Medium-deep hole mining method for inclined medium-thick fractured orebody

By adopting a diamond-shaped stope structure and deep-hole ore extraction method in inclined medium-thick fractured ore bodies, the safety and efficiency issues in mining inclined medium-thick fractured ore bodies have been solved, achieving safe and efficient ore recovery and ore dilution control.

WO2026232886A1PCT designated stage Publication Date: 2026-11-12SANSHANDAO GOLD MINE SHANDONG GOLD MINING LAIZHOU
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
PCT/CN2026/075108
Authority / Receiving Office
WO · WO
Patent Type
Applications
Current Assignee / Owner
Priority Date
2025-05-08
Filing Date
2026-01-27
Publication Date
2026-11-12

AI Technical Summary

Technical Problem

Existing technologies suffer from low safety, low efficiency, and severe ore dilution in the mining of inclined, medium-thick, fractured ore bodies. In particular, the upward and downward approach mining methods are difficult to support, complex to construct, and cause serious damage to the sidewall backfill.

Method used

The stope and pillars are arranged along the strike of the ore body. In the vertical direction, segmented roadways and backfilled return airways are constructed. Combined with downward and upward fan-shaped deep holes for ore extraction, the stope structure is optimized into a rhombus shape. High-efficiency backfilling is used for backfilling, and the stope is recycled.

Benefits of technology

It has enabled safe and efficient ore mining, improved mining efficiency, reduced ore dilution rate, ensured stope stability and backfilling, and enhanced operational safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN2026075108_12112026_PF_FP_ABST
    Figure CN2026075108_12112026_PF_FP_ABST
Patent Text Reader

Abstract

A medium-deep hole mining method for an inclined medium-thick fractured orebody. Stopes are arranged along the strike of an orebody (5). In the horizontal direction, the orebody at a level is divided into a plurality of stopes along the strike of the orebody (5). In the vertical direction, the orebody at the level is further divided into a plurality of sublevels. An overall stoping method for a stope is a downward sublevel room-based stoping method. A room structure is a diamond-shaped stope structure. Downward fan-shaped medium-deep holes (13) and upward fan-shaped medium-deep holes (14) are respectively constructed in a backfill return-air drift (11) and a drilling drift (6) of a stope (10) for ore breaking. Ore is drawn through downward ore-drawing crosscuts (4) of the sublevels. The mining method has high mining efficiency and good safety for fractured orebodies.
Need to check novelty before this filing date? Find Prior Art

Description

A method for deep-hole mining of inclined, medium-thick, fractured ore bodies Technical Field

[0001] This invention belongs to the field of mining technology and relates to a deep-hole mining method for inclined, medium-thick, fractured ore bodies. This method is mainly applicable to the mining of inclined, medium-thick, fractured ore bodies in underground gold mining. The inclined, medium-thick, fractured ore body refers to an ore body with a dip angle of 50° or more, a horizontal thickness of 15-20m, well-developed joints and fractures, and requiring timely anchor mesh support after exposure; otherwise, the roof is highly susceptible to collapse. Background Technology

[0002] As a current technology, in the mining of inclined, medium-thick, fractured ore bodies, due to the relatively fractured ore body, the upward or downward approach backfilling mining method is generally adopted to ensure mining safety. The main disadvantages of the upward approach backfilling mining method are: large support requirements, high support difficulty, and low mining efficiency. The main disadvantages of the downward approach backfilling mining method are: complex construction technology, which restricts mining production capacity. Furthermore, regardless of whether it is the upward or downward approach mining method, since the mining method is tunneling, the sidewall backfilling body is significantly damaged during mining, resulting in increased tailings dilution. In upward approach mining, some ore bodies are extremely difficult to support due to their fracture and high ground pressure, making safe ore recovery impossible and increasing the mining loss rate. Technical issues

[0003] The technical problem to be solved by the present invention is to provide a deep-hole mining method for inclined medium-thick fractured ore bodies, so as to achieve safe, efficient and low-loss mining of inclined medium-thick fractured ore bodies. Technical solutions

[0004] The technical solution of the present invention is as follows:

[0005] A deep-hole mining method for inclined, medium-thick, fractured ore bodies includes the following steps:

