A kind of pipe gallery diaphragm fast linkage construction trolley and pipe gallery diaphragm construction method
By designing a fast-linked construction trolley for the pipe gallery's transverse partitions, combined with the hydraulic system and adjustable formwork of the steel bar binding and concrete molding trolley, the problems of low construction efficiency and difficult organization of the traditional pipe gallery have been solved, and rapid linked construction has been achieved. , improving construction efficiency and quality.
Patent Information
- Application Number
- CN202010408399.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-05-14
- Publication Date
- 2025-01-24
- Estimated Expiration
- 2040-05-14
AI Technical Summary
The construction of traditional pipeline corridors has problems such as large material investment, low construction efficiency, and low concrete pouring operation. Especially under the closed pipeline corridor structure, the construction organization is difficult and the construction cycle is long.
A kind of tube gallery is designed to quickly link the construction platform vehicle, including steel bars tie tie vehicles and concrete mold building cars. Both are equipped with hydraulic systems and adjustable template structures. The rapid linkage of tied and concrete pouring.
The construction trolley and method can reduce the difficulty of construction organization, save material and manpower investment, speed up the construction turnover speed, shorten the construction period, and improve construction quality and safety.
Smart Images

Figure CN111365035B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a pipe gallery diaphragm quick linkage construction trolley and a pipe gallery diaphragm construction method, belonging to the technical field of construction engineering. Background Art
[0002] As a modern transportation mode, expressways play a very important role in the development of today's society. With the rapid development of expressways, the structural design concept has changed, and pipeline separation has become the mainstream concept of expressway tunnel and bridge culvert design. Expressway tunnels with two holes and one corridor and multiple corridor structures are becoming more and more common. Traditional corridor construction uses bracket + wooden formwork or small steel formwork, which requires a large amount of materials; the internal space of the corridor is narrow, the process is cross-cutting, the on-site construction organization is difficult, and the construction efficiency is low; the concrete pouring of the corridor adopts the traditional pumping method, which has low operability, and concrete pouring is another problem. A single corridor concrete pouring trolley is used for construction. The trolley is used as both a steel bar binding operation platform and a concrete pouring platform. The construction period is long, the concrete curing time occupies the total construction period, the trolley runs slowly, and the construction efficiency is low. Summary of the invention
[0003] The technical problem to be solved by the present invention is: to overcome the disadvantages of the above-mentioned technology and to provide a fast and linked pipeline corridor diaphragm construction trolley and a pipeline corridor diaphragm construction method.
[0004] In order to solve the above technical problems, the first technical solution proposed by the present invention is: a fast-linked construction trolley for the transverse partition of a pipe gallery, comprising: a steel bar binding trolley and a concrete molding trolley whose head end is connected to the rear end of the steel bar binding trolley; the steel bar binding trolley and the concrete molding trolley both include a gantry assembly and a drive system; the steel bar binding trolley also includes a binding platform, a wing plate formwork and a first hydraulic system; the concrete molding trolley also includes an I-shaped plate formwork assembly and a second hydraulic system; the gantry assembly includes a gantry, a column, a truss and an operating platform; the gantry is a main force-bearing structure for bearing loads; the column is a main supporting structure; the truss is used to connect the gantry, and the operating platform includes a worker passage and a standing platform; the drive system includes a walking wheel box arranged at the bottom of the column and a hydraulic motor driving the walking wheel box; the walking wheel box can travel along the guide rail arranged at the bottom of the pipe gallery;
[0005] The first hydraulic system includes a first transverse oil cylinder, a first vertical fine-tuning oil cylinder and a rotating oil cylinder; the binding platform is located on the top of the steel bar binding trolley and can be pushed by the first vertical fine-tuning oil cylinder to move in the vertical direction relative to the steel bar binding trolley; the binding platform can be pushed by the first transverse oil cylinder to move horizontally perpendicular to the steel bar binding trolley relative to the steel bar binding trolley; both sides of the binding platform are provided with flippable movable plates; the rotating oil cylinder can push the movable plates to flip; the wing plate template is supported by the door frame of the steel bar binding trolley;
[0006] The second hydraulic system includes a second transverse oil cylinder, a second vertical fine-tuning oil cylinder, a transverse oil cylinder and a rotating oil cylinder; the I-shaped plate template assembly is located on the top of the concrete molding trolley and can be pushed by the second vertical fine-tuning oil cylinder to move in the vertical direction relative to the concrete molding trolley; the I-shaped plate template assembly can be pushed by the second transverse oil cylinder to move in the transverse direction perpendicular to the concrete molding trolley relative to the concrete molding trolley; the I-shaped plate template assembly includes an upper cross-plate, a web template and a bottom template; the outer side of the upper cross template is provided with a telescopic adjustment plate; the transverse oil cylinder can push the telescopic adjustment plate to adjust the size of the upper cross template, and the rotating oil cylinder can push the web template to rotate;
[0007] The front end of the steel bar binding trolley is provided with a concrete hanger; the hanger is provided with a motor, which can lift the concrete trolley onto the steel bar binding trolley; the steel bar binding trolley and the top surface of the concrete molding trolley are connected with a track; the concrete trolley can move on the track.
