Electricity-carbon-green evidence market combined clearing method
By calculating the combined marginal carbon dioxide emission factor and the joint clearing model, combined with the MATLAB toolbox, the joint clearing of the electricity-carbon-green certificate market is realized, which solves the problems of insufficient information exchange and difficulty in reflecting the effects of the environmental rights system, and promotes resource Optimization and carbon reduction.
Patent Information
- Application Number
- CN202410651401.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-24
- Publication Date
- 2024-10-01
AI Technical Summary
The existing technology fails to effectively combine the electricity, carbon and green certificate markets, resulting in insufficient information exchange, difficulty in intuitively reflecting the effects of the environmental rights system, and failure to comprehensively assess the impact of new energy consumption and price transmission.
A joint clearing method for the electricity-carbon-green certificate market is proposed. By calculating the combined marginal carbon dioxide emission factor, joint clearing target model and evaluation model, the conversion of green certificates and CCER is realized, and the solution is combined with MATLAB's Yalmip toolbox and Gurobi It calculates the joint clearing results of the electricity-carbon-green certificate market and the separate clearing results of the electricity market, and evaluates carbon emission reduction, new energy consumption and price transmission indicators.
It avoids double calculation of the green value of new energy power generation, promotes the optimal allocation of resources, clarifies the role of carbon emission reduction and new energy consumption, reflects changes in electricity prices, and achieves the effective allocation and utilization of carbon quotas and green certificates.
Smart Images

Figure CN118735539A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of electric power technology, and in particular to a method for joint clearing of electricity-carbon-green certificate markets. Background Art
[0002] As one of the main sources of carbon emissions, the power industry has promoted emission reduction through the large-scale development of new energy units in recent years. Taking the power generation industry as an example, the carbon market is carried out through the principle of total volume trading and restriction, with carbon quotas as the subject of trading. The management department sets a total carbon quota upper limit for a period of time and allocates initial carbon quotas to participating entities according to certain principles. Then the entities can trade carbon quotas and submit carbon quotas that match the carbon emissions of the entities at the end of the compliance period; the green certificate market often operates with the quota of the renewable energy responsibility consumption mechanism. The management agency issues green certificates based on the power generation of renewable energy units. Market entities that bear the consumption responsibility need to purchase green certificates to meet the renewable energy consumption responsibility weight, that is, the green certificate holdings of the entity must be no less than a certain proportion of its own power generation, thereby promoting the use of renewable energy power generation. At the same time, new energy power generation can also obtain CCERs and sell them in the carbon market while obtaining green certificates, which may lead to repeated calculations of the green value of electricity. Due to the coupling relationship between the power industry and carbon emissions and new energy consumption, transactions in the carbon and green certificate markets will inevitably affect aspects such as power market prices and unit combinations through changes in power generation costs. Therefore, it is necessary to establish a joint clearing model of the electricity-carbon-green certificate market based on the conversion mechanism between CCER and green certificates, and to evaluate the emission reduction effects of the environmental rights system on the power industry by establishing appropriate evaluation indicators.
[0003] The existing technology mainly considers the independent operation of the electricity market, carbon market and green certificate market, and has not yet considered the joint bidding and clearing of the electricity-carbon-green certificate market, and lacks the conversion of CCER and green certificate, which is not conducive to the exchange of information between markets and the unique identification of the effect of environmental rights and interests system products. At the same time, the existing technology has not comprehensively evaluated the impact of the environmental rights and interests system on power generation units from multiple aspects such as emission reduction effect, new energy consumption and price transmission, and it is difficult to intuitively reflect the effect of the environmental rights and interests system. Therefore, how to provide a joint clearing method for the electricity-carbon-green certificate market is an urgent problem that technicians in this field need to solve. Summary of the invention
[0004] One purpose of the present invention is to propose a joint clearing method for the electricity-carbon-green certificate market. The present invention is conducive to new energy units participating in the carbon market and the green certificate market at the same time, while achieving the optimization of social welfare in economic and green aspects.
[0005] A method for joint clearing of electricity-carbon-green certificate markets according to an embodiment of the present invention comprises the following steps:
[0006] S1. Import the data required for market clearing calculations;
[0007] S2. Calculate the combined marginal carbon dioxide emission factor for green certificates and CCER conversion based on the data required for known market clearing calculations;
[0008] S3. Calculate the joint clearing results of the electricity-carbon-green certificate markets based on the joint clearing target model;
[0009] S4. Under the same data of S2 and S3, calculate the separate clearing results of the electricity market according to the electricity clearing target model;
[0010] S5. Based on the results of the joint clearing of the electricity-carbon-green certificate markets and the results of the separate clearing of the electricity market, the carbon emission reduction, new energy consumption and price transmission indicators are calculated according to the evaluation model to evaluate the effect of the joint clearing.
[0011] Optionally, the data required for importing market clearing calculations include power system node and branch information, unit information, the subject's declared price in each market, carbon emission intensity, carbon quota allocation information, total carbon quota upper limit, renewable energy responsibility absorption weight of thermal power units, and green certificate and CCER conversion information.
