Generator grid-connected controller and control method, and storage medium

Through the design of the generator grid-connected controller, the generator and mains power supply are combined, which solves the manual operation needs and diesel waste during the generator switching process, improves power supply efficiency and reliability, and reduces diesel consumption.

WO2024239265A1PCT designated stage expired Publication Date: 2024-11-28SHENZHEN HANGYI IP SERVICE CO LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
PCT/CN2023/095953
Authority / Receiving Office
WO · WO
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-05-24
Publication Date
2024-11-28

AI Technical Summary

Technical Problem

In the data center field, there is an interruption in the switching process of the generator when the mains input fails, and it requires manual operation, resulting in the diesel generator being not used for a long time, resulting in waste of diesel, and the generator cannot be connected to the mains power grid and cannot be effectively Use mains to reduce diesel consumption.

Method used

A generator grid-connected controller is designed. Through the combination of rectifier and inverter, the combined power supply mode of the generator and mains is realized. The control unit is used to intelligently control the switching state of the generator, judge the load power and automatically switch the power supply mode. , ensure efficient utilization of generators and energy storage units.

Benefits of technology

The grid-connected power supply between the generator and the mains power supply is realized, the power supply efficiency and reliability of the system is improved, the consumption and waste of diesel is reduced, the carbon deposit of diesel caused by low load operation of the generator is avoided, and the operation cost is optimized.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN2023095953_28112024_PF_FP_ABST
    Figure CN2023095953_28112024_PF_FP_ABST
Patent Text Reader

Abstract

The present invention relates to the technical field of power supply. The present invention provides a generator grid-connected controller and control method, and a storage medium. The generator grid-connected controller comprises a first conversion unit and a second conversion unit; one end of the first conversion unit is used for being connected to the output end of a generator, so that the first conversion unit is used for converting a first alternating-current voltage provided by the generator into a first direct-current voltage in a combined power supply mode; and one end of the second conversion unit is used for being connected to the other end of the first conversion unit, the other end of the second conversion unit is used for being connected to a first input end of a load, and the second conversion unit is used for converting the first direct-current voltage into a second alternating-current voltage and providing the second alternating-current voltage to the load in the combined power supply mode. Thus, the generator supplies power to the load by means of the generator grid-connected controller in combination with a first mains supply unit connected to the first input end of the load.
Need to check novelty before this filing date? Find Prior Art

Description

Generator grid-connected controller, control method and storage medium Technical Field

[0001] The present invention relates to the technical field of power supply, and in particular to a generator grid-connected controller, a control method and a storage medium. Background Art

[0002] The power supply device is a power supply device connected between the load of key equipment and the external power supply. It is used to provide continuous power to the load through the power supply when the power supply is working normally, and to supply power to the load through the energy storage unit when the power supply is interrupted or insufficient.

[0003] Currently, critical equipment loads in data centers support AC input power. In the event of a mains power failure or anomaly, the ATS (Automatic Transfer Switch) automatically switches to the generator, signaling it to start the generator. Once the ATS detects the generator's output voltage has reached a certain value, it switches to the generator. However, in practice, if a generator is used to power the actual load, the ATS (Automatic Transfer Switch) switching process is interrupted and requires manual operation, placing high demands on personnel.

[0004] Furthermore, generators typically use diesel, which has a shelf life. In data centers, generators are typically used as backup emergency power supplies and remain out of service for extended periods. To avoid manually switching the ATS during generator discharge testing, a dummy load is often connected to the generator to test the generator. However, a dummy load is a thermal load (similar to a resistive heating device, such as a hair dryer) that effectively blocks the generator's electrical energy. Furthermore, to ensure the quality of stored diesel, the generator's diesel needs to be dissipated through the dummy load each year before being recharged, resulting in significant diesel waste.

[0005] Summary of the Invention

[0006] Through research, the inventors found that when the power supply is tight, the power supply capacity of the power grid is usually limited. In application scenarios with ATS switching, power can only be supplied by generators or mains power. The generator cannot be connected to the mains power to supply power to the power load, and the mains power cannot be effectively utilized, while increasing the power supply cost of the diesel generator.

[0007] The present invention provides a generator grid-connected controller, a control method and a storage medium with high reliability and greater energy saving.

[0008] In a first aspect, the present invention provides a generator grid-connected controller for use in a power supply system having a first mains unit and a load, comprising a first conversion unit and a second conversion unit, wherein the first conversion unit comprises a rectifier or a first bidirectional converter, one end of the first conversion unit being used to connect to the output end of the generator, so as to convert the first AC voltage provided by the generator into a first DC voltage in a joint power supply mode; and the second conversion unit comprises an inverter or a second bidirectional converter, one end of the second conversion unit being used to connect to the other end of the first conversion unit, the other end of the second conversion unit being used to connect to the first input end of the load, the second conversion unit being used to convert the first DC voltage into a second AC voltage and provide the second AC voltage to the load in the joint power supply mode, so that the generator jointly supplies power to the load via the generator grid-connected controller and the first mains unit connected to the first input end of the load.

[0009] Compared with the prior art, the generator grid-connected controller in the embodiment of the present application can, in the combined power supply mode, enable the generator to jointly supply power to the load via the generator grid-connected controller and the first AC power unit connected to the first input end of the load, thereby effectively utilizing the electrical energy of the generator and saving energy, thereby improving the power supply efficiency and reliability of the entire system.

[0010] In one embodiment, the generator grid-connected controller further includes a control unit electrically connected to the first conversion unit, the second conversion unit, and the generator, and configured to control the generator grid-connected controller to enter the combined power supply mode. By providing this control unit, intelligent control of the power supply mode of the generator grid-connected controller can be achieved, thereby improving user experience and power supply efficiency.

[0011] In one embodiment, the control unit is further configured to determine whether the load power exceeds a set value. When the load power exceeds the set value, the control unit controls the system to enter the combined power supply mode; when the load power does not exceed the set value, the control unit controls the generator to shut down. The control unit can also control the generator to turn on or off based on the load power determination, enabling more intelligent control of the generator based on the actual load consumption, thereby improving power efficiency and reducing power costs.

