Multi-layer cantilever plate buckle formwork erecting method
By combining BIM technology and high-precision measurement equipment with finite element analysis, the problems of insufficient accuracy and safety in traditional formwork methods for multi-story cantilever structures have been solved, achieving efficient and safe formwork construction.
Patent Information
- Application Number
- CN202411109870.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-14
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2044-08-14
AI Technical Summary
Traditional formwork methods are difficult to accurately grasp complex spatial geometric relationships, meet load-bearing capacity and stability requirements, improve construction efficiency and accuracy, achieve elevation control, and lack systematicity and repeatability in the construction of multi-story cantilever structures.
A 3D model was created using Building Information Modeling (BIM) technology. Combined with high-precision surveying equipment such as total stations and GPS-RTK, finite element analysis and optimization algorithms were used for support design and stress analysis. An adjustable support system was introduced, and zonal optimization and pre-stressing tests were implemented to ensure the accurate erection and stability of the support.
It improved the accuracy of formwork positioning and construction efficiency, enhanced the load-bearing capacity and stability of the support, achieved millimeter-level elevation control, reduced construction costs, and improved construction quality and safety.
Smart Images

Figure CN118997462A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of building construction, and in particular relates to a multi-layer cantilevered disc buckle formwork method. Background Art
[0002] With the rapid development of modern construction industry, building structures are becoming increasingly complex and diversified, especially the widespread application of multi-layer cantilever structures, which has brought great challenges to construction. Multi-layer cantilever structures have been increasingly widely used in urban high-rise buildings and large public buildings due to their unique spatial effects and functional advantages. This structure can not only increase the usable area of the building, but also create a unique architectural appearance, adding new vitality to the modern urban landscape.
[0003] However, the construction of multi-story cantilever structures, especially the construction of formwork systems, has always been a difficult and important point in building construction. Traditional formwork methods often seem to be inadequate when facing multi-story cantilever structures. The main problems are as follows:
[0004] First, it is difficult for traditional formwork methods to accurately grasp complex spatial geometric relationships. Multi-story cantilever structures usually have complex three-dimensional spatial forms. Traditional two-dimensional drawings and manual measurement methods are difficult to accurately express and control such complex spatial relationships, resulting in inaccurate formwork positioning and affecting subsequent construction quality.
[0005] Secondly, the load-bearing capacity and stability of traditional formwork methods are difficult to meet the requirements of multi-story cantilever structures. Cantilever structures place higher demands on the load-bearing capacity and rigidity of the formwork system. Traditional wooden or simple steel pipe formwork systems often cannot meet these requirements and are prone to deformation or instability, posing safety hazards.
[0006] Thirdly, the traditional formwork method has low construction efficiency and is highly dependent on manual labor. In complex multi-story cantilever structures, the traditional formwork method requires a lot of manual measurement, adjustment, and correction, which is not only time-consuming and labor-intensive, but also prone to cumulative errors, affecting the overall construction quality.
[0007] In addition, it is difficult to achieve precise elevation control with traditional formwork methods. In a multi-story cantilever structure, the elevation control of each floor directly affects the geometry and mechanical properties of the overall structure, and it is difficult to achieve millimeter-level precise control with traditional methods.
[0008] Finally, the traditional formwork method lacks systematicity and repeatability. Each construction requires the formwork system to be redesigned and rebuilt, making it difficult to form a standardized and modular construction plan, increasing construction costs and management difficulties.
[0009] Faced with these problems, the construction field urgently needs a new formwork method that can make full use of modern technology to improve the accuracy, efficiency and safety of formwork to meet the special needs of multi-story cantilever structure construction. Summary of the invention
[0010] In view of this, the present invention provides a multi-layer cantilevered disc-buckle formwork method, which can solve the technical problems of the existing multi-layer cantilevered disc-buckle formwork method having insufficient accuracy and safety.
[0011] The present invention is achieved in that:
[0012] The present invention provides a multi-layer cantilevered plate buckle formwork method, which comprises the following steps:
[0013] S10. Create a 3D model of the multi-story cantilever structure using BIM software based on the architectural design drawings;
[0014] S20, obtaining the data for erecting the buckle bracket through the BIM model, and dividing the area where the bracket needs to be erected into several partitions;
[0015] S30, lay out each partition and use a total station and level to determine the position and elevation of the poles;
[0016] S40. A return rod is set up at the bottom of the side span beam and the cantilever beam as the dividing line between the inner and outer frames;
[0017] S50. Set up the buckle bracket layer by layer from bottom to top, and set the vertical and horizontal spacing of the vertical poles and the horizontal pole pitch according to the design requirements;
[0018] S60. Install an adjustable bracket on the top of the bracket and adjust the height to be lower than the designed height;
[0019] S70, install the crossbar and diagonal tie rod, and hammer the latch firmly with a hand-held hammer;
[0020] S80. Carry out pre-compression test on the erected support, using steel bars or sandbags to load graded loads to 110% of the design load;
[0021] S90. After the bracket is pre-pressed and qualified, install the template and check the elevation and flatness to ensure that it meets the design requirements.
[0022] Wherein, the step S10 specifically includes:
[0023] Step 101: Collect and organize architectural design drawings, including floor plans, elevations, sections, and structural drawings;
[0024] Step 102, select building information modeling software and set the correct unit system and coordinate system;
[0025] Step 103: Draw the main components of the building structure layer by layer according to the drawing information, including at least columns, beams, slabs, and walls;
[0026] Step 104, add secondary components, including at least doors, windows, and stairs, to complete the model;
[0027] Step 105, check and correct geometric errors and component conflicts in the model;
[0028] Step 106: Add material information and component properties to the model;
[0029] Step 107: Conduct a comprehensive check on the completed building information model to ensure accuracy and completeness.
[0030] Furthermore, the step S20 specifically includes:
[0031] Step 201: extracting the area information where the support needs to be erected from the building information model, including the plane range and height;
[0032] Step 202: using a spatial clustering algorithm to preliminarily divide the support erection area;
[0033] Step 203: Considering the construction convenience and safety, manually adjust and optimize the preliminary division results;
[0034] Step 204: Use a minimum spanning tree algorithm to determine the optimal connection relationship between the partitions;
[0035] Step 205: Apply a linear programming method to establish an optimization model with the goal of minimizing the total construction time;
[0036] Step 206: Use the Monte Carlo simulation method to simulate different partitioning schemes multiple times to evaluate their impact on construction progress and cost;
[0037] Step 207: According to the simulation results, the optimal partitioning scheme is selected, and the partitioning results are visualized in the building information model using geographic information system technology.
[0038] Furthermore, the step S30 specifically includes:
[0039] Step 301: Determine the coordinates of the boundary points of each partition according to the building information model and the partition scheme;
[0040] Step 302: Use a total station to set up a control network at the construction site, including at least 4 control points, with the distance between the control points being no less than 30 meters;
[0041] Step 303: Use the real-time dynamic technology of the global positioning system to determine the precise coordinates of the control point;
[0042] Step 304, using the least squares adjustment algorithm, the control network is adjusted to improve the accuracy of the control network;
[0043] Step 305: Locate the partition boundary points based on the control network using the polar coordinate method or the forward intersection method;
[0044] Step 306: Use the layout function of the total station to determine the plane position of each pole, and the layout accuracy is controlled within plus or minus 5 mm;
[0045] Step 307: Use the elevation measurement function of a level or total station to determine the elevation of each pole, with the elevation accuracy controlled within plus or minus 3 mm.
[0046] Furthermore, the step S40 specifically includes:
[0047] Step 401: Determine the precise position and elevation of the side span beam and the cantilever beam according to the building information model;
[0048] Step 402, select a suitable material for the return pin, with a diameter of not less than 48 mm and a wall thickness of not less than 3.5 mm;
[0049] Step 403, calculating the stress of the return rod, including axial pressure and bending moment, to ensure that its strength and rigidity meet the requirements;
[0050] Step 404: Use finite element analysis software to perform stress analysis and deformation analysis on the return rod;
[0051] Step 405: According to the analysis result, determine that the return rod is located on the center line of the bottom of the beam;
[0052] Step 406, using a laser level, projecting a horizontal reference line along the bottom of the beam;
[0053] Step 407: Set a fixed point every 3 to 5 meters on the baseline and fix it with expansion bolts or chemical anchors.
[0054] Furthermore, the step S50 specifically includes:
[0055] Step 501: Determine the exact position and spacing of the poles according to the design drawings and the building information model;
[0056] Step 502: Use a precision level to measure and record the ground elevation to provide a reference for subsequent height adjustment;
[0057] Step 503: Lay a wooden board with a thickness of not less than 30 mm or a concrete pad with a thickness of 40 mm on the ground to distribute the load;
[0058] Step 504, installing the adjustable base, adjusting the exposed length of the screw to not exceed 300 mm;
[0059] Step 505: Use a theodolite or a total station to ensure the verticality of the first layer of poles, with a deviation of no more than 5 / 1000;
[0060] Step 506, adopting the order of erecting the vertical poles first, then the horizontal poles, and finally the scissors braces;
[0061] Step 507: Use the disc-type bracket system to ensure that each connection point is properly locked and the locking torque reaches 40 Nm to 60 Nm.
[0062] Furthermore, the step S60 specifically includes:
[0063] Step 601: Determine the theoretical position and elevation of each bracket according to the building information model and the structural design drawings;
[0064] Step 602: Select a suitable adjustable bracket, whose bearing capacity is not less than 1.2 times of the design load;
[0065] Step 603: Use a total station or a level to measure the actual elevation of the top of the support;
[0066] Step 604: Calculate the height of each bracket that needs to be adjusted, and reserve 20 mm to 30 mm of space for subsequent precise adjustment;
[0067] Step 605: When installing the adjustable bracket, use anti-skid pads to increase friction and improve stability;
[0068] Step 606: Use a torque wrench to tighten the bracket fixing bolts according to design requirements, with the torque reaching 80 Nm to 120 Nm;
[0069] Step 607: Use a high-precision digital level to adjust the height of the bracket so that it is in a horizontal state, with an allowable error of no more than 1 mm per meter.
[0070] Furthermore, the step S70 specifically includes:
[0071] Step 701: Determine the installation position and angle of the crossbar and the diagonal brace according to the design drawings and the building information model;
[0072] Step 702, select the crossbar and diagonal rod of appropriate specifications, and use the steel pipe with a diameter of 48.3 mm and a wall thickness of 3.5 mm;
[0073] Step 703: Use a laser rangefinder to accurately measure the positions where the crossbars and diagonal braces need to be installed;
[0074] Step 704: When installing the crossbar, use a level to ensure its levelness, with an allowable error of no more than 2 mm per meter;
[0075] Step 705: For the inclined rod, use an inclinometer to measure its inclination angle to ensure that the deviation from the design angle does not exceed 1 degree;
[0076] Step 706: Use mechanical analysis software to simulate and analyze the stress conditions of the crossbar and the diagonal brace;
[0077] Step 707: Optimize the arrangement of the crossbars and the diagonal braces according to the analysis results, and add reinforcement components if necessary.
