A method and system for processing massive gas filling data at a gas filling station

By processing the historical data of the filling station and calculating the gas rate offset, the problems of insufficient gas volume of the filling station and difficulty in time being discovered by pipeline blockage/damage are solved, and timely judgment of the state of the filling station and the gas efficiency are achieved. Improvement.

CN118627755BActive Publication Date: 2025-01-03SHENZHEN MIAOJIA MOBILE CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411080977.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-08
Publication Date
2025-01-03
Estimated Expiration
2044-08-08

AI Technical Summary

Technical Problem

The gas station staff were unable to detect insufficient gas or blockage/damage of the pipeline in time, resulting in slowing inflation speed, increasing waiting time and potential safety hazards.

Method used

By extracting, preprocessing, searching and curve drawing of the historical data of the gas station, gas filling rate information is obtained, proximity analysis is carried out to calculate the gas filling rate offset, and the state of the gas filling station is judged based on the threshold value to determine the gas gas quantity and pipeline condition.

Benefits of technology

It has achieved timely detection of insufficient gas volume and abnormal pipelines in the filling station, ensuring filling efficiency and safety, reducing waiting time, and ensuring normal gas filling of subsequent users.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118627755B_ABST
    Figure CN118627755B_ABST
Patent Text Reader

Abstract

The present invention discloses a method and system for processing massive gas filling data at a gas filling station, which relates to the field of data processing technology, including extracting and processing the database of the gas filling station to obtain the historical data of the gas filling station; preprocessing the data based on the historical data of the gas filling station to obtain several groups of gas filling order information. The present invention introduces a gas filling rate offset, judges the gas filling rate offset with a first threshold, and outputs a first abnormal point. There are two abnormal points, one is that the rate slows down, and the other is that the rate is too large. The slow rate is related to the insufficient gas volume at the gas filling station and the blockage of the gas filling pipeline; if the gas volume is sufficient, but the gas rate increases, it means that the pipeline of the gas filling station is damaged. Therefore, the present invention introduces a second threshold and a third threshold, performs comparative analysis, and judges the state of the gas filling station, which is convenient for the staff to refuel or repair it, and ensures that the subsequent users refuel normally.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of data processing, and in particular to a method and system for processing massive gas filling data at a gas filling station. Background Art

[0002] A gas station usually refers to a filling station for liquefied petroleum gas (LPG) or natural gas, which is used to provide fuel for vehicles or equipment that use these energy sources.

[0003] During the refueling process at existing gas stations, staff cannot promptly detect that the gas volume in the station is insufficient, resulting in users being unable to complete refueling. The inflation speed may be significantly slowed down, which will increase waiting time and affect service efficiency, especially during peak hours. Staff are also unable to promptly detect whether the pipeline is blocked or damaged, which may pose a safety hazard in serious cases and make it difficult to meet the needs of staff. Summary of the invention

[0004] In order to solve the above technical problems, a technical solution is provided to solve the problem that the staff cannot timely find out whether the gas volume in the gas station is insufficient and whether the pipeline is blocked or damaged.

[0005] In order to achieve the above purpose, the technical solution adopted by the present invention is:

[0006] A method for processing massive gas filling data at a gas filling station, comprising:

[0007] Extract and process the database of the gas station to obtain the historical data of the gas station;

[0008] Preprocess the data based on the historical data of the gas station to obtain several groups of gas order information;

[0009] Search the database based on several groups of gas filling order information to obtain the gas filling rate information corresponding to the order;

[0010] Draw a curve based on the gas filling rate information corresponding to the order, and obtain several groups of order gas filling rate curves;

[0011] Perform data screening according to several groups of gas filling order information to obtain several groups of user gas filling times, wherein the several groups of user gas filling times correspond one to one with several groups of order gas filling rate curves;

[0012] Conduct a convergence analysis on the order gas filling rate curves in adjacent time periods to obtain the gas filling rate offset;

[0013] Extract and process the database of gas filling stations to obtain the average gas filling rate of the gas filling stations;

[0014] A judgment process is performed based on the gas filling rate offset to determine the status of the gas filling station.

