Tunnel work efficiency management system

By designing a tunnel efficiency management system and using advanced data collection and transmission technology, real-time monitoring and management of tunnel construction progress is achieved, solving the problems of inaccurate manual recording and cumbersome data management, improving construction efficiency and quality, and promoting information Share and collaborate.

CN119358944APending Publication Date: 2025-01-24CHINA RAILWAY 12TH BUREAU GRP CO LTD +1
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202411512146.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-28
Publication Date
2025-01-24

AI Technical Summary

Technical Problem

During tunnel construction, manual recording of the time, progress and problems of construction process are inaccurate and difficult to query, and data management is complicated, prone to errors, easily lost or damaged, affecting the optimization of construction management and the scientific nature of decision-making.

Method used

Design a tunnel efficiency management system, including data collection system, data transmission system, data system, tunnel information management system and personnel management system, using ultra-wideband UWB positioning base station, access control gate and positioning card for data collection and transmission, through management Databases, GIS spatial databases, etc. are used for data storage and analysis to achieve real-time monitoring and data sharing.

Benefits of technology

Realize the remote real -time monitoring and management of tunnel construction progress, improve construction efficiency and quality, promote information sharing and collaboration between different departments, and improve the scientificity and effectiveness of construction management.

✦ Generated by Eureka AI based on patent content.
Patent Text Reader

Abstract

The invention relates to the technical field of tunnel construction, in particular to a tunnel work efficiency management system. Real-time data communication is carried out between construction site sensing equipment and a software platform, real-time position information of personnel and machinery, working condition information of a construction area and personnel access information are transmitted to a data processing server in real time, and the current construction process is judged through a system algorithm, so that process time consumption, interval time and cycle operation time of tunnel construction are calculated. According to the method, the reasonability and stability of the construction progress can be comprehensively evaluated, the situation that the progress is lagged or advanced can be found in time, the development trend of the follow-up construction progress is predicted, a scientific basis is provided for adjustment of a construction plan and reasonable allocation of resources, and it is ensured that tunnel construction can be smoothly carried out according to preset time nodes and quality requirements. The method is mainly applied to a tunnel work efficiency management system.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of tunnel construction, and more specifically, to a tunnel work efficiency management system. Background Art

[0002] During tunnel construction, tunnel production dispatchers need to manually record the construction time, progress and problems encountered during the construction process of each part during the inspection of each construction area in the tunnel. However, manual records are prone to typos and unclear handwriting, which leads to inaccurate recorded information and difficulty in query. At the same time, environmental factors such as light and dust in the tunnel may also affect record archiving. The recorded data must be regularly entered into electronic spreadsheets for archiving. This process is cumbersome and error-prone. In addition, paper records are easily lost and damaged, which brings inconvenience to data management.

[0003] During regular construction meetings, managers will make detailed statistics on the time taken for each process this week, and through simple statistical analysis, they will look for problems with process connection or delays. However, manual recording makes it difficult to achieve real-time updates of construction data, which leads to processing delays for construction issues that require a quick response. When the amount of data is large, it is difficult to conduct effective data mining and analysis, which limits the optimization of construction management and the scientific nature of decision-making.

[0004] When performing progress analysis, the Engineering Management Department summarizes the progress analysis report based on the experience of the on-site dispatchers and makes overall scheduling arrangements. However, different inspectors may have different recording habits and standards, resulting in differences in the format and content of the recorded data, making it difficult to manage and analyze them in a unified manner. Summary of the invention

[0005] In order to solve the above technical problems, the present invention provides a tunnel work efficiency management system. The management system assists the project to strengthen the control of construction progress, provides effective monitoring means, helps construction managers to find problems in time, improve efficiency and quality; promotes information sharing and collaboration between different departments, grasps the situation on the construction site in real time and remotely dispatches collaboration, and improves construction efficiency.