[0008] A further improvement of the above scheme is that the columns are telescopic and are provided with lifting cylinders which can change the heights of the steel bar binding trolley and the concrete molding trolley.
[0009] A further improvement of the above scheme is that the wing plate template forms a four-bar linkage with the door frame through two connecting rods, and is supported on the door frame through an oblique screw rod.
[0010] A further improvement of the above solution is that: the operating platform also includes a ladder.
[0011] A further improvement of the above solution is that the hydraulic motor, the first hydraulic system and the second hydraulic system can be controlled by a remote control handle.
[0012] In order to solve the above technical problems, the second technical solution proposed by the present invention is: a pipeline corridor diaphragm construction method using the pipeline corridor diaphragm rapid linkage construction trolley as described above, comprising the following steps:
[0013] (1) The steel bar tying trolley enters the first workstation, ties the steel bars on both sides of the wing plate of the first workstation corridor diaphragm, and then carries out concrete pouring operations;
[0014] (2) During the curing of the concrete of the wing plates on both sides of the first-station corridor diaphragm, the steel bar tying trolley continues to carry out the steel bar tying operation of the I-shaped plate of the first-station corridor diaphragm;
[0015] (3) After the first station has completed the steel bar binding of the I-shaped plate of the corridor diaphragm, the stress points are arranged on the corridor, the steel bar skeleton of the I-shaped plate is lifted by the lifting rope, and the binding trolley moves forward to the next station to start binding the steel bars of the wing plates on both sides of the corridor diaphragm of the next station; at the same time, the concrete casting trolley is synchronously followed by the first station and put into place; the steel bar skeleton of the I-shaped plate is placed on the concrete casting trolley;
[0016] (4) The concrete casting trolley performs the concrete pouring operation of the I-shaped slab of the corridor diaphragm at the first station. During the concrete curing period, the steel bar tying trolley performs the concrete pouring operation of the wing slabs on both sides of the corridor diaphragm at the next station, and then performs the steel bar tying operation of the I-shaped slab of the corridor diaphragm at the next station;
[0017] (5) After the reinforcement binding work of the I-shaped plate of the corridor diaphragm is completed at the next workstation, the stress points are arranged on the corridor, and the reinforcement skeleton of the I-shaped plate is lifted up using a lifting rope. The reinforcement binding trolley moves forward to the next workstation to bind the reinforcement of the wing plates on both sides of the corridor diaphragm; at the same time, the concrete casting trolley is synchronously followed and put into place at the next workstation;
[0018] (6) The concrete casting trolley performs the concrete pouring operation of the I-shaped slab of the pipe gallery diaphragm at the next station. During the concrete curing period, the steel bar tying trolley performs the concrete pouring operation of the wing slabs on both sides of the pipe gallery diaphragm at the next station, and then performs the steel bar tying operation of the I-shaped slab of the pipe gallery diaphragm at the next station;
[0019] (7) Repeat steps (5) and (6) in sequence until the construction is completed.
[0020] Compared with the prior art, the pipeline gallery diaphragm rapid linkage construction trolley and pipeline gallery diaphragm construction method provided by the present invention can solve the construction difficulties of closed pipeline gallery diaphragms, reduce the difficulty of construction organization, save materials and manpower investment, speed up construction turnover, shorten the construction period, and improve construction quality and construction safety. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] The present invention will be further described below in conjunction with the accompanying drawings.
[0022] Figure 1 It is a schematic structural diagram of a preferred embodiment of the present invention.
[0023] Figure 2 yes Figure 1Schematic diagram of the steel bar tying trolley structure.
[0024] Figure 3 yes Figure 2 Schematic diagram of the AA structure.
[0025] Figure 4 yes Figure 2 Schematic diagram of the BB structure.
[0026] Figure 5 yes Figure 2 Schematic diagram of the CC structure.
[0027] Figure 6 yes Figure 2 Schematic diagram of the DD structure.
