Intelligent building construction management system and method based on BIM scene construction
By integrating multi-professional BIM models in the building construction management system, using conflict detection and genetic algorithms to optimize construction plans, and combining the Internet of Things to update data in real time, the problem of model conflicts and progress uncertainty during the construction process is solved, and the construction plan is achieved. Optimal execution and efficient resource allocation.
Patent Information
- Application Number
- CN202411456236.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-18
- Publication Date
- 2024-11-15
AI Technical Summary
The existing building construction management system is difficult to effectively coordinate conflicts and interference between multi-professional BIM models, resulting in overlapping processes, wasting resources and delays in progress during construction.
Using an intelligent construction management system based on BIM scenarios, integrating multi-professional models through the BIM model integration unit, using conflict detection algorithms and Quickhull algorithms to resolve model conflicts, and combining the three-dimensional BIM model with the time dimension through the construction progress management unit to build 4D BIM The model uses genetic algorithms to optimize construction plans, combines IoT devices to update dynamic data in real time, and uses fuzzy logic systems to generate the optimal construction plans.
Effectively identify and resolve conflicts between BIM models, optimize construction progress, reduce design errors and rework, ensure optimal implementation of construction plans, and avoid resource waste and construction period delays.
Smart Images

Figure CN118967070A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of building construction management, and in particular to an intelligent building construction management system and method based on BIM scenario construction. Background Art
[0002] The intelligent building construction management system and method based on BIM scenario construction aims to achieve efficient integrated management and precise construction progress control of construction projects. By utilizing the integrated management of BIM models and the construction plan adjustment of optimization algorithms, it controls resource allocation and task scheduling during the construction process, realizes visualization and intelligent management of the entire construction process, and improves the overall efficiency and quality of the project.
[0003] Existing construction management systems and methods are usually unable to effectively coordinate conflicts and interferences between multi-professional BIM models. In addition, due to the uncertainty of the progress of each task and the required resources during the construction process, problems such as overlapping processes, waste of resources and progress delays may occur during the construction process. Therefore, an intelligent construction management system and method based on BIM scenarios are provided. Summary of the invention
[0004] The purpose of the present invention is to provide an intelligent building construction management system and method based on BIM scenario construction, so as to solve the problems raised in the above background technology that the uncertainty of the progress of each task and the required resources in the construction process may lead to overlapping of processes, waste of resources and progress delays in the construction process.
[0005] To achieve the above objectives, the present invention provides an intelligent building construction management system based on BIM scenarios, including: A BIM model integration unit, wherein the BIM model integration unit is used to integrate and manage various professional BIM models in the entire construction project to build an overall BIM model; A construction progress management unit, which combines the three-dimensional BIM model with the time dimension to construct a 4D BIM model to dynamically simulate the construction process, optimizes the construction plan using a genetic algorithm, and updates the construction dynamic data in real time by integrating the BIM model with the Internet of Things devices, and generates an optimal construction plan using a fuzzy logic system and a task progress membership function; A quality management and detection unit, which is used to monitor and manage the project quality and construction specifications during the construction process; A safety risk control management unit is used to manage the safety and risk control of the construction site.
[0006] As a further improvement of the technical solution, the BIM model integration unit includes a model data integration module and a real-time data update and management module; The model data integration module is used to integrate BIM models, identify and resolve conflicts and interferences between BIM models using a conflict detection algorithm, and simplify the final BIM model using a Quickhull algorithm; Among them, the real-time data update and management module integrates the construction dynamic data into the final BIM model in real time through Internet of Things devices, sensors and real-time data acquisition tools.