[0006] 1) The stope is arranged along the strike of the ore body, and only the stope and pillars are arranged in the stope;

[0007] 2) In the vertical direction, between the middle section roadway and the upper middle section roadway in the mining area, segmented roadways are constructed in the footwall of the ore body;

[0008] 3) Construct several downward ore extraction cross passages from the vertical segment roadway to the footwall of the stope. After reaching the footwall of the ore body, construct a rock drilling roadway from the vertical downward ore extraction cross passage. Construct an upward filling return air connecting roadway from the vertical segment roadway to the footwall of the inter-pillar. After reaching the inter-pillar, construct an intra-vein filling return air connecting roadway within the inter-pillar to the footwall of the ore body. Construct a filling return air connecting roadway perpendicular to the intra-vein, connecting the filling return air connecting roadways of the two veins in the stope. At the middle position of the segment stope, construct a cutting riser from the rock drilling roadway upward to connect with the filling return air connecting roadway.

[0009] 4) When mining the stope, first slot the cutting riser; after slotting, advance parallel mining from the middle of the stope to the two side pillars, using a fan-shaped medium-deep hole for ore extraction, and use a loader to extract the ore in the downward ore extraction cross passage after blasting.

[0010] 5) After the sub-separated stope is mined out, high-ratio and low-ratio cemented backfill materials are used to fill the goaf.

[0011] 6) Following steps 2) to 5) above, the lower sub-stopes are mined in a cyclical manner until the entire stope is mined out.

[0012] Preferably, in step 1), the length of the stope is 50-60m, the width is the horizontal thickness of the ore body, and the width of the pillars is 8-10m.

[0013] Preferably, in step 2), a segmented roadway is constructed in the footwall of the ore body between the middle section roadway and the upper middle section roadway in the mining area; the height between the middle section roadways is 45-50m, and the height between the segmented roadways is 15-18m.

[0014] Preferably, in step 3), a portion of the filling return airway is arranged in the ore body, and another portion is arranged in the surrounding rock of the hanging wall of the ore body, and the top plate of the filling return airway is 1m higher than the top plate of the segmented stope.

[0015] Preferably, in step 4), the stope structure within the segment is a rhombus structure. At the middle position of the stope in the vertical direction, the maximum horizontal width of the stope is equal to the horizontal thickness of the ore body, and the stope height is 22-24m. The lower half of the rhombus structure stope has a “V” shaped ore chute structure on both sides, with an inclination angle of more than 50°. Downward fan-shaped medium-deep holes and upward fan-shaped medium-deep holes are constructed in the filling return airway and drilling tunnel of the stope for ore extraction.

[0016] The term "medium-thick fractured ore body" refers to an ore body with a horizontal thickness of 15-20m, a dip angle of more than 50°, and which requires support after exposure. Beneficial effects

[0017] The positive effects of this invention are as follows:

[0018] First, the mining area has a large production capacity and high mining efficiency. During stope mining, this invention uses a parallel mining method that advances from the middle of the stope towards the two side pillars, employing a fan-shaped medium-deep hole for ore extraction, resulting in a large production capacity and high mining efficiency.

[0019] Secondly, the stope structure adopts a rhombus-shaped stope structure, which has a large self-supporting capacity of the roof. This invention optimizes the stope structure into a rhombus-shaped stope structure, which can withstand greater ground stress and ensure greater safety of the stope roof.

[0020] Third, downward mining enables stress-relief mining, ensuring the safety and stability of the mining area. This invention, employing downward mining, cuts off the propagation path of high stress in the mining area, effectively regulates ground pressure, achieves stress-relief mining, reduces ground stress damage, ensures the safety and stability of the mining area, and solves the problems of large support requirements and difficult support in fractured ore bodies.

[0021] Fourth, the stope employs parallel drilling with medium-deep holes in both directions, resulting in high operational efficiency. This invention significantly improves drilling efficiency by constructing parallel downward and upward fan-shaped medium-deep holes in the filling return airway and drilling tunnel of the stope, respectively.