[0028] Figure 7 yes Figure 1 Schematic diagram of the steel bar tying trolley structure.
[0029] Figure 8 yes Figure 7 Schematic diagram of the AA structure.
[0030] Fig. 9 yes Figure 7 Schematic diagram of the BB structure.
[0031] Fig.10 yes Figure 7 Schematic diagram of the CC structure. DETAILED DESCRIPTION Example
[0032] The pipeline gallery diaphragm fast linkage construction trolley of this embodiment is as follows Figure 1 , including: a steel bar tying trolley 1 and a concrete molding trolley 2 whose head end is connected to the tail end of the steel bar tying trolley 1.
[0033] like Figures 2 to 6 The steel bar binding trolley 1 includes a gantry assembly and a drive system; it also includes a binding platform 5, a wing plate template 6 and a first hydraulic system; the gantry assembly includes a gantry 7, a column 4, a truss and an operating platform; the gantry 7 is the main force-bearing structure for bearing loads; the column 4 is the main supporting structure; the truss is used to connect the gantry 7. The operating platform 8 includes an operator channel, a standing platform and a ladder; the drive system includes a walking wheel box 9 arranged at the bottom of the column 4 and a hydraulic motor 10 driving the walking wheel box 9; the walking wheel box 9 can travel along the guide rail 11 arranged at the bottom of the pipe gallery. The column 4 can be telescopic, and the column 4 is provided with a lifting cylinder 4, which can change the height of the steel bar binding trolley 1. The wing plate template 6 forms a four-bar linkage with the gantry 7 through two connecting rods, and is supported on the gantry 7 by an oblique screw rod; in this way, when demoulding, the screw rod is removed, and through the characteristics of the four-bar linkage, it can be demoulded in the horizontal and vertical directions at the same time, which is easier.
[0034] The first hydraulic system includes a first transverse movement cylinder 12, a first vertical fine-tuning cylinder 13 and a rotating cylinder 14; the binding platform is located on the top of the steel bar binding trolley and can be pushed by the first vertical fine-tuning cylinder 13 to move in the vertical direction relative to the steel bar binding trolley 1; the binding platform can be pushed by the first transverse movement cylinder 12 to move horizontally perpendicular to the steel bar binding trolley 1 relative to the steel bar binding trolley 1; both sides of the binding platform are provided with flippable movable plates 15; the rotating cylinder 14 can push the movable plates 15 to flip; the wing plate formwork 6 is supported by the gantry 7 of the steel bar binding trolley.
[0035] like Figures 7 to 10 The main structure of the concrete mold trolley 2 is the same as that of the steel bar binding trolley, both of which are gantry assemblies and drive systems; no further description is given. The concrete mold trolley 2 also includes an I-shaped plate template assembly 20 and a second hydraulic system;
[0036] The second hydraulic system includes a second transverse shift cylinder 21, a second vertical fine-tuning cylinder 22, a transverse cylinder 23 and a rotating cylinder; the I-beam formwork assembly is located on the top of the concrete molding trolley 1 and can be pushed by the second vertical fine-tuning cylinder 22 to move in the vertical direction relative to the concrete molding trolley; the I-beam formwork assembly can be pushed by the second transverse shift cylinder 21 to move horizontally perpendicular to the concrete molding trolley relative to the concrete molding trolley; the I-beam formwork assembly includes an upper cross board, a web formwork and a bottom formwork; the outer side of the upper cross formwork is provided with a telescopic adjustment plate 26; the transverse cylinder 23 can push the telescopic adjustment plate 26 to adjust the size of the upper cross formwork, and the rotating cylinder can push the web formwork to rotate; in this embodiment, in order to simplify the structure and save costs, one end of the transverse cylinder 23 is detachably installed, so that the function of the rotating cylinder can be realized by installing the detachable end on the mounting hole 25 of the web formwork.
[0037] The front end of the steel bar tying trolley 1 is provided with a concrete hanger 16; the hanger 16 is provided with a motor 18, which can lift the concrete cart 17 onto the steel bar tying trolley 1, and the top surfaces of the steel bar tying trolley 1 and the concrete molding trolley 2 are provided with a connecting track 19; the concrete cart 17 can move on the track 19.
[0038] The hydraulic motor, the first hydraulic system and the second hydraulic system can be controlled by a remote control handle.
