Equipment operation assistance system

The equipment operation support system addresses the challenge of determining equipment influence ranges in large-scale facilities by using an operation support device to display and simulate connection changes, thereby enhancing operational accuracy and safety.

WO2024204586A1PCT designated stage expired Publication Date: 2024-10-03OSAKA GAS CO LTD +1
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
PCT/JP2024/012744
Authority / Receiving Office
WO · WO
Patent Type
Applications
Current Assignee / Owner
Priority Date
2023-03-30
Filing Date
2024-03-28
Publication Date
2024-10-03

AI Technical Summary

Technical Problem

In large-scale facility environments, especially electrical systems, determining the range of influence of equipment during operation is challenging due to the lack of centrally managed diagrams, leading to potential human errors and incorrect operations.

Method used

An equipment operation support system that includes an operation support device with a display section, instruction reception, storage, and search units to check and display connection diagrams, allowing for simulated operations to reflect changes in equipment connections, thereby aiding in accurate determination of influence ranges and appropriate operations.

Benefits of technology

The system enables accurate determination of equipment influence ranges and supports appropriate operations by displaying connection diagrams and simulated operation results, reducing human errors and ensuring safe and efficient facility management.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure JP2024012744_03102024_PF_FP_ABST
    Figure JP2024012744_03102024_PF_FP_ABST
Patent Text Reader

Abstract

The purpose of the present invention is to perform operation assistance for carrying out an appropriate operation. The present invention comprises: an operation assistance device 21; an instruction receiving unit that is provided to the operation assistance device 21, that receives attribute information 35 which identifies operation target equipment 5 subject to operation assistance, and that receives a simulated operation instruction 36; and a simulated operation unit that outputs a simulated operation diagram 33 obtained by reflecting, in an extracted connection operation diagram 32, a change in the connection relation of equipment included in the connection operation diagram 32 when the equipment is operated in accordance with the simulated operation instruction 36. When the attribute information 35 is received, a connection operation diagram 32 including the operation target equipment 5 is displayed on a display unit. When the simulated operation instruction 36 is received, a simulated operation diagram 33 is displayed on the display unit.
Need to check novelty before this filing date? Find Prior Art

Description

Equipment operation support system

[0001] The present invention relates to a facility operation support system used when operating a facility in a facility environment configured by connecting a plurality of facilities.

[0002] An example of a connection relationship in an equipment environment is an electrical system that supplies power from a power source to multiple pieces of equipment. In an electrical system, one power source is connected to multiple pieces of equipment via a power control device that turns the power supply on and off (connects or disconnects the supply line). For example, a power control device installed in such an electrical system may be turned off (disconnected). The power control device supplies power to multiple pieces of equipment, and turning the power control device on and off affects multiple pieces of equipment. Therefore, if the power control device is carelessly turned off, the power supply to equipment that requires power may be stopped, which may cause a malfunction in which equipment that should not be stopped stops operating.

[0003] Therefore, when disconnecting a power control device, the power control device is disconnected while checking the range of influence of the power control device by referring to an electrical system diagram, manual, etc. However, electrical system diagrams are not necessarily created to cover the range of influence of the power control device, and are generally not managed centrally.

[0004] Therefore, as shown in Patent Document 1, there have been cases where equipment (facilities) are searched for using keywords for multiple P&IDs (piping and instrumentation diagrams, electrical system diagrams) that are not centrally managed, and multiple P&IDs are associated and displayed, and the equipment is operated while checking the scope of influence of the equipment using these.

[0005] Japanese Patent Application Publication No. 9-91327

[0006] However, in large-scale equipment environments, the scope of influence of each piece of equipment is vast, and even when checking the connection screen displaying organized information, it is not easy to determine the scope of influence of each piece of equipment, and human error may occur when operating the equipment.

[0007] In order to solve the above problems, an object of the present invention is to provide operation support for performing appropriate operations.

[0008] In order to achieve the above object, a characteristic configuration of an equipment operation support system according to one embodiment of the present invention is an equipment operation support system for checking the connection status of a plurality of pieces of equipment in an equipment environment, comprising: an operation support device; a display unit provided in the operation support device; an instruction receiving unit provided in the operation support device, which receives attribute information identifying an operation target equipment, which is the equipment that is the target of operation support, and receives a simulated operation instruction; a display control unit provided in the operation support device, which controls the display unit; a memory unit which stores a plurality of connection operation diagrams showing the connection relationships of the plurality of pieces of equipment; a search unit which searches for and extracts the connection operation diagrams in which the operation target equipment is included as the equipment; and a simulated operation unit which outputs, in response to the simulated operation instruction, a simulated operation diagram in which a change in the connection relationship of the equipment when the equipment included in the extracted connection operation diagram is operated is reflected in the connection operation diagram, and the display control unit, when receiving the attribute information, causes the display unit to display the connection operation diagram in which the operation target equipment is included

[0009] With this configuration, a connection operation diagram including the equipment to be operated identified by the attribute information is displayed, and a simulated operation diagram reflecting changes in the connection relationships of the connection operation diagram in response to simulated operation instructions is displayed, thereby making it possible to accurately determine the scope of the impact when operating the equipment to be operated, and to perform appropriate operations.

[0010] The attribute information may be displayed using an identification code, and the instruction receiving unit may read the identification code.

[0011] With this configuration, attribute information can be easily acquired and the equipment to be operated can be identified.

[0012] The instruction receiving unit may receive the attribute information by voice input or manual input.

[0013] With this configuration, it is not necessary to display identification information on the equipment to be operated, and attribute information can be easily acquired with a simple configuration to identify the equipment to be operated.

[0014] In addition, the memory unit may store related materials for the equipment in association with the equipment, the instruction receiving unit may receive a material display instruction to display the related materials, and the display control unit may display the related materials corresponding to the equipment to be operated on the display unit based on the material display instruction.

[0015] With this configuration, the suitability of the operation can be determined while referring to related materials related to the equipment to be operated, thereby enabling more appropriate operation.

[0016] The operation assistance device may also include the storage unit, the search unit, and the operation simulation unit.

[0017] This makes it possible to realize an operation assistance system that can provide appropriate operation assistance with a simple configuration.

[0018] The operation assistance device may further include a server that performs data communication with the operation assistance device, the server including the storage unit, the search unit, and the operation simulation unit.

[0019] With this configuration, the operation assistance device can be made into a simpler configuration, and an operation assistance system with excellent workability can be realized.

[0020] In addition, one server can support multiple operation assistance devices, and even when operating multiple related pieces of equipment that are located in distant locations, operation assistance can be easily provided that reflects the operation results of each device.

[0021] The facility environment may be an electrical system, and the facility may include a power supply operation device.

[0022] This allows for appropriate support for the operation of the power supply equipment.

[0023] The system may further include a procedure manual creation unit that creates a work procedure manual including information indicating the equipment to be operated and the order of work to be performed on the equipment to be operated, based on an operation log that records the simulated operation instructions.

[0024] This makes it easier to create work procedures for the equipment to be operated. Also, since the work procedures are created based on the simulated operation instructions (more specifically, the operation log, which is the history of the simulated operation instructions) while the operator is checking (simulating) the changes in the equipment on the simulated operation diagram, it is possible to create work procedures that allow the work to be carried out more safely, and a safe work environment can be created.

[0025] When the display control unit receives an instruction indicating that the state switching work of the equipment to be operated, which is included as a work target in the work procedure manual, has been completed, it may change the state of the equipment to be operated, which is displayed on the connection operation diagram, in real time to the state after the work and display it.

