Immersed tube capable of reducing weight of reinforced concrete

By incorporating weight-reducing components and pre-embedded steel pipe assemblies within the immersed tube body, the problem of insufficient water depth during floating of the immersed tube was solved, resulting in safer and more economical floating and usage effects.

WO2024234536A1PCT designated stage expired Publication Date: 2024-11-21CCCC FOURTH HARBOR ENG CO LTD +1
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
PCT/CN2023/123663
Authority / Receiving Office
WO · WO
Patent Type
Applications
Current Assignee / Owner
Priority Date
2023-05-16
Filing Date
2023-10-10
Publication Date
2024-11-21

AI Technical Summary

Technical Problem

The existing immersed tubes are difficult to float in water depth, which makes floating difficult and the safety factor is low, especially in urban inland waterways.

Method used

Weight reduction components are installed inside the immersed tube body to reduce weight through cavities. After floating, concrete is poured into the cavities, and pre-embedded components are formed in combination with pre-embedded steel pipes to improve the safety and quality of floating.

Benefits of technology

The reduced weight of the immersed tubes allows for shallower draft during floating, improving floating safety, reducing the depth of river excavation, saving on project investment, and ensuring the quality of the immersed tubes in use.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN2023123663_21112024_PF_FP_ABST
    Figure CN2023123663_21112024_PF_FP_ABST
Patent Text Reader

Abstract

The present invention relates to an immersed tube capable of reducing weight of reinforced concrete, comprising a body. The reinforced concrete of the body is internally provided with a weight reducing component; the weight reducing component is provided with a cavity; the cavity is used for pouring concrete. The weight reducing component is arranged in the body of the immersed tube, and the weight reducing component reduces the weight of the immersed tube by means of the cavity, so that the immersed tube needs a shallower draft during floating transportation, floating transportation of the immersed tube is easier, and the safety of floating transportation of the immersed tube is improved; moreover, excavation deepening of a river below the floating transportation route of the immersed tube can be reduced, and engineering investment can be saved. Additionally, concrete can be poured into the cavity after the floating transportation of the immersed tube is completed or the immersed tube is transported to a middle position, so that the quality and safety of the immersed tube during use can be guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

A submerged tube for reducing the weight of reinforced concrete

[0001] This application claims priority to Chinese patent application No. 202310551034.9 filed on May 16, 2023. Technical Field

[0002] The present invention relates to the technical field of immersed tubes, in particular to an immersed tube capable of reducing the weight of reinforced concrete. Background Art

[0003] Currently, immersed tube construction projects both domestically and internationally can be broadly categorized into three structural types: early steel-shell immersed tubes (single-layer / double-layer), widely used reinforced concrete-reinforce ...

[0004] Summary of the Invention

[0005] The purpose of the present invention is to provide a submerged tube that reduces the weight of reinforced concrete, in order to solve the problems in the prior art of difficulty in floating the submerged tube and low safety factor of floating when the water depth for floating the submerged tube is difficult to meet.

[0006] In order to achieve the above object, the technical solution adopted by the present invention is:

[0007] A submerged tube for reducing the weight of reinforced concrete comprises a main body. The reinforced concrete of the main body is provided with a weight-reducing component. The weight-reducing component has a cavity which can be used for pouring concrete.

[0008] This solution employs a submerged tube structure that reduces the weight of reinforced concrete. Weight-reducing components are installed within the tube's body. These components reduce the tube's weight through a cavity, allowing for shallower draft during floating, making floating easier and safer. This also reduces the need for excavation and deepening of the river below the tube's floating route, saving project investment. Concrete can be poured into the cavity after the tube is floated, or after it reaches an intermediate position, ensuring the tube's quality and safety during operation.

[0009] Preferably, the weight-reducing component includes an embedded component having an embedded steel pipe, and the embedded steel pipe has a communication port communicating with the outside.

[0010] The embedded components formed by pre-buried steel pipes are embedded in the reinforced concrete of the immersed tube, which is convenient for pre-buried operations. After floating, concrete is poured into the embedded steel pipes through the connecting ports. The steel tube concrete structure formed by the combination of concrete and steel pipes can be perfectly integrated into the reinforced concrete of the immersed tube, so that the quality of the immersed tube during use can meet the early design requirements and satisfy the normal use conditions of the immersed tube.