[0022] Fifth, the stope goaf can be filled to ensure roof support, preventing subsidence of the upper filling body. To ensure that the stope goaf filling is properly connected to the roof, this invention optimizes the layout of the filling return airway. Part of the filling return airway is located in the ore body, and the other part is located in the surrounding rock of the hanging wall of the ore body. Furthermore, the roof of the filling return airway is 1m higher than the roof of the segmented stope. Therefore, the stope goaf can be filled to ensure roof support, effectively preventing subsidence of the upper filling body.

[0023] Sixth, the exposed area of ​​the mining operations is small, resulting in high operational safety. According to this invention, mining operations are carried out in the backfilling return airway and drilling roadway, while ore extraction is carried out in the ore extraction roadway. The exposed cross-sectional area of ​​the drilling and ore extraction roadways is small, resulting in higher operational safety. Attached Figure Description

[0024] Figure 1 is a longitudinal projection view of the mining area according to an embodiment of the present invention; Figure 1 is a cross-sectional view along line I-I in Figure 2;

[0025] Figure 2 is a cross-sectional view of II-II in Figure 1;

[0026] Figure 3 is a cross-sectional view of III-III in Figure 1;

[0027] Figure 4 is a cross-sectional view of section IV-IV in Figure 1.

[0028] In the diagram: 1—Middle section roadway; 2—Upper middle section roadway; 3—Sectional roadway; 4—Downward ore extraction cross roadway; 5—Ore body; 6—Drilling roadway; 7—Upward filling return air connecting roadway; 8—Interstitial pillar; 9—Vein filling return air connecting roadway; 10—Station; 11—Filled return air roadway; 12—Cutting riser; 13—Downward fan-shaped medium-deep borehole; 14—Upward fan-shaped medium-deep borehole; 15—Ore; 16—Filled retaining wall; 17—High-ratio cemented filling body; 18—Low-ratio cemented filling body. Embodiments of the present invention

[0029] The present invention will be further described below with reference to the accompanying drawings and specific embodiments.

[0030] Referring to Figures 1, 2, 3, and 4, this embodiment describes the mining of an ore body with a dip angle of 50° and a horizontal thickness of 20m. This ore body has well-developed joints and fractures, requiring timely anchor mesh support after exposure; otherwise, the roof is highly susceptible to collapse. This embodiment mainly includes the following steps:

[0031] Step 1: The stope is laid out along the strike of ore body 5, with a length of 58m, a width of 20m, a height of 45m in the middle section, and a height of 15m in each section. Only stopes 10 and pillars 8 are arranged within the stope. Pillar 8 is 8m wide and has no top or bottom pillars. Vertically, from top to bottom, the stope is divided into three stops 10 according to the sections of ore body 5. Each stope 10 is 50m long and has a rhomboid structure. At the middle position of the vertical direction, the maximum horizontal width of stope 10 is 20m, and the height is 24m. The lower half of the rhomboid stope 10 has a "V"-shaped ore chute structure on both sides, with dip angles all above 50°.

[0032] Step 2: In the vertical direction, between the middle section roadway 1 and the upper middle section roadway 2 in the mining area, 50m away from the footwall of the ore body 5, construct the segment roadway 3.

[0033] Step 3: Construct several downward ore extraction cross passages 4 vertically from the segmented roadway 3 to the footwall of the stope 10. The downward ore extraction cross passages 4 are spaced 10m apart. After reaching the footwall of the stope 10, construct a rock drilling roadway 6 vertically from the downward ore extraction cross passages 4. Construct an upward filling return air connecting roadway 7 vertically from the segmented roadway 3 to the footwall of the inter-pillar 8. After reaching the footwall of the inter-pillar 8, construct an intra-vein filling return air connecting roadway 9 in each inter-pillar 8 to the footwall of the ore body 5. Construct a filling return air roadway 11 perpendicular to the intra-vein filling return air connecting roadway 9 to connect the intra-vein filling return air connecting roadways 9 in the inter-pillar 8. To facilitate the filling of the goaf of the stope 10, optimize the layout of the filling return air roadway 11. Part of the filling return air roadway 11 is arranged in the ore body 5, and the other part is arranged in the surrounding rock of the footwall of the ore body 5. The roof of the filling return air roadway 11 is 1m higher than the roof of the segmented stope 10. In the middle of the segmented stope 10, the cutting shaft 12 is constructed from the rock drilling tunnel 6 upwards and connected to the filling return air tunnel 11.

