Anchor-plate-grouting collaborative supporting method with active water sealing function
By adopting the anchor-plate-injection coordinated support method in well construction, and using a combination of steel plates and anchor bolts to construct a water-tight layer, active water sealing of the well was achieved, solving the problem of well leakage, improving construction safety and efficiency, and reducing costs.
Patent Information
- Application Number
- CN202510996885.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-07-18
- Publication Date
- 2025-12-05
AI Technical Summary
In existing well construction, the grouting water sealing method is passive and unreliable, resulting in serious water leakage problems in the well wall, affecting construction safety and schedule, and is also costly.
An active water-sealing anchor-plate-injection coordinated support method is adopted to construct a water-proof layer from top to bottom between the well wall and the well side. A template is formed by combining steel plates and anchor rods. After the grout is injected and solidified, a continuous water-stopping structure is formed to achieve active waterproofing.
It enables active water sealing during shaft construction, ensuring reliable waterproofing, avoiding safety accidents and construction delays caused by water leakage, reducing construction costs, and has wide adaptability, applicable to various shaft and tunnel construction methods.
Smart Images

Figure CN121066637A_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The present application relates to the field of mine construction engineering support and waterproof technology, in particular to an anchor-plate-injection collaborative support method for active water sealing. BACKGROUND
[0002] In the field of shaft construction of mine construction engineering, the waterproofing and supporting effect directly affects the construction safety and subsequent use of the shaft. At present, anchor-mesh-spray is often used for primary support of shaft sides, and then secondary support is carried out. However, the sprayed concrete used in anchor-mesh-spray primary support has low strength, and the surface after spraying is uneven, which results in that the primary support does not have the function of water sealing at all.
[0003] In order to control the amount of water seepage in the shaft to meet the specification requirement (less than 6m 3 / h), the existing technology takes corresponding waterproofing measures for different construction methods. For the shaft constructed by drilling and blasting method, post-wall grouting is usually carried out to seal underground water after the shaft wall is constructed. For the shaft constructed by freezing method, double-layer reinforced concrete composite shaft wall is often used, and the inner layer shaft wall is constructed, and then inter-wall grouting is carried out to seal the seepage water. However, these grouting water sealing methods are all passive sealing methods, which are aimed at the joint and cracks of the shaft wall.
[0004] With the continuous increase of the depth and diameter of the shaft, the thickness of the shaft wall increases sharply, which further leads to the serious problem of crack prevention of the shaft wall mass concrete. After the freezing wall is thawed, underground water is easy to flow into the shaft through the joint and cracks of the shaft wall, which not only affects the normal use of the shaft, but also may cause flooding accident. For the joint leakage problem of the shaft wall, the existing single-layer shaft wall mainly sets various water stop plates in combination with subsequent grouting treatment, but there are problems of complex installation of grouting pipe and grouting treatment process, and the waterproofing effect is unreliable in actual application. In addition, the joint needs to be grouted at the right time, and a large amount of gushing water may be generated due to the cracks of the shaft wall and the joint leakage before the water sealing, which seriously threatens the safety and normal use of the mine.
[0005] Overall, the existing technology has many defects such as low reliability of grouting effect, uncontrollable construction period, passive water plugging method and high water plugging cost when solving the problem of water seepage in the shaft. SUMMARY
[0006] The technical problem to be solved by the present application is to overcome the above technical defects, and to provide an anchor-plate-injection collaborative support method for active water sealing. The present application adopts an active waterproofing method to solve the problem of water seepage in various shaft and roadway supports, and constructs a self-top-to-bottom water-resisting layer between the shaft wall and the shaft side. The water-resisting layer does not need to wait for the grouting liquid to solidify before entering the next process. The steel plate serves as a part of the formwork and support structure, which has the advantages of fast construction speed and good water sealing effect. In addition, the anchor rod is used to fix the steel plate, which greatly reduces the thickness of the steel plate, increases the stability of the support structure, and saves the engineering cost.