[0012] In one embodiment, the other end of the first conversion unit and one end of the second conversion unit are also used to electrically connect an energy storage unit, and the first conversion unit is also used to output the first DC voltage to charge the energy storage unit to a first preset capacity value in the joint power supply mode; when the joint power supply ends, the energy storage unit is also used to supply power to the load via the second conversion unit until the electric energy of the energy storage unit reaches a second preset capacity value. By setting the energy storage unit, the excess power of the generator can be used to charge the energy storage unit. If the output load is insufficient, the generator avoids low-load operation to cause diesel carbon deposits, thereby improving the working efficiency of the generator. At the same time, after shutting down the generator, the energy storage unit can continue to be discharged until the energy storage unit is discharged to the second preset capacity value, thereby improving the reliability of the power supply system and saving energy.

[0013] In one embodiment, the generator grid-connected controller further includes a switching unit, wherein a first end of the switching unit is connected to one end of the first conversion unit, and a second end of the switching unit is used to connect to the generator, so that the generator is connected to one end of the first conversion unit via the second end and the first end of the switching unit, and a third end of the switching unit is used to connect to the other end of the second conversion unit to connect to the load. When not in the combined power supply mode, the first end and the second end are disconnected, and the first end and the third end are connected; when in the combined power supply mode, the first end and the second end are connected, and the first end and the third end are disconnected. By providing a switching unit, when not in the combined power supply mode, there is no need to switch to the generator output conduction state, and when in the combined power supply mode, it is switched to the generator output conduction state, making the circuit conduction state easier to control without the need for human intervention.

[0014] In one embodiment, the generator grid-connected controller further comprises a switching unit, wherein a first end of the switching unit is connected to one end of the first conversion unit, a second end of the switching unit is used to connect to the generator, so that the generator is connected to one end of the first conversion unit via the second end and the first end of the switching unit, and a third end of the switching unit is used to connect the second input end of the load and the second mains unit. When not in the combined power supply mode, the first end and the second end are disconnected, the first end and the third end are connected, and the first bidirectional converter and the second bidirectional converter operate in reactive power compensation and / or active filtering mode; when in the combined power supply mode, the first end and the second end are connected, and the first end and the third end are disconnected. By providing the switching unit, when not in the combined power supply mode, there is no need to switch to the generator output conduction state. When in the combined power supply mode, the generator output is conducted, making the circuit conduction state easier to control without requiring human intervention.

[0015] In one embodiment, the control unit is further electrically connected to the switching unit to control the switching unit to be turned on and off.

[0016] In one embodiment, the generator grid-connected controller further includes a first switch, a second switch, and a third switch, one end of the first switch is used to connect the generator, and the other end is connected to the first conversion unit, so that the first conversion unit is connected to the generator via the first switch, the second switch is used to connect between the generator and a first AC bus, and the first AC bus is also used to connect the first mains unit and the first input end of the load, the third switch is used to connect between the first AC bus and the other end of the second conversion unit, so that the second conversion unit is connected to the first input end of the load via the third switch and the first AC bus; in the joint power supply mode, the first switch and the third switch are in the on state, and the second switch is in the off state.

[0017] In one embodiment, the generator grid-connected controller further includes a third conversion unit, the third conversion unit including an inverter or a third bidirectional converter, one end of the third conversion unit is used to connect to the other end of the first conversion unit, the other end of the third conversion unit is used to connect to the second input end of the load, and the third conversion unit is used to convert the first DC voltage into a fifth AC voltage and provide the fifth AC voltage to the load in the joint power supply mode, so that the generator jointly supplies power to the load via the generator grid-connected controller and the second AC unit connected to the second input end of the load. By setting the third conversion unit, multiple loads or multiple input ends of the load can be connected for power supply, thereby effectively utilizing the electrical energy of the generator and saving energy, thereby improving the power supply efficiency and reliability of the entire system.

[0018] In one embodiment, the power supply system has a generator test mode. When the first mains power unit is normal and in the generator test mode, the control unit controls the system to enter the combined power supply mode, so that during the generator test, the generator and the first mains power unit jointly supply power to the load. It is understood that in the generator test mode, the generator and the first mains power unit can simultaneously and jointly supply power to the load, thereby effectively utilizing the generator's electrical energy, saving energy, and thereby improving the power supply efficiency and reliability of the entire system.

[0019] In one embodiment, the control unit is configured to control the generator to start in the generator test mode, causing the generator to output the first AC voltage according to the set output power, and to cause the generator output electric energy meter to obtain the generator output electric energy and / or power supply time. The control unit is further configured to control the generator to shut down when the output electric energy and / or power supply time reach a preset value, thereby completing the generator test. By connecting the generator output electric energy meter to perform the generator test, accurate power supply capacity requirements can be obtained, power capacity requirements can be optimized, and operating costs can be reduced.

[0020] In one embodiment, the control unit is further used to determine whether it is in a peak power period. When it is in the peak power period, the first AC power unit is normal and is in the generator test mode, the control unit controls the entry into the combined power supply mode; when the peak power period ends, the control unit controls the end of the combined power supply mode and the generator is shut down.

[0021] In one embodiment, the other end of the first conversion unit and one end of the second conversion unit are further configured to electrically connect to an energy storage unit. The first conversion unit is further configured to output the first DC voltage to power the energy storage unit during the generator test mode, and when the generator test mode ends, the energy storage unit is further configured to power the load via the second conversion unit. By providing the energy storage unit, the generator test can be completed while the energy storage unit is being charged during the generator test mode, effectively utilizing the generator's electrical energy and conserving energy. Furthermore, after the generator test mode ends, the energy storage unit can continue to be discharged, thereby improving the reliability of the power supply system and conserving energy.

[0022] In a second aspect, the present invention provides a generator grid-connected control method, which is used in a power supply system having a first mains unit, a generator, a first conversion unit, a second conversion unit, and a load, wherein the first conversion unit includes a rectifier or a first bidirectional converter, one end of the first conversion unit is used to connect to the output end of the generator, the second conversion unit includes an inverter or a second bidirectional converter, one end of the second conversion unit is used to connect to the other end of the first conversion unit, and the other end of the second conversion unit is used to connect to the first input end of the load, the method comprising:

[0023] In the joint power supply mode, the first conversion unit is controlled to convert the first AC voltage provided by the generator into a first DC voltage, and the second conversion unit is controlled to convert the first DC voltage into a second AC voltage and provide the second AC voltage to the load, so that the generator and the first AC power unit connected to the first input end of the load jointly power the load.

