Pumped storage construction power supply system voltage-reactive compensation control strategy based on hierarchical compensation principle
Through a control strategy based on the principle of hierarchical compensation, in response to the voltage limit and reactive power optimization problems in the pumped storage construction power supply system, multi-objective decision control and NSGA-II algorithm are used to realize voltage-reactive power hierarchical coordination optimization, solving the problem of voltage-reactive power optimization The normal range of voltage and power improves the reliability and economics of the system.
Patent Information
- Application Number
- CN202410967981.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-18
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2044-07-18
AI Technical Summary
The existing technology has failed to effectively solve the problem of voltage overlimit and voltage reactive power optimization control in pumped storage construction power supply systems, especially in the absence of comprehensive governance strategies and coordinated optimization of overall power quality under multiple operating conditions.
The control strategy based on the principle of hierarchical compensation is adopted, and the voltage-reactive hierarchical coordinated optimization control is performed through the overall model and multi-objective decision-making control scheme, including decision vectors and state vectors, objective functions and constraints, and iterative optimization is performed using the NSGA-II algorithm. , until all node voltages and power are within the normal range.
Comprehensive voltage-reactive power control of the pumped storage construction power supply system is realized, which reduces system losses, improves power reliability and stability, and improves power quality.
Smart Images

Figure CN119010057A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of control strategies for pumped storage power supply systems, and relates to a voltage-reactive power compensation control strategy for a pumped storage construction power supply system based on a hierarchical compensation principle. Background Art
[0002] In the power supply system, most of the current attention is paid to the coordinated operation optimization of the underlying equipment in the distribution network or the management of single power quality issues. However, the management level of electricity consumption in the construction of pumped-storage power stations is still in a relatively extensive stage. The comprehensive management strategy for typical power quality problems under multiple working conditions of the power supply system for the construction of pumped-storage power stations and the coordinated optimization of the overall power quality have not yet been considered. The hierarchical coordinated compensation control mode and architecture urgently need to be further explored. Summary of the invention
[0003] The technical problem to be solved by the present invention is to provide a voltage-reactive power compensation control strategy for a pumped storage construction power supply system based on the principle of hierarchical compensation, to perform voltage over-limit control and voltage-reactive power optimization control and to make over-limit judgment, and then to perform global optimization and hierarchical coordinated control, and to use global optimization to supplement over-limit correction until the voltage and power of all nodes are within the normal range, thereby achieving system loss reduction and energy saving.
[0004] In order to solve the above technical problems, the technical solution adopted by the present invention is: a voltage-reactive power compensation control strategy for a pumped storage construction power supply system based on the hierarchical compensation principle, which comprises the following steps: S1, the overall model, implements a multi-objective decision-making control scheme based on hierarchical coordinated compensation for the location and capacity selection of DG, capacitor banks, and OLTC equipment in the construction power supply system; the optimization control model of the pumped storage construction power supply system is expressed as: (1) Where: is the overall objective function, , , is the sub-objective function; , It is the constraints related to the system and equipment; are system decision variables and system operation state variables respectively; the model is an overall voltage-reactive power hierarchical coordinated optimization control model; S2, control variables, including decision vector and state vector; S2-1, decision vector represents the decision vector of the optimization control model consisting of m control variables in the kth hierarchical optimization control cycle; the decision vector xk includes the tap position of the OLTC , Number of switched capacitor groups , SNOP's active and reactive power and and ; S2-2, state vector represents the state vector of the optimization control model composed of m control variables in the kth hierarchical optimization control cycle; the state vector Including the real-time active and reactive power of each node load and , predicted power and , node voltage and branch current And power factor ; S3, objective function, the objective function F(x k ,u k ,t) consists of three levels of objective functions, namely: the planning scheme F1(xk,uk,t) with the optimal control of distribution network voltage as the goal decision, the planning scheme F2(x k ,u k ,t), the planning scheme F3 (x k ,u k ,t); S4, constraints, including power flow constraints, node voltage and branch current constraints, flexible interconnection device operation constraints, flexible transformer operation constraints, comprehensive reactive power compensation operation constraints and power factor operation constraints; S5, solution, includes loading system real-time data information and models, initial power flow calculation, voltage over-limit judgment and correction, typical power quality problem judgment and hierarchical management, power factor over-limit judgment and correction, global voltage-reactive power optimization and layer-by-layer iterative optimization.