[0007] As a further improvement of the technical solution, the model data integration module is used to integrate BIM models and use a conflict detection algorithm to identify and resolve conflicts and interferences between BIM models. The specific steps are as follows: S1.1, construct AABB axis-aligned bounding box; S1.2. Check whether the bounding boxes of two geometric AABBs overlap. The detection conditions are as follows: ; ; ; in, and For geometry 1 and geometry 2, The coordinate value of the minimum boundary of the AABB bounding box in the axis direction; and For geometry 1 and geometry 2, The coordinate value of the maximum boundary of the AABB bounding box in the axis direction; and For geometry 1 and geometry 2, The coordinate value of the minimum boundary of the AABB bounding box in the axis direction; and For geometry 1 and geometry 2, The coordinate value of the maximum boundary of the AABB bounding box in the axis direction; and For geometry 1 and geometry 2, The coordinate value of the minimum boundary of the AABB bounding box in the axis direction; and For geometry 1 and geometry 2, The coordinate value of the maximum boundary of the AABB bounding box in the axis direction; If the bounding boxes of the two geometric AABBs do not overlap in all three directions, there is no conflict between the two geometries; S1.3. If the bounding boxes of two geometric AABBs overlap in all three directions, use the separating axis theorem to further detect whether the two geometric AABBs actually intersect; S1.4. For each pair of polyhedrons, calculate the outer product of each face normal vector and each pair of edges as the separating axis; S1.5, project each vertex of the polyhedron onto each separating axis, and calculate the minimum and maximum projection values; If there is an axis that makes the projection intervals of the two polyhedrons not overlap, then the two polyhedrons have no conflict. If there is overlap on all axes, then the two polyhedrons conflict. The specific steps of using the Quickhull algorithm to simplify the final BIM model are as follows: S1.6. Select four non-coplanar points to form an initial tetrahedron; S1.7, classify the remaining points according to their exterior relative to the initial tetrahedron; S1.8. For each external point, find all faces visible to the external point and remove them, then reconstruct a new face to form an extended polyhedron.
[0008] As a further improvement of the technical solution, the construction progress management unit includes a construction simulation optimization module and a construction progress management module; The construction simulation optimization module combines the three-dimensional BIM model with the time dimension to construct a 4D BIM model to dynamically simulate the construction process, and uses a genetic algorithm to optimize the construction plan; The construction progress management module integrates the BIM model with the IoT devices to obtain the construction site status information in real time, update the construction dynamic data, and generate the optimal construction plan using the fuzzy logic system and the task progress membership function.
[0009] As a further improvement of this technical solution, the construction simulation optimization module combines the three-dimensional BIM model with the time dimension, constructs a 4D BIM technology to dynamically simulate the construction process, and uses a genetic algorithm to optimize the construction plan. The specific method is as follows: S2.1.1. Combine the 3D BIM model with the construction task schedule to form a 4D BIM model; S2.1.2. Set the start time of each task in the 4D BIM model and task end time ; S2.1.3. Constructing a resource demand matrix , set the minimum total construction period The mathematical expression is: ; in, A collection of all project tasks; express It belongs to all project tasks collection One of the tasks; S2.1.4. Establish task dependencies, resource constraints, task execution constraints, and time window constraints during the construction process; S2.1.5, Generate initial construction plan using heuristic methods; S2.1.6. Minimize the total construction period using genetic algorithms , generate the optimal construction plan and apply it to the 4DBIM model; The construction progress management module integrates the BIM model with the IoT device to obtain the construction site status information in real time, update the construction dynamic data, and generate the optimal construction plan using the fuzzy logic system and the task progress membership function. The specific steps are as follows: S2.2.1. Use IoT devices to obtain real-time construction site status information and update construction dynamic data in the 4D BIM model; S2.2.2. Update the progress status of each task based on construction dynamic data , Resource usage status ; S2.2.3. Define the task progress membership function The task progress status data and resource usage data are input into the fuzzy logic system and the task progress membership function is used Handle task schedule ambiguity and analyze construction dynamic data.
[0010] As a further improvement of this technical solution, in S2.1.4, task dependencies, resource constraints, task execution constraints and time window constraints in the construction process are established. The specific method is as follows: Task dependencies: ; Resource constraints: ; in, A collection of all available resources for the project; Representation Resources Is a collection of all available resources belonging to the project part of; For time; Task execution constraints: ; in, For specific moments in a construction project; Time window constraints: ; in, For the task The start time of For the task End time of For the task The set of pre-tasks; is the resource requirement matrix, representing the task During execution, resources Quantity of demand; is the total supply of resources; is the time step; is a binary variable, indicating the task Is it in time step conduct; For the task the earliest allowed start time; For the task The latest allowed start time.
