Synchronous rapid construction method for concurrent construction of navigation lock and water gate in curved channel

By adopting a synchronous rapid construction method in curved rivers, including parallel construction of open diversion channels and ship locks, the problems of long construction cycles and high costs are solved, and a more efficient and safe construction process is achieved, adapting to weather and water flow changes.

WO2024250808A1PCT designated stage expired Publication Date: 2024-12-12THE FIRST CONSTRUCTION COMPANY OF CCCC SECOND HARBOR ENGINEERING CO LTD +2

Patent Information

Application Number
PCT/CN2024/084365
Authority / Receiving Office
WO · WO
Patent Type
Applications
Current Assignee / Owner
Priority Date
2023-11-30
Filing Date
2024-03-28
Publication Date
2024-12-12

AI Technical Summary

Technical Problem

The construction period of new ship locks and sluice locks in natural curved rivers is relatively long, it is difficult to deal with weather changes, and it is costly.

Method used

The synchronous rapid construction method of parallel curved river ship locks and sluices, including excavating diversion channels and lock foundation pits at the end of the flood season, using sluices and sluices downstream earth and rock cofferdams in the early stage of the dry season, quickly constructing sluices, and restoring natural conditions during the flood season The river flow is constructed by overflow using open diversion channels and locks. It is preferred to use a quick-disassembly structure and air cushion support prefabricated plates to improve construction efficiency and safety.

Benefits of technology

The construction period is shortened, the earth excavation is saved, and the construction cost is reduced. Through the use of quick-demolition structure and the use of air-cushion support prefabricated plates, the construction efficiency and safety are improved, and weather changes and water flow impact are adapted to weather changes.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN2024084365_12122024_PF_FP_ABST
    Figure CN2024084365_12122024_PF_FP_ABST
Patent Text Reader

Abstract

Provided in the present invention is a synchronous rapid construction method for concurrent construction of a navigation lock and a water gate in a curved channel. The synchronous rapid construction method comprises the following steps: S1, at the end of the wet season, excavating an open diversion ditch, synchronously excavating a foundation pit for a navigation lock which is not on a natural channel, and constructing the navigation lock; S2, constructing a steel trestle bridge for transportation; S3, in the early stage of the dry season, closing the natural channel by using an earth-rockfill cofferdam upstream of the water gate and an earth-rockfill cofferdam downstream of the water gate, and using the open diversion ditch for the travelling of water; S4, rapidly constructing the water gate on the closed natural channel, wherein the water gate is built close to two side portions of the natural channel; S5, before the next year's flood season, breaching the earth-rockfill cofferdam upstream of the water gate and the earth-rockfill cofferdam downstream of the water gate in the natural channel, and using the natural channel for passing through the flood season; and S6, after the flood season, restoring the earth-rockfill cofferdam upstream of the water gate on the natural channel, reusing the open diversion ditch for the travelling of water, and continuing to construct the water gate at the same time. The method of the present invention is ingenious and can reduce, from multiple aspects, the influence on construction caused by a water flow experiencing a sudden weather change and the flood season, thereby improving the overall construction efficiency.
Need to check novelty before this filing date? Find Prior Art

Description

A synchronous and rapid construction method for parallel ship locks and sluice gates in curved rivers Technical Field

[0001] The present invention relates to the technical field of water conservancy construction, in particular to a synchronous and rapid construction method for parallel ship locks and sluices in curved river channels. Background Art

[0002] When constructing new ship locks and sluices in naturally curved river channels, sluices are often built within the natural channel to cut off the channel, while ship locks are used to straighten the curve. Existing construction methods often involve building large diversion channels and completely blocking the natural channel, or constructing ship locks first and then using them to pass water, resulting in a long construction period. Chinese patent document CN 116145623 A describes a construction method combining a diversion channel with a navigation structure. However, this method requires excavating a navigable diversion channel, resulting in a massive excavation effort, a long project cycle, and high costs. Chinese patent document CN 110004959 A describes a method and formwork for rapidly constructing a concrete cofferdam in a dynamic water environment. However, this method does not describe how to utilize the diversion channel for construction, resulting in drawbacks. Summary of the Invention

[0003] The present invention provides a synchronous and rapid construction method for parallel ship locks and sluices in curved river channels, which solves the problems of long construction period, difficulty in coping with weather changes and high construction cost.