[0012] Optionally, the combined marginal CO2 emission factor EF CM The details are as follows:
[0013] EF CM =v e EF OM +ν c EF BM ;
[0014] Among them, ν e Represents the marginal emission factor weight of electricity, EF OM represents the marginal emission factor of electricity, ν c Represents the capacity marginal emission factor weight, EF BM represents the capacity marginal emission factor;
[0015] The marginal emission factor for electricity is the average value of the ratio of total emissions to power generation of all fossil fuel power plants in the power system in the past three years, and the marginal emission factor for capacity is the ratio of total emissions to power generation of newly built power plants that account for 20% of the total power generation in the power system.
[0016] Optionally, the joint clearing target model is specifically as follows:
[0017]
[0018] Where S represents the total social welfare of the electricity market, carbon market and green certificate market, u represents the power user number, k represents the renewable energy unit number, t represents the time period number, j represents the thermal power unit number, U represents the set of all power users, K represents the set of all renewable energy units, T represents the set of all time periods, J represents the set of all thermal power units, and J represents the set of all renewable energy units. buy represents the set of all thermal power units that need to buy carbon quotas, J sell represents the set of all thermal power units that need to sell carbon quotas, represents the price quoted by the electricity user in time period t, represents the power consumption of power user u in time period t, represents the price of thermal power unit j in time period t, represents the power generation of thermal power unit j in time period t, represents the price of new energy unit k in time period t, represents the power generation of the new energy unit k in time period t, represents the price of the coal-fired power unit j to buy carbon quota or CCER in time period t, represents the amount of carbon quota purchased by thermal power unit j in time period t, represents the price of the carbon quota sold by thermal power unit j in time period t, represents the amount of carbon quota sold by thermal power unit j in time period t, represents the price of CCER sold by new energy unit k in time period t, represents the CCER quantity sold by new energy unit k in time period t, It represents the price of buying green certificates of thermal power unit j in period t. It indicates the amount of green certificates purchased by thermal power unit j in period t. It represents the price of selling green certificates of new energy unit k in time period t. It indicates the amount of green certificates sold by new energy unit k in time period t.
[0019] Optionally, S3 further includes joint clearing constraints, and the joint clearing constraints include market coupling constraints, electricity market constraints, carbon market constraints and green certificate market constraints;
[0020] Market coupling constraints: Any thermal power unit uses the baseline method to allocate initial carbon quotas. Units with carbon emission intensity higher than the baseline value need to buy carbon quotas, and units with carbon emission intensity lower than the baseline value can sell carbon quotas. At the end of time T, the carbon quota holdings of any thermal power unit must not be less than its carbon emissions. After time T, any thermal power unit must hold a green certificate for a certain proportion of its power generation:
[0021]
[0022]
[0023]
[0024]
[0025]
[0026]
[0027] in, represents the initial holding of carbon quota of thermal power unit j, χ j represents the carbon emission intensity benchmark value of thermal power unit j, and Δt is the single clearing interval time; represents the final carbon quota holding of thermal power unit j, σ j represents the carbon emission intensity of thermal power unit j; represents the amount of green certificates obtained by the new energy unit k in the T time period, and β represents the amount of green certificates issued corresponding to the unit power generation of the new energy unit; represents the CCER amount converted from green certificates of new energy unit k in time period t, EF CM represents the combined marginal CO2 emission factor, represents the amount of green certificates that the new energy unit k needs to convert into CCER in time period t; ε j represents the renewable energy consumption weight of thermal power unit j;
[0028] Power market constraints: The total power generation in any time period is equal to the total power consumption; the power generation of any thermal power unit in any time period does not exceed its upper and lower limits; the power generation of any new energy unit in any time period does not exceed its predicted value and is not less than 0; the power flow of any branch of the power system in any time period does not exceed its upper and lower limits; the power consumption of any power market user in any time period does not exceed its upper and lower limits:
[0029]
[0030]
[0031]
[0032]
[0033]
[0034]
[0035] in, and They represent the upper and lower limits of power generation of thermal power unit j respectively; represents the predicted power generation value of the new energy unit k in time period t; P l,max represents the upper limit of power flow in branch l of the power system, P l,t represents the power flow of power system branch l in time period t, l represents the branch number of the power system, and L represents the set of all branches of the power system; T j,l , T k,l and T u,l They represent the power transmission distribution coefficients of thermal power unit j, new energy unit k and power demand side u in branch l respectively; and They represent the upper and lower limits of power consumption on the power demand side, respectively. The power transmission distribution coefficient represents the change of power flow in each branch when the input power of a certain node changes.