[0007] To solve the above technical problems, the technical scheme provided by the present application is as follows: a kind of anchor-plate-injection collaborative support method for active water sealing, applied to various shafts and roadways passing through water-bearing strata, especially the shaft well construction of frozen method construction, comprising the following steps:
[0008] S1, water-free or water working environment preparation: when using the frozen method construction, first form a frozen wall around the shaft well, and after the frozen wall reaches the designed strength and forms a closed water-stopping structure, carry out shaft excavation under the protection of the frozen wall; if the shaft and roadway are not constructed by the frozen method, after excavation, if there is water, strong drainage is carried out to make the drainage capacity greater than the water inflow to ensure that the working face is free of water. After the shaft well is excavated to a segment height, drill holes on the shaft side according to the preset interval and construct anchor rods, so that the anchor rods are exposed by a preset length;
[0009] S2, steel plate fixing and gap forming: fix a steel plate through the anchor rod, so that the outer surface of the steel plate is reduced by 50-200mm compared to the design contour size of the shaft well excavation rough section, and after fixing, the shape of the steel plate is adapted to the shape of the shaft well excavation rough section, and a grouting gap of 50-200mm is formed between the steel plate and the shaft side, which does not include the overbreak space during excavation;
[0010] S3, gap plugging: plug the gap between the bottom edge of the steel plate and the shaft side to a certain height with foam material, clay or other materials, so that the steel plate and the bottom plugging material form a grouting liquid pouring formwork;
[0011] S4, grouting and primary support forming: through the grouting pipe installed at the lower part of the steel plate, grouting liquid is injected into the grouting gap, and after the grouting liquid solidifies, the anchor rod, the steel plate and the grouting liquid together form a primary support structure of the current segment height, i.e. a grouting solidified body;
[0012] S5, multi-segment support and permanent support: after the primary support structure of the current segment height is formed, secondary support can be carried out immediately, or steps S1-S4 can be repeated to form multiple primary support structures of segment heights, and then secondary support is carried out; if multiple segment heights are formed and then secondary support is carried out, temporary reinforcement support is needed on the side of the steel plate facing the shaft well center with channel steel or other steel rings after primary support, and after multiple stable segment heights of primary segment heights are formed, steel reinforced concrete shaft walls are poured from bottom to top.
[0013] Wherein, the steel plate is provided with a steel plate connecting hole for connecting and fixing adjacent segment height steel plates; the frozen wall is arranged around the water-bearing strata, the steel reinforced concrete shaft wall is located on the side of the primary support structure away from the shaft side, and the bottom steel plate is used to close the gap between the shaft well bottom and the shaft side.
[0014] As preferred in the application, the anchor rod comprises a rod body and a limiting ring arranged at the front end of the rod body, the limiting ring divides the rod body into an anchoring section and an exposed section; the anchoring section is inserted into and anchored in the shaft lining, the steel plate is sleeved on the exposed section through the mounting hole arranged thereon, and the exposed section is threadedly connected with an anchor rod nut for pressing the steel plate to be confined between the limiting ring and the anchor rod nut.
[0015] As preferred in the application, the inner end face of the anchor rod nut and the outer end face of the limiting ring are both provided with a sealing gasket.
[0016] As preferred in the application, the slurry injected in step S4 is a micro-swelling cement slurry or a cement-sodium silicate double-liquid slurry; and the effective thickness of the grouting solidified body is kept at 50-200 mm.
[0017] As preferred in the application, when the construction section is located above soft rock or surface soil, a layer of foam material is laid or sprayed on the surface of the shaft lining before the steel plate is installed in step S3.
[0018] As preferred in the application, the thickness of the steel plate is 1-6 mm, and a steel mesh or a net frame is fixed on the outer side of the steel plate to increase the stability of the steel plate.
[0019] As preferred in the application, at least one layer of waterproof coiled material, waterproof board material or waterproof paint is pasted or sprayed on the inner surface of the steel plate.
[0020] As preferred in the application, the waterproof coiled material comprises a butyl rubber tape and an asphalt waterproof coiled material; the waterproof board material comprises an eva board, a PP board and a PE board; and the waterproof paint comprises non-solid asphalt rubber and polyurea.
