Variable cross-section pipe joint floating steering system and implementation method
Through the method of combining the water flow velocity control of steel bogies and steering rudders, the problems of floating direction and track control of variable-section pipe sections are solved, and the safe and stable floating transportation and transportation efficiency of the pipe sections are achieved.
Patent Information
- Application Number
- CN202410952335.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-16
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2044-07-16
AI Technical Summary
The existing sinking pipe floating transport device is difficult to effectively control the floating direction of the variable-section pipe section and avoid obstacles, resulting in complex operation, low efficiency and difficulty in achieving precise track control, which cannot meet the floating transport needs of the variable-section pipe section.
The method of using a steel bogie and a steering rudder combined with water flow velocity control is used to complete the steering through the torque generated by the distance between the water flow force and the center of gravity on the steering rudder, and the rotation angle is adjusted through the algorithm to ensure the safe and stable steering and precise track control of the pipe section.
It has achieved stable and safe floating of variable-section pipe sections, reduced channel width requirements, reduced channel dredging work, improved transportation efficiency, and reduced soil and water damage and transportation costs.
Smart Images

Figure CN118895783A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of variable-section pipe segment floating transportation, in particular to a variable-section pipe segment floating transportation steering system and a realization method. Background Art
[0002] Immersed tube tunnels have been increasingly widely used due to their short connection distance, low requirements on foundation bearing capacity, and high cross-section utilization. As a key process in the construction of immersed tube tunnels, the floating of immersed tubes is not only related to the structure of the tube section itself, but also affected by many factors such as meteorology, hydrology, waterways, and water facilities. The floating of tube sections is a process with high risks and difficulty coefficients in the construction of immersed tube tunnels.
[0003] Pipe sections are usually floated by tying barges around the pipe sections, and then assisted by push boats or tugboats. The floating method is controlled by many factors such as channel conditions, floating distance, hydrology and meteorology. There are mainly two construction schemes: (1) tugboat floating scheme (2) winch towing and tugboat pushing scheme.
[0004] Due to the limitations of the waterway and the huge size and weight of the pipe section, the pipe section is difficult to operate and has a lag in operation. When transporting tunnel pipe sections, it is difficult to float, change direction and avoid obstacles.
[0005] According to literature research, the existing submerged tube floating devices are large in size and complex to operate, making floating difficult in complex waters. At the same time, it is difficult to control the floating trajectory, which seriously affects the efficiency and convenience of pipe section floating.
[0006] CN 114319440 A discloses a method for floating and installing an inland river immersed tube. The method includes: winching the immersed tube to be floated and installed out of the dock; assembling a floating installation barge; winching the floating installation barge to straddle the immersed tube and connect it; filling the floating body with water, and applying a pre-tightening force to the hanging point so that the buoyancy box presses the top surface of the immersed tube, winching the floating installation barge to float the immersed tube to the installation position; draining the water in the floating body, pressurizing the immersed tube with water until its negative buoyancy reaches a predetermined value, and then the buoyancy box enters the water to provide buoyancy; then sinking the immersed tube for docking and installation. It can be found that the application does not solve the floating direction change problem of the variable cross-section pipe section, and does not carry out targeted solutions to the problems of turning and avoiding obstacles during floating, and it is impossible to control the floating cloud trajectory of the pipe section during floating.
[0007] CN 216549278 U discloses a floating device for a submerged tube, which lifts the submerged tube through a series combination lifting design, thereby reducing the requirement for water depth of the channel for submerged tube transportation, and at the same time reducing the navigation height required for submerged tube transportation. When encountering transportation conditions with insufficient water depth of the channel or limited height of the bridge hole, it can greatly reduce water and soil damage and increase in transportation costs. It can be found that: this application only solves the water depth requirement during floating transportation, and does not consider the problem of turning and avoiding obstacles during floating transportation.