[0024] In one embodiment, the power supply system further includes a third conversion unit, the third conversion unit including an inverter or a third bidirectional converter, the other end of the first conversion unit is used to connect to one end of the third conversion unit, one end of the third conversion unit is used to connect to the other end of the first conversion unit, and the other end of the third conversion unit is used to connect to the second input end of the load, and the method includes:

[0025] In the joint power supply mode, the third conversion unit is controlled to convert the first DC voltage into a fifth AC voltage and provide the fifth AC voltage to the load, so that the generator and the second AC power unit connected to the second input end of the load jointly power the load.

[0026] In one embodiment, the power supply system has a generator test mode, and the method includes:

[0027] When the first mains power unit is normal and in the generator test mode, the power supply system is controlled to enter the joint power supply mode, so that during the generator test, the generator and the first mains power unit jointly supply power to the load.

[0028] In a third aspect, the present invention provides a computer storage medium having a computer program stored thereon, wherein the computer program, when executed by a processor, implements any one of the power supply control methods described above. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] FIG1 is a schematic structural diagram of a power supply system according to a first embodiment of the present invention.

[0030] FIG2 is a schematic diagram of the power supply system shown in FIG1 in a combined power supply mode.

[0031] FIG3 is a schematic structural diagram of a power supply system according to a second embodiment of the present invention.

[0032] FIG4 is a schematic diagram of the power supply system shown in FIG3 in a combined power supply mode.

[0033] FIG5 is a schematic diagram of a power supply system according to a third embodiment of the present invention when the power supply system is not in the combined power supply mode.

[0034] FIG6 is a schematic diagram of the power supply system shown in FIG5 in a combined power supply mode.

[0035] FIG7 is a schematic diagram of a power supply system according to a fourth embodiment of the present invention when the power supply system is not in the combined power supply mode.

[0036] FIG8 is a schematic diagram of the power supply system shown in FIG7 in a combined power supply mode.

[0037] FIG9 is a schematic structural diagram of a power supply system according to a fifth embodiment of the present invention.

[0038] FIG10 is a schematic structural diagram of a power supply system according to a sixth embodiment of the present invention.

[0039] FIG11 is a schematic structural diagram of a power supply system according to a seventh embodiment of the present invention.

[0040] FIG12 is a schematic structural diagram of a power supply system according to an eighth embodiment of the present invention.

[0041] FIG13 is a flow chart of a generator grid-connected control method according to a first embodiment of the present invention.

[0042] FIG14 is a flow chart of a generator grid-connected control method according to a second embodiment of the present invention.

[0043] FIG15 is a flow chart of a generator grid-connected control method according to a third embodiment of the present invention.

[0044] FIG16 is a flow chart of a generator grid-connected control method according to a fourth embodiment of the present invention.

[0045] FIG17 is a flow chart of a generator grid-connected control method according to a fifth embodiment of the present invention.

[0046] FIG18 is a flow chart of a generator grid-connected control method according to a sixth embodiment of the present invention.

[0047] FIG19 is a schematic diagram of the structure of a computer storage medium according to an embodiment of the present invention. DETAILED DESCRIPTION

[0048] The following will clearly and completely describe the technical solutions in the embodiments of the present invention in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. All other embodiments obtained by ordinary technicians in this field based on the embodiments of the present invention without making any creative efforts shall fall within the scope of protection of the present invention.

[0049] The terms "first", "second" and "third" in the present invention are used only for descriptive purposes and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, a feature defined as "first", "second" and "third" may explicitly or implicitly include at least one of such features. In the description of the present invention, "multiple" means at least two, for example, two, three, etc., unless otherwise clearly and specifically defined. All directional indications in the embodiments of the present invention (such as up, down, left, right, front, back...) are only used to explain the relative positional relationship, movement, etc. between the components under a specific posture (as shown in the accompanying drawings). If the specific posture changes, the directional indication will also change accordingly. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions. For example, a process, method, system, product or device that includes a series of steps or units is not limited to the listed steps or units, but may optionally include steps or units that are not listed, or may optionally include other steps or units inherent to these processes, methods, products or devices.

[0050] References herein to "embodiments" mean that a particular feature, structure, or characteristic described in connection with the embodiments may be included in at least one embodiment of the present invention. The appearance of this phrase in various places in the specification does not necessarily refer to the same embodiment, nor does it constitute a separate or alternative embodiment that is mutually exclusive of other embodiments. It is understood, both explicitly and implicitly, by those skilled in the art that the embodiments described herein may be combined with other embodiments.

[0051] As shown in Figure 1, an embodiment of the present invention provides a generator grid-connected controller 1, which is used in a power supply system 100 having a first mains unit 4 and a load 3, and includes a first conversion unit 11 and a second conversion unit 12, wherein the first conversion unit 11 includes a rectifier or a first bidirectional converter, and one end of the first conversion unit 11 is used to connect to the output end of the generator 2, so as to convert the first AC voltage provided by the generator 2 into a first DC voltage in a joint power supply mode; and the second conversion unit 12 includes an inverter or a second bidirectional converter, one end of the second conversion unit 12 is used to connect to the other end of the first conversion unit 11, and the other end of the second conversion unit 12 is used to connect to the first input end 31 of the load 3, and the second conversion unit 12 is used to convert the first DC voltage into a second AC voltage and provide the second AC voltage to the load 3 in the joint power supply mode, so that the generator 2 jointly supplies power to the load 3 via the generator grid-connected controller 1 and the first mains unit 4 connected to the first input end 31 of the load 3. As shown in Figure 1 , in this embodiment, the first conversion unit 11 is a first bidirectional converter, and the second conversion unit 12 is a second bidirectional converter. A bidirectional converter, also known as a Power Conversion System (PCS), is a device that performs bidirectional conversion of electrical energy. It can convert DC power into AC power for transmission to the power grid or AC loads, or it can rectify AC power from the power grid into DC power for charging other devices.