[0011] As a further improvement of this technical solution, in S2.1.6, a genetic algorithm is used to minimize the total construction period , generate the optimal construction plan and apply it to the 4D BIM model. The specific method is as follows: S2.1.6.1. Define a population, including individuals, each of which represents a construction plan, generating A random initial construction plan; ; in, For the task The start time of S2.1.6.2. Calculate the end time of all tasks , and find the individual Total construction period , define the fitness function For individuals The inverse of the total duration: ; ; ; in, For the task duration of the project; For individuals Total construction period; All tasks that need to be completed in the project; is the total number of construction plan options; S2.1.6.3. Use the roulette wheel selection method to select individuals with higher fitness to enter the next generation, with a selection probability of : ; in, Represents an individual The fitness value of the individual With the task same; S2.1.6.4. Select individuals Initial construction plan and individual The initial construction plan is crossed, the start time of some tasks is exchanged, and individual Construction plan and individual Construction plan; ; ; ; ; in, For the task In the individual The start time in For the task In the individual The start time in is the intersection point; S2.1.6.5. Select individuals Tasks in the construction plan , randomly adjust the task Start time get ; ; in, For the task The new start time of is the random disturbance; S2.1.6.6. Repeat S2.1.6.2 to S2.1.6.5 until the maximum number of iterations is reached; S2.1.6.7. Select the minimum total duration in the final population The individual construction plan is taken as the optimal construction plan, and the optimal construction plan is applied to the 4D BIM model; ; in, For the optimal individual construction plan.
[0012] As a further improvement of the technical solution, the quality management detection unit includes a quality detection module and an abnormality detection and analysis module; The quality inspection module monitors the construction quality in real time by comparing it with the actual construction data and using the BIM model and on-site data detection; The anomaly detection and analysis module is used to collect and analyze quality data during the construction process and detect anomalies using statistical analysis methods.
[0013] As a further improvement of the present technical solution, the security risk control management unit includes a security monitoring and early warning module and a risk assessment and prevention module; Among them, the real-time monitoring technology of the safety monitoring and early warning module continuously monitors various safety parameters at the construction site and issues early warnings for safety risks; The risk assessment and prevention module is used to assess the safety risks during the construction process and formulate corresponding safety precautions based on the results of the risk assessment.
[0014] On the other hand, the present invention provides an intelligent building construction management method based on BIM scenario construction, which is used in any one of the intelligent building construction management systems based on BIM scenario construction described above, and comprises the following steps: S1. Integrate the BIM models of architecture, structure, and electromechanical disciplines to build an overall BIM model; S2. Combine the 3D BIM model with the time dimension to build a 4D BIM model, dynamically simulate the construction process, use genetic algorithms to optimize the construction plan, and integrate the BIM model with IoT devices to update the construction dynamic data in real time, and use the fuzzy logic system and task progress membership function to generate the optimal construction plan; S3. Monitor and manage the project quality and construction specifications during the construction process; S4. Manage construction site safety and risk control.
[0015] Compared with the prior art, the present invention has the following beneficial effects: 1. In the intelligent construction management system and method based on BIM scenario construction, conflict detection algorithm, AABB axis-aligned bounding box and separating axis theorem are used, and Quickhull algorithm is used to simplify complex models, identify and resolve conflicts and interferences between BIM models of different disciplines, reduce design errors and construction rework caused by model conflicts, and ensure the coordination and consistency of various disciplines in the construction project.
[0016] 2. In the intelligent building construction management system and method based on BIM scenario construction, by combining the three-dimensional BIM model with the time dimension, constructing a 4D BIM model and using genetic algorithm to optimize the construction progress, dynamic simulation and real-time optimization of the construction process are achieved, providing visual management of construction tasks, accurate resource allocation and progress adjustment, ensuring the optimal execution of the construction plan, and avoiding resource waste and construction delays caused by improper planning. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 It is the overall flow chart of the present invention; The meaning of each number in the figure is: 1. BIM model integration unit; 2. Construction progress management unit; 3. Quality management and inspection unit; 4. Safety risk control management unit. DETAILED DESCRIPTION
[0018] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0019] Embodiment 1: See also Figure 1 As shown in the figure, an intelligent building construction management system based on BIM scenarios is provided, including: A BIM model integration unit 1, wherein the BIM model integration unit 1 is used to integrate and manage various professional BIM models in the entire construction project to construct an overall BIM model; In this embodiment, the BIM model integration unit 1 includes a model data integration module and a real-time data update and management module; Among them, the model data integration module is used to integrate BIM models, use conflict detection algorithms to identify and resolve conflicts and interferences between BIM models, and use the Quickhull algorithm to simplify the final BIM model; Among them, the real-time data update and management module integrates construction dynamic data into the final BIM model in real time through IoT devices, sensors and real-time data collection tools.
