Compressor, method for manufacturing compressor, and method for evaluating coating material for compressor

JPWO2024201628A1Active Publication Date: 2024-10-03CARRIER JAPAN CORP
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
JP2025509261
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-03-27
Publication Date
2024-10-03
Estimated Expiration
2043-03-27

AI Technical Summary

Technical Problem

Hermetic compressors face challenges in rust prevention due to inadequate consideration of gas permeability in paint coatings, especially under varying temperature conditions, which can lead to moisture and oxygen permeation, causing rust in refrigeration cycle equipment.

Method used

A compressor design with a coating film on its outer surface that has nitrogen gas permeability of 2500 mol·μm/m at -40°C, 150 mol·μm/m at room temperature, and 2500 mol·μm/m at 100°C, using an epoxy resin with a benzene ring for improved rust prevention, and a method for evaluating paint based on gas permeability at multiple temperatures to select appropriate coatings.

Benefits of technology

The specified gas permeability of the coating film effectively suppresses moisture and oxygen permeation, preventing rust in both high-temperature and low-temperature environments, ensuring a more reliable compressor performance.

✦ Generated by Eureka AI based on patent content.
Patent Text Reader

Abstract

A compressor (1) comprises a compression mechanism unit (13) that compresses a refrigerant, an electric motor that drives the compression mechanism unit, and a case that accommodates the compression mechanism unit and the electric motor. The refrigerant, after being compressed by the compression mechanism unit (13), is discharged from the compressor (1) via a space inside the case, and the compression mechanism unit (13) is in a high-temperature atmosphere due to the compressed refrigerant. An iron-based metal material is used in a base material in the case. The nitrogen gas permeability of a coating film formed on the outer surface of the case is (a) 2500 [mol·μm / (m2·s·Pa)] or less at −40°C, (b) 150 [mol·μm / (m2·s·Pa)] or less at room temperature, and (c) 2500 [mol·μm / (m2·s·Pa)] or less at 100°C.
Need to check novelty before this filing date? Find Prior Art

Description

Compressor, compressor manufacturing method, and compressor paint evaluation method

[0001] FIELD Embodiments of the present invention relate to a compressor, a method for manufacturing a compressor, and a method for evaluating paint for a compressor.

[0002] There is a so-called hermetic compressor in which a compression mechanism and an electric motor are housed in a sealed case.

[0003] In a hermetic compressor, after being compressed by the compression mechanism, the refrigerant passes through a space inside the sealed case and is discharged from the compressor through a discharge pipe provided on the head or the like of the sealed case. During operation of the compressor, the space inside the sealed case is filled with the compressed refrigerant, and the sealed case is heated by the compressed refrigerant.

[0004] Japanese Patent Application Laid-Open No. 2020-153293

[0005] In the selection of paint for the outer surface of such compressors, emphasis is placed primarily on the adhesion between the substrate and the coating film to ensure the paint's anti-corrosion properties, with no particular consideration given to the gas permeability of the coating film.

[0006] When applied to a refrigeration cycle device, the sealed case is heated by the compressed refrigerant and cooled by the low-temperature refrigerant returning from the evaporator, and it is expected that the temperature may fall below 0°C in some places.

[0007] Therefore, when selecting a paint to be used for painting a compressor, it is important to consider not only the adhesion between the substrate and the coating, but also the gas permeability of the coating depending on the temperature so that the permeation of moist air is effectively blocked in the actual operating environment of the compressor.

[0008] In view of the above circumstances, an object of the present invention is to provide a compressor with higher reliability by confirming the rust prevention performance of a coating through an evaluation based on the gas permeability of the coating film.

[0009] A compressor according to one aspect of the present invention includes a compression mechanism that compresses a refrigerant, an electric motor that drives the compression mechanism, and a case that houses the compression mechanism and the electric motor, wherein the refrigerant compressed by the compression mechanism is discharged from the compressor through a space inside the case, and the compression mechanism is in a high-temperature atmosphere due to the compressed refrigerant, and the case has a base material made of an iron-based metal material, and a coating film formed on an outer surface thereof has a nitrogen gas permeability of (a) 2500 [mol μm / m] at −40° C. 2 ·s·Pa] or less, (b) 150 [mol·μm / m 2 ·s·Pa] or less and (c) 2500 [mol·μm / m 2 ·s·Pa] or less.

[0010] The nitrogen gas permeability of the coating film tends to increase not only in high temperature environments but also in low temperature environments relative to a reference temperature of room temperature or its vicinity. Based on this trend, the nitrogen gas permeability of the coating film formed on the outer surface of the case is (a) 2500 [mol μm / m 2 ·s·Pa] or less, (b) 150 [mol·μm / m 2 ·s·Pa] or less and (c) 2500 [mol·μm / m 2 By setting the gas permeability of the coating film to be equal to or less than [0.05 s Pa], the gas permeability of the coating film is adapted to the actual operating environment of the compressor. This effectively prevents moisture and oxygen from permeating through the coating film throughout the entire case, suppresses rust formation on the case, and makes it possible to provide a compressor with higher reliability.