[0005] In S2, the decision vector The maximum dimension of is determined by the total number of DG stations, feeder and substation CBs, OLTCs in the distribution network, and the active and reactive power of SNOPs in the interconnected area. The actual dimension of is determined by the pre-decision method proposed at each level; the state vector The maximum dimension of is determined by the real-time active and reactive power and predicted power of each node load in the distribution network, the node voltage and branch current, and the power factor of the feeder and load. The actual dimension of the state vector uk is determined by the pre-decision method proposed at each level during each optimization.
[0006] In S3, the hierarchical optimization model of the entire power supply system is expressed as: (1) Optimal control target of construction power supply system voltage: (2)
[0007] (2) Optimal control target of power factor of construction power supply system: (3)
[0008] (3) Objective of minimizing active power loss of construction power supply system: (4) .
[0009] In S4, (1) power flow constraints, (5) In the formula, , is the active power and reactive power injected by the generator at node i; , is the active power and reactive power injected by the load on node i; , is the voltage at node i and node j, is the conductance between node i and node j, is the susceptance between node i and node j, is the phase angle difference between node i and node j; (2) Node voltage and branch current constraints, (6) In the formula, and They are the upper and lower limits of the node voltage amplitude in the system respectively; is the current amplitude of branch ij, is the upper limit of the current amplitude of branch ij; (3) Operation constraints of flexible interconnection devices, (7) In the formula, and are the operating losses of the converters on the i and j sides in SNOP respectively; k is the loss coefficient of the converter; is the rated capacity of the SNOP converter; (4) Flexible transformer operation constraints, (8) In the formula, is the voltage on the high-voltage side of the flexible transformer, which is a constant; is the transformation ratio of the flexible transformer at time t; is the tap position at time t, which is an integer variable; is the ratio difference between adjacent gears; , are the maximum gear and minimum gear of the tap respectively; is a 0,1 variable. If it is 1, it means that the tap position of the on-load tap-changing transformer has changed. If it is 0, it means that the tap position remains unchanged; The maximum number of operations allowed for the flexible transformer; (5) Comprehensive reactive power compensation operation constraints, (9) In the formula, is the number of capacitor groups switched at node i in period t; It is the reactive power generated by a single group of capacitors at rated voltage; is the maximum number of capacitor groups switched at node i; It is a 0,1 variable, and its 0,1 state indicates whether the capacitor bank at node i in period t will be switched on at the next moment; The maximum number of permissible operations of group switching capacitors within 24 hours; , are the upper and lower limits of reactive power allowed to be generated by the static VAR compensator at node i; (6) Power factor operating constraints, (10).
[0010] In S5, the solution process is: Step 1, load the system real-time data information and model; Load the power load information of the low-voltage distribution feeder terminal node and the medium-voltage distribution circuit information required for voltage-reactive power control, and collect real-time data and models; the specific content includes the voltage, current, active power, reactive power, power factor and other parameters on each distribution circuit bus, and the tap position of the flexible on-load tap-changing transformer, capacitor, and reactor outgoing line switch position signal; Step 2, initial power flow calculation; Before the construction power supply system reactive power voltage optimization control is carried out, a power flow calculation is performed; the voltage calculated by the power flow in this process is used as the basis for judging whether the voltage exceeds the limit in Step 3; the power calculated by the power flow in this process is used as the basis for judging whether the power factor exceeds the limit in Step 5; the network loss calculated by the power flow in this process is used as the initial network loss for reactive power optimization of the construction power supply system in Step 6; Step 3, voltage over-limit judgment and correction; Step 3-1, determine whether there is a voltage over-limit based on the initial voltage of each feeder running independently, and end if all voltage nodes are within the normal range; Step 3-2, if there is an over-limit, further analyze the voltage over-limit degree and the cause of the over-limit; Step 3-3, determine whether the over-limit amount is within 10% based on the over-limit situation. If it exceeds 10%, there are many voltage over-limit nodes at this time, and it is necessary to further execute the optimization algorithm to constrain and correct the node voltage and branch power. When the requirements are met, the optimization iteration is exited; Step 3-4: If the voltage exceeds the limit by less than 10%, the voltage exceeding the limit is eliminated by hierarchical management of typical power quality problems layer by layer in the order from the load side to the grid side, that is, in the order from low to high voltage levels.
