Method and device for examining, evaluating, and / or analyzing the movement of substances dissolved in soil water
The method uses ion exchange resins and substrates to maintain soil structure and hydrology, addressing the inaccuracies and costs of existing methods, enabling accurate and efficient quantification of cations and anions for CO2 certificate issuance.
Patent Information
- Application Number
- PCT/EP2026/062954
- Authority / Receiving Office
- WO · WO
- Patent Type
- Applications
- Current Assignee / Owner
- Priority Date
- 2025-05-05
- Filing Date
- 2026-05-05
- Publication Date
- 2026-11-12
AI Technical Summary
Existing methods for monitoring and quantifying basic cations released during enhanced weathering are inaccurate, complex, and costly, and require significant manual labor, often leading to non-representative measurement results due to soil disturbance and accessibility issues, especially in agricultural land.
A method involving the use of a measuring device with ion exchange resins and a substrate that maintains the local soil structure and hydrology, allowing for the quantification of cations and anions over extended periods, using a combination of semi-automatic or automatic installation and extraction techniques to minimize soil disturbance.
This approach provides accurate, cost-effective, and representative measurements of cation and anion balances, enabling the issuance of CO2 certificates by maintaining soil hydrological integrity and allowing for large-scale, efficient deployment across various soil types.
Smart Images

Figure EP2026062954_12112026_PF_FP_ABST
Abstract
Description
[0001] Method and apparatus for investigating, evaluating and / or analyzing the displacement of substances dissolved in soil water
[0002] The invention relates to a method for investigating, evaluating, and / or analyzing the migration of substances dissolved in soil water into porous media. Furthermore, the invention relates to a measuring device and an excavation device for use in a method according to the invention.
[0003] STATE OF THE ART
[0004] Enhanced weathering (EW) refers to improved, or accelerated, rock or mineral weathering and is a climate protection technology that aims to accelerate the natural weathering process of rocks in order to bind carbon dioxide (CO2) from the atmosphere. In this process, finely ground silicate rock, often basalt, is spread on open land, such as fields. The cations released from weathering bind CO2 from the air permanently in geological, terrestrial, or oceanic reservoirs, or in newly formed precipitation products, via the ion balance.
[0005] The reaction mechanisms that occur after weathering are very well understood and effective from a scientific perspective, under the general concepts of electroneutrality of solutions and calcium carbonate equilibrium, but they are very slow in nature. Faster weathering is discussed and used as a promising method for negative emissions management, particularly in the context of carbon dioxide removal (CDR) technologies.
[0006] One challenge is to accelerate and detect weathering. This requires quantifying the "basic" cations released during weathering, which play a central role in CDR reactions after weathering has occurred.
[0007] In order for a verifiable CO2 certificate to be issued, the application, monitoring, reporting and final verification by external control bodies should be solved in a cost-effective and transparent manner.
[0008] ZER-8815WO
[0009] May 5, 2026 Regarding monitoring and reporting, existing technologies already offer methods for implementation. For example, regular soil sampling is carried out using hand-held augers. These soil samples provide snapshots of available or total concentrations of basic cations relevant for CDR calculations. To determine the absolute amount of released basic cations contributing to CDR, further assumptions and / or measurements regarding soil water balance and exchange and uptake processes are necessary. Another option is regular sampling of soil pore water using suction candles.
[0010] However, established methods have drawbacks in terms of accuracy and are also very complex. For example, known methods require the regular sampling and chemical analysis of a large number of individual samples, resulting in high personnel and laboratory costs.
[0011] Furthermore, these are only snapshots of soil or solution concentrations over time. To determine the absolute amount of released basic cations contributing to CDR, further assumptions and / or measurements of soil water balance are therefore necessary.
[0012] Furthermore, due to periods of drought, sampling of soil pore water can invariably lead to measurement failures, resulting, among other things, from a capillary barrier or exceeding the air entry point and collapse of the negative pressure used for obtaining the solution.
[0013] Regarding agricultural land, it is also necessary that the devices for sampling soil pore water be accessible from above, and therefore the area being measured must be closed off to agricultural machinery. This results in different conditions in this area compared to the majority of the surrounding arable land. Consequently, measurement results obtained using known methods are usually only representative of the entire area for which a CO2 certificate is to be verified under further assumptions, or not at all.
[0014] Another disadvantage of using solid soil sampling methods is the limited or sometimes impossible accessibility of agricultural land.
[0015] ZER-8815WO
[0016] 05.05.2026Areas, which leads to temporal or spatial gaps in sampling.
[0017] German patent DE 197 26 813 C2 describes a method as a possible solution that can cumulatively determine the displacement and / or leaching of ions. This is described as Self-Integrating Accumulation (SIA) method. It involves the cumulative measurement of dissolved substances using a mixture of adapted packing material and adsorbents. A disadvantage is the lack of functional adsorbent combinations that make all relevant ions measurable for ionic volume (EW). Furthermore, the soil hydrological prerequisites for the accuracy of the measurement with the described method are very narrowly defined and only exist in a few locations, because the method described above frequently leads to funneling or exclusion effects, resulting in incorrect calculations of water and substance fluxes.Furthermore, the method requires well-trained and experienced specialists to adapt it to local conditions, and a considerable amount of time is spent on manual digging and preparation work to obtain meaningful ("accurate") results. Large-scale application with a large number of samples and geographically widely dispersed measurement areas is therefore costly and time-consuming.
[0018] Furthermore, US 2024 / 0410853 A1 describes an EW method using sensors embedded in the ground. The sensors can be evaluated remotely and are only anchored in the surface.
[0019] For further information on the state of the art, reference can be made to WO 2020 / 263910 A1, which shows a composition that can be used in the EW.
[0020] US 2020 / 0132658 A1 shows a method in which the amounts of nutrients in the soil can be monitored using sensors embedded in the ground.