[0011] The compressor includes a low-pressure section that introduces refrigerant before compression by the compression mechanism and is configured to be able to separate the liquid refrigerant contained in the refrigerant, and a high-pressure section that is formed separately from the low-pressure section and is connected to the low-pressure section so that the refrigerant after separation of the liquid refrigerant can be introduced into the low-pressure section, and the case includes a first case of the low-pressure section and a second case of the high-pressure section, and it is preferable that the compression mechanism and the electric motor are housed in the second case, and the coating film is formed on the outer surface of at least one of the first case and the second case.

[0012] In this way, by forming the compressor 1 separately into a low-pressure section and a high-pressure section, configuring the low-pressure section to be able to separate liquid refrigerant from the refrigerant, and accommodating the compression mechanism and the electric motor in the high-pressure section, it is possible to prevent liquid refrigerant from flowing into the high-pressure section, particularly the compression mechanism. In this compressor, by forming a coating film having the above-mentioned specified gas permeability on at least one of the high-pressure section and the low-pressure section, it is possible to prevent moisture and other contaminants from permeating not only in areas heated by the compressed refrigerant but also in areas cooled by the refrigerant returning from the evaporator, thereby effectively preventing rust from occurring in both the low-pressure section and the high-pressure section.

[0013] The coating film is preferably formed from an epoxy resin having a benzene ring in part of the main chain of the amorphous molecular structure and in the additive.

[0014] In this way, by using a paint that combines epoxy resin with a high cross-linking density and benzene rings with a rigid molecular structure, it is possible to further reduce gas permeability and further improve the rust prevention performance of the paint.

[0015] A method for manufacturing a compressor according to another aspect of the present invention is a method for manufacturing a compressor in which a compression mechanism that compresses a refrigerant and an electric motor that drives the compression mechanism are housed in a case, and includes a paint selection step of selecting a paint to be applied to the outer surface of the case, in which the gas permeability of a coating film formed by the paint is measured at a plurality of temperatures including a first temperature below 0°C, or the gas permeability exhibited by the coating film at the plurality of temperatures is obtained, and a paint having a gas permeability within a predetermined range for each of the plurality of temperatures is selected.

[0016] In this way, by measuring the gas permeability of the coating film and conducting a selection evaluation based on this in the paint selection process, it is possible to confirm the rust prevention performance of the coating from the perspective of gas permeability and select a more appropriate paint. Furthermore, by measuring the gas permeability at multiple temperatures, including a first temperature below 0°C, and evaluating the gas permeability of the coating film, it is possible to conduct an evaluation under conditions that simulate the actual operating environment of the compressor, and to suppress the occurrence of rust throughout the entire case.

[0017] In the paint selection process, it is preferable that the plurality of temperatures include the first temperature and room temperature, and that a paint is selected whose gas permeability is equal to or less than a predetermined first threshold value at the first temperature and equal to or less than a predetermined second threshold value lower than the first threshold value at room temperature.

[0018] In this way, by measuring the gas permeability at a first temperature and at room temperature and setting the second threshold value for comparison with the gas permeability at room temperature lower than the first threshold value for comparison with the gas permeability at the first temperature, it is possible to reflect the change in gas permeability according to temperature in the selection evaluation of the coating film, thereby making it possible to select a more appropriate coating material.

[0019] The first temperature is preferably a temperature of -40°C or higher and -20°C or lower.

[0020] In this way, by setting the first temperature to a temperature of −40°C or higher and −20°C or lower, a more appropriate evaluation can be performed taking into account the tendency for gas permeability to increase with decreasing temperature, making it possible to select an appropriate paint.

[0021] A method for evaluating a paint for a compressor according to yet another embodiment of the present invention is a method for evaluating a paint for a compressor used to paint a compressor in which a compression mechanism for compressing a refrigerant and an electric motor for driving the compression mechanism are housed in a case, the method comprising: preparing a sample in which the paint is formed into a film; measuring the gas permeability, which indicates the amount of gas that permeates the sample per unit time, at a plurality of temperatures including a first temperature below 0°C; and evaluating the performance of the coating film made from the paint based on the gas permeability measured at each of the plurality of temperatures.

[0022] In this way, by preparing a sample of a coating film formed from a paint and evaluating the performance of the coating film based on the gas permeability of this sample, it is possible to confirm the rust prevention performance of the paint in a relatively simple manner and select an appropriate paint. Furthermore, by measuring the gas permeability at multiple temperatures including a first temperature below 0°C and evaluating the performance, the evaluation can be performed under conditions that simulate the actual operating environment of the compressor, and the performance evaluation can be performed with higher reliability.

[0023] According to the present invention, it is possible to appropriately evaluate the rust prevention performance of a coating from the viewpoint of gas permeability, and to provide a compressor with higher reliability.

[0024] 1 is a schematic diagram showing the configuration of a refrigeration cycle device equipped with a compressor according to one embodiment of the present invention; FIG. 2 is a cross-sectional view showing the configuration of the compressor; FIG. 3 is a flowchart showing the basic steps of a paint selection process; FIG. 4 is a schematic diagram showing the configuration of a coating film evaluation test device; FIG. 5 is a schematic diagram of test results showing changes in the differential pressure between a high temperature chamber and a low temperature chamber in the evaluation test device for a high temperature range above room temperature; FIG. 6 is a schematic diagram showing tests showing changes in the differential pressure between a high temperature chamber and a low temperature chamber in the evaluation test device for a low temperature range below room temperature; and FIG. 7 is a schematic diagram showing the relationship between the nitrogen gas permeability of a coating film and temperature.