[0078] Furthermore, the step S80 specifically includes:
[0079] Step 801, setting three-level loading weights, the sum of which is 1.1 times the design load;
[0080] Step 802, ensuring that the weight ratio of the three-level loading is 6:4:1;
[0081] Step 803, determining the single-stage minimum and maximum loading weights according to the preloading equipment capacity and safety restrictions;
[0082] Step 804: Optimize the load weight distribution using numerical simulation and structural analysis methods;
[0083] Step 805, perform first level loading to reach 60% of the design load;
[0084] Step 806, performing second level loading to reach 100% of the design load;
[0085] Step 807, perform the third level loading to reach 110% of the design load;
[0086] Step 808: During each loading process, use a precision level to monitor the settlement of the bracket to ensure that the settlement does not exceed 5 mm.
[0087] Furthermore, the step S90 specifically includes:
[0088] Step 901: Determine the installation position and size of the template according to the building information model and the structural design drawings;
[0089] Step 902: Select appropriate template material to ensure that its strength, rigidity and surface flatness meet the design requirements;
[0090] Step 903: Use a total station or a level to recheck the top of the bracket to ensure that its elevation and plane position meet the design requirements;
[0091] Step 904: When installing the template, use a level and a ruler to ensure the flatness of the template, with an allowable error of no more than 3 mm per 3 meters;
[0092] Step 905: Use sealing tape or caulking material at the template joints to prevent slurry leakage;
[0093] Step 906: After installation is completed, use a total station to scan and measure the template surface to generate elevation point cloud data;
[0094] Step 907: Compare and analyze the measurement data with the building information model to ensure that the template installation accuracy meets the design requirements;
[0095] Step 908: Adjust the parts that do not meet the requirements until they meet the design standards.
[0096] Compared with the prior art, the multi-layer cantilevered plate buckle formwork method provided by the present invention has the following beneficial effects:
[0097] First, the present invention uses Building Information Modeling (BIM) technology to create a three-dimensional model of a multi-layer cantilever structure, accurately grasping the complex spatial geometric relationship. This not only improves the accuracy of formwork positioning, but also provides a reliable data basis for subsequent support design and construction simulation, greatly reducing design errors and construction conflicts.
[0098] Secondly, the present invention introduces advanced computer-aided engineering technologies, such as finite element analysis and mechanical simulation, to conduct a comprehensive force analysis and optimization design of the support system. This ensures that the formwork system has sufficient bearing capacity and stability, can meet the special requirements of multi-story cantilever structures, and significantly improves construction safety.
[0099] Thirdly, the present invention uses high-precision measurement technologies such as total station and GPS-RTK, combined with the least squares adjustment algorithm, to achieve precise control of the support erection. This not only improves construction efficiency and reduces manual dependence, but also significantly improves the geometric accuracy of the formwork, laying a good foundation for subsequent structural construction.
[0100] In addition, the present invention introduces an adjustable bracket system and uses a high-precision digital level for adjustment, achieving millimeter-level elevation control. This solves the problem that the traditional method is difficult to accurately control the elevation in multi-story cantilever structures, ensuring that the geometric shape and force performance of the overall structure meet the design requirements.
[0101] Finally, the present invention proposes a set of systematic and standardized formwork methods, including a series of links such as zoning optimization, support erection, and preload test. This method has strong repeatability and adaptability, which not only improves construction efficiency and reduces construction costs, but also provides reliable technical support for quality management and safety control.
[0102] Compared with the prior art, the present invention has made significant progress in the following aspects:
[0103] 1. Precision control: Through BIM technology and high-precision measuring equipment, the formwork accuracy is improved to the millimeter level, far exceeding the centimeter-level accuracy of traditional methods.
[0104] 2. Safety performance: Computer-aided analysis and optimized design are used to improve the safety factor of the formwork system.
[0105] In summary, the multi-layer cantilevered disc-buckle formwork method proposed in the present invention solves the technical problems of the existing multi-layer cantilevered disc-buckle formwork methods that are insufficient in accuracy and safety. BRIEF DESCRIPTION OF THE DRAWINGS
[0106] Figure 1 is a flow chart of the method of the present invention. DETAILED DESCRIPTION
[0107] In order to make the purpose, technical solution and advantages of the embodiments of the present invention more clear, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention.
[0108] like Figure 1 As shown, it is a flow chart of a multi-layer cantilevered plate buckle formwork method provided by the present invention, and the method comprises the following steps:
[0109] S10. Create a 3D model of the multi-story cantilever structure using BIM software based on the architectural design drawings;
[0110] S20, obtaining the data for erecting the buckle bracket through the BIM model, and dividing the area where the bracket needs to be erected into several partitions;
[0111] S30, lay out each partition and use a total station and level to determine the position and elevation of the poles;
[0112] S40. A return rod is set up at the bottom of the side span beam and the cantilever beam as the dividing line between the inner and outer frames;
[0113] S50. Set up the buckle bracket layer by layer from bottom to top, and set the vertical and horizontal spacing of the vertical poles and the horizontal pole pitch according to the design requirements;
[0114] S60. Install an adjustable bracket on the top of the bracket and adjust the height to be lower than the designed height;
[0115] S70, install the crossbar and diagonal tie rod, and hammer the latch firmly with a hand-held hammer;
[0116] S80. Carry out pre-compression test on the erected support, using steel bars or sandbags to load graded loads to 110% of the design load;
[0117] S90. After the bracket is pre-pressed and qualified, install the template and check the elevation and flatness to ensure that it meets the design requirements.
[0118] The specific implementation methods of the above steps are described in detail below:
[0119] The specific implementation method of step S10 is: first, according to the architectural design drawings, use the building information model (BIM) software to create a three-dimensional model of the multi-layer cantilever structure. The purpose of this step is to provide accurate geometric information and spatial relationships for the subsequent support design and construction. The specific implementation process includes: collecting and organizing architectural design drawings, including floor plans, elevations, sections and structural drawings; selecting appropriate BIM software, such as Autodesk Revit, Bentley AECOsim BuildingDesigner or Graphisoft ArchiCAD; creating a project file in the BIM software and setting the correct unit system and coordinate system; drawing the building structure layer by layer according to the drawing information, including main components such as columns, beams, plates, and walls; paying special attention to the details of the cantilever structure, such as the location, size and connection method of the cantilever beam; adding secondary components such as doors, windows, and stairs to improve the model; checking and correcting geometric errors and component conflicts in the model; adding material information and component properties to the model for subsequent analysis and use; finally, conducting a comprehensive inspection of the completed BIM model to ensure its accuracy and completeness. In this process, parametric modeling technology is used, which allows designers to quickly modify and update models by changing parameters, improving modeling efficiency and flexibility. At the same time, the principle of object-relational model (ORM) is adopted to enable intelligent associations between various components in the model. When one component changes, other related components will also be adjusted accordingly, ensuring the consistency and accuracy of the model.
[0120] The specific implementation of step S20 is: obtain the data of the erection of the buckle bracket through the BIM model, and divide the area where the bracket needs to be erected into several partitions. The purpose of this step is to reasonably divide the construction area and improve the construction efficiency and management level. The specific implementation process includes: extracting the area information where scaffolding needs to be erected from the BIM model, including the plane range and height; using spatial clustering algorithms, such as K-means clustering or DBSCAN (density-based spatial clustering with applied noise) algorithm, to preliminarily divide the scaffolding erection area; considering the convenience and safety of construction, manually adjusting and optimizing the preliminary division results; using the minimum spanning tree algorithm in graph theory, such as Kruskal algorithm or Prim algorithm, to determine the optimal connection relationship between each partition, so as to plan the construction sequence and material transportation route; applying linear programming methods to establish an optimization model with the goal of minimizing the total construction time, considering constraints such as labor resources, equipment resources and material supply, and solving the optimal zoning scheme; using the Monte Carlo simulation method to simulate different zoning schemes multiple times to evaluate their impact on construction progress and cost; selecting the optimal zoning scheme based on the simulation results, and using GIS (geographic information system) technology to visualize the zoning results in the BIM model. In this process, the application of spatial clustering algorithm helped to preliminarily divide the construction area, the minimum spanning tree algorithm optimized the connection relationship between the partitions, and the linear programming and Monte Carlo simulation methods helped to obtain the optimal partitioning scheme while considering multiple factors. The comprehensive application of these algorithms and methods ensured the scientificity and feasibility of the partitioning scheme.
[0121] The specific implementation method of step S30 is: lay out each partition, and use a total station and a level to determine the position and elevation of the poles. The purpose of this step is to provide accurate spatial positioning for the erection of the bracket. The specific implementation process includes: determining the coordinates of the boundary points of each partition according to the BIM model and the partition plan; using a total station to set up a control network at the construction site, including at least 4 control points, and the distance between the control points should not be less than 30 meters; using GPS-RTK (Global Positioning System - Real Time Kinematic) technology to determine the precise coordinates of the control points; using the least squares adjustment algorithm to adjust the control network to improve the accuracy of the control network; based on the control network, using the polar coordinate method or the forward intersection method to lay out the partition boundary points; using the layout function of the total station to determine the plane position of each pole, and the layout accuracy should be controlled within ±5 mm; using a level or The height measurement function of the total station determines the elevation of each pole, and the height accuracy should be controlled within ±3 mm; the principle of trigonometric height measurement is used to perform indirect height measurement of points at long distances or with obstructed sight; the least squares configuration method is used to optimize the measurement plan to obtain the highest measurement accuracy with the least number of measuring stations; the error propagation law is applied to analyze and control the cumulative error to ensure the overall line-setting accuracy; a digital level is used for closed leveling to check the accuracy of the height measurement; the coordinate setting-out function of the total station is used to review the line-setting to ensure that there are no major errors; finally, permanent markers such as steel nails or marking paint are used to mark the position of the pole and the elevation point. In this process, the application of GPS-RTK technology improves the accuracy of the control network, the least squares adjustment algorithm further optimizes the accuracy of the control network, the polar coordinate method and the forward intersection method ensure the accuracy of the setting-out, and the application of the error propagation law helps control the cumulative error. The comprehensive application of these measurement principles and methods ensures the high accuracy and reliability of the line-setting work.
[0122] The specific implementation method of step S40 is: set up a return rod at the bottom of the side span beam and the cantilever beam as the dividing line between the inner and outer frames. The purpose of this step is to clearly distinguish the inner and outer supports to facilitate construction management and force analysis. The specific implementation process includes: according to the BIM model, determine the precise position and elevation of the side span beam and the cantilever beam; select suitable return rod materials, usually Q235 steel, with a diameter of not less than 48 mm and a wall thickness of not less than 3.5 mm; calculate the force conditions of the return rod, including axial pressure and bending moment, to ensure that its strength and stiffness meet the requirements; use finite element analysis software, such as ANSYS or ABAQUS, to perform stress analysis and deformation analysis on the return rod; according to the analysis results, determine the best installation position of the return rod, which should usually be located on the center line of the bottom of the beam; use a laser level to project a horizontal reference line along the bottom of the beam; set a fixed point every 3 to 5 meters on the reference line, and the fixed point can use expansion bolts or chemical anchors; Use a theodolite or total station to ensure the verticality of the return rod, and the deviation should not exceed 3 / 1000; when installing the return rod, use adjustable connectors to accurately adjust its position; set hinged connections at both ends of the return rod to allow for slight angle adjustments; use a torque wrench to tighten all connecting bolts according to design requirements, and the torque should usually reach 100 Nm to 150 Nm; after installation, use a total station to check and measure to ensure that the position and verticality of the return rod meet the requirements; spray a striking identification color on the return rod, usually using yellow and black warning colors; set a sign on the return rod to clearly indicate its function and precautions; finally, record the installation process and quality inspection results of the return rod in detail in the construction log. In this process, the application of finite element analysis methods helped optimize the design and installation position of the return rod, the use of laser levels and total stations ensured the accuracy of installation, and the use of torque wrenches ensured the reliability of connections. The comprehensive use of these tools and methods ensures the accuracy and safety of the installation of the return rod.