[0011] Step 4: Identify and manage typical power quality issues in a hierarchical manner; Step 4-1, determine whether there is a large line impedance based on the collected information; if so, implement local compensation by configuring a comprehensive compensation power electronic device consisting of a capacitor bank, further control the switching of the capacitor bank according to the change of the on-load voltage regulator gear position, realize a combination of multiple compensation capacities, estimate the action value of the control device required to eliminate the over-limit through the pre-calculated initial voltage, and make timely adjustments according to the terminal load working state or voltage changes; if not, proceed to the next step of judgment; Step 4-2, detect whether there is an impact current or power mutation in the distribution feeder according to the real-time data of the line; if there is, the distribution power transformer at the key node uses the flexible on-load voltage regulation control scheme to continuously adjust the voltage and reactive power at the low-voltage distribution station level, and perform reactive power-voltage compensation for the load at the lower end of the transformer; if there is no impact current or power mutation in the distribution feeder according to the real-time data of the line; if there is no impact current or power mutation in the distribution feeder according to the real-time data of the line, the next step of judgment is performed; Step 4-3, determine whether the power of different low-voltage distribution network feeders is unevenly distributed or exceeds the upper limit of the power threshold of a single area based on the distribution circuit bus data; at this time, due to the heavy load of the substation, the control device of a single area has reached the control constraint limit and cannot be further adjusted, so it seeks help from other areas of the same level. By configuring a power electronic flexible interconnection device, the power flow between multiple areas is regulated at the system level, the uneven power distribution is adjusted, the reactive power and voltage control between multiple areas are realized, and the voltage and reactive power balance regulation between multiple areas is realized.
[0012] Step 5: Power factor over-limit judgment and correction; If all power nodes are within the normal range, the operation ends; if there is a power over-limit, further analyze the cause of the power over-limit and eliminate the power over-limit; judge and correct the reference voltage over-limit, and make comprehensive adjustments through the power control of the flexible interconnection device, the flexible on-load voltage regulation tap position, and the switching of compensation capacitors and reactors, and then correct the power factor according to the real-time indicators and expected indicators to solve the problem of active and reactive power flow over-limit; Step 6: Global voltage-reactive power optimization; When the node voltage and power factor of the system are within the normal range, the next step of global reactive power optimization calculation and operation is carried out. According to the multi-objective function of the system, including the requirements of the constraints, the optimization goal of minimizing the loss of the construction power supply system is achieved, thereby improving the economy of the system operation. Step 7: Iterate the optimization layer by layer until the end condition is met and the voltage and power of all nodes are within the normal range; The voltage-reactive hierarchical coordinated control of the power supply system for construction of a pumped storage power station has complex optimization objectives and many constraints. It is a multidimensional nonlinear optimization model MOMINP. The improved Non-dominated Sorting Genetic Algorithm II with elite strategy, NSGA-II, is selected to solve the MOMINP model.
[0013] The main beneficial effects of the present invention are: Consider multi-level and graded management of typical power quality problems such as long power supply radius, impact load access, uneven power distribution or heavy load in the substation, and finally realize the voltage-reactive comprehensive regulation of the pumped storage construction power supply system through global reactive power optimization, so as to solve the problems of large reactive power loss of distribution network lines and unstable terminal voltage in the pumped storage power station construction power supply system, improve the power reliability, stability and economy of the pumped storage power station construction power supply system, and improve the power quality of the system.
[0014] First, voltage over-limit control is performed, followed by voltage reactive power optimization control; if the voltage is qualified, the power factor over-limit judgment and correction are performed.
[0015] Global voltage-reactive power optimization and layer-by-layer iterative global reactive power optimization are performed only when the voltage is qualified and the power factor does not exceed the limit.
[0016] If the voltage exceeds the limit, the degree of voltage exceeding the limit is judged. If it is within the threshold of the exceeding node, typical power quality problems are judged and managed in a hierarchical manner, power factor exceeding the limit is judged and corrected, and global voltage-reactive power optimization is performed in turn to achieve hierarchical coordinated control.
[0017] If the hierarchical coordination fails due to a large number of out-of-limit nodes outside the out-of-limit node threshold, global optimization is used to supplement the out-of-limit correction until the voltage and power of all nodes are within the normal range, thereby achieving system loss reduction and energy saving.
[0018] For different typical power quality problems, hierarchical management is carried out layer by layer from the load side to the grid side. In the hierarchical management process, voltage, reactive current, reactive power, power factor, etc. are used as the basic criteria for compensation control switching. A multi-objective function model is further constructed with minimum network loss, power factor and voltage deviation, considering the equipment and system operation constraints. Finally, the optimal voltage-reactive comprehensive compensation scheme for the pumped storage construction power supply system is obtained through repeated iterations of NSGA-II, thereby effectively solving the problems of large reactive power loss of distribution network lines and unstable terminal voltage in the pumped storage power station construction power supply system, and improving the power quality of the system. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] The present invention will be further described below in conjunction with the accompanying drawings and embodiments.