[0021] Compared with the prior art, the application has many advantages in the field of shaft construction, which are as follows:
[0022] 1. Active water plugging is realized and the effect is controllable. The method breaks through the passive waterproof mode of “leaking water first and then plugging”, builds a foundation frame by combining anchor rod and steel plate, builds a waterproof layer in advance and actively grouts. The steel plate has reliable water sealing performance as a water sealing material, and the continuous water stopping structure formed by cooperation with grouting can block the underground water inflow channel from the source. At the same time, the water plugging effect can be tested in time through pressure test, avoiding the problem that the effect is difficult to predict when traditional passive grouting is used to plug water, and ensuring the waterproof reliability.
[0023] 2. Safety and construction period risks are effectively avoided. Traditional waterproofing needs to be grouted after the shaft lining is jointed or cracks leak, which may cause flooding accidents due to a large amount of water gushing during this process, and the grouting process is complex and easy to cause construction period delay. The application completes active water sealing immediately after shaft excavation, eliminating the risk of water leakage in the shaft, and fundamentally solving the problems of construction period delay and safety accident hazards caused by water leakage and grouting.
[0024] 3. The support and water sealing are realized synchronously. Compared with the traditional primary support which only plays a supporting role, the application realizes active water sealing by the anchor-plate-injection synergy while completing the primary support. The combination design of the steel plate and the anchor rod controls the thickness of the steel plate in a relatively thin range under the premise of ensuring the supporting strength, not only reduces the material cost, but also is more convenient for construction application, and changes the situation that the traditional support and waterproof are mutually separated.
[0025] 4. The construction cost is significantly reduced. Since the water sealing layer formed by the application has reliable water stopping and load bearing auxiliary functions, the load bearing surface of the permanent support, especially the load bearing surface of the double-layer composite shaft lining, is transferred to the outer surface of the outer shaft lining, thereby effectively reducing the total thickness of the double-layer shaft lining, greatly reducing the amount of materials such as concrete and steel bars, and reducing the construction investment cost.
[0026] 5. The method has wide adaptability and flexible application. The method has wide adaptability to shafts and tunnels constructed by various construction methods (such as the freezing method and the drill-and-blast method), and can play a good effect through corresponding process adjustment regardless of typical water-bearing strata, soft rock or surface soil sections, or shafts with large water gushing risks.
[0027] 6. There is an essential difference between the anchor-shotcrete-net temporary support process. The shotcrete used in the traditional anchor-shotcrete-net temporary support has low strength and uneven surface, and does not have water sealing function at all, and additional waterproof treatment is required subsequently; while the application takes the steel plate as the core water sealing and support carrier, and combines anchor rod fixation and grouting filling to form a reliable water sealing structure while realizing support, and the surface of the steel plate is flat, which provides convenience for subsequent construction, saves a lot of leveling procedures, and has higher construction efficiency. BRIEF DESCRIPTION OF DRAWINGS
[0028] Figure 1 is a partial front view of a shaft after the anchor-plate-injection synergy support method with active water sealing of the application is adopted;
[0029] Figure 2 is an enlarged structural schematic view of the anchor rod of the application.
[0030] Figure 3 is Figure 1 is a structural enlarged schematic view of A in
[0031] Figure 4 is a partial top view schematic view of a shaft after the anchor-plate-injection synergy support construction method with active water sealing of the application is adopted.
[0032] Figure 5 is an installation schematic view of the channel steel shaft ring of the application.
[0033] As shown in the figure: 1, water-bearing stratum, 2, shaft side, 3, grout solid, 4, anchor rod, 41, rod body, 411, anchoring section, 412, exposed section, 42, limiting ring, 43, anchor rod nut, 44, sealing gasket, 5, steel plate, 6, reinforced concrete shaft wall, 7, grouting pipe, 8, bottom steel plate, 9, steel plate connecting hole, 10, frozen wall, 11, channel steel. DETAILED DESCRIPTION
[0034] The application will be further described below in conjunction with the accompanying drawings.
[0035] The specific embodiments of the application will be further described below in conjunction with the accompanying drawings. The same parts are denoted by the same reference numerals.