[0036] Carbon market constraints: The total amount of carbon quotas or emission reductions bought or sold in any time period is equal; the final total amount of carbon quotas of all thermal power units shall not exceed the total upper limit and shall not be less than 0; the carbon quotas or CCERs bought by thermal power units that buy carbon quotas or CCERs in any time period shall not exceed the upper limit and shall not be less than 0; the amount of carbon quotas sold by thermal power units that sell carbon quotas in any time period shall not exceed the upper limit and shall not be less than 0; the CCERs sold by new energy units in any time period shall not exceed the amount of CCERs converted from green certificates:
[0037]
[0038]
[0039]
[0040]
[0041]
[0042] Among them, Q cap Indicates the total upper limit of carbon quota; Indicates the purchase of carbon quota or emission reduction limit of thermal power unit j; represents the upper limit of carbon quota sold by thermal power unit j;
[0043] Green certificate market constraints: The total amount of green certificates purchased by all thermal power units is equal to the total amount of green certificates sold by all new energy units. The amount of green certificates purchased by thermal power units in any time period shall not exceed the upper limit and shall not be less than 0; the amount of green certificates sold by new energy units in any time period shall not exceed the upper limit and shall not be less than 0; the sum of the amount of green certificates sold by new energy units and the amount of green certificates converted into emission reductions shall not exceed the initial amount of green certificates:
[0044]
[0045]
[0046]
[0047]
[0048] in, It indicates the upper limit of the amount of green certificates purchased by thermal power unit j; Indicates the upper limit of green certificates sold by new energy unit k.
[0049] Optionally, according to the joint clearing constraints and the joint clearing target model, MATLAB's Yalmip toolbox and Gurobi solver are used to solve the problem and finally obtain the joint clearing result, in which the electricity market adopts the calculation method of the node marginal electricity price, and the carbon market and green certificate market adopt the marginal price.
[0050] Optionally, the power clearing target model is specifically as follows:
[0051]
[0052] Among them, S e represents the total social welfare of the electricity market; It represents the power consumption of power demand side u in time period t when the power system is cleared separately; represents the power generation of thermal power unit j in time period t when the power system is cleared separately; It represents the power generation of the new energy unit k in time period t when the power system is cleared separately.
[0053] Optionally, S4 also includes a separate clearing constraint, and the separate clearing constraint is specifically as follows:
[0054]
[0055]
[0056]
[0057]
[0058]
[0059]
[0060] in, and They represent the upper and lower limits of power generation of thermal power unit j respectively; represents the predicted power generation value of the new energy unit k in time period t; P l,max represents the upper limit of power flow in branch l of the power system, P l,trepresents the power flow of power system branch l in time period t, l represents the branch number of the power system, and L represents the set of all branches of the power system; T j,l , T k,l and T u,l They represent the power transmission distribution coefficients of thermal power unit j, new energy unit k and power demand side u in branch l respectively; and They respectively represent the upper and lower limits of electricity consumption on the electricity demand side.
[0061] Optionally, according to the individual clearing constraints and the power clearing target model, the Yalmip toolbox and Gurobi solver of MATLAB are used to solve the planning problem and obtain the clearing result.
[0062] Optionally, the evaluation model is as follows:
[0063]
[0064]
[0065]
[0066] Among them, ρ 1 Represents the carbon emission reduction effect index; σ j represents the carbon emission intensity of thermal power unit j; represents the power generation of thermal power unit j in time period t, Δt is the single clearing interval time, represents the power generation of thermal power unit j in time period t when the power system is cleared separately; ρ 2 Represents the new energy consumption index, represents the power generation of the new energy unit k in time period t, represents the power generation of the new energy unit k in time period t when the power system is cleared separately; ρ 3 represents the price transmission indicator, α LMP-average represents the average node marginal electricity price for the joint clearing of the electricity-carbon-green certificate market, α LMP-e-average Represents the average nodal marginal electricity price for individual clearing of the electricity market.
[0067] The beneficial effects of the present invention are:
[0068] The electricity-carbon-green certificate market joint clearing method and evaluation system provided by the present invention avoids repeated calculation of the green value of power generation of new energy units and repeated issuance of products by realizing the conversion of green certificates and CCERs, and reduces the impact of insufficient information exchange through joint clearing, promotes the optimal allocation of resources and the effective allocation and utilization of carbon quotas and green certificates, and clarifies the role of the electricity-carbon-green certificate market joint clearing in carbon emission reduction and new energy consumption by establishing an evaluation system, and reflects the changes in electricity prices caused by the increase in power generation costs of units under transactions in the carbon market and the green certificate market. BRIEF DESCRIPTION OF THE DRAWINGS
[0069] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:
[0070] Figure 1 This is a flow chart of a method for joint clearing of electricity-carbon-green certificate markets proposed in the present invention. DETAILED DESCRIPTION
[0071] The present invention will now be described in further detail with reference to the accompanying drawings. These drawings are simplified schematic diagrams, which only illustrate the basic structure of the present invention in a schematic manner, and therefore only show the components related to the present invention.
[0072] refer to Figure 1 , a method for joint clearing of electricity-carbon-green certificate markets, comprising the following steps:
[0073] S1. Import the data required for market clearing calculations;
[0074] In this implementation, the data required for importing market clearing calculations include power system node and branch information, unit information, the subject's declared price in each market, carbon emission intensity, carbon quota allocation information, the total carbon quota upper limit, the renewable energy responsibility absorption weight of thermal power units, and green certificate and CCER conversion information.