[0025] DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, embodiments of the present invention will be described with reference to the accompanying drawings.

[0026] (Configuration of Refrigeration Cycle Apparatus) FIG. 1 is a schematic diagram showing the configuration of a refrigeration cycle apparatus C including a compressor 1 according to one embodiment of the present invention.

[0027] The refrigeration cycle apparatus C is configured as an air conditioner and includes, in addition to a compressor 1, a four-way valve 2, an outdoor heat exchanger 3, an expansion valve 4, and an indoor heat exchanger 5, as well as refrigerant piping 6 (6a to 6f) connecting these refrigeration cycle elements 1 to 5. Refrigerant circulates through the refrigeration cycle apparatus C via the refrigerant piping 6. Refrigerants applicable to this embodiment include, for example, R32, R410A, R448A, R449A, R404A, R407C, R454A, R454B, R454C, and R744.

[0028] The operation of the refrigeration cycle device C can be switched between cooling operation and heating operation by switching the flow path of the four-way valve 2.

[0029] (Cooling Operation) During cooling operation, the refrigerant circulates through the path indicated by the solid arrow A1 in FIG.

[0030] Specifically, after leaving the compressor 1, the refrigerant flows through the refrigerant piping 6, passing through the four-way valve 2, the outdoor heat exchanger 3, the expansion valve 4, and the indoor heat exchanger 5 in this order. The high-pressure gas refrigerant compressed by the compressor 1 is cooled and condensed by heat exchange with outdoor air as it passes through the outdoor heat exchanger 3. The outdoor heat exchanger 3 is equipped with an outdoor fan 3', which sends outdoor air (i.e., outside air) into the outdoor heat exchanger 3. The pressure of the condensed gas-liquid mixed refrigerant is reduced as it passes through the expansion valve 4, becoming a low-pressure liquid refrigerant and being supplied to the indoor heat exchanger 5. The liquid refrigerant that flows into the indoor heat exchanger 5 is heated and evaporates through heat exchange with indoor air. The indoor heat exchanger 5 is equipped with an indoor fan 5', which sends indoor air into the indoor heat exchanger 5. The evaporated gas-liquid mixed refrigerant then passes through the four-way valve 2 and returns to the compressor 1.

[0031] (Heating Operation) During heating operation, the refrigerant circulates through the path indicated by the dashed arrow A2 in FIG.

[0032] Specifically, after leaving the compressor 1, the refrigerant flows through the refrigerant piping 6, passing through the four-way valve 2, the indoor heat exchanger 5, the expansion valve 4, and the outdoor heat exchanger 3 in this order. The high-pressure gas refrigerant compressed by the compressor 1 is cooled by heat exchange with the indoor air as it passes through the indoor heat exchanger 5 (i.e., it releases heat to the indoor air) and condenses. The pressure of the condensed gas-liquid mixed refrigerant is reduced as it passes through the expansion valve 4, and it becomes a low-pressure liquid refrigerant and is supplied to the outdoor heat exchanger 3. The liquid refrigerant that flows into the outdoor heat exchanger 3 is heated by heat exchange with the outdoor air (i.e., it absorbs heat from the outdoor air) and evaporates, and the evaporated gas-liquid mixed refrigerant passes through the four-way valve 2 and returns to the compressor 1.

[0033] (Defrosting Operation) During heating operation, when the refrigerant evaporates in the outdoor heat exchanger 3, heat is taken from the outdoor air, causing water vapor in the outdoor air to condense and turn into water droplets that adhere to the heat exchange members inside the outdoor heat exchanger 3. Here, due to the low temperature of the outdoor air, the adhered water may freeze and form frost. In this case, the frost may hinder heat exchange and cause a decrease in heat exchange efficiency, so a defrosting operation is performed to remove the frost.

[0034] During defrosting operation, the four-way valve 2 is set to the same state as during cooling operation, and the refrigerant flows in the same order as during cooling operation. However, both the outdoor fan 3' and the indoor fan 5' are stopped, and the high-temperature, high-pressure gas refrigerant delivered from the compressor 1 heats the heat exchange members of the outdoor heat exchanger 3, melting the frost. The resulting melted water is discharged from the outdoor heat exchanger 3 as drain.

[0035] (Configuration of Compressor) FIG. 2 is a cross-sectional view showing the internal structure of the compressor 1 according to this embodiment.

[0036] The compressor 1 includes a compressor main body 1a and an accumulator 1b. The accumulator 1b includes a suction pipe 21, through which refrigerant leaving a heat exchanger operating as an evaporator is supplied. The evaporator corresponds to the indoor heat exchanger 5 during cooling operation or the outdoor heat exchanger 3 during heating operation. The accumulator 1b separates the supplied refrigerant into gas and liquid, and supplies the refrigerant (i.e., gas refrigerant) after separation of the liquid refrigerant to the compressor main body 1a. As described above, the compressor 1 is divided into the compressor main body 1a and the accumulator 1b, which are connected to each other via a refrigerant inlet pipe 22. The compressor main body 1a constitutes the "high-pressure section" of the compressor 1, and the accumulator 1b constitutes the "low-pressure section" of the compressor 1. The sealed case 11 of the compressor body 1a corresponds to the "first case", and the case of the accumulator 1b corresponds to the "second case".