[0026] This allows the worker and the supervisor monitoring the work to easily grasp the progress of the work.

[0027] The storage unit may store a database that stores data for representing a plurality of connection operation diagrams showing current and future connection relationships in the facility.

[0028] This allows accurate confirmation of the current and future status of the facility, even when multiple tasks (construction works) are being carried out simultaneously on one facility, preventing work congestion.

[0029] The equipment environment may be a piping equipment, and the equipment may be a fluid control device that controls the flow of fluid through the piping equipment, and the simulated operation diagram may simulate changes in the state of the piping equipment in accordance with changes in the state of the fluid control device.

[0030] This allows for a safer working environment to be created in piping equipment where fluids flow.

[0031] FIG. 1 is a circuit diagram illustrating an electrical system according to the first embodiment. FIG. 2 is a diagram illustrating a power supply control panel according to the first embodiment. FIG. 3 is a diagram illustrating a schematic configuration of a power supply operation support system according to the first embodiment. FIG. 4 is a diagram illustrating functional blocks of the power supply operation support system according to the first embodiment. FIG. 5 is a diagram illustrating a simulated operation diagram according to the first embodiment. FIG. 6 is a diagram illustrating a processing flow for equipment maintenance according to the first embodiment. FIG. 7 is a diagram illustrating a schematic configuration of a valve operation support system according to a second embodiment. FIG. 8 is a diagram illustrating functional blocks of the valve operation support system according to the second embodiment. FIG. 9 is a diagram illustrating an example of a work procedure manual according to the second embodiment. FIG. 10 is a diagram illustrating an example of a piping and instrumentation diagram of piping equipment according to the second embodiment. FIG. 11 is a diagram for explaining a pinboard database that stores piping and instrumentation diagrams according to the second embodiment. FIG. 12 is a diagram illustrating an example of a simulated operation diagram according to the second embodiment. FIG. 13 is a diagram illustrating an example of a simulated operation diagram according to the second embodiment. FIG. 14 is a diagram illustrating an example of a workflow in a planning stage according to the second embodiment. FIG. 15 is a diagram illustrating an example of a workflow in a work execution stage according to the second embodiment. FIG. 16 is a diagram illustrating an example of a detail screen according to the second embodiment.

[0032] First Embodiment In an equipment environment in which a plurality of pieces of equipment 3 (see FIG. 1 ) are connected, an equipment operation support system supports the operation of the pieces of equipment 3 so that the scope of influence of the pieces of equipment 3 can be easily understood when operating the pieces of equipment 3. Hereinafter, a power operation support system 20 (see FIG. 1 ) that supports the operation of a power operation device 5 (see FIG. 1 , an example of an "equipment to be operated") will be described as an example in an electrical system 1 (see FIG. 1 , an example of an "equipment environment") that includes a power operation device 5 as the equipment 3.

[0033] [Electrical System] First, the electrical system 1 will be described with reference to FIGS.

[0034] As shown in Fig. 1, the electrical system 1 includes a plurality of pieces of equipment 3 to which power is supplied from a common power source 2 such as a power supply or a transformer, and a supply line 4 that supplies power from the power source 2 to each piece of equipment 3. A power supply operation device 5, which is a type of equipment 3, is provided on the supply line 4. The power supply operation device 5 can be switched between a connected state in which the supply line 4 is connected and a disconnected state in which the supply line 4 is disconnected. In the connected state, the supply line 4 supplies power, and in the disconnected state, the supply line 4 stops supplying power.

[0035] The electrical system 1 is subdivided into branch electrical systems 1a by a power control device 5. For example, in FIG. 1 , the electrical system 1 is subdivided into branch electrical systems 1a by a power control device 5a, branch electrical systems 1b by a power control device 5b, and branch electrical systems 1c by a power control device 5c. For example, power is supplied to equipment 3a provided in branch electrical system 1a when power control device 5a is connected, power is supplied to equipment 3b provided in branch electrical system 1b when power control device 5b is connected, and power is supplied to equipment 3c provided in branch electrical system 1c when power control device 5a and power control device 5c are connected. Furthermore, each equipment 3 may be connected to the supply line 4 via a selector switch 6. The selector switch 6 is a type of equipment 3 and can switch between connecting and disconnecting the supply line 4, controlling the power supply to each equipment 3. Although all equipment 3 in FIG. 1 are provided with selector switches 6, some or all of the equipment 3 may not be provided with selector switches 6.

[0036] As shown in FIG. 2 , multiple power control devices 5 are collected in one or more power control panels 10. Each power control device 5 includes a power switch 11, a meter 12 that displays power information, an indicator lamp 13 that indicates the connection status, and a QR code (registered trademark) 14 that identifies the power control device 5. The power switch 11 can switch between connecting and disconnecting the supply line 4, thereby controlling the supply of power to the corresponding electrical system 1. The QR code (registered trademark) 14 is an example of attribute information 35 (see FIG. 3 ). The attribute information 35 includes information for identifying the corresponding power control device 5 and may include various information such as the shape, name, and model of the power control device 5. The power control device 5 controls the supply of power to the corresponding electrical system 1 by operating the power switch 11. Note that at least some of the selector switches 6 may also be collected in one or more power control panels 10, similar to the power control devices 5. In this case, as with the power supply operation device 5, the operation section of the changeover switch 6 is provided with a power switch 11, a meter 12 that displays power information, an indicator lamp 13 that shows the connection status, and a QR code (registered trademark) 14 that identifies the power supply operation device 5.

[0037] [Power Operation Support System] Next, the configuration of the power operation support system 20 will be described using Figures 3 and 4 while also referring to Figure 1. First, the general configuration of the power operation support system 20 will be described.

[0038] As shown in FIG. 3 , the power operation support system 20 includes a portable operation support device 21, such as a tablet, and a server 22 capable of data communication with the operation support device 21. The power operation support system 20 uses the operation support device 21 to identify a power operation device 5 or a selector switch 6, which is the equipment to be operated and provides support for the operation of the power operation device 5 or the selector switch 6. A specific description will be given below, taking the operation of the power operation device 5 as an example. The operation support device 21 reads a QR code (registered trademark) 14 related to attribute information 35 to identify the power operation device 5. The QR code (registered trademark) 14 is provided on the power operation device 5, which is the equipment to be operated. The operation support device 21 transmits attribute information 35 of the identified power operation device 5 or information that can identify the power operation device 5 to the server 22. The attribute information 35 may include various information, but at least information that identifies (identifies) the power operation device 5 is transmitted.

[0039] The server 22 identifies an electrical system diagram (an example of a "connection operation diagram") 32 linked to the power operation device 5, which is the equipment to be operated, and the operation assistance device 21 displays the electrical system diagram 32. Furthermore, as will be described later, the operation assistance device 21 accepts a simulated operation instruction 36 and displays a simulated operation diagram 33 that reflects changes in the connection relationships associated with operations on the power operation device 5 and the selector switch 6 displayed on the electrical system diagram 32. The operator determines the appropriateness of the operation while referring to the displayed electrical system diagram 32 and simulated operation diagram 33, and operates the power operation device 5.

[0040] Next, a description will be given of specific functional configurations of the operation assistance device 21 and the server 22. As shown in Fig. 4, the operation assistance device 21 includes a display unit 25, a display control unit 26, an instruction receiving unit 27, a communication unit 28, and a storage unit 29.