[0052] Please refer to Figure 2. For example, in this embodiment, the power of the load 3 is 2000KW, and the output power of the generator 2 is 800KW. In the combined power supply mode, the first conversion unit 11 converts the first AC voltage provided by the generator 2 into a first DC voltage, and the second conversion unit 12 converts the first DC voltage into a second AC voltage and provides the second AC voltage to the load 3. At this time, the first AC power unit 4 only needs to provide an output power of 1200KW to enable the load 3 to work normally.

[0053] The generator grid-connected controller 1 of the embodiment of the present application can, in the combined power supply mode, enable the generator 2 to jointly supply power to the load 3 via the generator grid-connected controller 1 and the first AC power unit 4 connected to the first input terminal 31 of the load 3, thereby effectively utilizing the electric energy of the generator 2 and the AC power. The generator 2 serves as a supplement to the AC power supply, thereby effectively utilizing the AC power and the generator, saving energy, and improving the power supply efficiency and reliability of the entire system.

[0054] Furthermore, the generator grid-connected controller 1 also includes a control unit 13, which is electrically connected to the first conversion unit 11, the second conversion unit 12, and the generator 2. The control unit 13 is used to control the generator grid-connected controller 1 to enter the combined power supply mode. By providing the control unit 13, the power supply mode of the generator grid-connected controller 1 can be intelligently controlled, and the control of the generator 2 can be automated without manual operation of the switch, thereby improving the user experience and power supply efficiency.

[0055] Furthermore, the control unit 13 is also used to determine whether the power of the load 3 exceeds the set value. When the power of the load 3 exceeds the set value, the control unit 13 controls the entry into the joint power supply mode; when the power of the load 3 does not exceed the set value, the control unit 13 controls the generator 2 to shut down. 2 , in this embodiment, the set value can be 1200KW. At this time, the power of the load 3, 2000KW, exceeds the set value of 1200KW. The control unit 13 controls the operation of the combined power supply mode. In the combined power supply mode, the first mains unit 4 provides 1200KW of output power to the load 3, and the remaining 800KW is provided by the generator 2. The control unit 13 can also control the generator 2 to be turned on or off by judging whether the power of the load 3 exceeds the set value. The generator 2 can be controlled more intelligently according to the actual power consumption of the load 3. When the power of the load 3 exceeds the set value, the generator 2 and the first mains unit 4 are combined to supply power, reducing the power supply capacity demand and power capacity cost of the first mains unit 4, thereby improving the power efficiency of the mains and improving the power supply guarantee of the load. Especially when the mains load is too heavy (such as power rationing in hot summer), the combined power supply of the generator 2 and the first mains unit 4 can effectively reduce the mains load and improve the power supply guarantee.

[0056] Please refer to Figure 3, the other end of the first conversion unit 11 and one end of the second conversion unit 12 are also used to electrically connect to the energy storage unit 9, and the first conversion unit 11 is also used to output the first DC voltage to charge the energy storage unit 9 to a first preset capacity value (such as fully charged) in the joint power supply mode; when the joint power supply ends, the energy storage unit 9 is also used to supply power to the load 3 via the second conversion unit 12 until the electric energy of the energy storage unit 9 reaches a second preset capacity value (such as the minimum power). Referring to FIG. 4 , it can be understood that in the combined power supply mode, the first AC voltage output by the generator 2 is converted by the first conversion unit 11 into the first DC voltage. The first DC voltage is then converted by the second conversion unit 12 into the second AC voltage. While the second AC voltage is provided to the load 3, the first DC voltage also charges the energy storage unit 9 until the energy storage unit 9 reaches the first preset capacity. When the combined power supply ends and the generator 2 is shut down, the energy storage unit 9 can continue to supply power to the load 3 independently or in conjunction with the first mains unit 4. This not only ensures the stability and reliability of the power supply system 100, but also further utilizes the power generation characteristics of the generator 2 to operate at optimal power generation efficiency. Excess power is charged by the energy storage unit 9, allowing the generator 2 to operate at a higher power efficiency when the output load 3 is low. This further avoids diesel carbon deposition caused by low-load operation and reduces maintenance work on the generator 2. Furthermore, after the generator 2 is shut down, the energy storage unit 9 can continue to discharge until the energy storage unit 9 reaches the second preset capacity, thereby improving the reliability of the power supply system 100 and saving energy. It can be understood that the first preset capacity value and the second preset capacity value can be set according to actual needs, and the first preset capacity value and the second preset capacity value can be set differently, and the first preset capacity value can be smaller than the second preset capacity value.

[0057] Referring to Figures 5 and 6 , in one embodiment, the generator grid-connected controller 1 further includes a switching unit 14. A first end A of the switching unit 14 is connected to one end of the first conversion unit 11, and a second end B of the switching unit 14 is used to connect to the generator 2, such that the generator 2 is connected to one end of the first conversion unit 11 via the second end B and the first end A of the switching unit 14. A third end C of the switching unit 14 is used to connect to the other end of the second conversion unit 12 to connect to the load 3. As shown in Figure 5 , when not in the combined power supply mode, the first end A and the second end B are disconnected, and the first end A and the third end C are connected. As shown in Figure 6 , when in the combined power supply mode, the first end A and the second end B are connected, and the first end A and the third end C are disconnected. By providing the switching unit 14, it is not necessary to switch to the generator 2 output conduction state when not in the combined power supply mode. When in the combined power supply mode, the switching is performed to the generator 2 output conduction state, making the circuit conduction state easier to control without human intervention. It can be understood that in this embodiment, the switching unit 14 can be an ATS or STS automatic switching unit, or other switch components with basically the same principle as the switching unit 14, and is not limited to the above.

[0058] Please refer to Figures 7 and 8. In other embodiments, the generator grid-connected controller 1 further includes a switching unit 14, wherein the first end A of the switching unit 14 is connected to one end of the first conversion unit 11, and the second end of the switching unit 14 is used to connect the generator 2, so that the generator 2 is connected to one end of the first conversion unit 11 via the second end B and the first end A of the switching unit 14, and the third end C of the switching unit 14 is used to connect the second input end 32 of the load 3 and the second AC power unit 6. As shown in Figure 7, when not in the joint power supply mode, the first end A and the second end B are disconnected, the first end A and the third end C are turned on, and the first bidirectional converter and the second bidirectional converter operate in reactive compensation and / or active filtering mode; as shown in Figure 8, when in the joint power supply mode, the first end A and the second end B are turned on, and the first end A and the third end C are disconnected. By setting the switching unit 14, when the combined power supply mode is not in place, there is no need to switch to the generator 2 output conduction state. When the combined power supply mode is in place, the generator 2 output is turned on, making the circuit conduction state easier to control without human intervention.