[0034] Step 4: When mining stope 10, first slot the cutting riser 12; after slotting, advance parallel mining from the middle of stope 10 to the two side pillars 8. In the filling return airway 11 and the rock drilling roadway 6 of stope 10, respectively construct the downward fan-shaped medium-deep holes 13 and the upward fan-shaped medium-deep holes 14 to extract ore. The blasted ore 15 is extracted by a loader in the downward ore extraction cross roadway 4.

[0035] Step 5: After the segmented stope 10 is mined out, a backfilling retaining wall 16 is erected in the downward ore extraction cross passage 4 near the rock drilling roadway 6. Then, the goaf is backfilled. First, a high-ratio cemented backfill body 17 with a lime-sand ratio of 1:5 is used to fill 15m, and then a low-ratio cemented backfill body 18 with a lime-sand ratio of 1:16 is used to fill the remaining goaf.

[0036] Step 6: Following steps 2 to 5, continue mining the lower segment stope 10 in a cyclical manner until the entire stope has been mined.

[0037] The embodiments described above are merely preferred embodiments of the present invention and are not intended to limit the scope of the present invention. Various modifications and improvements made by those skilled in the art to the technical solutions of the present invention without departing from the spirit of the present invention should fall within the protection scope defined by the claims of the present invention.

Claims

1. A method of long-hole mining in a steeply dipping medium-thick ore body, characterised by Includes the following steps: 1) The stope is arranged along the strike of the ore body, and only the stope and pillars are arranged in the stope; 2) In the vertical direction, between the middle section roadway and the upper middle section roadway in the mining area, segmented roadways are constructed in the footwall of the ore body; 3) Construct several downward ore extraction cross passages from the vertical segment roadway to the footwall of the stope. After reaching the footwall of the ore body, construct a rock drilling roadway from the vertical downward ore extraction cross passage. Construct an upward filling return air connecting roadway from the vertical segment roadway to the footwall of the inter-pillar. After reaching the inter-pillar, construct an intra-vein filling return air connecting roadway within the inter-pillar to the footwall of the ore body. Construct a filling return air connecting roadway perpendicular to the intra-vein, connecting the filling return air connecting roadways of the two veins in the stope. At the middle position of the segment stope, construct a cutting riser from the rock drilling roadway upward to connect with the filling return air connecting roadway. 4) When mining the stope, first slot the cutting riser; after slotting, advance parallel mining from the middle of the stope to the two side pillars, using a fan-shaped medium-deep hole for ore extraction, and use a loader to extract the ore in the downward ore extraction cross passage after blasting. 5) After the sub-separated stope is mined out, high-ratio and low-ratio cemented backfill materials are used to fill the goaf. 6) Following steps 2) to 5) above, the lower sub-stopes are mined in a cyclical manner until the entire stope is mined out.

2. The method according to claim 1, characterized in that: In step 1), the length of the mining area is 50-60m, the width is the horizontal thickness of the ore body, and the width of the pillars is 8-10m.

3. The method according to claim 1, characterized in that: In step 2), segmented roadways are constructed in the footwall of the ore body between the middle roadway and the upper middle roadway in the mining area; the height between the middle roadways is 45-50m, and the height between the segmented roadways is 15-18m.

4. The method according to claim 1, characterized in that: In step 3), part of the filling return airway is arranged in the ore body, and the other part is arranged in the surrounding rock of the hanging wall of the ore body, and the roof of the filling return airway is 1m higher than the roof of the segmented stope.

5. The method according to claim 1, characterized in that: In step 4), the stope structure within the segment is a rhombus structure. At the middle position of the stope in the vertical direction, the maximum horizontal width of the stope is equal to the horizontal thickness of the ore body. The stope height is 22-24m. The lower half of the rhombus structure stope has a "V" shaped ore chute structure on both sides, with an inclination angle of more than 50°. Downward fan-shaped medium-deep holes and upward fan-shaped medium-deep holes are constructed in the filling return airway and drilling tunnel of the stope for ore extraction.

6. The method according to claim 1 or 2 or 3 or 4 or 5, characterized in that: The term "medium-thick fractured ore body" refers to an ore body with a horizontal thickness of 15-20m, a dip angle of more than 50°, and which requires support after exposure.