[0037] In this embodiment, the compressor 1 is a hermetic rotary compressor. The compressor 1, specifically, the compressor main body 1a, includes a hermetic case 11. Inside the hermetic case 11, an electric motor (hereinafter simply referred to as "motor") 12, which serves as a power source, and a compression mechanism 13 are housed. The motor 12 and the compression mechanism 13 are connected via a drive shaft 14, and the rotational driving force of the motor 12 is transmitted to the compression mechanism 13 via the drive shaft 14, thereby driving the compression mechanism 13. Electric power is supplied to the motor 12 from an external power source via a sealed terminal 15. The drive shaft 14 is rotatably supported relative to the hermetic case 11 by a plurality of bearings, in this embodiment, a main bearing 16a and a sub-bearing 16b.

[0038] The sealed case 11 has an overall cylindrical shape. The sealed case 11 has a cylindrical case body 11a that is open at the top and bottom, and the upper and lower ends of the case body 11a are closed by hemispherical end plates 11b and 11c, respectively. The case body 11a and the lower end plate 11c can be formed integrally. A refrigerant inlet pipe 22 extending from the accumulator 1b is connected to the case body 11a, and gas refrigerant separated by the accumulator 1b is introduced into the sealed case 11 through the refrigerant inlet pipe 22. The gas refrigerant compressed by the compression mechanism 13 passes through a space S within the sealed case 11, specifically, the entire interior of the sealed case 11 excluding spaces occupied by the motor 12, compression mechanism 13, drive shaft 14, etc., and is discharged to the outside of the sealed case 11 through a discharge pipe 23 attached to the upper end plate 11b.

[0039] Inside the sealed case 11, the motor 12 is housed in the upper half of the case body 11a, and the compression mechanism 12 is housed in the lower half of the case body 11a.

[0040] The motor 12 includes a stator 121 fixed to the case body 11a, and a rotor 122 disposed on the inner diameter of the stator 121 and fixed to the drive shaft 14. The rotor 122 is rotatable integrally with the drive shaft 14 relative to the stator 121. The motor 12 is a permanent magnet synchronous motor, with a coil formed on the stator 121 and a permanent magnet attached or embedded in the rotor 122. The rotor 122 can be rotated by passing current through the coil, driving the compression mechanism 13 via the drive shaft 14.

[0041] The compression mechanism 13 is provided between the main bearing 16 a and the auxiliary bearing 16 b. In this embodiment, the compression mechanism 13 has a single-stage compression mechanism and is composed of a cylinder 131, an eccentric portion 141 of the drive shaft 14, and a rolling piston 132. The number of stages in the compression mechanism is not limited to one, and may be multiple.

[0042] A cylinder chamber is formed in the cylinder 131, and the rolling piston 132 is annular and loosely fitted in the eccentric portion 141, and is housed in the cylinder chamber together with the eccentric portion 141. The inner diameter of the cylinder 131 is larger than the outer diameter of the rolling piston 132, and a gap is formed between the cylinder 131 and the rolling piston 132.

[0043] A vane groove extending radially from the inner periphery of the cylinder 131 is formed in the cylinder 131, and a slide vane 133 is inserted into this vane groove. A spring 134 is interposed in a compressed state between the cylinder 131 and the slide vane 133, and the slide vane 133 is pressed against the outer periphery of the rolling piston 132 by the spring 134.

[0044] The gap between the cylinder 131 and the rolling piston 132 is divided into two spaces, i.e., a suction chamber and a compression chamber, by a slide vane 133. The suction chamber and the compression chamber of the compression mechanism 13 are sealed by a main bearing 16a disposed on the upper side and a sub-bearing 16b disposed on the lower side.

[0045] The cylinder 131 has a suction port that opens to the inner peripheral surface of the cylinder 131 and is connected to the suction chamber, and a refrigerant introduction pipe 22 extending from the accumulator 1b is inserted and connected to this suction port, so that the refrigerant that has left the accumulator 1b is introduced from the refrigerant introduction pipe 22 through the suction port into the suction chamber.

[0046] Lubricating oil is sealed inside the sealed case 11, and most of the compression mechanism 13 is immersed in this lubricating oil. An example of a circulating oil that can be used in this embodiment is polyol ester lubricating oil to which 0.5% by mass of glycidyl ester epoxy and 0.1% by mass of a phenolic antioxidant have been added.

[0047] The cases of the compressor 1, specifically the sealed case 11 of the compressor main body 1a and the case of the accumulator 1b, both use an iron-based metal material as their base material. Examples of materials that can be used for the base material of these cases include steel plate, specifically hot-rolled steel plate (SPHE material), and in this embodiment, SPHE-P material is used. The base material of the case is then subjected to an appropriate plating process, such as electrogalvanization, to protect it from rust and the like, and then painted on its outer surface to form a coating film. Regarding the actual situation regarding the painting of the compressor 1, when selecting a paint to paint the outer surface of the sealed case 11, emphasis is placed primarily on the adhesion between the base material and the coating film, with no particular consideration given to the gas permeability of the coating film.