[0011] Preferably, the connecting port is located above the top plate. When floating, the connecting port is always above the water surface, which can prevent water from entering the embedded steel pipe. It is more convenient to pour concrete in the later stage and can ensure the molding quality of pouring concrete into the embedded steel pipe.

[0012] Preferably, the embedded assembly includes an upper embedded steel pipe component, the upper embedded steel pipe component is arranged in the top plate of the body, and the upper embedded steel pipe component has a communication port;

[0013] and / or,

[0014] The embedded component comprises a lower embedded steel pipe component, which is arranged in the side wall and the bottom plate of the main body and has a communication port.

[0015] For standard pipe sections, when the weight reduction of the immersed tube is low, the large number of outfitting components on the top plate will affect the installation of the outfitting components. While the construction difficulty of burying pipes in the bottom plate and wall is relatively low, burying pipes in the top plate requires hoisting steel pipes, which is relatively cumbersome. The increased weight of the steel pipes increases the load on the immersed tube formwork and increases potential risks. Therefore, from the perspective of installation difficulty, burying the lower pre-buried steel pipe components in the bottom plate and wall has a higher priority than burying the upper pre-buried steel pipe components in the top plate. When the weight reduction demand is high, it is necessary to bury the upper pre-buried steel pipe components in the top plate at the same time as burying the lower pre-buried steel pipe components in the bottom plate and wall.

[0016] Compared to standard pipe sections, variable-section pipe sections present leveling challenges. While calculating and balancing the steel pipes in the top plate is relatively easy, variable-section sunk pipes are more complex, and burying them in the bottom plate and walls presents greater challenges. However, burying pipes in the top plate offers a lower center of gravity than burying them in the bottom plate and walls, making them less likely to become unstable during floating. During floating, the outer walls and bottom plate of the sunk pipe bear the primary water pressure. Burying pipes in the top plate provides a safer structure, helping to reduce construction safety and quality risks. Therefore, when the weight reduction requirement for sunk pipes is low, burying the upper pre-buried steel pipe components in the top plate takes precedence over burying the lower pre-buried steel pipe components in the bottom plate and walls. However, when the need for weight reduction is high, burying the upper pre-buried steel pipe components in the top plate is necessary, along with burying the lower pre-buried steel pipe components in the bottom plate and walls.

[0017] Preferably, when the embedded assembly includes an upper embedded steel pipe member:

[0018] The upper embedded steel pipe component includes a first embedded pipe, which is arranged transversely along the top plate, and has connecting openings at both ends and in the middle of the first embedded pipe;

[0019] and / or,

[0020] The upper embedded steel pipe component includes a second embedded pipe and a third embedded pipe. The second embedded pipe and the third embedded pipe are located on the same cross-section of the body. The second embedded pipe and the third embedded pipe are arranged horizontally along the top plate. There is a gap between the second embedded pipe and the third embedded pipe. Both ends of the second embedded pipe and the third embedded pipe are respectively provided with connecting ports.

[0021] Connecting ports are provided at both ends and the middle of the first embedded pipe. The connecting ports at both ends serve as grouting ports for pouring concrete, and the middle connecting port serves as an exhaust port for discharging concrete from the first embedded pipe, thereby ensuring the pouring quality of concrete in the first embedded pipe.

[0022] A gap is created between the second and third embedded pipes to allow them to bypass the location where a measuring tower is required on the top plate of the immersed tube, ensuring that the required strength is met. Grouting ports are located at both ends of the second embedded pipe and at the end of the third embedded pipe near the side wall of the immersed tube, while the end near the center of the immersed tube serves as an exhaust port. This ensures that the concrete pouring position is aligned with the first embedded pipe, making pouring more convenient. Furthermore, it ensures balance during concrete pouring, making it safer when pouring over water.

[0023] Preferably, when the upper embedded steel pipe component includes a first embedded pipe, both ends of the first embedded pipe extend to the side walls on both sides of the body, and the portion of the first embedded pipe extending to the side wall is tilted downward;

[0024] When the upper embedded steel pipe component includes the second embedded pipe and the third embedded pipe, the second embedded pipe and the third embedded pipe extend to the corresponding side wall, and the parts of the second embedded pipe and the third embedded pipe extending to the side wall are arranged to be tilted downward.