[0006] In order to solve the above technical problems, the technical solution adopted by the present invention is: A tunnel work efficiency management system, a data collection system, a data transmission system, a data system, a tunnel information management system and a personnel management system; The data acquisition system includes an ultra-wideband UWB positioning base station, an access control gate and a positioning card; The data transmission system is to construct a heterogeneous network, including active roaming access technology; The data system includes a management database, a data model library, a business database and a GIS spatial database. Various types of data at the front end of tunnel construction are classified and stored in each database and provided to the platform application for comprehensive use; The information management system includes a tunnel basic information module and a tunnel surrounding rock grade recording module. The tunnel basic information module demarcates the attendance area of ​​the construction area and communicates with the personnel gate in the construction area; the tunnel surrounding rock grade recording module updates the surrounding rock distribution of the tunnel in real time; The personnel management system adopts a real-name system with one card for each person. When all relevant personnel are entered, they will be bound to the positioning card. When the corresponding personnel carry the positioning card, all areas and locations of the corresponding personnel can be identified; It also includes a construction record module, an early warning management module, a tunnel dispatch command center module, and a tunnel data analysis module; The construction record module graphically displays the ongoing cycle construction process; displays the completed construction process and cycle record information in a table; when the automatic process fails to start due to a power outage system fault light problem, the execution status of the process can be manually reported; The warning management module includes disconnection timeout alarm, surrounding rock grade change alarm, emergency rescue, process standard working time timeout alarm, cycle timeout alarm and low power alarm; The tunnel dispatching and command center module summarizes and analyzes various data, displays the overall construction progress of the tunnel, daily, weekly and monthly construction footage, visually tracks the personnel distribution and construction status in the tunnel, and provides intuitive chart display of process records, personnel information statistics and early warning record viewing; The tunnel data analysis module is used to predict and analyze the progress of the tunnel in the next 30 days: actual completion rate: actual completion / total length*100%, progress in the next month: (the amount of excavation in the next month + the actual amount completed) / total length*100%, the number of cycles per month X=30 days*(24 hours / time per cycle Y), the monthly footage C=the number of cycles per month X*L1, L1: take the mode of the footage this month under the current surrounding rock grade.

[0007] The ultra-wideband UWB positioning base station is installed on a waterproof trolley, and a blasting vibration meter is also installed. The heading face and the 250-meter range near the lining trolley are designated as key construction control areas for the tunnel.

[0008] The personnel management system includes subcontracting unit management: maintaining project subcontracting units, team management: maintaining all team information of subcontracting units, personnel roster: maintaining tunnel construction personnel roster, personnel entry and exit records: through gate machines or personnel positioning systems, personnel entering and exiting the electronic area will generate corresponding entry and exit information, thereby forming a personnel entry and exit ledger record, and personnel positioning records: the positioning system reflects changes in personnel location.

[0009] The construction record module also includes process record correction and footage statistics. Process record correction: deviations in automatic process records can be corrected manually; footage statistics: after each cycle is completed, the footage is automatically counted according to the mileage pile number.

[0010] The disconnection timeout alarm: using automated monitoring technology, accurately recording construction in and out through the positioning system electronic fence, real-time analysis of process connection, once a disconnection is found, an immediate intelligent warning, and a graded warning notification can be designed according to the different durations of disconnection; the surrounding rock grade change warning: when the surrounding rock grade predicted by geological advance in the construction stage differs from the surrounding rock grade in the design stage, the surrounding rock information table is updated, and timely warnings are given to various production departments to help tunnel safety and dynamic scheduling; the emergency rescue: the positioning card worn by the construction personnel has a one-button rescue function. When encountering an unexpected situation, press the one-button rescue button for help. The monitoring center will receive the rescue alarm information in time, locate the location information of the rescue personnel, and implement fast and accurate rescue; the process standard working time timeout warning: set the standard time for each process, and give a graded warning when it exceeds the process standard time; the cycle timeout warning: set the standard time for each cycle, and give a graded warning when it exceeds the process standard time; low power warning: set the warning power intelligence, and give a warning when it is lower than the warning power.

[0011] The tunnel dispatching and command center module includes tunnel overview: basic information of the tunnel, including the entire tunnel, excavation mileage, completion of each sub-item construction, and tunnel introduction; footage statistics: when a cycle is completed, the footage is automatically calculated according to the mileage pile number; construction progress overview: two-dimensional tunnel simulation diagram, personnel location distribution, surrounding rock grade distribution, construction point distribution, real-time step distance; construction process statistics: through the combination of personnel, machinery, and sensors, the start and end time of each process of each tunnel working cycle and the interval time between adjacent processes are displayed in the form of bar charts and tables; on-site personnel: display the total number of tunnel construction personnel, the number of on-duty personnel, the number of attendance personnel in each team, the real-time number of personnel and attendance rate; warning records: display process disconnection warning, long-term personnel stationary, and emergency rescue warning records.