[0020] In this embodiment, the model data integration module is used to integrate BIM models and use a conflict detection algorithm to identify and resolve conflicts and interferences between BIM models. The specific steps are as follows: S1.1, construct AABB axis-aligned bounding box; The steps to construct AABB are to determine a minimum cuboid bounding box based on the vertex coordinates of the three-dimensional geometry. The cuboid is aligned with the coordinate axis and completely contains the given geometry. The boundary of AABB is determined by the minimum and maximum values of the geometry in each axis direction. The specific steps are as follows: For a 3D geometric body, first you need to get all its vertex coordinates; calculate the minimum and maximum boundaries of the AABB; the minimum boundary point of the AABB is the minimum coordinate value of the geometric body on each coordinate axis; the maximum boundary point of the AABB is the maximum coordinate value of the geometric body on each coordinate axis; construct the AABB axis-aligned bounding box; S1.2. Check whether the bounding boxes of two geometric AABBs overlap. The detection conditions are as follows: ; ; ; in, and For geometry 1 and geometry 2, The coordinate value of the minimum boundary of the AABB bounding box in the axis direction; and For geometry 1 and geometry 2, The coordinate value of the maximum boundary of the AABB bounding box in the axis direction; and For geometry 1 and geometry 2, The coordinate value of the minimum boundary of the AABB bounding box in the axis direction; and For geometry 1 and geometry 2, The coordinate value of the maximum boundary of the AABB bounding box in the axis direction; and For geometry 1 and geometry 2, The coordinate value of the minimum boundary of the AABB bounding box in the axis direction; and For geometry 1 and geometry 2, The coordinate value of the maximum boundary of the AABB bounding box in the axis direction; If the bounding boxes of the two geometric AABBs do not overlap in all three directions, there is no conflict between the two geometries; S1.3. If the bounding boxes of two geometric AABBs overlap in all three directions, use the separating axis theorem to further detect whether the two geometric AABBs actually intersect; S1.4. For each pair of polyhedrons, calculate the outer product of each face normal vector and each pair of edges as the separating axis; S1.5, project each vertex of the polyhedron onto each separating axis, and calculate the minimum and maximum projection values; If there is an axis that makes the projection intervals of the two polyhedrons not overlap, then the two polyhedrons have no conflict. If there is overlap on all axes, then the two polyhedrons conflict. The specific steps of using the Quickhull algorithm to simplify the final BIM model are as follows: S1.6. Select four non-coplanar points to form an initial tetrahedron; S1.7, classify the remaining points according to their exterior relative to the initial tetrahedron; S1.8. For each external point, find all faces visible to the external point and remove them, then reconstruct a new face to form an extended polyhedron.
[0021] In the context of intelligent building construction management based on BIM scenarios, the Quickhull algorithm is used to simplify BIM models. The purpose of this simplification is to improve calculation and processing efficiency by reducing the complexity of the geometry while maintaining the shape and structural integrity of the model.
[0022] It also includes a construction progress management unit 2, which combines the three-dimensional BIM model with the time dimension to build a 4D BIM model to dynamically simulate the construction process, optimize the construction plan using a genetic algorithm, and update the construction dynamic data in real time by integrating the BIM model with the Internet of Things equipment, and generate an optimal construction plan using a fuzzy logic system and a task progress membership function; In this embodiment, the construction progress management unit 2 includes a construction simulation optimization module and a construction progress management module; The construction simulation optimization module combines the three-dimensional BIM model with the time dimension to construct a 4D BIM model to dynamically simulate the construction process, and uses a genetic algorithm to optimize the construction plan. Through visualization, the sequence, time arrangement and resource allocation of each construction task are intuitively displayed; The use of genetic algorithms for construction plan optimization can handle complex multi-objective optimization problems and multiple constraints, provide global optimal solutions, adapt to large-scale and dynamically changing construction environments, and does not rely on good initial solutions; The construction progress management module integrates the BIM model with the IoT devices to obtain the construction site status information in real time, update the construction dynamic data, and generate the optimal construction plan using the fuzzy logic system and the task progress membership function.
