Ship pipe fitting manufacturing code generation method, medium and electronic equipment

By acquiring and processing the bill of materials information for pipe fitting manufacturing in the ship design model, manufacturing codes and time data for pipe sections are generated, solving the problem of automated control and management in ship pipe fitting manufacturing and achieving efficient and lean production management.

CN120893393APending Publication Date: 2025-11-04ZHONGCHUAN NO 9 DESIGN & RES INST
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202511067963.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-07-31
Publication Date
2025-11-04

AI Technical Summary

Technical Problem

Under current technology, it is difficult to achieve automated control and management in the manufacturing of ship pipe fittings in an assembly line mode, resulting in low manufacturing efficiency and a high risk of errors.

Method used

By acquiring the bill of materials information for pipe fitting manufacturing from the ship design model, the manufacturing code and time data of the pipe section are determined and added to the bill of materials information, thus realizing automated coding and process management for pipe fitting manufacturing.

Benefits of technology

It enables efficient and lean management of pipe fitting manufacturing, provides digital support, and supports production management operations such as planning, scheduling, and logistics distribution in assembly line manufacturing.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120893393A_ABST
    Figure CN120893393A_ABST
Patent Text Reader

Abstract

The invention provides a ship pipe fitting manufacturing code generation method, a medium and electronic equipment, and can obtain pipe fitting manufacturing material list information in a ship design model, determine a manufacturing code corresponding to a pipe section according to production and manufacturing information of at least one pipe section in the pipe fitting manufacturing material list information, and generate a manufacturing code corresponding to the pipe section according to the manufacturing code. The method comprises the following steps: firstly, according to manufacturing codes corresponding to pipe sections, determining man-hour data corresponding to the pipe sections, and finally, adding the manufacturing codes and the man-hour data corresponding to the pipe sections into pipe fitting manufacturing material list information, so that working procedures such as materials, specifications, manufacturing procedures, pipe types, quality inspection and the like of each pipe section formed by ship pipe fittings can be defined; the working hours of the working procedures through which the pipe sections flow are calculated, digital support is provided for production management services such as planning scheduling and logistics distribution of pipe fitting assembly line manufacturing, and efficient and lean management of pipe fitting manufacturing is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of shipbuilding technology, and in particular to a method, medium, and electronic device for generating ship pipe fitting manufacturing codes. Background Technology

[0002] Pipe fittings are crucial components of shipbuilding products. A large ship's Bill of Material (BOM) contains tens of thousands of pipe fittings. Currently, pipe fitting manufacturing is primarily done manually, resulting in low efficiency and a high risk of errors. The shipbuilding industry is undergoing digital transformation, and pipe fitting manufacturing is shifting towards automated assembly lines. However, how to automatically control and manage the data related to the processes involved in pipe segment manufacturing remains a challenge.

[0003] Therefore, a solution is needed that can encode the automated manufacturing of pipe fittings in a production line manufacturing mode. Summary of the Invention

[0004] One objective of this application is to provide a method for generating manufacturing codes for ship pipe fittings, in order to solve the problem that it is difficult to automate the manufacturing of pipe fittings in a production line mode under the existing technology.

[0005] To achieve the above objectives, some embodiments of this application provide a method for generating manufacturing codes for ship pipe fittings, the method comprising:

[0006] Obtain the bill of materials information for pipe fitting manufacturing from the ship design model;

[0007] Based on the production and manufacturing information of at least one pipe segment in the pipe fitting manufacturing bill of materials, determine the manufacturing code corresponding to the pipe segment;

[0008] Based on the manufacturing code corresponding to the pipe section, determine the corresponding working hour data;

[0009] Add the manufacturing code and working time data corresponding to the pipe section to the pipe fitting manufacturing bill of materials information.

[0010] Furthermore, obtain the bill of materials information for pipe fitting manufacturing from the ship design model, including:

[0011] Obtain pipe fitting information from the ship design model;

[0012] Based on the pipe fitting information, organize the data table by project number and pallet number, and generate the pipe fitting manufacturing bill of materials information;

[0013] Obtain the bill of materials information for pipe fitting manufacturing.

[0014] Furthermore, the manufacturing information for the pipe section should include at least the following data: material, outer diameter specifications, wall thickness, pipe section length, component connection type, bend parameters, pipe fitting application, weld inspection, pump pressure test, surface treatment requirements, coating requirements, and insulation requirements.