[0021] The object of the invention is to provide a method and associated devices with which the potential of Enhanced Weathering can be fully exploited, improved, analyzed and independently certified.
[0022] This problem is solved by a method, a measuring device, and an excavation device according to the independent claims. Advantageous further developments of the invention are the subject of the dependent claims.
[0023] ZER-8815WO
[0024] May 5, 2026 REVELATION OF THE INVENTION
[0025] The invention relates to a method for investigating, evaluating and / or analyzing the displacement of substances dissolved in soil water into porous media,
[0026] It is proposed that the procedure include the following steps:
[0027] Providing at least one measuring device, wherein the measuring device comprises at least one ion exchange resin and one further substance; introducing, in particular at least semi-mechanically, the at least one measuring device into a porous soil, in particular of any soil structure, wherein the local soil structure and soil hydrology above the measuring device is substantially maintained, and introducing a substrate during the introduction, such that the measuring device in the installed state is partially or completely surrounded by a substrate;
[0028] Leaving at least one measuring device in the ground for a period of time t1,
[0029] - Removal, in particular at least semi-mechanical removal of at least one measuring device after the period t1,
[0030] - Evaluating the measuring device, in particular evaluating ions.
[0031] The method is particularly suitable for measuring devices with substrate-adsorber combinations specifically designed for EW (electrochemical ion exchange), as well as their placement in the soil, taking into account the local soil structure and hydrology, and recuperation using appropriate technical equipment on large open areas. Furthermore, it is ideally suited for subsequent quantification and evaluation of the relevant ions using adapted analytical methods.
[0032] Advantageously, according to the invention, the weathering of minerals, which can also be accelerated, for example, by spreading basalt, slag or similar materials onto the corresponding soils, can be measured in order to quantify CO2 binding equivalents for the sale of CO2 certificates.
[0033] The water conductivity of soils depends in particular on the soil texture, the current
[0034] ZER-8815WO
[0035] May 5, 2026. Soil moisture depends on soil structure and / or bulk density. All factors, except soil texture, change significantly with artificial mixing, such as by digging or similar processes, so that the hydraulic conductivity can change by a factor of 10 to 100, and in extreme cases by up to 1,000. Therefore, for soil science reasons, the measurement should ideally be carried out under the least disturbed soil flow conditions possible. If the structure and bulk density are disturbed too much, the deviation in the flow regime is so large that no measurement values representative of the rest of the area can be obtained.
[0036] The soil above the measuring device, i.e., the extracted soil sample, is therefore advantageously left unaltered or only minimally altered in its hydrological properties during the installation of the measuring device, in order to ensure the comparability of the measurement with the surrounding undisturbed soil. This is achieved in particular by being able to extract a soil sample in its entirety, as a monolith, so to speak, or by temporarily storing the extracted material in a sorted manner according to the extraction depth and then reinstalling it in the corresponding sequence.
[0037] To ensure not only the hydrologically correct inflow from the soil but also the hydrologically correct outflow into the measuring device during the measurement period t1, a substrate is used when installing the measuring device, which at least partially surrounds it. This allows the hydraulic properties around the measuring device to be taken into account. In particular, inflow and outflow effects are buffered directly into the measuring device, which would otherwise lead to a significant distortion of the total amount of substances transported with the soil water. Advantageously, the substrate can therefore serve as a kind of buffering substrate to correct the water balance in the vicinity of the measuring device.
[0038] Without such substrate buffering, direct lateral inflows and outflows can significantly distort the water volumes flowing through the measuring device. This also proportionally distorts the total amount of substance displaced. The substrate therefore advantageously serves as a type of drainage system. Particularly advantageously, in accordance with the invention, a universal substrate filling can be selected and used for many different soil types, which is equally suitable for each. In an advantageous embodiment, the substrate can exhibit a similar hydraulic conductivity under downward convection as the measuring device.
[0039] ZER-8815WO
[0040] May 5, 2026. The period t1 is, in particular, a time span of 1 month to 5 years. Specifically, the period t1 can be 6 to 15 months, preferably 10 to 14 months. Such a period is particularly suitable because the adsorber can be used optimally for measurements within this timeframe, and the period can be very well aligned with agricultural practice. For example, over a period of 1 year or several months, from the post-harvest of the previous crop to the post-harvest of the crop in period t1, the measuring device can be exchanged on the fields, which are then temporarily fallow, and a specific quantity of CC>2 weathering equivalents can be measured. Depending on the measured quantity of CC>2 weathering equivalents, a CC>2 certificate can then be issued, for example, to a farmer for specific agricultural areas. Other time spans are also conceivable.The time interval can, for example, be adjusted according to the measured CC>2 weathering equivalent quantity. If the measured quantity, and thus the required capacity or intake of the measuring device, is small, the period t1 can be extended, for example, while maintaining the same capacity.
[0041] The installation and / or removal can be carried out manually, semi-automatically, or fully automatically. For example, a drilling tool, pile driver, or other type of tool can be operated manually or at least semi-automatically.
[0042] In a preferred embodiment, ion balances can be measured and / or carbon dioxide binding in the soil solution can be determined via ion exchange resin measurement during the evaluation. According to the invention, adsorber combinations, in particular consisting of cation and anion exchange resins, can be provided that can measure all ions relevant to the ion balance in terms of quantity, especially with the exception of bicarbonate (HCO₃⁻), as well as the potentially toxic elements relevant in terms of quantity, e.g., relevant heavy metals and / or oxyanions. For example, specifically selected ion exchange resin combinations based on styrene-divinylbenzene with different functional end groups can be chosen as adsorbers.
[0043] In a preferred embodiment, the evaluation can measure the migration of substances dissolved in soil water from weakly acidic to basic rocks and / or rock flours that are applied to or incorporated into soils. Basic rocks and / or rock flours, in particular, have a pH value of pH > 6.