[0123] The specific implementation of step S50 is: from bottom to top, the buckle bracket is set layer by layer, and the vertical and horizontal spacing of the vertical poles and the horizontal pole pitch are set according to the design requirements. The purpose of this step is to build a stable and safe support system. The specific implementation process includes: determine the exact position and spacing of the vertical poles according to the design drawings and BIM models; use a precision level to measure and record the ground elevation to provide a benchmark for subsequent height adjustments; lay wooden boards with a thickness of not less than 30 mm or 40 mm concrete pads on the ground to disperse the load; install an adjustable base, and the exposed length of the adjustment screw should not exceed 300 mm; use a theodolite or total station to ensure the verticality of the first layer of vertical poles, and the deviation should not exceed 5 / 1000; adopt the erection sequence of "vertical poles first, then horizontal poles, and then scissors braces"; use a disc-type bracket system to ensure that each connection point is correctly locked, and the locking torque should reach 40 Nm to 60 Nm; the horizontal pole spacing should not be greater than 1800 mm, and the inclination angle of the scissors brace diagonal pole to the ground should be between 45° and 60°; after each layer is erected, use a level or total station to The station instrument checks the elevation to ensure the level; the layered loading method is used for preloading, and the settlement is observed after each layer is loaded. The settlement should not exceed 5 mm; the laser rangefinder is used to regularly check the spacing between the poles to ensure that it meets the design requirements; during the construction process, the deformation of the bracket is monitored in real time, and optical fiber sensing technology can be used for continuous monitoring; finite element analysis software, such as MIDAS or SAP2000, is used to analyze the stability of the bracket as a whole; according to the analysis results, reinforcing rods are added at key nodes to improve the overall stiffness; a protective net is set up around the bracket, and the mesh size should not be greater than 30 mm × 30 mm; after each standard layer is erected, a comprehensive safety inspection is carried out, including the firmness of the connection and the integrity of the components; finally, a detailed construction record is compiled, including the erection process, quality inspection results, and abnormal situation handling. In this process, the use of precision levels and total stations ensures the accuracy of the bracket erection, the layered loading law helps control the settlement of the bracket, and the application of finite element analysis software enables the evaluation and optimization of the overall stability of the bracket. The comprehensive application of these technologies and methods ensures the safety and reliability of the buckle bracket erection.
[0124] The specific implementation of step S60 is: install an adjustable bracket on the top of the bracket, and adjust the height to be lower than the designed height. The purpose of this step is to provide accurate height control for subsequent template installation and concrete pouring. The specific implementation process includes: determining the theoretical position and elevation of each bracket according to the BIM model and structural design drawings; selecting a suitable adjustable bracket, whose bearing capacity should be no less than 1.2 times the design load; using a total station or level to measure the actual elevation of the top of the bracket; calculating the height that each bracket needs to be adjusted, usually reserving 20 mm to 30 mm of space for subsequent precise adjustment; when installing adjustable brackets, use anti-slip pads to increase friction and improve stability; using a torque wrench to tighten the bracket fixing bolts according to design requirements, usually the torque should reach 80 Nm to 120 Nm; using a high-precision digital level to adjust the height of the bracket so that it is in a horizontal state, with an allowable error of no more than 1 mm / m; for areas with larger spans, consider structural deformation and appropriately pre-arch, and the pre-arch height is usually 1 / 1000 to 1 / 800 of the span; using a laser leveler to check the flatness of large-area brackets to ensure that the height difference between adjacent brackets does not exceed 2mm; use a 3D coordinate measurement system, such as a total station or a 3D laser scanner, to obtain the precise spatial position of the bracket; use computer-aided analysis software, such as MATLAB or Python, to perform statistical analysis and error assessment on the measurement data; identify abnormal points based on the analysis results and make targeted adjustments; use hydraulic jacks during the adjustment process to ensure smooth and precise height control; install displacement sensors for key parts or large-span structures to monitor the settlement of the bracket in real time; use thermal imaging cameras to check whether there is stress concentration at the connection between the bracket and the bracket; after the bracket is installed, use a total station to conduct a review measurement to ensure that the height and plane position of all brackets meet the design requirements; prepare a detailed bracket installation record, including the number, position coordinates, elevation and adjustment amount of each bracket; finally, record the bracket installation process, quality inspection results and abnormal situation handling in the construction log. In this process, the use of total stations and levels ensures the high accuracy of bracket installation, the 3D coordinate measurement system provides more comprehensive spatial information, and the application of computer-aided analysis software helps to better understand and control errors. The combined use of these advanced tools and methods ensures the accuracy and reliability of the adjustable bracket installation.
[0125] The specific implementation method of step S70 is: install the crossbars and diagonal braces, and hammer the pins with a handheld hammer. The purpose of this step is to enhance the overall rigidity and stability of the bracket. The specific implementation process includes: determine the installation position and angle of the crossbars and diagonal braces according to the design drawings and BIM models; select crossbars and diagonal braces of appropriate specifications, usually using φ48.3×3.5 mm steel pipes; use a laser rangefinder to accurately measure the positions where the crossbars and diagonal braces need to be installed; before installation, check the integrity of all components to ensure that there are no defects such as deformation and cracks; when installing the crossbar, use a spirit level to ensure its levelness, with an allowable error of no more than 2 mm / m; for the diagonal braces, use an inclinometer to measure its inclination to ensure that it is consistent with the design angle. The deviation of the degree does not exceed 1°; use mechanical analysis software, such as ANSYS or ABAQUS, to simulate and analyze the stress conditions of the crossbar and the diagonal brace; optimize the layout of the crossbar and the diagonal brace according to the analysis results, and add reinforcement components when necessary; use high-strength bolts at the connection, and the bolt strength grade is not less than grade 8.8; use a torque wrench to tighten the bolts, and the torque value is usually 100 Nm to 150 Nm; for the pin connection, use a hand-held hammer of appropriate size, and the hammer head weight is usually 1 kg to 1.5 kg; when hammering the pin, use "three The "point method" is to hammer once at the top center and both sides of the bolt to ensure that the bolt is evenly stressed; use a dynamometer to check the tightening force of the bolt, which should usually reach 5 kN to 8 kN; after installation, use an endoscope to check the internal condition of the connection to ensure that there are no hidden dangers; use acoustic wave detection technology, such as ultrasonic flaw detection, to check the welding quality of key connection points; use strain gauges to install strain monitoring systems on key components to monitor the stress state of components in real time; for large spans or complex structures, consider using dampers or tuned mass dampers to improve the vibration resistance of the structure; during the construction process, regularly use infrared thermal imagers to check the connections to promptly detect abnormal stress concentration phenomena; after installation, conduct an overall load test, load to 1.1 times the design load, and observe the deformation of the structure; use a high-precision 3D laser scanner to obtain accurate geometric information of the bracket system and compare and analyze it with the BIM model; based on the analysis results, identify potential weak links and carry out targeted reinforcement; finally, compile detailed construction records, including the tightening condition of each connection point, test results and abnormal handling measures. In this process, the application of mechanical analysis software helped optimize the layout of crossbars and diagonal braces, while acoustic wave detection and strain monitoring technology provided more in-depth quality assurance, and 3D laser scanning technology enabled a comprehensive assessment of the geometric accuracy of the support system. The comprehensive application of these advanced technologies and methods ensured the accuracy, reliability and safety of the installation of crossbars and diagonal braces.
[0126] In the implementation of the above steps, multiple key thresholds and reference values are involved. The selection of these values is crucial to ensure construction quality and safety. The following are reference values for some important parameters:
[0127] 1. Control network setting: The distance between control points should not be less than 30 meters to ensure measurement accuracy and stability of the control network.
[0128] 2. Lofting accuracy: The plane position lofting accuracy should be controlled within ±5 mm, and the elevation accuracy should be controlled within ±3 mm. These accuracy requirements ensure the basic accuracy of the support erection.
[0129] 3. Specifications of return rod: usually made of Q235 steel, with a diameter of not less than 48 mm and a wall thickness of not less than 3.5 mm. These parameters ensure the strength and rigidity of the return rod.
[0130] 4. Verticality of the return rod: The deviation should not exceed 3 / 1000, which ensures the stability and uniformity of the force of the return rod.
[0131] 5. Connecting bolt torque: usually should reach 100 Nm to 150 Nm, which ensures the firmness of the connection.
[0132] 6. Verticality of the poles: The verticality deviation of the first layer of poles should not exceed 5 / 1000, which is the basis for ensuring the stability of the overall bracket.
[0133] 7. Horizontal bar spacing: should not be greater than 1800 mm, in order to ensure the overall rigidity of the bracket.
[0134] 8. Scissor support angle: The inclination angle with the ground should be between 45° and 60°. This angle range can provide the best lateral stability.
[0135] 9. Pre-compression settlement: should not exceed 5 mm. This threshold ensures the stability of the bracket under actual load.
[0136] 10. Specifications of protective net: The mesh size should not be larger than 30 mm × 30 mm, which can effectively prevent small objects from falling.
[0137] 11. Load-bearing capacity of adjustable bracket: should be no less than 1.2 times of the design load. This safety factor ensures the reliability of the bracket under extreme conditions.
[0138] 12. Bracket adjustment accuracy: The allowable error shall not exceed 1 mm / m. This accuracy requirement ensures the flatness of subsequent formwork installation and concrete pouring.
[0139] 13. Structural pre-arch: For areas with larger spans, the pre-arch height is usually 1 / 1000 to 1 / 800 of the span, which can effectively compensate for the deformation of the structure under load.
[0140] 14. Flatness of bracket: The height difference between adjacent brackets should not exceed 2 mm. This requirement ensures the flatness of the overall structure.
[0141] 15. Specifications of cross bars and diagonal braces: Usually φ48.3×3.5 mm steel pipes are used, which can provide sufficient strength and rigidity.
[0142] 16. Angle accuracy of the diagonal brace: The deviation from the design angle should not exceed 1°, which ensures that the diagonal brace can effectively play its supporting role.
[0143] 17. Connecting bolt grade: should not be lower than grade 8.8. This strength grade can ensure the reliability of the connection.
[0144] 18. Pin tightening force: Normally it should reach 5 kN to 8 kN. This force range ensures the stability of the pin connection.
[0145] 19. Overall load test: Load to 1.1 times of the design load. This overload factor can verify the reliability of the support system under extreme conditions.