[0004] To solve the above technical problems, the technical solution adopted by the present invention is: a synchronous and rapid construction method for parallel ship locks and sluices in curved river channels, comprising the following steps:

[0005] S1. At the end of the flood season, diversion channels will be excavated, and simultaneously, foundation pits for ship locks that are not located on natural river channels will be excavated and ship locks constructed;

[0006] S2, construction traffic steel trestle;

[0007] S3. In the early dry season, earth and rock cofferdams upstream and downstream of the sluice gates are used to intercept the natural river channel, and diversion channels are used to pass the flow;

[0008] S4. Rapidly construct sluice gates on the cut-off natural river channel, and build the sluice gates on both sides close to the natural river channel;

[0009] S5. Before the next flood season arrives, open the earth and rock cofferdam upstream of the sluice gate and the earth and rock cofferdam downstream of the sluice gate in the natural river channel to use the natural river channel for flood control;

[0010] S6. After the flood season, restore the earth and rock cofferdam upstream of the sluice gate on the natural river channel and use the diversion channel to pass the water again, while continuing the sluice gate construction;

[0011] S7. Construction of the upstream navigation channel cofferdam, upstream cofferdam of the ship lock, downstream cofferdam of the ship lock and downstream navigation channel cofferdam on both sides of the ship lock;

[0012] S8. After the ship lock construction is completed, use the ship lock until the sluice gate construction is completed.

[0013] In the preferred solution, in S1, anti-seepage stability calculations should be performed on the diversion channel to ensure that the slope is not damaged.

[0014] In the preferred solution, in S3, vertical blocking method is used to intercept the flow. First, embankments are built on one or both sides of the riverbed, and dikes are built to continuously narrow the riverbed to form a dragon mouth. The dragon mouth is quickly filled and anti-seepage construction is carried out.

[0015] In the preferred solution, if the riverbed in S3 is easily eroded, stone dumping should be carried out to protect the bottom before diversion; if the riverbed base surface is relatively smooth, materials with good erosion resistance should be dumped to increase the riverbed roughness; for the deep water at the dragon mouth, stones should be dumped first to fill the deep groove.

[0016] In the preferred solution, in S3, the dragon mouth is located at a place with good riverbed geology and strong anti-scouring ability.

[0017] In the preferred solution, in S1, firstly, the historical weather data of the construction area and the current season are analyzed and judged, the time span of the wet season, the dry season and the flood season is calculated, and the construction nodes are reasonably controlled.

[0018] In a preferred solution, in S3, the earth-rock cofferdam upstream of the sluice and the earth-rock cofferdam downstream of the sluice are constructed using a quick-disassembly structure, which includes gabions and prefabricated panels.

[0019] In the preferred solution, gabions are set on both sides of the earth-rock cofferdam upstream of the sluice and the earth-rock cofferdam downstream of the sluice, and the gaps between the gabions and the natural river channel are filled with fine stones. Prefabricated panels or gabions are used to build the bottom in the middle, and then prefabricated panels are laid in sequence from bottom to top.

[0020] In a preferred solution, before the prefabricated panels are hoisted, air cushions are installed under the corresponding prefabricated panels according to the design. During installation, the air in the air cushions is kept discharged, and the prefabricated panels and the air cushions are tightly fitted.

[0021] In a preferred solution, embedded sleeves are installed on the side walls when the prefabricated panels are prefabricated, and then the prefabricated panels and the air cushions are fixed using connecting holes and bidirectional screws on the air cushions, and different air cushions are connected using drawstrings.

[0022] The beneficial effects of the present invention are as follows: excavating a diversion open channel, using the diversion open channel to get through the dry season, and using the diversion open channel and natural river channels, the diversion open channel and the ship lock to get through the flood season. Compared with the traditional large diversion open channel excavation, a large amount of earth excavation is saved, and compared with using the ship lock to pass the flow, the construction period is shorter. At the same time, in order to facilitate the subsequent breaking of the earth and rock cofferdam upstream and downstream of the sluice, the vacuumed air cushion is used to support the prefabricated plate to play a role of sealing and water blocking. When it needs to be dismantled, the air cushion is inflated, and the air cushion supports the prefabricated plate to shift under the action of the water flow. At the same time, multiple air cushions cooperate with each other to move to both sides for disassembly. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] The present invention will be further described below with reference to the accompanying drawings and examples:

[0024] FIG1 is a schematic diagram of the present invention;

[0025] FIG2 is a schematic cross-sectional view of the earth-rock cofferdam upstream and downstream of the sluice gate of the present invention;

[0026] FIG3 is a schematic diagram of the connection between the air cushion and the prefabricated plate of FIG2 ;

[0027] FIG4 is a schematic diagram of the explosion structure of FIG3 ;

[0028] FIG5 is a diagram of the air cushion of the present invention in state 1 during installation;

[0029] FIG6 is a second view of the air cushion of the present invention during installation.