[0036] It should be noted that the words "front", "back", "left", "right", "up" and "down" used in the following description refer to the directions in the drawings, and the words "inner" and "outer" refer to the directions towards or away from the geometric center of a particular part.
[0037] In order to make the content of the application more easily understood, the technical solutions in the embodiments of the application will be clearly and completely described below in conjunction with the accompanying drawings of the embodiments of the application.
[0038] Example 1: Typical water-bearing stratum freezing method construction shaft application
[0039] Reference is made to the accompanying drawings Figure 1 - the accompanying Figure 5 , this embodiment describes in detail the specific implementation process of the anchor-plate-injection collaborative support method for actively sealing water in the typical water-bearing stratum (such as water-rich sandstone, sand and gravel layer) shaft constructed by the freezing method.
[0040] S1, freezing and tunneling preparation:
[0041] Freezing wall formation: strictly according to the design requirements, freezing holes are arranged outside the design circumference of the shaft, low-temperature brine is circulated, and a freezing wall 10 with certain thickness and strength is formed in the water-bearing stratum 1 around the shaft. The development of the freezing wall temperature field is continuously monitored, the key point is to ensure that the freezing wall 10 not only reaches the design strength (usually refers to the frost resistance meets the requirements), more importantly, forms a complete, closed cylindrical water stop structure, effectively isolates the area to be excavated from the outside active underground water. The effect is to create safe conditions for subsequent dry or nearly dry excavation and support operations, and completely eliminate the risk of large water inflow in the shaft side 2 during excavation.
[0042] Shaft excavation: After confirming the reliability of the water-stopping effect of the frozen wall 10, the shaft is excavated using the drill-and-blast method or machinery (such as umbrella drilling or rock grab). Excavation is carried out in layers and sections, and the depth of each excavation is referred to as a "section height". The section height size is determined comprehensively based on the stability of the surrounding rock, the strength of the frozen wall, and the capacity of the construction equipment, and is usually 3-6 meters.
[0043] Anchor rod construction: After a section height is excavated and the exposed shaft wall 2 is formed, primary support work is immediately carried out. First, holes are drilled in the shaft wall 2 according to the predetermined spacing and row distance (e.g. 800mm x 800mm or adjusted according to calculations). The drilling depth needs to penetrate the possible loose surface layer and anchor in the relatively stable stratum. Then, a specially designed anchor rod 4 is installed. As shown in FIGS. 1 and 2, the anchor rod 4 is composed of a rod body 41, a limiting ring 42 arranged at the front end of the rod body (the end inserted into the shaft wall), and an anchor rod nut 43 threadedly connected to the exposed end 412 of the rod body. The key operation is to insert and anchor the anchoring section 411 of the anchor rod 4 completely into the hole (usually using a resin cartridge or fast-hardening cement end anchor) to ensure its gripping force. The exposed section 412 of the rod body 41 needs to have sufficient length (preset length, e.g. 100-200mm) to meet the space requirements for subsequent installation of steel plates 5, compression of sealing pads 44, and application of prestress (if needed). The design advantage is that the limiting ring 42 provides an internal pressure-bearing surface for the steel plate 5, and the anchor rod nut 43 provides external fastening force, which together effectively fix the steel plate and ensure sealing. Figure 1 and Figure 2
[0044] S2, Steel plate fixation and gap formation:
[0045] Steel plate selection and treatment: A ductile steel plate 5 with a thickness of 1-6mm (preferably 1.5-3mm), such as Q235A steel plate, is selected. To further enhance the waterproof effect on the inner surface of the steel plate 5 (the side facing the shaft center), one or more layers of waterproof material can be applied, such as butyl rubber tape (for joint sealing), EVA waterproof board, non-cured asphalt rubber waterproof coating, or polyurea coating. This measure can significantly improve the reliability of the steel plate itself as a waterproof barrier, providing additional waterproof protection even if there are minor defects in the future grouting body 3. On the steel plate 5, in addition to the installation holes for the anchor rod 4, steel plate connection holes 9 are also provided on the edges of the plate for reliable connection (such as bolt connection or welding) between the steel plates of adjacent section heights above and below.