[0008] In summary, the current pipe section floating devices have few preset scenarios for the direction change and track of variable cross-section pipe sections, and the existing devices have difficulties in avoiding obstacles, delayed steering effect, large space required for changing direction, and difficulty in controlling the steering angle. Therefore, it is difficult to use and achieve the desired effect in actual engineering. There is a lack of a floating device specifically for variable cross-section pipe sections that is easy to control, easy to implement, and simple to operate. Therefore, in order to solve the above-mentioned floating problem of variable cross-section pipe sections, a variable cross-section pipe section floating steering system and implementation method are proposed. Summary of the invention
[0009] The purpose of the present invention is to provide a variable-section pipe segment floating steering system and an implementation method, which controls the floating steering in combination with the water flow speed; the steering is completed by the large torque generated by the water flow force on the steering rudder and the long distance from the center of gravity. The steel bogie is sufficient to resist the water flow force when the pipe segment rotates, and can ensure the safety and stability of the pipe segment rotation; ensure the stability of the submerged tube floating.
[0010] The present invention is achieved through the following technical solutions:
[0011] A variable-section pipe segment floating and steering system, the variable-section pipe segment floating and steering system comprising a steel bogie, a steering rudder, a steering rudder control device, a water speed tester and a remote control end; the steel bogie is arranged at the rear of the variable-section pipe segment; the steering rudder is arranged at the lower part of the steel bogie through a steering rudder connector; the steering rudder control device is transmission-connected to the steering rudder through a belt drive device; the remote control end is communicatively connected to the steering rudder control device; when the variable-section pipe segment is floating and needs to be turned, the steering rudder angle and the rotational bending moment acting on the center point of the structure at the angle are calculated by the remote control end in combination with the water flow speed detected by the water speed tester to achieve the required steering angle, so that the variable-section pipe segment completes the turning.
[0012] As a further improvement of the technical solution of the present invention, the steel bogie is provided with fixing holes; the steel bogie is installed on the variable-section pipe segment by bolts engaging with the fixing holes.
[0013] As a further improvement of the technical solution of the present invention, the steel bogie is symmetrically arranged along the central axis of the variable-section pipe segment.
[0014] As a further improvement of the technical solution of the present invention, a wheel disc with a rotating shaft is reserved on the steel bogie, and the rotating shaft is connected to the steering rudder by bolts.
[0015] As a further improvement of the technical solution of the present invention, the steering rudder is kept parallel to the forward direction under normal conditions, and the turning moment during rotation = water flow resistance × distance from the steering rudder to the center of gravity, water flow resistance = 0.5ρAC s v 2 .
[0016] As a further improvement of the technical solution of the present invention, the water speed tester is welded to the bottom of the steel bogie through a steel plate.
[0017] As a further improvement of the technical solution of the present invention, the steering rudder control device is installed under the rear steel bogie, connected by bolts, and disassembled after floating is completed.
[0018] As a further improvement of the technical solution of the present invention, the steering rudder control device has a built-in motor, which is connected to the rotating shaft through a belt, and an algorithm is used to adjust the rotation angle.
[0019] As a further improvement of the technical solution of the present invention, the water speed tester is connected to the signal of the steering rudder control device, so that the steering of the variable cross-section pipe section is controlled in combination with the water speed.
[0020] As a further improvement of the technical solution of the present invention, a method for implementing a variable cross-section pipe segment floating steering system comprises the following steps:
[0021] Step S1: prefabrication of variable cross-section pipe segments;
[0022] Step S2: The steel bogie at the rear of the variable cross-section pipe segment is connected;
[0023] Step S3: Connecting the steering rudder connector;
[0024] Step S4: Steering rudder connection;
[0025] Step S5: installing the steering rudder control device;
[0026] Step S6: floating the variable cross-section pipe segment;
[0027] Step S7: during the floating process, the steering rudder control device is turned on to adjust the steering speed and direction when necessary;
[0028] Step S8: Floating is completed.