[0041] The display unit 25 displays an operation menu, an electrical system diagram 32, a simulated operation diagram 33, etc., and accepts various operations under the control of the display control unit 26. The instruction accepting unit 27 includes a camera 34, accepts information on a QR code (registered trademark) 14 read by the camera 34 as attribute information 35, and receives operation information related to the operation accepted by the display unit 25. The operation information is information such as a simulated operation instruction 36 related to an operation on the power supply operation device 5 or the selector switch 6 of the displayed electrical system diagram 32. The instruction accepting unit 27 stores the received information such as the attribute information 35 and the simulated operation instruction 36 in the storage unit 29. The communication unit 28 transmits various information to and from the server 22. The communication unit 28 transmits the received attribute information 35, the simulated operation instruction 36, etc., to the server 22, and receives the electrical system diagram 32, the simulated operation diagram 33, etc. from the server 22. The storage unit 29 also stores an electrical system diagram 32, a simulated operation diagram 33, and the like received from the server 22 via the communication unit 28.

[0042] The operation assistance device 21 also has a function of determining whether the operation target equipment to be operated is appropriate. In this case, the display unit 25 receives other information and instructions in addition to the operation information. For example, prior to operation assistance, the display unit 25 can separately receive operation schedule information related to the operation target equipment (power operation device 5 or selector switch 6) to be operated. The instruction receiving unit 27 stores the received operation schedule information in the memory unit 29. When attribute information 35 is received during operation assistance, the instruction receiving unit 27 or another control unit (not shown) compares the operation target equipment (power operation device 5 or selector switch 6) corresponding to the operation schedule information with the operation target equipment (power operation device 5 or selector switch 6) corresponding to the attribute information 35, and controls the display control unit 26 to display whether they match or do not match on the display unit 25. Furthermore, the operation assistance device 21 may also include a warning unit 31, and when the operation target equipment (power operation device 5 or changeover switch 6) corresponding to the operation schedule information does not match the operation target equipment (power operation device 5 or changeover switch 6) corresponding to the attribute information 35, the instruction receiving unit 27 or another control unit (not shown) may determine that an attempt is being made to operate the wrong operation target equipment and cause the warning unit 31 to issue a warning. The warning unit 31 may be a warning lamp or a speaker that issues an alarm. The warning may also be displayed on the display unit 25.

[0043] The server 22 includes a communication unit 41 , a control unit 42 , an identification unit 43 , a storage unit 44 , a search unit 45 , and an operation simulation unit 46 .

[0044] The communication unit 41 transmits and receives various information to and from the operation assistance device 21 under the control of the control unit 42. For example, the communication unit 41 receives attribute information 35 and simulated operation instructions 36 from the operation assistance device 21, and transmits the electrical system diagram 32 and simulated operation diagram 33 to the operation assistance device 21. The control unit 42 stores the received attribute information 35 and simulated operation instructions 36 in the storage unit 44.

[0045] The identification unit 43, under the control of the control unit 42, identifies the power operation device 5 or the changeover switch 6 that is the equipment to be operated that corresponds to the received attribute information 35. The search unit 45, under the control of the control unit 42, identifies the electrical system 1 that includes the identified power operation device 5 or the changeover switch 6, and searches the storage unit 44 for the electrical system diagram 32 that corresponds to this electrical system 1. The searched electrical system diagram 32 is transmitted to the operation assistance device 21 via the communication unit 41 under the control of the control unit 42.

[0046] Based on the simulated operation instructions 36 received via the communication unit 41, the simulated operation unit 46 generates a simulated operation diagram 33 that reflects the operation instructions of the power operation device 5 and the selector switch 6 in the electrical system diagram 32. The simulated operation diagram 33 shows the state of power supply to the supply line 4 and the equipment 3 when the power operation device 5 and the selector switch 6 are switched between a connected state and a disconnected state. As a result, while checking the electrical system diagram 32 displayed on the operation assistance device 21, the operator performs simulated operations of the power operation device 5 and the selector switch 6 on the electrical system diagram 32 on the operation assistance device 21, and determines whether the operation is appropriate by checking the simulated operation diagram 33 that corresponds to the operation results.

[0047] [Electrical System Diagram and Simulated Operation Diagram] Next, specific examples of the electrical system diagram 32 and the simulated operation diagram 33 will be described with reference to FIG. 4 and using FIG. 1, FIG. 5, and FIG.

[0048] 1 is displayed on the display unit 25 of the operation support device 21, and illustrates the equipment 3, power supply operation device 5, selector switch 6, and the supply line 4 showing the connection relationship between these in the electrical system 1. Furthermore, the electrical system diagram 32 can accept, as a simulated operation instruction 36, an operation to switch the power supply operation device 5 and the selector switch 6 between a connected state and a disconnected state on the electrical system diagram 32 in a simulated manner.

[0049] For example, a touch panel is used as display unit 25, and each time a power operation device 5 or a selector switch 6 to be operated on electrical system diagram 32 is touched, that power operation device 5 or selector switch 6 switches between a connected state and a disconnected state. Alternatively, a switch (not shown) corresponding to each power operation device 5 and selector switch 6 may be displayed on the touch panel, and each time that switch is touched, that power operation device 5 or selector switch 6 switches between a connected state and a disconnected state. In this case, the switch may be displayed on the corresponding power operation device 5 or selector switch 6, or may be displayed together in a separately provided operation area such as an operation menu.

[0050] The simulated operation diagram 33 is a diagram showing the state in which power is supplied, corresponding to the state of the power operating device 5 and the selector switch 6 in accordance with the simulated operation instruction 36. The state in which power is supplied is shown by highlighting the supply line 4 and the equipment 3 that form the supply path 37 through which power is supplied by using different colors, or by hatching the power supply path 37 as in the example of FIG.

[0051] For example, when power control device 5a and power control device 5b are simulated to be in the disconnected state, power is not supplied from power source 2 to anywhere. Therefore, as shown in Fig. 5, the hatching and color highlighting indicating power supply path 37 are displayed only from power source 2 to power control device 5a and power control device 5b. Furthermore, when power control device 5a and selector switch 6a are simulated to be in the connected state, power is supplied to supply line 4a and equipment 3d. Therefore, as shown in Fig. 6, the hatching and color highlighting indicating power supply path 37 are displayed for power source 2, power control device 5a, supply line 4a, and equipment 3d.

[0052] [Power Operation Support] Next, a specific example of a processing flow for supporting power operation will be described using FIG. 7 with reference to FIGS. 1 and 4. FIG.

[0053] The operation of the power supply control panel 10 may involve simply turning on and off a specific power supply operation device 5 or changeover switch 6, or may involve turning on and off multiple power supply operation devices 5 or changeover switches 6 in an appropriate order. Furthermore, there may be cases where line blocking is performed after turning on and off one or multiple power supply operation devices 5 or changeover switches 6 for maintenance of the equipment 3, etc. A specific example of the processing flow will be described below, taking as an example a case where maintenance of the equipment 3 is performed using the power supply control panel 10, which involves operating the power supply operation device 5 (power operation). The need for maintenance of the equipment 3 is determined in a location away from the power supply control panel 10, such as a factory or office. Therefore, a worker (operator) determines the need for maintenance of the equipment 3 by himself or herself at the factory, etc., or receives instructions to maintain the equipment 3, and then begins the maintenance work.

[0054] First, when it is decided to perform maintenance on equipment 3, the equipment 3 that requires operation is identified from drawings such as electrical diagrams and procedure manuals stored in a factory, etc. Then, information related to the power operation device 5 that has been identified as needing to be turned on and off in association with the maintenance is input to the operation support device 21 as information related to the equipment to be operated (step #1 in FIG. 7 ). The input information related to the equipment to be operated is stored in the memory unit 29 under the control of the instruction receiving unit 27. The information related to the equipment to be operated is input manually or otherwise by operating the operation menu displayed on the display unit 25 to display a screen for inputting information related to the equipment to be operated.