[0015] Furthermore, the manufacturing code corresponding to the pipe section shall include at least the following data: material, specifications, manufacturing type, pipe type, inspection, water pressure, surface treatment, coating, and insulation.

[0016] Furthermore, based on the manufacturing information of at least one pipe segment in the pipe fitting manufacturing bill of materials, the manufacturing code corresponding to the pipe segment is determined, including:

[0017] Based on the outer diameter specifications, wall thickness, pipe length, component connection type, bend parameters, and preset manufacturing type coding rules of at least one pipe segment in the pipe fitting manufacturing bill of materials information, determine the corresponding manufacturing type code for the pipe segment.

[0018] Furthermore, based on the manufacturing information of at least one pipe segment in the pipe fitting manufacturing bill of materials, the manufacturing code corresponding to the pipe segment is determined, which also includes:

[0019] Based on the material data in the production and manufacturing information of at least one pipe segment in the pipe fitting manufacturing bill of materials and the preset material coding rules, determine the material code corresponding to the pipe segment;

[0020] Based on the outer diameter specification data and preset specification coding rules in the production and manufacturing information of at least one pipe segment in the pipe fitting manufacturing bill of materials information, determine the specification code corresponding to the pipe segment.

[0021] Based on the pipe fitting usage data and preset pipe type coding rules in the production and manufacturing information of at least one pipe segment in the pipe fitting manufacturing bill of materials, determine the pipe type code corresponding to the pipe segment;

[0022] Based on the weld inspection data and preset inspection coding rules in the production and manufacturing information of at least one pipe segment in the pipe fitting manufacturing bill of materials information, determine the inspection code corresponding to the pipe segment;

[0023] Based on the pump pressure test data and preset water pressure coding rules in the production and manufacturing information of at least one pipe section in the pipe fitting manufacturing bill of materials, determine the water pressure code corresponding to the pipe section;

[0024] Based on the surface treatment requirement data in the production and manufacturing information of at least one pipe segment in the pipe fitting manufacturing bill of materials information and the preset surface treatment coding rules, determine the surface treatment code corresponding to the pipe segment;

[0025] Based on the coating requirement data and preset coating coding rules in the production and manufacturing information of at least one pipe segment in the pipe fitting manufacturing bill of materials information, determine the coating code corresponding to the pipe segment;

[0026] Based on the insulation requirement data and preset insulation coding rules in the manufacturing information of at least one pipe segment in the pipe fitting manufacturing bill of materials, determine the insulation code corresponding to the pipe segment.

[0027] Furthermore, the working time data corresponding to the pipe section includes the working time data of at least one process, and the working time data of the process includes at least the following data: production line number, process number, and duration.

[0028] Furthermore, based on the manufacturing code corresponding to the pipe segment, the corresponding working hour data is determined, including:

[0029] Based on the manufacturing code corresponding to the pipe segment and the processing capacity constraints of the production line, determine the production line number required for pipe segment manufacturing;

[0030] Based on the manufacturing code corresponding to the pipe segment, determine the corresponding manufacturing characteristics, and based on the manufacturing characteristics, determine the list of process numbers required for the manufacturing of the pipe segment;

[0031] Based on the production efficiency of the production line and the process data of the pipe section, determine the time required for pipe section manufacturing.

[0032] Based on the production line number, process number list, and duration list, determine the working hours data corresponding to the pipe section.

[0033] Some embodiments of this application also provide a computer-readable medium having computer-readable instructions stored thereon, which can be executed by a processor to implement the aforementioned method for generating ship pipe fitting manufacturing codes.

[0034] Some embodiments of this application also provide an electronic device, which includes a memory for storing computer program instructions and a processor for executing the computer program instructions, wherein when the computer program instructions are executed by the processor, the electronic device performs the aforementioned method for generating ship pipe manufacturing codes.