[0044] ZER-8815WO
[0045] May 5, 2026. In a preferred embodiment, the evaluation can measure the migration of substances dissolved in soil water from basic slags that are applied to or incorporated into soils. Basic slags, in particular, have a pH value of pH > 7.
[0046] In a preferred embodiment, the additional material can be a filling material that establishes soil hydrological conductivity to ensure the drainage of soil water through the measuring device. This can, for example, be a mineral substrate filling with silt or sand components, adapted to the adsorber and suitable for a wide range of soil types. Advantageously, the substrate filling therefore usually does not need to be adapted to the specific site.
[0047] In a preferred embodiment, the further material can be a quartz sand and / or quartz silt mixture, which in particular has a comparatively high hydraulic conductivity that is particularly suitable for many different soil types and soil species and re-establishes capillary contact with the soil after drying out when the soil becomes moist again.
[0048] In a preferred embodiment, the surrounding substrate can buffer funnel and exclusion effects in the water and ion flow, which can lead to a distortion of the water balance within the measuring device in relation to the environment.
[0049] In a preferred embodiment, the surrounding substrate and / or the at least one other substance in the measuring device can be matched in their soil hydrological properties in such a way that any distortion of the local water balance is particularly minimal. This allows the measurement results to be further improved.
[0050] In a preferred embodiment, the surrounding substrate and / or the at least one further substance in the measuring device can also be suitable for rewetting the at least one ion exchange resin when it has dried out.
[0051] In a preferred embodiment, a combination of ion exchange resins can be used in the measuring device to simultaneously measure, in particular, heavy and trace metals and / or sulfate.
[0052] ZER-8815WO
[0053] 05.05.2026In a preferred embodiment, a combination of ion exchange resins can be designed such that cations, anions, heavy metals and / or trace metals are quantitatively sorbed under the environmental conditions of the soil and are not desorbed again over the time of the measurement.
[0054] In a preferred embodiment, the combination of ion exchange resins, substrate and other materials can be designed such that heavy and trace metals are quantitatively sorbed under the environmental conditions of the soil and are not desorbed again over the time of the measurement.
[0055] In a preferred embodiment, the combination of ion exchange resins can be used to measure Ca 2+ , Mg 2+ , K + , NH4 + within a measuring device. In a preferred embodiment, the combination of ion exchange resins can be used to measure Ca 2+ , Mg 2+ , K + , NH4 + as well as NCh' and / or CI' being suitable within a measuring device.
[0056] In a preferred embodiment, a soil sample can be extracted during insertion and / or removal by a punching process, a turning process, a drilling process, a punch-turning process, or the like, whereby the soil structure of the porous soil is maintained, and the soil sample can be reinserted after insertion and / or removal of the measuring device. The process can be carried out manually, semi-automatically, or fully automatically. To extract an undisturbed soil structure such as a monolith or a core sample, a soil sample can be removed, for example, by punching, drilling, or a punch-turning process. For this purpose, a cylindrical element, which can also be designed in multiple parts, can be used. The cylindrical element can further include a holding device that facilitates the removal of the soil sample.The holding device can, for example, be designed as an internal cylinder, which may be configured as a clamping element. The cylinder element and / or the holding device may be made of stainless steel. A drill bit, particularly a replaceable one, may also be provided on the cylinder element to facilitate its insertion into the ground. The cylinder element can be operated manually, for example. Advantageously, it is operated mechanically, allowing the appropriate force for the punching, turning, drilling, or punch-turning process to be applied. For mechanical operation, for example, trapezoidal hydraulics on a tractor can be used, whereby the cylinder element is pressed into the ground and / or raised by the trapezoidal hydraulics.
[0057] ZER-8815WO
[0058] May 5, 2026: A shaft connected to the tractor can be rotated. For manual operation, a hammer drill can be used, for example, to which the cylinder element can be connected.
[0059] In a preferred embodiment, an installation method can be used that allows the measuring device to be installed in the lower part of the soil body, wherein, in particular, a portion of the soil body can be separated. Separating a portion of the soil body can be accomplished, for example, by a two-part cylindrical element that can be divided lengthwise along a corresponding dividing line. This allows the soil body to be divided into two cylindrical halves, one half of which can be reinserted above the measuring device after installation. It is also conceivable that a portion of the soil body is pushed out of the cylindrical element and then separated manually, for example, with a spade. Advantageously, the corresponding subsoil or topsoil can be selected to restore the original soil conditions.In particular, the upper part of the soil body, which exhibits the structure and aggregation typical for the site, can be reused undisturbed.
[0060] In a preferred embodiment, the soil sample can have a cross-sectional area that is 2 to 50 times larger than the cross-sectional area of the measuring device. For example, the cross-sectional area of the soil sample, which is defined in particular by its diameter, can be 10 times larger than the cross-sectional area of the measuring device. Advantageously, the soil sample is therefore, on average, significantly larger than the actual measuring area in which the measuring device is located. This avoids interference from the excavation edges, which could potentially disrupt the flow. In other words, it ensures that the flow characteristics above the measuring device are not affected by the removal of the soil sample, i.e., by the resulting interface.
[0061] In a preferred embodiment, a support element can be provided to secure the upper edge of the base around the base body during installation and / or removal. The support element can be designed as a type of cylinder with a collar. The collar preferably extends around the cylinder so that no material from the surrounding soil can slip into the installed opening. The collar can
[0062] ZER-8815WO
[0063] For example, a flange element could be formed on May 5, 2026. A funnel-shaped design is also conceivable. The support element could be made of plastic, for example. A steel version is also possible.
[0064] In a preferred embodiment, the substrate can be distributed over the entire cross-sectional area or a region essential for measurement within the volume freed up by the excavation of the soil body. In a preferred embodiment, the substrate can, for example, be arranged with a layer thickness of 0.3 cm to 10 cm next to, below, and / or above the measuring device. This advantageously prevents a so-called funnel effect, which describes undesirable additional water inflows from the sides, in the measurement area. The inflow can pass through the substrate on the outside of the enclosure, advantageously decoupling the "central cylinder" of the measurement from lateral inflows.