[0055] Next, the worker (operator) moves from the factory or the like to the installation location of the power supply control panel 10. Then, the worker (operator) reads the QR code (registered trademark) 14 provided on the power supply operation device 5 of the power supply control panel 10 with the camera 34 of the operation support device 21 (step #2 in FIG. 7 ). The attribute information 35 obtained by reading the QR code (registered trademark) 14 is stored in the storage unit 29.

[0056] The display control unit 26 also displays, on the display unit 25, the name of the power control device 5 corresponding to the attribute information 35 as the equipment to be operated (step #3 in FIG. 7 ). The worker (operator) checks the displayed name, determines whether the power control device 5 to be operated is appropriate, and proceeds to the next step. If it is not appropriate, the worker (operator) is operating the wrong power control device 5, and re-reads the QR code (registered trademark) 14 provided on the appropriate power control device 5. At this time, the instruction receiving unit 27 compares the power control device 5 corresponding to the input operation schedule information with the power control device 5 corresponding to the attribute information 35. If they do not match, the instruction receiving unit 27 may perform a process to prompt the worker to read the QR code (registered trademark) 14 of another power control device 5, or may further cause the warning unit 31 to issue a warning.

[0057] In this way, operation plan information for the equipment to be operated is input in advance into the operation support device 21, and when the attribute information 35 of the equipment to be operated that is actually to be operated is read, it is possible to compare and confirm whether the equipment to be operated that is actually to be operated is appropriate equipment 3, and it is possible to prevent operations such as turning off the power supply from being performed on the wrong power supply operation device 5.

[0058] Next, the instruction receiving unit 27 controls the communication unit 28 to transmit the attribute information 35 stored in the storage unit 29 to the server 22 (step #4 in FIG. 7). The control unit 42 of the server 22 stores the attribute information 35 received via the communication unit 41 in the storage unit 44.

[0059] Next, the identification unit 43, under the control of the control unit 42, identifies the power control device 5 that is the operation target equipment corresponding to the received attribute information 35 (step #5 in FIG. 7 ). Then, the search unit 45 searches for and extracts the electrical system diagram 32 related to the identified power control device 5 from the electrical system diagrams 32 stored in the storage unit 44 (step #6 in FIG. 7 ). Under the control of the control unit 42, the communication unit 41 transmits the searched electrical system diagram 32 to the operation assistance device 21.

[0060] Next, the operation assistance device 21 stores the electrical system diagram 32 received via the communication unit 28 in the storage unit 29. Then, the display control unit 26 of the operation assistance device 21 displays the electrical system diagram 32 stored in the storage unit 29 on the display unit 25 (step #7 in FIG. 7 ). The displayed electrical system diagram 32 is the electrical system diagram 32 that includes the equipment 3 to which power is supplied from the power operation device 5 corresponding to the read QR code (registered trademark) 14.

[0061] The worker (operator) checks the scope of the impact of the power control device 5 to be operated while checking the displayed electrical system diagram 32. Furthermore, to accurately check the scope of the impact, a simulated operation of the power control device 5 is performed on the display unit 25. To do this, the worker (operator) taps the power control device 5 on the display unit 25 to input a simulated operation instruction 36 for switching the power control device 5 on and off (step #8 in FIG. 7 ). Here, the simulated operation target is not limited to the power control device 5, but may also be the selector switch 6 displayed on the electrical system diagram 32. The instruction receiving unit 27 stores the simulated operation instruction 36 input by touching the display unit 25 in the memory unit 29. The instruction receiving unit 27 also transmits the stored simulated operation instruction 36 to the server 22 via the communication unit 28. The control unit 42 of the server 22 stores the simulated operation instruction 36 received via the communication unit 41 in the memory unit 44.

[0062] Next, the operation simulation unit 46 outputs the operation simulation diagram 33 corresponding to the operation simulation instruction 36 under the control of the control unit 42 (step #9 in FIG. 7 ). As described above, the operation simulation diagram 33 is a diagram in which the change in the connection relationship of the supply lines 4 accompanying the operation performed on specific equipment 3, such as the power operation device 5 or the selector switch 6, in the electrical system 1 in accordance with the operation simulation instruction 36 is reflected in the electrical system diagram 32. The output operation simulation diagram 33 is transmitted to the operation assistance device 21 via the communication unit 41 under the control of the control unit 42.

[0063] The simulated operation diagrams 33 are prepared in advance for the number of change patterns, in which supply paths 37 corresponding to changes in the connection relationships of the supply lines 4 that change in response to operations performed on specific equipment 3, such as the power operation device 5 or the selector switch 6, are reflected in the electrical system diagram 32, and are stored in the storage unit 44. Then, the simulated operation diagram 33 corresponding to the received simulated operation instruction 36 is selected and output. Alternatively, the supply paths 37 may be prepared in advance for the number of change patterns of the supply paths 37 corresponding to changes in the connection relationships of the supply lines 4, the supply paths 37 may be selected in response to the input simulated operation instruction 36, and the selected supply paths 37 may be integrated with the electrical system diagram 32 to generate and output the simulated operation diagram 33.

[0064] The transmitted operation simulation diagram 33 is stored in the storage unit 29 via the communication unit 28. Upon receiving the operation simulation diagram 33, the display control unit 26 causes the display unit 25 to display the operation simulation diagram 33 stored in the storage unit 29. The worker (operator) checks the displayed operation simulation diagram 33 and, while repeatedly inputting the operation simulation instructions 36 as necessary, simulates that the appropriate equipment to be operated (such as the power operation device 5 and the selector switch 6) is operated in the appropriate order (step #10 in FIG. 7 ). The worker (operator) then performs operations such as turning off the power operation device 5 (the equipment to be operated) in the confirmed order (step #11 in FIG. 7 ).

[0065] Finally, the worker (operator) performs the necessary operations such as line blocking, and then operates the equipment 3 to be maintained (step #12 in FIG. 7).

[0066] As described above, prior to actual operation, a simulated operation of the equipment to be operated can be performed, and the range of impact associated with the operation can be displayed to provide operational assistance. This allows the operator to confirm whether the operation is appropriate before performing it, thereby preventing incorrect operations and enabling appropriate operations to be performed.

[0067] Second Embodiment Next, an equipment operation support system according to a second embodiment will be described with reference to Fig. 8 to Fig. 16. Fig. 8 is a diagram showing the schematic configuration of the equipment operation support system according to the second embodiment.

[0068] As shown in FIG. 8 , the second embodiment differs from the first embodiment in that an equipment operation support system (a valve operation support system 120 in this embodiment) creates a procedure manual (hereinafter referred to as a work procedure manual D1) for work (operation) on target equipment (a valve 105 in this embodiment) provided in an equipment environment (a piping equipment 101 in this embodiment). The piping equipment 101 in this embodiment includes a pipe 104 through which a fluid such as a flammable gas flows, and a plurality of valves 105 (an example of a fluid control device) disposed in the pipe 104. Note that the piping equipment 101 also includes equipment such as flanges and pumps, and the work included in the work procedure manual D1 may include checks on equipment other than the valves 105, such as pumps. The pipe 104 is branched and differentiated in the same manner as described in the first embodiment.

[0069] In the piping equipment 101, a plurality of works are performed on each of the plurality of valves 105. Hereinafter, the plurality of works will be collectively referred to as construction work. Construction work may be performed over a plurality of days on one piping equipment 101. For this reason, a plurality of works may be performed in parallel on one piping equipment 101.