[0025] The ends of the first, second, and third embedded tubes near the side walls can be extended to the side walls, further reducing weight. The portions extending to the side walls are angled downward to accommodate the tilt of the immersed tube corners. This also strengthens the connection between the top plate and the side walls, improving the quality of the immersed tubes.

[0026] Preferably, when the embedded assembly includes a lower embedded steel pipe member:

[0027] The lower embedded steel pipe component includes a fourth embedded pipe arranged horizontally and at least three fifth embedded pipes arranged vertically. The fifth embedded pipe is connected downwardly to the fourth embedded pipe. The fourth embedded pipe is arranged on the bottom plate, the side wall is provided with the fifth embedded pipe, and at least one middle wall of the main body is provided with the fifth embedded pipe. The upper end of the fifth embedded pipe has a connecting port.

[0028] The use of these lower pre-buried steel pipe components ensures a good connection between the base plate and the immersed tube wall, significantly reducing weight by utilizing the walls and base plate of the immersed tube. The upper connection port of the fifth pre-buried pipe in the side wall serves as the pouring port, while the upper connection port of the fifth pre-buried pipe in the center wall serves as the exhaust port, ensuring balanced pouring and making it safer.

[0029] Preferably, the end of the fourth embedded pipe is tilted upward to connect to the lower end of the fifth embedded pipe located on the side wall, which can adapt to the inclination of the lower corner of the immersed pipe and facilitate the concrete poured from the connecting port at the upper end of the fifth embedded pipe on the side wall to flow slowly at the inclined part of the end of the fourth embedded pipe to the middle part of the fourth embedded pipe, thereby avoiding the accumulation of concrete at the end of the fourth embedded pipe, which makes it difficult to pour subsequent concrete.

[0030] Preferably, when the embedded component includes a lower embedded steel pipe component and an upper embedded steel pipe component, the lower embedded steel pipe component and the upper embedded steel pipe component are staggered along the longitudinal direction of the body.

[0031] When pouring the sunken tube, the bottom plate and wall are poured together, and the top plate is tied after the bottom plate and wall formwork are installed. The sunken tube first ties the bottom plate and wall reinforcement and buries the fourth and fifth embedded pipes inside. Then, the large formwork cavity is entered, and only then can the top plate reinforcement be tied and the first, second, and third embedded pipes be embedded. In order to set up the upward connecting port, the lower embedded steel pipe components and the upper embedded steel pipe components need to be staggered along the longitudinal direction of the main body. In addition, the thickness of the top plate is limited, and there are also the locations of the protective layer and reinforcement. The staggered arrangement is conducive to ensuring the structural strength of the top plate, better stress performance, and conducive to quality control and safety control.

[0032] Preferably, a protective pier is provided on the outer surface of the body, and the protective pier has a groove. At least part of the protective pier is provided corresponding to the communication port, and the communication port is located inside the groove corresponding to the protective pier.

[0033] At least part of the protective pier is adjusted according to the setting position of the connecting port so that the connecting port is located inside the groove of the corresponding protective pier. The protective pier not only serves as anti-collision protection for the immersed tube, but also protects the connecting port, ensuring smooth pouring in the later stage.

[0034] In summary, due to the adoption of the above technical solution, the beneficial effects of the present invention are:

[0035] 1. The present invention reduces the weight of reinforced concrete by installing a weight-reducing component within the main body of the immersed tube. This component reduces the weight of the tube through a cavity, allowing the tube to float more shallowly, making it easier and safer to float. It also reduces the need for excavation and deepening of the river below the floating route, saving project investment. Concrete can be poured into the cavity after the floating tube is completed or at an intermediate position, ensuring the quality and safety of the tube during operation.

[0036] 2. The immersed tube for reducing the weight of reinforced concrete described in the present invention adopts an embedded assembly formed by pre-buried steel tubes as a weight-reducing component, which is embedded in the reinforced concrete of the immersed tube, to facilitate the pre-buried operation; and after floating, concrete is poured into the embedded steel tube through the connecting port. The steel tube concrete structure formed by the combination of concrete and steel tube can be perfectly integrated into the reinforced concrete of the immersed tube, so that the quality of the immersed tube during use can meet the preliminary design requirements and satisfy the normal use conditions of the immersed tube.