[0020] Figure 1 A diagram of the voltage-reactive power hierarchical coordinated compensation control architecture optimized for operation of the present invention.
[0021] Figure 2 This is the flow chart of solving the multi-objective MOMINP model using the improved NSGA-II algorithm of the present invention. DETAILED DESCRIPTION
[0022] like Figure 1~Figure 2 In the present invention, a voltage-reactive power compensation control strategy for a pumped storage construction power supply system based on the hierarchical compensation principle is provided, which comprises the following steps: S1, the overall model, implements a multi-objective decision-making control scheme based on hierarchical coordinated compensation for the location and capacity selection of DG, capacitor banks, and OLTC equipment in the construction power supply system; the optimization control model of the pumped storage construction power supply system is expressed as: (1) Where: is the overall objective function, , , is the sub-objective function; , It is the constraints related to the system and equipment; are system decision variables and system operation state variables respectively; the model is an overall voltage-reactive power hierarchical coordinated optimization control model; S2, control variables, including decision vector and state vector; S2-1, decision vector represents the decision vector of the optimization control model consisting of m control variables in the kth hierarchical optimization control cycle; the decision vector xk includes the tap position of the OLTC , Number of switched capacitor groups , SNOP's active and reactive power and and ; S2-2, state vector represents the state vector of the optimization control model composed of m control variables in the kth hierarchical optimization control cycle; the state vector Including the real-time active and reactive power of each node load and , predicted power and , node voltage and branch current And power factor ; S3, objective function, the objective function F(x k ,u k ,t) consists of three levels of objective functions, namely: the planning scheme F1(xk,uk,t) with the optimal control of distribution network voltage as the goal decision, the planning scheme F2(x k ,u k ,t), the planning scheme F3 (x k ,u k ,t); S4, constraints, including power flow constraints, node voltage and branch current constraints, flexible interconnection device operation constraints, flexible transformer operation constraints, comprehensive reactive power compensation operation constraints and power factor operation constraints; S5, solution, includes loading system real-time data information and models, initial power flow calculation, voltage over-limit judgment and correction, typical power quality problem judgment and hierarchical management, power factor over-limit judgment and correction, global voltage-reactive power optimization and layer-by-layer iterative optimization.
[0023] In the preferred solution, in S2, the decision vector The maximum dimension of is determined by the total number of DG stations, feeder and substation CBs, OLTCs in the distribution network, and the active and reactive power of SNOPs in the interconnected area. The actual dimension of is determined by the pre-decision method proposed at each level; the state vector The maximum dimension of is determined by the real-time active and reactive power and predicted power of each node load in the distribution network, the node voltage and branch current, and the power factor of the feeder and load. The actual dimension of the state vector uk is determined by the pre-decision method proposed at each level during each optimization.
[0024] In the preferred solution, in S3, the hierarchical optimization model of the entire power supply system is expressed as: (1) Optimal control target of construction power supply system voltage: (2)
[0025] (2) Optimal control target of power factor of construction power supply system: (3)
[0026] (3) Objective of minimizing active power loss of construction power supply system: (4) .
[0027] In the preferred solution, in S4, (1) power flow constraint, (5) In the formula, , is the active power and reactive power injected by the generator at node i; , is the active power and reactive power injected by the load on node i; , is the voltage at node i and node j, is the conductance between node i and node j, is the susceptance between node i and node j, is the phase angle difference between node i and node j; (2) Node voltage and branch current constraints, (6) In the formula, and They are the upper and lower limits of the node voltage amplitude in the system respectively; is the current amplitude of branch ij, is the upper limit of the current amplitude of branch ij; (3) Operation constraints of flexible interconnection devices, (7) In the formula, and are the operating losses of the converters on the i and j sides in SNOP respectively; k is the loss coefficient of the converter; is the rated capacity of the SNOP converter; (4) Flexible transformer operation constraints, (8) In the formula, is the voltage on the high-voltage side of the flexible transformer, which is a constant; is the transformation ratio of the flexible transformer at time t; is the tap position at time t, which is an integer variable; is the ratio difference between adjacent gears; , are the maximum gear and minimum gear of the tap respectively; is a 0,1 variable. If it is 1, it means that the tap position of the on-load tap-changing transformer has changed. If it is 0, it means that the tap position remains unchanged; The maximum number of operations allowed for the flexible transformer; (5) Comprehensive reactive power compensation operation constraints, (9) In the formula, is the number of capacitor groups switched at node i in period t; It is the reactive power generated by a single group of capacitors at rated voltage; is the maximum number of capacitor groups switched at node i; It is a 0,1 variable, and its 0,1 state indicates whether the capacitor bank at node i in period t will be switched on at the next moment; The maximum number of permissible operations of group switching capacitors within 24 hours; , are the upper and lower limits of reactive power allowed to be generated by the static VAR compensator at node i; (6) Power factor operating constraints, (10).