[0030] In the figure: upstream navigation channel cofferdam 1; upstream cofferdam 2 of ship lock; downstream cofferdam 3 of ship lock; downstream navigation channel cofferdam 4; ship lock 5; diversion channel 6; sluice gate 7; earth-rock cofferdam 8 upstream of sluice gate; earth-rock cofferdam 9 downstream of sluice gate; natural river channel 10; gabion 11; prefabricated panel 12; air cushion 13; connecting hole 1301; bidirectional screw 1302; connecting plate 1303; first magnetic plate 1304; second magnetic plate 1305; avoidance position 1306; pull rope 14; embedded sleeve 15. Modes for Carrying Out the Invention

[0031] As shown in Figure 1, a synchronous and rapid construction method for parallel ship locks and sluices in a curved river includes the following steps:

[0032] S1. At the end of the flood season, diversion channel 6 is excavated. Simultaneously, the foundation pit of ship lock 5, which is not on the natural river channel 10, is excavated and ship lock 5 is constructed. The project exploration drawings are obtained, and then, based on the location of sluice 7, a suitable location for diversion channel 6 is found to ensure the overall water retention capacity.

[0033] S2, construction traffic steel trestle;

[0034] S3. In the early dry season, the earth-rock cofferdam 8 upstream of the sluice and the earth-rock cofferdam 9 downstream of the sluice are used to intercept the natural river channel 10, and the diversion channel 6 is used to pass the flow; the earth-rock cofferdam 8 upstream of the sluice and the earth-rock cofferdam 9 downstream of the sluice ensure that the conditions are stable during the construction of the sluice 7 in the natural river channel 10 without the influence of water flow.

[0035] S4. Rapidly construct the sluice gate 7 on the cut-off natural river channel 10, and build the sluice gate 7 close to both sides of the natural river channel 10; constructing the sluice gate 7 on both sides can avoid the impact of the sudden increase in water flow when sudden weather occurs. The construction is carried out in a manner of gradually approaching the two sides to the middle, which reduces the impact and damage of the water flow on the constructed structure and plays a role in alleviating the unloading force.

[0036] S5. Before the next flood season, the earth-rock cofferdam 8 upstream of the sluice and the earth-rock cofferdam 9 downstream of the sluice are opened in the natural river channel 10, and the natural river channel 10 is used to pass the flood season; the earth-rock cofferdam 8 upstream of the sluice and the earth-rock cofferdam 9 downstream of the sluice are broken down as needed to ensure that the broken water flow opening meets the demand for flood discharge.

[0037] S6. After the flood season, the earth and rock cofferdam 8 upstream of the sluice gate on the natural river channel 10 is restored, and the diversion channel 6 is used to flow again. At the same time, the construction of the sluice gate 7 is continued; the sluice gate is restored to the state before the break to maintain the water blocking effect.

[0038] S7. Construction is carried out on the upstream navigation channel cofferdam 1, the upstream cofferdam 2, the downstream cofferdam 3 and the downstream navigation channel cofferdam 4 on both sides of the ship lock 5; each section is constructed simultaneously to facilitate the control of the overall construction progress.

[0039] S8. After the construction of ship lock 5 is completed, ship lock 5 is used until the construction of sluice 7 is completed. Ship lock 5 will not be interrupted during the entire process, and the overall construction period is guaranteed. Then, after the construction of ship lock 5 is completed, it can be used as the main flow channel to continue to provide a good construction environment for sluice 7. Until the construction of sluice 7 reaches the maintenance intensity and can play the role of water blocking, the opening and closing tests of small flow, medium flow and large flow are carried out in sequence.

[0040] In the preferred solution, in S1, anti-seepage stability calculations should be performed on the diversion channel 6 to ensure that the slope is not damaged. During construction, the address structure of the project site should be considered to select an appropriate fitting formula for calculation to ensure the safety and stability of the overall construction.