[0037] 3. The immersed tube for reducing the weight of reinforced concrete described in the present invention adjusts at least part of the protective pier according to the setting position of the connecting port, so that the connecting port is located inside the groove of the corresponding protective pier. The protective pier not only serves as an anti-collision protection for the immersed tube, but also protects the connecting port, ensuring that the pouring can be carried out smoothly in the later stage. BRIEF DESCRIPTION OF THE DRAWINGS

[0038] FIG1 is a schematic structural diagram of a top plate of an immersed tube for reducing the weight of reinforced concrete in Example 1, in which embedded steel pipes are provided;

[0039] FIG2 is a schematic cross-sectional view taken along line AA in FIG1 ;

[0040] FIG3 is a schematic cross-sectional view taken along line BB in FIG1 ;

[0041] FIG4 is a schematic cross-sectional view taken along line CC in FIG1 ;

[0042] FIG5 is a partial enlarged schematic diagram of point A in FIG4 ;

[0043] FIG6 is a partial enlarged schematic diagram of point B in FIG4;

[0044] FIG7 is a schematic cross-sectional view taken along line DD in FIG1 ;

[0045] FIG8 is a schematic cross-sectional view taken along line EE in FIG1 ;

[0046] FIG9 is a schematic cross-sectional view taken along line LL in FIG1 ;

[0047] 10 is a schematic structural diagram of the bottom plate of the immersed tube for reducing the weight of reinforced concrete in Example 1;

[0048] FIG11 is a schematic cross-sectional view taken along line JJ in FIG10 ;

[0049] FIG12 is a partial enlarged schematic diagram of the circle in FIG11;

[0050] FIG13 is a schematic cross-sectional view of a portion KK in FIG10 ;

[0051] FIG14 is a schematic cross-sectional view taken along line MM in FIG10 .

[0052] Icons: 1-main body; 11-top plate; 12-bottom plate; 13-side wall; 14-middle wall; 211-measuring tower; 23-jack pull-close seat; 241-double-column mooring bollard; 242-single-column mooring bollard; 25-pipe section lifting point; 27-guide rod; 3-embedded steel pipe; 31-first embedded pipe; 32-second embedded pipe; 33-third embedded pipe; 34-fourth embedded pipe; 35-fifth embedded pipe; 41-grouting hole; 42-exhaust hole; 43-through pipe; 5-protective pier; 51-groove. DETAILED DESCRIPTION

[0053] The present invention will be described in detail below with reference to the accompanying drawings.

[0054] In order to make the purpose, technical solutions and advantages of the present invention more clearly understood, the present invention will be further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention.

[0055] Example 1

[0056] This embodiment provides an immersed tube for reducing the weight of reinforced concrete, referring to Figures 1 to 14, comprising a main body 1, wherein the reinforced concrete of the main body 1 has a weight-reducing component, the weight-reducing component has a cavity, and the cavity can be used for pouring concrete.

[0057] The immersed tube that reduces the weight of reinforced concrete as described in this solution can be a standard tube section or a variable-section tube section. A weight-reducing component is provided in the body 1 of the immersed tube. The weight-reducing component reduces the weight of the immersed tube through the cavity, so that the draft required for floating the immersed tube is shallower, making floating of the immersed tube easier and improving the safety of floating of the immersed tube; and it can reduce the excavation and deepening of the river below the floating route of the immersed tube, which can save engineering investment. Concrete can be poured into the cavity of the immersed tube after the floating is completed or floated to the middle position, which can ensure the quality and safety of the immersed tube during use. The weight-reducing component can be made of various steel structures with cavities, which can use the cavity to reduce weight and ensure the quality of the immersed tube after concrete is poured into the cavity at a later stage.

[0058] As shown in Figure 1, the immersed tubes are standard tube sections with the same cross-sectional dimensions and are arranged symmetrically in the longitudinal direction to ensure the balance of floating transportation.