[0039] The pipe gallery diaphragm construction method using the pipe gallery diaphragm quick linkage construction trolley as described above comprises the following steps:
[0040] (1) The steel bar tying trolley enters the first workstation, ties the steel bars of the wing plates on both sides of the first workstation's pipe gallery diaphragm, and then performs concrete pouring operations; the jacking cylinder, the first transverse cylinder, and the first vertical fine-tuning cylinder adjust the position and elevation of the tying platform for precise positioning; and during the wing plate pouring operation, the movable plate 15 is pushed to flip by the rotating cylinder 14, thereby making room on both sides so that the concrete truck can pour from top to bottom;
[0041] (2) During the curing of the concrete of the wing plates on both sides of the first-station corridor diaphragm, the steel bar tying trolley continues to carry out the steel bar tying operation of the I-shaped plate of the first-station corridor diaphragm;
[0042] (3) After the first station of the corridor diaphragm I-shaped plate reinforcement is tied, the technicians arrange the stress points on the corridor according to the simulated stress structure, use the lifting rope to lift the reinforcement frame of the I-shaped plate, and move the tying trolley forward to the next station to start tying the wing plate reinforcement on both sides of the corridor diaphragm; at the same time, the concrete casting trolley synchronously follows the first station and takes position; the reinforcement frame of the I-shaped plate is placed on the concrete casting trolley;
[0043] (4) Similarly, the concrete molding trolley can adjust the position and elevation through the jacking cylinder, the second lateral movement cylinder 21, and the second vertical fine-tuning cylinder 22 for precise positioning;
[0044] Since there will inevitably be errors in the pouring of the side walls of the pipe gallery, a telescopic adjustment plate 26 is designed on the outer side of the upper horizontal formwork in contact with the side wall, and is pushed by the horizontal oil cylinder 23 for adjustment to adapt to the error. In actual construction, since one end of the horizontal oil cylinder 23 is a movable and detachable structure, this end can be connected to the telescopic adjustment plate 26 to adjust according to the on-site environment;
[0045] Since the web template is vertical, it is very stable during layout. Therefore, after one end of the transverse oil cylinder 23 is connected to the web template, the web template can be tilted to the position, rotated to a vertical state, and then reinforced by a screw.
[0046] The concrete casting trolley performs the concrete pouring operation of the I-shaped slab of the corridor diaphragm at the first station. During the concrete curing period, the steel bar tying trolley performs the concrete pouring operation of the wing slabs on both sides of the corridor diaphragm at the next station, and then performs the steel bar tying operation of the I-shaped slab of the corridor diaphragm at the next station.
[0047] (5) After the reinforcement binding work of the I-shaped plate of the corridor diaphragm is completed at the next workstation, the stress points are arranged on the corridor, and the reinforcement skeleton of the I-shaped plate is lifted up using a lifting rope. The reinforcement binding trolley moves forward to the next workstation to bind the reinforcement of the wing plates on both sides of the corridor diaphragm; at the same time, the concrete casting trolley is synchronously followed and put into place at the next workstation;
[0048] (6) The concrete casting trolley performs the concrete pouring operation of the I-shaped slab of the pipe gallery diaphragm at the next station. During the concrete curing period, the steel bar tying trolley performs the concrete pouring operation of the wing slabs on both sides of the pipe gallery diaphragm at the next station, and then performs the steel bar tying operation of the I-shaped slab of the pipe gallery diaphragm at the next station;
[0049] (7) Repeat steps (5) and (6) in sequence until the construction is completed.
[0050] The present invention is not limited to the specific technical solutions described in the above embodiments. In addition to the above embodiments, the present invention may also have other implementations. All technical solutions formed by equivalent replacement are within the protection scope required by the present invention.