[0029] Compared with the prior art, the present invention has the following technical advantages:
[0030] The present invention controls the floating direction in combination with the water flow speed; the steering is completed by the large torque generated by the water flow force on the steering rudder and the long distance from the center of gravity. The steel bogie is sufficient to resist the water flow force when the pipe section is rotated, and can ensure the safety and stability of the pipe section rotation; ensure the stability of the submerged tube floating; the present invention adopts an algorithm to adjust the rotation angle, and can accurately control the track; reduce the requirements of the submerged tube transportation on the channel width, reduce or avoid the channel dredging work required for the submerged tube transportation, and speed up the overall work efficiency; the present invention can reduce water and soil damage and reduce transportation costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] Figure 1 It is a structural schematic diagram of installing a steel bogie and a steering rudder respectively on a variable cross-section pipe segment according to an embodiment of the present invention;
[0032] Figure 2 This is a schematic diagram of the overall structure of a variable cross-section pipe segment floating steering system according to an embodiment of the present invention;
[0033] Figure 3 The figure is a schematic diagram of signal connection between the steering rudder control device and the remote control terminal according to an embodiment of the present invention.
[0034] The numbers in the figure are:
[0035] 1-variable cross-section pipe section; 2-steel bogie; 3-fixing hole; 4-steering rudder; 5-steering rudder control device; 6-belt transmission device; 7-steering rudder connector; 8-remote control terminal. DETAILED DESCRIPTION
[0036] The present invention will be described in detail below in conjunction with the accompanying drawings and specific embodiments. The exemplary embodiments and descriptions of the present invention are used to explain the present invention, but are not intended to limit the present invention.
[0037] It should be noted that all directional indications in the embodiments of the present invention (such as up, down, left, right, front, back, upper end, lower end, top, bottom...) are only used to explain the relative position relationship, movement status, etc. between the components in a certain specific posture (as shown in the accompanying drawings). If the specific posture changes, the directional indication will also change accordingly.
[0038] In the present invention, unless otherwise clearly defined and limited, the term "connection" should be understood in a broad sense, for example, "connection" can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0039] In addition, in the present invention, the descriptions of "first", "second", etc. are only used for descriptive purposes and cannot be understood as indicating or implying their relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features; in addition, the technical solutions between the various embodiments can be combined with each other, but they must be based on the ability of ordinary technicians in the field to implement them. When the combination of technical solutions is contradictory or cannot be implemented, it should be considered that such a combination of technical solutions does not exist and is not within the scope of protection required by the present invention.
[0040] The present invention is further described in detail below in conjunction with the accompanying drawings.
[0041] like Figures 1 to 3 As shown, a variable cross-section pipe segment floating steering system, the variable cross-section pipe segment floating steering system includes a steel bogie 2, a steering rudder 4, a steering rudder control device 5, a water speed tester and a remote control terminal 8; the steel bogie 2 is arranged at the rear of the variable cross-section pipe segment 1; the steering rudder 4 is arranged at the lower part of the steel bogie 2 through a steering rudder connector 7; the steering rudder control device 5 is transmission-connected to the steering rudder 4 through a belt drive device 6; the remote control terminal 8 is communicatively connected to the steering rudder control device 5; when the variable cross-section pipe segment 1 is floating, when it is necessary to turn, the steering rudder angle and the rotational bending moment acting on the center point of the structure at the angle are calculated by the remote control terminal 8 in combination with the water flow speed detected by the water speed tester to achieve the required steering angle. It should be noted that the rotational bending moment must first resist the resistance of the water to start rotating, which is the condition for starting rotation. The increase in this force thereafter is a means of adjusting the track curve, which can be understood as making a large circle turn or a small circle turn. This is the calculation of the steering rudder angle, which is the angle between the horizontal movement speed and the normal operating speed. The horizontal movement speed is provided by the torque, which can be calculated according to the directional kinetic energy and momentum theorem, and the normal operating speed is obtained according to the actual situation. That is, for an object moving forward at a uniform speed, a horizontal torque is provided to provide the horizontal speed, and the rotation angle is the arctan forward length / horizontal movement length per unit time; so that the variable cross-section pipe section 1 completes the steering. The present invention combines the water flow speed to control the floating direction; the steering is completed by the large torque generated by the water flow force on the steering rudder 4 and the long distance from the center of gravity. The steel bogie 2 is sufficient to resist the water flow force when the pipe section rotates, which can ensure the safety and stability of the pipe section rotation; ensure the stability of the submerged pipe floating.