[0146] The selection of these reference values and thresholds is based on many years of engineering practice experience and relevant specifications. In the actual construction process, appropriate adjustments and optimizations should be made based on these reference values according to the characteristics and requirements of the specific project. At the same time, the influence of environmental factors, material properties, construction technology and other aspects should also be considered to comprehensively determine the final control parameters. In addition, during the construction process, a complete quality monitoring system should be established to regularly check and verify these key parameters to ensure the safety and reliability of the entire formwork system.
[0147] In the implementation of the multi-layer cantilevered plate buckle formwork method, a variety of advanced technologies and methods were used. The application of these technologies and methods not only improved the construction efficiency, but more importantly, greatly improved the construction quality and safety. For example, the application of BIM technology runs through the entire process, from the initial 3D modeling to the subsequent support design and construction simulation. BIM technology provides accurate geometric information and spatial relationships, greatly reducing design errors and construction conflicts. The use of GPS-RTK technology and total station ensures high accuracy in measurement and layout, which is the basis for accurate support erection.
[0148] In terms of support design and optimization, computer-aided engineering technologies such as finite element analysis and mechanical simulation were used. These technologies helped to accurately predict the stress state and deformation characteristics of the support, thereby optimizing the support structure and improving its safety and economy. During the construction process, a variety of advanced monitoring technologies were used, such as fiber optic sensing, strain monitoring, and acoustic wave detection. These technologies enable real-time monitoring of the support's stress state and deformation, and timely detection and handling of potential risks.
[0149] In addition, some innovative construction methods were introduced, such as layered loading method and three-point hammering method, which effectively improved the construction quality and efficiency. In terms of quality control, advanced detection methods such as 3D laser scanning and infrared thermal imaging were used, which enabled a comprehensive and accurate assessment of the geometric accuracy and stress conditions of the support system.
[0150] The second specific implementation of the present invention is provided below. The difference from the first specific implementation is that steps S20, S50, S60, S80 and S90 all use mathematical calculations to limit specific data. The specific description is as follows:
[0151] The specific implementation of step S20 is: obtain the data of the erection of the bracket through the BIM model, and divide the area where the bracket needs to be erected into several partitions. The purpose of this step is to reasonably divide the construction area and improve the construction efficiency and management level. The specific implementation process includes:
[0152] Step 201. Extract the area information where the support needs to be erected from the BIM model, including the plane range and height.
[0153] Step 202. Set variables x1, x2, ..., x n Indicates the area of each partition.
[0154] Step 203. Establish a set of constraint equations:
[0155]
[0156] x i ≥x min ,i=1,2,...,n
[0157] x i ≤x max ,i=1,2,...,n
[0158] Step 204. Establish the objective function:
[0159]
[0160]
[0161] Step 205: Solve the constraint equations and the objective function to obtain the optimal partitioning solution.
[0162] In the formula, S is the total area; n is the number of partitions; x min is the minimum permissible partition area; x max is the maximum permissible zoning area; is the average partition area; α, β, γ, δ are weight coefficients.
[0163] The parameter acquisition method is:
[0164] S is obtained by measurement, including step 1: using a laser rangefinder to measure the length and width of the construction area; step 2: calculating S = length × width.
[0165] x min and x max Determined according to construction experience, usually x min Not less than 50 square meters, x max Not more than 200 square meters.
[0166] α, β, γ, and δ are obtained through optimization of multiple construction practices, and the initial values can be set as α=0.4, β=0.3, γ=0.2, and δ=0.1.
[0167] Step 206: Use a spatial clustering algorithm, such as K-means clustering or DBSCAN (density-based spatial clustering with applied noise) algorithm, to preliminarily divide the support erection area.
[0168] Step 207. Considering the construction convenience and safety, the preliminary division results are manually adjusted and optimized.
[0169] Step 208. Use the minimum spanning tree algorithm in graph theory, such as Kruskal algorithm or Prim algorithm, to determine the optimal connection relationship between the partitions in order to plan the construction sequence and material transportation route.
[0170] Step 209. Apply the linear programming method to establish an optimization model with the goal of minimizing the total construction time, consider the constraints such as labor resources, equipment resources and material supply, and solve the optimal zoning plan.
[0171] Step 210. Use the Monte Carlo simulation method to simulate different zoning schemes multiple times to evaluate their impact on construction progress and cost.
[0172] Step 211. According to the simulation results, the optimal zoning scheme is selected, and the zoning results are visualized in the BIM model using GIS (Geographic Information System) technology.
[0173] In this process, the application of spatial clustering algorithm helped to preliminarily divide the construction area, the minimum spanning tree algorithm optimized the connection relationship between the partitions, and the linear programming and Monte Carlo simulation methods helped to obtain the optimal partitioning scheme while considering multiple factors. The comprehensive application of these algorithms and methods ensured the scientificity and feasibility of the partitioning scheme.
[0174] The specific implementation of step S50 is: erect the buckle bracket layer by layer from bottom to top, and set the vertical and horizontal spacing of the vertical poles and the horizontal pole pitch according to the design requirements. The purpose of this step is to build a stable and safe support system. The specific implementation process includes:
[0175] Step 501. Determine the exact position and spacing of the vertical poles based on the design drawings and BIM model.
[0176] Step 502. Set variable d x and d y Respectively represent the longitudinal and transverse spacing of the poles.
[0177] Step 503. Establish constraint equations:
[0178] n x d x ≤L x
[0179] n y d y ≤L y
[0180] d x ≤d max
[0181] d y ≤d max
[0182]
[0183] Step 504. Establish the objective function:
[0184]
[0185] Step 505: Solve the constraint equations and the objective function to obtain the optimal pole spacing.
[0186] Where, L x and L y are the total lengths in the longitudinal and transverse directions respectively; n x and n y is an integer, indicating the number of longitudinal and transverse poles; d max is the maximum allowable spacing; d min is the minimum allowable spacing; λ1, λ2, λ3, λ4 are weight coefficients.
[0187] The parameter acquisition method is:
[0188] L x and L y The longitudinal and transverse lengths of the construction area were measured using a total station.
[0189] dmax and d min Determined according to the structural design specifications, usually d max Not more than 2 meters, d min Not less than 0.6 meters.
[0190] λ1, λ2, λ3, and λ4 are obtained through numerical simulation and structural analysis optimization, and the initial value can be set to λ1 = 0.4.
[0191] λ2=0.3, λ3=0.2, λ4=0.1.
[0192] Step 506. Use a precision level to measure and record the ground elevation to provide a reference for subsequent height adjustments.
[0193] Step 507. Lay wooden boards with a thickness of not less than 30 mm or concrete pads with a thickness of 40 mm on the ground to distribute the load.
[0194] Step 508. Install the adjustable base. The exposed length of the adjusting screw should not exceed 300 mm.
[0195] Step 509. Use a theodolite or total station to ensure the verticality of the first layer of poles. The deviation should not exceed 5 / 1000.
[0196] Step 510. Use the erection sequence of "vertical poles first, then horizontal poles, and finally scissors braces".
[0197] Step 511. Use the disc-type bracket system to ensure that each connection point is properly tightened, and the tightening torque should reach 40Nm to 60Nm.
[0198] Step 512. The horizontal rod spacing should not be greater than 1800 mm, and the inclination angle of the scissors support diagonal rod to the ground should be between 45° and 60°.
[0199] Step 513. After each layer is erected, use a level or total station to check the elevation to ensure it is level.
[0200] Step 514. Use layered loading method for preloading, and observe the settlement after each layer is loaded. The settlement should not exceed 5 mm.
[0201] Step 515. Use a laser rangefinder to regularly check the distance between the poles to ensure that it meets the design requirements.
[0202] Step 516. During the construction process, the deformation of the bracket is monitored in real time, and optical fiber sensing technology can be used for continuous monitoring.
[0203] Step 517: Use finite element analysis software, such as MIDAS or SAP2000, to perform stability analysis on the entire stent.
[0204] Step 518. Based on the analysis results, additional reinforcing rods are installed at key nodes to improve the overall stiffness.
[0205] Step 519. Set up a protective net around the bracket, and the mesh size should not be larger than 30 mm × 30 mm.
[0206] Step 520. After each standard layer is erected, a comprehensive safety inspection is carried out, including the firmness of connections, component integrity, etc.
[0207] In this process, the use of precision levels and total stations ensured the accuracy of the support erection, the layered loading rule helped control the settlement of the support, and the application of finite element analysis software enabled the evaluation and optimization of the overall stability of the support. The comprehensive application of these technologies and methods ensured the safety and reliability of the buckle support erection.
[0208] The specific implementation of step S60 is: install an adjustable bracket on the top of the bracket and adjust the height to be lower than the designed height. The purpose of this step is to provide accurate elevation control for subsequent template installation and concrete pouring. The specific implementation process includes:
[0209] Step 601. Determine the theoretical position and elevation of each bracket based on the BIM model and structural design drawings.
[0210] Step 602. Set variables h1, h2, ..., h n Indicates the height of each bracket.
[0211] Step 603. Establish a set of constraint equations:
[0212] h i +δ i =H+∈ i ,i=1,2,...,n
[0213] |h i -h j |≤Δh max ,
[0214] h min ≤h i ≤h max ,i=1,2,...,n
[0215] Step 604. Establish the objective function:
[0216]
[0217] Step 605: Solve the constraint equations and the objective function to obtain the optimal bracket height distribution.
[0218] Where H is the design height; δi To reserve space; i is the allowable error; h avg is the average height; Δh max h is the maximum height difference between adjacent brackets; min and h max are the minimum and maximum heights of the bracket respectively; is the partial derivative of the bracket height with respect to the horizontal position; μ1, μ2, μ3, μ4 are weight coefficients.
[0219] The parameter acquisition method is:
[0220] H and δ i Determined according to the structural design drawings.
[0221] ∈ i Obtained through measurement error analysis, usually no more than 5 mm.
[0222] Δh max 、h min and h max Determined according to construction specifications.
[0223] Compute by numerical difference method: where x i is the horizontal position of the ith bracket.
[0224] μ1, μ2, μ3, and μ4 are obtained through optimization of multiple construction practices, and the initial values can be set as μ1=0.4, μ2=0.3, μ3=0.2, and μ4=0.1.
[0225] Step 606. Select a suitable adjustable bracket, whose load-bearing capacity should be no less than 1.2 times the design load.
[0226] Step 607. Use a total station or a level to measure the actual elevation of the top of the support.
[0227] Step 608. Calculate the height that each bracket needs to be adjusted, usually leaving 20 mm to 30 mm of space for subsequent precise adjustment.
[0228] Step 609. When installing the adjustable bracket, use non-slip pads to increase friction and improve stability.
[0229] Step 610. Use a torque wrench to tighten the bracket fixing bolts according to the design requirements. Normally, the torque should reach 80 Nm to 120 Nm.
[0230] Step 611. Use a high-precision digital level to adjust the height of the bracket so that it is in a horizontal state, with an allowable error of no more than 1 mm / m.
[0231] Step 612. For areas with larger spans, structural deformation is taken into consideration and appropriate pre-arching is performed. The pre-arch height is usually 1 / 1000 to 1 / 800 of the span.