[0015] Preferably, the data preprocessing based on the historical data of the gas station to obtain several groups of gas filling order information specifically includes the following steps:

[0016] Perform outlier deletion processing on historical data to obtain first processed data;

[0017] Perform missing value filling processing on the first processed data to obtain second processed data;

[0018] The specific calculation formula for the missing value filling process is: ;

[0019] In the formula, is the filling data; i is the number of filling data; are different types of historical data; n is the number of different types of historical data;

[0020] Classification is performed based on the second processed data to obtain several groups of gas filling order information.

[0021] Preferably, searching the database based on several groups of gas filling order information to obtain the gas filling rate information corresponding to the order specifically includes the following steps:

[0022] Searching the database based on several groups of gas filling order information to obtain gas filling volume information and gas filling completion time information;

[0023] Calculate based on the gas filling volume information and the gas filling completion time information to obtain the gas filling rate information;

[0024] The specific calculation formula for obtaining the gas filling rate is: ;

[0025] In the formula, is the gas filling rate, T is the gas filling completion time, and S is the gas filling volume.

[0026] Preferably, the step of drawing a curve based on the gas filling rate information corresponding to the order to obtain a plurality of groups of order gas filling rate curves specifically comprises the following steps:

[0027] A rectangular coordinate system is established with the filling completion time information as the X-axis and the filling volume information as the Y-axis;

[0028] Based on the gas filling rate information corresponding to the several groups of orders, curves are drawn in a rectangular coordinate system to obtain the gas filling rate curves of the several groups of orders.

[0029] Preferably, the step of performing a proximity analysis on the order gas filling rate curves of adjacent time periods to obtain the gas filling rate offset specifically comprises the following steps:

[0030] Performing time analysis on the gas filling rate curve based on the gas filling order information to determine the gas filling rate curve information for adjacent time periods;

[0031] The gas filling rate offset is obtained by performing calculation based on the gas filling rate curve information of adjacent time periods.

[0032] Preferably, the calculation and processing based on the gas filling rate curve information of adjacent time periods to obtain the gas filling rate offset specifically includes the following steps:

[0033] Extract time features from the gas filling rate curves in adjacent time periods to determine the completion time of two groups of gas filling;

[0034] Calculate and process the two groups of gas filling completion time to obtain the minimum gas filling completion time;

[0035] The specific calculation formula for the minimum gas filling completion time is: ;

[0036] in, The gas filling completion time for two groups respectively;

[0037] The minimum gas filling completion time is set as the reference time, and the curve of another group of gas filling completion time is removed by the reference time to obtain the gas filling rate curve;

[0038] A comparison process is performed based on the processed gas filling rate curve and the gas filling rate curve corresponding to the reference time to obtain the gas filling rate offset.

[0039] Preferably, the determination of the state of the gas filling station based on the gas filling rate offset comprises the following steps:

[0040] Making a judgment based on the gas filling rate offset and a set first threshold;

[0041] If the gas filling rate offset is greater than the set first threshold, the first gas filling rate abnormal point is output;

[0042] If the gas filling rate offset is equal to the set first threshold, the output gas filling is normal;

[0043] If the gas filling rate offset is less than the set first threshold, a second judgment is made on the gas filling rate offset;

[0044] Analyze the first abnormal point of gas filling rate to determine the status of the gas filling station.

[0045] Preferably, the secondary determination of the gas filling rate offset specifically comprises the following steps:

[0046] Making a judgment based on the gas filling rate offset and a set second threshold;

[0047] If the gas filling rate offset is less than the set second threshold, the second gas filling rate abnormal point is output;

[0048] If the gas filling rate offset is greater than or equal to the set second threshold, the output gas filling is normal;

[0049] Obtaining time data corresponding to the second gas filling rate abnormal point;

[0050] Performing data extraction processing on the database based on the time data corresponding to the abnormal point of the second gas filling rate, and determining the second gas storage volume of the gas filling station;

[0051] Making a judgment based on a second gas storage volume of the gas filling station and a set third threshold;

[0052] If the second gas storage volume of the gas filling station is less than or equal to the set third threshold, the output gas filling station has insufficient gas storage and cannot reach the average gas filling rate, and the gas filling station is in normal state;

[0053] If the gas storage volume of the gas filling station is greater than the set third threshold, the output gas filling station pipeline is abnormal.