[0059] Furthermore, it can be understood that the control unit 13 is also electrically connected to the switching unit 14 in the above two embodiments to control the on and off of the switching unit 14, making the circuit conduction state easier to control without human intervention.

[0060] Please refer to Figure 9. In some embodiments, the generator grid-connected controller 1 further includes a first switch 16, a second switch 17 and a third switch 18. One end of the first switch 16 is used to connect the generator 2, and the other end is connected to the first conversion unit 11, so that the first conversion unit 11 is connected to the generator 2 via the first switch 16. The second switch 17 is used to be connected between the generator 2 and the first AC bus 5. The first AC bus 5 is also used to connect the first mains unit 4 and the first input end 31 of the load 3. The third switch 18 is used to be connected between the first AC bus 5 and the other end of the second conversion unit 12, so that the second conversion unit 12 is connected to the first input end 31 of the load 3 via the third switch 18 and the first AC bus 5. In the joint power supply mode, the first switch 16 and the third switch 18 are in the on state, and the second switch 17 is in the off state. It is understood that in the above embodiments, as shown in Figures 1, 2, and 4, in the combined power supply mode, the connection between the generator 2 and the first conversion unit 11 can be achieved by turning on the first switch 16, the disconnection between the generator 2 and the first AC bus 5 can be achieved by turning off the second switch 17, and the connection between the first AC bus 5 and the other end of the second conversion unit 12 can be achieved by turning on the third switch 18. Similarly, the first switch 16, the second switch 17, and the third switch 18 can also be connected to the control unit 13 and controlled by the control unit 13, making the circuit conduction state easier to control without human intervention. Moreover, the first switch 16, the second switch 17, and the third switch 18 can achieve further control and isolation, effectively ensuring the stable operation of the power supply system. In addition, it is understood that in other embodiments (such as the embodiments shown in Figures 1-8), the first switch 16, the second switch 17, and the third switch 18 can be added at the corresponding positions to achieve further control and isolation, effectively ensuring the stable operation of the power supply system.

[0061] Referring to FIG. 10 , in some other embodiments, the generator grid-connected controller 1 further includes a third conversion unit 15, the third conversion unit 15 including an inverter or a third bidirectional converter. One end of the third conversion unit 15 is connected to the other end of the first conversion unit 11, and the other end of the third conversion unit 15 is connected to the second input terminal 32 of the load 3. The third conversion unit 15 is configured to convert the first DC voltage into a fifth AC voltage in the combined power supply mode and provide the fifth AC voltage to the load 3. Thus, the generator 2 jointly supplies power to the load 3 via the generator grid-connected controller 1 and the second mains unit 6 connected to the second input terminal 32 of the load 3. It should be noted that the load 3 may be a plurality of sub-loads 3, i.e., a plurality of electrical devices. Different electrical devices may be supplied with power by one or more of the first mains unit 4 and the second mains unit 6 through the first input terminal 31 and the second input terminal 32 according to power demand. The first input terminal 31 and the second input terminal 32 may be power supply input terminals for different electrical devices, or may be multiple different power supply input terminals for the same electrical device. By providing the third conversion unit 15 , power can be supplied to multiple loads 3 or multiple input terminals of the loads 3 , thereby effectively utilizing the electrical energy of the generator 2 and saving energy, thereby improving the power supply efficiency and reliability of the entire system.

[0062] As shown in FIG11 , considering the daily operation and maintenance requirements of the generator 2, it is necessary to test the generator 2. Therefore, the power supply system 100 can also have a generator test mode. In this embodiment, when the first mains unit 4 is normal and in the generator test mode, the control unit 13 controls the entry into the joint power supply mode, so that when the generator 2 is tested, the generator 2 and the first mains unit 4 jointly supply power to the load 3. It can be understood that in the generator test mode, the generator 2 and the first mains unit 4 can also enter the shown joint power supply mode and jointly supply power to the load 3, thereby effectively utilizing the electrical energy of the generator 2 and saving energy, thereby improving the power supply efficiency and reliability of the entire system. In particular, compared with the energy waste caused by the use of dummy loads in the existing generator test mode, in the embodiment of the present application, the electrical energy released during the generator 2 test is used to supply power to the load 3, which can achieve better energy-saving effects, ensure the quality of diesel, and avoid serious diesel waste.

[0063] Furthermore, the control unit 13 is configured to control the generator 2 to start in the generator test mode, so that the generator 2 outputs the first AC voltage according to the set output power, and the generator output energy meter 7 obtains the output energy and / or power supply time of the generator 2. The control unit 13 is further configured to control the generator 2 to shut down when the output energy and / or power supply time reach a preset value, thereby completing the generator 2 test. It is understood that the generator 2 calculates output power * time = output energy based on the set output power and / or power supply time. This portion can be obtained by measuring the input side of the generator output energy meter 7, or by obtaining it from the output side. When the preset value is reached, the control unit 13 issues a shutdown command for the generator 2, and the generator 2 shuts down, thereby completing the generator 2 test. By connecting the generator output energy meter 7 to perform the generator 2 test, accurate power supply capacity requirements can be obtained, power capacity requirements can be optimized, and operating costs can be reduced.

[0064] Furthermore, in one embodiment, the control unit 13 is also used to determine whether it is in a peak power period. When it is in the peak power period, the first mains power unit is normal and is in the generator test mode, the control unit 13 controls the entry into the combined power supply mode; when the peak power period ends, the control unit 13 controls the end of the combined power supply mode and the generator 2 is shut down. It can be understood that entering the generator 2 test mode during the peak power period to test the generator 2 allows the use of the electricity generated by the generator 2 during the peak power period, and the electricity generated by the generator 2 can also be provided to the load 3 instead of connecting a dummy load. This not only reduces the mains power supply power during the peak power period, thereby saving costs and improving the reliability of the mains power supply, but also avoids energy waste during the test process, effectively utilizing the electricity of the generator 2 and saving energy.