[0232] Step 613. Use a laser leveler to check the flatness of large-area brackets to ensure that the height difference between adjacent brackets does not exceed 2 mm.
[0233] Step 614. Use a three-dimensional coordinate measurement system, such as a total station or a three-dimensional laser scanner, to obtain the precise spatial position of the bracket.
[0234] Step 615. Use computer-aided analysis software, such as MATLAB or Python, to perform statistical analysis and error assessment on the measurement data.
[0235] Step 616. Based on the analysis results, identify outliers and make targeted adjustments.
[0236] Step 617. During the adjustment process, use the hydraulic jacks to ensure smooth, precise height control.
[0237] Step 618. For key locations or large-span structures, install displacement sensors to monitor the settlement of the bracket in real time.
[0238] Step 619. Use a thermal imaging camera to check whether there is stress concentration at the connection between the bracket and the support.
[0239] Step 620. After the brackets are installed, use a total station to perform a recheck measurement to ensure that the height and plane position of all brackets meet the design requirements.
[0240] In this process, the use of total stations and levels ensures the high accuracy of bracket installation, the three-dimensional coordinate measurement system provides more comprehensive spatial information, and the application of computer-aided analysis software helps to better understand and control errors. The comprehensive use of these advanced tools and methods ensures the accuracy and reliability of the adjustable bracket installation.
[0241] The specific implementation of step S80 is: pre-compression test is performed on the erected support, and materials such as steel bars or sandbags are graded to load to 110% of the design load. The purpose of this step is to verify the load-bearing capacity and stability of the support to ensure that it can safely withstand the load during the construction process. The specific implementation process includes:
[0242] Step 801. Set variables w1, w2, and w3 to represent the three levels of loading weight.
[0243] Step 802. Establish constraint equations:
[0244] w1+w2+w3=1.1W
[0245] w1:w2:w3=6:4:1
[0246] w i ≥w min , i=1,2,3
[0247] w i ≤w max , i=1,2,3
[0248] Step 803. Establish the objective function:
[0249]
[0250] Step 804: Solve the constraint equations and the objective function to obtain the optimal loading weight distribution.
[0251] Where W is the design load; w min and w max are the minimum and maximum loading weights of a single stage, respectively; is the average loading weight; ν1, ν2, ν3, and ν4 are weight coefficients.
[0252] The parameter acquisition method is:
[0253] W is determined based on structural design calculations.
[0254] w min and w max Determined based on preloading equipment capacity and safety limitations.
[0255] ν1, ν2, ν3, and ν4 are obtained through numerical simulation and structural analysis optimization, and the initial value can be set to ν1 = 0.3.
[0256] ν2=0.3, ν3=0.2, ν4=0.2.
[0257] Step 805. Prepare pre-stressing materials such as steel bars, sandbags or water tanks according to the calculation results.
[0258] Step 806. Evenly lay waterproof cloth on the top of the bracket to prevent the pre-pressed material from damaging the bracket.
[0259] Step 807. Use a precision level to measure and record the initial elevations of key points of the support.
[0260] Step 808. Perform the first level of loading, with the loading weight being 60% of the design load (w1).
[0261] Step 809. Use a precision level to monitor the settlement of the support and record the settlement value of each measuring point.
[0262] Step 810. Maintain the first level of load for 24 hours and observe the deformation of the bracket.
[0263] Step 811. Perform the second level of loading, and the total loading weight reaches 100% of the design load (w1+w2).
[0264] Step 812. Measure and record the stent settlement value again and observe for 24 hours.
[0265] Step 813. Perform the third level of loading, and the total loading weight reaches 110% of the design load (w1+w2+w3).
[0266] Step 814. Measure and record the final settlement value and maintain the load for 24 hours.
[0267] Step 815. During each level of loading, use a precision level to monitor the settlement of the bracket to ensure that the settlement does not exceed 5 mm.
[0268] Step 816. Use strain gauges or optical fiber sensors to monitor the strain conditions of key parts of the stent in real time.
[0269] Step 817. Use a total station or a three-dimensional laser scanner to obtain the spatial deformation data of the bracket at different loading stages.
[0270] Step 818. Use the data acquisition system to continuously record the load-deformation curve during the loading process.
[0271] Step 819. Use finite element analysis software, such as ANSYS or ABAQUS, to perform regression analysis on the measured data to evaluate the actual load-bearing capacity of the bracket.
[0272] Step 820. During the entire preloading process, arrange dedicated personnel to monitor on-site 24 hours a day to detect and handle abnormal situations in a timely manner.
[0273] Step 821. After the pre-compression test is completed, unload slowly, observe for 1 hour after each level of unloading, and record the rebound value.
[0274] Step 822. After complete unloading, measure the permanent deformation value of the bracket to ensure that it is within the allowable range.
[0275] In this process, the use of precision levels ensures accurate monitoring of the support's settlement, strain monitoring technology and 3D scanning technology provide more comprehensive deformation data, and the application of finite element analysis software helps to deeply understand the support's stress state. The comprehensive use of these advanced technologies and methods ensures the scientificity and reliability of the preload test, providing important guarantees for subsequent construction.
[0276] The specific implementation of step S90 is: after the bracket pre-pressing is qualified, the template is installed and the elevation and flatness are checked to ensure that the design requirements are met. The purpose of this step is to provide accurate molding conditions for concrete pouring. The specific implementation process includes:
[0277] Step 901. Determine the installation location and size of the template based on the building information model and structural design drawings.
[0278] Step 902. Select appropriate template material to ensure that its strength, rigidity and surface flatness meet the design requirements.
[0279] Step 903. Use a total station or level to recheck the top of the support to ensure that its elevation and plane position meet the design requirements.
[0280] Step 904. When installing the template, use a spirit level and a ruler to ensure the flatness of the template, with an allowable error of no more than 3 mm per 3 meters.
[0281] Step 905. Use sealing tape or caulking material on the template joints to prevent leakage.
[0282] Step 906. After the installation is completed, use a total station to scan and measure the template surface to generate elevation point cloud data.
[0283] Step 907: Compare and analyze the measurement data with the building information model to ensure that the template installation accuracy meets the design requirements.
[0284] Step 908: Adjust the parts that do not meet the requirements until they meet the design standards.
[0285] Step 909. Use a laser leveler to check the flatness of the large-area template to ensure that the height difference between adjacent templates does not exceed 2 mm.
[0286] Step 910. Install displacement sensors at key locations (such as beam-column nodes and cantilevered locations) to monitor the deformation of the template in real time.
[0287] Step 911. Use an infrared thermal imager to check the temperature distribution on the template surface to ensure there is no obvious temperature difference and prevent deformation caused by temperature stress.
[0288] Step 912. Apply release agent to the surface of the formwork to ensure even coverage for subsequent concrete demolding.
[0289] Step 913. Check the formwork support system to ensure that all support components are firmly installed without looseness or deformation.
[0290] Step 914. Perform a pre-compression test on the formwork, load it to 1.2 times the design load, and observe the deformation.
[0291] Step 915. Use a 3D laser scanner to obtain the precise geometric information of the formwork after installation and compare it with the BIM model.
[0292] Step 916. Use computer-aided analysis software, such as AutoCAD or Revit, to analyze the scan data and generate a contour map and a deviation distribution map.
[0293] Step 917. Based on the analysis results, identify potential problem areas and make targeted adjustments.
[0294] Step 918. Set elevation control points on the template surface for real-time monitoring during concrete pouring.
[0295] In this process, the use of total stations and 3D laser scanners ensures the high accuracy of formwork installation, displacement sensors and thermal imagers provide real-time monitoring data, and the application of computer-aided analysis software helps to comprehensively evaluate the geometric accuracy of the formwork. The comprehensive application of these advanced technologies and methods ensures the accuracy and reliability of formwork installation, laying a solid foundation for subsequent concrete pouring.
[0296] Specifically, the principle of the present invention is:
[0297] 1. Information integration principle: The present invention adopts the building information model (BIM) technology to achieve the comprehensive integration of design information, construction information and management information. The BIM model not only contains the geometric information of the building, but also includes non-geometric information such as material properties, construction procedures, and costs. This comprehensive information integration enables construction personnel to foresee and solve potential problems in a virtual environment, greatly reducing errors and rework in actual construction.
[0298] 2. Principle of accurate measurement: The present invention introduces high-precision measurement technologies such as total station and GPS-RTK, combined with the least squares adjustment algorithm, to achieve accurate control of the support erection. The core idea of the least squares adjustment algorithm is to obtain the best estimate by minimizing the sum of squares of measurement errors. This method can not only improve the accuracy of single-point measurement, but also optimize the accuracy of the entire measurement network, thereby providing a high-precision spatial positioning basis for the formwork system.
[0299] 3. Structural mechanics principle: The present invention uses finite element analysis and mechanical simulation technology to conduct comprehensive force analysis and optimization design of the bracket system. Finite element analysis discretizes complex continua into a finite number of units and simulates the stress state of the structure by solving a large-scale set of equations. This method can accurately predict the stress distribution and deformation of the bracket system under various load conditions, providing a reliable theoretical basis for bracket design.
[0300] 4. Optimization theory: The present invention introduces optimization algorithms in the partition design, support layout and other links. For example, linear programming and Monte Carlo simulation methods are used in the partition design. Linear programming can find the optimal partition scheme under the premise of meeting various constraints; while Monte Carlo simulation evaluates the feasibility and advantages and disadvantages of different schemes through a large number of random experiments. The application of these optimization methods ensures that the formwork scheme achieves the best balance in terms of efficiency and safety.
[0301] In order to better understand and implement the present invention, a specific embodiment 1 of the present invention is provided below: Construction of multi-layer cantilevered structure formwork of a high-rise office building: This embodiment 1 takes the construction of multi-layer cantilevered structure formwork of a high-rise office building as the background, and describes in detail the specific implementation process of the present invention. The office building is located in the central business district of a first-tier city, with a total height of 180 meters and a total of 45 floors, of which the 15th to 20th floors are designed with characteristic cantilevered structures, and each floor cantilevers outward by 1.5 meters, forming a unique architectural appearance.
[0302] 1. Building Information Model (BIM) Creation
[0303] First, we used Autodesk Revit software to create a 3D BIM model of the high-rise office building based on the architectural design drawings. We focused on the cantilevered structure from the 15th to the 20th floors, and accurately modeled the cantilevered beams, floor slabs, and related structural components of each floor. The model included detailed geometric information, material properties, and component relationships. For example, the cantilevered beams were made of C50 concrete with a cross-sectional size of 500mm×800mm, and the floor slab thickness was 200mm.
[0304] 2. Partitioning of support erection areas
[0305] Through BIM model analysis, it was determined that the total area of the area where the support needed to be erected was 1,200 square meters. The K-means clustering algorithm was used to preliminarily divide the area. Considering the convenience and safety of construction, the area was finally divided into 6 zones, each with an area of about 200 square meters.
[0306] Linear programming was applied to establish an optimization model with the goal of minimizing the total construction time. Taking into account the available labor resources (30 workers), equipment resources (2 tower cranes) and material supply, the optimal zoning scheme and construction sequence were obtained by solving the optimization model.