[0028] In the preferred solution, in S5, the solution process is: Step 1, load the system real-time data information and model; Load the power load information of the low-voltage distribution feeder terminal node and the medium-voltage distribution circuit information required for voltage-reactive power control, and collect real-time data and models; the specific content includes the voltage, current, active power, reactive power, power factor and other parameters on each distribution circuit bus, and the tap position of the flexible on-load tap-changing transformer, capacitor, and reactor outgoing line switch position signal; Step 2, initial power flow calculation; Before the construction power supply system reactive power voltage optimization control is carried out, a power flow calculation is performed; the voltage calculated by the power flow in this process is used as the basis for judging whether the voltage exceeds the limit in Step 3; the power calculated by the power flow in this process is used as the basis for judging whether the power factor exceeds the limit in Step 5; the network loss calculated by the power flow in this process is used as the initial network loss for reactive power optimization of the construction power supply system in Step 6; Step 3, voltage over-limit judgment and correction; Step 3-1, determine whether there is a voltage over-limit based on the initial voltage of each feeder running independently, and end if all voltage nodes are within the normal range; Step 3-2, if there is an over-limit, further analyze the voltage over-limit degree and the cause of the over-limit; Step 3-3, determine whether the over-limit amount is within 10% based on the over-limit situation. If it exceeds 10%, there are many voltage over-limit nodes at this time, and it is necessary to further execute the optimization algorithm to constrain and correct the node voltage and branch power. When the requirements are met, the optimization iteration is exited; Step 3-4: If the voltage exceeds the limit by less than 10%, the voltage exceeding the limit is eliminated by hierarchical management of typical power quality problems layer by layer in the order from the load side to the grid side, that is, in the order from low to high voltage levels.
[0029] In the preferred solution, Step 4, typical power quality problem judgment and hierarchical management; Step 4-1, determine whether there is a large line impedance based on the collected information; if so, implement local compensation by configuring a comprehensive compensation power electronic device consisting of a capacitor bank, further control the switching of the capacitor bank according to the change of the on-load voltage regulator gear position, realize a combination of multiple compensation capacities, estimate the action value of the control device required to eliminate the over-limit through the pre-calculated initial voltage, and make timely adjustments according to the terminal load working state or voltage changes; if not, proceed to the next step of judgment; Step 4-2, detect whether there is an impact current or power mutation in the distribution feeder according to the real-time data of the line; if there is, the distribution power transformer at the key node uses the flexible on-load voltage regulation control scheme to continuously adjust the voltage and reactive power at the low-voltage distribution station level, and perform reactive power-voltage compensation for the load at the lower end of the transformer; if there is no impact current or power mutation in the distribution feeder according to the real-time data of the line; if there is no impact current or power mutation in the distribution feeder according to the real-time data of the line, the next step of judgment is performed; Step 4-3, determine whether the power of different low-voltage distribution network feeders is unevenly distributed or exceeds the upper limit of the power threshold of a single area based on the distribution circuit bus data; at this time, due to the heavy load of the substation, the control device of a single area has reached the control constraint limit and cannot be further adjusted, so it seeks help from other areas of the same level. By configuring a power electronic flexible interconnection device, the power flow between multiple areas is regulated at the system level, the uneven power distribution is adjusted, the reactive power and voltage control between multiple areas are realized, and the voltage and reactive power balance regulation between multiple areas is realized.
[0030] In the preferred solution, Step 5: over-limit judgment and correction of power factor; If all power nodes are within the normal range, the operation ends; if there is a power over-limit, further analyze the cause of the power over-limit and eliminate the power over-limit; judge and correct the reference voltage over-limit, and make comprehensive adjustments through the power control of the flexible interconnection device, the flexible on-load voltage regulation tap position, and the switching of compensation capacitors and reactors, and then correct the power factor according to the real-time indicators and expected indicators to solve the problem of active and reactive power flow over-limit; Step 6: Global voltage-reactive power optimization; When the node voltage and power factor of the system are within the normal range, the next step of global reactive power optimization calculation and operation is carried out. According to the multi-objective function of the system, including the requirements of the constraints, the optimization goal of minimizing the loss of the construction power supply system is achieved, thereby improving the economy of the system operation. Step 7: Iterate the optimization layer by layer until the end condition is met and the voltage and power of all nodes are within the normal range; The voltage-reactive hierarchical coordinated control of the power supply system for construction of a pumped storage power station has complex optimization objectives and many constraints. It is a multidimensional nonlinear optimization model MOMINP. The improved Non-dominated Sorting Genetic Algorithm II with elite strategy, NSGA-II, is selected to solve the MOMINP model.