[0065] Furthermore, in some other embodiments, the control unit 13 is further configured to determine whether the power load of the load 3 exceeds a set value. When the power load of the load 3 exceeds the set value and the first AC power unit is normal and in the generator test mode, the control unit 13 controls the generator 2 to enter the generator test mode. When the power load of the load 3 does not exceed the set value, the control unit 13 controls the generator 2 to shut down. It is understood that when the power load of the load 3 exceeds the set value and the first AC power unit is normal and in the generator test mode, the control unit 13 controls the generator 2 to enter the generator 2 test mode, thereby completing the generator 2 test while simultaneously supplying power to the load 3, effectively utilizing the power of the generator 2 and saving energy.

[0066] Furthermore, as shown in Figures 3 and 4, the other end of the first conversion unit 11 and one end of the second conversion unit 12 are also used to electrically connect to the energy storage unit 9. The first conversion unit 11 is also used to output the first DC voltage to supply power to the energy storage unit 9 in the generator test mode until the electric energy of the energy storage unit 9 reaches the first preset capacity value (such as fully charged), and when the generator test mode ends, the energy storage unit 9 is also used to supply power to the load 3 via the second conversion unit 12 until the electric energy of the energy storage unit 9 reaches the second preset capacity value (such as the minimum power). By setting the energy storage unit 9, the generator 2 test can be completed while charging the energy storage unit 9 in the generator test mode. The power generation characteristics of the generator 2 can be effectively utilized to operate at the optimal power generation efficiency. The excess electric energy is used to charge the energy storage unit 9, so that when the output load 3 is low, the generator 2 operates under a more efficient power generation efficiency condition, further avoiding the diesel carbon deposition phenomenon caused by low-load operation, and reducing the maintenance work of the generator 2. At the same time, after the generator test mode ends, the energy storage unit 9 can continue to be discharged until the energy storage unit 9 is discharged to reach the second preset capacity value, thereby improving the reliability of the power supply system 100 and saving energy.

[0067] It should be noted that in all the above embodiments, in addition to the control unit 13 being able to control the power supply system 100 to enter different power supply modes according to actual power consumption, manual control can also be supported. In addition, referring to FIG12 , the generator 2 can be a single generator or a generator set consisting of multiple generators. The generator 2 or the generator set can be controlled by the control unit 13 to start or shut down one or more of the generators. When the generator 2 or the generator set can be of different voltages, it can also include different voltage conversion devices 8, such as transformers. As shown in FIG12 , in this embodiment, the first AC power unit 4 is a 10KV voltage input, and multiple generators 2 with an output voltage of 10KV are connected in parallel. The first AC bus 5 is a 10KV output, which is converted into a 380V AC bus through the voltage conversion device 8, such as a transformer, and output to the load 3.

[0068] Referring to FIG. 13 , the present invention provides a method for controlling a generator connected to the grid, for use in the aforementioned power supply system 100 having a first mains unit 4, a generator 2, a first conversion unit 11, a second conversion unit 12, and a load 3. The first conversion unit 11 comprises a rectifier or a first bidirectional converter, one end of which is connected to the output end of the generator 2. The second conversion unit 12 comprises an inverter or a second bidirectional converter, one end of which is connected to the other end of the first conversion unit 11, and the other end of the second conversion unit 12 is connected to the first input end 31 of the load 3. The method may include the following step S101.

[0069] Step S101: In the joint power supply mode, the first conversion unit 11 is controlled to convert the first AC voltage provided by the generator 2 into a first DC voltage, and the second conversion unit 12 is controlled to convert the first DC voltage into a second AC voltage and provide the second AC voltage to the load 3, so that the generator 2 jointly supplies power to the load 3 via the generator grid-connected controller 1 and the first AC power unit 4 connected to the first input terminal 31 of the load 3.

[0070] Furthermore, in the embodiment shown in FIG14 , the method may further include the following steps:

[0071] Step S301: Determine whether the power of the load 3 exceeds a set value.

[0072] Step S302: When the power of the load 3 exceeds the set value, the control enters the joint power supply mode.

[0073] In step S302, when entering the combined power supply mode, the above step S101 may be executed. The specific content has been explained in step S101 and will not be repeated here.

[0074] Step S303: When the power of the load 3 does not exceed the set value, the generator 2 is controlled to be turned off.

[0075] Please refer to FIG3 , FIG4 and FIG13 , further, the other end of the first conversion unit 11 and one end of the second conversion unit 12 are also used to electrically connect to the energy storage unit 9 , and the method further includes the following step S102 .

[0076] Step S102: Control the first conversion unit 11 to also output the first DC voltage to charge the energy storage unit 9 in the joint power supply mode; when the joint power supply ends, control the energy storage unit 9 to also supply power to the load 3 via the second conversion unit 12 until the electric energy of the energy storage unit 9 reaches a preset capacity value.

[0077] Referring to FIG. 5 , FIG. 6 , and FIG. 15 , further, in another embodiment, the power supply system 100 further includes a switching unit 14, wherein a first end A of the switching unit 14 is connected to one end of the first conversion unit 11, and a second end B of the switching unit 14 is used to connect to the generator 2, such that the generator 2 is connected to one end of the first conversion unit 11 via the second end B and the first end A of the switching unit 14, and a third end C of the switching unit 14 is used to connect to the other end of the second conversion unit 12 to connect to the load 3. The method further includes the following steps:

[0078] Step S501: when the combined power supply mode is not in effect, the first terminal and the second terminal are controlled to be disconnected, and the first terminal and the third terminal are controlled to be connected.

[0079] Step S502: When in the combined power supply mode, control the first terminal and the second terminal to be connected, and the first terminal and the third terminal to be disconnected.

[0080] Referring to Figures 7, 8, and 16, in some other embodiments, the power supply system 100 further includes a switching unit 14, wherein a first end A of the switching unit 14 is connected to one end of the first conversion unit 11, and a second end B of the switching unit 14 is used to connect to the generator 2, such that the generator 2 is connected to one end of the first conversion unit 11 via the second end B and the first end A of the switching unit 14, and a third end C of the switching unit 14 is used to connect to the second input end 32 of the load 3 and the second mains unit 6. The method further includes the following steps:

[0081] Step S601: When not in the joint power supply mode, control the first end and the second end to be disconnected, the first end and the third end to be connected, and the first bidirectional converter and the second bidirectional converter to operate in reactive compensation and / or active filtering mode.