[0059] In this embodiment, as shown in Figures 1 and 10, the weight-reducing component includes an embedded component having an embedded steel pipe 3. The embedded component formed by the embedded steel pipe 3 is embedded in the reinforced concrete of the immersed tube to facilitate the embedded operation; the embedded steel pipe 3 has a connecting port connected to the outside world. After floating, concrete is poured into the embedded steel pipe 3 through the connecting port. The steel tube concrete structure formed by the combination of concrete and steel pipe can be perfectly integrated into the reinforced concrete of the immersed tube, so that the quality of the immersed tube during use can meet the early design requirements and meet the normal use conditions of the immersed tube.

[0060] As shown in Figures 5 and 6, in this embodiment, the connecting port is suitably arranged above the top plate 11. The connecting port is always located above the water surface during floating, which can prevent water from entering the embedded steel pipe 3. It is also more convenient for pouring concrete in the later stage, and can ensure the molding quality of pouring concrete into the embedded steel pipe 3.

[0061] As shown in Figures 4-6, a protective pier 5 is provided on the outer surface of the main body 1. This pier 5 serves as a collision protection structure for the immersed tube. In this embodiment, the pier 5 has a groove 51. At least a portion of the pier 5 is positioned corresponding to the communication port, and the communication port is located within the groove 51 of the corresponding pier 5. Specifically, at least a portion of the pier 5 is adjusted based on the position of the communication port so that the communication port is located within the groove 51 of the corresponding pier 5. This allows the pier 5 to not only protect the immersed tube from collision but also protect the communication port, ensuring smooth subsequent pouring.

[0062] Example 2

[0063] This embodiment provides an immersed tube for reducing the weight of reinforced concrete, which is a refinement on the basis of Example 1. Referring to Figures 1 to 8, the embedded component includes an upper embedded steel pipe member, which is arranged in the top plate 11 of the main body 1 and has a connecting port.

[0064] In this embodiment, the upper pre-buried steel pipe components are arranged at intervals along the longitudinal direction of the immersed tube, which can ensure the strength of the top plate 11.

[0065] As shown in Figures 1, 2, and 4 to 8, the upper embedded steel pipe component includes a first embedded pipe 31, which is arranged horizontally along the top plate 11. Communication ports are provided at both ends and the middle of the first embedded pipe 31; communication ports are provided at both ends and the middle of the first embedded pipe 31, and the communication ports at both ends serve as grouting ports for pouring concrete, and the middle communication port serves as an exhaust port to discharge the first embedded pipe 31, which can ensure the pouring quality of the concrete in the first embedded pipe 31.

[0066] As shown in Figures 1 and 2, the top plate 11 near the left end of the immersed tube is equipped with a jack seat 23, a double-post bollard 241, and a guide rod 27. To ensure the strength of the top plate 11 at the locations where these structures are located, pre-buried steel pipes 3 are not embedded in these locations, thereby ensuring the strength of the ends of the immersed tube's top plate 11. Furthermore, the ends of the first pre-buried pipe 31 corresponding to Figure 1 do not extend to the side wall 13, ensuring that the strength of the top plate 11 at the location where the double-post bollard 241 is located meets the required strength.

[0067] As shown in Figures 1 and 3, the upper pre-buried steel pipe structure also includes a second pre-buried pipe 32 and a third pre-buried pipe 33. The second and third pre-buried pipes 32, 33 are located on the same cross-section of the main body 1 and are arranged transversely along the top plate 11. A gap is provided between the second and third pre-buried pipes 32, 33 to allow them to skip over the location where the measurement tower 211 is required on the top plate 11 of the immersed tube. This ensures that the location of the measurement tower 211 on the immersed tube top plate 11 meets the required strength. Both ends of the second and third pre-buried pipes 32 and 33 are provided with communication ports. Specifically, the ends of the second and third pre-buried pipes 32 and 33 near the side wall 13 of the immersed tube serve as grouting ports, while the ends near the middle of the immersed tube serve as exhaust ports. This ensures that the concrete is poured in the same position as the first pre-buried pipe 31, making pouring more convenient. Furthermore, it ensures balance during concrete pouring, making it safer when pouring concrete over water. As shown in Figures 3 to 5, both ends of the first embedded tube 31 extend to the side walls 13 on both sides of the main body 1, and the portion of the first embedded tube 31 extending to the side wall 13 is tilted downward; the second embedded tube 32 and the third embedded tube 33 extend to the corresponding side walls 13, and the portion of the second embedded tube 32 and the third embedded tube 33 extending to the side wall 13 is tilted downward. The ends of the first embedded tube 31, the second embedded tube 32, and the third embedded tube 33 close to the side wall 13 can extend to the side wall 13, which can reduce weight even more. The portion extending to the side wall 13 is tilted downward to adapt to the inner tilt of the corner of the immersed tube, as shown in Figure 5; and it can strengthen the connection between the immersed tube top plate 11 and the side wall 13, making the quality of the immersed tube better.