[0035] Compared with existing technologies, the solution provided in this application can obtain the bill of materials (BOM) information for pipe fitting manufacturing from the ship design model, and determine the manufacturing code corresponding to the pipe segment based on the production and manufacturing information of at least one pipe segment in the BOM information. Then, based on the manufacturing code corresponding to the pipe segment, the corresponding working time data is determined. Finally, the manufacturing code and working time data corresponding to the pipe segment are added to the BOM information for pipe fitting manufacturing. This allows for the definition of the material, specifications, manufacturing process, pipe type, quality inspection, and other processes for each pipe segment in the ship's pipe fittings, and the calculation of the working time for the processes through which the pipe segment flows. This provides digital support for production management operations such as planning and scheduling, and logistics distribution in pipe fitting assembly line manufacturing, achieving efficient and lean management of pipe fitting manufacturing. Attached Figure Description

[0036] Other features, objects, and advantages of this application will become more apparent from the following detailed description of non-limiting embodiments with reference to the accompanying drawings:

[0037] Figure 1 A flowchart illustrating a method for generating manufacturing codes for ship pipe fittings, provided for some embodiments of this application.

[0038] Figure 2 Examples of pipe fitting information data tables provided for some embodiments of this application. Detailed Implementation

[0039] The present invention will now be described in detail with reference to the accompanying drawings and specific embodiments. These embodiments are based on the technical solution of the present invention and provide detailed implementation methods and specific operating procedures. However, the scope of protection of the present invention is not limited to the following embodiments.

[0040] Here, the method for generating ship pipe fitting manufacturing codes according to the embodiments of this application is suitable for scenarios in the shipbuilding industry where pipe fittings are manufactured on an assembly line.

[0041] In this scenario, pipe fittings are manufactured automatically according to the processes involved in the constituent pipe sections. Before manufacturing, it is necessary to define the relevant processes of the pipe sections, calculate the working hours, and provide digital support for production management operations such as planning, scheduling, and logistics.

[0042] The method for generating manufacturing codes for ship pipe fittings provided in this application can obtain the bill of materials (BOM) information for pipe fitting manufacturing from the ship design model, determine the manufacturing code corresponding to at least one pipe segment based on the production and manufacturing information of the pipe segment in the BOM information, determine the corresponding working hours data based on the corresponding manufacturing code, and finally add the corresponding manufacturing code and working hours data to the BOM information. This allows for the definition of the material, specifications, manufacturing process, pipe type, quality inspection, and other processes for each pipe segment in the ship pipe fitting assembly line, and the calculation of the working hours for the processes through which the pipe segment flows. This provides digital support for production management operations such as planning and scheduling, and logistics distribution in pipe fitting assembly line manufacturing, and achieves efficient and lean management of pipe fitting manufacturing.

[0043] Figure 1 The present application illustrates a flowchart of a method for generating ship fitting manufacturing codes using electronic devices in some embodiments of the present application. The electronic devices are the executing entities of the method, such as... Figure 1 As shown, the method may include the following steps:

[0044] Step S101: Obtain the bill of materials information for pipe fitting manufacturing from the ship design model.

[0045] It is understood that electronic devices may include, but are not limited to, laptops, desktop computers, tablets, mobile phones, wearable devices, head-mounted displays, servers, mobile email devices, portable game consoles, portable music players, e-reader devices, televisions in which one or more processors are embedded or coupled, or other electronic devices capable of accessing networks.

[0046] In some embodiments of this application, obtaining the bill of materials information for pipe fitting manufacturing in a ship design model may include the following steps:

[0047] (1) Obtain pipe fitting information from the ship design model;

[0048] (2) Based on the pipe fitting information, organize the data table by project number and pallet number, and generate the pipe fitting manufacturing bill of materials information;

[0049] Here, the project number is a number assigned by the shipyard to the vessel being built, also known as the ship number, which can be understood as the vessel's identification number. A vessel represents a project, and the project number of a vessel can be, for example, "H1594". A vessel typically includes tens of thousands or even hundreds of thousands of pipe fittings.

[0050] Based on the distribution area of ​​the pipe fittings on the ship, the pipe fittings of a ship are assigned to hundreds of pallets to facilitate production organization and management. The pallet number or pallet name is the code for these pallets.

[0051] The data in the organization's pipe fitting information table can be obtained by extracting parameters from the 3D model of the ship design, such as material, pipe diameter, wall thickness, and length. These parameters are then organized into a tree-like structure table based on assembly relationships, such as project number—pallet name—pipe fitting number—part number, etc. A ship has several pallets, each pallet contains several pipe fittings, and each pipe fitting contains several parts, including pipe sections and accessories.

[0052] The pipe fitting information data sheet may include, but is not limited to, the following data: project number, pallet name, pipe fitting number, group code, mark, part number, material, outer diameter, wall thickness, pipe section length, process pipe section, etc. Figure 2 Examples of pipe fitting information data tables are shown in some embodiments of this application.