[0042] Specifically, in the present embodiment, the steel bogie 2 is provided with fixing holes 3; the steel bogie 2 is installed on the variable-section pipe segment 1 by bolts engaging with the fixing holes 3.
[0043] Specifically, in this embodiment, the steel bogie 2 is symmetrically arranged along the central axis of the variable-section pipe segment 1.
[0044] Specifically, in the present embodiment, a wheel disc with a rotating shaft is reserved on the steel bogie 2, and the rotating shaft is connected to the steering rudder 4 by bolts.
[0045] Specifically, in this embodiment, the steering rudder 4 is kept parallel to the forward direction under normal conditions, and the turning moment during rotation = water flow resistance × distance from the steering rudder to the center of gravity, water flow resistance = 0.5ρAC s v 2 .
[0046] Specifically, in this embodiment, the water speed tester is welded to the bottom of the steel bogie 2 through a steel plate.
[0047] Specifically, in the present embodiment, the steering rudder control device 5 is installed below the rear steel bogie 2 and connected by bolts, and is disassembled after the floating transportation is completed.
[0048] Specifically, in the present embodiment, the steering rudder control device 5 has a built-in motor, which is connected to the rotating shaft through a belt, and an algorithm is used to adjust the rotation angle. It should be noted that, as described above, controlling the steering angle requires controlling the rotation torque, so the rotation torque requires the component force of the water flow resistance to the steering rudder, so the algorithm must combine the above required steering angle to obtain the required rotation torque, and then obtain the component force of the water flow resistance to the steering rudder and the distance between the component force and the center of gravity, the value of which is related to the steering rudder rotation angle, because the angle determines the vertical component force of the water flow resistance on the steering rudder and the distance between the force and the center of gravity; the present invention uses an algorithm to adjust the rotation angle, which can accurately control the track; reduce the requirements of the immersed tube transportation on the channel width, reduce or avoid the channel dredging work required during the immersed tube transportation, and speed up the overall work efficiency; the present invention can reduce water and soil damage and reduce transportation costs.
[0049] Specifically, in the present embodiment, the water speed tester is connected to the steering rudder control device 5 by signal, so that the steering of the variable cross-section pipe section 1 is controlled in combination with the water speed. It should be noted that after the water speed tester detects the water flow speed, the detected water speed data is sent to the steering rudder control device 5 by wireless communication, and the steering rudder control device 5 controls the floating direction in combination with the water flow speed; the steering is completed by the large torque generated by the water flow force on the steering rudder and the long distance from the center of gravity.
[0050] Specifically, in this embodiment, a method for implementing a variable cross-section pipe segment floating steering system includes the following steps:
[0051] Step S1: prefabricate the variable cross-section pipe segment 1;
[0052] Step S2: the steel bogie 2 at the rear of the variable cross-section pipe segment 1 is connected;
[0053] Step S3: the steering rudder connector 7 is connected;
[0054] Step S4: the steering rudder 4 is connected;
[0055] Step S5: installing the steering rudder control device 5;
[0056] Step S6: the variable cross-section pipe segment 1 floats;
[0057] Step S7: during the floating process, the steering rudder control device 5 is turned on to adjust the steering speed and direction when necessary;
[0058] Step S8: Floating is completed.
[0059] Compared with the prior art, the present invention has the following beneficial effects:
[0060] The present invention controls the floating direction in combination with the water flow speed; the steering is completed by the large torque generated by the water flow force on the steering rudder and the long distance from the center of gravity. The steel bogie 2 is sufficient to resist the water flow force when the pipe section is rotated, and can ensure the safety and stability of the pipe section rotation; ensure the stability of the submerged tube floating; the present invention adopts an algorithm to adjust the rotation angle, and can accurately control the track; reduce the requirements of the submerged tube transportation on the channel width, reduce or avoid the channel dredging work required for the submerged tube transportation, and speed up the overall work efficiency; the present invention can reduce water and soil damage and reduce transportation costs.