[0075] S2. Calculate the combined marginal carbon dioxide emission factor for green certificates and CCER conversion based on the data required for known market clearing calculations;
[0076] In this implementation, the combined marginal carbon dioxide emission factor EF CM The details are as follows:
[0077] EF CM =v e EF OM +ν c EF BM ;
[0078] Among them, ν eRepresents the marginal emission factor weight of electricity, EF OM represents the marginal emission factor of electricity, ν c Represents the capacity marginal emission factor weight, EF BM represents the capacity marginal emission factor;
[0079] The marginal emission factor for electricity is the average ratio of the total emissions to the power generation of all fossil fuel power plants in the power system in the past three years, and the marginal emission factor for capacity is the ratio of the total emissions to the power generation of newly built power plants that account for 20% of the total power generation in the power system.
[0080] S3. Calculate the joint clearing results of the electricity-carbon-green certificate markets based on the joint clearing target model;
[0081] In this implementation, the joint clearing target model is specifically as follows:
[0082]
[0083] Where S represents the total social welfare of the electricity market, carbon market and green certificate market, u represents the power user number, k represents the renewable energy unit number, t represents the time period number, j represents the thermal power unit number, U represents the set of all power users, K represents the set of all renewable energy units, T represents the set of all time periods, J represents the set of all thermal power units, and J represents the set of all renewable energy units. buy represents the set of all thermal power units that need to buy carbon quotas, J sell represents the set of all thermal power units that need to sell carbon quotas, represents the price quoted by the electricity user in time period t, represents the power consumption of power user u in time period t, represents the price of thermal power unit j in time period t, represents the power generation of thermal power unit j in time period t, represents the price of new energy unit k in time period t, represents the power generation of the new energy unit k in time period t, represents the price of the coal-fired power unit j to buy carbon quota or CCER in time period t, represents the amount of carbon quota purchased by thermal power unit j in time period t, represents the price of the carbon quota sold by thermal power unit j in time period t, represents the amount of carbon quota sold by thermal power unit j in time period t, represents the price of CCER sold by new energy unit k in time period t, represents the CCER quantity sold by new energy unit k in time period t, It represents the price of buying green certificates of thermal power unit j in period t. It indicates the amount of green certificates purchased by thermal power unit j in period t. It represents the price of selling green certificates of new energy unit k in time period t. It indicates the amount of green certificates sold by new energy unit k in time period t.
[0084] In this implementation, S3 also includes joint clearing constraints, which include market coupling constraints, power market constraints, carbon market constraints, and green certificate market constraints;
[0085] Market coupling constraints: Any thermal power unit uses the baseline method to allocate initial carbon quotas. Units with carbon emission intensity higher than the baseline value need to buy carbon quotas, and units with carbon emission intensity lower than the baseline value can sell carbon quotas. At the end of time T, the carbon quota holdings of any thermal power unit must not be less than its carbon emissions. After time T, any thermal power unit must hold a green certificate for a certain proportion of its power generation:
[0086]
[0087]
[0088]
[0089]
[0090]
[0091]
[0092] in, represents the initial holding of carbon quota of thermal power unit j, χ j represents the carbon emission intensity benchmark value of thermal power unit j, and Δt is the single clearing interval time; represents the final carbon quota holding of thermal power unit j, σ j represents the carbon emission intensity of thermal power unit j; represents the amount of green certificates obtained by the new energy unit k in the T time period, and β represents the amount of green certificates issued corresponding to the unit power generation of the new energy unit; represents the CCER amount converted from green certificates of new energy unit k in time period t, EF CM represents the combined marginal CO2 emission factor, represents the amount of green certificates that the new energy unit k needs to convert into CCER in time period t; ε j represents the renewable energy consumption weight of thermal power unit j;
[0093] Power market constraints: The total power generation in any time period is equal to the total power consumption; the power generation of any thermal power unit in any time period does not exceed its upper and lower limits; the power generation of any new energy unit in any time period does not exceed its predicted value and is not less than 0; the power flow of any branch of the power system in any time period does not exceed its upper and lower limits; the power consumption of any power market user in any time period does not exceed its upper and lower limits:
[0094]
[0095]
[0096]
[0097]
[0098]
[0099]
[0100] in, and They represent the upper and lower limits of power generation of thermal power unit j respectively; represents the predicted power generation value of the new energy unit k in time period t; P l,max represents the upper limit of power flow in branch l of the power system, P l,t represents the power flow of power system branch l in time period t, l represents the branch number of the power system, and L represents the set of all branches of the power system; T j,l , T k,l and T u,l They represent the power transmission distribution coefficients of thermal power unit j, new energy unit k and power demand side u in branch l respectively; and They represent the upper and lower limits of power consumption on the power demand side, respectively. The power transmission distribution coefficient represents the change of power flow in each branch when the input power of a certain node changes.