[0054] Preferably, the analyzing the abnormal point of the first gas filling rate to determine the state of the gas filling station specifically comprises the following steps:

[0055] Performing data extraction processing on the database based on the time data corresponding to the first gas filling rate abnormal point to determine the first gas storage volume of the gas filling station;

[0056] Making a judgment based on a first gas storage volume of the gas filling station and a set fourth threshold;

[0057] If the first gas storage volume of the gas filling station is less than or equal to the set fourth threshold value, the output gas filling station has insufficient gas storage and cannot reach the average gas filling rate, and the gas filling station is in a normal state;

[0058] If the first gas storage volume of the gas filling station is greater than the set fourth threshold, the pipeline of the gas filling station is abnormal.

[0059] A system for processing massive gas filling data at a gas filling station, comprising:

[0060] An extraction module, which is used to extract the database of the gas filling station, obtain the historical data of the gas filling station and obtain the average gas filling rate of the gas filling station;

[0061] A data preprocessing module, which is used to preprocess the historical data of the gas station and obtain several groups of gas filling order information;

[0062] A search module, the search module is used to search a database for several groups of gas filling order information to obtain gas filling rate information corresponding to the order;

[0063] A curve drawing module, the curve drawing module is used to draw a curve for the gas filling rate information corresponding to the order, and obtain a plurality of groups of order gas filling rate curves;

[0064] A data screening module, which is used to screen the gas filling order information and obtain the gas filling time of several groups of users;

[0065] A proximity analysis module, which is used to perform a proximity analysis on the order gas filling rate curves in adjacent time periods to obtain a gas filling rate offset;

[0066] The judgment module is used to judge the gas filling rate offset and determine the state of the gas filling station.

[0067] Compared with the prior art, the present invention provides a method and system for processing massive gas filling data at a gas filling station, which has the following beneficial effects:

[0068] The present invention first obtains the gas filling orders of all users on the same day, extracts the gas filling rates of all users by means of data retrieval, and then obtains the gas filling time of the users by means of data screening, draws a curve for the gas filling rate of all users, and the gas filling time of each user is in a one-to-one correspondence with the gas filling rate curve of the respective order; then the gas filling rate curves of the orders in adjacent time periods are subjected to a proximity analysis, and the proximity refers to the overlap relationship, and the adjacent time period refers to the comparison of the gas filling rates of two adjacent users before and after the gas filling process on the same day, because only when the gas filling of two adjacent users before and after one day is taken, the data is targeted, if The data is not logical if the number of days between them is large. After comparison, the gas filling station may have been refueled, and the gas filling rate offset is obtained. The gas filling rate offset is judged with the first threshold, and the first abnormal point is output. There are two types of abnormal points, one is that the rate slows down, and the other is that the rate is too large. The slow rate is related to the insufficient gas volume at the gas filling station and the blockage of the gas pipeline. If the gas volume is sufficient and the gas rate increases, it means that the gas station pipeline is damaged. Therefore, the present invention introduces the second threshold and the third threshold for comparison and analysis to determine the status of the gas filling station, which is convenient for the staff to refuel or repair it, and ensure that subsequent users refuel normally. BRIEF DESCRIPTION OF THE DRAWINGS

[0069] Figure 1 It is a schematic flow chart of the gasification data processing method in the present invention;

[0070] Figure 2A schematic flow chart of a method for preprocessing data based on historical data of a gas filling station to obtain several groups of gas filling order information in the present invention;

[0071] Figure 3 A schematic flow chart of a method for determining the state of a gas filling station by judging and processing the gas filling rate offset in the present invention;

[0072] Figure 4 It is a schematic flow chart of the method for secondary determination of the gas filling rate offset in the present invention;

[0073] Figure 5 The figure is a flow chart of a method for analyzing the abnormal point of the first gas filling rate and determining the state of the gas filling station in the present invention. DETAILED DESCRIPTION

[0074] The following description is used to disclose the present invention so that those skilled in the art can implement the present invention. The preferred embodiments described below are only examples, and those skilled in the art may think of other obvious variations.