[0041] In the preferred solution, in S3, vertical blocking is used to intercept the flow. First, dikes are built on one or both sides of the riverbed. The dikes are then built to gradually narrow the riverbed, forming a creek mouth. The creek mouth is then quickly filled and anti-seepage construction is carried out. This ensures strong water retention and structural stability under the action of gravity, avoiding the problem of a rapid increase in overall impact due to the gradual reduction of the water flow cross-section.

[0042] In the preferred solution, if the riverbed is prone to scouring in S3, riprap should be used to protect the bottom before diversion. If the riverbed surface is smooth, erosion-resistant materials should be added to increase the roughness of the riverbed. For deep water at the mouth of the dam, riprap should be used to fill the deep groove. Using riprap to build the bottom can better resist the impact of water flow from the bottom and ensure continuous sealing until the entire dam is closed.

[0043] In the preferred solution, in S3, the dragon mouth is located in an area with good riverbed geology and strong anti-scour ability. This ensures safe and efficient construction, reduces the use of stone materials, and further avoids the occurrence of dangerous situations.

[0044] In the preferred solution, in S1, historical weather data for the construction area and the current season are analyzed and assessed to estimate the time spans of the wet season, dry season, and flood season, allowing for reasonable control of construction nodes. When necessary, weather cloud maps are used to regularly broadcast information to the project site, facilitating efficient work and coordination among construction workers.

[0045] As shown in Figure 2, in the preferred solution, in S3, the earth-rock cofferdam 8 upstream of the sluice gate and the earth-rock cofferdam 9 downstream of the sluice gate are constructed using a quick-disassembly structure, which includes gabions 11 and prefabricated panels 12. This structure improves overall construction efficiency and significantly reduces construction difficulty. The gabions 11 and prefabricated panels 12 are hoisted using hoists, resulting in a good cross-sectional coordination effect.

[0046] In the preferred solution, gabions 11 are set on both sides of the earth and rock cofferdam 8 upstream of the sluice gate and the earth and rock cofferdam 9 downstream of the sluice gate, and the gap between the gabions 11 and the natural river channel 10 is filled with fine stones. Prefabricated panels 12 or gabions 11 are used to build the bottom in the middle, and then the prefabricated panels 12 are laid in sequence from bottom to top. With this structure, the overall water retaining effect is good, the force is stable, the bearing capacity is strong, and the interception and water retaining work can be completed efficiently, providing good construction conditions for the construction of the sluice gate 7. During the construction process, the flow rate of the natural river channel can be reasonably allocated according to the size of the water flow during the flood season. Due to current scientific and technological means, the weather changes and the actual conditions cannot be guaranteed to be completely consistent, and there may be situations where the weather forecast and the actual weather are opposite. When the construction of the sluice gate 7 is not completed and the cast structure is in the maintenance stage, in order to avoid excessive discharge through the natural river channel 10, the sluice gate is 7's structural impact and damage, initially, when the flood season flow is controllable, the diversion channel 6 is kept at full load, further increasing the maintenance time of the sluice 7, thereby providing sufficient guarantee for the sluice 7 to reach the maintenance intensity, and timely analysis and judgment are made according to weather changes and water flow changes. Since the hoisting method is adopted, the gabion 11 and the prefabricated plate 12 can be quickly hoisted. When the diversion channel 6 is overloaded, the number of prefabricated plates 12 is adjusted from top to bottom according to needs until it is completed. In particular, it provides convenience for the construction and maintenance of the sluice 7, ensuring the safety of construction personnel and the safety of the cast structure.

[0047] As shown in Figures 3-4, in the preferred solution, before the prefabricated panel 12 is hoisted, an air cushion 13 is installed under the corresponding prefabricated panel 12 according to the design. During installation, the air in the air cushion 13 is kept discharged, and the prefabricated panel 12 and the air cushion 13 are tightly fitted. In Figures 3 and 4, when the air cushion 13 is inflated, the prefabricated panel 12 can be completely wrapped. A rubber buffer layer is provided on the side of the air cushion 13 close to the prefabricated panel 12. This structure prevents the prefabricated panel 12 from being separated from the air cushion 13 under the impact of water flow, causing damage to the prefabricated panel 12 and damage to the air cushion 13, which makes it impossible to reuse the prefabricated panel 12 and requires salvaging the prefabricated panel 12.