[0101] Carbon market constraints: The total amount of carbon quotas or emission reductions bought or sold in any time period is equal; the final total amount of carbon quotas of all thermal power units shall not exceed the total upper limit and shall not be less than 0; the carbon quotas or CCERs bought by thermal power units that buy carbon quotas or CCERs in any time period shall not exceed the upper limit and shall not be less than 0; the amount of carbon quotas sold by thermal power units that sell carbon quotas in any time period shall not exceed the upper limit and shall not be less than 0; the CCERs sold by new energy units in any time period shall not exceed the amount of CCERs converted from green certificates:
[0102]
[0103]
[0104]
[0105]
[0106]
[0107] Among them, Q cap Indicates the total upper limit of carbon quota; Indicates the purchase of carbon quota or emission reduction limit of thermal power unit j; represents the upper limit of carbon quota sold by thermal power unit j;
[0108] Green certificate market constraints: The total amount of green certificates purchased by all thermal power units is equal to the total amount of green certificates sold by all new energy units. The amount of green certificates purchased by thermal power units in any time period shall not exceed the upper limit and shall not be less than 0; the amount of green certificates sold by new energy units in any time period shall not exceed the upper limit and shall not be less than 0; the sum of the amount of green certificates sold by new energy units and the amount of green certificates converted into emission reductions shall not exceed the initial amount of green certificates:
[0109]
[0110]
[0111]
[0112]
[0113] in, It indicates the upper limit of the amount of green certificates purchased by thermal power unit j; Indicates the upper limit of green certificates sold by new energy unit k.
[0114] In this implementation, according to the joint clearing constraints and the joint clearing target model, MATLAB's Yalmip toolbox and Gurobi solver are used to solve the problem and finally obtain the joint clearing result, in which the electricity market adopts the node marginal electricity price calculation method, and the carbon market and green certificate market adopt marginal price.
[0115] S4. Under the same data of S2 and S3, calculate the separate clearing results of the electricity market according to the electricity clearing target model;
[0116] In this implementation, the power clearing target model is as follows:
[0117]
[0118] Among them, S e represents the total social welfare of the electricity market; It represents the power consumption of power demand side u in time period t when the power system is cleared separately; represents the power generation of thermal power unit j in time period t when the power system is cleared separately; It represents the power generation of the new energy unit k in time period t when the power system is cleared separately.
[0119] In this implementation, S4 also includes a separate clearing constraint, which is specifically as follows:
[0120]
[0121]
[0122]
[0123]
[0124]
[0125]
[0126] in, and They represent the upper and lower limits of power generation of thermal power unit j respectively; represents the predicted power generation value of the new energy unit k in time period t; P l,max represents the upper limit of power flow in branch l of the power system, P l,t represents the power flow of power system branch l in time period t, l represents the branch number of the power system, and L represents the set of all branches of the power system; T j,l , T k,l and T u,l They represent the power transmission distribution coefficients of thermal power unit j, new energy unit k and power demand side u in branch l respectively; and They respectively represent the upper and lower limits of electricity consumption on the electricity demand side.
[0127] In this implementation, according to the individual clearing constraints and the power clearing target model, the Yalmip toolbox and Gurobi solver of MATLAB are used to solve the planning problem and obtain the clearing result.
[0128] S5. Based on the results of the joint clearing of the electricity-carbon-green certificate markets and the results of the separate clearing of the electricity market, the carbon emission reduction, new energy consumption and price transmission indicators are calculated according to the evaluation model to evaluate the effect of the joint clearing.
[0129] In this implementation, the evaluation model is specifically as follows:
[0130]
[0131]
[0132]
[0133] Among them, ρ 1 Represents the carbon emission reduction effect index; σ j represents the carbon emission intensity of thermal power unit j; represents the power generation of thermal power unit j in time period t, Δt is the single clearing interval time, represents the power generation of thermal power unit j in time period t when the power system is cleared separately; ρ 2 Represents the new energy consumption index, represents the power generation of the new energy unit k in time period t, represents the power generation of the new energy unit k in time period t when the power system is cleared separately; ρ 3 represents the price transmission indicator, α LMP-average represents the average node marginal electricity price for the joint clearing of the electricity-carbon-green certificate market, α LMP-e-average Represents the average nodal marginal electricity price for individual clearing of the electricity market.
[0134] Embodiment 1:
[0135] This embodiment is modified based on the 30-node power system to obtain the embodiment data, all branch flows P l,max It is 99999MW; the lower limit of electricity consumption of power users is 0.65 times of the node load, and the upper limit is the node load value; among them, G1-G5 are thermal power units, W1-W4 are wind power units, which are located at nodes 1, 2, 22, 23 and 13 respectively, and the unit capacity is between 200MW and 400MW; W1-W4 are wind power units, which are located at nodes 12, 5, 7 and 25 respectively, among which units W1 and W3 have the same predicted output, between 32-165MW, and units W2 and W4 have the same predicted output, between 60-210MW, and all show a trend of large predicted output at night and small predicted output during the day.
