Method and system for controlling signals of station clampers in rear area of double highlines

By obtaining the real-time position and signal of the station clamper in the back area of ​​the double-high line, outputting the fault signal and triggering the correction mechanism, the production interruption problem caused by the station clamper signal failure in the back area of ​​the double-high line is solved, and efficient control and fault handling of the clamper is achieved, which improves working efficiency and reduces safety risks.

CN119620707APending Publication Date: 2025-03-14YANGCHUN NEW STEEL CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411702693.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-26
Publication Date
2025-03-14

AI Technical Summary

Technical Problem

In the prior art, the signal failure of the double-high line rear area station clamper leads to the inability to hook in the entire region, resulting in production interruption, reduced production, waste of energy consumption and increased safety risks.

Method used

By obtaining the real-time position of the clamping element of the clamping device, outputting the clamping position signal, and collecting the clamping signal for comparison, outputting the fault signal and triggering the correction mechanism, efficient control and fault handling of the clamping device are achieved.

Benefits of technology

It realizes efficient control of the clamping station clamping station is opened and clamped in place, avoiding the inability to hook in the entire area caused by clamping signal failure, improving work efficiency and reducing safety risks.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119620707A_ABST
    Figure CN119620707A_ABST
Patent Text Reader

Abstract

The invention discloses a signal control method for a double-high-speed-line rear-area station clamping device, relates to the technical field of steel production, and solves the technical problem that production interruption is finally caused by the fact that hook sending cannot be carried out in the whole domain due to signal faults of an existing double-high-speed-line rear-area station clamping device. The method comprises the steps that the real-time position of a clamping element of the clamping device is obtained, when the real-time position of the clamping element is a clamping in-place position, a first clamping position signal is output, meanwhile, a clamping in-place signal of the clamping device is collected, the time when the clamping in-place signal is collected is compared with the time when the first clamping position signal is received, and if the clamping in-place signal is not collected, the clamping in-place signal is obtained. And when the time when the clamping in-place signal is collected is inconsistent with the time when the first clamping position signal is received, a clamping fault signal is output, and a first correction mechanism is triggered. The invention further discloses a control system for the signals of the double-altitude line rear area station clamping device. The situation that hook sending cannot be carried out in the whole domain due to signal faults of the clamping device is avoided, and the working efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of steel production, and more particularly to a control method and system for a signal of a clamping device in a rear area of ​​a double-high wire. Background Art

[0002] It is very important for the finished coil transport chain in the rear area of ​​the double-high line of the rolling mill to hook normally, because if the hook is not hooked normally, it will directly lead to production interruption, which will lead to a decrease in output and an increase in the production cost per ton of steel. The existing fault is generally the signal failure of the clamping device in the rear area of ​​the double-high line, which leads to the inability to hook in the entire area, which will lead to production interruption. First, the signal failure of the clamping device in the rear area of ​​the double-high line will lead to the inability to hook in the entire area, which will lead to full coverage of the relevant fault analysis points. In this way, the troubleshooting of the fault points will be as many as 200 points, which requires a lot of time to troubleshoot, which will lead to a significant reduction in output and waste of related energy media consumption. Then, the signal failure of the clamping device in the rear area of ​​the double-high line will lead to the inability to hook in the entire area. The entire processing process is all high-altitude operations, and the entire investigation area is very large, which will bring great safety risks to the entire troubleshooting process, and then increase the safety risks of personnel in related process positions and equipment maintenance positions. Finally, a signal failure at the clamping device in the rear area of ​​the double-high line will cause the entire area to be unable to hook. Due to differences and uncertainties in the relevant order of troubleshooting, timing logic errors may cause chain damage during local trials, further leading to the expansion of the fault and an increase in spare parts costs. Summary of the invention

[0003] The technical problem to be solved by the present invention is to provide a control method and system for the signal of the clamp of the rear area station of a double-high line in view of the shortcomings of the prior art, so as to solve the technical problem that the signal failure of the clamp of the rear area station of the existing double-high line leads to the inability to release the hook in the entire area and finally causes the production interruption.

[0004] The present invention discloses a method for controlling a clamping signal of a rear area station of a double-high-speed line. The method comprises:

[0005] Acquire the real-time position of the clamping element of the clamp, and when the real-time position of the clamping element is the clamping position, output a first clamping position signal, and simultaneously acquire the clamping signal of the clamp, and compare the time of the clamping signal with the first clamping position signal, and when the clamping signal is inconsistent with the first clamping position signal, output a clamping fault signal and trigger a first correction mechanism;

[0006] When the real-time position of the clamping element is the open position, a first open position signal is output, and the open position signal of the clamp is collected at the same time, and the open position signal is compared with the first open position signal. When the open position signal is inconsistent with the first open position signal, an open fault signal is output and a second correction mechanism is triggered.