[0023] In this embodiment, the construction simulation optimization module combines the three-dimensional BIM model with the time dimension to construct a 4D BIM technology to dynamically simulate the construction process, and uses a genetic algorithm to optimize the construction plan. The specific method is as follows: S2.1.1. Combine the 3D BIM model with the construction task schedule to form a 4D BIM model; S2.1.2. Set the start time of each task in the 4D BIM model and task end time ; Through visualization tools, the execution order of construction tasks, resource usage and possible task conflicts are intuitively displayed; S2.1.3. Constructing a resource demand matrix , set the minimum total construction period The mathematical expression is: ; in, A collection of all project tasks; express It belongs to all project tasks collection One of the tasks; S2.1.4. Establish task dependencies, resource constraints, task execution constraints, and time window constraints during the construction process; S2.1.5, Generate initial construction plan using heuristic methods; Heuristic methods are algorithms or rules used to quickly solve complex problems. They use domain knowledge of the problem and some approximate or empirical rules to generate preliminary solutions without guaranteeing the optimality of the solution. The advantage of heuristic methods is that they are fast in calculation and can generate a feasible solution in a short time. They are suitable for generating initial solutions for large-scale and complex problems. Heuristic methods for generating initial construction plans refer to the use of heuristic algorithms or rules to quickly generate a preliminary construction plan in complex construction projects. This plan is based on empirical rules or domain knowledge rather than precise calculations, which provides a starting point for the genetic algorithm to converge to the optimal solution more quickly; The main advantage of using heuristic methods to generate initial construction plans is that it can quickly provide a feasible initial solution, reasonably arrange the order of construction tasks and resource allocation, thereby significantly shortening the optimization calculation time and improving the convergence speed and efficiency of genetic algorithms. The initial plan generated by the heuristic method has high quality, reduces unnecessary trial and error processes, provides a good starting point for the subsequent optimization process, and further improves the overall optimization effect of the construction plan.
[0024] S2.1.6. Minimize the total construction period using genetic algorithms , generate the optimal construction plan and apply it to the 4DBIM model; In this embodiment, the construction progress management module integrates the BIM model and the IoT device to obtain the construction site status information in real time, update the construction dynamic data, and generate the optimal construction plan using the fuzzy logic system and the task progress membership function. The specific steps are as follows: S2.2.1. Use IoT devices to obtain real-time construction site status information and update construction dynamic data in the 4D BIM model; S2.2.2. Update the progress status of each task based on construction dynamic data , Resource usage status ; S2.2.3. Define the task progress membership function The task progress status data and resource usage data are input into the fuzzy logic system and the task progress membership function is used Handle task schedule ambiguity and analyze construction dynamic data.
[0025] In this embodiment S2.1.4, task dependencies, resource constraints, task execution constraints and time window constraints in the construction process are established. The specific method is as follows: Task dependencies: ; Resource constraints: ; in, A collection of all available resources for the project; Representation Resources Is a collection of all available resources belonging to the project part of; For time; Task execution constraints: ; in, For specific moments in a construction project; Time window constraints: ; in, For the task The start time of For the task End time of For the task The set of pre-tasks; is the resource requirement matrix, representing the task During execution, resources Quantity of demand; is the total supply of resources; is the time step; is a binary variable, indicating the task Is it in time step conduct; For the task the earliest allowed start time; For the task The latest allowed start time.
[0026] In this embodiment S2.1.6, a genetic algorithm is used to minimize the total construction period , generate the optimal construction plan and apply it to the 4D BIM model. The specific method is as follows: S2.1.6.1. Define a population, including individuals, each of which represents a construction plan, generating A random initial construction plan; ; in, For the task The start time of S2.1.6.2. Calculate the end time of all tasks , and find the individual Total construction period , define the fitness function For individuals The inverse of the total duration: ; ; ; in, For the task duration of the project; For individuals Total construction period; All tasks that need to be completed in the project; is the total number of construction plan options; The value of the fitness function is calculated based on the total duration of each individual. Since the optimization goal is to minimize the total duration, the fitness function is defined as the inverse of the total duration; S2.1.6.3. Use the roulette wheel selection method to select individuals with higher fitness to enter the next generation, with a selection probability of : ; in, Represents an individual The fitness value of the individual With the task same; The roulette wheel selection method is a probability-based selection strategy used in genetic algorithms to select individuals with higher fitness to enter the next generation. The fitness values of all individuals are standardized into a probability distribution, and then the selection probability of each individual is assigned according to the size of the fitness value. The higher the fitness of an individual, the greater the corresponding probability of selection, just as the larger the area occupied on a roulette wheel, the higher the probability of being selected.
[0027] In the context of intelligent building construction management based on BIM scenarios, the use of the roulette wheel selection method helps to maintain population diversity, while tending to retain individuals with high fitness, effectively accelerating convergence to the global optimal solution and avoiding premature convergence to the local optimal solution.