[0136] The market is cleared once every hour, for a total of 24 times, i.e. Δt = 1 and T = 24. The total limit of carbon emission clearing Q cap =20000tCO 2 , carbon emission intensity benchmark value χ j =0.9. The amount of green certificates issued for the unit power generation of new energy units β = 1, and the weight of the renewable energy consumption responsibility of thermal power units ε j =0.08. Weight of marginal emission factor of electricity consumption ν e =0.75, capacity marginal emission factor weight ν c =0.25, electricity marginal emission factor EF OM =0.7921, capacity marginal emission factor EF BM =0.387.
[0137] The Yalmip toolbox and Gurobi solver of MATLAB are used to solve the problem and obtain the power generation of the units, the carbon quota or CCER trading situation and the market prices. In terms of power generation, the power generation of wind turbines W1-W4 is basically consistent with the predicted output. The power generation of thermal power units with relatively low carbon emission intensity such as G1 is still large, reaching the capacity limit of 400MW. The power generation of thermal power units with relatively high carbon emission intensity such as G4 is small, and the power generation is below 120MW most of the time, and only reaches the capacity limit of 300MW during a small number of peak power consumption periods; in terms of carbon quota or CCER, the carbon emission intensity of thermal power units such as G1 is lower than the benchmark value, and the trading volume is subject to the upper limit constraint, in the range of 0-50tCO 2 The carbon emission intensity of G3 and other thermal power units is higher than the benchmark value, and the trading volume is subject to an upper limit of 0-50tCO 2 In terms of green certificates, wind turbines convert some green certificates into CCERs and trade them in the carbon market. 2 between.
[0138] Thermal power units with carbon emission intensity higher than the benchmark value need to buy carbon quotas or CCERs to meet power generation needs, such as G1 and G2, while units with lower carbon emission intensity such as G3-G5 can sell carbon quotas to obtain additional income. In addition, W3 converts part of the green certificates into CCERs and sells them in the carbon market to obtain more income. In the green certificate market, thermal power units need to buy green certificates from wind turbines to meet the renewable energy consumption weight requirements, and the greater the power generation of the unit, the more green certificates need to be purchased.
[0139] According to the constraints and objective function, the Yalmip toolbox and Gurobi solver of MATLAB are used to solve the power market clearing model to obtain the electricity price and unit power generation. In terms of clearing price, the power market clearing price is about 530 yuan / MWh, while the joint clearing price is about 950 yuan / MWh, and the carbon price is 49-54 yuan / tCO 2 , the price of green certificates is 54-59 yuan / MWh; in terms of unit power generation, under the separate clearing of the electricity market, the power generation of thermal power units is large, such as G1, G4 and G5 units have reached the capacity limit, 400MW, 300MW and 200MW respectively, while the power generation of wind turbines is relatively small, such as W2 with a power generation of 0-135MW.
[0140] From the comparison of the clearing results, it can be seen that the output of wind turbines increased and the output of thermal power units decreased in the electricity-carbon-green certificate joint clearing compared with the electricity market clearing alone, which reflects the effectiveness of this method in promoting emission reduction and new energy consumption. For example, in the electricity market clearing alone mode, W2's output was 0 at 6:00, but reached the predicted output value in the joint clearing; G3's total output was significantly less in the joint clearing than in the electricity market clearing alone.
[0141] In terms of electricity prices, when electricity, carbon and green certificates are jointly cleared, due to the increase in emission reduction and new energy consumption demand, the electricity price is significantly higher than the electricity market clearing alone. Therefore, the unit can obtain more benefits in the electricity market, thereby balancing the costs of the carbon market and the green certificate market to a certain extent. In addition, under the electricity-carbon-green certificate coupled clearing mode, the electricity price is affected by the carbon price and the green certificate price. For example, the electricity price under the electricity market clearing alone from 12:00 to 13:00 has decreased, but in the joint clearing, due to the influence of the green certificate price, the electricity price during the same period has increased.
[0142] Finally, according to the evaluation index data, the joint clearing of electricity, carbon and green certificates can effectively reduce the carbon emissions of the power system and promote the consumption of electricity from new energy units, reducing the abandonment of wind and solar power. At the same time, the additional costs incurred by the units in transactions in the carbon market and the green certificate market are transmitted to the demand side through electricity prices.
[0143] It can be seen that the present invention can realize the conversion of green certificate market and carbon market products, and achieve the reduction of carbon emissions and the consumption of new energy electricity through the joint clearing of electricity-carbon-green certificate, and reflect the increase in electricity prices of power generators due to transactions in the carbon market and green certificate market in the electricity price. The evaluation indicators can intuitively reflect the effect of the joint market clearing.
[0144] The electricity-carbon-green certificate market joint clearing method and evaluation system provided by the present invention avoids repeated calculation of the green value of power generation of new energy units and repeated issuance of products by realizing the conversion of green certificates and CCERs, and reduces the impact of insufficient information exchange through joint clearing, promotes the optimal allocation of resources and the effective allocation and utilization of carbon quotas and green certificates, and clarifies the role of the electricity-carbon-green certificate market joint clearing in carbon emission reduction and new energy consumption by establishing an evaluation system, and reflects the changes in electricity prices caused by the increase in power generation costs of units under transactions in the carbon market and the green certificate market.