[0068] As shown in Figures 1 and 7, the ends of the first pre-buried pipe 31 do not extend far enough to reach the side wall 13, avoiding the pipe section lifting point 25 of the immersed tube, ensuring the safety of the immersed tube's lifting. As shown in Figures 1 and 8, the ends of the first pre-buried pipe 31 do not extend far enough to reach the side wall 13, avoiding the single-column mooring bollard 242 of the immersed tube, ensuring the strength of the top plate 11 at the single-column mooring bollard 242 and the safety of the immersed tube's mooring.

[0069] As shown in FIG. 5-FIG . 6 , the communication openings of the first embedded pipe 31 , the second embedded pipe 32 and the third embedded pipe 33 are formed by vertically arranged through-pipes 43 passing through the upper layer of the top plate 11 and the protective pier 5 .

[0070] Example 3

[0071] This embodiment provides an immersed tube for reducing the weight of reinforced concrete, which is a refinement on the basis of Example 1. Referring to Figures 10 to 14, the embedded assembly includes a lower embedded steel pipe member, which is arranged in the side wall 13 and the bottom plate 12 of the main body 1, and the lower embedded steel pipe member has a connecting port.

[0072] In this embodiment, the lower pre-buried steel pipe components are arranged at intervals along the longitudinal direction of the immersed tube, which can ensure the strength of the immersed tube bottom plate 12 and the wall.

[0073] In this embodiment, the lower embedded steel pipe member includes a fourth embedded pipe 34 arranged horizontally and at least three fifth embedded pipes 35 arranged vertically. The fifth embedded pipe 35 is downwardly connected to the fourth embedded pipe 34. The fourth embedded pipe 34 is arranged on the bottom plate 12, as shown in Figure 14; the side wall 13 is provided with a fifth embedded pipe 35, and at least one middle wall 14 of the main body 1 is provided with a fifth embedded pipe 35. The upper end of the fifth embedded pipe 35 has a connecting port.

[0074] This arrangement ensures a good connection between the base plate 12 and the immersed tube wall, significantly reducing weight by utilizing the immersed tube wall and base plate 12. The upper end of the fifth embedded tube 35 in the side wall 13 serves as the pouring port, while the upper end of the fifth embedded tube 35 in the center wall 14 serves as the exhaust port, ensuring balanced pouring and making it more convenient and safe.

[0075] As shown in Figure 11, the fifth pre-buried pipe 35, serving as an exhaust outlet, is located on the left side of the middle wall 14. As shown in Figure 13, the fifth pre-buried pipe 35, serving as an exhaust outlet, is located on the right side of the middle wall 14. Of course, in this embodiment, the fifth pre-buried pipe 35 can also be installed in both middle walls 14. As shown in Figure 10, the fifth pre-buried pipe 35, serving as an exhaust outlet, is staggered along the longitudinal direction of the immersed tube in the two middle walls 14. This ensures the strength of the immersed tube middle walls 14 while meeting exhaust requirements and ensuring balanced casting.

[0076] As shown in Figure 12, the end of the fourth embedded pipe 34 is tilted upward and connected to the lower end of the fifth embedded pipe 35 located on the side wall 13, which can adapt to the inclination of the inner side of the lower corner of the immersed tube, and facilitates the concrete poured from the connecting port at the upper end of the fifth embedded pipe 35 of the side wall 13 to flow slowly at the inclined part of the end of the fourth embedded pipe 34 to the middle of the fourth embedded pipe 34, thereby avoiding the accumulation of concrete at the end of the fourth embedded pipe 34, which makes it difficult to pour subsequent concrete.