[0007] As a further improvement, when the clamping fault signal is received, a clamping failure alarm is issued.

[0008] Furthermore, the first correction mechanism is: replacing the clamping-in-place signal with a first clamping position signal, and performing a clamping-in-place operation on the clamper according to the first clamping position signal.

[0009] Furthermore, when the opening fault signal is received, an opening failure alarm is performed.

[0010] Furthermore, the second correction mechanism is to replace the fully opened signal with a first open position signal, and perform a fully opened operation on the clamp according to the first open position signal.

[0011] Furthermore, the working state of the power supply of the clamp is obtained, and when the working state of the power supply of the clamp is a fault state, the clamp is shut down.

[0012] A control system for a clamping device signal at a rear workstation of a double-high line, the system comprising:

[0013] A first proximity switch is installed at the open position of the clamp and is used to output an open position signal when the clamping element is close to the open position;

[0014] A second proximity switch is installed at the clamping position of the clamp and is used to output a clamping signal when the clamping element approaches the clamping position;

[0015] A position sensor, mounted on the clamping element, for acquiring the real-time position of the clamping element and outputting a real-time position signal of the clamping element;

[0016] A controller, used for receiving the opening position signal, the clamping position signal and the real-time position signal of the clamping element;

[0017] The controller performs opening and clamping operations on the clamp according to the above-mentioned method for controlling the clamp signal of the rear area workstation of the double-high line through the opening position signal, the clamping position signal and the real-time position signal of the clamping element.

[0018] Beneficial Effects

[0019] The advantages of the present invention are:

[0020] 1. The present invention obtains the clamping position and the opening position of the clamping element of the clamping device to obtain the real-time position of the clamping element. When the real-time position of the clamping element is the clamping position, a first clamping position signal is output, and the clamping signal of the clamping element is collected at the same time. When the real-time position of the clamping element is the opening position, a first opening position signal is output, and the opening signal of the clamping element is collected at the same time. The clamping and opening of the clamp are operated according to the first clamping position signal, the clamping signal, the first opening position signal and the opening signal, so as to realize efficient control of the opening and clamping of the clamp at the winding station, realize emergency operation of the clamping signal failure state and the opening signal failure state, avoid the situation that the hook cannot be released in the whole area due to the failure of the clamping signal, and improve work efficiency.

[0021] 2. The present invention obtains the working state of the power supply of the clamp. When the working state of the power supply of the clamp is a fault state, the clamp is shut down to obtain the power supply fault state and handle the fault, thereby reducing the risk of damage to the clamp due to the power supply. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] Figure 1 This is a flow chart of the control method of the clamping device signal of the rear area workstation of the double high line of the present invention. DETAILED DESCRIPTION

[0023] The present invention will be further described below in conjunction with the embodiments, but it does not constitute any limitation to the present invention. Any limited number of modifications made by anyone within the scope of the claims of the present invention are still within the scope of the claims of the present invention.

[0024] See also Figure 1 The present invention provides a control method for a clamping device signal of a double-high-line rear zone workstation, the method comprising:

[0025] The real-time position of the clamping element of the clamp is obtained to achieve accurate quantification of the position of the clamping element.

[0026] When the real-time position of the clamping element is the clamping position, the first clamping position signal is output, and the clamping position signal of the clamp is collected at the same time, and the clamping position signal is compared with the first clamping position signal. When the clamping position signal is inconsistent with the first clamping position signal, a clamping fault signal is output and the first correction mechanism is triggered, so as to realize the control and efficient diagnosis of the clamping position signal.

[0027] When a clamping fault signal is received, a clamping fault alarm is issued to quickly remind the user of the clamping fault signal.

[0028] The first correction mechanism is: replacing the clamping in place signal with the first clamping position signal, and performing a clamping in place operation on the clamper according to the first clamping position signal, thereby achieving replacement and optimization of the clamping in place signal.

[0029] When the real-time position of the clamping element is the fully opened position, the first open position signal is output, and the fully opened signal of the clamp is collected at the same time, and the fully opened signal is compared with the first open position signal. When the fully opened signal is inconsistent with the first open position signal, an open fault signal is output and the second correction mechanism is triggered, so as to realize the control and efficient diagnosis of the fully opened signal.