[0065] In a preferred embodiment, a precision GPS sensor can be used to locate the measuring device at its original position. This can be achieved by combining a precision GPS, such as an RTK GPS or similar, with at least one magnet. If the magnet is positioned centrally beneath the measuring device, the inaccuracy of GPS positioning can be particularly advantageously corrected, allowing the measuring device to be located precisely at the same position and subsequently replaced with pinpoint accuracy.
[0066] In a preferred embodiment, at least one magnetic element can therefore be embedded in the ground during installation, enabling the measuring device to be located at its installed position using a magnetic field sensor. To locate measuring devices installed in very large cultivated areas, such as arable land or grassland, or in areas with poor visibility, such as forests, and especially to locate them correctly in the same location without unnecessarily disrupting prior work, a highly precise method is required.
[0067] In a preferred embodiment, the magnetic element is therefore installed centrally beneath the measuring device. The magnetic element can be installed together with the measuring device, and in particular, can be integrated into the measuring device.
[0068] In a preferred embodiment, the evaluation can be carried out by desorption of target ions from the ion exchangers used with at least one extraction solution in at least one extraction step and / or with at least one repetition using the
[0069] ZER-8815WO
[0070] May 5, 2026. The analysis can therefore be carried out by desorption of the ions from the specific ion exchangers with one or more extraction solutions in one or more extraction steps and / or repetitions with the same extraction solvent.
[0071] The selection of extraction solvents is preferably carried out experimentally, determining the recovery rates and errors based on the target ions (analytes) and the adsorbents used. Depending on the desired analytical accuracy and precision, such as the limit of detection, limit of quantification, calibration range, reproducibility, and / or relative measurement error, two to four extraction solvents may be required for the entire spectrum of substances of interest, in one to five extraction steps. These solvents may include salt solutions with different pH values, buffer solutions, and reducing or oxidizing agents. From the measured concentrations in the extract, the area of ion discharge per measurement point can be inferred, particularly via the mass of the instrument's charge and / or its cross-sectional area. Furthermore, the area of ion discharge can be determined from the statistics of the measurement repetitions.in mol / ha or kg / ha using a statistical measure of dispersion, typically the standard error of the mean.
[0072] In a preferred embodiment, the extraction solution can be composed of a neutral salt and a pH buffer during evaluation.
[0073] In a preferred embodiment, the extraction solution can be formed from a neutral salt and a pH buffer during evaluation, and therefore, in particular, Ca2+, Mg2+, K+, NH4+ as well as NO3- and / or CI- can be quantitatively desorbed simultaneously.
[0074] In a preferred embodiment, the extraction solution can be formed from a neutral salt and a pH buffer during evaluation, and therefore, in particular, trace metals and sulfate can be quantitatively desorbed simultaneously.
[0075] In a preferred embodiment, the extraction solutions can be measured by or on ICP-MS (inductively coupled plasma mass spectrometry) or ICP-OES (inductively coupled plasma optical emission spectrometry) during evaluation.
[0076] In a preferred embodiment, the extraction solutions can be measured on the ion chromatograph during evaluation.
[0077] ZER-8815WO
[0078] 05.05.2026 In a preferred embodiment, the extraction solutions can be measured on a colorimetric or spectroscopic flow analyzer during evaluation.
[0079] In a preferred embodiment, the evaluation can calculate the areal discharge of the target ions from the displacement of substances dissolved in the soil water and calculate CO2 equivalents from this. For example, an online analytical database can be combined with a specific soil water evaluation program. Advantageously, the CO2 equivalents can be calculated largely automatically and, for example, forwarded to the certifying organization along with measurement data.
[0080] According to the invention, a method can therefore be provided that is reproducible and cost-effective and, when the corresponding process steps are carried out, can lead to the determination of the ions from the EW for obtaining CDR certificates.
[0081] In a preferred embodiment, the target ions can represent > 99% of the anion loading absorbed by the measurement method during the measurement period.
[0082] In a preferred embodiment, the target ions can represent > 99% of the cation loading absorbed by the measurement method during the measurement period.
[0083] In a preferred embodiment, the target ions can represent > 99% of the anion loading absorbed during the measurement period, in particular excluding HCO3 and CO3. 2 '.
[0084] In a preferred embodiment, when evaluating the nearly complete cation and anion balances, HCOa' and COs can be obtained. 2 ' will be calculated.
[0085] The invention further relates to a measuring device for use in a method according to the invention. The measuring device is characterized in that it has a housing, preferably box-shaped or cylindrical, and thus comprises at least an ion exchange resin and a further substance. The measuring device can therefore be arranged, for example, in a rectangular, cylindrical, or square housing, which in particular allows flow from the top towards the bottom.
[0086] ZER-8815WO
[0087] May 5, 2026. Advantageously, the measuring device can cover both the required spectrum of ions, preferably including pollutants, and a wide range of soil locations. The ion exchange resin can adsorb the ions required for the CDR calculations. The filling material can create the appropriate soil hydrological conductivity needed to ensure the drainage of soil water through the measuring device, for example, by allowing the adsorbers to collect the target substances.
[0088] In a preferred embodiment of the measuring device, a hook or loop element can be provided on its upper side, which is designed to be foldable. In a first position, it serves to pull out the measuring device, and in a second position, it does not impede the flow through the measuring device. This provides a type of removal hook that, when installed, can be folded away from the measuring device, for example, to the side. This allows the measuring device to be grasped and pulled out mechanically or manually, for example, when it needs to be removed and / or evaluated.
[0089] The invention further relates to an excavation device for use in a method according to the invention. The excavation device is characterized in that it comprises at least one cylindrical element designed for excavating an undisturbed soil element, wherein the cylindrical element is designed, in particular at least partially by machine, to be driven, pushed, drilled or struck into the ground and / or pulled or rotatable from the ground.