[0070] [Outline of Valve Operation Support System] The valve operation support system 120 supports the operation (closing operation or opening operation) of at least one of the multiple valves 105 provided in the piping equipment 101 (plant).

[0071] The valve 105 may be configured to be manually openable and closable, or may be configured as an electromagnetic valve whose state can be switched by operating a valve control panel 110 located in a factory, as in the first embodiment. The valve control panel 110 may include a switch 113 that can switch the state of the valve 105 between an open state and a closed state, and a QR code (registered trademark) 114 for identifying the valve 105. The valve control panel 110 may also include an indicator lamp (not shown) that indicates the state of the valve 105.

[0072] The state of the valve 105 is switched to control the flow of fluid through the pipe 104. Specifically, when the valve 105 is open, the fluid flows through the pipe 104, and when the valve 105 is closed, the flow of the fluid is stopped.

[0073] 8 and 9, the valve operation support system 120 includes an operation support device 121 and a server 122 capable of data communication with the operation support device 121. Note that Fig. 9 is a diagram illustrating the functional blocks of the valve operation support system 120.

[0074] [Operation Support Device] In the second embodiment, the operation support device 121 includes a first operation support device 121a and a second operation support device 121b. In this embodiment, the first operation support device 121a is an operation support device 121 used by a monitor in a control room to check the work, and is, for example, a tablet terminal. The second operation support device 121b is an operation support device 121 brought to the site by a worker performing work on the valve 105, and is, for example, a smartphone. Note that the configurations of the first operation support device 121a and the second operation support device 121b are similar to the configuration of the operation support device 21 described with reference to FIG. 4 . However, the operation support device 121 may omit the camera 34.

[0075] 9, the server 122 further includes a procedure manual creation unit 47 in addition to the communication unit 41, control unit 42, identification unit 43, storage unit 44, search unit 45, and operation simulation unit 46 described in the first embodiment. In the second embodiment, the storage unit 44 stores a work procedure manual database DB1, a pinboard database DB2 (an example of a database), and a work result database DB3. The storage unit 44 is configured, for example, with a semiconductor memory, a magnetic disk device, or the like.

[0076] The work procedure manual database DB1 stores data indicating the work procedure manual D1 created by the procedure manual creation unit 47.

[0077] Pinboard database DB2 stores data representing a plurality of piping and instrumentation diagrams 132 and / or simulated operation diagrams 133, which represent the current and future states of piping equipment 101 and indicate the connection relationships of a plurality of valves 105 (pipes 104). Pinboard database DB2 stores information for indicating the states of all valves 105 provided in piping equipment 101 in chronological order. For example, pinboard database DB2 stores information for indicating the states of all valves 105 provided in piping equipment 101 at preset time intervals (e.g., every hour). The time intervals can be arbitrarily set by the system designer.

[0078] The work result database DB3 stores data indicating the history of work results.

[0079] The procedure manual creation unit 47 shown in FIG. 9 generates data indicating a work procedure manual D1 for smoothly progressing construction work (multiple tasks). The procedure manual creation unit 47 can transmit the generated data indicating the work procedure manual D1 to the operation assistance device 121 via the communication unit 41. When the operation assistance device 121 (the first operation assistance device 121a and / or the second operation assistance device 121b) receives the data indicating the work procedure manual D1 via the communication unit 28, the operation assistance device 121 stores the data in the storage unit 29. Furthermore, the operation assistance device 121 (the display control unit 26) displays the work procedure manual D1 on the display unit 25 based on the data indicating the work procedure manual D1. Hereinafter, the screen indicating the work procedure manual D1 displayed on the display unit 25 will be referred to as a work procedure manual screen DG1.

[0080] FIG. 10 is a diagram showing an example of the work procedure manual D1. As shown in FIG. 10, the work procedure manual D1 includes at least information indicating the order in which the work is to be performed, the work procedure (the work content), the person in charge of the work, and the progress of the work. Note that for work that does not involve opening or closing the valve 105 (for example, the pre-work meeting shown in No. 1 in FIG. 10), the operator can input the work by using a fixed phrase stored in the operation support device 121 or the server 122. However, the operator can also freely input sentences other than the fixed phrases.

[0081] In this embodiment, the procedure manual creation unit 47 creates data for the work procedure manual D1 based on an operation log that records the simulated operation instructions 136 (touch operation instructions on the screen) made by the operator on a screen displaying the piping and instrumentation diagram 132 and / or the simulated operation instructions 136.

[0082] The identification unit 43 shown in FIG. 9 identifies the valve 105 corresponding to the attribute information 135 received from the operation assistance device 121, and the search unit 45 extracts data indicating a piping and instrumentation diagram 132 (an example of a connection operation diagram) corresponding to the identified valve 105 from the storage unit 44. The control unit 42 transmits the data indicating the extracted piping and instrumentation diagram 132 to the operation assistance device 121 via the communication unit 41. When the operation assistance device 121 (the first operation assistance device 121a and / or the second operation assistance device 121b) receives the data indicating the piping and instrumentation diagram 132 via the communication unit 28, the operation assistance device 121 (the display control unit 26) displays the piping and instrumentation diagram 132 on the display unit 25 based on the data indicating the piping and instrumentation diagram 132. Hereinafter, the piping and instrumentation diagram 132 displayed on the display unit 25 may be referred to as a piping and instrumentation diagram screen G1 (see FIG. 11 ).

[0083] 11 is a diagram showing an example of a piping instrumentation diagram 132 of the piping equipment 101. The piping instrumentation diagram 132 shows the connection relationships of multiple valves 105 (pipes 104) in the piping equipment 101. Note that, hereinafter, valves 105 in a closed state are shown filled in black, and valves 105 in an open state are shown white.

[0084] 12 , in this embodiment, the piping and instrumentation diagram 132 includes a plurality of piping and instrumentation diagrams 132 in different states at different dates and times. Specifically, the piping and instrumentation diagram 132 includes a piping and instrumentation diagram 132 that shows the state of the piping equipment 101 (the plurality of valves 105) at the current time (e.g., the time when the piping and instrumentation diagram 132 is displayed on the display unit 25) and a piping and instrumentation diagram 132 that shows the state of the piping equipment 101 (the plurality of valves 105) from the current time onward. The plurality of piping and instrumentation diagrams 132 are stored in the storage unit 44 (pinboard database DB2) of the server 122. By specifying a date and time, the operator can refer to the piping and instrumentation diagram 132 for the specified date and time.

[0085] The operation simulation unit 46 shown in FIG. 9 generates data representing an operation simulation diagram 133 (see FIGS. 13A to 13C ). Specifically, the operation simulation unit 46 generates data for the operation simulation diagram 133, which simulates the state of the piping equipment 101 changing in response to an operation simulation instruction 136 on a screen displaying the piping and instrumentation diagram 132 shown in FIG. 11 , i.e., on the piping and instrumentation diagram screen G1, or on a screen displaying the operation simulation diagram 133. The state of the piping equipment 101 changes when the state of the valve 105 changes in response to the operation simulation instruction 136 on the piping and instrumentation diagram screen G1 or on a screen displaying the operation simulation diagram 133. After generating the data for the operation simulation diagram 133, the operation simulation unit 46 transmits the data to the operation assistance device 121. The operation assistance device 121 (display unit 25) displays the operation simulation diagram 133 based on the data transmitted from the server 122 (operation simulation unit 46). Hereinafter, the operation simulation diagram 133 displayed on the display unit 25 will be referred to as an operation simulation screen G2.