[0012] Compared with the prior art, the present invention has the following beneficial effects: It can remotely and comprehensively understand the progress of the project, the real-time use of manpower and mechanical materials, and other aspects, so as to achieve efficient and powerful control of the construction site; analyze the efficiency of manpower and machinery, conduct cost accounting and risk analysis of the construction process, control potential risks such as quality and progress, and avoid unnecessary waste; make efficient decisions based on historical data, such as choosing the best construction process, rather than blindly trying, to ensure the scientificity and effectiveness of the decision, and improve the management level; can deeply analyze the management order and construction efficiency during the construction process, accurately evaluate the speed and management status of the project progress of each unit, and help optimize cooperation and asset appreciation; promote information sharing and collaboration between different departments through the synchronization of construction data and decision-making data. For example, if the surrounding rock conditions change or the construction is interrupted during the construction process, promptly notify all relevant decision makers to change the construction strategy as soon as possible; rely on the system to provide automatically monitored standardized construction process data and analysis results, which is helpful to optimize the construction process management, and can display standardized management results during bidding. The construction site can use data to avoid liability disputes, such as using construction records to avoid wage disputes. DETAILED DESCRIPTION

[0013] In order to more clearly understand the above-mentioned purpose, features and advantages of the present invention, the present invention is further described in detail below in conjunction with specific embodiments. It should be noted that the embodiments of the present application and the features in the embodiments can be combined with each other without conflict.

[0014] In the following description, many specific details are set forth to facilitate a full understanding of the present invention. However, the present invention may also be implemented in other ways different from the description. Therefore, the protection scope of the present invention is not limited to the specific embodiments disclosed below.

[0015] A tunnel work efficiency management system, comprising a data acquisition system, a data transmission system, a data system, a tunnel information management system and a personnel management system; The data collection system includes ultra-wideband UWB positioning base station, access control gate and positioning card; The data transmission system is used to build a heterogeneous network, including active roaming access technology; the network is set up to ensure the continuity and stability of communication inside the tunnel.

[0016] The data system includes management database, data model library, business database and GIS spatial database. Various data at the front end of tunnel construction are classified and stored in various databases and provided to platform applications for comprehensive use; The information management system includes a tunnel basic information module and a tunnel surrounding rock grade recording module. The tunnel basic information module demarcates the attendance area of ​​the construction area and communicates with the personnel gate in the construction area. It is suitable for basic information maintenance scenarios of different sections of the tunnel, and can simultaneously demarcate the attendance area. After the personnel gate is installed, both attendance information and synchronous entry and exit personnel records can be obtained. The construction progress of the excavation, invert, and secondary lining sub-projects can be manually updated and maintained. The tunnel surrounding rock grade recording module updates the surrounding rock distribution of the tunnel in real time; when the surrounding rock grade changes, an early warning can be issued to inform the corresponding staff to adjust the corresponding plans and measures for the changed surrounding rock grade in a timely manner.