[0077] Example 4

[0078] This embodiment provides an immersed tube for reducing the weight of reinforced concrete, which is refined on the basis of Example 1. Referring to Figures 1 to 14, the embedded component includes the upper embedded steel pipe member of Example 2, which is arranged in the top plate 11 of the main body 1, and the upper embedded steel pipe member has a connecting port; the embedded component also includes the lower embedded steel pipe member of Example 3, which is arranged in the side wall 13 and the bottom plate 12 of the main body 1, and the lower embedded steel pipe member has a connecting port.

[0079] For standard pipe segments, when the weight reduction for sunken tubes is low, burying pipes will affect the installation of outfitting components due to the large number of outfitting components in the top plate 11. While burying pipes in the bottom plate 12 and walls is easier, burying pipes in the top plate 11 requires hoisting steel pipes, which is relatively cumbersome. The added weight of the steel pipes increases the load on the sunken tube formwork, increasing potential risks. Therefore, based on the ease of installation, burying the lower pre-buried steel pipe components in the bottom plate 12 and walls takes precedence over burying the upper pre-buried steel pipe components in the top plate 11. When the need for weight reduction is high, it is necessary to bury the upper pre-buried steel pipe components in the top plate 11 at the same time as burying the lower pre-buried steel pipe components in the bottom plate 12 and walls.

[0080] Compared to standard pipe sections, variable-section pipe sections have posture leveling issues. Calculating the leveling counterweight when burying steel pipes in the top plate 11 is relatively easy. Furthermore, variable-section sunk pipes are relatively complex, and burying pipes in the bottom plate and walls is even more difficult. Burying pipes in the top plate 11 has a lower center of gravity than burying pipes in the bottom plate 12 and walls, making it less likely to become unstable during the floating process. During floating, the outer walls and bottom plate 12 of the sunk pipe bear the water pressure. Burying pipes in the top plate 11 is a safer structure, helping to reduce construction safety and quality risks. Therefore, when the weight reduction of the sunk pipe is low, burying the upper pre-buried steel pipe components in the top plate 11 has a higher priority than burying the lower pre-buried steel pipe components in the bottom plate 12 and walls. When the need for weight reduction is high, it is necessary to bury the upper pre-buried steel pipe components in the top plate 11 at the same time as burying the lower pre-buried steel pipe components in the bottom plate 12 and walls.

[0081] As shown in FIG9 , when the embedded assembly includes a lower embedded steel pipe component and an upper embedded steel pipe component, the lower embedded steel pipe component and the upper embedded steel pipe component are staggered along the longitudinal direction of the body 1 .

[0082] When the immersed tube is cast, the bottom plate 12 and the wall are cast together, and the top plate 11 is tied after the bottom plate 12 and the wall formwork are installed. The immersed tube first ties the bottom plate 12 and the wall reinforcement and buries the fourth embedded pipe 34 and the fifth embedded pipe 35 inside. Then the large cavity of the formwork enters, and only then can the reinforcement of the top plate 11 be tied and the first embedded pipe 31, the second embedded pipe 32 and the third embedded pipe 33, etc. be embedded. In order to set up the upward connecting port, the lower embedded steel pipe components and the upper embedded steel pipe components need to be staggered along the longitudinal direction of the main body 1. In addition, the thickness of the top plate 11 is limited, and there is also the position of the protective layer and the reinforcement. The staggered arrangement is conducive to ensuring the structural strength of the top plate 11, better stress performance, and conducive to quality control and safety control.

[0083] When manufacturing the immersed tube that reduces the weight of reinforced concrete in the above-mentioned embodiment, cooling water can be injected into the embedded steel pipe to improve the heat dissipation effect of the concrete and reduce the probability of cracks appearing on the concrete surface of the bottom plate, side wall or top plate; and the injected cooling water will not affect the quality of the secondary pouring of the cavity in the later stage.

[0084] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.

Claims

1. An immersed tube for reducing the weight of reinforced concrete, characterized in that: The invention comprises a main body (1), wherein the reinforced concrete of the main body (1) has a weight-reducing component, the weight-reducing component has a cavity, and the cavity can be used for pouring concrete.