[0086] In other words, the simulated operation diagram 133 shown in Figures 13B to 13C is a diagram that simulates the change in connection relationship that occurs with the simulated operation instruction 136 (touch operation in this embodiment) for the valve 105 displayed on the simulated operation screen G2 shown in Figure 13A, and shows the state of the piping equipment 101 when the state of the valve 105 is simulated switched.

[0087] 13B and 13C, the simulated operation screen G2 visually displays and simulates changes in the state of the piping equipment 101 in accordance with changes in the state of the valve 105 in response to the simulated operation instruction 136. Specifically, the simulated operation screen G2 displays the direction of fluid flow, and the pipes 104 that are the start and end points of the isolation area are depicted as being different from the pipes 104 in other areas. Note that by connecting the pipes 104 in the isolation area by the shortest distance, the operator can identify areas where fluid accumulation may occur when nitrogen is injected (purged) to remove flammable gases.

[0088] For example, in the simulated operation screen G2 shown in Figure 13A, when valve 105a (hereinafter referred to as the first operation target valve 105a) and valve 105b (hereinafter referred to as the second operation target valve 105b) are switched from an open state to a closed state, a liquid seal point (liquid seal state) where fluid remains in the piping 104 between the first operation target valve 105a and the second operation target valve 105b is displayed, as shown in Figure 13B.

[0089] 13B and 13C, when valve 105c (hereinafter referred to as third valve 105c) and valve 105d (hereinafter referred to as fourth valve 105d) that are downstream of first valve 105a and different from second valve 105b, and valve 105e (hereinafter referred to as fifth valve 105e) that are upstream of third valve 105c and fourth valve 105d are switched from the closed state to the open state, the liquid seal state is released, but the remaining liquid location (residual liquid state) in pipe 104 is displayed. Note that depending on the pressure when valve 105 (at least one of third valve 105c, fourth valve 105d, and fifth valve 105e) is open, the remaining liquid state as shown in FIG. 13C may not occur.

[0090] The piping 104 in a location that is in a liquid-sealed state, a residual liquid state, etc. is displayed by the display unit 25 in a different color, a different line type, a different thickness, and / or hatching from the piping 104 in other locations.

[0091] In other words, the simulated operation screen G2 visually displays the change in the state of the piping equipment 101 in accordance with the change in the state of the valve 105 due to the simulated operation instruction 136, making it easier for the operator to understand the change in the state of the piping equipment 101.

[0092] The operation simulation unit 46 may use AI technology to generate the data for the operation simulation diagram 133. Specifically, the data for the operation simulation diagram 133 may be generated using a trained model that has been machine-learned in advance by associating information indicating the pressure of the fluid (in a static state) and the flow rate of the fluid as parameters with the piping 104, and inputting the parameters of the piping 104 and the parameters of the valve 105 (information indicating the state of the valve 105), and information indicating the state of the fluid as training data.

[0093] Next, the flow in the planning stage of construction work will be described with reference to Figures 8 to 14. Figure 14 is a diagram showing an example of a workflow in the planning stage. Note that, although the following describes a case where the work procedure manual D1 is created by the first operation support device 121a, the work procedure manual D1 can also be created by the second operation support device 121b.

[0094] 14 , once construction work is planned (step #11), the operator calls up the piping and instrumentation diagram 132 (step #12). Specifically, the operator operates the first operation support device 121a to specify the planned construction date and time and the valve 105, which is the equipment to be operated (in this embodiment, the operator inputs the attribute information 135 of the valve 105, which is the equipment to be operated). In response, the display control unit 26 of the first operation support device 121a transmits information indicating the specified date and time and the attribute information 135 of the valve 105, which is the equipment to be operated, to the server 122 via the communication unit 28, and requests transmission of the piping and instrumentation diagram 132 data.

[0095] When a request is made to transmit data on the piping and instrumentation diagram 132, the control unit 42 of the server 122 extracts data indicating the piping and instrumentation diagram 132 for the specified date and time from the data on the piping and instrumentation diagram 132 stored in the pinboard database DB2, among the piping and instrumentation diagrams 132 including the valve 105 identified by the attribute information 135, and transmits the extracted data to the operation support device 121 (the first operation support device 121a in the example shown in FIG. 14 ). The first operation support device 121a displays the piping and instrumentation diagram 132 (piping and instrumentation diagram screen G1) on the display unit 25 (a touch panel in this embodiment) based on the received data.

[0096] The operator issues a simulated operation instruction 136 on the piping and instrumentation diagram screen G1 (or the simulated operation screen G2) (step #13). For example, the operator sequentially selects valves 105, which are the equipment to be operated, from the piping and instrumentation diagram screen G1 (or the simulated operation screen G2) in the order of the planned work, and sequentially switches the states of the valves 105. The display control unit 26 records an operation log indicating the operator's simulated operation instruction 136 (the selected valves 105 and the order of selection).

[0097] Thereafter, in response to the operator's operation to complete the simulated operation instruction 136 or to instruct the creation of the work procedure manual D1, the procedure manual creation unit 47 generates data indicating the work procedure manual D1 based on the operation log (step #14). Specifically, data indicating the work procedure manual D1 (see FIG. 10 ) is generated (step #14), in which the selected valves 105 are clearly indicated (e.g., listed) to be performed in the selected order. The generated data indicating the work procedure manual D1 is stored in the work procedure manual database DB1. For example, the work procedure manual database DB1 stores data indicating the work name (e.g., closing the inlet valve of the ____ meter), the work order (e.g., No. 2), information identifying the valve 105 to be operated (e.g., the inlet valve of the ____ meter), the content of the work procedure (e.g., closing), the work date and time (e.g., December 22, 2023, 1:00 PM), the person in charge, and the like, in association with each other.

[0098] The created work procedure manual D1 must be approved by an approver (e.g., a superior) using the operation support device 121 or another device before the operator goes to the work site (step #15). Data indicating that the approval has been received is transmitted from the operation support device 121 or another device to the server 122.

[0099] When the control unit 42 of the server 122 receives the data indicating the approval, it updates the pinboard database DB2 to reflect the state of the valve 105 that changes as a result of the work included in the approved work procedure manual D1 (step #16). For example, the pinboard database DB2 associates and stores data indicating information that identifies the valve 105 (e.g., "XX meter inlet valve"), the state of the valve 105 (e.g., "closed state"), and the duration of the state of the valve 105 (e.g., from 9:00 AM on December 21, 2023 to 1:05 PM on December 22, 2023).

[0100] As described above, multiple construction works may be scheduled in parallel for the piping equipment 101. Therefore, if work overlaps with the same valve 105, that is, if work is scheduled for the same date and time, the control unit 42 sends an alert indicating that the work overlaps to the operation support device 121 (the first operation support device 121a and / or the second operation support device 121b), and causes the warning unit 31 of the operation support device 121 to issue the alert. This allows the operator to review the work procedure manual D1.

[0101] It is also possible that after the work procedure manual D1 is created, tasks for the equipment to be operated may be changed, deleted, and / or added. In this case, the operator can update a previously created work procedure manual D1 by retrieving it from the work procedure manual D1 (data) already stored in the work procedure manual database DB1. In this case, it is possible that the state of the valve 105, which is the equipment to be operated, may differ between the time the data for the work procedure manual D1 was stored in the work procedure manual database DB1 (hereinafter referred to as the previous creation time) and the time the work procedure manual D1 is retrieved from the work procedure manual database DB1 (hereinafter referred to as the current creation time). Therefore, the control unit 42 causes the warning unit 31 of the operation support device 121 to issue an alert to notify the operator that there is a valve 105 whose state has changed between the previous creation time and the current creation time. This allows the operator to review the work procedure manual D1. In other words, even when multiple construction projects are being carried out simultaneously on a single piece of equipment, the operator can accurately check the state of the piping equipment 101 (valves 105) and prevent work congestion.