[0307] 3. Line positioning
[0308] A Leica TS16 total station was used to set up a control network at the construction site, with a total of 6 control points, and the minimum distance between control points was 35 meters. The China Measurement GPS-RTK system was used to determine the precise coordinates of the control points, with a coordinate accuracy of ±5mm.
[0309] The control network was adjusted using the least squares adjustment algorithm to improve the overall accuracy of the control network. After the adjustment, the relative accuracy of the control network reached 1:50000.
[0310] Based on the control network, the polar coordinate method of the total station is used to lay out the partition boundary points and the positions of the poles. The layout accuracy is controlled within ±3mm. The Leica DNA03 digital level is used to determine the elevation of each pole, and the elevation accuracy is controlled within ±2mm.
[0311] 4. Installation of return rod
[0312] The return rods are installed at the bottom of the cantilever beams from the 15th to the 20th floors. Q345 steel, 60mm diameter, 4mm wall thickness round steel tubes are selected as the return rods. Finite element analysis of the return rods is performed using ANSYS software. Under the most unfavorable working conditions (considering wind loads and construction loads), the maximum stress is 210MPa and the maximum deformation is 12mm, both within the safety range.
[0313] Use the Leica LAR200 automatic leveling laser to project a horizontal reference line along the bottom of the beam. Set a fixed point every 4 meters on the reference line and fix it with M16 expansion bolts. During installation, use the Leica FTA360-S adapter with a total station to ensure the verticality of the return rod, and the deviation is controlled within 2 / 1000.
[0314] 5. Set up the buckle bracket
[0315] φ48.3×3.5mm steel pipes are used as vertical poles, with a vertical and horizontal spacing of 1200mm. φ48.3×3.2mm steel pipes are used as horizontal poles, with a step distance of 1800mm. Leica 3D Disto three-dimensional laser distance meter is used to ensure the verticality of each vertical pole, with the deviation controlled within 3 / 1000.
[0316] After the first layer of support was erected, the TRIMBLE DiNi digital level was used to observe the settlement. The initial settlement was 3mm, which was within the allowable range. Then the support was erected layer by layer, and the overall settlement was observed every three layers.
[0317] At key nodes, such as the corners of cantilever structures and large span areas, diagonal braces are added for reinforcement. The inclination angle of the diagonal braces to the ground is maintained at 55° to provide optimal lateral stability.
[0318] 6. Adjustable bracket installation
[0319] An adjustable bracket is installed on the top of the bracket, and a heavy-duty adjustable bracket with a load capacity of 50kN is selected. The flatness of the large-area bracket is checked using a Leica Rugby880 laser leveler, and the height difference between adjacent brackets is controlled within 1.5mm.
[0320] Use a torque wrench to tighten the bracket fixing bolts, and set the torque value to 100 Nm. Use the Leica Disto S910 handheld laser rangefinder to adjust the bracket height to 25 mm below the design height to reserve space for subsequent adjustments.
[0321] 7. Installation of crossbars and diagonal rods
[0322] According to the results of finite element analysis, crossbars and diagonal braces are added at key stress-bearing locations. The crossbars are made of φ48.3×3.5mm steel pipes, and the diagonal braces are made of φ42×3.5mm steel pipes. A Leica DISTO X4 laser rangefinder is used to ensure the horizontality of the crossbars, with an allowable error of no more than 2mm / m.
[0323] For the inclined rod, use a digital inclinometer to measure its inclination to ensure that the deviation from the design angle does not exceed 0.5°. Use 10.9 grade high-strength bolts at the connection and tighten them with a digital torque wrench, with the torque value set to 130 Nm.
[0324] 8. Preload test
[0325] Carry out three-level loading preload test according to 110% of design load. Design load is 4kN / m 2 , the total preload is 4.4kN / m 2 Prefabricated reinforced concrete blocks are used as loading materials, each weighing 25kg and with dimensions of 500mm×500mm×100mm.
[0326] The three levels of loading weight are:
[0327] -First stage: 2.64kN / m 2 (60% of total load)
[0328] -Second stage: 1.76kN / m 2 (40% of total load)
[0329] -Level 3: 0.44kN / m 2 (10% of total load)
[0330] A Leica LS15 digital level was used to monitor the settlement of the bracket during each level of loading. After the first level of loading, the maximum settlement was 4.2 mm; after the second level of loading, the cumulative maximum settlement was 6.8 mm; after the third level of loading, the cumulative maximum settlement was 7.5 mm, all within the allowable range (less than 10 mm).
[0331] 9. Template installation and adjustment
[0332] Use 18mm thick film-coated board as the template material. When installing the template, use Leica Rugby CLA laser leveler to ensure the flatness of the template, with an allowable error of no more than 3mm / 3m. Use sealing tape at the template joints to prevent leakage.
[0333] After installation, the Leica RTC360 3D laser scanner was used to scan and measure the template surface to generate elevation point cloud data. The measured data was imported into Autodesk Navisworks software for comparative analysis with the BIM model. The analysis results showed that 98.5% of the regional errors were within ±5mm, and the maximum error was 7.2mm, located at the edge of the cantilever.
[0334] Adjustments were made to the parts that did not meet the requirements, mainly by adjusting the height of the bracket and adding pads locally. After the adjustments, scanning and measurement were performed again. After the adjustments, 99.2% of the regional errors were within ±5mm, and the maximum error was reduced to 6.3mm.
[0335] 10. Construction process monitoring
[0336] During the entire formwork process, a variety of advanced monitoring technologies are used for all-round monitoring:
[0337] -Use Monnit wireless inclination sensors, install 20 measuring points at key locations, and monitor the tilt of the bracket in real time. Set the alarm threshold to 0.5°, and an alarm will be triggered immediately if it is exceeded.
[0338] -Fiber Bragg grating strain sensors are used to arrange 30 measuring points on the main load-bearing components to monitor the stress state of the components.
[0339] -Use Leica AP20 automated total station, set up 4 monitoring points, and monitor the overall deformation of the bracket 24 hours a day.
[0340] All monitoring data is transmitted to the data center at the construction site in real time through the Internet of Things technology and integrated with the BIM model to form a digital twin system. Through big data analysis and machine learning algorithms, the health status of the support system is evaluated and warned in real time.
[0341] 11. Construction effect evaluation
[0342] The formwork construction of the entire multi-story cantilever structure took 15 days, saving about 40% of the time compared to traditional methods. During the construction process, no safety accidents occurred. After the final concrete pouring was completed, the cantilever structure was fully inspected for quality:
[0343] -The cantilever structure was 3D scanned using the Leica BLK360 imaging laser scanner. Compared with the design model, the geometric dimension error was within ±10mm, which is better than the specification requirement of ±15mm.
[0344] -The ZBL-R800 multifunctional concrete steel bar detector was used to test the thickness of the steel bar protective layer of the cantilever beam. The average thickness was 52mm and the standard deviation was 3.2mm, which met the design requirements.
[0345] -Using ZBL-C310 concrete strength tester, the cantilever structure was sampled and tested. The average 28-day compressive strength reached 54.6MPa, which is higher than the design requirement of 50MPa.
[0346] Through comparative analysis with similar projects, this project has achieved remarkable results in the following aspects:
[0347] 1. Construction accuracy: The construction error of key parts is controlled within 5mm, which is 60% higher than the traditional method.
[0348] 2. Construction efficiency: The total construction period was shortened by 40%, greatly speeding up the project progress.
[0349] 3. Material utilization: Through optimized design, the use of formwork materials has been reduced by 25%, reducing costs.
[0350] 4. Safety performance: No safety accidents occurred during the entire construction process, and the safety performance was better than the industry average.
[0351] 5. Structural quality: All indicators of the final cantilever structure are better than the design requirements and industry standards.
[0352] This Example 1 fully demonstrates the application effect of the multi-layer cantilevered plate buckle formwork method proposed by the present invention in actual projects. By integrating advanced measurement technology, computer-aided design and analysis, intelligent monitoring system, etc., high-precision, high-efficiency and high-safety formwork construction is achieved, providing a technical solution for the construction of similar complex structures.
[0353] In order to further better understand the present invention, another specific embodiment 2 of the present invention is provided below: This embodiment 2 involves a large commercial complex project with a total construction area of about 250,000 square meters, including a 5-story podium and three towers with 30, 40 and 50 floors respectively. Among them, the podium part is designed with multiple cantilever structures, with the maximum cantilever length reaching 6 meters, which brings great challenges to the construction. The multi-layer cantilevered plate buckle formwork method of the present invention has been successfully applied in the cantilever structure construction of the project.
[0354] Step S10: Based on the architectural design drawings, use Autodesk Revit 2023 to create a 3D model of the multi-story cantilever structure. The project construction staff first collected and sorted out the architectural design drawings, including floor plans, elevations, sections, and structural drawings. Then, a project file was created in Revit, and the correct unit system (mm) and coordinate system () were set.
[0355] The project construction staff drew the building structure layer by layer, paying special attention to the details of the cantilever structure. On the third floor of the podium, there is a 6-meter-long cantilever platform with a width of 12 meters and a thickness of 600 mm. The cantilever beam adopts a variable cross-section design, with a root height of 1,200 mm and an end height of 600 mm. In order to improve the accuracy of the model, the construction staff also added secondary components such as doors, windows, and stairs.
[0356] During the model creation process, the construction staff used parametric modeling technology. For example, for the cantilever beam, an adjustable family was created, whose height can automatically change according to the distance from the cantilever end. In this way, when the cantilever length needs to be adjusted, the cross-section of the beam will be automatically updated.
[0357] Finally, the construction staff conducted a comprehensive inspection of the completed BIM model to ensure its accuracy and completeness. During the inspection, several component collision problems were found and corrected, especially at the connection between the cantilever structure and the facade curtain wall system.
[0358] Step S20: Obtain the data of the installation of the bracket through the BIM model, and divide the area where the bracket needs to be installed into several partitions. First, the construction personnel extracted the area information where the bracket needs to be installed from the BIM model. For the 6-meter cantilever platform on the third floor, the total area of the bracket installation area is 72 square meters (6 meters × 12 meters).
[0359] Considering the convenience and safety of construction, the construction workers decided to divide the area into 6 zones, each with an area of about 12 square meters. In order to optimize the zone plan, the construction workers used MATLAB R2023a software for calculation.
[0360] Set variables x1, x2, x3, x4, x5, and x6 to represent the area of each partition, and establish the constraint equations and objective function as follows:
[0361] Constraint equations:
[0362]
[0363] x i ≥10, i=1,2,...,6
[0364] x i ≤15, i=1,2,...,6
[0365] Objective function:
[0366]
[0367] The solution results are as follows:
[0368] x1=12.2m 2
[0369] x2=11.8m 2
[0370] x3=12.1m 2
[0371] x4=11.9m 2
[0372] x5=12.0m 2
[0373] x6=12.0m 2
[0374] This result shows a relatively uniform zoning scheme, with the difference between the largest and smallest zoning areas being only 0.4 square meters.
[0375] Next, the construction workers used the K-means clustering algorithm to make a preliminary division of the support erection area. Considering the convenience of actual construction, the preliminary division results were fine-tuned. For example, a main beam that originally spanned two partitions was adjusted to the same partition.
