citations
JP1971013733Y1
JP1975015714Y1
JP1992084650U
Suspended scaffolding
JP2005171703A
Assembling structure of scaffold for construction work
JP2010189970A