[0053] (3) Obtain the bill of materials information for pipe fitting manufacturing.

[0054] Here, the pipe fitting information in the ship design model may include, but is not limited to: fitting number, part number, material, outer diameter, wall thickness, pipe section length, component connection type, bend parameters, and other data.

[0055] The bill of materials information for pipe fitting manufacturing includes relevant bill of materials information used in the manufacturing of pipe fittings, such as the production and manufacturing information of multiple pipe sections that make up the pipe fittings.

[0056] Step S102: Determine the manufacturing code corresponding to the pipe segment based on the production and manufacturing information of at least one pipe segment in the pipe fitting manufacturing bill of materials information.

[0057] In some embodiments of this application, the manufacturing information of the pipe section may include, but is not limited to, the following data: material, outer diameter specification, wall thickness, pipe section length, component connection form, bend parameters, pipe fitting application, weld inspection, pump pressure test, surface treatment requirements, coating requirements, insulation requirements, etc.

[0058] In some embodiments of this application, the manufacturing code corresponding to the pipe segment may include, but is not limited to, the following data: material, specifications, manufacturing type, pipe type, inspection, water pressure, surface treatment, coating, insulation, etc.

[0059] Specifically, the manufacturing code corresponding to the pipe segment can be implemented as a 9-bit code data, and the meaning of each bit is described in Table 1 below:

[0060] Table 1

[0061]

[0062]

[0063] Here, when coding, the corresponding manufacturing codes are generated sequentially according to the pipe segment order in the pipe fitting, using the pipe segment as the unit. Alternatively, the manufacturing codes can be manually entered.

[0064] In some embodiments of this application, determining the manufacturing code corresponding to a pipe segment based on the production and manufacturing information of at least one pipe segment in the pipe fitting manufacturing bill of materials information may include the following steps:

[0065] (1) Determine the material code corresponding to the pipe segment based on the material data in the production and manufacturing information of at least one pipe segment in the pipe fitting manufacturing bill of materials information and the preset material coding rules; here, the material coding rules are similar to those in Table 1 above.

[0066] (2) Determine the specification code corresponding to the pipe segment based on the outer diameter specification data in the production and manufacturing information of at least one pipe segment in the pipe fitting manufacturing bill of materials information and the preset specification coding rules.

[0067] (3) Determine the manufacturing type code corresponding to the pipe section based on the outer diameter specification, wall thickness, pipe section length, component connection form, bend parameters and preset manufacturing type coding rules in the manufacturing information of at least one pipe section in the pipe fitting manufacturing bill of materials.

[0068] (4) Determine the pipe type code corresponding to the pipe section based on the pipe use data in the production and manufacturing information of at least one pipe section in the pipe fitting manufacturing bill of materials information and the preset pipe type coding rules;

[0069] (5) Determine the inspection code corresponding to the pipe section based on the weld inspection data in the production and manufacturing information of at least one pipe section in the pipe fitting manufacturing bill of materials information and the preset inspection coding rules;

[0070] (6) Determine the water pressure code corresponding to the pipe section based on the pump pressure test data and the preset water pressure coding rules in the production and manufacturing information of at least one pipe section in the pipe fitting manufacturing bill of materials information;

[0071] (7) Determine the surface treatment code corresponding to the pipe segment based on the surface treatment requirement data in the production and manufacturing information of at least one pipe segment in the pipe fitting manufacturing bill of materials information and the preset surface treatment coding rules;

[0072] (8) Determine the coating code corresponding to the pipe segment based on the coating requirement data and preset coating coding rules in the production and manufacturing information of at least one pipe segment in the pipe fitting manufacturing bill of materials information.

[0073] (9) Determine the insulation code corresponding to the pipe section based on the insulation requirement data in the production and manufacturing information of at least one pipe section in the pipe fitting manufacturing bill of materials information and the preset insulation coding rules.

[0074] Finally, the 9-bit codes determined through the above steps are combined to obtain the manufacturing code corresponding to the pipe segment.

[0075] Step S103: Determine the working time data corresponding to the pipe segment based on the manufacturing code corresponding to the pipe segment.