[0061] The technical solutions provided by the embodiments of the present invention are introduced in detail above. Specific examples are used herein to illustrate the principles and implementation methods of the embodiments of the present invention. The description of the above embodiments is only applicable to help understand the principles of the embodiments of the present invention. At the same time, for those skilled in the art, according to the embodiments of the present invention, there will be changes in the specific implementation methods and application scopes. In summary, the content of this specification should not be understood as limiting the present invention.
Claims
1. A variable cross-section pipe segment floating steering system, characterized in that: The variable-section pipe segment floating steering system includes a steel bogie, a steering rudder, a steering rudder control device, a water speed tester and a remote control end; the steel bogie is arranged at the rear of the variable-section pipe segment; the steering rudder is arranged at the lower part of the steel bogie through a steering rudder connector; the steering rudder control device is transmission-connected to the steering rudder through a belt drive device; the remote control end is communicatively connected to the steering rudder control device; when the variable-section pipe segment is floating and needs to be turned, the steering rudder angle and the rotational bending moment acting on the center point of the structure at the angle are calculated through the remote control end in combination with the water flow speed detected by the water speed tester to achieve the required steering angle, so that the variable-section pipe segment completes the steering.
2. A variable cross-section pipe segment floating steering system according to claim 1, characterized in that: The steel bogie is provided with fixing holes; the steel bogie is installed on the variable-section pipe segment by bolts matching the fixing holes.
3. A variable cross-section pipe segment floating steering system according to claim 2, characterized in that: The steel bogie is symmetrically arranged along the central axis of the variable-section pipe segment.
4. The variable cross-section pipe segment floating steering system according to claim 1, characterized in that: A wheel disc with a rotating shaft is reserved on the steel bogie, and the rotating shaft is connected to the steering rudder through bolts.
5. The variable cross-section pipe segment floating steering system according to claim 1, characterized in that: The steering rudder is normally kept parallel to the forward direction. When turning, the turning moment = water flow resistance × the distance from the steering rudder to the center of gravity, water flow resistance = 0.5ρAC s v 2 .
6. The variable cross-section pipe segment floating steering system according to claim 1, characterized in that: The water speed tester is welded to the bottom of the steel bogie through a steel plate.
7. The variable cross-section pipe segment floating steering system according to claim 1, characterized in that: The steering rudder control device is installed under the rear steel bogie and connected by bolts, and is disassembled after floating is completed.
8. The variable cross-section pipe segment floating steering system according to claim 1, characterized in that: The steering rudder control device has a built-in motor, which is connected to the rotating shaft through a belt, and uses an algorithm to adjust the rotation angle.
9. The variable cross-section pipe segment floating steering system according to claim 1, characterized in that: The water speed tester is connected to the steering rudder control device signal so that the steering of the variable cross-section pipe section is controlled in combination with the water speed.
10. A method for implementing a variable cross-section pipe segment floating steering system, characterized in that: The following steps are involved: Step S1: prefabrication of variable cross-section pipe segments; Step S2: The steel bogie at the rear of the variable cross-section pipe segment is connected; Step S3: Connecting the steering rudder connector; Step S4: Steering rudder connection; Step S5: installing the steering rudder control device; Step S6: floating the variable cross-section pipe segment; Step S7: during the floating process, the steering rudder control device is turned on to adjust the steering speed and direction when necessary; Step S8: Floating is completed.
Citation Information
Patent Citations
Navigation velocity adjustment and steering control device of bamboo raft boat
CN110032104A
ROV with wall climbing function
CN111645831A
Boat fixing type stabilizing instrument
CN210592355U
Submarine
CN2799396Y
Ship and ship maneuvering method
JP2019014294A