[0145] The present invention is conducive to the new energy units participating in the carbon market and the green certificate market at the same time, while realizing the optimization of social welfare in economic and green aspects.
[0146] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A method for joint clearing of electricity-carbon-green certificate markets, characterized in that: The steps include: S1. Import the data required for market clearing calculations; S2. Calculate the combined marginal carbon dioxide emission factor for green certificates and CCER conversion based on the data required for known market clearing calculations; S3. Calculate the joint clearing results of the electricity-carbon-green certificate markets based on the joint clearing target model; S4. Under the same data of S2 and S3, calculate the separate clearing results of the electricity market according to the electricity clearing target model; S5. Based on the results of the joint clearing of the electricity-carbon-green certificate markets and the results of the separate clearing of the electricity market, the carbon emission reduction, new energy consumption and price transmission indicators are calculated according to the evaluation model to evaluate the effect of the joint clearing.
2. The electricity-carbon-green certificate market joint clearing method according to claim 1 is characterized in that: The data required for importing market clearing calculations include power system node and branch information, unit information, the subject's declared price in each market, carbon emission intensity, carbon quota allocation information, the total carbon quota upper limit, the renewable energy responsibility absorption weight of thermal power units, and green certificate and CCER conversion information.
3. The electricity-carbon-green certificate market joint clearing method according to claim 2 is characterized in that: The combined marginal CO2 emission factor EF CM The details are as follows: EF CM =n e EF OM +n c EF BM ; Among them, ν e Represents the marginal emission factor weight of electricity, EF OM represents the marginal emission factor of electricity, ν c Represents the capacity marginal emission factor weight, EF BM represents the capacity marginal emission factor; The marginal emission factor for electricity is the average value of the ratio of total emissions to power generation of all fossil fuel power plants in the power system in the past three years, and the marginal emission factor for capacity is the ratio of total emissions to power generation of newly built power plants that account for 20% of the total power generation in the power system.
4. The electricity-carbon-green certificate market joint clearing method according to claim 3 is characterized in that: The joint clearing target model is as follows: Where S represents the total social welfare of the electricity market, carbon market and green certificate market, u represents the power user number, k represents the renewable energy unit number, t represents the time period number, j represents the thermal power unit number, U represents the set of all power users, K represents the set of all renewable energy units, T represents the set of all time periods, J represents the set of all thermal power units, and J represents the set of all renewable energy units. buy represents the set of all thermal power units that need to buy carbon quotas, J sell represents the set of all thermal power units that need to sell carbon quotas, represents the price quoted by the electricity user in time period t, represents the power consumption of power user u in time period t, represents the price of thermal power unit j in time period t, represents the power generation of thermal power unit j in time period t, represents the price of new energy unit k in time period t, represents the power generation of the new energy unit k in time period t, represents the price of the coal-fired power unit j to buy carbon quota or CCER in time period t, represents the amount of carbon quota purchased by thermal power unit j in time period t, represents the price of the carbon quota sold by thermal power unit j in time period t, represents the amount of carbon quota sold by thermal power unit j in time period t, represents the price of CCER sold by new energy unit k in time period t, represents the CCER quantity sold by new energy unit k in time period t, It represents the price of buying green certificates of thermal power unit j in period t. It indicates the amount of green certificates purchased by thermal power unit j in period t. It represents the price of selling green certificates of new energy unit k in time period t. It indicates the amount of green certificates sold by new energy unit k in time period t.