[0028] S2.1.6.4. Select individuals Initial construction plan and individual The initial construction plan is crossed, the start time of some tasks is exchanged, and individual Construction plan and individual Construction plan; ; ; ; ; in, For the task In the individual The start time in For the task In the individual The start time in is the intersection point; S2.1.6.5. Select individuals Tasks in the construction plan , randomly adjust the task Start time get ; ; in, For the task The new start time of is the random disturbance; S2.1.6.6. Repeat S2.1.6.2 to S2.1.6.5 until the maximum number of iterations is reached; S2.1.6.7. Select the minimum total duration in the final population The individual construction plan is taken as the optimal construction plan, and the optimal construction plan is applied to the 4D BIM model; ; in, For the optimal individual construction plan.
[0029] It also includes a quality management detection unit 3, which is used to monitor and manage the project quality and construction specifications during the construction process; In this embodiment, the quality management detection unit 3 includes a quality detection module and an abnormality detection and analysis module; The quality inspection module monitors the construction quality in real time by comparing it with the actual construction data and using the BIM model and on-site data detection; The anomaly detection and analysis module is used to collect and analyze quality data during the construction process and detect anomalies using statistical analysis methods.
[0030] Statistical analysis methods usually include mean and standard deviation analysis, control chart method, regression analysis and time series analysis, etc. By analyzing the quality data of the construction process, such as material strength, dimensional deviation, construction temperature and other quality data, abnormal conditions with large deviations from the expected quality standards can be detected; In this embodiment, the control chart method can be used to monitor quality indicators in real time and identify abnormal data points that exceed the control limits; mean and standard deviation analysis can detect deviation trends that do not meet quality standards; It also includes a safety risk control management unit 4, which is used to manage the safety and risk control of the construction site; In this embodiment, the security risk control management unit 4 includes a security monitoring and early warning module and a risk assessment and prevention module; Among them, the real-time monitoring technology of the safety monitoring and early warning module continuously monitors various safety parameters at the construction site and issues early warnings for safety risks; The risk assessment and prevention module is used to assess the safety risks during the construction process and formulate corresponding safety precautions based on the results of the risk assessment.
[0031] Embodiment 2: The difference between Example 2 of the present invention and Example 1 is that this example introduces the static mechanical properties collection and analysis method used by the intelligent building construction management system built based on the BIM scenario.
[0032] The intelligent building construction management method based on BIM scenario construction is used for any of the above-mentioned intelligent building construction management systems based on BIM scenario construction, and comprises the following steps: S1. Integrate the BIM models of architecture, structure, and electromechanical to build an overall BIM model; S2. Combine the 3D BIM model with the time dimension to build a 4D BIM model, dynamically simulate the construction process, use genetic algorithms to optimize the construction plan, and integrate the BIM model with IoT devices to update the construction dynamic data in real time, and use the fuzzy logic system and task progress membership function to generate the optimal construction plan; S3. Monitor and manage the project quality and construction specifications during the construction process; S4. Manage construction site safety and risk control.
[0033] The above shows and describes the basic principles, main features and advantages of the present invention. Those skilled in the art should understand that the present invention is not limited by the above embodiments, and the above embodiments and descriptions are only preferred examples of the present invention, and are not intended to limit the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, and these changes and improvements all fall within the scope of the present invention to be protected.
Claims
1. Intelligent building construction management system based on BIM scenario, It is characterized in that include: A BIM model integration unit (1), wherein the BIM model integration unit (1) is used to integrate and manage multiple professional BIM models in the entire building project to construct an overall BIM model; A construction progress management unit (2), wherein the construction progress management unit (2) combines the three-dimensional BIM model with the time dimension to construct a 4D BIM model to dynamically simulate the construction process, optimize the construction plan using a genetic algorithm, and update the construction dynamic data in real time by integrating the BIM model with an Internet of Things device, and generate an optimal construction plan using a fuzzy logic system and a task progress membership function; A quality management and detection unit (3), the quality management and detection unit (3) is used to monitor and manage the project quality and construction specifications during the construction process; A safety risk control management unit (4), wherein the safety risk control management unit (4) is used to manage the safety and risk control of a construction site.
2. According to the intelligent building construction management system based on BIM scenario construction according to claim 1, Features: The BIM model integration unit (1) comprises a model data integration module and a real-time data updating and management module; The model data integration module is used to integrate BIM models, identify and resolve conflicts and interferences between BIM models using a conflict detection algorithm, and simplify the final BIM model using a Quickhull algorithm; Among them, the real-time data update and management module integrates the construction dynamic data into the final BIM model in real time through Internet of Things devices, sensors and real-time data acquisition tools.