[0046] Steel plate installation and gap control: The processed steel plates 5 are hoisted to the working face. Through the installation holes on the steel plates 5, the steel plates 5 are sleeved on the exposed section 412 of the anchor rod 4. The key operation is accurate positioning: by adjusting the position of the steel plate 5 and using the anchor rod system for fastening, it is ensured that the outer surface of the steel plate 5 is uniformly "shrunk" by 50-200 mm (for example, the commonly used value is 50-100 mm) to the center of the wellbore relative to the profile size of the designed discontinuous section of the wellbore. The effect is that when the steel plate 5 is finally pressed against the limiting ring 42 by the anchor rod nut 43 (note that the inner end surface of the anchor rod nut 43 and the outer end surface of the limiting ring 42 are provided with elastic sealing pads 44 to ensure the sealing of the contact surface), an effective annular cavity (i.e. 50-200 mm), i.e. the grouting gap, is naturally formed between the steel plate 5 and the uneven surface of the lower well wall 2. The accurate control of this gap is one of the cores of the present application, which provides a template space for subsequent grouting and finally determines the effective thickness of the grouting solid body.
[0047] Pre-stress application (optional): In order to improve the timeliness of the primary support and the restraining effect on the surrounding rock, a certain pre-stress can be applied to the exposed section 412 using a special tensioning device before the anchor rod nut 43 is tightened. The tensioning force is determined according to the design calculation, and the anchor rod nut 43 is locked after the tensioning is in place. This can make the steel plate 5 generate a certain active supporting force on the well wall 2 before grouting, thereby inhibiting the relaxation deformation of the surface surrounding rock.
[0048] S3, gap plugging:
[0049] Bottom sealing: After the steel plate 5 is installed and fixed, there will be a gap between the bottom edge (the bottom edge of the current section height) of the steel plate 5 and the well wall 2. If this gap is not plugged, the slurry will leak from this place during grouting, resulting in grouting failure. Therefore, a flexible, easily shaped and water-stopping material, such as a closed-cell foam plastic strip (such as a PE foam rod), a quick-setting expanding clay (such as a bentonite clay strip) or a thick geotextile roll, must be tightly inserted and compacted into the bottom gap. The effect is that the lower opening of the annular grouting gap between the steel plate 5 and the well wall 2 is effectively closed, making it a "U" or "L" shaped template cavity (the specific shape depends on the well wall design) with an open top and a closed bottom. This step is crucial as it directly determines whether the subsequent grouting can be successfully carried out and whether a complete shell of the designed thickness can be formed. For the steel plate of the bottom section height, the bottom sealing is particularly important, and a specially designed arc-shaped bottom steel plate 8 is often used in combination with sealing materials to close it.
[0050] S4, grouting and primary support forming:
[0051] Grouting system setting: At least one grouting pipe 7 is pre-installed or installed at the lower part of the steel plate 5 (usually near the bottom sealing position). The grouting pipe 7 needs to penetrate the steel plate 5 and be sealed to it, and the inner port should extend into the grouting gap.
[0052] Slurry selection and grouting: The slurry is injected into the sealed grouting gap through the grouting pipe 7 by the grouting pump. The selection of the slurry should consider the setting time, fluidity, strength and expansibility:
[0053] Micro-expansive cement slurry: The commonly used choice. The cement grade is not less than P.O 42.5, the water-cement ratio is controlled at 0.3-0.7, and an appropriate amount (according to the product instructions) of expansive agent (such as UEA, HEA) is added. Its advantages are: lower cost, stable strength development, micro-expansion can effectively fill the gap and compensate for shrinkage, ensure the tight bonding of the grouted body 3 with the steel plate 5 and the shaft side 2, and form good overall and waterproof performance.
[0054] Cement-sodium silicate double liquid slurry: Used when there is slightly more water leakage or when rapid sealing is required. By adjusting the ratio and concentration of cement slurry and sodium silicate solution, the gel time (from tens of seconds to several minutes) can be accurately controlled. Its effect is: it can quickly solidify and stop water, providing immediate strength and water stopping effect, especially suitable for local thawing of frozen wall or water leakage point treatment. The grouting pressure needs to be strictly controlled (usually 0.1-0.5 MPa), and the slurry should be filled in the gap and smoothly discharged from the exhaust hole. The key requirement is: to ensure that the slurry rises uniformly and densely fills the entire annular gap, and the effective thickness of the grouted body 3 formed by the final solidification must be maintained within the designed range of 50-200 mm, without voids or segregation.