2. The immersed tube for reducing the weight of reinforced concrete according to claim 1, characterized in that: The weight-reducing component comprises an embedded component having an embedded steel pipe (3), wherein the embedded steel pipe (3) has a connecting port connected to the outside.

3. The immersed tube for reducing the weight of reinforced concrete according to claim 2, characterized in that: The communication port is located above the top plate (11).

4. The immersed tube for reducing the weight of reinforced concrete according to claim 3, characterized in that: The embedded component comprises an upper embedded steel pipe component, which is arranged in the top plate (11) of the main body (1), and has a communication port; and / or, The embedded component comprises a lower embedded steel pipe component, which is arranged in the side wall (13) and the bottom plate (12) of the main body (1), and has a communication port.

5. The immersed tube for reducing the weight of reinforced concrete according to claim 3, characterized in that: When the embedded components include upper embedded steel pipe components: The upper embedded steel pipe component comprises a first embedded pipe (31), the first embedded pipe (31) is arranged transversely along the top plate (11), and both ends and the middle of the first embedded pipe (31) are provided with communication ports; and / or, The upper embedded steel pipe component comprises a second embedded pipe (32) and a third embedded pipe (33). The second embedded pipe (32) and the third embedded pipe (33) are located on the same cross section of the body (1). The second embedded pipe (32) and the third embedded pipe (33) are arranged transversely along the top plate (11). There is a gap between the second embedded pipe (32) and the third embedded pipe (33). Both ends of the second embedded pipe (32) and the third embedded pipe (33) are respectively provided with communication ports.

6. The immersed tube for reducing the weight of reinforced concrete according to claim 5, characterized in that: When the upper embedded steel pipe component includes a first embedded pipe (31), both ends of the first embedded pipe (31) extend to the side walls (13) on both sides of the body (1), and the portion of the first embedded pipe (31) extending to the side wall (13) is arranged to be tilted downward; When the upper embedded steel pipe component includes a second embedded pipe (32) and a third embedded pipe (33), the second embedded pipe (32) and the third embedded pipe (33) are extended to the corresponding side wall (13), and the parts of the second embedded pipe (32) and the third embedded pipe (33) extending to the side wall (13) are arranged to be tilted downward.

7. The immersed tube for reducing the weight of reinforced concrete according to claim 3, characterized in that: When the embedded components include lower embedded steel pipe components: The lower embedded steel pipe component comprises a fourth embedded pipe (34) arranged horizontally and at least three fifth embedded pipes (35) arranged vertically, the fifth embedded pipe (35) is connected downwardly to the fourth embedded pipe (34), the fourth embedded pipe (34) is arranged on the bottom plate (12), the side wall (13) is provided with the fifth embedded pipe (35), at least one middle wall (14) of the body (1) is provided with the fifth embedded pipe (35), and the upper end of the fifth embedded pipe (35) has a connecting port.

8. The immersed tube for reducing the weight of reinforced concrete according to claim 7, characterized in that: The end of the fourth embedded pipe (34) is tilted upward and connected to the lower end of the fifth embedded pipe (35) located on the side wall (13).

9. The immersed tube for reducing the weight of reinforced concrete according to claim 3, characterized in that: When the embedded component comprises a lower embedded steel pipe component and an upper embedded steel pipe component, the lower embedded steel pipe component and the upper embedded steel pipe component are staggeredly distributed along the longitudinal direction of the body (1).

10. The immersed tube for reducing the weight of reinforced concrete according to any one of claims 2 to 9, characterized in that: A protective pier (5) is provided on the outer surface of the body (1), the protective pier (5) having a groove (51), at least part of the protective pier (5) being arranged corresponding to the communication port, and the communication port being located inside the groove (51) corresponding to the protective pier (5).

Citation Information

Patent Citations

  • Shell-type immersed pipes underwater installation method

    CN109183851A

  • Self-weight-adjustable immersed tube of reinforced concrete embedded tube and design and construction method

    CN113863379A

  • Immersed tube joint staged forming construction method

    CN113898011A

  • Immersed tube capable of reducing weight of reinforced concrete

    CN116378083A

  • Secondary floating state pouring type immersed tube structure and secondary floating state pouring method

    CN116479940A