[0076] In some embodiments of this application, the working time data corresponding to the pipe segment includes working time data corresponding to at least one process. The working time data represents the working time required for each process experienced by each pipe segment, and may include, but is not limited to, the following data: production line number, process number, and duration. The production line number can be represented by one English letter, such as "H" representing production line H; the process number can be represented by two English letters, such as "SL" representing the material loading process; the duration can be represented by a decimal number in hours.

[0077] The format of the working hours data for the corresponding pipe section is shown in Table 2 below:

[0078] Table 2

[0079]

[0080] Here, the production line process through which each pipe segment flows can be determined based on the manufacturing code, and the working hours of each process through which the pipe segment flows can be generated based on the material, specifications, and process parameters of the pipe segment.

[0081] In some embodiments of this application, determining the working time data corresponding to a pipe segment based on its manufacturing code may include the following steps:

[0082] (1) Determine the production line number required for pipe segment manufacturing based on the manufacturing code corresponding to the pipe segment and the processing capacity constraints of the production line.

[0083] Taking the cutting process as an example, the processing capacity constraints of the cutting equipment include: cutting type constraints and pipe diameter constraints. Cutting type constraints include two types: straight cut and straight cut + beveling. Pipes requiring beveling can only be processed on cutting equipment with beveling capabilities. Pipe diameter constraints stipulate that the cutting equipment can only process pipes within a preset diameter range. For example, the cutting equipment for line A has a pipe diameter range of 60mm to 114mm; pipes outside this range cannot be processed on this equipment.

[0084] Similarly, for assembly and welding processes, constraints include welding type constraints and pipe length constraints. Welding type constraints include butt welding and fillet welding; pipe length constraints stipulate that assembly and welding equipment can only process pipes within a preset pipe length range. For example, pipe sections exceeding 800mm can only be processed on assembly or welding equipment suitable for long pipes; otherwise, they must be processed on assembly or welding equipment suitable for short pipes.

[0085] (2) Based on the manufacturing code corresponding to the pipe section, determine the corresponding manufacturing characteristics, and based on the manufacturing characteristics, determine the list of process numbers required for the manufacturing of the pipe section.

[0086] For example, if there are four cutting machines on the production line, numbered 1, 2, 3, and 4, with machine number 1 being a straight cutter for pipe diameters ranging from 60mm to 114mm, machine number 2 a bevel cutter for pipe diameters ranging from 60mm to 114mm, machine number 3 a straight cutter for pipe diameters ranging from 115mm to 150mm, and machine number 4 a bevel cutter for pipe diameters ranging from 115mm to 150mm, then a pipe section with a diameter of 120mm that requires bevel cutting must be processed on machine number 4. Similarly, subsequent assembly, welding, and pipe bending processes also require selecting appropriate process equipment based on the constraints of the process equipment and the parameters of the pipe section.

[0087] (3) Based on the production efficiency of the production line and the process data of the pipe section, determine the time required for pipe section manufacturing;

[0088] For example, pipe section A goes through 6 processes on the production line: feeding, cutting, assembly, welding, bending, and intersecting line cutting. Based on the historical records of the measured working time data of the equipment processing the same type of pipe section in each process, the working time list can be determined as [3, 2.1, 6.5, 9.8, 6, 3], in minutes.

[0089] (4) Determine the working hours data corresponding to the pipe section based on the production line number, process number list and duration list.

[0090] Here, workshop production lines and production line processes can be numbered in advance for use when determining the production line numbers and process change lists required for pipe segment manufacturing.

[0091] After determining the production line number, process number list, and duration list data, these data are combined to obtain the working time data corresponding to the pipe section.

[0092] Step S104: Add the manufacturing code and working time data corresponding to the pipe segment to the pipe fitting manufacturing bill of materials information.

[0093] Finally, the generated manufacturing code data and working hour data are added to the pipe fitting manufacturing bill of materials information input into the system, providing a data interface for third-party systems such as planning and scheduling, and material matching. At the same time, it can also be exported as spreadsheet data for users to view.

[0094] Some embodiments of this application also provide a computer-readable medium having computer-readable instructions stored thereon, which can be executed by a processor to implement the aforementioned method for generating ship pipe fitting manufacturing codes.

[0095] Some embodiments of this application also provide an electronic device, which includes a memory for storing computer program instructions and a processor for executing the computer program instructions, wherein when the computer program instructions are executed by the processor, the electronic device performs the aforementioned method for generating ship pipe manufacturing codes.