[0082] Step S602: in the combined power supply mode, controlling the first terminal and the second terminal to be connected, and the first terminal and the third terminal to be disconnected.

[0083] As shown in Figure 10, in some other embodiments, the power supply system 100 also includes a third conversion unit 15, the third conversion unit 15 includes an inverter or a third bidirectional converter, one end of the third conversion unit 15 is used to connect to the other end of the first conversion unit 11, and the other end of the third conversion unit 15 is used to connect to the second input end 32 of the load 3. The method also includes, in the joint power supply mode, controlling the third conversion unit 15 to convert the first DC voltage into a fifth AC voltage and providing the fifth AC voltage to the load 3, so that the generator 2 jointly supplies power to the load 3 via the generator grid controller 1 and the second AC power unit 6 connected to the second input end 32 of the load 3.

[0084] Referring to FIG. 11 and FIG. 17 , in another embodiment, the power supply system 100 may have a generator test mode, and the method may include:

[0085] Step S701: When the first AC power unit 4 is operating normally and in the generator 2 test mode, the control unit 13 controls the power supply system 100 to enter the combined power supply mode, so that when the generator 2 is tested, the generator 2 and the first AC power unit 4 jointly supply power to the load 3. In step S701, once the combined power supply mode is entered, step S101 above may be executed. The details of step S101 have been described in detail and will not be repeated here.

[0086] In another embodiment, the method may further include:

[0087] Step S702: Control the generator 2 to start in the generator test mode, so that the generator 2 outputs the first AC voltage according to the set output power, and the generator output power meter 7 obtains the output power and / or power supply time of the generator 2.

[0088] Step S703: When the output power and / or the power supply time reaches a preset value, the generator 2 is controlled to be turned off, thereby completing the generator 2 test.

[0089] Furthermore, in one embodiment, as shown in FIG18 , the method includes:

[0090] Step S801: Determine whether it is in the peak power period and whether the first AC power unit is normal. When it is in the peak power period and the first AC power unit is normal, execute step S802; when the peak power period ends, execute step S803.

[0091] Step S802: When the system is in the peak power period, the first mains power unit is normal and in the generator test mode, the system controls the system to enter the combined power supply mode.

[0092] In step S802, when entering the combined power supply mode, the above step S101 may be executed. The specific content has been explained in step S101 and will not be repeated here.

[0093] Step S803: When the peak power period ends, the combined power supply mode is controlled to end, and the generator 2 is turned off.

[0094] Furthermore, the other end of the first conversion unit 11 and one end of the second conversion unit 12 are also used to electrically connect to the energy storage unit 9. As shown in Figures 3 and 4, the method includes:

[0095] In the generator test mode, the first conversion unit 11 is controlled to output the first DC voltage to supply power to the energy storage unit 9 until the energy storage unit 9 reaches the first preset capacity (such as fully charged), and when the generator test mode ends, the energy storage unit 9 is controlled to also supply power to the load 3 via the second conversion unit 12 until the electric energy of the energy storage unit 9 reaches a second preset capacity value (such as the minimum power).

[0096] It can be understood that the generator grid-connected control method described in Figures 13 to 18 can achieve the same effect as the power supply system of the corresponding embodiments above, and the beneficial effects of the generator grid-connected control method will not be repeated here.

[0097] Refer to Figure 19, which is a schematic diagram of the structure of a computer storage medium according to an embodiment of the present invention. The computer storage medium according to an embodiment of the present invention stores a program file 200 capable of implementing all of the above methods, wherein the program file 200 can be stored in the above computer storage medium in the form of a software product, including a number of instructions for causing a computer device (which can be a personal computer, server, or network device, etc.) or a processor to execute all or part of the steps of the method described in each embodiment of the present invention. The aforementioned computer storage medium includes: various media that can store program codes, such as a USB flash drive, a mobile hard disk, a read-only memory (ROM), a random access memory (RAM), a magnetic disk or an optical disk, or terminal devices such as a computer, a server, a mobile phone, and a tablet.

[0098] In the several embodiments provided by the present invention, it should be understood that the disclosed systems, devices, and methods can be implemented in other ways. For example, the device embodiments described above are merely illustrative. For example, the division of units is merely a logical function division. In actual implementation, there may be other division methods, such as multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. In addition, the mutual coupling or direct coupling or communication connection shown or discussed can be through some interface, indirect coupling or communication connection of devices or units, which can be electrical, mechanical or other forms.

[0099] In addition, the functional units in the various embodiments of the present invention may be integrated into a single processing unit, each unit may exist physically separately, or two or more units may be integrated into a single unit. The aforementioned integrated units may be implemented in the form of hardware or software functional units.

[0100] The above are merely embodiments of the present invention and are not intended to limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made using the contents of the present invention description and drawings, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.

Claims

1. A generator grid-connected controller, used in a power supply system having a first mains unit and a load, comprising: A first conversion unit, including a rectifier or a first bidirectional converter, one end of the first conversion unit is used to connect to the output end of the generator, so as to convert the first AC voltage provided by the generator into a first DC voltage in a joint power supply mode; as well as The second conversion unit includes an inverter or a second bidirectional converter, one end of the second conversion unit is used to connect to the other end of the first conversion unit, and the other end of the second conversion unit is used to connect to the first input end of the load. The second conversion unit is used to convert the first DC voltage into a second AC voltage and provide the second AC voltage to the load in the joint power supply mode, so that the generator jointly supplies power to the load via the generator grid-connected controller and the first AC power unit connected to the first input end of the load.

2. The generator grid-connected controller according to claim 1, characterized in that: The generator grid-connected controller also includes a control unit, which is used to electrically connect the first conversion unit, the second conversion unit and the generator, and the control unit is used to control the generator grid-connected controller to enter the joint power supply mode.

3. The generator grid-connected controller according to claim 2, characterized in that: The control unit is also used to determine whether the load power exceeds a set value. When the load power exceeds the set value, the control unit controls the entry into the combined power supply mode; when the load power does not exceed the set value, the control unit controls the generator to shut down.