[0031] Preferably, in the above architecture, voltage over-limit control is performed first, and voltage reactive power optimization control is performed secondly.
[0032] Preferably, if the voltage is qualified, a judgment is made in Step 5 as to whether the power factor exceeds the limit, and global reactive power optimization in Steps 6 and 7 is performed only when the voltage is qualified and the power factor does not exceed the limit.
[0033] Preferably, if there is a voltage over-limit, step 3 is performed to determine the voltage over-limit degree. If it is within the over-limit node threshold, step 4, step 5, and step 6 are performed in sequence to perform hierarchical coordinated control.
[0034] Preferably, if the hierarchical coordination fails due to a large number of out-of-limit nodes outside the out-of-limit node threshold, global optimization is used to supplement the out-of-limit correction; until the voltage and power of all nodes are within the normal range, the system loss reduction and energy saving are achieved.
[0035] Consider multi-level and graded management of typical power quality problems such as long power supply radius, impact load access, uneven power distribution or heavy load in the substation, and finally realize the voltage-reactive comprehensive regulation of the pumped storage construction power supply system through global reactive power optimization, so as to solve the problems of large reactive power loss of distribution network lines and unstable terminal voltage in the pumped storage power station construction power supply system, improve the power reliability, stability and economy of the pumped storage power station construction power supply system, and improve the power quality of the system.
[0036] For different typical power quality problems, hierarchical management is carried out layer by layer from the load side to the grid side. In the hierarchical management process, voltage, reactive current, reactive power, power factor, etc. are used as the basic criteria for compensation control switching. A multi-objective function model is further constructed with minimum network loss, power factor and voltage deviation, considering the equipment and system operation constraints. Finally, the optimal voltage-reactive comprehensive compensation scheme for the pumped storage construction power supply system is obtained through repeated iterations of NSGA-II, thereby effectively solving the problems of large reactive power loss of distribution network lines and unstable terminal voltage in the pumped storage power station construction power supply system, and improving the power quality of the system.
[0037] The above-mentioned embodiments are only preferred technical solutions of the present invention and should not be regarded as limitations of the present invention. The embodiments and features in the embodiments of the present application can be arbitrarily combined with each other without conflict. The protection scope of the present invention shall be the technical solutions recorded in the claims, including the equivalent replacement solutions of the technical features in the technical solutions recorded in the claims. That is, equivalent replacement improvements within this scope are also within the protection scope of the present invention.
Claims
1. A voltage-reactive power compensation control strategy for a pumped storage construction power supply system based on the principle of graded compensation, characterized in that: It includes the following steps: S1, the overall model, implements a multi-objective decision-making control scheme based on hierarchical coordinated compensation for the location and capacity selection of DG, capacitor banks, and OLTC equipment in the construction power supply system; the optimization control model of the pumped storage construction power supply system is expressed as: (1) Where: is the overall objective function, , , is the sub-objective function; , It is the constraints related to the system and equipment; are system decision variables and system operation state variables respectively; the model is an overall voltage-reactive power hierarchical coordinated optimization control model; S2, control variables, including decision vector and state vector; S2-1, decision vector represents the decision vector of the optimization control model consisting of m control variables in the kth hierarchical optimization control cycle; the decision vector xk includes the tap position of the OLTC , Number of switched capacitor groups , SNOP's active and reactive power and and ; S2-2, state vector represents the state vector of the optimization control model composed of m control variables in the kth hierarchical optimization control cycle; the state vector Including the real-time active and reactive power of each node load and , predicted power and , node voltage and branch current And power factor ; S3, objective function, the objective function F(x k ,u k ,t) consists of three levels of objective functions, namely: the planning scheme F1(xk,uk,t) with the optimal control of distribution network voltage as the goal decision, the planning scheme F2(x k ,u k ,t), the planning scheme F3 (x k ,u k ,t); S4, constraints, including power flow constraints, node voltage and branch current constraints, flexible interconnection device operation constraints, flexible transformer operation constraints, comprehensive reactive power compensation operation constraints and power factor operation constraints; S5, solution, includes loading system real-time data information and models, initial power flow calculation, voltage over-limit judgment and correction, typical power quality problem judgment and hierarchical management, power factor over-limit judgment and correction, global voltage-reactive power optimization and layer-by-layer iterative optimization.