[0048] During operation of the compressor 1, the space inside the sealed case 11 is filled with compressed refrigerant, and the sealed case 11 is heated by the compressed refrigerant. On the other hand, the case of the accumulator 1b is expected to be cooled to below 0°C by the relatively low-temperature refrigerant returned from the evaporator. The same is true for the case of the compressor main body 1a, i.e., the sealed case 11; some locations, such as the joint to which the refrigerant inlet pipe 22 is connected and its surroundings, are expected to be cooled to below 0°C.

[0049] Therefore, in selecting the paint to be used for painting the compressor 1, not only is the adhesion between the substrate and the paint film considered, but also the gas permeability of the paint film according to temperature is taken into consideration in the selection of the paint so that the permeation of moist air is effectively suppressed in the actual operating environment of the compressor 1; in other words, so that the necessary gas barrier properties are ensured not only in the normal environment at room temperature but also in both the heating environment caused by the refrigerant after compression and the cooling environment caused by the refrigerant returned from the evaporator.

[0050] (Explanation of Paint Selection Process) FIG. 3 is a flowchart showing the basic steps of the paint selection process according to this embodiment.

[0051] FIG. 4 is a schematic diagram showing the configuration of a coating evaluation test device 101.

[0052] The process of selecting a coating film applicable to the manufacture of the compressor 1 according to this embodiment will be described mainly with reference to FIG. 3 while also referring to FIG. 4 as appropriate.

[0053] The coating film selection process according to this embodiment includes a step of measuring the nitrogen gas permeability R of the coating film. The targets that are actually intended to be blocked by the coating film in order to inhibit rust formation are oxygen and moisture in the air, and nitrogen gas is used as the measurement gas because a correlation has been found between nitrogen gas and oxygen and moisture in gas permeability. The nitrogen gas permeability R is measured using a method in accordance with Japanese Industrial Standards (JIS) K7126-1 or International Organization for Standardization (ISO) Standard 15105-2, specifically using the differential pressure method defined in JIS K7126-1.

[0054] In S201, a coating sample F is created or prepared and placed in the evaluation test device 101.

[0055] Sample F is prepared by forming the paint into a film of a predetermined thickness (for example, 130 μm). Specifically, the paint to be tested is baked onto a mold of an appropriate shape to which a releasing agent has been applied, and then the paint film alone is released from the mold. Further, paint is applied to the released paint film as many times as necessary to obtain Sample F of the predetermined thickness. The paint is baked when forming the paint film because painting during mass production is done by baking.

[0056] As shown in Fig. 4, the evaluation test device 101 includes a container 111 that can be separated into an upper half 111a and a lower half 111b. The interior of the container 111 is separated into a high-pressure space (hereinafter referred to as the "high-pressure chamber") Ca and a low-pressure space (hereinafter referred to as the "low-pressure chamber") Cb by a sample F sandwiched between the upper half 111a and the lower half 111b. That is, in this embodiment, the interior of the upper half 111a forms the high-pressure chamber Ca, and the interior of the lower half 111b forms the low-pressure chamber Cb. An appropriate sealant 201, such as an O-ring, is interposed between the sample F and the upper half 111a.

[0057] The upper half 111a is formed with a first vacuum / gas inlet ha penetrating the upper half 111a from inside to outside, and the lower half 111b is formed with a second vacuum / gas inlet hb penetrating the lower half 111b from inside to outside. The first vacuum / gas inlet ha allows residual gas to be exhausted from the high-pressure chamber Ca and a predetermined test gas to be introduced. Meanwhile, the second vacuum / gas inlet hb allows residual gas to be exhausted from the low-pressure chamber Cb and a predetermined test gas to be introduced. Specifically, a vacuum pump and a first gas supplier are connected to the high-pressure chamber Ca via the first vacuum / gas inlet ha, and a vacuum pump and a second gas supplier are connected to the low-pressure chamber Cb via the second vacuum / gas inlet hb. In this embodiment, nitrogen gas is used as the test gas. Pressure sensors 301a, 301a are connected to the upper half portion 111a and the lower half portion 111b, respectively, so as to be able to detect the pressures Pa, Pb of the high pressure chamber Ca and the low pressure chamber Cb.

[0058] In S202, the remaining gas is sucked from both the high-pressure chamber Ca and the low-pressure chamber Cb, and the chambers Ca and Cb are evacuated to a vacuum, thereby removing the dissolved gas from the sample F and discharging it from the chambers Ca and Cb together with the remaining gas.

[0059] In S203, nitrogen gas is introduced into the high pressure chamber Ca and the low pressure chamber Cb until the pressure reaches atmospheric pressure.

[0060] In S204, a pressure difference Pd is formed between the high-pressure chamber Ca and the low-pressure chamber Cb. Specifically, after the pressures in the chambers Ca and Cb reach atmospheric pressure, nitrogen gas is further introduced into the high-pressure chamber Ca. In this embodiment, the pressure difference Pd is set to 0.020 MPa. The pressure difference Pd can be set appropriately within a range that does not cause deformation of the sample F placed in the apparatus 101.

[0061] In addition to the above, the differential pressure Pd can also be formed by evacuating each chamber Ca and Cb and then introducing nitrogen gas into the high-pressure chamber Ca until a predetermined pressure (0.020 MPa in this embodiment) is reached.