[0055] Support structure formation: After the slurry solidifies and hardens, the primary support structure of the current segment height is formed, that is, the support structure of the grouted body 3 + steel plate + anchor rod. This structure is the core result of the synergy of anchor-plate-grouting:
[0056] The anchor rod 4 provides deep anchoring force and tension to the steel plate.
[0057] The steel plate 5 serves as a formwork and initial support surface layer before grouting, and becomes a permanent outer protective layer and part of the waterproof layer of the grouted body 3 after grouting.
[0058] The grouted body 3 tightly bonds the anchor rod 4 and the steel plate 5 into a whole, forming a thin-shell support structure (effective thickness 50-200 mm) with both rigidity and flexibility. Its significant effect is:
[0059] Active waterproofing: The composite structure immediately forms a continuous and reliable water barrier (composed of steel plate, sealing gasket and grouted body) from top to bottom after the shaft is excavated, completely isolating the water-bearing stratum 1 from the inside of the shaft. This fundamentally solves the passive situation of "leaking water first and then plugging" in traditional methods, and realizes true active water sealing.
[0060] High support strength: the combination of the anchoring of the anchor rod 4, the restraint of the steel plate 5 and the compression resistance of the grouting body makes the thin-layer structure have a support strength and stiffness much higher than that of the same thickness of plain concrete, which can effectively control the deformation of the shaft side.
[0061] Surface smoothness: the steel plate 5 provides a smooth inner surface, which provides an extremely smooth base surface for the construction of the subsequent secondary support (inner shaft wall), and eliminates a large amount of leveling work after the traditional anchor-shotcrete support.
[0062] S5, multi-section support and permanent support:
[0063] Multi-section support implementation: after the completion of the initial support of the anchor-plate-grouting of the current section height, according to the construction organization design and the stability of the surrounding rock, two modes can be selected:
[0064] Mode one (section-by-section continuous support): immediately perform the secondary support of the section height (i.e. the construction of the inner reinforced concrete shaft wall 6). This mode is suitable for situations where the surrounding rock pressure appears quickly.
[0065] Mode two (multi-section primary support): repeat steps S1-S4, and continuously construct the anchor-plate-grouting initial support structure of 2 or more section heights upwards. In this process, the steel plates 5 of adjacent section heights above and below need to be reliably connected (bolted or welded) through the steel plate connecting holes 9 to ensure the sealing of the joint, so that each section of the initial support structure also forms a continuous waterproof shell in the longitudinal direction. After the completion of the initial support of multiple section heights, the secondary support of these section heights is concentrated. Among them, if the permanent support is to be formed after multiple section heights, temporary reinforcement support of the steel plate can be performed by using a channel steel 11 or other type of steel ring after the initial support. After the formation of multiple stable section heights of the initial section height, the reinforced concrete shaft wall is poured from bottom to top. The purpose is to avoid the problem of deformation caused by insufficient support strength due to the excessive height of the initial support. The ring support ensures the shape stability of the initial support during the continuous construction of multiple section heights. With the construction of the permanent support structure from bottom to top, the ring support can be recycled.
[0066] Secondary support (permanent shaft wall) construction: regardless of which mode is adopted, the secondary support is performed inside the initial support structure (i.e. the inner surface of the grout solid body 3 + steel plate 5). Specifically:
[0067] Binding the steel reinforcement cage of the inner reinforced concrete shaft wall 6.
[0068] Erecting the shaft wall formwork (usually hydraulic slip form or assembled formwork), and the inner surface of the formwork constitutes the final design net section of the shaft.
[0069] Pouring concrete and curing to achieve strength before removing the formwork.