5. The electricity-carbon-green certificate market joint clearing method according to claim 4 is characterized in that: The S3 also includes joint clearing constraints, which include market coupling constraints, electricity market constraints, carbon market constraints and green certificate market constraints; Market coupling constraints: Any thermal power unit uses the baseline method to allocate initial carbon quotas. Units with carbon emission intensity higher than the baseline value need to buy carbon quotas, and units with carbon emission intensity lower than the baseline value can sell carbon quotas. At the end of time T, the carbon quota holdings of any thermal power unit must not be less than its carbon emissions. After time T, any thermal power unit must hold a green certificate for a certain proportion of its power generation: in, represents the initial holding of carbon quota of thermal power unit j, χ j represents the carbon emission intensity benchmark value of thermal power unit j, and Δt is the single clearing interval time; represents the final carbon quota holding of thermal power unit j, σ j represents the carbon emission intensity of thermal power unit j; represents the amount of green certificates obtained by the new energy unit k in the T time period, and β represents the amount of green certificates issued corresponding to the unit power generation of the new energy unit; represents the CCER amount converted from green certificates of new energy unit k in time period t, EF CM represents the combined marginal CO2 emission factor, represents the amount of green certificates that the new energy unit k needs to convert into CCER in time period t; ε j represents the renewable energy consumption weight value of thermal power unit j; Power market constraints: The total power generation in any time period is equal to the total power consumption; the power generation of any thermal power unit in any time period does not exceed its upper and lower limits; the power generation of any new energy unit in any time period does not exceed its predicted value and is not less than 0; the power flow of any branch of the power system in any time period does not exceed its upper and lower limits; the power consumption of any power market user in any time period does not exceed its upper and lower limits: in, and They represent the upper and lower limits of power generation of thermal power unit j respectively; represents the predicted power generation value of the new energy unit k in time period t; P l,max represents the upper limit of power flow in branch l of the power system, P l,t represents the power flow of power system branch l in time period t, l represents the branch number of the power system, and L represents the set of all branches of the power system; T j,l 、T k,l and T u,l They represent the power transmission distribution coefficients of thermal power unit j, new energy unit k and power demand side u in branch l respectively; and They represent the upper and lower limits of power consumption on the power demand side, respectively. The power transmission distribution coefficient represents the change of power flow in each branch when the input power of a certain node changes. Carbon market constraints: The total amount of carbon quotas or emission reductions bought or sold in any time period is equal; the final total amount of carbon quotas of all thermal power units shall not exceed the total upper limit and shall not be less than 0; the carbon quotas or CCERs bought by thermal power units that buy carbon quotas or CCERs in any time period shall not exceed the upper limit and shall not be less than 0; the amount of carbon quotas sold by thermal power units that sell carbon quotas in any time period shall not exceed the upper limit and shall not be less than 0; the CCERs sold by new energy units in any time period shall not exceed the amount of CCERs converted from green certificates: Among them, Q cap Indicates the total upper limit of carbon quota; Indicates the purchase of carbon quota or emission reduction limit of thermal power unit j; represents the upper limit of carbon quota sold by thermal power unit j; Green certificate market constraints: The total amount of green certificates purchased by all thermal power units is equal to the total amount of green certificates sold by all new energy units. The amount of green certificates purchased by thermal power units in any time period shall not exceed the upper limit and shall not be less than 0; the amount of green certificates sold by new energy units in any time period shall not exceed the upper limit and shall not be less than 0; the sum of the amount of green certificates sold by new energy units and the amount of green certificates converted into emission reductions shall not exceed the initial amount of green certificates: in, It indicates the upper limit of the amount of green certificates purchased by thermal power unit j; Indicates the upper limit of green certificates sold by new energy unit k.
6. The electricity-carbon-green certificate market joint clearing method according to claim 5 is characterized in that: According to the joint clearing constraints and the joint clearing target model, MATLAB's Yalmip toolbox and Gurobi solver are used to solve the problem, and finally the joint clearing result is obtained. The electricity market adopts the calculation method of the node marginal electricity price, and the carbon market and green certificate market adopt the marginal price.
7. The electricity-carbon-green certificate market joint clearing method according to claim 6 is characterized in that: The power clearing target model is as follows: Among them, S e represents the total social welfare of the electricity market; It represents the power consumption of power demand side u in time period t when the power system is cleared separately; represents the power generation of thermal power unit j in time period t when the power system is cleared separately; It represents the power generation of the new energy unit k in time period t when the power system is cleared separately.
8. The electricity-carbon-green certificate market joint clearing method according to claim 7 is characterized in that: The S4 also includes a separate clearing constraint, which is specifically as follows: in, and They represent the upper and lower limits of power generation of thermal power unit j respectively; represents the predicted power generation value of the new energy unit k in time period t; P l,max represents the upper limit of power flow in branch l of the power system, P l,t represents the power flow of power system branch l in time period t, l represents the branch number of the power system, and L represents the set of all branches of the power system; T j,l 、T k,l and T u,l They represent the power transmission distribution coefficients of thermal power unit j, new energy unit k and power demand side u in branch l respectively; and They respectively represent the upper and lower limits of electricity consumption on the electricity demand side.
9. The electricity-carbon-green certificate market joint clearing method according to claim 8 is characterized in that: According to the individual clearing constraints and the power clearing target model, the Yalmip toolbox and Gurobi solver of MATLAB are used to solve the planning problem and obtain the clearing results.
10. The electricity-carbon-green certificate market joint clearing method according to claim 9 is characterized in that: The evaluation model is as follows: Among them, ρ1 represents the carbon emission reduction effect index; σ j represents the carbon emission intensity of thermal power unit j; represents the power generation of thermal power unit j in time period t, Δt is the single clearing interval time, represents the power generation of thermal power unit j in time period t when the power system is cleared separately; ρ2 represents the new energy consumption index, represents the power generation of the new energy unit k in time period t, represents the power generation of the new energy unit k in time period t when the power system is cleared separately; ρ3 represents the price transmission index, α LMP-average represents the average node marginal electricity price for the joint clearing of the electricity-carbon-green certificate market, α LMP-e-average Represents the average nodal marginal electricity price for individual clearing of the electricity market.
Citation Information
Cited By
Power system dispatching optimization operation method and system considering source-load interaction
CN119651773A
Time-sharing green evidence value equivalent dynamic evaluation method and system
CN121745490A
Electricity-carbon-green three market coupling collaborative optimization method for solving repeated accounting
CN122115017A