[0048] As shown in Figures 5-6, in a preferred solution, embedded sleeves 15 are installed on the side walls during prefabrication of the prefabricated panels 12. The prefabricated panels 12 and air cushions 13 are then secured using connection holes 1301 and bidirectional screws 1302 on the air cushions 13. Different air cushions 13 are connected using drawstrings 14. Fixing rods are installed on both sides of the cofferdam, and the drawstrings 14 of the uppermost air cushion are fixed to the fixing rods on both sides of the natural river channel 10. This prevents the prefabricated panels from drifting downstream with the air cushions and impacting the sluice gate. Four connecting plates 1303 are provided in the middle of the air cushion 13, and the bidirectional screw 1302 is threadedly connected to the connecting plate 1303 and the embedded sleeve 15 respectively. The thread directions of the connecting plate 1303 and the embedded sleeve 15 are opposite. A first magnetic plate 1304 and a second magnetic plate 1305 with opposite magnetic properties are provided on both sides of the air cushion 13, and are marked with different colors. Since the air cushion is set to maintain a roughly flush state on both sides after degassing and vacuuming, a plurality of avoidance positions 1306 are formed along the circumference of the air cushion 13, and adjacent avoidance positions 1306 are provided. The first magnetic plate 1304 and the second magnetic plate 1305 on one side of 306 are magnetically attracted to each other, so that the prefabricated panel 12 can be accurately positioned when it is installed. The prefabricated panel 12 will have a certain amount of shaking during the hoisting. When the air cushion 13 supports the prefabricated panel 12 and gradually approaches the installed prefabricated panel, it is attracted by the magnetism and the pulling direction of the prefabricated panel is manually observed for adjustment. The position is calibrated under the interaction of the first magnetic plate 1304 and the second magnetic plate 1305, which greatly facilitates the use of the construction workers, especially when there is no good installation and accurate Under such circumstances, it can ensure high precision and good effect during installation, thereby better playing the role of water blocking. After the two adjacent air cushions 13 are installed in place in the uninflated state, the magnetic plates of the two adjacent air cushions attract each other and maintain a high-precision strong flexible connection with each other. This structure makes the overall reuse efficiency high, the effect good, and the installation and use convenient. The air cushion 13 will not enter the natural river channel 10 with the impact of the water flow. Even if the problem of the pull rope breaking occurs and it flows downward, it can be cut off according to the drifting state. The air cushion is made of multi-layer rubber, which can cope with the impact of external forces and avoid damage to it by sharp objects. At the same time, because it completely wraps the prefabricated board 12, it can avoid the problem of direct contact and impact of the prefabricated board 12 on existing buildings or structures. In order to ensure the safety of water flowing through the sluice 7, and at this time when the maintenance strength of the sluice 7 has not reached the design strength, in order to further reduce the impact of external forces, an air cushion is installed on the upstream side of the cast structure facing the natural river channel 10 for shock absorption, so as to better cope with the water flow impact problem under sudden weather changes and ensure the safety and stability of the construction of the sluice 7.

[0049] The above embodiments are merely preferred technical solutions of the present invention and should not be construed as limiting the present invention. The scope of protection of the present invention shall be the technical solutions set forth in the claims, including equivalent alternatives to the technical features of the technical solutions set forth in the claims. In other words, equivalent alternatives and improvements within this scope are also within the scope of protection of the present invention.

Claims

1. A synchronous and rapid construction method for a curved river channel ship lock and sluice in parallel, characterized by: The following steps are involved: S1. At the end of the flood season, excavate the diversion channel (6), simultaneously excavate the foundation pit of the ship lock (5) which is not on the natural river channel (10), and construct the ship lock (5); S2, construction traffic steel trestle; S3. In the early dry season, the earth-rock cofferdam (8) upstream of the sluice gate and the earth-rock cofferdam (9) downstream of the sluice gate are used to intercept the natural river channel (10), and the diversion open channel (6) is used for flow; S4, quickly constructing a sluice gate (7) on the cut-off natural river channel (10), and building two sides of the sluice gate (7) close to the natural river channel (10); S5. Before the next flood season arrives, the earth-rock cofferdam (8) upstream of the sluice gate and the earth-rock cofferdam (9) downstream of the sluice gate in the natural river channel (10) are opened, and the natural river channel (10) is used for flood control; S6, after the flood season, the earth and rock cofferdam (8) upstream of the sluice gate on the natural river channel (10) is restored, and the diversion channel (6) is used for flow again, while the construction of the sluice gate (7) continues; S7, constructing the upstream navigation channel cofferdam (1) on both sides of the ship lock (5), the upstream cofferdam (2) of the ship lock, the downstream cofferdam (3) of the ship lock, and the downstream navigation channel cofferdam (4); S8. After the construction of the ship lock (5) is completed, the ship lock (5) is used until the construction of the water lock (7) is completed.