[0062] In S205, the change in pressure in the high pressure chamber Ca is monitored for a predetermined time. In this embodiment, the time for monitoring the change in pressure is approximately 10 hours. As nitrogen gas passes through the sample F from the high pressure chamber Ca to the low pressure chamber Cb, the pressure in the high pressure chamber Ca decreases. Since the pressure in the low pressure chamber Cb is maintained at atmospheric pressure, the change in pressure in the high pressure chamber Ca indicates a change in the differential pressure Pd between the high pressure chamber Ca and the low pressure chamber Cb.

[0063] In S206, the nitrogen gas permeability R of the sample F is calculated from the change in pressure in the high pressure chamber Ca, that is, the change in the differential pressure Pd between the high pressure chamber Ca and the low pressure chamber Cb. The nitrogen gas permeability R is calculated using the following equations: μ={Vc / (R×T×Pu×A)}×dP / dt (1) Q=μ×h (2)

[0064] The above formula (1) is the gas permeability [mol / (m 2 s Pa)], and the above formula (2) represents the gas permeability coefficient [mol μm / (m 2 Vc is the volume of the high pressure chamber Ca [m 3 ], R is the gas constant, T is the test temperature [K], Pu is the differential pressure [Pa], A is the gas permeation area [m 2 ], dP / dt indicates pressure change [Pa / s]. Furthermore, h indicates the thickness [μm] of sample F. In this embodiment, the gas permeability coefficient Q of nitrogen gas is used as the nitrogen gas permeability R, and the performance of the coating film is evaluated from the perspective of the gas permeability of nitrogen gas. As mentioned above, when the low-pressure chamber Cb is maintained in a vacuum state and nitrogen gas at a predetermined pressure is introduced into the high-pressure chamber Ca, it is also possible to monitor the change in pressure in the low-pressure chamber Cb and calculate the nitrogen gas permeability R based on the pressure in the low-pressure chamber Cb.

[0065] In this embodiment, the steps shown in the flowchart in Figure 3 are carried out at multiple test temperatures T, including temperatures below 0°C. In this embodiment, the test temperatures T are -40°C, -20°C, -10°C, 0°C, 25°C, 40°C, 50°C, 70°C, and 106°C. Furthermore, in this embodiment, an epoxy resin having a benzene ring in part of the main chain of an amorphous molecular structure and in the additive is used as the paint. Here, 25°C is considered to be room temperature, and 106°C corresponds to the glass transition temperature of a coating film made of epoxy resin.

[0066] FIG. 5 is a schematic diagram of test results showing the change in the pressure difference Pd between the high temperature chamber Ca and the low temperature chamber Cb in the evaluation test device 101 for each test temperature T above room temperature.

[0067] In the figure, the horizontal axis represents time t, and the vertical axis represents the differential pressure Pd. The thick solid line La represents the differential pressure Pd at test temperature Tr=25°C, the dotted line Lb represents the differential pressure Pd at test temperature Tp1=40°C, the two-dot chain line Lc represents the differential pressure Pd at test temperature Tp2=50°C, the long dashed line Ld represents the differential pressure Pd at test temperature Tp3=70°C, and the one-dot chain line Le represents the differential pressure pd at test temperature Tp4=106°C.

[0068] Under high-temperature conditions above room temperature Tr, the differential pressure Pd is roughly the same at room temperature Tr and at Tp1 = 40°C, or is only slightly lower at Tp1 = 40°C. This indicates that there is no significant change in nitrogen gas permeability R between room temperature Tr and Tp1 = 40°C. In contrast, at Tp2 = 50°C, the differential pressure Pd is significantly reduced compared to Tp1 = 40°C, indicating that the nitrogen gas permeability R began to increase as the temperature increased from Tp1 = 40°C to Tp2 = 50°C. There was almost no change in differential pressure Pd between Tp2 = 50°C and Tp3 = 70°C, but at the glass transition temperature, Tp4 = 106°C, the differential pressure Pd again decreased sharply, meaning that the nitrogen gas permeability R increased sharply.

[0069] FIG. 6 is a schematic diagram of test results showing the change in the pressure difference Pd between the high temperature chamber Ca and the low temperature chamber Cb in the evaluation test device 101 for each test temperature T below room temperature.

[0070] In the figure, the horizontal axis represents time t, and the vertical axis represents the differential pressure Pd. The thick solid line La represents the differential pressure Pd at test temperature Tr=25°C, the dotted line Lf represents the differential pressure Pd at test temperature Tn1=0°C, the two-dot chain line Lg represents the differential pressure Pd at test temperature Tn2=-10°C, the long dashed line Lh represents the differential pressure Pd at test temperature Tn3=-20°C, and the one-dot chain line Li represents the differential pressure pd at test temperature Tn4=-40°C.

[0071] Under low-temperature conditions below room temperature Tr, from room temperature Tr=25°C to Tn2=-10°C, the lower the test temperature T, the more gradual the decrease in differential pressure Pd, which indicates that the nitrogen gas permeability R tends to decrease at least until Tn2=-10°C. In contrast, at Tn3=-20°C, the differential pressure Pd is lower than when room temperature Tr=25°C, and it can be seen that the nitrogen gas permeability R began to increase as the temperature decreased from Tn2=-10°C to Tn3=-20°C. Then, at Tn4=-40°C, the differential pressure Pd decreased sharply, that is, the nitrogen gas permeability R increased sharply.