[0090] In a preferred embodiment of the excavation device, the cylindrical element can be designed to excavate a soil sample from 5 cm to 100 cm deep, particularly 30 cm deep. Preferably, soil material is excavated to a depth of 30 cm. The soil sample can thus, for example, be designed as a core sample 30 cm long. The measuring device can therefore be installed in the ground at a depth of 30 cm, for example. Other, particularly greater, installation depths are also conceivable.
[0091] In a preferred embodiment of the excavation device, the cylindrical element for excavating a soil mass can be designed with a diameter of 20 cm to 100 cm, particularly 30 cm. In particular, the diameter of the soil mass is several times larger, at least by a factor of 2 to 5, than the diameter of the measuring device, so that the flow behavior is not affected by the joint created during excavation.
[0092] ZER-8815WO
[0093] May 5, 2026. In a preferred embodiment of the excavation device, a holding device can be provided inside the cylinder element, preferably designed as an inner sleeve or clamping element. The holding device is designed to receive the soil body after the cylinder element has been inserted into the ground and is furthermore slidably relative to the cylinder element or detachable from the cylinder element. The soil body can be held in the holding device when it is to be removed from the surrounding ground. Therefore, the soil body can be stored separately from the outer excavation device and thus preferably remain largely undisturbed. The clamping element can be designed as a type of spring element comprising spring steel or sheet metal and having a slot.In particular, the clamping element can expand after being removed from the cylinder element, allowing the base to be removed with less resistance and thus more easily. The holding device can be removed from the cylinder element, while the base can be held in the holding element during removal.
[0094] In a preferred embodiment of the excavation device, the holding device on the cylinder element can be secured against being pulled upwards out of the cylinder element when the excavation device is inserted into the ground, particularly when the excavation device is inserted with a ramming head. The holding device can be secured from above by an attachment on the cylinder element, preferably designed as a type of stop or groove, to prevent it from being pushed upwards during insertion into the ground. The stop can be designed to be releasable, so that the holding device can subsequently be removed from the cylinder element.
[0095] In a preferred embodiment of the excavation device, the holding device on the cylinder element can be secured against downward pull-out during the excavation process, particularly by a support. The holding device can be secured against becoming stuck in the ground during excavation by a drill bit, a type of stop, and / or a groove arranged on the cylinder element. The holding device can be supported against the stop, the groove, or the drill bit. The drill bit, the stop, and / or the groove can be detachably arranged on the cylinder element, allowing the holding device to be subsequently removed from the cylinder element.
[0096] ZER-8815WO
[0097] 05.05.2026In a preferred embodiment, the excavation device can be designed in at least two parts and / or have a hinge element, wherein, when removed, the excavation device can be separated into at least two parts and / or folded by the hinge element.
[0098] In a preferred embodiment, the cylindrical element can, for example, be formed in two parts, with the two elements being designed as half-shells. This allows the cylindrical element to be opened halfway along its length. At least one hinge element can be arranged on the cylindrical element to rotate the halves relative to each other and open the cylindrical element.
[0099] In a preferred embodiment, the excavation device can be connected to an interchangeable drill bit. This allows, for example, the use of drill bits with different diameters.
[0100] Furthermore, the holding device, particularly as a relievable internal structure, can be designed as an inner cylinder that fits snugly against the steel cylinder and is not completely closed. The holding device can support the base during removal and, when removed from the cylinder element, can also be easily relieved of its load. This allows the removal of the base to require significantly less force and / or energy and can be done manually.
[0101] On disturbed soils, such as those that are regularly plowed, a standard, productive earth auger with a diameter of approximately 25 cm can be used. The plow depth can be selected as the installation level, ensuring that the measuring device is not affected or damaged by plowing. The plow can restore typical soil conditions as it turns over the entire field, covering the measuring point with surrounding material.
[0102] The method and devices therefore also allow for the replacement of measuring devices, and a final extraction is also possible, which may also take place under disturbed soil conditions for simplification purposes.
[0103] The method and devices according to the invention are suitable not only for installing at least one measuring device, but also for changing the measuring device at the same location, while maintaining the essential hydrological properties.
[0104] ZER-8815WO
[0105] 05.05.2026In particular, a large number of measuring devices can be installed and removed at any location using the method and devices according to the invention.
[0106] The same techniques and principles as described can therefore also be used for replacing measuring devices in the field, particularly with adapted dimensions. When replacing devices of the same type, consideration can be given to the fact that, during the replacement, the undisturbed soil layer rests on the measuring setup and can therefore be removed separately to remain as undisturbed as possible.
[0107] DRAWINGS
[0108] Further advantages become apparent from the accompanying drawings and drawing descriptions. The drawings illustrate exemplary embodiments of the invention. The drawing, the description, and the claims contain numerous features in combination. A person skilled in the art will expediently consider the features individually and combine them into meaningful further combinations.
[0109] It shows:
[0110] Fig. 1 shows a schematic representation of a method according to the invention in one possible embodiment;
[0111] Fig. 2 shows a schematic representation of a method according to the invention in one possible embodiment;
[0112] Fig. 3 shows a schematic representation of a method according to the invention in one possible embodiment;
[0113] Fig. 4 shows a schematic representation of a method according to the invention in one possible embodiment;
[0114] Fig. 5 shows a schematic representation of a method according to the invention in one possible embodiment;
[0115] Fig. 6 shows a schematic representation of a method according to the invention in one possible embodiment;
[0116] ZER-8815WO
[0117] 05.05.2026 Fig. 7 a schematic representation of a method according to the invention in one possible embodiment;
[0118] Fig. 8 shows a schematic representation of a method according to the invention in one possible embodiment;
[0119] Fig. 9 shows a schematic representation of a method according to the invention in one possible embodiment;
[0120] Fig. 10 shows a schematic representation of a method according to the invention in one possible embodiment;
[0121] Fig. 11 shows a schematic representation of a method according to the invention in one possible embodiment;
[0122] Fig. 12 shows a schematic representation of a method according to the invention in one possible embodiment;
[0123] Fig. 13 shows a schematic representation of a method according to the invention in one possible embodiment;
[0124] Fig. 14 shows a schematic representation of a method according to the invention in one possible embodiment;
[0125] Fig. 15 shows a schematic representation of an excavation device according to the invention in one possible embodiment;
[0126] Fig. 16 Components of an excavation device according to the invention;
[0127] Fig. 17 shows a schematic representation of an excavation device according to the invention in one possible embodiment;
[0128] Fig. 18 shows a schematic representation of an excavation device according to the invention in one possible embodiment.