2. According to the method for synchronous and rapid construction of ship locks and sluices in a curved river in parallel according to claim 1, it is characterized by: In S1, anti-seepage stability calculations should be performed on the diversion channel (6) to ensure that the slope is not damaged.

3. According to claim 1, a synchronous and rapid construction method for a curved river channel ship lock and sluice in parallel, characterized by: In S3, the vertical blocking method is used to intercept the flow. First, a dike is built on one or both sides of the riverbed, and the dike is filled to make the riverbed narrower and form a dragon mouth. The dragon mouth is quickly filled and anti-seepage construction is carried out.

4. According to claim 3, a synchronous and rapid construction method for a curved river channel ship lock and sluice in parallel is characterized by: In S3, if the riverbed is easily eroded, stones should be thrown to protect the bottom before diversion; if the riverbed base is relatively smooth, materials with good erosion resistance should be thrown to increase the roughness of the riverbed; for the deep water at the dragon mouth, stones should be thrown first to fill the deep groove.

5. According to claim 3, a synchronous and rapid construction method for a curved river channel ship lock and sluice in parallel is characterized by: In S3, the Longkou location is chosen where the riverbed geology is good and the anti-scouring ability is strong.

6. According to claim 1, a synchronous and rapid construction method for a curved river channel ship lock and sluice gate in parallel, characterized in that: In S1, we first analyze and judge the historical weather data of the construction area and the current season, calculate the time span of the flood season, dry season and flood season, and reasonably control the construction nodes.

7. The synchronous rapid construction method for parallel ship locks and sluice gates in a curved river according to claim 1, characterized in that: In S3, the earth-rock cofferdam (8) upstream of the sluice gate and the earth-rock cofferdam (9) downstream of the sluice gate are constructed using a quick-disassembly structure, which includes a gabion (11) and a prefabricated panel (12).

8. The synchronous rapid construction method for parallel ship locks and sluice gates in a curved river according to claim 7, characterized in that: Gabions (11) are arranged on both sides of an earth-rock cofferdam (8) upstream of a sluice gate and an earth-rock cofferdam (9) downstream of the sluice gate, and the gap between the gabions (11) and the natural river channel (10) is filled with fine stones. A prefabricated board (12) or a gabion (11) is used to build a bottom in the middle, and then the prefabricated boards (12) are laid in sequence from bottom to top.

9. The synchronous rapid construction method for a curved river channel ship lock and sluice in parallel according to claim 8 is characterized by: Before the prefabricated panel (12) is hoisted, an air cushion (13) is installed under the corresponding prefabricated panel (12) according to the design. During installation, the air in the air cushion (13) is discharged, and the prefabricated panel (12) and the air cushion (13) are tightly fitted.

10. The synchronous rapid construction method for parallel ship locks and sluice gates in a curved river according to claim 9, characterized in that: When the prefabricated plate (12) is prefabricated, the embedded sleeve (15) is installed on the side wall, and then the prefabricated plate (12) and the air cushion (13) are fixed by using the connection hole (1301) and the bidirectional screw (1302) on the air cushion (13), and different air cushions (13) are connected by using the pull rope (14).

Citation Information

Patent Citations

  • Once-closure and staging-closure combined dam type power plant construction diversion method

    CN104032714A

  • Construction method of diversion channel and navigation building combined structure

    CN116145623A

  • Flood discharge gate metal structure construction method for accelerating gate dam engineering construction progress

    CN116732948A

  • Synchronous rapid construction method for parallel ship lock and water lock of curved river channel

    CN117431892A

  • Disaster risk reduction method substituting collapse risk of large dam with numerous small dams or banks, and stationary bank / breakwater capable of being installed at low cost and in short time and to be emergency water source and emergency small-sized power source

    JP2015129427A

Cited By

  • Method and device for calculating mechanical parameters of vertical blocking flow

    CN119885978A