3. According to the intelligent building construction management system based on BIM scenario construction according to claim 2, Features: The model data integration module is used to integrate BIM models and use conflict detection algorithms to identify and resolve conflicts and interferences between BIM models. The specific steps are as follows: S1.1, construct AABB axis-aligned bounding box; S1.
2. Check whether the bounding boxes of two geometric bodies AABB overlap. The detection conditions are as follows: ; ; ; in, and For geometry 1 and geometry 2 The coordinate value of the minimum boundary of the AABB bounding box in the axis direction; and For geometry 1 and geometry 2 The coordinate value of the maximum boundary of the AABB bounding box in the axis direction; and For geometry 1 and geometry 2 The coordinate value of the minimum boundary of the AABB bounding box in the axis direction; and For geometry 1 and geometry 2 The coordinate value of the maximum boundary of the AABB bounding box in the axis direction; and For geometry 1 and geometry 2 The coordinate value of the minimum boundary of the AABB bounding box in the axis direction; and For geometry 1 and geometry 2 The coordinate value of the maximum boundary of the AABB bounding box in the axis direction; If the bounding boxes of the two geometric AABBs do not overlap in all three directions, there is no conflict between the two geometries; S1.
3. If the bounding boxes of two geometric AABBs overlap in all three directions, use the separating axis theorem to further detect whether the two geometric AABBs actually intersect; S1.
4. For each pair of polyhedrons, calculate the outer product of each face normal vector and each pair of edges as the separating axis; S1.5, project each vertex of the polyhedron onto each separating axis, and calculate the minimum and maximum projection values; If there is an axis that makes the projection intervals of the two polyhedrons not overlap, then the two polyhedrons have no conflict. If there is overlap on all axes, then the two polyhedrons conflict. The specific steps of using the Quickhull algorithm to simplify the final BIM model are as follows: S1.
6. Select four non-coplanar points to form an initial tetrahedron; S1.7, classify the remaining points according to their exterior relative to the initial tetrahedron; S1.
8. For each external point, find all faces visible to the external point and remove them, then reconstruct a new face to form an extended polyhedron.
4. According to claim 1, the intelligent building construction management system based on BIM scenario construction, Features: The construction progress management unit (2) comprises a construction simulation optimization module and a construction progress management module; The construction simulation optimization module combines the three-dimensional BIM model with the time dimension to construct a 4D BIM model to dynamically simulate the construction process, and uses a genetic algorithm to optimize the construction plan; The construction progress management module integrates the BIM model with the IoT devices to obtain the construction site status information in real time, update the construction dynamic data, and generate the optimal construction plan using the fuzzy logic system and the task progress membership function.
5. According to the intelligent building construction management system based on BIM scenario construction according to claim 4, Features: The construction simulation optimization module combines the three-dimensional BIM model with the time dimension, constructs a 4D BIM technology to dynamically simulate the construction process, and uses a genetic algorithm to optimize the construction plan. The specific method is as follows: S2.1.
1. Combine the 3D BIM model with the construction task schedule to form a 4D BIM model; S2.1.
2. Set the start time of each task in the 4D BIM model and task end time ; S2.1.
3. Constructing a resource demand matrix , set the minimum total construction period The mathematical expression is: ; in, A collection of all project tasks; express It belongs to all project tasks collection One of the tasks; S2.1.
4. Establish task dependencies, resource constraints, task execution constraints, and time window constraints during the construction process; S2.1.5, Generate initial construction plan using heuristic methods; S2.1.
6. Minimize the total construction period using genetic algorithms , generate the optimal construction plan and apply it to the 4D BIM model; The construction progress management module integrates the BIM model with the IoT device to obtain the construction site status information in real time, update the construction dynamic data, and generate the optimal construction plan using the fuzzy logic system and the task progress membership function. The specific steps are as follows: S2.2.
1. Use IoT devices to obtain real-time construction site status information and update construction dynamic data in the 4D BIM model; S2.2.
2. Update the progress status of each task based on construction dynamic data , Resource usage status ; S2.2.
3. Define the task progress membership function The task progress status data and resource usage data are input into the fuzzy logic system and the task progress membership function is used Handle task schedule ambiguity and analyze construction dynamic data.
6. According to claim 5, the intelligent building construction management system based on BIM scenario construction, Features: In S2.1.4, the task dependencies, resource constraints, task execution constraints and time window constraints in the construction process are established. The specific method is as follows: Task dependencies: ; Resource constraints: ; in, A collection of all available resources for the project; Representation Resources Is a collection of all available resources belonging to the project part of; For time; Task execution constraints: ; in, For specific moments in a construction project; Time window constraints: ; in, For the task The start time of For the task End time of For the task The set of pre-tasks; is the resource requirement matrix, representing the task During execution, resources Quantity of demand; is the total supply of resources; is the time step; is a binary variable, indicating the task Is it in time step conduct; For the task the earliest allowed start time; For the task The latest allowed start time.