[0096] In summary, the solution provided in this application can obtain the bill of materials (BOM) information for pipe fitting manufacturing from the ship design model, determine the manufacturing code corresponding to at least one pipe segment based on the production and manufacturing information of the pipe segment in the BOM information, determine the corresponding working hours data based on the corresponding manufacturing code, and finally add the corresponding manufacturing code and working hours data to the BOM information for pipe fitting manufacturing. This allows for the definition of the material, specifications, manufacturing process, pipe type, quality inspection, and other processes for each pipe segment in the ship's pipe fittings, and the calculation of the working hours for the processes through which the pipe segment flows. This provides digital support for production management operations such as planning and scheduling, and logistics distribution in pipe fitting assembly line manufacturing, achieving efficient and lean management of pipe fitting manufacturing.

[0097] It should be noted that this application can be implemented in software and / or a combination of software and hardware, for example, using an application-specific integrated circuit (ASIC), a general-purpose computer, or any other similar hardware device. In one embodiment, the software program of this application can be executed by a processor to implement the steps or functions described above. Similarly, the software program of this application (including related data structures) can be stored in a computer-readable recording medium, such as RAM memory, magnetic or optical drives, floppy disks, and similar devices. Furthermore, some steps or functions of this application can be implemented in hardware, for example, as circuitry that cooperates with a processor to perform the various steps or functions.

[0098] In a typical configuration of this application, both the terminal and the network device include one or more processors (CPU), input / output interfaces, network interfaces, and memory.

[0099] Memory may include non-persistent storage in computer-readable media, such as random access memory (RAM) and / or non-volatile memory, such as read-only memory (ROM) or flash RAM. Memory is an example of computer-readable media.

[0100] Computer-readable media includes both permanent and non-permanent, removable and non-removable media that can store information by any method or technology. Information can be computer-readable instructions, data structures, modules of programs, or other data. Examples of computer storage media include, but are not limited to, phase-change memory (PRAM), static random access memory (SRAM), dynamic random access memory (DRAM), other types of random access memory (RAM), read-only memory (ROM), electrically erasable programmable read-only memory (EEPROM), flash memory or other memory technologies, CD-ROM, digital versatile optical disc (DVD) or other optical storage, magnetic tape, magnetic disk storage or other magnetic storage devices, or any other non-transferable medium that can be used to store information accessible by a computing device. As defined herein, computer-readable media does not include non-transitory computer-readable media, such as modulated data signals and carrier waves.

[0101] Furthermore, a portion of this application can be applied as a computer program product, such as computer program instructions, which, when executed by a computer, can invoke or provide the methods and / or technical solutions according to this application through the operation of the computer. The program instructions invoking the methods of this application may be stored in a fixed or removable recording medium, and / or transmitted via a data stream in a broadcast or other signal carrying medium, and / or stored in the working memory of a computer device operating according to the program instructions. Here, one embodiment of this application includes a device comprising a memory for storing computer program instructions and a processor for executing the program instructions, wherein, when the computer program instructions are executed by the processor, the device is triggered to run methods and / or technical solutions based on the foregoing embodiments of this application.

[0102] It will be apparent to those skilled in the art that this application is not limited to the details of the exemplary embodiments described above, and that this application can be implemented in other specific forms without departing from the spirit or essential characteristics of this application. Therefore, the embodiments should be considered exemplary and non-limiting in all respects, and the scope of this application is defined by the appended claims rather than the foregoing description. Thus, all variations falling within the meaning and scope of equivalents of the claims are intended to be embraced within this application. No reference numerals in the claims should be construed as limiting the scope of the claims. Furthermore, it is clear that the word "comprising" does not exclude other units or steps, and the singular does not exclude the plural. Multiple units or devices recited in the apparatus claims may also be implemented by a single unit or device in software or hardware. The terms "first," "second," etc., are used to indicate names and do not indicate any particular order.

Claims

1. A method for generating manufacturing codes for ship pipe fittings, characterized in that, The method includes: Obtain the bill of materials information for pipe fitting manufacturing from the ship design model; Based on the production and manufacturing information of at least one pipe segment in the pipe fitting manufacturing bill of materials information, determine the manufacturing code corresponding to the pipe segment; Based on the manufacturing code corresponding to the pipe segment, determine the working time data corresponding to the pipe segment; The manufacturing code corresponding to the pipe segment and the working time data are added to the pipe fitting manufacturing bill of materials information.