2. The voltage-reactive power compensation control strategy for the pumped storage construction power supply system based on the hierarchical compensation principle according to claim 1 is characterized by: In S2, the decision vector The maximum dimension of is determined by the total number of DG stations, feeder and substation CBs, OLTCs in the distribution network, and the active and reactive power of SNOPs in the interconnected area. The actual dimension of is determined by the pre-decision method proposed at each level; the state vector The maximum dimension of is determined by the real-time active and reactive power and predicted power of each node load in the distribution network, the node voltage and branch current, and the power factor of the feeder and load. The actual dimension of the state vector uk is determined by the pre-decision method proposed at each level during each optimization.
3. The voltage-reactive power compensation control strategy for the pumped storage construction power supply system based on the hierarchical compensation principle according to claim 1 is characterized by: In S3, the hierarchical optimization model of the entire power supply system is expressed as: (1) Optimal control target of construction power supply system voltage: (2) (2) Optimal control target of power factor of construction power supply system: (3) (3) Objective of minimizing active power loss of construction power supply system: (4) 。 4. The voltage-reactive power compensation control strategy for the pumped storage construction power supply system based on the hierarchical compensation principle according to claim 1 is characterized by: In S4, (1) power flow constraints, (5) In the formula, , is the active power and reactive power injected by the generator at node i; , is the active power and reactive power injected by the load on node i; , is the voltage at node i and node j, is the conductance between node i and node j, is the susceptance between node i and node j, is the phase angle difference between node i and node j; (2) Node voltage and branch current constraints, (6) In the formula, and They are the upper and lower limits of the node voltage amplitude in the system respectively; is the current amplitude of branch ij, is the upper limit of the current amplitude of branch ij; (3) Operation constraints of flexible interconnection devices, (7) In the formula, and are the operating losses of the converters on the i and j sides in SNOP respectively; k is the loss coefficient of the converter; is the rated capacity of the SNOP converter; (4) Flexible transformer operation constraints, (8) In the formula, is the voltage on the high-voltage side of the flexible transformer, which is a constant; is the transformation ratio of the flexible transformer at time t; is the tap position at time t, which is an integer variable; is the ratio difference between adjacent gears; , are the maximum gear and minimum gear of the tap respectively; is a 0,1 variable. If it is 1, it means that the tap position of the on-load tap changer has changed. If it is 0, it means that the tap position remains unchanged; The maximum number of operations allowed for the flexible transformer; (5) Comprehensive reactive power compensation operation constraints, (9) In the formula, is the number of capacitor groups switched at node i in period t; It is the reactive power generated by a single group of capacitors at rated voltage; is the maximum number of capacitor groups switched at node i; It is a 0,1 variable, and its 0,1 state indicates whether the capacitor bank at node i in period t will be switched on at the next moment; The maximum number of permissible operations of group switching capacitors within 24 hours; , are the upper and lower limits of reactive power allowed to be generated by the static VAR compensator at node i; (6) Power factor operating constraints, (10)。 5. The voltage-reactive power compensation control strategy for the pumped storage construction power supply system based on the hierarchical compensation principle according to claim 1 is characterized by: In S5, the solution process is: Step 1, load the system real-time data information and model; Load the power load information of the low-voltage distribution feeder terminal node and the medium-voltage distribution circuit information required for voltage-reactive power control, and collect real-time data and models; the specific content includes the voltage, current, active power, reactive power, power factor and other parameters on each distribution circuit bus, and the tap position of the flexible on-load tap-changing transformer, capacitor, and reactor outgoing line switch position signal; Step 2, initial power flow calculation; Before the construction power supply system reactive power voltage optimization control is carried out, a power flow calculation is performed; the voltage calculated by the power flow in this process is used as the basis for judging whether the voltage exceeds the limit in Step 3; the power calculated by the power flow in this process is used as the basis for judging whether the power factor exceeds the limit in Step 5; the network loss calculated by the power flow in this process is used as the initial network loss for reactive power optimization of the construction power supply system in Step 6; Step 3, voltage over-limit judgment and correction; Step 3-1, determine whether there is a voltage over-limit based on the initial voltage of each feeder running independently, and end if all voltage nodes are within the normal range; Step 3-2, if there is an over-limit, further analyze the voltage over-limit degree and the cause of the over-limit; Step 3-3, determine whether the over-limit amount is within 10% based on the over-limit situation. If it exceeds 10%, there are many voltage over-limit nodes at this time, and it is necessary to further execute the optimization algorithm to constrain and correct the node voltage and branch power. When the requirements are met, the optimization iteration is exited; Step 3-4: If the voltage exceeds the limit by less than 10%, the voltage exceeding the limit is eliminated by hierarchical management of typical power quality problems layer by layer in the order from the load side to the grid side, that is, in the order from low to high voltage levels.