7. The intelligent building construction management system based on BIM scenario construction according to claim 6, Features: In S2.1.6, the genetic algorithm is used to minimize the total construction period , generate the optimal construction plan and apply it to the 4D BIM model. The specific method is as follows: S2.1.6.
1. Define a population, including individuals, each of which represents a construction plan, generating A random initial construction plan; ; in, For the task The start time of S2.1.6.
2. Calculate the end time of all tasks , and find the individual Total construction period , define the fitness function For individuals The inverse of the total duration: ; ; ; in, For the task duration of the project; For individuals Total construction period; All tasks that need to be completed in the project; is the total number of construction plan options; The value of the fitness function is calculated based on the total duration of each individual. Since the optimization goal is to minimize the total duration, the fitness function is defined as the inverse of the total duration; S2.1.6.
3. Use the roulette wheel selection method to select individuals with higher fitness to enter the next generation, with a selection probability of : ; in, Represents an individual The fitness value of the individual With the task same; S2.1.6.
4. Select individuals Initial construction plan and individual The initial construction plan is crossed, the start time of some tasks is exchanged, and individual Construction plan and individual Construction plan; ; ; ; ; in, For the task In the individual The start time in For the task In the individual The start time in is the intersection point; S2.1.6.
5. Select individuals Tasks in the construction plan , randomly adjust the task Start time get ; ; in, For the task The new start time of is the random disturbance; S2.1.6.
6. Repeat S2.1.6.2 to S2.1.6.5 until the maximum number of iterations is reached; S2.1.6.
7. Select the minimum total duration in the final population The individual construction plan is taken as the optimal construction plan, and the optimal construction plan is applied to the 4D BIM model; ; in, For the optimal individual construction plan.
8. The intelligent building construction management system based on BIM scenario construction according to claim 1, Features: The quality management detection unit (3) comprises a quality detection module and an abnormality detection and analysis module; The quality inspection module monitors the construction quality in real time by comparing it with the actual construction data and using the BIM model and on-site data detection; The anomaly detection and analysis module is used to collect and analyze quality data during the construction process and detect anomalies using statistical analysis methods.
9. The intelligent building construction management system based on BIM scenario construction according to claim 1, Features: The security risk control management unit (4) includes a security monitoring and early warning module and a risk assessment and prevention module; Among them, the real-time monitoring technology of the safety monitoring and early warning module continuously monitors various safety parameters at the construction site and issues early warnings for safety risks; The risk assessment and prevention module is used to assess the safety risks during the construction process and formulate corresponding safety precautions based on the results of the risk assessment.
10. An intelligent building construction management method based on BIM scenario construction, used in an intelligent building construction management system based on BIM scenario construction as claimed in any one of claims 1 to 9, It is characterized in that The following steps are involved: S10.
1. Integrate the BIM models of architecture, structure, and electromechanical disciplines to build an overall BIM model; S10.
2. Combine the three-dimensional BIM model with the time dimension to build a 4D BIM model, dynamically simulate the construction process, use genetic algorithms to optimize the construction plan, and integrate the BIM model with IoT devices to update the construction dynamic data in real time, and use the fuzzy logic system and task progress membership function to generate the optimal construction plan; S10.
3. Monitor and manage the project quality and construction specifications during the construction process; S10.
4. Manage construction site safety and risk control.
Citation Information
Patent Citations
Special-shaped steel structure parameterization design construction method based on BIM technology
CN111625890A
Horizontal dimension airspace conflict detection method
CN113781846A
Comprehensive pipeline space-time analysis and risk estimation method based on 4D-BIM technology
CN114418330A
Multi-type collision detection method and system of BIM lightweight model
CN116305386A
Bridge construction organization method based on three-dimensional digital technology
CN116596483A
Cited By
Building modeling design method and system based on BIM model
CN119227211A
Building construction data acquisition method and system based on BIM model
CN119988400A
Architectural design monitoring management system and method based on AR assistance
CN120724529A
Electromechanical engineering resource allocation method and system based on spatial coupling degree
CN120851559A
Thermal power building engineering construction optimization method based on BIM (Building Information Modeling) technology
CN122634728A