[0017] The personnel management system adopts a real-name system with one card for each person. When all relevant personnel are entered, they will be bound to the positioning card. When the corresponding personnel carry the positioning card, all areas and locations of the corresponding personnel can be identified; It also includes a construction record module, an early warning management module, a tunnel dispatch command center module, and a tunnel data analysis module; The construction record module graphically displays the ongoing cycle construction process; displays the completed construction process and cycle record information in a table; when the automatic process fails to start due to a power outage system fault light problem, the execution status of the process can be manually reported; The early warning management module includes disconnection timeout alarm, surrounding rock grade change alarm, emergency rescue, process standard working time overtime alarm, cycle timeout alarm and low power alarm; The tunnel dispatching and command center module aggregates and analyzes various data, displays the overall construction progress of the tunnel, daily, weekly and monthly construction footage, visually tracks the personnel distribution and construction status in the tunnel, and provides intuitive chart display of process records, personnel information statistics and early warning record viewing; The tunnel data analysis module is used to predict and analyze the progress of the tunnel in the next 30 days: actual completion rate: actual completion / total length*100%, progress in the next month: (the number of excavations in the next month + the actual number of completions) / total length*100%, the number of monthly cycles X=30 days*(24 hours / each cycle time Y), the monthly footage C=the number of monthly cycles X*L1, L1: take the mode of the footage of this month under the current surrounding rock grade. Example: Each cycle takes 20 hours L1: 3 meters The number of monthly cycles = 30*(24 / 20) = 36 Monthly advance = 36*3 = 108 meters, which is equivalent to 108 meters of excavation in 36 cycles in the next month. However, the above excavation calculation is equivalent to the calculation under the same surrounding rock grade on the working days of the next month. The cycle time and footage remain unchanged. The actual number of cycles per month X = 30 days * (24 hours / each cycle time Y), the monthly footage C = the number of cycles per month * L L1: Take the mode of footage of level 1 surrounding rock grade last month as the footage of that grade next month L2: Take the mode of footage of level 2 surrounding rock grade last month as the footage of that grade next month L3: Take the mode of footage of level 3 surrounding rock last month as the footage of that level next month L4: Take the mode of footage of the 4th grade surrounding rock last month as the footage of the next month of that grade L5: Take the mode of footage of the 5th grade surrounding rock last month as the forecast of footage of the grade next month Assume that the first section starts from the current construction pile number and the current surrounding rock grade is grade 1 The footage is L1=2. We know that the surrounding rock grade 1 is 50 meters = C1. The time for each cycle is Y=30 Number of cycles this month X = C1 / L1 = 25 Number of days for excavation of surrounding rock grade 1 D1 = number of cycles this month X / (24 hours / time per cycle Y) D1=30 / (24 / 30)=24 D1<30 days D2=30-D1=6 The second section is the secondary surrounding rock grade Y=15 L2=3 C=20 X=6(24 / 15)=9.6 C2=X*L2=28.8 meters Is C2 less than the length of the surrounding rock grade 2 (c)? If less than then This month's footage C = C1 + C2 = 50 + 28.8 = 78.8 meters C2 is greater than the length of the surrounding rock grade 2. The required length of surrounding rock grade C2-2 is c2=28.8-20=8.8 D2 is calculated and then calculated according to the judgment of d1+d2 below In summary: The first section: Given footage L1 Time per cycle Y1 C1 It can be calculated that X=C1 / L1 D1=X / (24 / Y1) D1 and 26 days comparison D1=30, then excavation this month is C1 meters. D1<30, the second section is D2 C2. If D1+D2=30, then C=C1+C2 D1+D2>30 Then c2=((30-D1)24H / Y2) c=c1+c2 D1+D2<30 Continue to calculate the time Dn used for the next construction period until D1+D2+Dn>30, then Cn=(30-D1-D2-Dn)*24H / Yn)*Ln) C=C1+C2+....Cn D1>26 C=30*(24H / Y)*L Through real-time data communication between the sensing equipment on the construction site and the software platform, the real-time location information of personnel and machinery, the working condition information of the construction area, and the personnel access information are transmitted to the data processing server in real time. The combination of personnel and machinery in the construction area is converted into a process, and the time when personnel and machinery enter and exit the construction area is used to determine the start and end of the tunnel construction process. The system algorithm determines which construction process is currently in, so as to calculate the process time, interval time, and cycle operation time of the tunnel construction.

[0018] Preferably, an ultra-wideband UWB positioning base station is installed on a waterproof trolley, and a blasting vibration meter is also installed, and the heading face and the range of 250 meters near the lining trolley are designated as key construction control areas of the tunnel.

[0019] Preferably, the personnel management system includes subcontracting unit management: maintaining project subcontracting units, team management: maintaining all team information of subcontracting units, personnel roster: maintaining the tunnel construction personnel roster, personnel entry and exit records: through gate machines or personnel positioning systems, personnel entering and exiting the electronic area will generate corresponding entry and exit information, thereby forming a personnel entry and exit ledger record, and personnel positioning records: the positioning system reflects changes in personnel location.

[0020] Preferably, the construction record module also includes process record correction and footage statistics. Process record correction: deviations in automatic process records can be corrected manually; footage statistics: after each cycle is completed, the footage will be automatically counted according to the mileage pile number.