[0129] In the figures, identical or similar components are numbered with the same reference symbols.
[0130] ZER-8815WO
[0131] 05.05.2026Figures 1 to 14 show different embodiments of the method 10 according to the invention. Possibilities are shown for burying at least one measuring device 12 in the ground.
[0132] Fig. 1 shows a possible embodiment of method 10, in which a base body 14 is removed from the base 22 using a punching or rotary tool with a cylindrical element 42. After the measuring device 12 is inserted, the base body 14 can be reinserted into the base 22 or the resulting opening. Since the measuring device 12 requires a certain amount of space, the base body 14 can be cut along a dividing line 32, so that not the entire base body 14 is reinserted, as shown in Fig. 2. The partial section 16 can therefore be detached. It is thus possible for the cylindrical element 42 to be designed in at least two parts, so that the cylindrical element 42 can be horizontally divided into the at least two elements shown in the illustration in order to also cut the base body 14 along the dividing line 32.The cutting of the soil material along the separation line 32 can be carried out mechanically or manually, for example with a spade or the like. The cylindrical element 42 is preferably designed as a steel cylinder, in particular made of stainless steel. This can, for example, form a punching tool or a rotary tool, in particular a rotary punch or the like.
[0133] Using method 10, the soil sample 14 can be extracted from any grassland, arable land, or the like. To prevent further soil material from sliding down into the created opening, a support element 18 can be provided to support the upper edge of the opening and prevent further soil material from sliding down. The support element 18 is, for example, designed as a cylinder with a flange element or collar. The collar is formed around the entire circumference of the cylinder, so that the upper edge of the opening can be reinforced all around. The support element 18 can, for example, be made of plastic or a plastic material. It is also conceivable that it could be made of steel or a steel material.
[0134] The measuring device 12 is preferably embedded in a substrate 24. Alternatively, the substrate 24 can also be provided only below the measuring device 12. It is also possible that at least one magnetic element 26 is buried in the area of the measuring device 12. Preferably, a magnetic element 26 is arranged below, and in particular centrally below, the measuring device 12. This makes it possible for the
[0135] ZER-8815WO
[0136] 05.05.2026 Measuring device 12 can be located again with pinpoint accuracy.
[0137] Alternatively, soil material can be extracted using a drilling tool 36, as shown in Figures 3 and 4. In contrast to the embodiment using a punching tool, a processed soil material 34 is introduced above the measuring device 12. The soil material 34 corresponds to the soil material that was extracted from the soil 22, but mixed by the drilling tool 36. In one possible embodiment, a soil sample 14 is extracted first, which has a larger diameter than the diameter of the borehole, see Figure 4. The soil sample 14 can be extracted with a cylindrical element 42 as previously explained, but preferably has a shallower extraction depth. In other words, the length of the cylindrical element 42 is preferably shorter than described in the embodiment according to Figures 1 and 2.
[0138] Another embodiment is shown in Figure 5, in which the entire soil core 14 is removed using a rotating punching tool. This is particularly advantageous if the soil around the soil core 22 is not too loose or stony. With such a method, the final installation depth of the measuring device 12 can be achieved by punching out an intact soil core only once. A cylindrical element 42 can also be used in this process.
[0139] Fig. 6 shows, in comparison to Fig. 5, the punching depth achieved in combination with a drilling tool 36. Comparing Figures 5 and 6, it can be seen that the depth of the drill core in Fig. 5 is less than in Fig. 6. The drill core extracted according to Fig. 6 can be processed using a method as shown in Fig. 4.
[0140] It is also conceivable to carry out the drilling using a drilling machine, either manually or mechanically, as shown in Fig. 7. The drilling machine, i.e., the drilling tool 36, can be used to create a hole up to the installation depth of the measuring device 12. The material can be conveyed to the surface, for example, by means of a screw conveyor and deposited around the bore, as shown in Fig. 7. Preferably, the material removed by the conveying device is sorted and deposited, with the topsoil and bottomsoil being stored separately. This allows the soil layers to be reinstalled in the same order as when removed, in accordance with the surrounding soil 22.
[0141] ZER-8815WO
[0142] May 5, 2026. For comparison, Figure 8 shows the possibility of punching out the topsoil and bottomsoil from the soil 22 in one piece. The resulting soil body 14 can remain in the cylinder element 42 while the measuring device 12 is inserted into the opening. Preferably, a partial section 16 is separated along the dividing line 32, which can be aligned at the appropriate height. Cutting along the dividing line 32 can be achieved, for example, by partially pushing the soil body 14 out of the cylinder element 42 and separating it with a spade. Furthermore, it is possible for the cylinder element 42 to be made in multiple sections, which can be separated into two parts along the dividing line 32.
[0143] Fig. 9 shows two ways of installing the measuring device 12 in the base 22. Variant A shows the possibility using a punching tool or rotary punching tool according to Fig. 8. Variant B shows a possibility using a drilling tool 36 according to Fig. 7. A direct comparison shows that different diameters can be achieved. In particular, a smaller diameter can be achieved with a drilling tool 36 than is possible with a punching tool.
[0144] Figure 10 shows the representation in an exploded view.