[0075] Please refer to Figure 1-Figure 5 As shown, a method for processing massive gas filling data at a gas filling station includes:

[0076] Extract and process the database of the gas station to obtain the historical data of the gas station;

[0077] Preprocess the data based on the historical data of the gas station to obtain several groups of gas order information;

[0078] Search the database based on several groups of gas filling order information to obtain the gas filling rate information corresponding to the order;

[0079] Draw a curve based on the gas filling rate information corresponding to the order, and obtain several groups of order gas filling rate curves;

[0080] Data is screened based on several groups of gas filling order information to obtain several groups of user gas filling times, and the several groups of user gas filling times correspond to several groups of order gas filling rate curves one by one;

[0081] Conduct a convergence analysis on the order gas filling rate curves in adjacent time periods to obtain the gas filling rate offset;

[0082] Extract and process the database of gas filling stations to obtain the average gas filling rate of the gas filling stations;

[0083] A judgment process is performed based on the gas filling rate offset to determine the status of the gas filling station.

[0084] It can be understood by those skilled in the art that the gas filling orders of all users on the same day are first obtained, and the gas filling rates of all users are extracted by means of data retrieval. Then, the gas filling time of the users is obtained by means of data screening, and a gas filling rate curve is drawn for all users. The gas filling time of each user is in a one-to-one correspondence with the gas filling rate curve of their respective orders. Then, a proximity analysis is performed on the gas filling rate curves of the orders in adjacent time periods. The proximity refers to the overlap relationship. The adjacent time periods refer to the comparison of the gas filling rates of two adjacent users before and after the gas filling process on the same day. Because only when the gas filling of two adjacent users before and after one day is taken, the data is targeted. If the number of days between the two users is large, the gas station may have been gassed, and the data will not be logical. After the comparison, the gas filling rate offset is obtained, and the gas filling rate offset is judged to obtain the status of the gas station.

[0085] Preprocessing the data based on the historical data of the gas station to obtain several groups of gas order information specifically includes the following steps:

[0086] Perform outlier deletion processing on historical data to obtain first processed data;

[0087] Perform missing value filling processing on the first processed data to obtain second processed data;

[0088] The specific calculation formula for filling missing values ​​is: ;

[0089] In the formula, is the filling data; i is the number of filling data; are different types of historical data; n is the number of different types of historical data;

[0090] Classification is performed based on the second processed data to obtain several groups of gas filling order information.

[0091] Searching the database based on several groups of gas filling order information to obtain the gas filling rate information corresponding to the order specifically includes the following steps:

[0092] Searching the database based on several groups of gas filling order information to obtain gas filling volume information and gas filling completion time information;

[0093] Calculate based on the gas filling volume information and the gas filling completion time information to obtain the gas filling rate information;

[0094] Among them, the specific calculation formula for obtaining the gas filling rate is: ,

[0095] In the formula, is the gas filling rate, T is the gas filling completion time, and S is the gas filling volume.

[0096] Drawing a curve based on the gas filling rate information corresponding to the order, and obtaining a number of groups of order gas filling rate curves specifically include the following steps:

[0097] A rectangular coordinate system is established with the filling completion time information as the X-axis and the filling volume information as the Y-axis;

[0098] Based on the gas filling rate information corresponding to the several groups of orders, curves are drawn in a rectangular coordinate system to obtain the gas filling rate curves of the several groups of orders.

[0099] The steps of performing a proximity analysis on the order gas filling rate curves in adjacent time periods and obtaining the gas filling rate offset are as follows:

[0100] Performing time analysis on the gas filling rate curve based on the gas filling order information to determine the gas filling rate curve information for adjacent time periods;

[0101] The gas filling rate offset is obtained by performing calculation based on the gas filling rate curve information of adjacent time periods.

[0102] The calculation and processing based on the gas filling rate curve information of adjacent time periods to obtain the gas filling rate offset specifically includes the following steps:

[0103] Extract time features from the gas filling rate curves in adjacent time periods to determine the completion time of two groups of gas filling;

[0104] Calculate and process the two groups of gas filling completion time to obtain the minimum gas filling completion time;

[0105] Among them, the specific calculation formula for the minimum gas filling completion time is: ;

[0106] in, The gas filling completion time for two groups respectively;

[0107] The minimum gas filling completion time is set as the reference time, and the curve of another group of gas filling completion time is removed by the reference time to obtain the gas filling rate curve;

[0108] A comparison process is performed based on the processed gas filling rate curve and the gas filling rate curve corresponding to the reference time to obtain the gas filling rate offset.