[0030] When an opening fault signal is received, an opening fault alarm is issued to realize a quick reminder of the opening fault signal failure.

[0031] The second correction mechanism is to replace the fully opened signal with the first open position signal, and perform fully opened operation on the clamp according to the first open position signal.

[0032] The working status of the power supply of the clamp is obtained through the visualized conversion output, and the working status of the power supply of the clamp can be displayed on the central control screen. When the working status of the power supply of the clamp displayed on the central control screen is a fault state, the clamp is shut down to obtain the power supply fault state and handle the fault, thereby reducing the risk of damage to the clamp due to power supply.

[0033] A control system for a clamping device signal at a rear workstation of a double-high line, the system comprising:

[0034] The first proximity switch is installed at the fully opened position of the clamp and is used to output a fully opened signal when the clamping element approaches the fully opened position.

[0035] The second proximity switch is installed at the clamping position of the clamp and is used to output a clamping signal when the clamping element approaches the clamping position.

[0036] The position sensor is installed on the clamping element and is used to obtain the real-time position of the clamping element and output the real-time position signal of the clamping element.

[0037] The controller is used to receive the opening position signal, the clamping position signal and the real-time position signal of the clamping element.

[0038] The controller performs opening and clamping operations on the clamp according to the above-mentioned control method for the clamp signal of the rear area workstation of the double-high line through the opening position signal, the clamping position signal and the real-time position signal of the clamping element.

[0039] The system realizes efficient control over the opening and clamping of the clamps at the winding station, and implements emergency operations for the clamping signal failure state and the opening signal failure state, thus avoiding the situation where the entire area cannot release the hook due to the clamping signal failure, and improving work efficiency.

[0040] The above is only a preferred embodiment of the present invention. It should be pointed out that for those skilled in the art, several modifications and improvements can be made without departing from the structure of the present invention, which will not affect the effect of the implementation of the present invention and the practicality of the patent.

Claims

1. A control method for the clamp signal of the rear area of ​​a double-high line, characterized in that: The method is, Acquire the real-time position of the clamping element of the clamp, and when the real-time position of the clamping element is the clamping position, output a first clamping position signal, and simultaneously acquire the clamping signal of the clamp, and compare the time of the clamping signal with the first clamping position signal, and when the clamping signal is inconsistent with the first clamping position signal, output a clamping fault signal and trigger a first correction mechanism; When the real-time position of the clamping element is the open position, a first open position signal is output, and the open position signal of the clamp is collected at the same time, and the open position signal is compared with the first open position signal. When the open position signal is inconsistent with the first open position signal, an open fault signal is output and a second correction mechanism is triggered.

2. A control method for a clamping device signal of a double-high-line rear area workstation according to claim 1, characterized in that: When the clamping fault signal is received, a clamping fault alarm is issued.

3. The control method of the clamp signal of the rear area station of the double high line according to claim 1 is characterized in that: The first correction mechanism is: replacing the clamping-in-place signal with a first clamping position signal, and performing a clamping-in-place operation on the clamper according to the first clamping position signal.

4. The control method of the clamping device signal of the rear area of ​​the double-high line according to claim 1 is characterized in that: When the opening fault signal is received, an opening failure alarm is issued.

5. The control method of the clamp signal of the rear area station of the double high line according to claim 1 is characterized in that: The second correction mechanism is to replace the fully opened signal with a first open position signal, and perform fully opened operation on the clamp according to the first open position signal.

6. The control method of the clamping device signal of the rear area of ​​the double-high line according to claim 1 is characterized in that: The working state of the power supply of the clamp is obtained, and when the working state of the power supply of the clamp is a fault state, the clamp is shut down.

7. A control system for the clamping signal of the rear area of ​​a double high-speed line, characterized in that: The system includes, A first proximity switch is installed at the open position of the clamp and is used to output an open position signal when the clamping element of the clamp is close to the open position; A second proximity switch is installed at the clamping position of the clamp and is used to output a clamping signal when the clamping element approaches the clamping position; A position sensor, mounted on the clamping element, for acquiring the real-time position of the clamping element and outputting a real-time position signal of the clamping element; A controller, used for receiving the opening position signal, the clamping position signal and the real-time position signal of the clamping element; The controller performs opening and clamping operations on the clamp according to the control method of the double-high-line rear area workstation signal described in claims 1-6 through the opening position signal, the clamping position signal and the real-time position signal of the clamping element.