[0070] The advantages of the present invention are particularly prominent after the permanent support:
[0071] Waterproof reliability: Because of the reliable water barrier formed by the primary support, the reinforced concrete shaft lining 6 is basically not affected by external water pressure and seepage erosion during construction and later use, greatly reducing the risk of leakage. Even if there is a small shrinkage crack in the inner wall, external water cannot flow into the shaft.
[0072] Structural optimization: In traditional double-layer shaft lining design, the outer shaft lining (usually cast-in-place concrete) must be designed thick enough to withstand the entire water and soil pressure after the frozen wall is thawed and waterproof. In the present invention, the primary support structure (anchor-plate-injection) has already taken on the functions of water sealing and partial support, and it can be part of the permanent support. This allows the secondary support of the reinforced concrete shaft lining 6 to be designed thinner:
[0073] Example 2: Reinforcement measures for soft rock or surface soil section
[0074] When the construction section is high above the soft rock or unconsolidated surface soil layer with poor stability, the shaft side 2 may be loose or prone to spalling, making it difficult to install steel plates 5 directly on its surface, and the grout may seep into the surrounding rock during grouting, resulting in incomplete gap filling. To address this situation, a key measure is added before step S2 (installing steel plates):
[0075] Shaft surface pretreatment: After completing the anchor rod 4 construction, immediately lay or spray a layer of low-density closed-cell foam plastic (such as polyethylene or polyurethane foam board, thickness about 10-30mm) or spray a layer of quick-setting flexible material (such as polymer-modified cement slurry) on the exposed shaft side 2 surface. Its role is:
[0076] Filling and leveling: Fill the larger pits and uneven places on the shaft surface to provide a relatively flat base for subsequent steel plate 5 installation and positioning.
[0077] Temporary closure: Quickly close the loose or broken rock and soil surface to prevent it from collapsing and falling apart before the steel plate 5 is installed.
[0078] Grout-blocking layer: Most importantly, it effectively prevents the subsequent injected grout from excessively seeping into the soft formation under pressure. Without this layer, the grout will be lost in large quantities into the formation, resulting in incomplete filling of the grouting gap, insufficient thickness of the grouting solid body 3, and even hollows, which seriously affect the support strength and waterproof effect.
[0079] Buffer layer: provides a flexible buffer layer for the steel plate 5, reducing local stress concentration. After this pretreatment, the steel plate 5 is installed, the bottom is sealed, and grouting is performed according to the steps of Example 1. At this time, a grouting gap exists between the steel plate 5 and this layer of foam / sprayed material, and the slurry will fill this gap and wrap the material layer. The effect is to ensure that a complete and effective grouting solid 3 can also be formed in the soft rock surface soil section.
[0080] This method can also be used for roadway construction, which can be regarded as a transverse wellbore, and its core construction logic is consistent with that of the wellbore: after the roadway sides are formed by excavation, the anchor rods are installed according to the preset interval and row spacing, the steel plates are fixed by the anchor rods and form a grouting gap with the roadway sides, the foam is used to seal the gap between the steel plate bottom and the roadway sides, the slurry is injected through the grouting pipe to form the primary support structure, and the secondary support can be performed immediately after the primary support or after multiple cycles of the primary support. This application conforms to the adaptability of the method to various construction methods and strata, and does not require the freezing-related steps, and can realize active water sealing and synchronous support in roadway construction.
[0081] The above describes the present application and its embodiments, which are not limited, and the drawings only show one of the embodiments of the present application, and the actual structure is not limited thereto. In summary, if a person skilled in the art is inspired by it, without departing from the purpose of the present application, without creative design, similar structure and embodiments of the technical solution can be designed, which should belong to the protection scope of the present application.