[0376] The Kruskal algorithm was used to determine the optimal connection relationship between the partitions. Based on the algorithm results, the construction sequence was determined as: partition 1 → partition 2 → partition 4 → partition 3 → partition 5 → partition 6. This sequence can minimize the material transportation distance and improve construction efficiency.
[0377] Finally, the construction personnel used the Monte Carlo simulation method to simulate the zoning scheme 1,000 times. The simulation results showed that in 95% of cases, the zoning scheme could control the total construction time within the expected range (±5%).
[0378] Step S30: Lay out each partition and use a total station and level to determine the position and elevation of the poles. First, the project construction personnel used the Trimble R12i GNSS receiver to set up a control network at the construction site, including 4 control points, with the shortest distance between the control points being 35 meters.
[0379] The control network was adjusted using the least squares adjustment algorithm, and the plane accuracy of the control network reached ±3 mm, and the elevation accuracy reached ±2 mm. Based on this high-precision control network, the construction personnel used the Leica TS60 high-precision total station to stake out the partition boundary points.
[0380] The construction workers used the polar coordinate method to determine the position of the poles. The plane position of each pole was set out with an accuracy of ±3 mm. The elevation of each pole was determined using a Leica LS15 digital level, with an elevation accuracy of ±2 mm.
[0381] During the layout process, the construction workers paid special attention to the control of cumulative errors. They used the error propagation law for analysis and optimized the layout of the measuring stations to control the overall layout accuracy within ±5 mm.
[0382] Finally, the construction workers used steel nails and fluorescent paint to mark the positions of the poles and elevation points, and reviewed the layout to ensure that there were no major errors.
[0383] Step S40: A return rod is set up at the bottom of the side span beam and the cantilever beam as the boundary between the inner and outer frames. The precise position of the return rod is determined according to the BIM model. A round tube made of Q345 steel with a diameter of 60 mm and a wall thickness of 4 mm is selected as the return rod.
[0384] Finite element analysis of the return rod was performed using ANSYS2023R1 software. The analysis results showed that under the most unfavorable load condition, the maximum stress of the return rod was 210MPa and the maximum deflection was 12mm, both within the allowable range.
[0385] Use a Bosch GLL 3-80CG laser level to project a horizontal reference line along the bottom of the beam. Set a fixed point every 3.5 meters on the reference line and fix it with M16 expansion bolts.
[0386] When installing the return rod, an adjustable connection is used to precisely adjust its position. Using a Hilti ST 1800-A22 cordless torque wrench, the connection bolts are tightened to 120 Nm as required by the design.
[0387] After the installation was completed, a Leica TS60 total station was used for verification measurement. The measurement results showed that the maximum verticality deviation of the return rod was 2.5 / 1000, which met the requirement of 3 / 1000.
[0388] Step S50: The buckle brackets are set up layer by layer from bottom to top, and the vertical and horizontal spacing of the vertical poles and the horizontal pole pitch are set according to the design requirements. First, the construction personnel determine the exact position and spacing of the vertical poles according to the design drawings and BIM models.
[0389] In order to optimize the spacing between the poles, the construction workers used MATLAB R2023a software to perform calculations. The variables dx and dy were set to represent the longitudinal and transverse spacing of the poles, respectively, and the constraint equations and objective function were established as follows:
[0390] Constraint equations:
[0391] n x d x ≤6000
[0392] n y d y ≤12000
[0393] d x ≤1800
[0394] d y ≤1800
[0395]
[0396] Objective function:
[0397]
[0398] The solution results are as follows:
[0399] dx=1500mm
[0400] dy=1500mm
[0401] nx=4
[0402] ny=8
[0403] This result shows that the best support effect can be obtained by setting 4 and 8 vertical poles in the longitudinal and transverse directions respectively, with a spacing of 1500 mm.
[0404] The ground elevation was measured and recorded using a Leica LS15 digital level to provide a reference for subsequent height adjustments. A 40 mm thick concrete pad was laid on the ground to distribute the load.
[0405] When installing the adjustable base, use a vernier caliper to control the exposed length of the screw to not exceed 250 mm. Use a Leica TS60 total station to ensure the verticality of the first layer of poles. The measurement results show that the maximum deviation is 4.2 / 1000, which meets the requirement of 5 / 1000.
[0406] The erection sequence is "vertical poles first, then horizontal poles, and then scissor braces". A disc-type bracket system is used, and each connection point is tightened to 50 Nm using a HiltiST 1800-A22 cordless torque wrench.
[0407] The horizontal rod spacing is set to 1500 mm, and the scissor brace diagonal rod is inclined at an angle of 55° to the ground. After each layer is erected, the Leica LS15 digital level is used to check the elevation to ensure levelness.
[0408] The preloading was carried out by layered loading method, with 2 tons per layer and 3 layers in total. The settlement was observed using a precision level, and the maximum settlement was 3.8 mm, which met the requirement of not exceeding 5 mm.
[0409] The Hilti PD-E laser distance meter was used to check the distance between the poles every 4 hours to ensure that it met the design requirements. During the entire construction process, fiber optic sensing technology was used to monitor the deformation of the bracket in real time.
[0410] MIDAS GEN 2023 software was used to analyze the stability of the entire support. The analysis results showed that under the most unfavorable load condition, the maximum stress of the support was 205MPa and the maximum displacement was 18mm, both within the allowable range. Based on the analysis results, four reinforcing rods were added in the area near the cantilever end to further improve the overall stiffness.
[0411] A protective net with a mesh size of 20 mm x 20 mm is set up outside the support. After each standard layer is erected, a comprehensive safety inspection is carried out, including the firmness of the connection and the integrity of the components.
[0412] Step S60: Install an adjustable bracket on the top of the bracket and adjust the height to be lower than the designed height. First, the construction personnel determine the theoretical position and elevation of each bracket according to the BIM model and the structural design drawings.
[0413] In order to optimize the height distribution of the brackets, the construction personnel used MATLAB R2023a software for calculation. The variables h1, h2, ..., h32 were set to represent the height of each bracket (a total of 32 brackets), and the constraint equations and objective function were established as follows:
[0414] Constraint equations:
[0415] h i +25=3600+∈ i , i=1,2,...,32
[0416] |h i -h j |≤5,
[0417] 3570≤h i ≤3580, i=1,2,...,32
[0418] Objective function:
[0419]
[0420] The solution results show that the heights of the 32 brackets are between 3573 mm and 3577 mm, with a maximum height difference of 4 mm, which meets the design requirements.
[0421] An adjustable bracket with a load capacity of 50 kN was selected, which is 1.25 times higher than the design load of 40 kN. The actual elevation of the top of the bracket was measured using a Leica TS60 total station with a measurement accuracy of ±1 mm.
[0422] Calculate the height that each bracket needs to be adjusted, and leave 25 mm of space for subsequent precise adjustment. When installing the adjustable bracket, use a rubber gasket with an anti-slip coefficient of not less than 0.6 to increase friction.
[0423] Tighten the bracket fixing bolts to 100 Nm using a Hilti ST 1800-A22 cordless torque wrench. Use a digital level with an accuracy of 0.02 mm / m to adjust the height of the bracket so that it is level.
[0424] For the cantilever area with a span of 6 meters, a 6 mm pre-arch (1 / 1000 span) was set to consider structural deformation. The top of the bracket was 3D scanned using a Leica BLK360 laser scanner to generate a point cloud model. The point cloud data showed that the maximum deviation of the flatness of the top of the bracket was 4.7 mm, which met the 5 mm requirement.
[0425] In order to monitor the deformation of the support during construction, the construction workers installed 8 optical fiber strain sensors and 4 inclination sensors at key locations. These sensors are connected to the on-site monitoring center via a wireless network and transmit data in real time.
[0426] Step S70: Install the crossbar and diagonal brace, and hammer the pins with a hand-held hammer. First, the specific layout of the crossbar and diagonal brace is determined based on the BIM model. The crossbar is made of φ48×3.5 mm steel pipe with a spacing of 1500 mm; the diagonal brace is made of φ40×3.0 mm steel pipe, which is at an angle of 45° to the horizontal plane.
[0427] During installation, first connect the buckles at both ends of the horizontal bar to the vertical bar, and then install the diagonal rod. Use the Hilti TE 6-A36 cordless electric hammer drill to drill holes in the concrete structure, install M16 expansion bolts, and fix the ends of the diagonal rod.
[0428] To ensure a firm connection, the project construction workers used a special alloy hammer weighing 1.5 kg. Each connection point was hammered 30-40 times until the pin was completely hammered. The tightening torque of the connection points was randomly checked using a torque wrench, and the average value was 65 N·m, which exceeded the design requirement of 60 N·m.
[0429] During the installation process, the construction workers paid special attention to the construction sequence and force balance. Adopting the principle of "symmetry and balance", the installation was carried out from the middle to both sides simultaneously to ensure the stability of the structure. After each horizontal plane was installed, a FAROFocus S 350 laser scanner was used to scan the overall geometry of the structure.
[0430] Step S80: Perform a pre-compression test on the erected support, and use materials such as steel bars or sandbags to load the design load in stages to 110%. First, the construction personnel determined the design load W to be 360 kN based on the structural design calculation. Considering the 110% loading requirement, the total loading weight should be 396 kN.
[0431] In order to optimize the loading scheme, the construction personnel used MATLAB software to calculate and obtained the following three-level loading weights:
[0432] w1=218.9 kN
[0433] w2=145.9 kN
[0434] w3=31.2 kN
[0435] The loading materials used were 25 kg standard sandbags and 25 mm diameter steel bars. The first level of loading used sandbags, a total of 8,756 bags were needed; the second level of loading used steel bars, with a total length of about 1,860 meters; the third level of loading used mixed materials, including 1,048 sandbags and 100 meters of steel bars.
[0436] During the loading process, the deformation of the bracket was monitored in real time using a Leica TS60 total station and a precision level. 12 displacement measurement points were set at key locations and observations were made after each level of loading was completed. The following Table 1 is the observation data:
[0437] Table 1 Observation data table
[0438] Loading Level Maximum vertical displacement (mm) Maximum horizontal displacement (mm) First level 5.8 3.2 Level 2 9.7 5.5 Level 3 12.3 7.1
[0439] The data showed that the maximum vertical displacement of the bracket was 12.3 mm, and the maximum horizontal displacement was 7.1 mm, both of which were within the design allowable values (15 mm vertically and 10 mm horizontally).
[0440] During the loading process, the construction workers also used a FLIR E95 infrared thermal imager to perform thermal imaging scans on the bracket to check whether there were any areas of stress concentration. The scan results showed that the bracket temperature was evenly distributed, with the highest temperature being 28.5°C and the lowest temperature being 26.8°C, and the temperature difference was within the normal range.
[0441] After loading for 24 hours, the stent was unloaded and the rebound was observed. Two hours after unloading, the residual deformation of the stent was 1.8 mm, and the recovery rate reached 85.4%, meeting the design requirements (≥80%).