[0072] FIG. 7 is a schematic diagram showing the relationship between the nitrogen gas permeability R of a coating film and the temperature T, with the horizontal axis representing the temperature T and the vertical axis representing the nitrogen gas permeability R.

[0073] 4 and 5, the nitrogen gas permeability R exhibits a minimum value at room temperature Tr=25°C or a temperature close to this, Tn1=0°C, and increases as the temperature T rises from above Tp1=40°C toward Tp4=106°C. On the other hand, the nitrogen gas permeability R begins to increase when the temperature T falls below Tn2=-10°C, and increases as the temperature T decreases toward Tn4=-40°C. Based on these results, FIG. 7 shows a schematic diagram of the relationship between temperature T and nitrogen gas permeability R.

[0074] In this embodiment, the temperature T for evaluating the nitrogen gas permeability R of the coating film is set to several temperatures T1 to T3, including T1, which is less than 0°C. Specifically, assuming the actual operating environment of the compressor 1 in the refrigeration cycle device C, T1 = -40°C, T2 = 25°C, and T3 = 100°C are set. T1 = -40°C is a temperature simulating a cooling environment caused by refrigerant returning from the evaporator, T2 = 25°C is a temperature simulating a normal state at room temperature, and T3 = 100°C is a temperature simulating a heating environment caused by refrigerant after compression. The temperatures T1 to T3 can be set appropriately depending on the actual operating environment of the compressor 1, i.e., the temperatures that the refrigerant can reach during operation of the compressor 1. Here, temperature T1 corresponds to the "first temperature" in this embodiment.

[0075] In step S206 of the flow chart shown in FIG. 3, the nitrogen gas permeability R is measured at each of the test temperatures T1=-40°C, T2=25°C, and T3=100°C, and the performance of the coating film is evaluated. Specifically, (a) if the nitrogen gas permeability R at T1=-40°C is 2500 [mol μm / (m 2 ·s·Pa)] or less, (b) nitrogen gas permeability R at T2 = 25°C is 150 [mol·μm / (m 2 · s · Pa)] or less, and (c) the nitrogen gas permeability R at T3 = 100 ° C is 2500 [mol · μm / (m 2 A sample having a viscosity of 1000 [mol·μm / (m 2 ·s·Pa)] corresponds to the “first threshold” of the gas permeability according to this embodiment, and R=150 [mol·μm / (m 2 ·s·Pa)] corresponds to the "second threshold value" of the gas permeability according to this embodiment.

[0076] After the paint is selected, the compressor 1, specifically the outer surface of the sealed case of the compressor body 1a and the outer surface of the case of the accumulator 1b, are powder coated, and then the compressor 1 is assembled. The assembly process after painting can be carried out in the same manner as before.

[0077] (Explanation of Action and Effect) In this embodiment, the nitrogen gas permeability R of the coating film formed on the outer surface of the case of the compressor 1, specifically, the compressor body 1a and the accumulator 1b, is (a) 2500 [mol μm / m 2 ·s·Pa] or less, (b) 150 [mol·μm / m 2 ·s·Pa] or less and (c) 2500 [mol·μm / m 2 By keeping the pressure [MPa] or less, it is possible to effectively suppress the permeation of moisture and oxygen through the coating film in the actual operating environment of the compressor 1, and to suppress the occurrence of rust in the base material, which is an iron-based metal material, throughout the entire case, thereby making it possible to provide a compressor 1 with higher reliability.

[0078] The compressor 1 is formed by dividing it into a low-pressure section (accumulator 1b) and a high-pressure section (compressor main body 1a), and a coating film having the above-mentioned specified nitrogen gas permeability R is formed on at least one of the case of the low-pressure section, i.e., the case of accumulator 1b, and the case of the high-pressure section, i.e., the sealed case 11 of the compressor main body 1a. This effectively suppresses not only the permeation of moisture and the like in the areas heated by the compressed refrigerant, but also the permeation in the areas cooled by the refrigerant returning from the evaporator, making it possible to suppress the occurrence of rust in both the low-pressure section and the high-pressure section.

[0079] As a specific example of a paint, by using an epoxy resin with a high cross-linking density and a benzene ring with a rigid molecular structure, it is possible to further reduce gas permeability and promote further improvement of the rust prevention performance of the paint.

[0080] In selecting the paint to be used for painting the case of the compressor 1, the gas permeability of the paint film was measured and performance evaluation was carried out based on this, which enabled us to confirm the rust prevention performance of the paint film from the perspective of gas permeability and select a more appropriate paint. By using nitrogen gas as the test gas, we were able to maintain a correlation in gas permeability with oxygen and moisture, which are the actual objects to be blocked, and it became possible to carry out performance evaluation safely and appropriately.

[0081] Furthermore, by measuring the gas permeability at a plurality of temperatures including a temperature below 0°C (first temperature) and evaluating the gas permeability of the coating film, it is possible to perform the evaluation under conditions that simulate the actual operating environment of the compressor 1 and to suppress the occurrence of rust in the case throughout the compressor 1. By evaluating the adhesion between the substrate and the coating film in addition to the gas permeability, it is possible to further improve the performance of the coating film.