[0109] It can be understood by those skilled in the art that, because the order information is different, the filling time and volume are also different, and therefore it is necessary to use the shortest time as a reference to eliminate the long-time curve, so that the short-time curve and the long-time curve are judged within the same time to obtain the filling rate offset between the two; and if an order data is too long and is eliminated, the eliminated data pattern is the same as the non-eliminated data pattern.

[0110] The judgment process based on the gas filling rate offset is used to determine the state of the gas filling station, which specifically includes the following steps:

[0111] Making a judgment based on the gas filling rate offset and a set first threshold;

[0112] If the gas filling rate offset is greater than the set first threshold, the first gas filling rate abnormal point is output;

[0113] If the gas filling rate offset is equal to the set first threshold, the output gas filling is normal;

[0114] If the gas filling rate offset is less than the set first threshold, a second judgment is made on the gas filling rate offset;

[0115] Analyze the first abnormal point of gas filling rate to determine the status of the gas filling station.

[0116] The secondary judgment of the gas filling rate offset specifically includes the following steps:

[0117] Making a judgment based on the gas filling rate offset and a set second threshold;

[0118] If the gas filling rate offset is less than the set second threshold, the second gas filling rate abnormal point is output;

[0119] If the gas filling rate offset is greater than or equal to the set second threshold, the output gas filling is normal;

[0120] Obtaining time data corresponding to the second gas filling rate abnormal point;

[0121] Performing data extraction processing on the database based on the time data corresponding to the abnormal point of the second gas filling rate, and determining the second gas storage volume of the gas filling station;

[0122] Making a judgment based on a second gas storage volume of the gas filling station and a set third threshold;

[0123] If the second gas storage volume of the gas filling station is less than or equal to the set third threshold, the output gas filling station has insufficient gas storage and cannot reach the average gas filling rate, and the gas filling station is in normal state;

[0124] If the gas storage volume of the gas filling station is greater than the set third threshold, the output gas filling station pipeline is abnormal.

[0125] Analyzing the first abnormal point of the gas filling rate and determining the state of the gas filling station specifically includes the following steps:

[0126] Performing data extraction processing on the database based on the time data corresponding to the first gas filling rate abnormal point to determine the first gas storage volume of the gas filling station;

[0127] Making a judgment based on a first gas storage volume of the gas filling station and a set fourth threshold;

[0128] If the first gas storage volume of the gas filling station is less than or equal to the set fourth threshold value, the output gas filling station has insufficient gas storage and cannot reach the average gas filling rate, and the gas filling station is in a normal state;

[0129] If the first gas storage volume of the gas filling station is greater than the set fourth threshold, the pipeline of the gas filling station is abnormal.

[0130] It can be understood by those skilled in the art that when the gas filling rate offset is greater than the set first threshold, there are two abnormal situations, one is that the rate slows down, and the other is that the rate is too large. The slow rate is related to insufficient gas at the gas station and blockage in the gas pipeline. If the gas volume is sufficient and the gas rate increases, it means that the gas station pipeline is damaged. Therefore, the present invention introduces the second threshold and the third threshold for comparative analysis to determine the status of the gas station, which is convenient for the staff to refuel or repair it and ensure that subsequent users can refuel normally.

[0131] A system for processing massive gas filling data at a gas filling station, comprising:

[0132] An extraction module is used to extract the database of the gas filling station, obtain the historical data of the gas filling station and obtain the average gas filling rate of the gas filling station;

[0133] The data preprocessing module is used to preprocess the historical data of the gas station and obtain several groups of gas filling order information;

[0134] A search module is used to search a database for several groups of gas filling order information to obtain gas filling rate information corresponding to the order;

[0135] A curve drawing module is used to draw a curve for the gas filling rate information corresponding to the order, and obtain several groups of order gas filling rate curves;

[0136] The data screening module is used to screen the gas filling order information and obtain the gas filling time of several groups of users;

[0137] The proximity analysis module is used to perform proximity analysis on the order gas filling rate curves in adjacent time periods to obtain the gas filling rate offset;

[0138] The judgment module is used to judge the gas filling rate offset and determine the state of the gas filling station.