[0145] Figures 11 and 12 show how to remove the measuring device 12 from the ground 22. This is done in two steps. Step 1 is shown in Fig. 11. In this step, a soil sample is excavated above the measuring device 12. This sample can be unprocessed soil 14 or processed soil 34, depending on the method used to install the measuring device 12. The soil sample 14, 34 is excavated only to the required depth, so that the measuring device 12 remains in the ground. A support element 18 can also be used during the removal of the measuring device 12 to prevent soil material from shifting. After removing the soil sample 14, 34, the measuring device 12 is removed in a second step, as shown in Fig. 12. The measuring device 12 can be removed manually or mechanically.For example, the measuring device 12 can be dug out using a spade.
[0146] The measuring device 12 can have a housing 28, preferably box-shaped or cylindrical. It is also conceivable that a gripping device 38 is provided on the measuring device 12, which may, for example, have a loop, a hook element 30, or the like. The gripping device 38 can be contacted by means of a gripping tool 38' and the measuring device 12 can be pulled out of the base 22.
[0147] ZER-8815WO
[0148] May 5, 2026. Gripping device 38 can have different configurations. As shown in Fig. 12(b), it can contact the measuring device 12 from the inside. It is also conceivable that the measuring device 12 is contacted from the outside via the gripping device 38, as shown in Fig. 12(c). In this way, a kind of hinged hook can be designed that can be folded to the side and therefore does not affect the flow through the measuring device 12.
[0149] The gripping device 38 includes, for example, at least one spring element, so that the gripping device 38 can be held against the measuring device 12 by spring tension. Alternatively, mechanical fastening options are also conceivable. The gripping device 38 offers the advantage that the measuring device 12 can be easily and safely removed from the borehole or punched hole.
[0150] It is also conceivable that when removing the measuring device 12 using the punching tool, the measuring device 12 is removed directly along with the sample, as shown in Figures 13 and 14. In this case, a complete core sample is extracted from the soil, containing the soil body 14 or 34, the measuring device 12, and, in particular, the substrate 24. In such an embodiment, it is advantageous if the substrate 24 surrounding the measuring device 12 is moistened beforehand to prevent substrate 24 from falling out of the underside of the cylindrical element 42. This can be achieved, for example, by moistening the material inside the cylindrical element 42.
[0151] Fig. 15 shows a possible embodiment of an excavation device 40, which comprises at least one cylindrical element 42. The excavation device 40 can be used for ramming or rotary ramming, as described in the previous embodiments. The excavation device 40 can comprise the cylindrical element 42 as an outer sleeve and a holding device 46. The holding device 46 is, in particular, designed as a type of core catcher sleeve, inner sleeve, or inner tube, and can, for example, be made of sheet metal. As shown in Fig. 16, the inner sleeve can be designed as a clamping element 48, which is implemented, in particular, by a slotted, cylindrical sleeve. The holding device 46, designed as a clamping element 48 or inner tube, can, in particular, have a wall thickness of 1 mm to 2 mm, and can have a slot of 2 cm to 4 cm, in particular 3 cm. The slot serves to relieve stress and bend open without deformation of the clamping element 48.Inner tube.
[0152] To prevent the retaining device 46 from slipping out of the cylinder element 42, the retaining device 46 can be held on the underside of the cylinder element 42.
[0153] ZER-8815WO
[0154] May 5, 2026. For this purpose, a support 52 can be provided, as shown in Fig. 17(a). The support 52 can further be designed as a kind of groove or have a groove for engaging the retaining device 46. The retaining device 46 can be supported against the support 52 in such a way that it cannot escape downwards from the cylinder element 42 when the excavation device 40 is pulled out of the ground 22. In such an embodiment, the cylinder element 42 is preferably designed with at least one hinge element 44, as shown in Fig. 16(a) and Fig. 17(a). The cylinder element 42 can be opened via the hinge element 44. For this purpose, the cylinder element 42 is formed in at least two parts, in particular with two half-shell-shaped partial elements.
[0155] To prevent the retaining device 46 from slipping out of the cylinder element 42, it can alternatively be supported downwards by a drill bit 50, as shown in Fig. 17(b). For this purpose, for example, a projection is provided on the head of the drill bit 50 against which the retaining device 46 can be supported downwards. In such an embodiment, the cylinder element 42 can also be formed without hinge elements, and thus, in particular, as a single piece. The drill bit 50 can, for example, be screwed to the cylinder element 42 and therefore be removable.
[0156] Fig. 18 shows an embodiment in which the cylinder element 42 is designed without a hinge element. The cylinder element 42 can, for example, be formed as a closed stainless steel tube. The holding device 46 can be supported, for example, by means of the overhang on the drill bit 50. After removing the drill bit 50, the holding device 46 can be pushed out of the cylinder element 42, for example, with a ramming element 54 whose diameter is adapted to the holding device 46. This makes it easier to remove the soil body 14 from the cylinder element 42.
[0157] The embodiments of the excavation device 40 can, for example, be used to carry out the method 10 as described in Figures 1 to 14. The holding device 46, which is designed as a type of spring element with a slot, makes it particularly advantageous to remove the soil body 14 from the excavation device 40 as a whole and then to reinsert it into the ground 22 as an undisturbed soil body 14.