[0021] Optimally, the disconnection timeout alarm: using automated monitoring technology, accurately recording the construction entry and exit through the positioning system electronic fence, real-time analysis of process connection, once a disconnection is found, an immediate intelligent warning, and a graded warning notification can be designed according to the different durations of the disconnection; surrounding rock grade change warning: when the geological advance prediction of the surrounding rock grade in the construction stage is different from the surrounding rock grade in the design stage, the surrounding rock information table is updated, and timely warnings are given to various production departments to help tunnel safety and dynamic scheduling; emergency rescue: the positioning card worn by the construction personnel has a one-button call for help function. In case of an unexpected situation, press the one-button call for help button for help. The monitoring center will receive the rescue alarm information in time, locate the location information of the rescue personnel, and implement fast and accurate rescue; process standard working time overtime warning: set the standard time for each process, and give a graded warning when the process standard time is exceeded; cycle timeout warning: set the standard time for each cycle, and give a graded warning when the process standard time is exceeded; low power warning: set the warning power intelligence, and give a warning when the power is lower than the warning power.

[0022] Preferably, the tunnel dispatching and command center module includes tunnel overview: basic information of the tunnel, including the entire tunnel, excavation mileage, completion of each sub-item construction, and tunnel introduction; footage statistics: when a cycle is completed, the footage is automatically calculated according to the mileage pile number; construction progress overview: two-dimensional tunnel simulation diagram, personnel location distribution, surrounding rock grade distribution, construction point distribution, real-time step distance; construction process statistics: through the combination of personnel, machinery, and sensors, the start and end time of each process of each tunnel working cycle and the interval time between adjacent processes are displayed in the form of bar charts and tables; on-site personnel: display the total number of tunnel construction personnel, the number of on-duty personnel, the number of attendance personnel in each team, the real-time number of personnel and attendance rate; warning records: display process disconnection warnings, long-term personnel stationary, and emergency rescue warning records.

[0023] About equipment management: Equipment ledger: Maintenance of all equipment information in the cave, equipment operators and positioning cards are also bound. After binding, the corresponding equipment entering and leaving the work area will also be recorded; Blasting equipment ledger: Maintenance of blasting noise monitoring equipment; Blasting record and monitoring ledger: Blasting noise monitoring equipment will monitor all noise in the environment in real time, and set the unique decibel of blasting product noise according to data analysis and comparison to identify blasting to distinguish cycles. The records in the ledger can be checked to see if there are errors or suspected blasting.

[0024] Process management: used to configure the rules required for the standard process of construction process, as well as the construction team and construction machinery for each process. The system records the construction process ledger according to the process cycle rules. The system identifies people and machinery entering the construction area by positioning the system electronic fence and other methods. According to the basic configuration rules, the number of people or equipment entering the hole is set. When the number of people entering the electronic fence area reaches the set number, the process starts recording. The number of people or equipment leaving the hole is set. When the number of people leaving the electronic fence reaches the set number, the process ends recording. At the same time, different teams are configured for different processes. After the combination of processes and personnel is identified by the system algorithm, the construction process is recorded according to the rules; when the first necessary process in the process management configuration rules begins, the cycle is judged to start, and when all necessary processes in the process management configuration rules have been completed, the cycle is judged to end; if there is blasting monitoring, the current process cycle is ended according to the blasting record and a new process cycle is generated.

[0025] Only the preferred embodiments of the present invention are described in detail above, but the present invention is not limited to the above embodiments. Various changes can be made within the knowledge scope of ordinary technicians in this field without departing from the purpose of the present invention, and various changes should be included in the protection scope of the present invention.