[0139] To summarize, first obtain the gas filling orders of all users on the same day, extract the gas filling rates of all users through data retrieval, and then obtain the gas filling time of the users through data screening, draw a curve for the gas filling rate of all users, and the gas filling time of each user is in a one-to-one correspondence with the gas filling rate curve of their respective orders; then perform a proximity analysis on the gas filling rate curves of orders in adjacent time periods, and the proximity refers to the overlap relationship. Adjacent time periods refer to the comparison of the gas filling rates of two adjacent users before and after the gas filling process on the same day. Because only when the gas filling of two adjacent users on the same day is taken before and after, the data is targeted. If the number of days between the data is large, the gas station may have been refueled, and the data will not be logical. After comparison, the gas filling rate offset is obtained, and the gas filling rate offset is judged with the first threshold value to output the first abnormal point. There are two types of abnormal points, one is that the rate slows down, and the other is that the rate is too large. The slow rate is related to the insufficient gas volume at the gas station and the blockage of the gas pipeline; if the gas volume is sufficient and the gas rate increases, it means that the gas station pipeline is damaged. Therefore, the present invention introduces the second threshold and the third threshold value, and compares and analyzes them to determine the status of the gas station, which is convenient for the staff to refuel or repair it, and ensure that subsequent users refuel normally.

[0140] The above shows and describes the basic principles, main features and advantages of the present invention. Those skilled in the art should understand that the present invention is not limited to the above embodiments. The above embodiments and descriptions only describe the principles of the present invention. The present invention may be subject to various changes and improvements without departing from the spirit and scope of the present invention. These changes and improvements fall within the scope of the present invention. The scope of protection claimed by the present invention is defined by the attached claims and their equivalents.