[0442] Step S90: After the bracket is pre-pressed, the template is installed and the elevation and flatness are checked to ensure that the design requirements are met. The template uses 18 mm thick plywood and a layer of release agent is applied on the surface. Before installing the template, use the Bosch GSL 2 professional laser level to project a horizontal reference line on the top of the bracket as a reference for installation.
[0443] The formwork is installed in a "large plate assembly" manner, with each plate covering an area of approximately 4 square meters. The formwork is fixed to the secondary keel using a HILTI SF10W-A22 rechargeable electric drill and self-tapping screws, with the screw spacing controlled at 200 mm. Weather-resistant sealing tape is used to seal the joints of the formwork to prevent leakage.
[0444] After installation, the Leica DNA03 electronic level was used to measure the elevation of the template surface. A total of 72 measuring points were set in the 6m × 12m cantilever area, forming a 1m × 1m grid. The measurement results are shown in Table 2:
[0445] Table 2 Measurement results
[0446] Statistics Value(mm) highest point +2.8 Lowest point -3.1 Average elevation -0.3 Standard Deviation 1.2
[0447] The data shows that the maximum height difference of the template surface is 5.9 mm, which meets the design specification requirements (≤8 mm).
[0448] Use a 1-meter ruler and a feeler gauge to check the flatness of the template surface, randomly check one point per square meter, and check a total of 72 points. The inspection results are shown in Table 3:
[0449] Table 3 Inspection results
[0450] Flatness range (mm) Points percentage 0-1 43 59.7% 1-2 21 29.2% 2-3 8 11.1% >3 0 0%
[0451] The flatness of all inspection points is within 3 mm, meeting the design requirements (≤3 mm).
[0452] In Example 2, the multi-layer cantilevered plate buckle formwork method of the present invention was adopted, and the project successfully completed the construction of a complex cantilevered structure. Compared with the traditional construction method, this method improves the construction accuracy, reduces material waste, shortens the construction period, and significantly improves the construction safety. The structural inspection report after the project was completed showed that all technical indicators of the cantilevered structure met or exceeded the design requirements.
[0453] The above description is only a specific implementation mode of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can easily think of changes or substitutions within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A multi-layer cantilevered plate buckle formwork method, characterized in that: The following steps are involved: S10. Create a 3D model of the multi-story cantilever structure using BIM software based on the architectural design drawings; S20, obtaining the data for erecting the buckle bracket through the BIM model, and dividing the area where the bracket needs to be erected into several partitions; S30, lay out each partition and use a total station and level to determine the position and elevation of the poles; S40. A return rod is set up at the bottom of the side span beam and the cantilever beam as the dividing line between the inner and outer frames; S50. Set up the buckle bracket layer by layer from bottom to top, and set the vertical and horizontal spacing of the vertical poles and the horizontal pole pitch according to the design requirements; S60. Install an adjustable bracket on the top of the bracket and adjust the height to be lower than the designed height; S70, install the crossbar and diagonal tie rod, and hammer the latch firmly with a hand-held hammer; S80. Carry out pre-compression test on the erected support, using steel bars or sandbags to load graded loads to 110% of the design load; S90. After the bracket is pre-pressed and qualified, install the template and check the elevation and flatness to ensure that it meets the design requirements.
2. A multi-layer cantilevered plate buckle formwork method according to claim 1, characterized in that: The step S10 specifically includes: Step 101: Collect and organize architectural design drawings, including floor plans, elevations, sections, and structural drawings; Step 102, select building information modeling software and set the correct unit system and coordinate system; Step 103: Draw the main components of the building structure layer by layer according to the drawing information, including at least columns, beams, slabs, and walls; Step 104, add secondary components, including at least doors, windows, and stairs, to complete the model; Step 105, check and correct geometric errors and component conflicts in the model; Step 106: Add material information and component properties to the model; Step 107: Conduct a comprehensive check on the completed building information model to ensure accuracy and completeness.
3. A multi-layer cantilevered plate buckle formwork method according to claim 2, characterized in that: The step S20 specifically includes: Step 201: extracting the area information where the support needs to be erected from the building information model, including the plane range and height; Step 202: using a spatial clustering algorithm to preliminarily divide the support erection area; Step 203: Considering the construction convenience and safety, manually adjust and optimize the preliminary division results; Step 204: Use a minimum spanning tree algorithm to determine the optimal connection relationship between the partitions; Step 205: Apply a linear programming method to establish an optimization model with the goal of minimizing the total construction time; Step 206: Use the Monte Carlo simulation method to simulate different partitioning schemes multiple times to evaluate their impact on construction progress and cost; Step 207: According to the simulation results, the optimal partitioning scheme is selected, and the partitioning results are visualized in the building information model using geographic information system technology.
4. A multi-layer cantilevered plate buckle formwork method according to claim 3, characterized in that: The step S30 specifically includes: Step 301: Determine the coordinates of the boundary points of each partition according to the building information model and the partition scheme; Step 302: Use a total station to set up a control network at the construction site, including at least 4 control points, with the distance between the control points being no less than 30 meters; Step 303: Use the real-time dynamic technology of the global positioning system to determine the precise coordinates of the control point; Step 304, using the least squares adjustment algorithm, the control network is adjusted to improve the accuracy of the control network; Step 305: Locate the partition boundary points based on the control network using the polar coordinate method or the forward intersection method; Step 306: Use the layout function of the total station to determine the plane position of each pole, and the layout accuracy is controlled within plus or minus 5 mm; Step 307: Use the elevation measurement function of a level or total station to determine the elevation of each pole, with the elevation accuracy controlled within plus or minus 3 mm.
5. A multi-layer cantilevered plate buckle formwork method according to claim 4, characterized in that: The step S40 specifically includes: Step 401: Determine the precise position and elevation of the side span beam and the cantilever beam according to the building information model; Step 402, select a suitable material for the return pin, with a diameter of not less than 48 mm and a wall thickness of not less than 3.5 mm; Step 403, calculating the stress of the return rod, including axial pressure and bending moment, to ensure that its strength and rigidity meet the requirements; Step 404: Use finite element analysis software to perform stress analysis and deformation analysis on the return rod; Step 405: According to the analysis result, determine that the return rod is located on the center line of the bottom of the beam; Step 406, using a laser level, projecting a horizontal reference line along the bottom of the beam; Step 407: Set a fixed point every 3 to 5 meters on the baseline and fix it with expansion bolts or chemical anchors.
6. A multi-layer cantilevered plate buckle formwork method according to claim 5, characterized in that: The step S50 specifically includes: Step 501: Determine the exact position and spacing of the poles according to the design drawings and the building information model; Step 502: Use a precision level to measure and record the ground elevation to provide a reference for subsequent height adjustment; Step 503: Lay a wooden board with a thickness of not less than 30 mm or a concrete pad with a thickness of 40 mm on the ground to distribute the load; Step 504, installing the adjustable base, adjusting the exposed length of the screw to not exceed 300 mm; Step 505: Use a theodolite or a total station to ensure the verticality of the first layer of poles, with a deviation of no more than 5 / 1000; Step 506, adopting the order of erecting the vertical poles first, then the horizontal poles, and finally the scissors braces; Step 507: Use the disc-type bracket system to ensure that each connection point is properly locked and the locking torque reaches 40 Nm to 60 Nm.
7. A multi-layer cantilevered plate buckle formwork method according to claim 6, characterized in that: The step S60 specifically includes: Step 601: Determine the theoretical position and elevation of each bracket according to the building information model and the structural design drawings; Step 602: Select a suitable adjustable bracket, whose bearing capacity is not less than 1.2 times of the design load; Step 603: Use a total station or a level to measure the actual elevation of the top of the support; Step 604: Calculate the height of each bracket that needs to be adjusted, and reserve 20 mm to 30 mm of space for subsequent precise adjustment; Step 605: When installing the adjustable bracket, use anti-skid pads to increase friction and improve stability; Step 606: Use a torque wrench to tighten the bracket fixing bolts according to design requirements, with the torque reaching 80 Nm to 120 Nm; Step 607: Use a high-precision digital level to adjust the height of the bracket so that it is in a horizontal state, with an allowable error of no more than 1 mm per meter.
8. A multi-layer cantilevered plate buckle formwork method according to claim 7, characterized in that: The step S70 specifically includes: Step 701: Determine the installation position and angle of the crossbar and the diagonal brace according to the design drawings and the building information model; Step 702, select the crossbar and diagonal rod of appropriate specifications, and use the steel pipe with a diameter of 48.3 mm and a wall thickness of 3.5 mm; Step 703: Use a laser rangefinder to accurately measure the positions where the crossbars and diagonal braces need to be installed; Step 704: When installing the crossbar, use a level to ensure its levelness, with an allowable error of no more than 2 mm per meter; Step 705: For the inclined rod, use an inclinometer to measure its inclination angle to ensure that the deviation from the design angle does not exceed 1 degree; Step 706: Use mechanical analysis software to simulate and analyze the stress conditions of the crossbar and the diagonal brace; Step 707: Optimize the arrangement of the crossbars and the diagonal braces according to the analysis results, and add reinforcement components if necessary.
9. A multi-layer cantilevered plate buckle formwork method according to claim 8, characterized in that: The step S80 specifically includes: Step 801, setting three-level loading weights, the sum of which is 1.1 times the design load; Step 802, ensuring that the weight ratio of the three-level loading is 6:4:1; Step 803, determining the single-stage minimum and maximum loading weights according to the preloading equipment capacity and safety restrictions; Step 804: Optimize the load weight distribution using numerical simulation and structural analysis methods; Step 805, perform first level loading to reach 60% of the design load; Step 806, performing second level loading to reach 100% of the design load; Step 807, perform the third level loading to reach 110% of the design load; Step 808: During each loading process, use a precision level to monitor the settlement of the bracket to ensure that the settlement does not exceed 5 mm.
10. A multi-layer cantilevered plate buckle formwork method according to claim 9, characterized in that: The step S90 specifically includes: Step 901: Determine the installation position and size of the template according to the building information model and the structural design drawings; Step 902: Select appropriate template material to ensure that its strength, rigidity and surface flatness meet the design requirements; Step 903: Use a total station or a level to recheck the top of the bracket to ensure that its elevation and plane position meet the design requirements; Step 904: When installing the template, use a level and a ruler to ensure the flatness of the template, with an allowable error of no more than 3 mm per 3 meters; Step 905: Use sealing tape or caulking material at the template joints to prevent slurry leakage; Step 906: After installation is completed, use a total station to scan and measure the template surface to generate elevation point cloud data; Step 907: Compare and analyze the measurement data with the building information model to ensure that the template installation accuracy meets the design requirements; Step 908: Adjust the parts that do not meet the requirements until they meet the design standards.
Citation Information
Patent Citations
Curved-surface concrete bridge deck joint measurement and control elevation positioning method
CN104636545A
Whole process optimization method for hydraulic climbing formwork scaffold construction of super high-rise building
CN108319755A
Method for erecting ring lock support of subway station main body structure based on building information modeling (BIM)
CN112252362A
Fabricated curtain wall overall lifting installation construction method based on BIM model construction technical support
CN112347677A
Arc-shaped ramp construction joint elevation control and strip-shaped segmentation formwork erecting method
CN114411482A