Claims

1. A tunnel ergonomic management system, characterized by: Including data acquisition system, data transmission system, data system, tunnel information management system and personnel management system; The data acquisition system includes an ultra-wideband UWB positioning base station, an access control gate and a positioning card; The data transmission system is to construct a heterogeneous network, including active roaming access technology; The data system includes a management database, a data model library, a business database and a GIS spatial database. Various types of data at the front end of tunnel construction are classified and stored in each database and provided to the platform application for comprehensive use; The information management system includes a tunnel basic information module and a tunnel surrounding rock grade recording module. The tunnel basic information module demarcates the attendance area of ​​the construction area and communicates with the personnel gate in the construction area; the tunnel surrounding rock grade recording module updates the surrounding rock distribution of the tunnel in real time; The personnel management system adopts a real-name system with one card for each person. When all relevant personnel are entered, they will be bound to the positioning card. When the corresponding personnel carry the positioning card, all areas and locations of the corresponding personnel can be identified; It also includes a construction record module, an early warning management module, a tunnel dispatch command center module, and a tunnel data analysis module; The construction record module graphically displays the ongoing cycle construction process; displays the completed construction process and cycle record information in a table; when the automatic process fails to start due to a power outage system fault light problem, the execution status of the process can be manually reported; The warning management module includes disconnection timeout alarm, surrounding rock grade change alarm, emergency rescue, process standard working time timeout alarm, cycle timeout alarm and low power alarm; The tunnel dispatching and command center module summarizes and analyzes various data, displays the overall construction progress of the tunnel, daily, weekly and monthly construction footage, visually tracks the personnel distribution and construction status in the tunnel, and provides intuitive chart display of process records, personnel information statistics and early warning record viewing; The tunnel data analysis module is used to predict and analyze the progress of the tunnel in the next 30 days: actual completion rate: actual completion / total length*100%, progress in the next month: (the amount of excavation in the next month + the actual amount completed) / total length*100%, the number of cycles per month X=30 days*(24 hours / time per cycle Y), the monthly footage C=the number of cycles per month X*L1, L1: take the mode of the footage this month under the current surrounding rock grade.

2. A tunnel ergonomics management system according to claim 1, characterized in that: The ultra-wideband UWB positioning base station is installed on a waterproof trolley, and a blasting vibration meter is also installed. The heading face and the 250-meter range near the lining trolley are designated as key construction control areas for the tunnel.

3. A tunnel ergonomics management system according to claim 1, characterized in that: The personnel management system includes subcontracting unit management: maintaining project subcontracting units, team management: maintaining all team information of subcontracting units, personnel roster: maintaining tunnel construction personnel roster, personnel entry and exit records: through gate machines or personnel positioning systems, personnel entering and exiting the electronic area will generate corresponding entry and exit information, thereby forming a personnel entry and exit ledger record, and personnel positioning records: the positioning system reflects changes in personnel location.

4. A tunnel ergonomics management system according to claim 1, characterized in that: The construction record module also includes process record correction and footage statistics. Process record correction: deviations in automatic process records can be corrected manually; footage statistics: after each cycle is completed, the footage is automatically counted according to the mileage pile number.

5. A tunnel ergonomics management system according to claim 1, characterized in that: The disconnection timeout alarm: using automated monitoring technology, accurately recording construction in and out through the positioning system electronic fence, real-time analysis of process connection, once a disconnection is found, an immediate intelligent warning will be issued, and graded warning notifications can be designed according to the different durations of disconnection; the surrounding rock grade change warning: when the geological advance prediction of the surrounding rock grade in the construction stage is different from the surrounding rock grade in the design stage, the surrounding rock information table will be updated, and timely warnings will be issued to various production departments to help tunnel safety and dynamic scheduling; the emergency rescue: the positioning card worn by the construction personnel has a one-button rescue function. In case of an unexpected situation, the one-button rescue button will be pressed for help. The monitoring center will receive the rescue alarm information in time, locate the location information of the rescue personnel, and implement fast and accurate rescue; the process standard working time overtime warning: set the standard time for each process, and issue a graded warning when the process standard time is exceeded; The cycle timeout warning: set the standard time for each cycle, and issue a graded warning when the process standard time is exceeded; low power warning: set the warning power level, and issue a warning when the power level is lower than the warning power level.

6. A tunnel ergonomics management system according to claim 1, characterized in that: The tunnel dispatching and command center module includes tunnel overview: basic information of the tunnel, including the entire tunnel, excavation mileage, completion of each sub-item construction, and tunnel introduction; footage statistics: when a cycle is completed, the footage is automatically calculated according to the mileage pile number; construction progress overview: two-dimensional tunnel simulation diagram, personnel location distribution, surrounding rock grade distribution, construction point distribution, real-time step distance; construction process statistics: through the combination of personnel, machinery, and sensors, the start and end time of each process of each tunnel working cycle and the interval time between adjacent processes are displayed in the form of bar charts and tables; on-site personnel: display the total number of tunnel construction personnel, the number of on-duty personnel, the number of attendance personnel in each team, the real-time number of personnel and attendance rate; warning records: display process disconnection warning, long-term personnel stationary, and emergency rescue warning records.

Citation Information

Cited By

  • Tunnel construction efficacy management method and system based on generative visual large model

    CN121684715A

  • Tunnel construction command management method and system based on Internet of Things

    CN122264359A