Claims

1. A method for processing massive gas filling data at a gas filling station, characterized in that: include: Extract and process the database of the gas station to obtain the historical data of the gas station; Preprocess the data based on the historical data of the gas station to obtain several groups of gas order information; Search the database based on several groups of gas filling order information to obtain the gas filling rate information corresponding to the order; Draw a curve based on the gas filling rate information corresponding to the order, and obtain several groups of order gas filling rate curves; Perform data screening according to several groups of gas filling order information to obtain several groups of user gas filling times, wherein the several groups of user gas filling times correspond one to one with several groups of order gas filling rate curves; Conduct a convergence analysis on the order gas filling rate curves in adjacent time periods to obtain the gas filling rate offset; Extract and process the database of gas filling stations to obtain the average gas filling rate of the gas filling stations; Perform judgment processing based on the gas filling rate offset to determine the state of the gas filling station; The step of searching the database based on a plurality of sets of gas filling order information to obtain the gas filling rate information corresponding to the order specifically includes the following steps: Searching the database based on several groups of gas filling order information to obtain gas filling volume information and gas filling completion time information; Calculate based on the gas filling volume information and the gas filling completion time information to obtain the gas filling rate information; The specific calculation formula for obtaining the gas filling rate is: , In the formula, is the gas filling rate, T is the gas filling completion time, and S is the gas filling volume; The method of drawing a curve based on the gas filling rate information corresponding to the order to obtain a plurality of groups of order gas filling rate curves specifically includes the following steps: A rectangular coordinate system is established with the filling completion time information as the X-axis and the filling volume information as the Y-axis; Based on the gas filling rate information corresponding to the several groups of orders, curves are drawn in a rectangular coordinate system to obtain the gas filling rate curves of the several groups of orders; The method of performing a proximity analysis on the order gas filling rate curves of adjacent time periods to obtain the gas filling rate offset specifically includes the following steps: Performing time analysis on the gas filling rate curve based on the gas filling order information to determine the gas filling rate curve information for adjacent time periods; Calculate and process the gas filling rate curve information in adjacent time periods to obtain the gas filling rate offset; The calculation and processing based on the gas filling rate curve information of adjacent time periods to obtain the gas filling rate offset specifically includes the following steps: Extract time features from the gas filling rate curves in adjacent time periods to determine the completion time of two groups of gas filling; Calculate and process the two groups of gas filling completion time to obtain the minimum gas filling completion time; The specific calculation formula for the minimum gas filling completion time is: ; in, The gas filling completion time for two groups respectively; The minimum gas filling completion time is set as the reference time, and the curve of another group of gas filling completion time is removed by the reference time to obtain the gas filling rate curve; Comparing the processed gas filling rate curve with the gas filling rate curve corresponding to the reference time, obtaining the gas filling rate offset; The determination process based on the gas filling rate offset to determine the state of the gas filling station specifically includes the following steps: Making a judgment based on the gas filling rate offset and a set first threshold; If the gas filling rate offset is greater than the set first threshold, the first gas filling rate abnormal point is output; If the gas filling rate offset is equal to the set first threshold, the output gas filling is normal; If the gas filling rate offset is less than the set first threshold, a second judgment is made on the gas filling rate offset; Analyze the first abnormal point of gas filling rate to determine the status of the gas filling station; The secondary determination of the gas filling rate offset specifically comprises the following steps: Making a judgment based on the gas filling rate offset and a set second threshold; If the gas filling rate offset is less than the set second threshold, the second gas filling rate abnormal point is output; If the gas filling rate offset is greater than or equal to the set second threshold, the output gas filling is normal; Obtaining time data corresponding to the second gas filling rate abnormal point; Performing data extraction processing on the database based on the time data corresponding to the abnormal point of the second gas filling rate, and determining the second gas storage volume of the gas filling station; Making a judgment based on a second gas storage volume of the gas filling station and a set third threshold; If the second gas storage volume of the gas filling station is less than or equal to the set third threshold, the output gas filling station has insufficient gas storage and cannot reach the average gas filling rate, and the gas filling station is in normal state; If the gas storage volume of the gas filling station is greater than the set third threshold, the output gas filling station pipeline is abnormal; The analyzing of the first abnormal point of the gas filling rate to determine the state of the gas filling station specifically comprises the following steps: Performing data extraction processing on the database based on the time data corresponding to the first gas filling rate abnormal point to determine the first gas storage volume of the gas filling station; Making a judgment based on a first gas storage volume of the gas filling station and a set fourth threshold; If the first gas storage volume of the gas filling station is less than or equal to the set fourth threshold value, the output gas filling station has insufficient gas storage and cannot reach the average gas filling rate, and the gas filling station is in a normal state; If the first gas storage volume of the gas filling station is greater than the set fourth threshold, the pipeline of the gas filling station is abnormal.

2. A method for processing massive gas filling data at a gas filling station according to claim 1, characterized in that: The data preprocessing based on the historical data of the gas filling station to obtain several groups of gas filling order information specifically includes the following steps: Perform outlier deletion processing on historical data to obtain first processed data; Perform missing value filling processing on the first processed data to obtain second processed data; The specific calculation formula for the missing value filling process is: ; In the formula, is the filling data; i is the number of filling data; are different types of historical data; n is the number of different types of historical data; Classification is performed based on the second processed data to obtain several groups of gas filling order information.

3. A system for processing massive gas filling data at a gas filling station, used to implement a method for processing massive gas filling data at a gas filling station as claimed in any one of claims 1 to 2, characterized in that: include: An extraction module, which is used to extract the database of the gas filling station, obtain the historical data of the gas filling station and obtain the average gas filling rate of the gas filling station; A data preprocessing module, which is used to preprocess the historical data of the gas station and obtain several groups of gas filling order information; A search module, the search module is used to search a database for several groups of gas filling order information to obtain gas filling rate information corresponding to the order; A curve drawing module, the curve drawing module is used to draw a curve for the gas filling rate information corresponding to the order, and obtain a plurality of groups of order gas filling rate curves; A data screening module, which is used to screen the gas filling order information and obtain the gas filling time of several groups of users; A proximity analysis module, which is used to perform a proximity analysis on the order gas filling rate curves in adjacent time periods to obtain a gas filling rate offset; The judgment module is used to judge the gas filling rate offset and determine the state of the gas filling station.