[0158] ZER-8815WO
[0159] 05.05.2026 Reference number list
[0160] 10 procedures
[0161] 12 Measuring device
[0162] 14 soil bodies
[0163] 16 Sub-area of the soil body
[0164] 18 support elements
[0165] 20 Top edge of the soil around the soil body 22 Soil around the soil body
[0166] 24 substrate
[0167] 26 magnetic element
[0168] 28 cases
[0169] 30 hook elements
[0170] 32 Dividing line
[0171] 34 Processed soil material
[0172] 36 Drilling tools
[0173] 38 Gripping device
[0174] 40 Excavation device
[0175] 42 Cylinder element
[0176] 44 hinge element
[0177] 46 Holding device
[0178] 48 clip elements
[0179] 50 drill bits
[0180] 52 supports
[0181] 54 Pile driving tools
[0182] ZER-8815WO
[0183] May 5, 2026
Claims
Patent claims 1. Method (10) for investigating, evaluating and / or analyzing the translocation of substances dissolved in soil water into porous media, characterized by the following steps: Providing at least one measuring device (12), wherein the measuring device (12) comprises at least one ion exchange resin and one further substance, introducing, in particular at least semi-mechanically, the at least one measuring device into a porous soil, in particular of any soil structure, wherein the local soil structure and soil hydrology above the measuring device (12) is substantially maintained, and during introduction a substrate (24) is introduced such that the measuring device (12) is partially or completely surrounded by a substrate (24) in the installed state, leaving the at least one measuring device (12) in the soil for a period t1 , - Removal, in particular at least semi-mechanical removal, which includes at least one measuring device (12) after the period t1, - Evaluating the measuring device (12), in particular evaluating ions.
2. Method according to claim 1, characterized in that ion balances are measured and / or carbon dioxide binding in the soil solution is determined via the ion exchange resin during the evaluation.
3. Method according to claim 1 or 2, characterized in that the evaluation measures the displacement of substances dissolved in soil water from weakly acidic to basic rocks and / or rock flours applied to or incorporated into soils, or that the evaluation measures the displacement of substances dissolved in soil water from basic slags applied to or incorporated into soils. ZER-8815WO 05.05.20264. Method according to one of the preceding claims, characterized in that the further substance is a filling material which establishes a soil hydrological conductivity in order to ensure drainage of soil water through the measuring device (12).
5. Method according to one of the preceding claims, characterized in that a combination of ion exchange resins is used in the measuring device to measure, in particular, heavy and trace metals and / or sulfate.
6. Method according to one of the preceding claims, characterized in that during insertion and / or removal a soil body (14) is removed by a punching method, a turning method, a drilling method, a punch-turning method or the like, wherein the soil structure of the porous soil is maintained, and wherein the soil body (14) is reinserted after insertion and / or removal of the measuring device (12).
7. Method according to claim 6, characterized in that an installation method is used during insertion which enables the installation of the measuring device (12) in the lower part of the base body (14), wherein in particular a partial area (16) of the base body (14) is separable.
8. Method according to one of claims 6 or 7, characterized in that the base body (14) has a cross-sectional area which is 2 times to 50 times larger than a cross-sectional area of the measuring device (12).
9. Method according to one of claims 7 or 8, characterized in that a support element (18) is provided for securing an upper edge (20) of the floor (22) around the floor body during insertion and / or removal. ZER-8815WO 05.05.202610. Method according to claim 9, characterized in that the substrate (24) is distributed over the entire cross-sectional area or an area essential for measurement of the area freed up by the excavation of the soil body (14).
11. Method according to one of the preceding claims, characterized in that, when installed with a precision GPS sensor, it is possible to locate the measuring device (12) at the installed position.
12. Method according to one of the preceding claims, characterized in that at least one magnetic element (26) is inserted into the ground during installation, so that the measuring device (12) can be located again at the installed position by means of a magnetic field sensor.
13. Method according to claim 12, characterized in that the magnetic element (26) is installed centrally under the measuring device (12).
14. Method according to one of the preceding claims, characterized in that during evaluation, desorption of target ions from the ion exchangers used is carried out with at least one extraction solution in at least one extraction step and / or with at least one repetition using the same extraction agent.
15. Method according to claim 14, characterized in that, during the evaluation, an area-wide discharge of the target ions from the displacement of the substances dissolved in the soil water is calculated and CO2 equivalents are calculated therefrom.
16. Measuring device (12) for use in a method according to one of the preceding claims, characterized in that the measuring device (12) has a housing (28), preferably box-shaped or cylindrical, and thus comprises at least an ion exchange resin and a further substance. ZER-8815WO 05.05.202617. Measuring device (12) according to claim 16, characterized in that a hook element (30) or loop element is provided on an upper side, which is designed to be foldable, so that in a first position it serves to pull out the measuring device (12) and in a second position does not affect the flow through the measuring device (12).
18. Excavation device (40) for use in a method according to one of claims 1 to 15, characterized in that at least one cylindrical element (42) is included which is designed for excavating an undisturbed soil body (14), wherein the cylindrical element (42) is designed, in particular at least partially by machine, to be driven, pushed, drilled or struck into the ground and / or to be pulled out of the ground or rotatable.
19. Excavation device (40) according to claim 18, characterized in that the cylinder element (42) is designed for excavating a soil body of 10 cm to 100 cm depth, in particular 30 cm depth.
20. Excavation device (40) according to claim 18 or 19, characterized in that a holding device (46, 48) is provided inside the cylinder element (42), which is preferably designed as an inner sleeve (46) or clamping element (48), wherein the holding device (46) is designed to receive the soil body (14) after the cylinder element (42) has been inserted into the soil (22), and is furthermore designed to be displaceable relative to the cylinder element (42) or detachable from the cylinder element (42).
21. Excavation device (40) according to claim 20, characterized in that the holding device (46) on the cylinder element (42) is secured against being pulled upwards out of the cylinder element (42) when the excavation device (40) is inserted into the ground (22), in particular when the excavation device (40) is inserted with a ramming tool head (54), and / or against being pulled downwards out of the cylinder element (42) when the excavation device (40) is pulled out of the ground (22), in particular by a support (52). ZER-8815WO 05.05.202622. Excavation device (40) according to one of claims 18 to 21, characterized in that the excavation device (40) is designed in at least two parts and / or has a hinge element (44), wherein, when removed, the excavation device (40) can be separated into at least two parts and / or folded by means of the hinge element (44), and / or that the excavation device (40) can be connected to an interchangeable drill bit (50). ZER-8815WO May 5, 2026