2. The method according to claim 1, characterized in that, Obtain the bill of materials information for pipe fitting manufacturing from the ship design model, including: Obtain pipe fitting information from the ship design model; Based on the pipe fitting information, organize the data table by project number and pallet number, and generate the pipe fitting manufacturing bill of materials information; Obtain the bill of materials information for the pipe fitting manufacturing.

3. The method according to claim 1, characterized in that, The manufacturing information of the pipe section shall include at least the following data: material, outer diameter specification, wall thickness, pipe section length, component connection type, bend parameters, pipe fitting application, weld inspection, pump pressure test, surface treatment requirements, coating requirements, and insulation requirements.

4. The method according to claim 3, characterized in that, The manufacturing code corresponding to the pipe section shall include at least the following data: material, specifications, manufacturing type, pipe type, inspection, water pressure, surface treatment, coating, and insulation.

5. The method according to claim 4, characterized in that, Based on the manufacturing information of at least one pipe segment in the pipe fitting manufacturing bill of materials, determine the manufacturing code corresponding to the pipe segment, including: Based on the outer diameter specifications, wall thickness, pipe length, component connection type, bend parameters, and preset manufacturing type coding rules of at least one pipe segment in the bill of materials information for pipe fitting manufacturing, determine the manufacturing type code corresponding to the pipe segment.

6. The method according to claim 4, characterized in that, Based on the production and manufacturing information of at least one pipe segment in the pipe fitting manufacturing bill of materials information, the manufacturing code corresponding to the pipe segment is determined, and the method further includes: Based on the material data in the production and manufacturing information of at least one pipe segment in the bill of materials for pipe fittings and the preset material coding rules, determine the material code corresponding to the pipe segment; Based on the outer diameter specification data and preset specification coding rules in the production and manufacturing information of at least one pipe segment in the bill of materials for pipe fitting manufacturing, determine the specification code corresponding to the pipe segment. Based on the pipe fitting usage data in the production and manufacturing information of at least one pipe segment in the pipe fitting manufacturing bill of materials information and the preset pipe type coding rules, determine the pipe type code corresponding to the pipe segment; Based on the weld inspection data in the production and manufacturing information of at least one pipe segment in the bill of materials for pipe fittings and the preset inspection coding rules, determine the inspection code corresponding to the pipe segment; Based on the pump pressure test data and preset water pressure coding rules in the production and manufacturing information of at least one pipe segment in the bill of materials for pipe fitting manufacturing, the water pressure code corresponding to the pipe segment is determined; Based on the surface treatment requirement data in the production and manufacturing information of at least one pipe segment in the bill of materials for pipe fittings and the preset surface treatment coding rules, determine the surface treatment code corresponding to the pipe segment; Based on the coating requirement data and preset coating coding rules in the production and manufacturing information of at least one pipe segment in the bill of materials for pipe fitting manufacturing, determine the coating code corresponding to the pipe segment; Based on the insulation requirement data in the production and manufacturing information of at least one pipe segment in the bill of materials information for pipe fittings and the preset insulation coding rules, the insulation code corresponding to the pipe segment is determined.

7. The method according to claim 1, characterized in that, The working time data corresponding to the pipe section includes working time data for at least one process, and the working time data for the process includes at least the following data: production line number, process number, and duration.

8. The method according to claim 7, characterized in that, Based on the manufacturing code corresponding to the pipe segment, the corresponding working hour data is determined, including: Based on the manufacturing code corresponding to the pipe segment and the processing capacity constraints of the production line, determine the production line number required for manufacturing the pipe segment; Based on the manufacturing code corresponding to the pipe segment, determine the corresponding manufacturing characteristics, and based on the manufacturing characteristics, determine a list of process numbers required for the manufacturing of the pipe segment; Based on the production efficiency of the production line and the process data of the pipe section, a list of the time required for manufacturing the pipe section is determined; Based on the production line number, the process number list, and the duration list, determine the working hours data corresponding to the pipe section.

9. A computer-readable medium having stored thereon computer-readable instructions that can be executed by a processor to implement the method as described in any one of claims 1 to 8.

10. An electronic device comprising a memory for storing computer program instructions and a processor for executing the computer program instructions, wherein, When the computer program instructions are executed by the processor, the electronic device performs the method as described in any one of claims 1 to 8.