[0102] [Work Implementation] Next, the flow during work implementation will be described with reference to Figures 8 to 16. During work implementation, a monitor in the control room monitors the work using the first operation support device 121a, while a worker heads to the site with the second operation support device 121b. Figure 15 is a diagram showing an example of a work flow during the work implementation stage. Figure 16 is a diagram showing an example of the details screen G3.

[0103] When the worker arrives at the work site, the worker displays the work procedure manual D1 (work procedure manual screen DG1) on the display unit 25 of the second operation support device 121b. The worker performs the work in accordance with the work procedure manual D1 while viewing the work procedure manual D1 (step #21). The worker may perform the work in accordance with the procedure described with reference to FIG. 7 in the first embodiment, for example. The worker checks the valve 105 of the equipment to be operated and switches the state of the valve 105, etc.

[0104] In this embodiment, the display control unit 26 of the second operation support device 121b can also display detailed work items 134 showing details of the selected work on the display unit 25, as shown in FIG. 16 . Hereinafter, the detailed work items 134 displayed on the display unit 25 will be referred to as a detail screen G3. The detail screen G3 is displayed when a desired work is selected from the items (work) displayed on the work procedure manual screen DG1, which displays the work procedure manual D1. Note that data showing the detail screen G3 may be generated in advance and stored in the storage unit 29 of the second operation support device 121b, or may be generated by the display control unit 26 in response to an operation.

[0105] The details screen G3 may include a scheduled date for performing the work, the order of the work, detailed information about the valve 105 of the equipment to be operated, and a confirmation button B1. The confirmation button B1 is a button for confirming that the state of the valve 105 of the equipment to be operated has been switched.

[0106] When the operator completes one task included in the work procedure manual D1 (step #21), the operator can record the completion of the task (the completion of switching the state of the valve 105, which is the equipment to be operated) in the second operation support device 121b by operating (pressing) the confirmation button B1 (step #22). In response, the display control unit 26 of the second operation support device 121b displays the completion of the task on the display unit 25 (step #23). Specifically, as shown in FIG. 10 , the display control unit 26 of the second operation support device 121b displays a check mark CH in the progress column of the task in the work procedure manual D1 (work procedure manual screen DG1). At the same time, information indicating the completion of the task is transmitted from the second operation support device 121b to the first operation support device 121a (e.g., transmitted from the second operation support device 121b to the first operation support device 121a via the server 122). When the first operation support device 121a receives information indicating the completion of one task, the display control unit 26 of the first operation support device 121a changes the state of the valve 105 on the piping and instrumentation diagram 132 (piping and instrumentation diagram screen G1) displayed on the display unit 25 to the state after the task (after switching) in real time. In other words, the completion of the task is displayed in real time on the piping and instrumentation diagram 132 (step #23). As a result, the monitor (and worker) monitoring in the control room can easily grasp the progress of the task.

[0107] When all the work in the work procedure manual D1 is completed by repeating the processes of steps #21 to #23, the worker (or operator) operates the operation support device 121 to store information indicating the history of the work that has been performed in the work result database DB3. For example, the work result database DB3 stores data indicating the work content (e.g., closing the inlet valve of a certain meter), the date and time of the work (e.g., 13:00 on December 22, 2023), and the like, in association with each other.

[0108] As described above, according to the second embodiment, the work procedure manual D1 is created based on the operation log of the simulated operation instructions 136, which facilitates the work of the work procedure manual D1 for the work on the valve 105. Furthermore, the work procedure manual D1 is created based on the simulated operation instructions 136 (the operation log of the simulated operation instructions 136) while the operator is checking the changes in the piping equipment 101 on the simulated operation diagram 133, so that the work procedure manual D1 that allows the work to be carried out more safely can be created, and a safe work environment can be created.

[0109] (1) The equipment to be operated is not limited to the power operation device 5, but may be a changeover switch 6 or other operable equipment 3. As in the above embodiment, the power operation support system 20 identifies the electrical system 1 including the target equipment from the attribute information 35 corresponding to the equipment to be operated, and displays an electrical system diagram 32 corresponding to this electrical system 1 and a simulated operation diagram 33 corresponding to the input simulated operation instruction 36 to support the operation.

[0110] (2) In each of the above embodiments, the operation assistance device 21 (the operation assistance device 121 in the second embodiment, the same applies hereinafter) may display not only the simulated operation diagram 33 (the simulated operation diagram 133 in the second embodiment, the same applies hereinafter) but also related materials related to the equipment to be operated and other equipment 3. For example, the related materials include operation procedures, various drawings, instruction manuals, specifications, and various books. The related materials are pre-stored in the storage unit 44 of the server 22. The instruction receiving unit 27 of the operation assistance device 21 receives a material display instruction and transmits the material display instruction to the server 22 via the communication unit 28. The server 22 reads out related materials related to the equipment to be operated identified by the attribute information 35 (the attribute information 135 in the second embodiment, the same applies hereinafter) from the storage unit 44 and transmits them to the operation assistance device 21 via the communication unit 41. The display control unit 26 of the operation assistance device 21 displays the received related materials on the display unit 25. By displaying the related materials, the worker (operator) can easily check the related materials and confirm appropriate operations.

[0111] (3) In each of the above embodiments, the equipment environment is not limited to a power supply system including a power supply operating device 5, but may also be a collection of equipment 3 that is composed of various equipment 3 and whose interconnected relationships change by operating the equipment 3 (equipment to be operated).

[0112] For example, as described in the second embodiment, the facility environment may be a supply facility that supplies fluids such as gas or tap water. Such supply facility includes a valve as the facility to be operated. The facility operation support system according to this embodiment identifies the valve as the facility to be operated based on attribute information 35, displays a connection operation diagram for the supply facility within the range affected by the operation of the valve, and receives a simulated operation instruction 36 (a simulated operation instruction 136 in the second embodiment; the same applies below) to display a simulated operation diagram 33 corresponding to the operation of the valve. In addition to the change in the connection state of the pipe (supply line 4) corresponding to the valve operation, the simulated operation diagram 33 may also display the reading of an indicator located at a predetermined location on the pipe (supply line 4).

[0113] This configuration makes it possible to check changes in the facility environment caused by valve operation and to confirm the suitability of the operation, thereby ensuring appropriate operation.

[0114] (4) In each of the above embodiments, the operation of the equipment to be operated is not limited to on / off, and may also be adjustment of the supply amount. For example, if the equipment to be operated is a valve, the valve opening may be operated as the simulated operation instruction 36. Furthermore, if the equipment to be operated is a power operating device 5, the amount of power supply may be operated as the simulated operation instruction 36. When simulating an adjustment of the supply amount, the simulated operation diagram 33 displays a change in state according to the adjusted supply amount.

[0115] (5) In each of the above embodiments, the configuration is not limited to the configuration in which the simulated operation diagram 33 and the supply paths 37 corresponding to changes in the connection relationships of the supply lines 4 and the like are prepared in advance, but a configuration in which a program is embedded in the electrical system diagram 32 and the program is run to display the supply paths 37 on the electrical system diagram 32 (connection operation diagram) in response to the simulated operation instructions 36 and generate the simulated operation diagram 33 is also possible. This eliminates the need to prepare a large number of simulated operation instructions 36 in advance, and allows for more efficient operation support.