Claims
1. A method of active water-sealed anchor-plate-grouting collaborative support, characterized in that, The application is applied to various shafts passing through water-bearing strata (1), especially the shaft construction by freezing method, and comprises the following steps: S1, water-free or water-accumulation working environment preparation: when the freezing method is used, a frozen wall (10) is formed around the shaft, and after the frozen wall (10) reaches the design strength and forms a closed water-stopping structure, the shaft excavation is carried out under the protection of the frozen wall (10); if the shaft is not constructed by the freezing method, after the excavation, if there is water, strong drainage is carried out to make the drainage amount greater than the water inflow to ensure that the working face is free of water, and after the shaft is excavated to a section height, holes are drilled on the shaft side (2) according to the preset interval and anchor rods (4) are constructed to make the anchor rods (4) protrude by a preset length; S2, steel plate fixation and gap formation: the steel plate (5) is fixed through the anchor rod (4) to make the outer surface of the steel plate (5) smaller than the design contour size of the shaft excavation section by 50-200 mm, the shape of the fixed steel plate (5) is adapted to the shape of the shaft excavation section, and a grouting gap of 50-200 mm is formed between the steel plate (5) and the shaft side (2), which does not include the overbreak space during excavation; S3, gap blocking: the foam material and clay are used to block the gap between the bottom edge of the steel plate (5) and the shaft side (2) to a certain height, so that the steel plate and the bottom blocking material form a grouting liquid pouring formwork; S4, grouting and primary support forming: the grouting pipe (7) installed at the lower part of the steel plate (5) is used to inject grout into the grouting gap, and after the grout solidifies, the anchor rod (4) and the steel plate (5) jointly form the primary support structure of the current section height, that is, the grouting solidified body (3); S5, multi-section support and permanent support: after the primary support structure of the current section height is formed, secondary support can be immediately carried out, or steps S1-S4 are repeated to form multiple primary support structures of section heights, and then secondary support is carried out; if multiple section heights are formed and then secondary support is carried out, after the primary support, temporary reinforcement support is carried out on the side of the steel plate (5) facing the shaft center by using a channel steel (11) or other steel rings to form multiple stable primary section heights, and then the reinforced concrete shaft wall (6) is poured from bottom to top; Wherein, the steel plate (5) is provided with a steel plate connecting hole (9) for connecting and fixing the adjacent section height steel plate (5); the frozen wall (10) is arranged around the water-bearing strata (1), the reinforced concrete shaft wall (6) is located on the side of the primary support structure away from the shaft side (2), and the bottom steel plate (8) is used to close the gap between the bottom of the steel plate and the shaft side (2).
2. The method of claim 1, wherein the method further comprises, The anchor rod (4) comprises a rod body (41) and a limiting ring (42) arranged at the front end of the rod body (41), the limiting ring (42) divides the rod body (41) into an anchoring section (411) and an exposed section (412); the anchoring section (411) is inserted and anchored in the shaft side (2), the steel plate (5) is sleeved on the exposed section (412) through the mounting hole arranged thereon, and the exposed section (412) is threadedly connected with an anchor rod nut (43) for pressing and limiting the steel plate (5) between the limiting ring (42) and the anchor rod nut (43).
3. The active water-sealed anchor-plate-injection collaborative support method according to claim 2, characterized in that, The inner end surface of the anchor rod nut (43) and the outer end surface of the limiting ring (42) are provided with sealing pads (44).
4. The method according to claim 1, wherein, The slurry injected in step S4 is a slightly expanded cement slurry or a cement-sodium silicate double liquid slurry; the effective thickness of the grouting solid body (3) is kept at 50-200 mm.
5. The method of claim 1, wherein the method further comprises, When the construction section is high above soft rock or surface soil, a layer of foam material is laid or sprayed on the surface of the shaft side (2) before the steel plate (5) is installed in step S3.
6. The method of claim 1, wherein the method further comprises, The thickness of the steel plate (5) is 1-6 mm, and a steel mesh or a net frame is fixed outside the steel plate (5) to increase the stability of the steel plate.
7. The anchor-plate-grouting synergic support method and construction process according to any one of claims 1-6, characterized in that, At least one layer of waterproof coiled material, waterproof board material or waterproof paint is pasted or sprayed on the inner surface of the steel plate (5).
8. The method of claim 7, wherein the method further comprises, The waterproof coiled material includes butyl rubber tape and asphalt waterproof coiled material; the waterproof board material includes eva board, PP board and PE board; the waterproof paint includes non-solid asphalt rubber and polyurea.
Citation Information
Cited By
Expansive soft rock stratum well wall structure and construction method
CN121345578A
An expandable soft rock stratum well wall structure and construction method
CN121345578B