4. The generator grid-connected controller according to claim 2, characterized in that: The other end of the first conversion unit and one end of the second conversion unit are also used to electrically connect to an energy storage unit, and the first conversion unit is also used to output the first DC voltage in the joint power supply mode to charge the energy storage unit to a first preset capacity value; when the joint power supply ends, the energy storage unit is also used to supply power to the load via the second conversion unit until the electric energy of the energy storage unit reaches a second preset capacity value.

5. The generator grid-connected controller according to claim 2, characterized in that: The generator grid-connected controller also includes a switching unit, a first end of the switching unit is connected to one end of the first conversion unit, and a second end of the switching unit is used to connect the generator, so that the generator is connected to one end of the first conversion unit via the second end and the first end of the switching unit, and a third end of the switching unit is used to connect the other end of the second conversion unit to connect the load, when not in the combined power supply mode, the first end and the second end are disconnected, and the first end and the third end are connected; when in the combined power supply mode, the first end and the second end are connected, and the first end and the third end are disconnected.

6. The generator grid-connected controller according to claim 2, characterized in that: The generator grid-connected controller also includes a switching unit, a first end of the switching unit is connected to one end of the first conversion unit, and a second end of the switching unit is used to connect the generator, so that the generator is connected to one end of the first conversion unit via the second end and the first end of the switching unit, and the third end of the switching unit is used to connect the second input end of the load and the second AC power unit. When not in the combined power supply mode, the first end and the second end are disconnected, the first end and the third end are connected, and the first bidirectional converter and the second bidirectional converter operate in reactive compensation and / or active filtering mode; when in the combined power supply mode, the first end and the second end are connected, and the first end and the third end are disconnected.

7. The generator grid-connected controller according to claim 2, characterized in that: The generator grid-connected controller also includes a first switch, a second switch and a third switch. One end of the first switch is used to connect the generator, and the other end is connected to the first conversion unit, so that the first conversion unit is connected to the generator via the first switch. The second switch is used to connect between the generator and a first AC bus. The first AC bus is also used to connect the first mains unit and the first input end of the load. The third switch is used to connect between the first AC bus and the other end of the second conversion unit, so that the second conversion unit is connected to the first input end of the load via the third switch and the first AC bus. In the joint power supply mode, the first switch and the third switch are in an on state, and the second switch is in a closed state.

8. The generator grid-connected controller according to claim 1 or 2, characterized in that: The generator grid-connected controller also includes a third conversion unit, which includes an inverter or a third bidirectional converter. One end of the third conversion unit is used to connect to the other end of the first conversion unit, and the other end of the third conversion unit is used to connect to the second input end of the load. The third conversion unit is used to convert the first DC voltage into a fifth AC voltage in the joint power supply mode and provide the fifth AC voltage to the load, so that the generator jointly supplies power to the load via the generator grid-connected controller and the second AC power unit connected to the second input end of the load.

9. The generator grid-connected controller according to claim 2, characterized in that: The power supply system has a generator test mode. When the first AC power unit is normal and in the generator test mode, the control unit controls entry into the joint power supply mode, so that during the generator test, the generator and the first AC power unit jointly supply power to the load.

10. The generator grid-connected controller according to claim 9, characterized in that: The control unit is used to control the start-up of the generator in the generator test mode, so that the generator outputs the first AC voltage according to the set output power, and enables the generator output electric energy meter to obtain the output electric energy and / or power supply time of the generator. The control unit is also used to control the generator to shut down when the output electric energy and / or the power supply time reaches a preset value, thereby completing the generator test.

11. The generator grid-connected controller according to claim 9, characterized in that: The control unit is also used to determine whether it is in a peak power period. When it is in the peak power period, the first AC power unit is normal and in the generator test mode, the control unit controls entering the combined power supply mode; when the peak power period ends, the control unit controls the end of the combined power supply mode and the generator is shut down.

12. The generator grid-connected controller according to claim 9, characterized in that: The other end of the first conversion unit and one end of the second conversion unit are also used to electrically connect an energy storage unit. The first conversion unit is also used to output the first DC voltage to power the energy storage unit in the generator test mode, and when the generator test mode ends, the energy storage unit is also used to power the load via the second conversion unit.

13. A method for controlling a generator connected to the grid, used in a power supply system having a first AC power unit, a generator, a first conversion unit, a second conversion unit and a load, wherein the first conversion unit comprises a rectifier or a first bidirectional converter, one end of the first conversion unit is used to connect to the output end of the generator, the second conversion unit comprises an inverter or a second bidirectional converter, one end of the second conversion unit is used to connect to the other end of the first conversion unit, and the other end of the second conversion unit is used to connect to the first input end of the load, characterized in that: The method comprises: In the combined power supply mode, the first conversion unit is controlled to convert the first AC voltage provided by the generator into a first DC voltage, and the second conversion unit is controlled to convert the first DC voltage into a second AC voltage and provide the second AC voltage to the load, so that the generator and the first AC power unit connected to the first input terminal of the load jointly power the load.

14. The generator grid-connected control method according to claim 13, characterized in that: The other end of the first conversion unit is used to connect one end of a third conversion unit, the third conversion unit includes an inverter or a third bidirectional converter, and the other end of the third conversion unit is used to connect the second input end of the load. The method includes: In the combined power supply mode, the third conversion unit is controlled to convert the first DC voltage into a fifth The generator and the second AC power unit connected to the second input terminal of the load jointly supply power to the load.

15. The generator grid-connected control method according to claim 14, characterized in that: The power supply system has a generator test mode, and the method comprises: When the first mains power unit is normal and in the generator test mode, control is performed to enter the joint power supply mode, so that during the generator test, the generator and the first mains power unit jointly supply power to the load.

16. A computer storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the power supply control method according to any one of claims 13 to 15 is implemented.

Citation Information

Patent Citations

  • Controlling method of energy feedback type diesel engine testing device

    CN102570506A

  • Alternating current and direct current hybrid micro-grid system and control strategy thereof

    CN104505867A

  • Energy feedback system applied to power generator and power generation system

    CN109412199A

  • Converter and control method thereof

    CN109787298A

  • Active grid-connected and off-grid switching control method and system for energy storage grid-connected converter

    CN115085261A