[0116] Furthermore, the simulated operation diagram 33 does not have to be a drawing, but may be information showing changes in the state of the facility environment. For example, the simulated operation diagram 33 may be a table listing the facilities 3 to which power is supplied and the facilities 3 into which fluid flows, or a table adding the supply and inflow amounts.

[0117] (6) In each of the above embodiments, the server 22 (the server 122 in the second embodiment, and the same below) may correspond to a plurality of operation assistance devices 21 (the operation assistance devices 121 in the second embodiment, and the same below), and the simulated operation diagram 33 may be configured to be able to constantly reflect the state of the operable equipment 3. With such a configuration, when a plurality of pieces of equipment to be operated are operated in relation to each other, it is possible to perform simulated operations of one piece of equipment to be operated while reflecting the actual operation of the other piece of equipment to be operated, and it is possible to provide appropriate operation assistance even for operations that span a plurality of pieces of equipment to be operated.

[0118] (7) In each of the above embodiments, the operation assistance device 21 (the operation assistance device 121 in the second embodiment) includes a processor such as a CPU. The operation assistance device 21 may be configured as hardware, or at least some of its functions may be configured as software. In this case, the software is stored in the storage unit 29 and operated by the processor. The configuration of the functional blocks is also not limited to the above configuration, and each functional block may be appropriately aggregated or subdivided. Similarly, the server 22 includes a processor such as a CPU. The server 22 may also be configured as hardware, or at least some of its functions may be configured as software. In this case, the software is stored in the storage unit 44 and operated by the processor. The configuration of the functional blocks is also not limited to the above configuration, and each functional block may be appropriately aggregated or subdivided.

[0119] (8) In each of the above embodiments, at least one of the identification unit 43, the search unit 45, and the operation simulation unit 46 may be provided in the operation assistance device 21 (the operation assistance device 121 in the second embodiment) rather than the server 22 (the server 122 in the second embodiment). When all of these are provided in the operation assistance device 21, the operation assistance system (the power supply operation assistance system 20 in the first embodiment, and the valve operation assistance system 120 in the second embodiment) may be configured without including the server 22. In this case, the operation assistance device 21 selects the electrical system diagram 32 (connection operation diagram), and selects or generates the operation simulation diagram 33. Furthermore, at least one of the identification unit 43, the search unit 45, and the operation simulation unit 46 may be configured independently of the operation assistance device 21 and the server 22.

[0120] (9) In the above embodiments, the attribute information 35 is identified by the QR code (registered trademark) 14. However, the attribute information 35 is not limited to the QR code (registered trademark) 14 and may be identified by various identification codes.

[0121] For example, an identification code such as a barcode can be used as the identification code, or the name of the equipment to be operated itself can be used. Furthermore, the attribute information 35 may be location information of the equipment to be operated, and the location information may include, for example, latitude, longitude, and height from a reference point (e.g., above sea level). The attribute information 35 may be input by reading it from a camera 34, manually inputting (inputting manually) from a keyboard, or by voice input from a microphone. Instead of the QR code (registered trademark) 14, an RFID (radio frequency identifier) ​​tag may be provided on the power supply operation device 5 (valve), and the attribute information 35 stored in the RFID tag may be read by a reader provided in the operation support device 21.

[0122] In addition, the configurations disclosed in the above embodiments (including other embodiments, the same applies below) can be applied in combination with configurations disclosed in other embodiments, as long as no contradiction arises. Furthermore, the embodiments disclosed in this specification are examples, and the embodiments of the present invention are not limited to these, and can be modified as appropriate within the scope that does not deviate from the purpose of the present invention.

[0123] The present invention can be applied to support equipment operation in various equipment environments that include operable equipment.

[0124] LIST OF SYMBOLS 1 Electrical system (equipment environment) 3 Equipment 5 Power supply operation device (equipment to be operated) 6 Changeover switch (equipment to be operated) 14 QR code (registered trademark) (identification code) 20 Power supply operation support system (equipment operation support system) 21 Operation support device 22 Server 25 Display unit 26 Display control unit 27 Instruction reception unit 28 Communication unit 29 Memory unit 32 Electrical system diagram (connection operation diagram) 33 Simulated operation diagram 35 Attribute information 36 Simulated operation instruction 41 Communication unit 42 Control unit 43 Identification unit 44 Memory unit 45 Search unit 46 Simulated operation unit 47 Procedure manual creation unit 101 Piping equipment (equipment environment) 105 Valve (equipment to be operated: fluid control device) 120 Valve operation support system (equipment object support system) 121 Operation support device 122 Server 132 Piping and instrumentation diagram (connection and operation diagram) 133 Simulated operation diagram 135 Attribute information 136 Simulated operation instructions D1 Work procedure manual DB2 Pinboard database (database)

Claims

1. An equipment operation support system for checking a connection state of a plurality of pieces of equipment in an equipment environment, comprising: an operation support device; a display unit provided in the operation support device; an instruction receiving unit provided in the operation support device for receiving attribute information identifying an operation target equipment, which is the equipment that is the target of operation support, and for receiving a simulated operation instruction; a display control unit provided in the operation support device for controlling the display unit; a memory unit for storing a plurality of connection operation diagrams showing the connection relationships of the plurality of pieces of equipment; a search unit for searching for and extracting the connection operation diagram in which the operation target equipment is included as the equipment; and a simulated operation unit for outputting, in response to the simulated operation instruction, a simulated operation diagram in which a change in the connection relationship of the equipment when the equipment included in the extracted connection operation diagram is operated, 2. The equipment operation support system according to claim 1, wherein the attribute information is displayed using an identification code, and the instruction receiving unit reads the identification code.

3. The equipment operation support system according to claim 1, wherein the instruction receiving unit receives the attribute information by voice input or manual input.

4. The equipment operation support system of claim 1, wherein the memory unit stores related materials for the equipment in association with the equipment, the instruction receiving unit receives a material display instruction to display the related materials, and the display control unit displays the related materials corresponding to the equipment to be operated on the display unit based on the material display instruction.

5. The equipment operation support system according to claim 1, wherein the operation support device comprises the memory unit, the search unit, and the operation simulation unit.

6. The equipment operation support system according to claim 1, further comprising a server for data communication with said operation support device, said server comprising said memory unit, said search unit, and said operation simulation unit.

7. An equipment operation support system according to any one of claims 1 to 6, wherein the equipment environment is an electrical system, and the equipment includes a power supply operation device.

8. The equipment operation support system of claim 1, further comprising an instruction manual creation unit that creates a work instruction manual including information indicating the equipment to be operated and the order of work to be performed on the equipment to be operated based on an operation log that records the simulated operation instructions.

9. The equipment operation support system of claim 8, wherein when the display control unit receives an instruction indicating that the state switching work of the equipment to be operated, which is included as a work target in the work procedure manual, has been completed, the display control unit changes in real time the state of the equipment to be operated displayed on the connection operation diagram to the state after the work and displays it.

10. The equipment operation support system of claim 1, wherein the memory unit stores a database that stores data for representing a plurality of connection operation diagrams showing current and future connection relationships in the equipment.

11. The equipment operation support system of claim 1, wherein the equipment environment is a piping equipment, the equipment is a fluid control device that controls the flow of fluid through piping provided in the piping equipment, and the simulated operation diagram simulates changes in the state of the piping equipment in accordance with changes in the state of the fluid control device.