[0082] By measuring the gas permeability at a first temperature and at room temperature and setting a second threshold value for comparison with the gas permeability at room temperature lower than the first threshold value for comparison with the gas permeability at the first temperature, it is possible to reflect the change in gas permeability according to temperature in the performance evaluation of the coating film, thereby making it possible to select a more appropriate coating material.

[0083] By setting the first temperature to a temperature of −40° C. or higher and −20° C. or lower, it becomes possible to perform a more appropriate evaluation taking into account the increasing tendency of gas permeability, specifically, nitrogen gas permeability R, relative to a decrease in temperature.

[0084] Furthermore, by preparing a coating sample F in the form of a film made from the paint and evaluating the performance of the coating based on the gas permeability of this sample F, it is possible to confirm the rust prevention performance of the paint in a relatively simple manner and select an appropriate paint.

[0085] Although several embodiments of the present invention have been described, these embodiments are presented as examples and are not intended to limit the scope of the invention. These novel embodiments can be embodied in various other forms, and various omissions, substitutions, and modifications can be made without departing from the spirit of the invention. These embodiments and their modifications are included within the scope and spirit of the invention, and are also included in the scope of the invention and its equivalents as defined in the claims.

[0086] C...refrigeration cycle device, 1...compressor, 1a...compressor body, 1b...accumulator, 11...sealed case, 11a...case body, 11b, 11c...end plate, 12...motor, 121...stator, 122...rotor, 13...compression mechanism, 131...cylinder, 132...rolling piston, 133...slide vane, 134...spring, 14...drive shaft, 15...sealed terminal, 16a...main bearing, 16b...auxiliary bearing, 21...suction pipe, 22...discharge pipe, 23...refrigerant introduction pipe, 2...four-way valve, 3...outdoor heat exchanger, 3'...outdoor fan, 4...expansion valve, 5...indoor heat exchanger, 5'...indoor fan, 6 (6a to 6f)...refrigerant piping, S...space inside the sealed case.

Claims

1. A compressor comprising: a compression mechanism for compressing a refrigerant; an electric motor for driving the compression mechanism; and a case for accommodating the compression mechanism and the electric motor, wherein the refrigerant compressed by the compression mechanism is discharged from the compressor through a space inside the case, and the compression mechanism is in a high-temperature atmosphere due to the compressed refrigerant, wherein the case is made of an iron-based metal material as a base material, and the nitrogen gas permeability of a coating film formed on the outer surface is (a) 2500 [mol μm / (m 2 .s.Pa)] or less at room temperature, and (b) 150 [mol.μm / (m 2 s Pa)] or less, and (c) at 100° C., it is 2500 [mol μm / (m 2 .s.Pa)] or less.

2. A compressor as described in claim 1, comprising: a low pressure section configured to introduce refrigerant before compression by the compression mechanism and be capable of separating liquid refrigerant contained in the refrigerant; and a high pressure section formed separately from the low pressure section and connected to the low pressure section so as to be able to introduce refrigerant after separation of the liquid refrigerant, wherein the case includes a first case of the low pressure section and a second case of the high pressure section, the compression mechanism and the electric motor are housed in the second case, and the coating is formed on the outer surface of at least one of the first case and the second case.

3. A compressor according to claim 1 or 2, wherein the coating is formed from an epoxy resin having a benzene ring in part of the main chain of a non-crystalline molecular structure and as an additive.

4. A method for manufacturing a compressor in which a compression mechanism for compressing a refrigerant and an electric motor for driving the compression mechanism are housed in a case, the method including a paint selection step of selecting a paint to be applied to the outer surface of the case, wherein in the paint selection step, the gas permeability of a coating film formed by the paint is measured at a plurality of temperatures including a first temperature below 0°C, or the gas permeability exhibited by the coating film at the plurality of temperatures is obtained, and a paint having a gas permeability within a predetermined range for each of the plurality of temperatures is selected.

5. A method for manufacturing a compressor as described in claim 4, wherein in the paint selection step, the multiple temperatures include the first temperature and room temperature, and a paint is selected whose gas permeability is equal to or lower than a predetermined first threshold value at the first temperature and equal to or lower than a predetermined second threshold value lower than the first threshold value at room temperature.

6. The method for manufacturing a compressor according to claim 5, wherein the first temperature is a temperature between -40°C and -20°C.

7. A method for evaluating paints for compressors used to paint a compressor in which a compression mechanism for compressing a refrigerant and an electric motor for driving the compression mechanism are housed in a case, the method comprising the steps of: preparing a sample in which the paint is formed into a film; measuring the gas permeability, which indicates the amount of gas that permeates the sample per unit time, at a plurality of temperatures including a first temperature below 0°C; and evaluating the performance of the coating film made from the paint based on the gas permeability measured at each of the plurality of temperatures.

Citation Information

Patent Citations

  • Compressor for refrigeration

    JP2010127272A

  • Hydrogen storage pellets

    JP2016502968A

  • Tantalum carbide-covered carbon material and process for producing the same

    WO2006085635A1