Claims
1. A fast linkage construction trolley for pipe gallery diaphragms, characterized in that: include: A steel bar binding trolley and a concrete molding trolley whose head end is connected to the rear end of the steel bar binding trolley; the steel bar binding trolley and the concrete molding trolley both include a gantry assembly and a drive system; the steel bar binding trolley also includes a binding platform, a wing plate formwork and a first hydraulic system; the concrete molding trolley also includes an I-shaped plate formwork assembly and a second hydraulic system; the gantry assembly includes a gantry, a column, a truss and an operating platform; the gantry is the main force-bearing structure for bearing loads; the column is the main supporting structure; the truss is used to connect the gantry, and the operating platform includes an operator passage and a standing platform; the drive system includes a walking wheel box arranged at the bottom of the column and a hydraulic motor driving the walking wheel box; the walking wheel box can travel along the guide rails arranged at the bottom of the pipe gallery; The first hydraulic system includes a first transverse oil cylinder, a first vertical fine-tuning oil cylinder and a rotating oil cylinder; the binding platform is located on the top of the steel bar binding trolley and can be pushed by the first vertical fine-tuning oil cylinder to move in the vertical direction relative to the steel bar binding trolley; the binding platform can be pushed by the first transverse oil cylinder to move horizontally perpendicular to the steel bar binding trolley relative to the steel bar binding trolley; both sides of the binding platform are provided with flippable movable plates; the rotating oil cylinder can push the movable plates to flip; the wing plate template is supported by the door frame of the steel bar binding trolley; The second hydraulic system includes a second transverse oil cylinder, a second vertical fine-tuning oil cylinder, a transverse oil cylinder and a rotating oil cylinder; the I-shaped plate template assembly is located on the top of the concrete molding trolley and can be pushed by the second vertical fine-tuning oil cylinder to move in the vertical direction relative to the concrete molding trolley; the I-shaped plate template assembly can be pushed by the second transverse oil cylinder to move in the transverse direction perpendicular to the concrete molding trolley relative to the concrete molding trolley; the I-shaped plate template assembly includes an upper transverse template, a web template and a bottom template; the outer side of the upper transverse template is provided with a telescopic adjustment plate; the transverse oil cylinder can push the telescopic adjustment plate to adjust the size of the upper transverse template, and the rotating oil cylinder can push the web template to rotate; The front end of the steel bar binding trolley is provided with a concrete hanger; the hanger is provided with a motor, which can lift the concrete trolley onto the steel bar binding trolley; the steel bar binding trolley and the top surface of the concrete molding trolley are connected with a track; the concrete trolley can move on the track.
2. The pipe gallery diaphragm rapid linkage construction trolley according to claim 1 is characterized in that: The column is telescopic and is provided with a lifting cylinder, which can change the height of the steel bar binding trolley and the concrete molding trolley.
3. The pipe gallery diaphragm rapid linkage construction trolley according to claim 1 is characterized in that: The wing plate template forms a four-bar linkage with the portal frame through two connecting rods, and is supported on the portal frame through an oblique screw rod.
4. The pipe gallery diaphragm rapid linkage construction trolley according to claim 1 is characterized in that: The operating platform also includes a ladder.
5. The pipe gallery diaphragm rapid linkage construction trolley according to claim 1 is characterized in that: The hydraulic motor, the first hydraulic system and the second hydraulic system can be controlled by a remote control handle.
6. A method for constructing a pipe gallery diaphragm using the pipe gallery diaphragm rapid linkage construction trolley as claimed in claim 1, characterized in that: The steps include: (1) The steel bar tying trolley enters the first workstation, ties the steel bars on both sides of the wing plate of the first workstation corridor diaphragm, and then carries out concrete pouring operations; (2) During the curing of the concrete of the wing plates on both sides of the first-station corridor diaphragm, the steel bar tying trolley continues to carry out the steel bar tying operation of the I-shaped plate of the first-station corridor diaphragm; (3) After the first station has completed the steel bar binding of the I-shaped plate of the corridor diaphragm, the stress points are arranged on the corridor, the steel bar skeleton of the I-shaped plate is lifted by the lifting rope, and the binding trolley moves forward to the next station to start binding the steel bars of the wing plates on both sides of the corridor diaphragm of the next station; at the same time, the concrete casting trolley is synchronously followed by the first station and put into place; the steel bar skeleton of the I-shaped plate is placed on the concrete casting trolley; (4) The concrete casting trolley performs the concrete pouring operation of the I-shaped slab of the corridor diaphragm at the first station. During the concrete curing period, the steel bar tying trolley performs the concrete pouring operation of the wing slabs on both sides of the corridor diaphragm at the next station, and then performs the steel bar tying operation of the I-shaped slab of the corridor diaphragm at the next station; (5) After the reinforcement binding work of the I-shaped plate of the corridor diaphragm is completed at the next workstation, the reinforcement skeleton of the I-shaped plate of the corridor diaphragm is lifted up with steel pipes, and the reinforcement binding trolley moves forward to the next workstation to bind the reinforcement of the wing plates on both sides of the corridor diaphragm; at the same time, the concrete casting trolley is synchronously followed and put into place at the next workstation; (6) The concrete casting trolley performs the concrete pouring operation of the I-shaped slab of the pipe gallery diaphragm at the next station. During the concrete curing period, the steel bar tying trolley performs the concrete pouring operation of the wing slabs on both sides of the pipe gallery diaphragm at the next station, and then performs the steel bar tying operation of the I-shaped slab of the pipe gallery diaphragm at the next station; (7) Repeat steps (5) and (6) in sequence until the construction is completed.