6. The voltage-reactive power compensation control strategy for the pumped storage construction power supply system based on the hierarchical compensation principle according to claim 5 is characterized by: Also includes, Step 4: Identify and manage typical power quality issues in a hierarchical manner; Step 4-1, determine whether there is a large line impedance based on the collected information; if so, implement local compensation by configuring a comprehensive compensation power electronic device consisting of a capacitor bank, further control the switching of the capacitor bank according to the change of the on-load voltage regulator gear position, realize a combination of multiple compensation capacities, estimate the action value of the control device required to eliminate the over-limit through the pre-calculated initial voltage, and make timely adjustments according to the terminal load working state or voltage changes; if not, proceed to the next step of judgment; Step 4-2, detect whether there is an impact current or power mutation in the distribution feeder according to the real-time data of the line; if there is, the distribution power transformer at the key node uses the flexible on-load voltage regulation control scheme to continuously adjust the voltage and reactive power at the low-voltage distribution station level, and perform reactive power-voltage compensation for the load at the lower end of the transformer; if there is no impact current or power mutation in the distribution feeder according to the real-time data of the line; if there is no impact current or power mutation in the distribution feeder according to the real-time data of the line, the next step of judgment is performed; Step 4-3, determine whether the power of different low-voltage distribution network feeders is unevenly distributed or exceeds the upper limit of the power threshold of a single area based on the distribution circuit bus data; at this time, due to the heavy load of the substation, the control device of a single area has reached the control constraint limit and cannot be further adjusted, so it seeks help from other areas of the same level. By configuring a power electronic flexible interconnection device, the power flow between multiple areas is regulated at the system level, the uneven power distribution is adjusted, the reactive power and voltage control between multiple areas are realized, and the voltage and reactive power balance regulation between multiple areas is realized.
7. The voltage-reactive power compensation control strategy for the pumped storage construction power supply system based on the hierarchical compensation principle according to claim 6 is characterized by: Also includes, Step 5: Power factor over-limit judgment and correction; If all power nodes are within the normal range, the operation ends; if there is a power over-limit, further analyze the cause of the power over-limit and eliminate the power over-limit; judge and correct the reference voltage over-limit, and make comprehensive adjustments through the power control of the flexible interconnection device, the flexible on-load voltage regulation tap position, and the switching of compensation capacitors and reactors, and then correct the power factor according to the real-time indicators and expected indicators to solve the problem of active and reactive power flow over-limit; Step 6: Global voltage-reactive power optimization; When the node voltage and power factor of the system are within the normal range, the next step of global reactive power optimization calculation and operation is carried out. According to the multi-objective function of the system, including the requirements of the constraints, the optimization goal of minimizing the loss of the construction power supply system is achieved, thereby improving the economy of the system operation. Step 7: Iterate the optimization layer by layer until the end condition is met and the voltage and power of all nodes are within the normal range; The voltage-reactive hierarchical coordinated control of the power supply system for construction of a pumped storage power station has complex optimization objectives and many constraints. It is a multidimensional nonlinear optimization model MOMINP. The improved Non-dominated Sorting Genetic Algorithm II with elite strategy, NSGA-II, is selected to solve the MOMINP model.
Citation Information
Patent Citations
Enterprise power grid reactive power optimization method and system based on comprehensive benefit analysis
CN103595061A
Substation dynamic reactive power optimization method and system based on improved bat algorithm
CN105406485A
Mixed integer cone programming based intelligent distribution system synthetic voltage reactive power optimization method
CN105740973A
Voltage reactive power optimization control method and system for photovoltaic power generation access
CN106208090A
Active distribution grid load flow calculation method
CN106849097A
Cited By
Reactive compensation configuration method
CN120300824A
High-density composite fluid regulation and control method for pumping and storage system
CN121093862A
Water storage joint debugging system for synergic phase modulation of super capacitor and pumped storage
CN121791226A